RU2010864C1 - Method of producing steel - Google Patents

Method of producing steel Download PDF

Info

Publication number
RU2010864C1
RU2010864C1 SU803217507A SU3217507A RU2010864C1 RU 2010864 C1 RU2010864 C1 RU 2010864C1 SU 803217507 A SU803217507 A SU 803217507A SU 3217507 A SU3217507 A SU 3217507A RU 2010864 C1 RU2010864 C1 RU 2010864C1
Authority
RU
Russia
Prior art keywords
bath
oxygen
height
calm
lance
Prior art date
Application number
SU803217507A
Other languages
Russian (ru)
Inventor
Бротцманн Карл
Мантей Пауль-Герхард
Original Assignee
Айзенверк Гезельшафт Максимилиансхютте мбХ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Айзенверк Гезельшафт Максимилиансхютте мбХ filed Critical Айзенверк Гезельшафт Максимилиансхютте мбХ
Application granted granted Critical
Publication of RU2010864C1 publication Critical patent/RU2010864C1/en

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/30Regulating or controlling the blowing
    • C21C5/35Blowing from above and through the bath

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

FIELD: ferrous metallurgy. SUBSTANCE: new method of producing steel in converter included steps of charging scrap metal, pouring in pig iron, blowing off bath with oxygen, feeding oxygen by free jets to bath center via side lances from above and height of 2 to 10 m over level of calm bath, charging powdery materials from below with beginning of blowing and powdery lime on foaming of slag, supplying oxygen-free gas into bath from below, blowing off bath with oxygen from overhead through central multijet lance in desiliconization phase, raising lance to height of 1.5 to 10 m above level of calm bath, and feeding oxygen by free jets. Rate of oxygen flow admitted via side lances was maintained at 25 to 50 % of total amount to be consumed. EFFECT: higher quality and efficiency.

Description

Изобретение относится к области металлургии, конкретнее к способам получения стали в конвертере, снабженном соплами, расположенными ниже уровня металла, и имеющем устройства продувки в виде охлаждаемого водой кислородного копья и/или сопел для продувки сверху. The invention relates to the field of metallurgy, and more particularly to methods for producing steel in a converter equipped with nozzles located below the metal level and having purge devices in the form of an oxygen-cooled spear and / or nozzles for purging from above.

Целью изобретения является повышение доли лома в шихте. The aim of the invention is to increase the proportion of scrap in the charge.

Сущность изобретения заключается в том, что в способе получения стали в конвертере, включающем загрузку скрапа, заливку чугуна, продувку ванны кислородом, подачу сверху, с высотой 2-10 м над уровнем спокойной ванны, через боковые фурмы в центре ванны кислорода в виде свободных струй, подачу снизу порошкообразных материалов одновременно с началом продувки и порошкоообразной извести при вспенивании шлака, снизу в ванну подают свободный от кислорода газ, а продувку ванны кислородом осуществляют сверху через центральную многосопловую фурму в течение фазы обескремнивания, после чего фурму поднимают до высоты 1,5-10 м над уровнем спокойной ванны и подают кислород в виде свободных струй, при этом расход кислорода через боковые фурмы поддерживают равным 25-50% от общего его расхода. The essence of the invention lies in the fact that in the method of producing steel in a converter, comprising loading scrap, pouring cast iron, purging the bath with oxygen, feeding from above, with a height of 2-10 m above the level of a calm bath, through the side tuyeres in the center of the bath of oxygen in the form of free jets , the supply of powder materials from below at the same time as the start of blowing and powder of lime during foaming of slag, oxygen-free gas is supplied to the bottom of the bath, and the bath is purged with oxygen from above through a central multi-nozzle lance into during the phase of desiliconization, after which the tuyere is raised to a height of 1.5-10 m above the level of a calm bath and oxygen is supplied in the form of free jets, while the oxygen flow through the side tuyeres is maintained equal to 25-50% of its total consumption.

П р и м е р 1. В конвертер емкостью 200 т, снабженный водоохлаждаемой трубкой, установленной с возможностью перемешивания в верхней конусе, двумя формами с внутренним диаметром 45 мм, установленными в боковой стенке на высоте 3 мм над поверхностью спокойной ванны, и восемью донными фурмами с внутренним диаметром 24 мм, подали 155 т чугуна, содержащего 4,4% углерода, 1% кремния, 0,6% марганца и 0,1% фосфора и 70 т скрапа. По обеим фурмам в боковой стенке подали 2500 нм2 (25% от общего количества) кислорода во время процесса фришевания, причем его расход на фурму составлял 105 нм3/мин в течение 11 мин и 95 нм3 в течение 1 мин. По окончании фазы обескремнивания (примерно через 2 мин после начала процесса) водоохлаждаемую трубку подняли с высоты 0,5 м на высоту 1,5 м над поверхностью спокойной ванны. Во время процесса фришевания через водоохлаждаемую трубку вдували на поверхность ванны 7500 нм3 кислорода при расходе 625 нм3/мин. Расстояние между выходным отверстием трубки и поверхностью ванны обеспечивает то, что кислород проходит путь в газовом пространстве в виде свободной струи. Через донные фурмы в течение первых 8 мин вдували 130 нм3/мин азота, содержащего 9 кг/м3 порошковой извести. По истечении 8 мин подачу азота прекратили и вдували 130 нм3/мин аргона без извести. Через 2 мин после начала вдувания аргона образуется пенистый шлак, о чем свидетельствует изменение уровня шума в конвертере. При этом в течение 30 с вместе с аргоном вводили 600 кг порошковой извести, в результате чего пенистый шлак устраняется и подавляется его образование.EXAMPLE 1. To a converter with a capacity of 200 tons, equipped with a water-cooled tube mounted with the possibility of mixing in the upper cone, two forms with an inner diameter of 45 mm, mounted in the side wall at a height of 3 mm above the surface of a calm bath, and eight bottom tuyeres with an inner diameter of 24 mm fed 155 tons of cast iron containing 4.4% carbon, 1% silicon, 0.6% manganese and 0.1% phosphorus and 70 tons of scrap. 2500 lm 2 (25% of the total amount) of oxygen was supplied to both lances in the side wall during the process of flaking, and its lance consumption was 105 nm 3 / min for 11 min and 95 nm 3 for 1 min. At the end of the phase of desiliconization (approximately 2 minutes after the start of the process), the water-cooled tube was lifted from a height of 0.5 m to a height of 1.5 m above the surface of a calm bath. During the process of frothing, 7500 nm 3 of oxygen was blown onto the surface of the bath through a water-cooled tube at a flow rate of 625 nm 3 / min. The distance between the outlet of the tube and the surface of the bath ensures that oxygen passes through the gas space in the form of a free stream. 130 nm 3 / min of nitrogen containing 9 kg / m 3 of powdered lime was blown through the bottom tuyeres during the first 8 minutes. After 8 minutes, the flow of nitrogen was stopped and 130 nm 3 / min of argon was blown without lime. 2 minutes after the start of argon injection, foamy slag is formed, as evidenced by a change in the noise level in the converter. At the same time, 600 kg of powdered lime were introduced along with argon within 30 s, as a result of which foamy slag is eliminated and its formation is suppressed.

По истечении 12 мин произвели выпуск стали, количество которой на 1,5% превышает количество стали, выпускаемой в аналогичных условиях известным способом. After 12 minutes, steel was produced, the amount of which is 1.5% higher than the amount of steel produced under similar conditions in a known manner.

П р и м е р 2. В конвертер емкостью 300 т, снабженный водоохлаждаемой трубкой, установленной с возможностью перемещения в верхней части, четырьмя фурмами с внутренним диаметром 45 м, мм установленными в боковой стенке на высоте 5 м над поверхностью спокойной ванны и десятью донными фурмами, подали 220 т чугуна, указанного в примере 1, и 110 т скрапа. По фурмам в боковой стенке подали 7500 нм3 (50% от общего количества) кислорода во время процесса фришевания в течение 11 мин, причем его расход на фурму составлял 170 нм3/мин в течение 10 мин и 175 нм3 в течение 1 мин. По окончании фазы обескремнивания (примерно 2 мин) водоохаждаемую трубку подняли с высоты 0,6 м на высоту 10 м над поверхностью спокойной ванны. Во время фришевания через водоохлаждаемую трубку вдували на поверхность ванны 7500 нмм2 кислорода при расходе 680 нм3/мин. Расстояние между выходным отверстием трубки и поверхностью ванны обеспечивает то, что кислород проходит путь в газовом пространстве в виде свободной струи. Через донные фурмы в течение первых 8 мин вдували 170 нм3/мин азота, содержащего 10 кг/м3 порошковой извести. В течение последних 3 мин процесса по донным фурмам вдували только аргон в количестве 170 нм3/мин. Через 1,5 мин после начала продувки аргоном образуется пенистый шлак. В течение 20 с вместе с аргоном вводили 850 кг порошковой извести, в результате чего образование пенистого шлака подавляется.PRI me R 2. In the converter with a capacity of 300 tons, equipped with a water-cooled tube mounted with the ability to move in the upper part, four tuyeres with an inner diameter of 45 m, mm installed in the side wall at a height of 5 m above the surface of a calm bath and ten bottom tuyeres, served 220 tons of cast iron specified in example 1, and 110 tons of scrap. 7500 nm 3 (50% of the total amount) of oxygen was supplied by tuyeres in the side wall during the flaking process for 11 min, and its tuyere consumption was 170 nm 3 / min for 10 min and 175 nm 3 for 1 min. At the end of the phase of desiliconization (approximately 2 min), the water-cooled tube was lifted from a height of 0.6 m to a height of 10 m above the surface of a calm bath. During the process of frothing, 7500 nmm 2 oxygen was blown onto the surface of the bath through a water-cooled tube at a flow rate of 680 nm 3 / min. The distance between the outlet of the tube and the surface of the bath ensures that oxygen passes through the gas space in the form of a free stream. During the first 8 minutes, 170 nm 3 / min of nitrogen containing 10 kg / m 3 of powdered lime was blown through the bottom tuyeres. During the last 3 min of the process, only argon was injected into the bottom tuyeres in an amount of 170 nm 3 / min. 1.5 minutes after the start of the argon purge, foamy slag is formed. Within 20 s, 850 kg of powdered lime was introduced along with argon, as a result of which the formation of foamy slag is suppressed.

По истечении 11 мин произвели выпуск стали, количество которой на 1,9% превышает количество стали, выпускаемой в аналогичных условиях известным способом. After 11 minutes, steel was produced, the amount of which is 1.9% higher than the amount of steel produced under similar conditions in a known manner.

П р и м е р 3. Повторяли пример 1 с той разницей, что по фурмам боковой стенке вдували 2016 нм3 (20,16% от общего количества) кислорода при расходе 84 нм3/мин и по окончании фазы обескремнивания водоохлаждаемую трубку поднимают на высоту 1 м над поверхностью спокойной ванны. При этом в конвертере можно было переработать только 63 т скрапа.Example 3. Example 1 was repeated with the difference that 2016 nm 3 (20.16% of the total amount) of oxygen was blown into the tuyeres of the side wall at a flow rate of 84 nm 3 / min and at the end of the phase of desalination, the water-cooled tube was lifted 1 m above the surface of a calm bath. At the same time, only 63 tons of scrap could be processed in the converter.

Подача только 20,16% от общего количества кислорода через фурмы в боковой стенке и подъем водоохлаждаемой трубки на высоту 1 м над поверхностью спокойной ванны имеет следующие недостатки:
количество перерабатываемого скрапа снижается с 70 до 63 т, т. е. на 10% ;
количество выпускаемой стали практически то же самое, что и в способе по прототипу. (56) Патент СССР N 1306482, кл. С 21 С 5/28, 1977.
The supply of only 20.16% of the total amount of oxygen through the tuyeres in the side wall and the rise of the water-cooled tube to a height of 1 m above the surface of a calm bath has the following disadvantages:
the amount of scrap processed is reduced from 70 to 63 tons, i.e. by 10%;
the amount of steel produced is almost the same as in the prototype method. (56) USSR patent N 1306482, cl. C 21 C 5/28, 1977.

Claims (1)

СПОСОБ ПОЛУЧЕНИЯ СТАЛИ в конвертере, включающий загрузку скрапа, заливку чугуна, продувку ванны кислородом, подачу сверху с высоты 2 - 10 м над уровнем спокойной ванны через боковые фурмы в центр ванны кислорода в виде свободных струй, подачу снизу порошкообразных материалов одновременно с началом продувки и порошкообразной извести при вспенивании шлака, отличающийся тем, что, с целью повышения доли лома в шихте, снизу в ванну подают свободный от кислорода газ, а продувку ванны кислородом осуществляют сверху через центральную многосопловую фурму в течение фазы обескремнивания, после чего фурму поднимают на высоту 1,5 - 10,0 м над уровнем спокойной ванны и подают кислород в виде свободных струй, при этом расход кислорода через боковые фурмы поддерживают равным 25 - 50% от общего его расхода. METHOD FOR PRODUCING STEEL in a converter, including scrap loading, cast iron casting, oxygen bath purging, flowing from above from a height of 2-10 m above the level of a calm bath through the side tuyeres to the center of the bath oxygen in the form of free jets, supplying powder materials from below simultaneously with the start of purging and powdered lime during foaming of slag, characterized in that, in order to increase the proportion of scrap in the charge, oxygen-free gas is supplied from below to the bath, and the bath is purged with oxygen from above through a central multi-nozzle lance during the phase of desiliconization, after which the lance is raised to a height of 1.5 - 10.0 m above the level of a calm bath and oxygen is supplied in the form of free jets, while the oxygen flow through the lateral lances is maintained at 25-50% of its total consumption.
SU803217507A 1979-12-11 1980-12-10 Method of producing steel RU2010864C1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE792951156 1979-12-11
DE19792951156 DE2951156A1 (en) 1979-12-11 1979-12-11 Steel prodn. in top and bottom blown converter - with bottom nozzles fed at least periodically with solids-laden oxygen-free gas

Publications (1)

Publication Number Publication Date
RU2010864C1 true RU2010864C1 (en) 1994-04-15

Family

ID=6088947

Family Applications (1)

Application Number Title Priority Date Filing Date
SU803217507A RU2010864C1 (en) 1979-12-11 1980-12-10 Method of producing steel

Country Status (5)

Country Link
JP (1) JPS56105413A (en)
DE (1) DE2951156A1 (en)
MX (1) MX157359A (en)
RU (1) RU2010864C1 (en)
ZA (1) ZA807738B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2123056C1 (en) * 1997-10-15 1998-12-10 Открытое акционерное общество "Северсталь" Process of blow-through of converter bath
US8747518B2 (en) 2010-01-19 2014-06-10 Sms Siemag Aktiengesellschaft Method for foamed slag generation of a non-corrosive melt in a converter

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56163211A (en) * 1980-05-16 1981-12-15 Nippon Steel Corp Steel making method
NL8201269A (en) * 1982-03-26 1983-10-17 Hoogovens Groep Bv METHOD FOR MANUFACTURING STEEL IN A CONVERTER FROM CRUDE IRON AND SCRAP.
US11155890B2 (en) * 2019-07-17 2021-10-26 Air Products And Chemicals, Inc. Tuyere for a basic oxygen furnace
CN112322825B (en) * 2020-10-26 2022-07-15 北京首钢股份有限公司 Method for reducing total iron content of semisteel furnace slag

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT337736B (en) * 1973-02-12 1977-07-11 Voest Ag METHOD OF REFRESHING BIG IRON
DE2316768B2 (en) * 1973-04-04 1977-03-03 Fried. Krupp Gmbh, 4300 Essen PROCESS FOR REFRESHING METALS, IN PARTICULAR PIG IRON, AND DEVICE FOR CARRYING OUT THE PROCESS
JPS5813816B2 (en) * 1977-07-15 1983-03-16 松下電器産業株式会社 High frequency heating device
US4195985A (en) * 1977-12-10 1980-04-01 Eisenwerk-Gesellschaft Maximilianshutte Mbh. Method of improvement of the heat-balance in the refining of steel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2123056C1 (en) * 1997-10-15 1998-12-10 Открытое акционерное общество "Северсталь" Process of blow-through of converter bath
US8747518B2 (en) 2010-01-19 2014-06-10 Sms Siemag Aktiengesellschaft Method for foamed slag generation of a non-corrosive melt in a converter
RU2518837C2 (en) * 2010-01-19 2014-06-10 Смс Зимаг Аг Production of expanded slag on melt of stainless steel at converter

Also Published As

Publication number Publication date
MX157359A (en) 1988-11-17
DE2951156A1 (en) 1981-06-25
JPS6138249B2 (en) 1986-08-28
JPS56105413A (en) 1981-08-21
DE2951156C2 (en) 1987-07-16
ZA807738B (en) 1981-12-30

Similar Documents

Publication Publication Date Title
US3771998A (en) Method and converter for refining pig iron
HU182867B (en) Method for improving the thermal equilibrium at steel refining
CA1165128A (en) Vortex reactor and method for adding solids to molten metal therewith
SU1306482A3 (en) Method for steel melting in converter
CZ278884B6 (en) Steel making process
CA1211630A (en) Lance structure and oxygen-blowing process for top- blown converters
RU2010864C1 (en) Method of producing steel
US5658368A (en) Reduced dusting bath method for metallurgical treatment of sulfide materials
CA1305862C (en) Method and plant for fully continuous production of steel strip from ore
JPS6023163B2 (en) steel smelting method
JPS5935407B2 (en) Carbon supply method to iron melt in converter
US3907548A (en) Process for the production of steels having high chromium content and lowest possible carbon content
JP2013209746A (en) Method for refining molten iron in converter type refining furnace
RU2031131C1 (en) Method for steel making in converter
JP2808197B2 (en) Vacuum refining of molten steel using large diameter immersion tube
US3192037A (en) Desulfurization method
HU184357B (en) Method for improving the heat utilization at steelmaking sarried out from solid iron stock
US3687435A (en) Process for refining liquid pig iron in a spray refining plant and spray refining plant for carrying out such process
JP2003193121A (en) Hot metal refining method
ITRM960551A1 (en) PROCEDURE FOR THE DIRECT PRODUCTION OF CAST IRON STARTING FROM FERRIFEROUS MATERIAL AND APPROPRIATE EQUIPMENT FOR THE EXECUTION OF SUCH PROCE =
US3591159A (en) Apparatus for producing steel from pig iron in continuous process
RU2131571C1 (en) Method of application of coat on lining of metallurgical unit and on lining of metallurgical reservoir
SU1090724A1 (en) Method for smelting low-nitrogen steel (modifications)
SU1504262A1 (en) Method of melting steel in converter
AU606457B2 (en) Process for melt reduction of cr starting material and melt reduction furnace