WO2000024535A1 - Installation de coulee continue verticale avec mesure optimisee du niveau de metal - Google Patents

Installation de coulee continue verticale avec mesure optimisee du niveau de metal Download PDF

Info

Publication number
WO2000024535A1
WO2000024535A1 PCT/EP1999/007868 EP9907868W WO0024535A1 WO 2000024535 A1 WO2000024535 A1 WO 2000024535A1 EP 9907868 W EP9907868 W EP 9907868W WO 0024535 A1 WO0024535 A1 WO 0024535A1
Authority
WO
WIPO (PCT)
Prior art keywords
measuring
level
metal
measuring system
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/EP1999/007868
Other languages
German (de)
English (en)
Inventor
Etienne Caloz
Jean-Pierre Seppey
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
3A Composites International AG
Original Assignee
Alusuisse Lonza Services Ltd
Alusuisse Technology and Management Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Alusuisse Lonza Services Ltd, Alusuisse Technology and Management Ltd filed Critical Alusuisse Lonza Services Ltd
Priority to EP99950752A priority Critical patent/EP1133371A1/fr
Priority to AU63407/99A priority patent/AU749027B2/en
Priority to CA002348613A priority patent/CA2348613A1/fr
Publication of WO2000024535A1 publication Critical patent/WO2000024535A1/fr
Priority to IS5920A priority patent/IS5920A/is
Priority to NO20011978A priority patent/NO20011978L/no
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/16Controlling or regulating processes or operations
    • B22D11/18Controlling or regulating processes or operations for pouring
    • B22D11/181Controlling or regulating processes or operations for pouring responsive to molten metal level or slag level
    • B22D11/185Controlling or regulating processes or operations for pouring responsive to molten metal level or slag level by using optical means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/16Controlling or regulating processes or operations
    • B22D11/18Controlling or regulating processes or operations for pouring
    • B22D11/181Controlling or regulating processes or operations for pouring responsive to molten metal level or slag level
    • B22D11/186Controlling or regulating processes or operations for pouring responsive to molten metal level or slag level by using electric, magnetic, sonic or ultrasonic means

Definitions

  • the invention relates to a vertical continuous casting system, in particular a vertical continuous casting system for the automatic continuous casting of aluminum alloys, comprising at least one mold with a start-up base arranged on a lowerable casting table, a pouring channel system for transporting a molten metal from an oven into the individual molds, and a measuring device for determining each mold of the time-dependent metal melt level N (t) and a flow control device for controlling the metal supply into the individual molds as a function of the difference between a predetermined setpoint curve N so n (t) and the measured time-dependent metal melt level N (t).
  • the invention further relates to a method for vertical continuous casting of metals, in particular aluminum alloys, in a casting plant comprising at least one mold, in which method the liquid metal is fed from an oven to the individual molds via a trough system and into the mold via a flow control device closed molds are initially guided during a filling phase from start-up floors arranged on a lowerable casting table, starting from an initial level of the metal melt, at which metal melt level control begins, to a predetermined start level, at which the lowering of the casting table to generate the metal strands begins, and during the entire lowering phase the time-dependent metal level N (t) in each mold is measured with a measuring device and compared with a time-dependent setpoint specification N so u (t), and the metal supply into the individual molds by means of a through flow control device is controlled according to the time-dependent difference between the actual and target value of the metal level.
  • Such a method, as well as such a vertical continuous casting installation containing several molds are known for example from DE-OS 32 05 480 AI.
  • the detection of the metal level takes place by means of a float as a measuring sensor, which rests on the surface of the metal column and consists of a heat-resistant material, which must be selected such that absorption of molten metal or contamination is avoided.
  • Patent EP-B 0 517 629 also describes an apparatus described at the outset and a corresponding method for vertical continuous casting of metals, a capacitive sensor being used to record the time-dependent metal melt level in the individual molds.
  • the capacitive level measurement takes place between the surface of the molten metal and one at a certain distance from it located plate, which is adjusted in its distance from the metal surface by means of a servo motor in such a way that the capacity is constant and equal to a reference capacity.
  • WO 98/32559 describes a method according to that the metal level in all molds is controlled simultaneously according to a setpoint curve that is identical for all molds, the gradient of which is greater at the beginning of the cleaning process than the average gradient and is smaller than the average gradient at the end of the start-up phase.
  • the filling level of the molds for the start of the lowering process is typically between 120 and 200 mm.
  • the precise control of the metal level is of crucial importance for trouble-free operation of a casting system, especially in the lowering phase.
  • the precise control of the metal level in the individual molds requires a correspondingly precise measurement of the fill level.
  • the precise metal level control of a casting system requires precise and reproducible level measurement over a large measuring range of typically 200 mm.
  • the importance of a precise metal level determination is greatly increased, in particular in the further developed controls of multi-mold continuous casting plants, such as, for example, controls according to WO 98/32559, in which the level control takes place with non-linear setpoint curves.
  • Inductive or capacitive sensors are suitable for the exact level determination.
  • the required accuracy can only be achieved with inductive sensors in a measuring range of approx. 30-50 mm.
  • the vertical continuous casting plants known from the prior art therefore use most devices in which such sensors are tracked by means of a precision mechanism in cooperation with a servo or stepper motor in such a way that the measuring range permitted for the required measuring accuracy is not exceeded.
  • Capacitive sensors can be used for large measuring ranges of up to 300 mm, for example; however, they show a great dependency on the external measurement conditions, so that frequent recalibration is necessary.
  • laser-optical, ultrasound and microwave methods are also known for level and distance measurements.
  • Laser-optical methods can only be used to a limited extent for the level measurement of highly reflective samples. Such methods are in principle suitable for level measurement of metal alloys, for example aluminum alloys, during the filling phase of the mold and at the beginning of the lowering phase. During the lowering phase - at least with aluminum alloys - a highly reflective oxide layer forms after a few minutes after the start of the lowering phase, which severely impairs or even makes it impossible to use laser-optical methods for level measurement.
  • metal alloys for example aluminum alloys
  • Ultrasound and microwave methods based on the radar principle have a large measuring range and allow contactless level measurement, but do not show the required measuring accuracy, at least not for the lowering phase of the continuous casting process.
  • the ultrasonic level measurement methods are strongly temperature-dependent, and the microwave level measurement methods are sensitive to the measurement environment.
  • the invention is therefore based on the object of providing a vertical continuous casting installation of the type mentioned at the outset with a precise, functionally reliable and inexpensive fill level measurement and of specifying a method of the type mentioned at the outset in which the metal level measurement is carried out in a simple manner with high precision can be.
  • the object on which the vertical continuous casting installation is based is achieved in that the measuring device consists of two physically different working measuring systems with one sensor each, the sensors of each measuring device are fixed at a predetermined and fixed distance with respect to the mold, and the first measuring system in a measuring range of at least 200 mm has a measuring accuracy of at least ⁇ 2 mm, and the second measuring system has a measuring accuracy of at least ⁇ 0.1 mm in a measuring range of at least 20 mm.
  • the invention advantageously relates to vertical continuous casting plants with several molds.
  • the device according to the invention also comprises vertical continuous casting plants with only a single mold.
  • the solution according to the invention is based on the idea that at the beginning of the continuous casting process, that is to say during the first filling phase of the mold which is initially closed by the start-up floor, and during the remaining filling phase, and during the lowering process of the casting table, different level measuring devices can be used which meet the specific requirements Optimally take into account requirements during the basically different phases.
  • the invention is further based on the knowledge that a large measuring range of approx. 200 mm is only required during the first filling phase of the mold, which is initially closed by the start-up floor, and in the subsequent filling and lowering phase of the casting table, a smaller measuring range of, for example, 15- 20 mm is sufficient.
  • less high measuring accuracy is required during the start phase than in the subsequent filling and lowering phase, since the filling level changes very quickly in the first filling phase.
  • a very high measuring accuracy is required during the subsequent filling and lowering phase.
  • measuring range means a measuring range in which the values in the entire range can lie between a maximum and a minimum measuring value, the difference between the maximum and the minimum value corresponding to the measuring range in terms of amount.
  • the measured values with a measuring range of 200 mm are in a range between 0 and 200 mm.
  • a measuring device is preferred in which the first measuring system is based on an optical, capacitive, ultrasonic or microwave method, and the second measuring system is based on an inductive, capacitive or optical method.
  • a measuring device is particularly preferred in which the first measuring system is based on an optical or an ultrasound or microwave method, and the second measuring system is based on an inductive or capacitive method.
  • the first filling phase of the mold closed with the start-up floor usually takes place at the highest possible speed, so that the metal level rises very quickly at the beginning of the mold filling.
  • a turbulent flow is formed in the mold at the beginning of the filling phase, so that there is no flat melt surface at the start of the filling process, as a result of which the reflective properties of the melt surface are significantly lower compared to a flat surface of the same metal.
  • Oxide skin allows the first filling phase to be measured using laser-optical methods.
  • the subsequent casting process ie during the remaining filling phase and during the lowering process of the casting table, the use of a laser-optical level measurement process is not suitable for all alloys due to the high reflection of the essentially flat molten metal surface.
  • the first measuring system can relate to sensors or sensors which are based on one of the level measurement methods described below: a) ultrasound method b) optical method c) microwave method according to the radar principle d) capacitive method
  • a level measurement with ultrasound is based either on measuring the transit time of a sound pulse or on measuring sound absorption. Measurement of the transit time of an ultrasonic pulse, i.e. the distance from the melt surface is calculated from the transit time between the transmitted and received signal.
  • the runtime method usually works on the principle of the echo sounder, i.e. An electrical pulse is converted, for example, by a piezoelectric oscillator attached to the start-up floor or to a lower region of the mold into an ultrasound pulse which is emitted into the melt and is partially reflected by the melt-air boundary layer, the reflected ultrasound pulse (echo) being of a similar type hits the piezoelectric oscillator by converting the echo back into an electrical pulse.
  • the fill level results from the transit time of the sound pulse and the speed of sound.
  • the level can also be measured using the same sonar principle if the ultrasonic transmitter and receiver are located in the air space above the melt surface.
  • the temperature of the measuring media must be taken into account when measuring the ultrasound level, since the speed of sound is temperature-dependent.
  • microwave transmitters and receivers as well as an antenna are attached above the mold.
  • the surface of the molten metal partially reflects the usually frequency-modulated, electromagnetic waves or pulses emerging from the microwave transmitter.
  • the distance between the antenna and the melt surface is measured according to the radar principle.
  • a microwave signal of constant amplitude is emitted and again after the reflection received and mixed with part of the transmission signal; the frequency of the mixer output signal is proportional to the transit time and thus a measure of the distance between the transmitter and the melt surface.
  • An optical level measurement can relate to an interf erometric distance measurement, a laser runtime method or a triangulation method.
  • the distance of the reflecting melt surface is measured by a sensor. Either the phase angle difference between the reflected and unreflected, modulated laser beam is evaluated as the measurement signal, or the displacement of the reflector surface (melt surface) is measured with a counting laser interferometer.
  • a monochromatic laser beam is expediently split into a measuring and a reference beam on a semitransparent mirror. Both beams are reflected by one reflector, one fixed and one movable. The reflected rays are superimposed on the semi-transparent mirror, creating interference fringes that lie across the receiver and are analyzed by it.
  • the level measurement can be carried out by a direct transit time measurement of a light pulse or by a phase measurement.
  • the transmission signal is expediently modulated onto a carrier signal, for example in the MHz range, the phase shift being measured in the receiver after demodulation.
  • the direct transit time measurement is based on the radar principle, whereby the smallest time differences in the nano to picosecond range are measured.
  • the level measurement is traced back to an angle measurement.
  • a highly concentrated beam of light from a laser hits the melt surface at an acute angle and is reflected there.
  • the reflected light beam strikes a specific point on the receiver, ie, for example a position detector.
  • the position detector can represent, for example, a CCD line (Charge Coupled Device), which consists of a large number of light-sensitive components (pixels) arranged in a line. This position can be recorded with a CCD line and converted into the level using the angle or path difference.
  • the location of the reflected laser beam on the position detector shifts depending on the distance of the melt surface from the sensor.
  • the capacitance is measured as a function of the melt height.
  • the capacity changes, for example, through the degree of coverage or the distance between two given surfaces.
  • the capacitance also changes due to a change in the dielectric constant (e.g. the air) due to the introduction of the molten metal.
  • a change in capacitance is detected, for example, by changing the capacitive resistance.
  • the second measuring system can relate to sensors or sensors which are based on one of the level measurement methods described below: e) capacitive f) inductive g) optical
  • the inductive sensors are preferably based on measuring the change in the inductive resistance X L , with:
  • A the one penetrated by the magnetic field lines
  • the sensors are arranged at a predetermined and fixed distance with respect to the mold, i.e. the two measuring systems have no device for height adjustment of the sensors.
  • measuring systems which have no mechanically movable parts, and in particular no mechanical precision parts. Measuring systems which operate in a contactless manner with regard to the molten metal are further preferred.
  • a measuring device for each casting unit (mold) is particularly preferred, in which the first measuring system is based on an optical method, in particular on a triangulation method, and the second measuring system is based on an inductive method.
  • a first measuring system with a measuring range of up to 200 mm is very particularly preferred, with a measuring accuracy of ⁇ 1 mm being achieved in the entire measuring range.
  • the measuring accuracy of the first measuring system is typically between ⁇ 0.1 mm and ⁇ 2 mm, preferably between ⁇ 0.1 mm and ⁇ 1 mm.
  • the measuring range of the second measuring system is typically 20 to 50 mm, the measuring accuracy typically being between ⁇ 0.01 mm and ⁇ 0.1 mm, preferably between ⁇ 0.01 mm and ⁇ 0.08 mm.
  • the combination of an optical sensor with an inductive sensor allows the provision of a compact and powerful measuring device which, on the one hand, does not require expensive, sensitive and elaborately designed mechanical sensor tracking devices and, on the other hand, has a sensor characteristic that is adapted to the individual casting phases in terms of measuring range and measuring accuracy efficient level measurement of the molten metal allowed with sufficiently high accuracy.
  • the continuous casting installation according to the invention is also particularly suitable for a control algorithm for introducing metal into the individual molds, in which non-linear setpoint curves are used to control the level of molten metal.
  • the solution according to the invention to the problem relating to the method is that the measurement of the time-dependent metal level N (t) is carried out with a measuring device consisting of two physically different measuring systems, starting from the initial level until reaching a predetermined melt level by a first measuring system with a first Sensor happens, and for the further measurement of the time-dependent metal level curve N (t) during the subsequent filling and lowering phases, a second measuring system with a second sensor is used, and the sensors of the two measuring systems with respect to the mold are fixed and throughout Continuous casting process take a constant position.
  • the filling phase begins with the introduction of liquid metal onto the start-up floor and ends with the start of lowering the start-up floor, ie when the start level N s is reached at time t s .
  • the metal level control usually only starts when a certain metal level N a at time t a in which the mold, which was initially closed by the start-up floor, is reached.
  • the first filling phase denotes the period from the start of the introduction of liquid metal into the mold until the time t w , at which the change from the first to the second measuring system for the metal level determination takes place, where t w denotes the time at which the metal level in the first a mold closed by the start-up floor reaches a predetermined height N w .
  • the period between t w and t s describes the second or the further filling phase, or that of the first filling phase that follows.
  • the lowering phase begins when the start level N s is reached at time t s and lasts until the end or the termination of the continuous casting process.
  • the flow control device is controlled as a function of the difference in the measured metal level curve N (t) from the setpoint curve N so n (t) by means of a control unit, the flow control device determining the amount of metal melt flowing into the mold.
  • the control unit determines, for example, the starting time t a of the mold filling, the time t w for changing the measuring system, the starting time t s of the lowering process, the filling of the mold or the amount of metal to be introduced into the mold per unit of time during the filling phase and during the Lowering process, the lowering speed of the casting table and the control of the measuring system responsible for level measurement N (t).
  • the control unit may also be used to monitor and control further process parameters, such as cooling water supply, CO 2 supply, grain refining agent supply, EMC power supply, and automatically initiate the lowering process of the casting table, for example.
  • the metal supply into the individual molds is only regulated directly up to the starting time t s by the time-dependent difference between the actual and the setpoint value of the metal level. Furthermore, the direct control of the metal supply takes place after the start of the lowering process as a function of the bar length, ie as a function of the vertical casting table position, and on the basis of the difference between the actual and target value of the metal level. Accordingly, the control of the metal supply takes place after the start time t s by the bar length-dependent difference between the actual and target value of the metal level.
  • the bar length increases linearly with time, so that the regulation of the metal supply is also regulated during the lowering process in accordance with the time-dependent difference between the actual and target value of the metal level.
  • the time t a of the start of the level control is preferably determined by measuring the metal level, in particular by level measurement using a laser-optical method.
  • the level measurement by means of the second measuring system ie the time of the change of the measuring systems, can either be triggered by a control unit on the basis of the measured metal level, or according to a preferred embodiment, in particular when using a second measuring system with an inductive measuring method, directly are triggered by the melt level by changing the measuring system at a time at which the melt enters, for example, the cavity formed by an inductively operating measuring coil.
  • the method according to the invention is suitable for casting plants with only one mold; however, it is particularly suitable for vertical continuous casting plants with several molds.
  • the sensors of the two measuring systems of a casting unit have a fixed position with respect to the mold and are constant during the entire continuous casting process, i.e. the measurement is carried out without any mechanical tracking device, for example in the form of a height adjustment of the sensors.
  • the level measurement is preferably carried out without contact during the first filling phase with respect to the molten metal.
  • the measuring systems include continuously and discontinuously operating level detection systems. Accordingly, the method according to the invention can be carried out by a continuous and / or discontinuous level measurement.
  • a continuous metal level measurement is preferred for level measurement with the second measuring system.
  • the measurement with the first measurement system is preferably carried out at discrete times, in particular with 3 to 10 measurement values, the level measurement being carried out continuously with the second measurement system.
  • the lowering of the casting table with the start-up trays expediently begins as soon as the start level is reached in a mold.
  • the metal level in the casting trough is also preferably kept at a constant level from the start of the filling phase of the start-up trays and the molds up to and with the stationary casting phase (lowering phase).
  • the continuous casting installation according to the invention and the method according to the invention are suitable for the casting of all continuously castable metals, but preferably for the continuous casting of aluminum, magnesium and copper alloys.
  • the continuous casting installation according to the invention and the method according to the invention are particularly suitable for the continuous casting of aluminum alloys.
  • FIG. 1 schematically shows a simplified cross section through part of a mold with the approach floor retracted.
  • Figure 2 shows schematically a setpoint curve of the time course of the metal level in a mold.
  • the vertical continuous casting installation shown in FIG. 1 contains a mold 10 with a start-up floor 14 arranged on a lowerable casting table 16, a lifting / lowering device 11 for the casting table, which is driven by a motor 12, the motor being controlled by a control unit 34, a metal level measuring device consisting of two measuring systems 22, 26, a pouring channel system 20 for transporting a molten metal 18 from a furnace (not shown) into the mold 10, a flow control device 30 controlled by the control unit 34 determining the quantity of molten metal to be introduced into the mold.
  • the control unit 34 determines, among other things, the starting time t a of the mold filling, the starting time t s of the lowering process, the filling of the mold or the amount of metal 18 to be introduced into the mold 10 per unit of time during the filling phase and during the lowering process and the lowering speed of the casting table 16 wherein the control unit 34 so ⁇ in dependence of the metal level measurement N (t) and a predetermined setpoint curve N (t) is working.
  • the flow control device 30 shown by way of example in FIG. 1 essentially consists of an inlet opening 33 located in the casting trough 20, which can be closed by a vertically movable stopper 32.
  • the stopper 32 can be brought into the closed position on the one hand by lowering it into the inlet opening 33, or by lifting the opening cross section and thus the supply of molten metal 18 into the mold 10 can be increased accordingly.
  • the stopper 32 has a stopper rod which is guided by a holding device and driven by a motor 31, the motor being controlled via the control unit 34.
  • the inlet opening 33 of the trough 20 is opened by lifting the stopper 32 of the flow control device 30 and the filling of the approach floors 14 and the molds 10 begins with the liquid metal 18 .
  • the metal level N (t) in the approach floor 14 or in the mold 10 takes place, for example PID-controlled, via a measuring device containing two measuring systems 22, 26.
  • the mold 10 shown in Figure 1 is shown in the closed state, i.e. the start-up floor rests on the mold 10, the lowering process not yet having started. However, the filling phase is almost complete since the mold 10 is already filled with liquid metal 18 up to close to the second sensor 28.
  • the first sensor 24 is at a greater distance from the approach floor 14 than the second sensor 28. This ensures that the first sensor 24, which is based on a laser-optical method, does not come into contact with the melt 18. However, the second sensor 28, which is based on an inductive measurement method, requires, at least in part, direct contact with the melt 18.
  • the sensors 24 and 28 are connected at a fixed distance to the respective other measuring system 22 and 26, respectively.
  • the two measuring systems 22 and 26 are mechanically firmly connected to one another, i.e.
  • the two measuring systems usually form a mechanical unit with one another.
  • the distance of the sensors 24, 28 from the mold is constant during the entire continuous casting process, ie the distance of the sensors 24, 28 from the metal surface changes constantly, in particular during the filling phase of the mold. Accordingly, at the beginning of the filling phase, the distance of the sensors 24, 28 from the molten metal surface, respectively. to the approach floor 14 is greatest, while this distance decreases continuously or discontinuously during the filling phase and remains essentially constant after reaching the start level N s , ie at the beginning and during the lowering process.
  • the exemplary embodiment shown in the drawing relates to continuous casting with a conventional mold.
  • the vertical continuous casting installation according to the invention also includes other casting methods, such as, for example, casting in an alternating electromagnetic field (EMC), ie using an electromagnetic mold.
  • EMC alternating electromagnetic field
  • FIG. 2 shows an example of a setpoint curve N so n (t) for the method according to the invention.
  • the metal level control begins on the basis of the setpoint profile N So i ⁇ (t) and the measured metal level N (t) until the metal level in the through the approach floor 14 closed mold 10 has reached the start level N s at the start time t s , where the lowering of the casting table 16 for producing the metal strands begins.
  • the setpoint curve N so n (t) shown in FIG. 2 is polygonal and is suitable, for example, for discontinuous control of the metal level.
  • the setpoint curve N sou (t) has a larger slope than the average slope ⁇ ⁇ r.
  • the setpoint curve N soll (t) points in one against the
  • Starting level N s nearby area has a smaller gradient than the average gradient.
  • the switch from the first measuring system 22 to the second measuring system 26 takes place.
  • the point in time t w is determined by the entry of the melt into the cavity formed by an inductively working measuring coil. Accordingly, the metal height N (t) above the approach floor 14 during the first filling phase, ie until the filling height has reached the value N w , is determined with the first measuring system 22, which has a large measuring range.
  • the metal height is determined with the second measuring system 26, the measuring range of which is smaller than the first measuring system 22, but has a high measuring accuracy.
  • the high measurement accuracy is particularly important from time t w , since thereafter the setpoint curve N thus ⁇ (t) is preferably flatter than the mean slope, and thus the metal supply to the individual casting units in a continuous casting installation having several molds 10 until the actual casting start t s , which is initiated by lowering the casting table 16, can be optimally controlled.
  • the starting level N s ie the height of the surface of the liquid metal 18 above the approach floor 14 at the starting time t s , is typically between 100 and 200 mm and in particular between 120 and 190 mm.
  • Starting level t a - the starting level N s is typically reached within a time of 20 to 90 s or preferably within 25 to 45 s.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Measurement Of Levels Of Liquids Or Fluent Solid Materials (AREA)
  • Continuous Casting (AREA)

Abstract

L'invention concerne une installation de coulée continue verticale, comportant au moins une lingotière (10) avec un faux-fond (14) placé sur une table de coulée (16) pouvant être abaissée (14), un système de canaux de coulée (20) pour le transport du bain entre le four et les lingotières individuelles (10), et, pour chaque lingotière (10), un dispositif de mesure servant à déterminer le niveau de bain métallique N(t) en fonction du temps, ainsi qu'un dispositif de régulation de débit (30) pour réguler l'apport de métal dans les lingotières individuelles (10) en fonction de la différence entre un écoulement de consigne Nsoll(t) et le niveau mesuré de bain métallique N(t) en fonction du temps. Le dispositif de mesure comprend deux systèmes de mesure (22, 26) opérant de manière différente physiquement, comportant chacun un détecteur (24, 28) fixé à une distance prédéterminée et fixe par rapport à la lingotière (10). Le premier système de mesure (22) présente dans une plage de mesure inférieure à 200 mm une précision de mesure d'au moins +/- 2 mm et sert à mesurer le niveau N(t) pendant une phase de remplissage de la lingotière (10), et le deuxième système (26) présente dans une plage de mesure d'au moins 20 mm une précision de mesure d'au moins +/- 0,1 mm et sert à mesurer le niveau N(t) pendant une phase finale de remplissage et pendant la phase d'abaissement de la table de coulée (16).
PCT/EP1999/007868 1998-10-23 1999-10-16 Installation de coulee continue verticale avec mesure optimisee du niveau de metal Ceased WO2000024535A1 (fr)

Priority Applications (5)

Application Number Priority Date Filing Date Title
EP99950752A EP1133371A1 (fr) 1998-10-23 1999-10-16 Installation de coulee continue verticale avec mesure optimisee du niveau de metal
AU63407/99A AU749027B2 (en) 1998-10-23 1999-10-16 Vertical continuous casting installation with optimized measurement of the metal level
CA002348613A CA2348613A1 (fr) 1998-10-23 1999-10-16 Installation de coulee continue verticale avec mesure optimisee du niveau de metal
IS5920A IS5920A (is) 1998-10-23 2001-04-18 Búnaður fyrir lóðrétta, samfellda steypuvinnslu með kjörmælingu á málmhæðinni
NO20011978A NO20011978L (no) 1998-10-23 2001-04-20 Vertikalstrengstöpeanlegg med optimalisert metallnivåmåling

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
EP98811066A EP0995523A1 (fr) 1998-10-23 1998-10-23 Installation de coulée continue verticale avec mesure optimisée du niveau de métal liquide
EP98811066.4 1998-10-23

Publications (1)

Publication Number Publication Date
WO2000024535A1 true WO2000024535A1 (fr) 2000-05-04

Family

ID=8236404

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP1999/007868 Ceased WO2000024535A1 (fr) 1998-10-23 1999-10-16 Installation de coulee continue verticale avec mesure optimisee du niveau de metal

Country Status (7)

Country Link
EP (2) EP0995523A1 (fr)
AU (1) AU749027B2 (fr)
CA (1) CA2348613A1 (fr)
IS (1) IS5920A (fr)
NO (1) NO20011978L (fr)
WO (1) WO2000024535A1 (fr)
ZA (1) ZA200102812B (fr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017111722A1 (de) * 2017-05-30 2018-12-06 Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. Verfahren und vorrichtung zum charakterisieren eines objekts, verfahren und vorrichtung zum bestimmen einer zusammensetzung eines objekts sowie verfahren und vorrichtung zum erkennen eines elektrisch leitfähigen und/oder magnetisch permeablen objekts

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7296613B2 (en) * 2003-06-13 2007-11-20 Wagstaff, Inc. Mold table sensing and automation system
WO2010078201A1 (fr) * 2008-12-31 2010-07-08 Tenedora Nemak, S.A. De C.V. Moulage en sable basse pression d'éléments de moteur à cylindres en alliage d'aluminium
AT509736B1 (de) * 2010-05-14 2012-03-15 Inteco Special Melting Technologies Gmbh Verfahren und vorrichtung zur kontinuierlichen erfassung des schlackenniveaus in esu-anlagen mit kurzen gleitkokillen
CN110508764B (zh) * 2019-09-20 2021-01-15 哈尔滨工业大学 一种等外径薄壁合金铸件行波磁场/超声波协同优化的半连铸设备及其半连铸方法
CN116583613A (zh) * 2021-01-26 2023-08-11 诺维尔里斯公司 含钙的铸造铝合金及相关工艺

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3205480A1 (de) * 1981-05-26 1982-12-16 Kaiser Aluminum & Chemical Corp., 94643 Oakland, Calif. Verfahren und einrichtung zum regeln des metallbadpegels in einer mehrzahl von vertikalen kontinuierlichen oder halbkontinuierlichen giesseinheiten
JPH0819844A (ja) * 1994-07-05 1996-01-23 Sumitomo Metal Ind Ltd 連続鋳造機における鋳造制御方法
EP0776715A1 (fr) * 1995-02-28 1997-06-04 Nkk Corporation Procede et appareil de regulation de la coulee continue
WO1998032559A1 (fr) * 1997-01-24 1998-07-30 Alusuisse Technology & Management Ag Procede pour la coulee continue verticale de metaux

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3205480A1 (de) * 1981-05-26 1982-12-16 Kaiser Aluminum & Chemical Corp., 94643 Oakland, Calif. Verfahren und einrichtung zum regeln des metallbadpegels in einer mehrzahl von vertikalen kontinuierlichen oder halbkontinuierlichen giesseinheiten
JPH0819844A (ja) * 1994-07-05 1996-01-23 Sumitomo Metal Ind Ltd 連続鋳造機における鋳造制御方法
EP0776715A1 (fr) * 1995-02-28 1997-06-04 Nkk Corporation Procede et appareil de regulation de la coulee continue
WO1998032559A1 (fr) * 1997-01-24 1998-07-30 Alusuisse Technology & Management Ag Procede pour la coulee continue verticale de metaux

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 096, no. 005 31 May 1996 (1996-05-31) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017111722A1 (de) * 2017-05-30 2018-12-06 Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. Verfahren und vorrichtung zum charakterisieren eines objekts, verfahren und vorrichtung zum bestimmen einer zusammensetzung eines objekts sowie verfahren und vorrichtung zum erkennen eines elektrisch leitfähigen und/oder magnetisch permeablen objekts
US11156490B2 (en) 2017-05-30 2021-10-26 Fraunhofer-Gesellschaft Zur Foerderung Der Angewandten Forschung E.V. Method and apparatus for determining a fill level of a storage container

Also Published As

Publication number Publication date
ZA200102812B (en) 2001-11-15
EP1133371A1 (fr) 2001-09-19
NO20011978L (no) 2001-06-08
EP0995523A1 (fr) 2000-04-26
AU6340799A (en) 2000-05-15
CA2348613A1 (fr) 2000-05-04
IS5920A (is) 2001-04-18
NO20011978D0 (no) 2001-04-20
AU749027B2 (en) 2002-06-13

Similar Documents

Publication Publication Date Title
DE68929292T2 (de) Aufbringen und Abstreichen von Stereolithografischen Schichten
DE2840783C2 (fr)
DE2839953C3 (de) Vorrichtung und Verfahren zum Messen der Badspiegelhöhe in einer Stranggießkokille
DE19501379A1 (de) Verfahren und Vorrichtung zur Bandbreitensyntheseradarpegelmessung
EP0015550A1 (fr) Procédé et dispositif de détermination des propriétés visco-élastiques de fluides
DE10037715A1 (de) Vorrichtung zur Messung des Füllstands eines Füllguts in einem Behälter
EP0581786A1 (fr) Procede pour le reglage des parametres de coulee dans une machine a couler sous pression.
DE1297827B (de) Verfahren und Vorrichtung zur Regelung der aus einer Giesspfanne ausfliessenden Metallmenge
EP1133371A1 (fr) Installation de coulee continue verticale avec mesure optimisee du niveau de metal
DD297703A5 (de) Verfahren zur kontinuierlichen bestimmung der dicke einer fluessigen schlackenschicht auf der oberflaeche einer metallscmelze
DE2452669A1 (de) Vorrichtung zur bestimmung der lageaenderung eines gegenstandes
EP0131979B1 (fr) Procédé de réglage du niveau d'un bain de métal fondu
DE2921049C3 (de) Anordnung zur Rauschunterdrückung für Wirbelstrom-Abstandsmeßvorrichtung zum Messen des Badspiegels von geschmolzenem Metall in einer Stranggießkokille
DE19607681B4 (de) Verfahren und Vorrichtung zur kontinuierlichen Messung und Regelung der Zusammensetzung einer Feuchtmittellösung für den Offsetdruck
EP1059516A1 (fr) Appareil et procédé pour la mesure du niveau de remplissage de récipients
DE19516789A1 (de) Vorrichtung zur Überwachung des Füllstandes eines Vorratsbehälters
EP0120338B1 (fr) Procédé pour la détection de l'usure de la paroi de la coquille pendant la coulée continue et pour la détection du décollement de la croûte solidifiée de la barre de la paroi intérieure de la coquille
DE69216276T2 (de) Verfahren zum Messen des Molekulargewichts eines Polymers
DE2906641A1 (de) Verfahren zur optisch-elektrischen messung des abstandes zwischen einer messeinrichtung und einem pruefling
DE3323748A1 (de) Verfahren zur messung und regelung des fuellstandes von in einem behaelter befindlichen stoffen
DE3307393A1 (de) Verfahren und vorrichtung zur bestimmung des oberflaechen-niveaus von fluessigem metall
EP0451929B1 (fr) Procédé pour la détermination et le réglage d'un niveau du bain de métal liquide
DE2428364A1 (de) Pegelbestimmungsvorrichtung
WO2017202639A1 (fr) Dispositif et procédé pour déterminer la vitesse d'écoulement d'une matière liquide
EP4075107B1 (fr) Appareil de mesure radar destiné à la détection d'une cavité

Legal Events

Date Code Title Description
ENP Entry into the national phase

Ref country code: AU

Ref document number: 1999 63407

Kind code of ref document: A

Format of ref document f/p: F

AK Designated states

Kind code of ref document: A1

Designated state(s): AE AU CA CZ HU IS JP NO US ZA

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE

121 Ep: the epo has been informed by wipo that ep was designated in this application
DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
WWE Wipo information: entry into national phase

Ref document number: 1999950752

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2001/02812

Country of ref document: ZA

Ref document number: 200102812

Country of ref document: ZA

WWE Wipo information: entry into national phase

Ref document number: 09807271

Country of ref document: US

ENP Entry into the national phase

Ref document number: 2348613

Country of ref document: CA

Ref country code: CA

Ref document number: 2348613

Kind code of ref document: A

Format of ref document f/p: F

WWE Wipo information: entry into national phase

Ref document number: 63407/99

Country of ref document: AU

WWP Wipo information: published in national office

Ref document number: 1999950752

Country of ref document: EP

WWG Wipo information: grant in national office

Ref document number: 63407/99

Country of ref document: AU

WWW Wipo information: withdrawn in national office

Ref document number: 1999950752

Country of ref document: EP