WO1996036780A1 - Ossature provisoire utilisee dans la construction d'un batiment - Google Patents
Ossature provisoire utilisee dans la construction d'un batiment Download PDFInfo
- Publication number
- WO1996036780A1 WO1996036780A1 PCT/JP1995/002761 JP9502761W WO9636780A1 WO 1996036780 A1 WO1996036780 A1 WO 1996036780A1 JP 9502761 W JP9502761 W JP 9502761W WO 9636780 A1 WO9636780 A1 WO 9636780A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- girder
- temporary
- construction
- frame
- main
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/26—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
- B66C23/28—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
- B66C23/32—Self-hoisting cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/26—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
- B66C23/28—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
- B66C23/283—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels with frameworks composed of assembled elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/24—Safety or protective measures preventing damage to building parts or finishing work during construction
- E04G21/28—Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence
Definitions
- the second invention relates to an all-weather construction temporary m-structure * device capable of performing construction work even in bad weather.
- An all-weather temporary frame has been proposed as a temporary scaffold for the construction of high-rise buildings with RC structures.
- This temporary frame is composed of a plurality of temporary columns erected around the structure to be constructed, and a roof frame supported above the temporary columns and having a shape sufficient to cover the entire upper surface of the planned structure. With the height of the structure being built, the temporary supports are added upward and the roof frame is raised, so that the project can be performed without being affected by the weather.
- overhead cranes are arranged on the lower surface of the roof frame, and construction materials lifted by a lifting machine such as a freight lift and a man lift are transported to various parts by the overhead cranes and assembled.
- the overhead crane is provided with a main girder that can reciprocate on the main rail, a sub-girder that can reciprocate on a sub-rail that is arranged parallel to the side of the main rail, and a movable girder along the main girder and the sub-girder. It is equipped with a hoist that can be transferred between each girder in a state where both girder are aligned in a straight line. Generally, two hoists are provided, and one hoist is transferred to the main girder, and materials lifted from the hoist are lifted to the construction floor, and the main girder moves on the main rail in this state.
- the hoist is transferred in a state of being aligned with one side of the sub-garg, and the sub-gadder to which the hoist has moved is moved along the sub-rail, so that the material is conveyed to the target site. I have.
- the construction of the temporary frame should be Conventionally, as shown in Japanese Unexamined Patent Publication No. Hei 4-221171, for example, a lifting device placed around a temporary column (temporary tower) on the ground is required. A method has been proposed in which a temporary support is lifted by means and new support is added to the lower part.
- a temporary support column is composed of a plurality of telescopic long posts that can be extended and retracted, and a work station is provided above the long post.
- a method has also been proposed in which a work station is raised by disposing a long post and sequentially extending a long post.
- any of the inventions since the temporary support itself moves, the support cannot be obtained from the structure under construction, and the higher the structure is, the less independent the individual temporary support stand becomes. Become stable. In order to resolve the independence of independence, it is conceivable that a brace is laid as a reinforcing material between the temporary columns, but it is not only troublesome to put the brace, but also the load of the brace increases and the Therefore, there is a problem that more power is required.
- the conventional all-weather construction frame is unsuitable as a temporary construction system for constructing a multi-story structure such as a skyscraper.
- the present invention makes it possible to reduce the driving force for raising the roof frame and keep it constant at all times while effectively utilizing the existing devices, and to support the temporary columns
- the primary objective is to suppress bending of the roof frame when it rises and to perform the work of adding the top temporary supports without competing with the construction work.
- the present invention is to improve the transfer efficiency by rapidly receiving materials by setting the main girder to a double type and leaving at least one of these main girder empty. For the second purpose. Disclosure of the invention
- the present invention is to provide a structure in which a structure is erected close to or within a planned construction position and is sequentially added upward according to an increase in construction height.
- a plurality of temporary supports, a climbing mechanism which is vertically movable around the temporary supports via upper and lower guide rollers, and a jack for raising and lowering is arranged; and between the upper and lower guide rollers of the climbing mechanism.
- a roof frame that is supported and covers the entire top surface of the structure.
- the present invention provides one or more temporary supports that are erected near or within a planned construction position of a structure and that are successively extended upward as the construction height increases,
- the climbing mechanism is arranged so that it can be lifted and lowered around the column via upper and lower guide rollers, and a climbing mechanism having a jack for lifting and lowering is supported in a suspended state below the climbing mechanism. It is characterized by having a roof frame that covers horizontally.
- the temporary support is a mast of a tower crane, the temporary support is supported on a structure side via a horizontal stay, and an overhead crane for material transfer is disposed on a lower surface of the roof frame. .
- the present invention is characterized in that the overhead crane comprises: a main girder capable of reciprocating on a main rail; and a sub girder capable of reciprocating on a sub rail arranged parallel to a side of the main rail.
- a load hoist is mounted so as to be movable along the sub-girder and can be transferred between the respective girders in a state where the two girders are aligned in a straight line, and the material is located on the main girder. It is delivered between the hoist and the main girder is a double type provided with two in the main rail extension direction, and a plurality of hoists are provided. Things.
- the double main girder is integrally movable, and is provided between the main rail and the sub-rail, and can be linearly connected to each crane girder. It is preferable that a fixed girder is provided, and that the transported object is lifted and transported to a target transport position while being transferred via each crane girder and the fixed girder.
- FIG. 1 is a side view of a temporary frame device according to an embodiment of the present invention.
- FIG. 2 is a front view of the same.
- FIG. 3 (a) is a sectional view taken along line AA of FIG. 1
- FIG. 3 (b) is a sectional view taken along line BB of FIG. 1
- FIG. 3 (c) is a sectional view taken along line CC of FIG.
- FIG. 4 is a side view of a temporary frame device according to another embodiment of the present invention in an initial assembled state.
- Fig. 5 is a side view during construction using the same device.
- FIG. 6 is a schematic plan view for explaining the operation of the overhead crane according to the present invention.
- FIG. 1 and Fig. 2 four temporary frame devices are installed outside the structure 1 to be constructed and are erected on a foundation located above the ground (only two are shown in the figures).
- Mast 2 a climbing mechanism 3 attached to each mast 2 so as to be able to move up and down, a roof frame 4 with four corners fixed to each climbing mechanism 3, and covering the entire top surface of the structure 1 horizontally.
- It is equipped with an overhead crane 5 arranged on the lower surface of the frame 4 and a jib crane 7 movably arranged along a guide rail 6 provided on the upper surface of the roof frame 4. Placed in the center).
- a freight lift and a lifting machine such as a human elevator (hereinafter simply referred to as a lifting machine) 8 are arranged at the center of one side of the structure 1. Construction material was handed over to a hoist 9 running on an overhead crane 5 And supplied to each part of structure 1.
- the mast 2 and the climbing mechanism 3 apply an existing mechanism used for a tower crane, and the mast 2 can select a cylindrical column in addition to the truss column, as shown in FIG.
- the mast material 2a lifted by the jib crane 7 in accordance with the rise of the construction floor is connected to the upper part of the mast material 2a while being supported by the horizontal stay 10 having one end fixed to the appropriate structure 1 side and maintaining the self-standing stability.
- the height can be gradually increased by adding.
- the climbing mechanism 3 includes a guide sleeve 3 a penetrating the outer periphery of the mast 2, an upper frame 3 b and an intermediate frame 3 c integrated above and below the guide sleeve 3 a and surrounding the mast 2.
- the roof frame 4 is fixed between the lower surface of the guide sleeve 3a and the upper surface of the intermediate frame 3c. Also, a lower frame 3d surrounding the mast 2 is disposed below the intermediate frame 3c, and the two frames 3c and 3d are connected by a plurality of lifting hydraulic jacks 3e.
- each of the frames 3b, 3c and 3d there are a plurality of guide rollers 11 which roll in contact with the outer part of the mast 2 as shown in the cross section in FIGS. 3 (a) to (). Is arranged, and guides each frame 3 b to 3 c so as to be able to move up and down.
- a pair of pins 12 for supporting a vertical load are respectively inserted into the middle frame 3c and the lower frame 3d so as to be able to be inserted into and removed from the mast 2 as shown in FIGS.
- the mechanism 3 is supported and fixed around the mast 2.
- the existing mast 2 is fixed as it is in order to add the mast 2 upward sequentially, so that the support of the mast 2 is kept horizontally and the structure 1 is taken to the structure 1 side. be able to.
- the climbing mechanism 3 is lifted while supporting the weight of only the roof frame 4 during the ascent work, the driving force for raising the roof frame 4 can be kept small and constant.
- the mast 2 can secure self-standing stability by the horizontal stay 10 and can reduce or eliminate the need for braces connecting the masts 2, which also has the effect of reducing weight.
- the four climbing mechanisms 3 are simultaneously moved upward during a process where there is no work for transporting construction materials.
- the four corners of the roof frame 4 are positioned at the height of the mast 2 and are supported horizontally. After that, the transport of construction materials can be resumed.
- the roof frame 4 is removed, leaving the frame portion to be bridged between the overhead crane 5 and the climbing mechanism 3, and these are removed by a jib crane left on the roof of Structure 1.
- the climbing mechanism 3 is reversely climbed to lower the frame portion bridged between them, and at this time, the mast 2 is moved from above by the jib crane. Distribute in order.
- the jib crane is dismantled and removed with a relatively small crane, and the small crane is lowered by the elevator of the structure 1, etc. Remove the entire device.
- the structure 1 has a rectangular cross-section and the mast 2 is arranged at four places outside the structure 1 has been described, but only one to three masts are required depending on the floor area of the structure. It can be arranged and its upper part can be covered with a roof frame. Of course, if the floor area is large, more may be provided.
- a roof frame 4 is supported below the climbing mechanism 3 with four corners suspended.
- the climbing mechanism 3 includes a guide sleeve 3a penetrating the outer periphery of the mast 2, an upper frame 3b integrated with a lower portion of the guide sleeve 3a, and a lower part of the upper frame 3b.
- a lower frame 3c is provided, and a plurality of lifting hydraulic jacks 3e connected between the upper and lower frames 3b, 3c.
- the roof frame 4 is provided with the mast 2 penetrating the lower surface of the lower frame 3c. It is supported in a suspended state.
- a support frame 3 f is fixed to the outer periphery of the mast 2 on the lower surface side of the roof frame 4.
- the jib crane 7 is of a fixed type.
- the lines A--A, B--B, and C--C are shown, which are shown in FIGS. 3 (a), (b), and (c) of the aforementioned embodiment. Each corresponds.
- the roof frame 4 can be assembled close to or in contact with the ground, so that the assembling workability is good, a high-precision frame can be obtained, and the height of the roof frame 4 at the time of assembly can be reduced. Work can be done safely o
- the overhead crane 5 used in the above two embodiments is in the form shown in FIG.
- the overhead crane 5 is located at the center of the lower surface of the roof frame 4 corresponding to the Main rail 20 and sub-rails 22, 22a located on both sides of the main rail 20 and arranged in parallel with the main rail 20.
- the transfer girder 2.4 as a main girder is movable on the main rail 20. While being supported, the built-in girder 26, 26a as a sub-girder is movably supported on the sub-rail 22, 22a.
- the overhead crane 5 is provided with three first, second, and third hoists 9a, 9b, 9c, and the first hoist 9a is located on the transfer girder 24, and
- the second and third hoists 9b and 9c show the case where they are located on the built girder 26 and 26a on both sides.
- the transfer girder 24 is configured as a two-unit type which is juxtaposed in the direction in which the main rail 20 extends (in the figure, a two-unit type main gag is integrated).
- 1, 2nd girder 24a, 24b is provided.
- the first and second girders 24a, 24b are connected to each other via connecting portions 28, 28, and move on the main rail 20 as one body.
- At least one of the first and second girder 24a, 24b constituting the double girder is provided with one empty hoist among the small hoists 9a, 9b, 9c. And the material lifted by the heavy lifting machine 8 is always available.
- the transfer girder 24 is of a double type by the first and second girder 24a, 24b, the first and second gutters are provided. At least one of the wheels 24a and 24b can be empty, that is, the hoist has not been transferred. For this reason, the material lifted from the hoisting machine 8 is received by the hoist located on one of the first and second girder 24a, 24b and moved on the main rail 20, and the building gutter 26 , 26a, the hoist of the built-in girder 26, 26a is connected to the first and the second girder even if the hoist is located in the built-in girder 26, 26a.
- the suspended hoist of the first and second girder a, b can be transferred to the built-in girder 26, 26a.
- the first and second girders 24a, 24b are moved to the lifting machine 8 with an empty hoist, whereby Lifting machine 8 The material can be immediately taken into the empty hoist.
- the overhead crane 5 of this embodiment is provided with three first, second, and third hoists 9a, 9b, and 9c as hoists, and is located at the built-in girder 26, 26a.
- the material lifted by the hoist 8 is suspended in the first hoist 9a located on the first girder 24a of the transport gag.
- the transfer girder 24 is moved to the second girder 9b.
- 24 b is arranged in a straight line with one built-in girder 26, and the second hoist 9 b located on this built-in girder 26 is transferred to the second girder 24 b.
- the first girder 24 a where the first hoist 9 a in the suspended state is located is matched with the built-in girder 26, and the first hoist 9 a is connected to the built-in girder 26. Transfer.
- the first hoist 9a moves along the built-in girder 26 and the built-in girder 26 moves on the sub-rail 22 so that the first hoist 9a is moved from the main rail 20 as shown in FIG.
- the material can be moved down to any position in the middle left half area.
- the empty second hoist 9b is located on the transfer girder 24, and the material to be subsequently lifted by the lifting machine 8 can be immediately suspended in the second hoist 9b. .
- the first hoist 9a can of course be transferred to the other built-in girder 26a in the same manner.
- the first hoist 9a suspended from the load is located on the second girder 24b of the transfer girder 24, and the second or third hoist emptied from the built-in girder 26 or 26a.
- the first hoist 9a and the second or the second girder can be connected between the transfer girder 24 and the built girder 26 or 26a. Exchange with the third hoists 9b and 9c can be performed smoothly.
- the hoist 9 can be positioned in the direction. Therefore, when the material is lifted from the hoisting machine 8, the work at the hoist 9 located at the built-in girder 22 You can pick up the material at the hoist 9 located on one side of the double wing yard 24 without waiting for it to finish.
- the hoist 9 in the suspended state is transferred from the transport girder 24 to the built-in girder 26, 26a with the material received, first, the built-in girder 26, 26a By transferring the empty hoist 9 to the other side of the transfer girder 24, it is possible to smoothly switch between the hoist in the suspended state and the empty hoist. Therefore, the material lifted by the lifting machine 8 can be quickly received, and an excellent effect of significantly improving material transfer efficiency can be obtained.
- the hoist is located at one of the first and second girders 24a and 24b constituting the transfer girder, whereby only one drive source is required, and two Since the control of the transport girder is significantly easier than in the case of individually controlling the transport girder, the driving means can be simplified, which can contribute to the simplification of the entire apparatus.
- the first and second girders 24a and 24b can be brought back to the hoisting machine 8 with empty hoists 9 positioned on both, and materials can be hung on each hoist 9. .
- the transfer girder is configured by connecting the first and second girders 24a and 24b, and the case where each of them is moved integrally is disclosed.
- the first and second girders 24a and 24b are separated and can be moved independently by installing a travel control device in each girder, so that the girders 26 and 26a are located.
- the degree of freedom of transportation can be improved according to the state of construction of the suspended load of the hoist 9 to be lifted by the hoist 9.
- the lifting machine 8 is disclosed as being provided only on the side (the lower side in FIG. 6) of the transfer girder, if the floor area of the structure 1 is large, the lifting machine 8 is lifted and transferred. Due to the large amount of materials to be provided, it is preferable to install the lifting machine 8 on both sides of the transport rail (upper side in the figure). In this case, the materials are lifted from two lifting machines to one transport girder, but the transport girder is provided with two girders, and as a result, the materials can be transported efficiently. As a whole, material transport efficiency can be significantly improved, which can contribute to further shortening of the period. In this case, it is possible to use two transport rails and a total of four built-in rails. If necessary, there can be three or more transfer rails, and the number of built-in rails can be increased accordingly.One transfer is not necessarily required on both sides of each transfer rail. A single built-in rail can be installed for each rail.
- the main rail A fixed girder is provided between the poles perpendicular to the 20 and the sub rails 22, 22a, and the transfer girder 24 and the building girder 26, 26a are provided through the fixed girder. Can be transferred in a straight line to enable the transfer of the hoist.
- the hoist 9 of the transfer girder 24 and the built-in girder 26 and 26a are provided.
- any part of the structure 1 can be reached.
- the material can be lifted and transported.
- the case where the construction materials are transported is exemplified.
- the present invention is not limited to the above-described embodiment. It can also be applied to lifting and transporting parts, finished products, and other items.
- the present invention is applied in a garbage cleaning plant, the above-mentioned fixed girder is naturally disposed at a position avoiding a pillar provided at an appropriate place in a large garbage collection hole. Yes (in other words, pillars will be placed between fixed girder).
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Transportation (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
Claims
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP95942313A EP0771916A4 (en) | 1995-05-15 | 1995-12-28 | PROVISIONAL FRAMEWORK STRUCTURE FOR BUILDING A BUILDING |
| US08/765,967 US5881504A (en) | 1995-05-15 | 1995-12-28 | Temporary frame system for construction |
Applications Claiming Priority (6)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7116125A JP3070438B2 (ja) | 1995-05-15 | 1995-05-15 | 建設用仮設架構装置 |
| JP7/116125 | 1995-05-15 | ||
| JP7/116124 | 1995-05-15 | ||
| JP7116124A JP3027924B2 (ja) | 1995-05-15 | 1995-05-15 | 建設用仮設架構装置 |
| JP7/232823 | 1995-09-11 | ||
| JP23282395 | 1995-09-11 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO1996036780A1 true WO1996036780A1 (fr) | 1996-11-21 |
Family
ID=27313090
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP1995/002761 Ceased WO1996036780A1 (fr) | 1995-05-15 | 1995-12-28 | Ossature provisoire utilisee dans la construction d'un batiment |
Country Status (3)
| Country | Link |
|---|---|
| US (1) | US5881504A (ja) |
| EP (1) | EP0771916A4 (ja) |
| WO (1) | WO1996036780A1 (ja) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1997039974A1 (de) * | 1996-04-23 | 1997-10-30 | Mannesmann Aktiengesellschaft | Laufkran |
| AU722381B2 (en) * | 1996-04-23 | 2000-08-03 | Mannesmann Aktiengesellschaft | Travelling crane |
| WO2008000054A1 (en) * | 2006-06-30 | 2008-01-03 | Cerqueira Leite Weber Jr | Autoliftable bridge crane system for building and tower construction |
| CN102616651A (zh) * | 2012-03-27 | 2012-08-01 | 武桥重工集团股份有限公司 | 一种用于爬坡架梁起重机的牵引走行机构 |
| CN114922445A (zh) * | 2022-06-29 | 2022-08-19 | 北京华泰源建筑装饰工程有限公司 | 一种施工中使用的防护型装板 |
Families Citing this family (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| NO313119B1 (no) * | 2000-10-18 | 2002-08-12 | Dag Vilnes | Rammekonstruksjon for plane konstruksjoner |
| US7290672B2 (en) * | 2001-03-21 | 2007-11-06 | Federated Equipment Co. Llc | Tower crane device |
| RU2376234C2 (ru) * | 2005-07-25 | 2009-12-20 | Павел Владимирович Корчагин | Подъемная система для обслуживания высотных сооружений |
| ES2308934B1 (es) * | 2007-05-29 | 2009-09-25 | Navarra Intelligent Concrete System, S.L | Sistema automatico de construccion de edificios. |
| US8544237B2 (en) * | 2009-01-07 | 2013-10-01 | Aerojet Rocketdyne Of De, Inc. | Lifting system for solar power tower components |
| GB2481595A (en) * | 2010-06-29 | 2012-01-04 | Shepherd Engineering Services Ltd | System and method for positioning a first structure relative to a second structure. |
| IT1401371B1 (it) * | 2010-08-05 | 2013-07-18 | Gru Dalbe Srl | Struttura di supporto autosollevante per edilizia. |
| KR101330469B1 (ko) | 2012-01-30 | 2013-11-20 | 신용찬 | 교량 공사용 크레인 |
| AU2014287354A1 (en) | 2013-07-08 | 2016-02-18 | Bainter Construction Services, L.L.C. | Jack with two masts |
| CN106015729B (zh) * | 2016-06-08 | 2018-03-06 | 中国十七冶集团有限公司 | 一种厂房封闭下汽化烟道逆向就位的方法 |
| US11193287B2 (en) * | 2016-09-23 | 2021-12-07 | Sh Technologies Pte Ltd | Construction system and method |
| CN108590197A (zh) * | 2018-05-09 | 2018-09-28 | 湖南易兴建筑有限公司 | 一种装配式建筑人工智能转运安装系统及实施工艺 |
| CN111502293B (zh) * | 2020-05-19 | 2021-06-15 | 太原理工大学 | 一种装配式建筑单块外围构件吊装方法及系统 |
| CN111661768B (zh) * | 2020-05-19 | 2021-07-16 | 太原理工大学 | 一种装配式建筑多块外围构件吊装方法及系统 |
| CN111877761B (zh) * | 2020-06-19 | 2022-06-07 | 上海建工集团股份有限公司 | 一种可装配式预制混凝土柱自动化安装工装系统及方法 |
| CN117320995A (zh) * | 2021-10-25 | 2023-12-29 | 广州建筑湾区智造科技有限公司 | 一种全预制装配式多高层混凝土厂房的施工方法 |
| CN115043330B (zh) * | 2022-05-24 | 2023-05-30 | 中建三局第一建设工程有限责任公司 | 非核心筒区塔吊内爬框的支撑结构、内爬框架及塔吊 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH059981A (ja) * | 1991-01-28 | 1993-01-19 | Shimizu Corp | ビルの建設方法 |
| JPH0586651A (ja) * | 1991-09-30 | 1993-04-06 | Maeda Corp | 柱及び梁の構築方法及び装置 |
| JPH0673891A (ja) * | 1992-08-24 | 1994-03-15 | Mitsubishi Heavy Ind Ltd | 物品自動搬送システム |
| JPH0726477B2 (ja) * | 1991-06-11 | 1995-03-22 | 戸田建設株式会社 | 建築物の構築工法 |
Family Cites Families (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB377512A (en) * | 1931-10-22 | 1932-07-28 | Maximilian Weihoenig | Improvements in or relating to silos for storing raw foodstuffs |
| FR941587A (fr) * | 1944-06-12 | 1949-01-14 | Perfectionnements au montage d'édifices | |
| DE1228040B (de) * | 1961-09-19 | 1966-11-03 | Markus Schmidt Tychsen Derrick | Kran, dessen Saeule aus einer Mehrzahl von Mastelementen aufgebaut ist |
| US3748805A (en) * | 1971-10-18 | 1973-07-31 | Y Boros | Building structure and method of erecting same |
| DE2312509A1 (de) * | 1973-03-13 | 1974-10-10 | Kresic Marjan Dipl Ing | Verfahren zur errichtung eines mehrgeschoessigen bauwerkes aus stahlbeton, sowie allwetter- vorrichtung zur ausfuehrung des verfahrens |
| US3921362A (en) * | 1974-03-18 | 1975-11-25 | Pablo Cortina Ortega | Method of and means for multi-story building construction |
| US4197689A (en) * | 1978-01-13 | 1980-04-15 | Demuth Steel Products Company | Bulk storage vessels |
| DE2917972A1 (de) * | 1979-05-04 | 1980-11-13 | Gerd Drespa | Allwetter-baufortschritt-system |
| FR2639664B1 (fr) * | 1988-11-25 | 1991-01-11 | Duez Alain | Procede et dispositif pour la construction et/ou l'execution de travaux sur des parois de batiments |
| GB2250731B (en) * | 1990-08-09 | 1994-06-01 | Mitsubishi Heavy Ind Ltd | Apparatus and method for constructing a building |
-
1995
- 1995-12-28 WO PCT/JP1995/002761 patent/WO1996036780A1/ja not_active Ceased
- 1995-12-28 EP EP95942313A patent/EP0771916A4/en not_active Withdrawn
- 1995-12-28 US US08/765,967 patent/US5881504A/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH059981A (ja) * | 1991-01-28 | 1993-01-19 | Shimizu Corp | ビルの建設方法 |
| JPH0726477B2 (ja) * | 1991-06-11 | 1995-03-22 | 戸田建設株式会社 | 建築物の構築工法 |
| JPH0586651A (ja) * | 1991-09-30 | 1993-04-06 | Maeda Corp | 柱及び梁の構築方法及び装置 |
| JPH0673891A (ja) * | 1992-08-24 | 1994-03-15 | Mitsubishi Heavy Ind Ltd | 物品自動搬送システム |
Non-Patent Citations (1)
| Title |
|---|
| See also references of EP0771916A4 * |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1997039974A1 (de) * | 1996-04-23 | 1997-10-30 | Mannesmann Aktiengesellschaft | Laufkran |
| AU722381B2 (en) * | 1996-04-23 | 2000-08-03 | Mannesmann Aktiengesellschaft | Travelling crane |
| WO2008000054A1 (en) * | 2006-06-30 | 2008-01-03 | Cerqueira Leite Weber Jr | Autoliftable bridge crane system for building and tower construction |
| CN102616651A (zh) * | 2012-03-27 | 2012-08-01 | 武桥重工集团股份有限公司 | 一种用于爬坡架梁起重机的牵引走行机构 |
| CN114922445A (zh) * | 2022-06-29 | 2022-08-19 | 北京华泰源建筑装饰工程有限公司 | 一种施工中使用的防护型装板 |
Also Published As
| Publication number | Publication date |
|---|---|
| EP0771916A4 (en) | 1997-07-23 |
| US5881504A (en) | 1999-03-16 |
| EP0771916A1 (en) | 1997-05-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO1996036780A1 (fr) | Ossature provisoire utilisee dans la construction d'un batiment | |
| US4102463A (en) | Transporter for slab casting tables | |
| JP2980020B2 (ja) | 塔状構造物の押し上げ式セルフクライミング装置 | |
| JPH0483060A (ja) | 建築物構造 | |
| CN113233343A (zh) | 一种架设设备、架设方法及过高低不平面的方法 | |
| JP3027925B2 (ja) | 建設用仮設架構装置 | |
| CN215208144U (zh) | 一种架设设备 | |
| JP3027924B2 (ja) | 建設用仮設架構装置 | |
| JPH09137506A (ja) | 建物の建設方法 | |
| JP3070438B2 (ja) | 建設用仮設架構装置 | |
| JPH10245994A (ja) | 仮設養生体 | |
| JPH08312149A (ja) | 建設用仮設架構装置 | |
| JP3075162B2 (ja) | 吊上げ搬送装置及びその搬送方法 | |
| KR200200364Y1 (ko) | 고층 건축물 시공장치 | |
| JPH0745778B2 (ja) | リフト用蓮台の昇降方法と装置 | |
| JP2761518B2 (ja) | 建築物の施工方法 | |
| JP2750472B2 (ja) | 建築物の施工方法およびその装置 | |
| JPH08326323A (ja) | 高層建築物の建設装置 | |
| JPH028098B2 (ja) | ||
| JP3078207B2 (ja) | ホイスト乗移り式天井クレーンの運転方法 | |
| JP2778842B2 (ja) | ビルの建設方法 | |
| JP2717158B2 (ja) | 建築物の施工方法 | |
| JPH1162244A (ja) | 躯体構築用フレームおよびそれを用いた躯体構築方法 | |
| JP3103715B2 (ja) | 揚重搬送装置および揚重搬送方法 | |
| JPH05125843A (ja) | ユニツト階段 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AK | Designated states |
Kind code of ref document: A1 Designated state(s): SG US |
|
| AL | Designated countries for regional patents |
Kind code of ref document: A1 Designated state(s): AT BE CH DE DK ES FR GB GR IE IT LU MC NL PT SE |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 1995942313 Country of ref document: EP |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
| WWE | Wipo information: entry into national phase |
Ref document number: 08765967 Country of ref document: US |
|
| WWP | Wipo information: published in national office |
Ref document number: 1995942313 Country of ref document: EP |
|
| WWW | Wipo information: withdrawn in national office |
Ref document number: 1995942313 Country of ref document: EP |