RU2419701C1 - Method to lay reinforced concrete sleepers onto railway lines - Google Patents
Method to lay reinforced concrete sleepers onto railway lines Download PDFInfo
- Publication number
- RU2419701C1 RU2419701C1 RU2009147181/11A RU2009147181A RU2419701C1 RU 2419701 C1 RU2419701 C1 RU 2419701C1 RU 2009147181/11 A RU2009147181/11 A RU 2009147181/11A RU 2009147181 A RU2009147181 A RU 2009147181A RU 2419701 C1 RU2419701 C1 RU 2419701C1
- Authority
- RU
- Russia
- Prior art keywords
- reinforced concrete
- sleepers
- blocks
- sleeper
- railway
- Prior art date
Links
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 49
- 238000000034 method Methods 0.000 title claims description 4
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 8
- 239000010959 steel Substances 0.000 claims abstract description 8
- 238000003032 molecular docking Methods 0.000 claims description 15
- 241001669679 Eleotris Species 0.000 abstract description 8
- 230000008878 coupling Effects 0.000 abstract 6
- 238000010168 coupling process Methods 0.000 abstract 6
- 238000005859 coupling reaction Methods 0.000 abstract 6
- 238000010276 construction Methods 0.000 abstract 1
- 239000000126 substance Substances 0.000 abstract 1
- 238000004519 manufacturing process Methods 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 3
- 229910001018 Cast iron Inorganic materials 0.000 description 2
- 239000004568 cement Substances 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
Images
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Abstract
Description
ОБЛАСТЬ ТЕХНИКИFIELD OF TECHNOLOGY
Изобретение относится к железнодорожному (ж/д) транспорту к изготовлению и укладке на ж/д полотно продольных блоков железобетонных (ж/б) шпал, соединенных поперечными ж/б шпалами, с уложенными на продольные блоки шпал рельсами. Стыковка блоков ж/б шпал производится посредством поперечной «стыковочной» шпалы, оборудованной стыковочными узлами. Технический результат - экономия расходных материалов, уменьшение шума, снижение затрат на эксплуатацию ж/д пути.The invention relates to railway (railway) transport for the manufacture and laying on a railway sheet of longitudinal blocks of reinforced concrete (reinforced concrete) sleepers connected by transverse reinforced concrete sleepers, with rails laid on the longitudinal blocks of sleepers. Joining of blocks of reinforced concrete sleepers is carried out by means of a transverse “docking” sleepers equipped with docking nodes. The technical result is the saving of consumables, reducing noise, reducing the cost of operating the railway track.
Известен «Способ укладки шпал на ж/д пути», патент №2262565 C1 от 20.10.2005 г. (1), где шпалы длиной 2,75 м укладываются нитью каждого рельса с зазором 0,5 м и соединяются в поперечном направлении круглыми деревянными стержнями диаметром 30 мм.The well-known "Method of laying sleepers on the railway track", patent No. 2262565 C1 of 10.20.2005, (1), where sleepers 2.75 m long are laid with the thread of each rail with a gap of 0.5 m and are connected in the transverse direction by round wooden rods with a diameter of 30 mm.
Недостатком является:The disadvantage is:
- продольные шпалы не взаимосвязаны между собой, что снижает безопасность пути;- longitudinal sleepers are not interconnected, which reduces the safety of the path;
- связка продольных шпал не имеет достаточной прочности.- a bunch of longitudinal sleepers does not have sufficient strength.
Известна ж/б шпала, патент №2155836 C1 от 10.09.2000 г. (2), включающая в себя арматуру, устройство для увеличения ее сопротивления переменной нагрузке и перемещениям поперек и вдоль пути. К недостатку можно отнести малую эффективность устройства к перемещениям.Known reinforced concrete sleepers патент C1 of September 10, 2000 (2), which includes reinforcement, a device to increase its resistance to variable load and displacements across and along the path. The disadvantage is the low efficiency of the device to movements.
РАСКРЫТИЕ ИЗОБРЕТЕНИЯSUMMARY OF THE INVENTION
Ж/Б блоки шпал изготавливаются длиной одного рельса /25 м/, ФИГ.2, либо длиной одной шпалы /2,75 м/, ФИГ.1, соединяемые ж/б поперечными шпалами 2, ФИГ.1, 2, отстоящими друг от друга на расстоянии 2,8 или 4 м в зависимости от сложности пути /подъем, спуск, повороты/ или соответственно посредине одной шпалы /1,35 м/, /крутые повороты, стрелки и др./ и служат для повышения надежности ж/д пути. Изготовление блоков шпал производится на ж/б заводе заливкой цемента подготовленной арматуры предварительно напряженной конструкции для повышения прочности к переменным нагрузкам (3).Reinforced concrete blocks of sleepers are made with the length of one rail / 25 m /, FIG. 2, or the length of one sleepers / 2.75 m /, FIG. 1, connected by reinforced
Для стыковки блоков ж/б шпал изготавливается «стыковочная» ж/б шпала 1, ФИГ.1, 2, в которую вмонтированы стыковочные сквозные узлы - стальная труба (штырь) 9, ФИГ.1, 2, 3, диаметром 30 мм, толщиной 3-4 мм, длиной 40-50 см, входящая в гнездо 8 блока ж/б шпал, ФИГ.1, 2, диаметром 30+/3-5/ мм, толщиной 3-4 мм, длиной 40-50 см и фиксируется горизонтальным болтом 12, ФИГ.1, 2 (4 шт.) при окончании глухой стыковки укладываемых блоков ж/б шпал. При этом предусматривается температурный зазор и возможность поворота блока по оси ж/д линии на угол 15-20°. При предварительном монтаже блоков ж/б шпал «стыковочная» ж/б шпала наглухо присоединяется к готовому для монтажа блоку ж/б шпал и затем уже на полотне стыкуется с последующим блоком ж/б шпал, глухо. После стыковки производится сварка рельсов либо стыковка посредством болтов. Для повышения сопротивления к продольным и поперечным перемещениям под каждую поперечную ж/б шпалу, в том числе «стыковочную», устанавливаются и скрепляются со шпалой /не показано/ прямые или бочкообразные чугунные цилиндры 11, ФИГ.1, 2, 3, диаметром до 1 м, высотой до 0,3 м, с толщиной стенки 3-4 мм, которые заполняются балластом /щебнем/ и служат для нивелировки ж/д полотна, повышают надежность пути и уменьшают профилактические работы.For joining the blocks of reinforced concrete sleepers, a “connecting” reinforced
На ФИГ.1 изображен блок ж/б шпал длиной одной шпалы /2,75 м/. На ФИГ.2 изображен ж/б блок шпал длиной в один рельс /25 м/. На ФИГ.3 изображен вид А. Приняты следующие обозначения: 1 - поперечная «стыковочная» шпала, 2 - поперечные промежуточные шпалы, 3 - рельс, 4 - подставка под рельс, 5 - болт, 6 - узел крепления рельса, 7 - гайка, 8 - металлическое гнездо /труба/, 9 - труба /либо стальной штырь/ диаметром 30 мм, в «стыковочной» шпале, 10 - продольный блок ж/б шпал, 11 - чугунный цилиндр, 12 - болт, соединяющий трубу /штырь/ «стыковочной» шпалы с трубой в продольном блоке ж/б шпал.Figure 1 shows a block of reinforced concrete sleepers with a length of one sleepers / 2.75 m /. Figure 2 shows the reinforced concrete block of sleepers in the length of one rail / 25 m /. Figure 3 shows a view A. The following notation is adopted: 1 - transverse "docking" sleepers, 2 - transverse intermediate sleepers, 3 - rail, 4 - stand under the rail, 5 - bolt, 6 - rail mount, 7 - nut, 8 - a metal socket / pipe /, 9 - a pipe / or a steel pin / with a diameter of 30 mm, in the "docking" tie, 10 - a longitudinal block of reinforced concrete sleepers, 11 - a cast-iron cylinder, 12 - a bolt connecting the pipe / pin / " docking "sleepers with a pipe in the longitudinal block of reinforced concrete sleepers.
Эмпирическая оценка использования блоков ж/б шпал дает следующий технический результат:An empirical assessment of the use of blocks of reinforced concrete sleepers gives the following technical result:
- экономия расходных материалов от 40 до 50%;- saving of consumables from 40 to 50%;
- снижение шума более 30%;- noise reduction of more than 30%;
- повышение скорости ж/д транспорта более 30%;- increase the speed of railway transport more than 30%;
- снижение трудозатрат при эксплуатации ж/д пути до 40%;- reduction of labor costs during the operation of the railway track up to 40%;
- снижение вероятности схода с рельсов вагонов при теракте.- reduction in the probability of derailment of wagons during a terrorist attack.
Предлагаемый способ изготовления и укладки блоков в ж/б шпал легко применим для укладки трамвайных рельсов и ж/д рельсов в метро с добавлением третьего рельса съема напряжения /не показано/, которые крепятся болтами к «стыковочной» и промежуточным ж/б шпалам.The proposed method for the manufacture and stacking of blocks in reinforced concrete sleepers is easily applicable for laying tram rails and railway rails in the subway with the addition of a third voltage removal rail (not shown), which are bolted to the “docking” and intermediate reinforced concrete sleepers.
РАБОТА ПО ИЗГОТОВЛЕНИЮ И УКЛАДКЕ Ж/Б ШПАЛ НА Ж/Д ПУТИWORK ON MANUFACTURE AND LAYING R / W TEMPLES ON THE RAILWAY
На ж/б заводе изготовление ж/б блоков шпал в длину одной шпалы и в длину одного рельса производится заливкой бетона в предварительно напряженную конструкцию арматуры блоков шпал. Отдельно таким же способом изготавливается «стыковочная» шпала. «Стыковочная» ж/б шпала стыковочными узлами одномоментно, глухо, присоединяется с помощью горизонтальных болтов к одной стороне ж/б блока шпал, пристыковываются два рельса и укладываются на подготовленное ж/д полотно, пристыковываются к ранее уложенному блоку ж/б шпал. Далее рельсы либо свариваются, либо стыкуются с помощью болтов, соблюдая повороты колеи ж/д пути. Для прокладки ж/д пути с крутыми поворотами для стрелок и стыков рельс используются ж/б блоки длиной одной шпалы /не показано/. После укладки ж/б блоков шпал производится подсыпка, утрамбовка и нивелировка ж/д пути.At the reinforced concrete plant, the production of reinforced concrete blocks of sleepers in the length of one sleepers and in the length of one rail is made by pouring concrete into the prestressed structure of the reinforcement of the blocks of sleepers. Separately, in the same way a “docking” railroad tie is made. A “docking” reinforced concrete railroad tie by connecting nodes simultaneously, deafly, joins with the help of horizontal bolts to one side of the reinforced concrete railroad ties block, joins two rails and stacks on the prepared railroad cloth, joins to the previously laid-out railroad rail ties block. Further, the rails are either welded or joined with bolts, observing the turns of the railway track. To lay railway tracks with sharp turns for arrows and rail joints, reinforced concrete blocks with the length of one railway sleepers are used (not shown). After laying the reinforced concrete blocks of the sleepers, the railway is filled, rammed and leveled.
ИСТОЧНИКИ ИНФОРМАЦИИINFORMATION SOURCES
1. ПАТЕНТ №2262565 C1 от 20.10.2005 г.1. PATENT No. 2262565 C1 of 10.20.2005.
2. ПАТЕНТ №2155836 C1 от 10.09.2000 г.2. PATENT No. 2155836 C1 of 09/10/2000
3. БЭС, №20, ИЗД. «СОВ. ЭНЦИКЛОПЕДИЯ», 1975 г., г.Москва, СТР.501.3. BES, No. 20, ED. "OWL. ENCYCLOPEDIA ", 1975, Moscow, P. 501.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| RU2009147181/11A RU2419701C1 (en) | 2009-12-21 | 2009-12-21 | Method to lay reinforced concrete sleepers onto railway lines |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| RU2009147181/11A RU2419701C1 (en) | 2009-12-21 | 2009-12-21 | Method to lay reinforced concrete sleepers onto railway lines |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| RU2419701C1 true RU2419701C1 (en) | 2011-05-27 |
Family
ID=44734899
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| RU2009147181/11A RU2419701C1 (en) | 2009-12-21 | 2009-12-21 | Method to lay reinforced concrete sleepers onto railway lines |
Country Status (1)
| Country | Link |
|---|---|
| RU (1) | RU2419701C1 (en) |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1446202A1 (en) * | 1987-01-15 | 1988-12-23 | Всесоюзный Научно-Исследовательский Институт Железнодорожного Транспорта | Railway track structure |
| US6581848B1 (en) * | 1998-09-16 | 2003-06-24 | Peter Plica | Sleeper frame for a rail system for rail-mounted vehicles, especially for a ballasted track |
| PT1274901E (en) * | 2000-04-17 | 2007-03-30 | Composite Damping Material Nv | Railway comprising successive sleepers |
| JP3987875B1 (en) * | 2006-11-27 | 2007-10-10 | 東海旅客鉄道株式会社 | Sleeper structure and sleeper structure manufacturing method |
-
2009
- 2009-12-21 RU RU2009147181/11A patent/RU2419701C1/en not_active IP Right Cessation
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1446202A1 (en) * | 1987-01-15 | 1988-12-23 | Всесоюзный Научно-Исследовательский Институт Железнодорожного Транспорта | Railway track structure |
| US6581848B1 (en) * | 1998-09-16 | 2003-06-24 | Peter Plica | Sleeper frame for a rail system for rail-mounted vehicles, especially for a ballasted track |
| PT1274901E (en) * | 2000-04-17 | 2007-03-30 | Composite Damping Material Nv | Railway comprising successive sleepers |
| JP3987875B1 (en) * | 2006-11-27 | 2007-10-10 | 東海旅客鉄道株式会社 | Sleeper structure and sleeper structure manufacturing method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206538637U (en) | A kind of track strengthening device for existing railway | |
| CN201843076U (en) | Groove-shaped steel bridge deck structure of high-speed railway steel tied arched bridge | |
| CN104631219B (en) | Construction method of replacing integral ballast bed with floating slab ballast bed in subway operating line tunnel | |
| CN204282185U (en) | A kind of armful rail magnetic levitation track traffic bridge | |
| CN109183530B (en) | Line temporary overhead device and method for ballastless track disease remediation | |
| CN203065950U (en) | Railway bridge composed of simply-supported T-shaped beams | |
| CN104480805A (en) | Framed sleeper unit | |
| CN105178164B (en) | Prefabrication and lifting fish belly Wavelike steel webplate prestressing with bond combined box beam and its construction method | |
| CN209538017U (en) | Paving structure at highway bridge deck expansion joint | |
| CN209798444U (en) | A truss sleeper ballastless track for super-slope cog railway | |
| CN105239475B (en) | Track strengthening structure under complicated existing railway line in culvert jack-in process | |
| RU2003127024A (en) | FLOORING FOR RAILWAY | |
| CN203546516U (en) | Longitudinal continuous limit ballastless track on steel truss girder bridge | |
| RU2419701C1 (en) | Method to lay reinforced concrete sleepers onto railway lines | |
| CN208009170U (en) | Plate-type ballastless track on a kind of steel truss girder bridge | |
| CN103911948B (en) | Be applied to horizontal purlin formula steel work and the construction method thereof of wide concrete rib plate-girder | |
| CN110219250A (en) | The continuous combined overhead beam of multilayer | |
| CN115354529A (en) | Assembled suspension track beam | |
| CN105696455A (en) | Box type web simply supported U-shaped girder of double-track railway | |
| CN210439155U (en) | Multi-layer continuous combined overhead beam | |
| CN110258190B (en) | Ballast blocking wall structure of corrugated steel web of common-speed and heavy-load railway and construction method of ballast blocking wall structure | |
| CN107974878A (en) | A kind of rail yard track switch reinforcement means and structure | |
| CN202194031U (en) | A ballastless track large unit track slab | |
| CN204959604U (en) | A board -like ballastless track bridge floor for rushing to repair girder steel | |
| CN204919326U (en) | Adopt ultra high performance concrete's simply supported girder bridge bridge floor to construct in succession |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| MM4A | The patent is invalid due to non-payment of fees |
Effective date: 20121222 |