RU2171377C2 - Method of opencast mining of steep elongated mineral deposits - Google Patents
Method of opencast mining of steep elongated mineral deposits Download PDFInfo
- Publication number
- RU2171377C2 RU2171377C2 RU99122575/03A RU99122575A RU2171377C2 RU 2171377 C2 RU2171377 C2 RU 2171377C2 RU 99122575/03 A RU99122575/03 A RU 99122575/03A RU 99122575 A RU99122575 A RU 99122575A RU 2171377 C2 RU2171377 C2 RU 2171377C2
- Authority
- RU
- Russia
- Prior art keywords
- dump
- quarry
- internal
- opencast
- berm
- Prior art date
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
Description
Изобретение относится к горной промышленности и может быть использовано при разработке крутопадающих вытянутых месторождений карьерами, имеющими предельное дно ступенчатой формы. The invention relates to the mining industry and can be used in the development of steeply falling elongated deposits with quarries having a limiting bottom in a stepped form.
Известен способ разработки крутопадающих вытянутых месторождений, включающий внешнее и внутреннее отвалообразование, выделение в центре или на фланге карьерного поля участка, отработку его до конечной глубины с удалением вскрышных пород во внешний отвал. Разработку оставшейся части карьерного поля ведут по всей его глубине с перемещением вскрышных пород во внутренний отвал [1]. A known method of developing steeply falling elongated deposits, including external and internal dumping, allocation in the center or on the flank of the quarry field site, mining it to a final depth with the removal of overburden in an external dump. The development of the remaining part of the quarry field is conducted along its entire depth with the movement of overburden rocks into the internal dump [1].
Недостатком этого способа является его применимость для отработки карьерных полей больших размеров как по простиранию, так и вкрест простирания; карьерное поле должно иметь постоянную предельную глубину. The disadvantage of this method is its applicability for mining career fields of large sizes both along strike and across strike; the quarry field should have a constant maximum depth.
Известен также способ разработки крутопадающих месторождений, включающий отработку карьерного поля блоками, формирование под углом к горизонту, меньшим угла естественного откоса вскрышных пород, дна карьера и размещение на нем внутреннего отвала указанных пород. Блоки отрабатывают вкрест простирания залежи [2]. There is also known a method of developing steeply dipping deposits, including mining the quarry field in blocks, forming at an angle to the horizon less than the angle of repose of the overburden, the bottom of the quarry and placing an internal dump of these rocks on it. Blocks work out across the strike of the reservoir [2].
Недостатком этого способа является ограниченная область применения, так как способ может быть применен при разработке карьерных полей больших размеров, позволяющих вести разработку как минимум двумя независимыми карьерами. Способ сложный в применении. The disadvantage of this method is the limited scope, since the method can be applied in the development of career fields of large sizes, allowing the development of at least two independent quarries. The method is difficult to use.
Наиболее близким к заявленному по технической сущности и достигаемому результату является способ разработки крутопадающих месторождений [3], включающий отработку карьерного поля этапами, возведение пионерной насыпи на предельном горизонте этапа, соединяющей уступы противоположных бортов карьера и разделяющей выработанное пространство на отвальную зону и зону вскрышных и добычных работ. После возведения пионерной насыпи размещение породы во внутреннем отвале осуществляют по замкнутому контуру, от периферии к центру. The closest to the claimed technical essence and the achieved result is a method of developing steeply dipping deposits [3], which includes mining the quarry field in stages, erecting a pioneer embankment at the limit of the stage connecting the ledges of the opposite sides of the quarry and dividing the worked out space into the dumping zone and overburden and mining zone works. After the construction of the pioneer embankment, the rock is placed in an internal dump in a closed loop, from the periphery to the center.
Недостатком этого способа является то, что сформированное пространство под внутренний отвал включает транспортные бермы по всему периметру уступов. Это значительно уменьшает объем внутреннего отвала. The disadvantage of this method is that the formed space under the internal dump includes transport berm around the perimeter of the ledges. This significantly reduces the volume of the inner blade.
В предлагаемом способе, в отличие от известного, включающего отработку карьерного поля этапами, подготовку горной массы к экскавации буровзрывным способом, транспортирование полезного ископаемого и породы автосамосвалами, размещение вскрышных пород во внешнем и внутреннем отвалах, отличающийся тем, что в части карьера размещения внутреннего отвала на глубине H,
где H0 - глубина карьера до нижнего основания внутреннего отвала, м; F - ширина дна карьера на границе разделения его на отвальную часть и часть ведения вскрышных и добычных работ, м; bt - ширина транспортной бермы, съезда, м; d - ширина бермы безопасности на погашенном борту карьера, м; β - угол откоса борта карьера с транспортными бермами, град; γ - угол откоса борта карьера с погашенными уступами на граничном контуре, град.; f - количество ярусов внутреннего отвала высотой h, равной высоте погашенного уступа на граничном контуре карьера, отсыпанных породами, доставленными по съезду, возведенному в отвальной части карьера с горизонта верхней транспортной бермы, сопряженно погашенному борту, продолжающему трассу, проходящую по верхней транспортной берме,
на погашаемом борту, борту размещения стационарной трассы, устраивают горизонтальную вытянутую площадку шириной, достаточной для тупикового разворота автосамосвала, привязывают ее к трассе, например, соединяющей фланговые выезды из карьера. И по достижении внутреннего отвала отметки горизонтальной вытянутой площадки на ней и далее по контуру карьера, сопряженно погашенному борту, в направлении, противоположном основному развитию рабочей зоны карьера, возводят спиральный съезд. Породу в нижнюю часть внутреннего отвала доставляют по транспортным бермам и возведенному с горизонта верхней транспортной бермы, сопряженно погашенному борту карьера, съезду. В верхнюю часть внутреннего отвала породу доставляют по горизонтальной вытянутой площадке и возведенному на ней и далее, сопряженно погашенному борту карьера спиральному съезду.In the proposed method, in contrast to the known one, including mining the quarry field in stages, preparing the rock mass for excavation using a blasting method, transporting minerals and rocks with dump trucks, placing overburden rocks in the outer and inner dumps, characterized in that, in terms of the quarry, the dumping is depth H
where H 0 - the depth of the quarry to the lower base of the internal dump, m; F - the width of the quarry bottom at the border of its separation into the dump part and part of the overburden and mining operations, m; b t - width of the transport berm, exit, m; d is the width of the safety berm on the quenched quarry side, m; β - angle of slope of the side of the quarry with transport berm, degrees; γ - angle of slope of the pit side with offset steps on the boundary contour, deg .; f is the number of tiers of the internal dump with a height h equal to the height of the quenched ledge on the boundary contour of the quarry, sprinkled with rocks delivered along the ramp erected in the dump part of the quarry from the horizon of the upper transport berm, conjugated to the canceled side, continuing the route passing through the upper transport berm,
on the redeemable board, the board of the fixed route placement, arrange a horizontal elongated platform with a width sufficient for a dead end of the dump truck, tie it to the track, for example, connecting flank exits from the quarry. And upon reaching the internal dump of the horizontal elongated site mark on it and further along the contour of the quarry, the conjugate board is canceled, in the direction opposite to the main development of the working zone of the quarry, a spiral exit is erected. The rock is delivered to the lower part of the internal dump via transport berms and a ramp erected from the horizon of the upper transport berm, conjugated to the side of the quarry. The rock is delivered to the upper part of the internal dump via a horizontal elongated platform and a spiral ramp erected on it and further, conjugated to the side of the quarry.
На фиг. 1 изображен план разрабатываемого карьерного поля; на фиг. 2 - продольный разрез разрабатываемого карьерного поля; на фиг. 3 - фрагмент плана карьера с внутренним отвалом, нижняя часть отвала; на фиг. 4 - фрагмент плана карьера с внутренним отвалом, заполненный отвал. Где 1 - разграничительная площадка; 2 - контуры разграничительной площадки; 3 - контур внутреннего отвала; 4 - часть карьера для размещения внутреннего отвала; 5 - горизонтальная вытянутая площадка; 6 - временный целик под транспортную берму; 7 - внутренний отвал; 8, 9 - съезды, возведенные из вскрышных пород в отвальной части карьера; 10 - берма безопасности; 11 - стационарный съезд; 12 - временный съезд; 13 - текущее дно карьера; 14 - контур залежи полезного ископаемого; 15 - граничный контур карьера. In FIG. 1 shows a plan of a quarry being developed; in FIG. 2 - a longitudinal section of the developed career field; in FIG. 3 - a fragment of the plan of the quarry with an internal dump, the lower part of the dump; in FIG. 4 - a fragment of a quarry plan with an internal dump, a filled dump. Where 1 is the demarcation site; 2 - contours of the demarcation site; 3 - contour of the internal dump; 4 - part of the quarry for placement of the internal dump; 5 - horizontal elongated platform; 6 - temporary pillar under the transport berm; 7 - internal dump; 8, 9 - congresses erected from overburden in the dump part of the quarry; 10 - security berm; 11 - stationary exit; 12 - temporary congress; 13 - the current bottom of the quarry; 14 - contour of a mineral deposit; 15 - boundary contour of the quarry.
Способ заключается в следующем. Карьерное поле отрабатывают двумя этапами. По глубине границу первого этапа устанавливают на горизонте, совпадающем с одной из ступеней предельного контура карьера, по условию размещения автомобильного съезда до конечной глубины второго этапа и минимальной энергоемкости отработки запасов полезного ископаемого в граничном контуре карьера. На означенной ступени, от верхней бровки постановки уступа в предельное положение, выделяют разграничительную площадку 1, разделяющую карьер на часть для размещения внутреннего отвала и часть для ведения вскрышных и добычных работ. От контура 2 площадки 1 устанавливают контур 3, который разграничивает по бортам выделенную часть карьерного пространства 4 под отвал и остальную. The method is as follows. The career field is practiced in two stages. In depth, the boundary of the first stage is set on the horizon, which coincides with one of the steps of the limiting contour of the quarry, according to the condition of placing the car exit to the final depth of the second stage and the minimum energy consumption of mining of mineral resources in the boundary contour of the quarry. At the indicated step, from the upper edge of setting the ledge to the limiting position, a
Отработку первого этапа осуществляют с размещением вскрышных пород во внешнем отвале. При этом в части карьера 4 на глубине H,
где H0 - глубина карьера до нижнего основания внутреннего отвала, м; F - ширина дна карьера на границе разделения его на отвальную часть и часть ведения вскрышных и добычных работ, м; bt - ширина транспортной бермы, съезда, м; d - ширина бермы безопасности на погашенном борту карьера, м; β - угол откоса борта карьера с транспортными бермами, град; γ - угол откоса борта карьера с погашенными уступами на граничном контуре, град.; f - количество ярусов внутреннего отвала высотой h, равной высоте погашенного уступа на граничном контуре карьера, отсыпанных породами, доставленными по съезду, возведенному в отвальной части карьера с горизонта верхней транспортной бермы, сопряженно погашенному борту, продолжающему трассу, проходящую по верхней транспортной берме,
на погашаемом борту, борту размещения стационарной трассы, устраивают горизонтальную вытянутую площадку 5 шириной, достаточной для тупикового разворота автосамосвала; привязывают ее к трассе, например, соединяющей фланговые выезды из карьера. С понижением горных работ на противоположном борту, от контура 3 в сторону рабочей зоны карьера, формируют временные целики 6 под транспортные бермы 6 высотой, равной высоте погашенного уступа на граничном контуре карьера. Возможное количество целиков 6, по условию производительной работы технологического оборудования и транспортного доступа в рабочую зону карьера, устанавливают по зависимости
По завершении отработки первого этапа карьерного поля переходят к складированию вскрышных пород в отвальной части карьера 4. В нижнюю часть отвала 7 породу доставляют по транспортным бермам 6 и съезду 8, который возводят сопряженно борту карьера и наращивают по мере отсыпки отвала 7. В верхнюю часть овала 7 породу доставляют по горизонтальной вытянутой площадке 5 и спиральному съезду 9. Съезд 9 возводят из вскрышных пород на площадке 5 и далее, по мере отсыпки верхней части отвала 7, по спирали сопряженно погашенному борту карьера до выхода его к торцовому откосу отвала 7 со стороны рабочей зоны карьера. Далее съезд 9 развивают по контуру отвала, не сопряженному с контуром карьера.The development of the first stage is carried out with the placement of overburden in an external dump. Moreover, in the part of quarry 4 at a depth of H,
where H 0 - the depth of the quarry to the lower base of the internal dump, m; F - the width of the quarry bottom at the border of its separation into the dump part and part of the overburden and mining operations, m; b t - width of the transport berm, exit, m; d is the width of the safety berm on the quenched quarry side, m; β - angle of slope of the side of the quarry with transport berm, degrees; γ - angle of slope of the pit side with offset steps on the boundary contour, deg .; f is the number of tiers of the internal dump with a height h equal to the height of the quenched ledge on the boundary contour of the quarry, sprinkled with rocks delivered along the ramp erected in the dump part of the quarry from the horizon of the upper transport berm, conjugated to the canceled side, continuing the route passing through the upper transport berm,
on a redeemable board, a board for placing a fixed route, arrange a horizontal elongated platform with a width of 5 sufficient for a dead end of a dump truck; they tie it to the track, for example, connecting flank exits from the quarry. With a decrease in mining operations on the opposite side, from circuit 3 towards the working area of the quarry, temporary pillars 6 are formed under transport berms 6 with a height equal to the height of the offset bench on the boundary contour of the quarry. The possible number of pillars 6, according to the conditions of productive work of technological equipment and transport access to the working area of the quarry, is set according to
Upon completion of the mining of the first stage of the quarry field, they begin to store overburden in the dump part of quarry 4. The rock is delivered to the lower part of dump 7 via transport berms 6 and ramp 8, which are erected in conjunction with the quarry board and are expanded as dump 7 is dumped. To the upper part of the oval 7, the rock is delivered along a horizontal
Отвал отсыпают ярусами снизу вверх. Отсыпку частей отвала 7, ограниченных горизонтами нижнего основания отвала 7 и верхней транспортной бермы 6, окончания съезда 8 и горизонтальной вытянутой площадки 5 осуществляют ярусами высотой, равной высоте погашенного уступа на граничном контуре карьера. Части отвала 7, ограниченные горизонтами начала и окончания съездов 8 и 9 отсыпают ярусами высотой, установленной, исходя из минимальной энергоемкости размещения породы в теле отвала 7. The dump is poured in tiers from the bottom up. The dumping of parts of the blade 7, limited by the horizons of the lower base of the blade 7 and the upper transport berm 6, the end of the exit 8 and the horizontal
Список информационных источников
1. П. И. Томаков, B.C.Коваленко. Основные направления повышения эффективности использования земельных ресурсов при открытой разработке месторождений полезных ископаемых /Проблемы комплексного освоения месторождений твердых полезных ископаемых //Моск. горн. институт; Под ред. Л.А. Пучкова. - М.: Недра. - 1989. - с. 94.List of Information Sources
1. P.I. Tomakov, BCKovalenko. The main directions of increasing the efficiency of land use in the open development of mineral deposits / Problems of integrated development of solid mineral deposits // Mosk. horn institute; Ed. L.A. Puchkova. - M .: Subsoil. - 1989. - p. 94.
2. Авторское свидетельство N 1812321 СССР, кл. E 21 C 41/26. Способ открытой разработки крутопадающих и наклонных месторождений. 2. Copyright certificate N 1812321 of the USSR, cl. E 21 C 41/26. The method of open development steeply dipping and inclined deposits.
3. Патент N 2013550 РФ, МКИ E 21 C 41/26. Способ открытой разработки крутопадающих месторождений. 3. Patent N 2013550 RF, MKI E 21 C 41/26. The method of open development steeply declining deposits.
Claims (1)
где Но - глубина карьера до нижнего основания внутреннего отвала, м;
F - ширина дна карьера на границе разделения его на отвальную часть и часть ведения вскрышных и добычных работ, м;
bt - ширина транспортной бермы, съезда, м;
d - ширина бермы безопасности на погашенном борту карьера, м;
β - угол откоса борта карьера с транспортными бермами, град.;
γ - угол откоса борта карьера с погашенными уступами на граничном контуре, град.;
f - количество ярусов внутреннего отвала высотой h, равной высоте погашенного уступа на граничном контуре карьера, отсыпанных породами, доставленными по съезду, возведенному в отвальной части карьера с горизонта верхней транспортной бермы,
сопряженно погашенному борту, продолжающему трассу, проходящую по верхней транспортной берме, на погашаемом борту, борту размещения стационарной трассы устраивают горизонтальную вытянутую площадку шириной, достаточной для тупикового разворота автосамосвала, привязывают ее к трассе, например, соединяющей фланговые выезды из карьера, и по достижении внутреннего отвала отметки горизонтальной вытянутой площадки на ней и далее по контуру карьера, сопряженно погашенному борту в направлении, противоположном основному развитию рабочей зоны карьера, возводят спиральный съезд, породу в нижнюю часть внутреннего отвала доставляют по транспортным бермам и возведенному с горизонта верхней транспортной бермы, сопряженно погашенному борту карьера съезду, в верхнюю часть внутреннего отвала породу доставляют по горизонтальной вытянутой площадке и возведенному на ней и далее, сопряженно погашенному борту карьера спиральному съезду.A method for open-cast mining of steeply dipping elongated deposits, including mining a quarry field in stages, preparing the rock mass for excavation using a blasting method, transporting rock and minerals with dump trucks, placing overburden rocks in the external and internal dumps, characterized in that, in the part of the quarry, the internal dump is located at a depth of H ,
where N about - the depth of the quarry to the lower base of the internal dump, m;
F - the width of the quarry bottom at the border of its separation into the dump part and part of the overburden and mining operations, m;
b t - width of the transport berm, exit, m;
d is the width of the safety berm on the quenched quarry side, m;
β - angle of slope of the side of the quarry with transport berm, deg .;
γ - angle of slope of the pit side with offset steps on the boundary contour, deg .;
f is the number of tiers of the internal dump with a height h equal to the height of the quenched ledge on the boundary contour of the quarry, covered with rocks delivered along the ramp erected in the dump part of the quarry from the horizon of the upper transport berm,
a conjugate canceled board, continuing the route passing through the upper transport berth, on the canceled board, the fixed-route placement board, arrange a horizontal elongated platform wide enough for a dead end of the dump truck, tie it to the track, for example, connecting the flank exits from the quarry, and upon reaching the internal a dump of a mark of a horizontal elongated site on it and further along the contour of the quarry, conjugate to an offset board in the direction opposite to the main development of the working areas open pit, erect a spiral ramp, the rock is delivered to the lower part of the internal dump via transport berms and the ramp erected from the horizon of the upper transport berry, the ramp is conjugated to the upper part of the internal dump, the rock is delivered to the upper part of the internal dump, and erected on it and further conjugated board a quarry spiral ramp.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| RU99122575/03A RU2171377C2 (en) | 1999-10-27 | 1999-10-27 | Method of opencast mining of steep elongated mineral deposits |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| RU99122575/03A RU2171377C2 (en) | 1999-10-27 | 1999-10-27 | Method of opencast mining of steep elongated mineral deposits |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| RU2171377C2 true RU2171377C2 (en) | 2001-07-27 |
| RU99122575A RU99122575A (en) | 2001-08-10 |
Family
ID=20226276
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| RU99122575/03A RU2171377C2 (en) | 1999-10-27 | 1999-10-27 | Method of opencast mining of steep elongated mineral deposits |
Country Status (1)
| Country | Link |
|---|---|
| RU (1) | RU2171377C2 (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2224109C2 (en) * | 2002-04-17 | 2004-02-20 | Институт химии и химической технологии СО РАН | Process of opencast mining of steeply deeping stretched-out mineral deposits |
| RU2490462C2 (en) * | 2011-11-09 | 2013-08-20 | Федеральное Государственное Бюджетное Учреждение Науки Институт Химии И Химической Технологии Сибирского Отделения Российской Академии Наук (Иххт Со Ран) | Method of open mining of steep oblong deposits |
| RU2553672C2 (en) * | 2013-08-01 | 2015-06-20 | Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) | Method of opened development of long steep dipping fields with internal dumping |
| RU2637667C1 (en) * | 2016-10-31 | 2017-12-06 | Виктор Сергеевич Федотенко | Method for open pit mining of mineral deposits |
| CN117432413A (en) * | 2023-11-29 | 2024-01-23 | 中国矿业大学 | A right-angle steering method for open-pit mines based on end-gannel mining |
| CN118498995A (en) * | 2024-06-21 | 2024-08-16 | 中国矿业大学 | Double-sector complementary steering method for parallel mining areas of strip mine |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2013550C1 (en) * | 1989-07-28 | 1994-05-30 | Красноярский отдел Института горного дела СО РАН | Method for open-pit mining of steeply dipping mineral deposits |
| RU2065049C1 (en) * | 1992-09-07 | 1996-08-10 | Александр Владимирович Фролов | Method for open-pit exploitation of inclined and steeply dipping deposits |
| RU2097561C1 (en) * | 1995-06-29 | 1997-11-27 | Отдел проблем освоения недр СО РАН | Method for mining steeply-dipping elongated deposits |
-
1999
- 1999-10-27 RU RU99122575/03A patent/RU2171377C2/en not_active IP Right Cessation
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2013550C1 (en) * | 1989-07-28 | 1994-05-30 | Красноярский отдел Института горного дела СО РАН | Method for open-pit mining of steeply dipping mineral deposits |
| RU2065049C1 (en) * | 1992-09-07 | 1996-08-10 | Александр Владимирович Фролов | Method for open-pit exploitation of inclined and steeply dipping deposits |
| RU2097561C1 (en) * | 1995-06-29 | 1997-11-27 | Отдел проблем освоения недр СО РАН | Method for mining steeply-dipping elongated deposits |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2224109C2 (en) * | 2002-04-17 | 2004-02-20 | Институт химии и химической технологии СО РАН | Process of opencast mining of steeply deeping stretched-out mineral deposits |
| RU2490462C2 (en) * | 2011-11-09 | 2013-08-20 | Федеральное Государственное Бюджетное Учреждение Науки Институт Химии И Химической Технологии Сибирского Отделения Российской Академии Наук (Иххт Со Ран) | Method of open mining of steep oblong deposits |
| RU2553672C2 (en) * | 2013-08-01 | 2015-06-20 | Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) | Method of opened development of long steep dipping fields with internal dumping |
| RU2637667C1 (en) * | 2016-10-31 | 2017-12-06 | Виктор Сергеевич Федотенко | Method for open pit mining of mineral deposits |
| CN117432413A (en) * | 2023-11-29 | 2024-01-23 | 中国矿业大学 | A right-angle steering method for open-pit mines based on end-gannel mining |
| CN118498995A (en) * | 2024-06-21 | 2024-08-16 | 中国矿业大学 | Double-sector complementary steering method for parallel mining areas of strip mine |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| RU2127809C1 (en) | Method for opencast development of deposits | |
| RU2171377C2 (en) | Method of opencast mining of steep elongated mineral deposits | |
| RU2052630C1 (en) | Method for development of open pit | |
| RU2490462C2 (en) | Method of open mining of steep oblong deposits | |
| RU2064582C1 (en) | Method for openpit mining of minerals | |
| RU2167297C2 (en) | Method of opencast mining of steeply dipping stretched deposits | |
| RU2233982C1 (en) | Method for opening and processing deep horizons of kimberlite pipes | |
| RU2098627C1 (en) | Method of open-pit mining | |
| RU2353769C2 (en) | Pit border | |
| SU1710754A1 (en) | Method of opencast reconstruction | |
| RU2435032C1 (en) | Development method of mineral resources by spiral pit | |
| RU2118456C1 (en) | Quarry development method | |
| RU2224109C2 (en) | Process of opencast mining of steeply deeping stretched-out mineral deposits | |
| RU2278261C1 (en) | Method of combined open-cut and underground steeply pitching deposit development | |
| RU2196230C2 (en) | Method of dump formation | |
| RU99122575A (en) | METHOD FOR OPEN DEVELOPMENT OF CLOSE FALLING EXTENDED DEPOSITS | |
| RU2376471C1 (en) | Method of steep trench performance | |
| RU2187648C1 (en) | Method of mining of steeply dipping deposits of working of deep horizons of opencast | |
| SU1008450A1 (en) | Method for open-pit working of gently sloping mineral deposits | |
| RU2685587C1 (en) | Method for open development of steeply-dipping deposits with application of combined temporary non-working sides | |
| RU2139429C1 (en) | Method for opencast mining of flat and sloping deposits of minerals | |
| RU2039267C1 (en) | Method for formation of open pit transfer point | |
| RU2395443C1 (en) | Method of reloading mined rock in combined truck-railway transportation | |
| RU99116204A (en) | METHOD FOR OPEN DEVELOPMENT OF CLOSE FALLING EXTENDED DEPOSITS | |
| RU2088760C1 (en) | Method for recultivation of slopes in opencast mining of mineral deposits |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| MM4A | The patent is invalid due to non-payment of fees |
Effective date: 20031028 |