Method of discharging water in the process of draining rock massif Download PDFInfo
- Publication number
- RU2037012C1 RU2037012C1 SU5037906A RU2037012C1 RU 2037012 C1 RU2037012 C1 RU 2037012C1 SU 5037906 A SU5037906 A SU 5037906A RU 2037012 C1 RU2037012 C1 RU 2037012C1
- Authority
- RU
- Russia
- Prior art keywords
- water
- area
- drainage
- drained
- injection wells
- Prior art date
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 40
- 238000000034 method Methods 0.000 title claims abstract description 17
- 239000011435 rock Substances 0.000 title claims abstract description 10
- 238000007599 discharging Methods 0.000 title abstract 2
- 238000010276 construction Methods 0.000 claims abstract description 7
- 238000005553 drilling Methods 0.000 claims abstract description 7
- 238000002347 injection Methods 0.000 claims description 18
- 239000007924 injection Substances 0.000 claims description 18
- 230000006837 decompression Effects 0.000 claims description 6
- 239000008398 formation water Substances 0.000 claims description 4
- 238000001035 drying Methods 0.000 claims 1
- 238000005086 pumping Methods 0.000 abstract description 7
- 238000005065 mining Methods 0.000 abstract description 6
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- 230000000694 effects Effects 0.000 abstract 1
- 239000000126 substance Substances 0.000 abstract 1
- 239000003643 water by type Substances 0.000 abstract 1
- 230000015572 biosynthetic process Effects 0.000 description 3
- 230000007613 environmental effect Effects 0.000 description 3
- 238000010521 absorption reaction Methods 0.000 description 2
- 239000002253 acid Substances 0.000 description 1
- 150000007513 acids Chemical class 0.000 description 1
- 239000000654 additive Substances 0.000 description 1
- 239000007864 aqueous solution Substances 0.000 description 1
- 238000003491 array Methods 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 238000011109 contamination Methods 0.000 description 1
- 238000000280 densification Methods 0.000 description 1
- 239000003657 drainage water Substances 0.000 description 1
- 238000001914 filtration Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- QAOWNCQODCNURD-UHFFFAOYSA-N sulfuric acid group Chemical class S(O)(O)(=O)=O QAOWNCQODCNURD-UHFFFAOYSA-N 0.000 description 1
- 239000002351 wastewater Substances 0.000 description 1
- 230000003245 working effect Effects 0.000 description 1
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Description
Изобретение относится к строительству и горному делу и может быть использовано при добыче полезных ископаемых и строительстве подземных сооружений. The invention relates to the construction and mining and can be used in mining and construction of underground structures.
Известен способ осушения водоносных пластов, включающий бурение дренажных скважин на осушаемом участке и закачных скважин за пределами осушаемого участка, откачку воды через дренажные скважины, ее перекачку по водоводу к закачным скважинам и закачку через них в подземную формацию под давлением, превышающим величину пластового давления подземной формации [1]
Недостатком известного способа являются нежелательные экологические последствия из-за того, что вода перекачивается из одного пласта в другой, что особенно неприемлемо при агрессивности и загрязненности вод, а для их очистки требуются большие затраты.There is a known method of draining aquifers, including drilling drainage wells in a drained area and injection wells outside a draining area, pumping water through drainage wells, pumping it through a water conduit to injection wells, and pumping through them into an underground formation under pressure exceeding the formation pressure of the underground formation [1]
The disadvantage of this method is the undesirable environmental consequences due to the fact that water is pumped from one reservoir to another, which is especially unacceptable with aggressiveness and contamination of the water, and for their treatment require large costs.
Известен также способ отвода воды из подземных выработок, включающий сооружение дренажных устройств, бурение закачных скважин с заглублением их в водоприемный участок, отвод воды от дренажных устройств и подачу ее в закачные скважины по водоводу с разуплотнением пород водоприемного участка, введение в отводимую воду добавки, в качестве которой используют смесь водных растворов азотной и серной кислот [2]
Недостаток известного способа нежелательные экологические последствия, вызываемые введением кислот, и постепенная кольматация скважин.There is also a known method of water drainage from underground workings, including the construction of drainage devices, drilling injection wells with deepening them into the water intake section, water drainage from the drainage devices and supplying it to the injection wells through the water conduit with decompression of the rocks of the water receiving section, adding additives to the waste water, the quality of which is used a mixture of aqueous solutions of nitric and sulfuric acids [2]
The disadvantage of this method is the undesirable environmental consequences caused by the introduction of acids, and the gradual mudding of wells.
Задача, решаемая изобретением, создание способа отвода воды при осушении месторождения, позволяющего производить осушение без экологических нарушений, вызываемых перекачкой воды из одного пласта в другой, с минимальными затратами. The problem solved by the invention, the creation of a method of water drainage during the drainage of the field, allowing drainage without environmental damage caused by pumping water from one reservoir to another, at minimal cost.
Поставленная задача достигается тем, что в способе отвода воды при осушении горного массива, включающем сооружение дренажных устройств, бурение закачных скважин с заглублением их в водоприемный участок, отвод воды от дренажных устройств и подачу ее в закачные скважины по водоводу с разуплотнением пород водоприемного участка, водоприемный участок выделяют в водоносном горизонте ниже уровня осушаемого участка в направлении движения пластовых вод, а разуплотнение его пород производят перед подачей воды в закачные скважины по водоводу. The problem is achieved in that in the method of water drainage during the drainage of the rock mass, including the construction of drainage devices, drilling injection wells with deepening them into the water intake section, water drainage from the drainage devices and supplying it to the injection wells through the water conduit with decompression of rocks of the water intake section, water intake the site is isolated in an aquifer below the level of the drained area in the direction of formation water movement, and the decompression of its rocks is carried out before water is supplied to the injection wells through a water conduit.
Предлагаемый способ поясняется чертежом. The proposed method is illustrated in the drawing.
Способ осуществляется следующим образом. The method is as follows.
На месторождении, на основе изучения гидро- и инженерно-геологической обстановки, определяют направление движения подземных вод осушаемого горизонта, выделяются участки первоочередной отработки и осушения, а также участки пригодные для размещения закачных скважин. Затем приступают к сооружению дренажных устройств (скважин) 1 на осушаемом участке 2 и бурению закачных скважин 3, с заглублением их в водоприемный участок 4, расположенный ниже уровня осушаемого участка 2 в направлении движения пластовых вод. Зона поглощения закачных скважин 3 должна размещаться ниже уровня осушаемого горизонта 5. Практически зона поглощения должна размещаться ниже уровня нижнего рабочего горизонта, на котором будут идти основные горные работы. Если одновременно ведутся подготовительные горные работы на более глубоком горизонте 5, то они должны вестись в направлении, противоположном направлению движения пластовых вод во избежание дополнительного подтапливания. At the field, based on the study of the hydro- and engineering-geological situation, the direction of groundwater movement of the drained horizon is determined, the areas of primary development and drainage, as well as areas suitable for placement of injection wells, are identified. Then proceed to the construction of drainage devices (wells) 1 in the drained section 2 and the drilling of injection wells 3, with their deepening into the water intake section 4 located below the level of the drained section 2 in the direction of the formation water movement. The absorption zone of the injection wells 3 should be located below the level of the drained horizon 5. In practice, the absorption zone should be located below the level of the lower working horizon at which the main mining operations will go. If preparatory mining operations are conducted at a deeper horizon 5 at the same time, they should be carried out in the direction opposite to the direction of formation water movement in order to avoid additional flooding.
После бурения закачных скважин 3 приступают к разуплотнению пород водоприемного участка 4, в который они пробурены. Это осуществляется для увеличения проницаемости пород на значительном пространстве вокруг них, чтобы закачка воды практически не увеличивала уровень дренируемого горизонта в районе осушаемого участка 2. After drilling the injection wells 3, they begin to decompress the rocks of the water intake section 4 into which they are drilled. This is done to increase the permeability of rocks in a significant space around them, so that the injection of water practically did not increase the level of the drained horizon in the area of the drained area 2.
Разуплотнение массива может быть достигнуто различными методами, но наиболее приемлем геотехнологический метод, так как он позволяет оказывать воздействие на массив на большом расстоянии, не вызывая локальных уплотнений и сохраняя естественную структуру скелета массива. В частности методом скважинной гидродобычи могут быть разуплотнены массивы, имеющие достаточно жесткий скелет, заполненный рыхлыми разностями руд, имеющими низкие фильтрационные свойства. Densification of the array can be achieved by various methods, but the geotechnological method is most acceptable, since it allows you to influence the array at a great distance without causing local compaction and preserving the natural structure of the skeleton of the array. In particular, arrays having a sufficiently rigid skeleton filled with loose ore varieties having low filtration properties can be decompressed by the method of downhole hydraulic production.
После разуплотнения массива через закачные скважины 3 производят опробование их характеристик, например, используя наиболее отдаленную, как дренажную, и затем соединяют закачные 3 и дренажные 1 скважины водоводом 6. Подача воды в скважины может производиться под давлением или свободным наливом в зависимости от того горизонта, где находится приемный оголовок закачной скважины 3. After decompression of the massif through injection wells 3, their characteristics are tested, for example, using the most distant ones, such as drainage, and then the injection 3 and drainage 1 wells are connected with a water conduit 6. Water can be supplied to the wells under pressure or in bulk, depending on the horizon, where is the receiving head of the injection well 3.
При реализации предлагаемой схемы осушения может быть, максимально обеспечено экологическое равновесие, так как дренажные воды будут находиться в том же осушаемом горизонте, что особенно важно при разном качестве вод с разных горизонтов. When implementing the proposed drainage scheme, ecological balance can be maximally ensured, since the drainage water will be in the same drained horizon, which is especially important with different quality of water from different horizons.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU5037906 RU2037012C1 (en) | 1992-04-16 | 1992-04-16 | Method of discharging water in the process of draining rock massif |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU5037906 RU2037012C1 (en) | 1992-04-16 | 1992-04-16 | Method of discharging water in the process of draining rock massif |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| RU2037012C1 true RU2037012C1 (en) | 1995-06-09 |
Family
ID=21602154
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SU5037906 RU2037012C1 (en) | 1992-04-16 | 1992-04-16 | Method of discharging water in the process of draining rock massif |
Country Status (1)
| Country | Link |
|---|---|
| RU (1) | RU2037012C1 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2347073C1 (en) * | 2007-08-16 | 2009-02-20 | Государственное образовательное учреждение высшего профессионального образования "Белгородский государственный университет" | Method of excavating deep-seated deposits of mineral deposits |
| RU2382144C1 (en) * | 2008-05-19 | 2010-02-20 | Общество с ограниченной ответственностью Научно-технический и экспертный центр новых экотехнологий в гидрогеологии и гидротехнике "НОВОТЭК" | Method of draining of tubelike mineral deposit |
| RU2405891C2 (en) * | 2006-03-14 | 2010-12-10 | РОДРИГЕС Хорхе ЛОПЕС | Pump to drain wells by alternating aspitation and repulsion cycles that operates on pneumatic principle |
-
1992
- 1992-04-16 RU SU5037906 patent/RU2037012C1/en active
Non-Patent Citations (2)
| Title |
|---|
| 1. Авторское свидетельство СССР N 727759, E02D 19/06, 1978. * |
| 2. Авторское свидетельство СССР N 1449639, кл, E 02D 19/10, 1986. * |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2405891C2 (en) * | 2006-03-14 | 2010-12-10 | РОДРИГЕС Хорхе ЛОПЕС | Pump to drain wells by alternating aspitation and repulsion cycles that operates on pneumatic principle |
| RU2347073C1 (en) * | 2007-08-16 | 2009-02-20 | Государственное образовательное учреждение высшего профессионального образования "Белгородский государственный университет" | Method of excavating deep-seated deposits of mineral deposits |
| RU2382144C1 (en) * | 2008-05-19 | 2010-02-20 | Общество с ограниченной ответственностью Научно-технический и экспертный центр новых экотехнологий в гидрогеологии и гидротехнике "НОВОТЭК" | Method of draining of tubelike mineral deposit |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103422868B (en) | The structure of a kind of Super-void Water Pressure that dissipates, reinforcing shield tunnel soil body and method | |
| CN102926392A (en) | Foundation pit dewatering system and construction method thereof | |
| RU2320849C2 (en) | Well construction and operation method | |
| RU2037012C1 (en) | Method of discharging water in the process of draining rock massif | |
| RU2529197C1 (en) | Drilling wastes underground burial | |
| RU2129660C1 (en) | Method of degassing coal seams | |
| RU2076923C1 (en) | Method of formation of flagging screen in water-encroached rocks | |
| CN115929402B (en) | Method for transferring water storage resources by using loess of coal mining fracture | |
| SU666276A1 (en) | Mine drainage method | |
| CN103291307B (en) | A kind of rich water rockhole Dewatering by leading level method | |
| Rahbar et al. | The design and construction of grouting against water ingress in the headrace tunnel for the Uma Oya Project, Sri Lanka | |
| RU2016188C1 (en) | Method for oil and gas well casing cementing | |
| RU2126085C1 (en) | Method for underground lixiviation of metals from waterless rock | |
| SU1435505A1 (en) | Method of storing toxic brines in permafrost environment | |
| SU1710759A1 (en) | Method of extraction of minerals from thick underground formations through holes and device for its realization | |
| SU972145A1 (en) | Method of hydraulic working of high-gas coal seam | |
| RU2127361C1 (en) | Method for extracting liquid minerals from salt mines | |
| RU2517728C1 (en) | Hydraulic borehole mining of hard minerals | |
| SU1129372A1 (en) | Method of plugging the base of a hydraulic structure | |
| SU1105651A1 (en) | Method and apparatus for well-production of frozen separately grained rock | |
| SU1343021A1 (en) | Method of winning from production levels | |
| SU1070312A1 (en) | Method of constructing a plugging pad | |
| SU1298404A1 (en) | Method of degassing coal-bearing strata | |
| SU1693265A1 (en) | Method of hydraulic mining of coal bed | |
| RU2183260C2 (en) | Process of development of oil field at late stage of its operation |