CN201026643Y - Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner - Google Patents

Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner Download PDF

Info

Publication number
CN201026643Y
CN201026643Y CNU2007200365167U CN200720036516U CN201026643Y CN 201026643 Y CN201026643 Y CN 201026643Y CN U2007200365167 U CNU2007200365167 U CN U2007200365167U CN 200720036516 U CN200720036516 U CN 200720036516U CN 201026643 Y CN201026643 Y CN 201026643Y
Authority
CN
China
Prior art keywords
outer mold
concrete
permeable
seepage
liner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007200365167U
Other languages
Chinese (zh)
Inventor
陈迅捷
张燕迟
鄢俊
梁菊明
钱文勋
欧阳幼玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiaxing Wufeng Cement Product Manufacturing Co Ltd
Nanjing Hydraulic Research Institue Ministryof Water Resources Ministry Of Communications
Original Assignee
Jiaxing Wufeng Cement Product Manufacturing Co Ltd
Nanjing Hydraulic Research Institue Ministryof Water Resources Ministry Of Communications
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiaxing Wufeng Cement Product Manufacturing Co Ltd, Nanjing Hydraulic Research Institue Ministryof Water Resources Ministry Of Communications filed Critical Jiaxing Wufeng Cement Product Manufacturing Co Ltd
Priority to CNU2007200365167U priority Critical patent/CN201026643Y/en
Application granted granted Critical
Publication of CN201026643Y publication Critical patent/CN201026643Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

利用透水模板衬垫预制混凝土防渗U型槽的设备:弹簧支架上设置有外模,外模上设有振动器,外模内放置有内模;其特征在于,在外模的内壁上设有透水模板衬垫,同时该外模上设有抽水孔,所述的抽水孔通过抽水管与抽水机连接。优化方案的透水模板衬垫采用土工布和土工格栅复合而成;或由纱布复合多孔板材构成。振动器可采用附着振动器;抽水管上可设有阀门;抽水机可采用混凝土真空吸水机。本实用新型可提高混凝土U型防渗槽密实性、强度和抗渗性,提高成品质量;还可降低成本;浇筑后可立即脱除U型槽钢外模和透水模板衬垫,钢外模和透水模板衬垫重复使用率提高,预制生产效率提高。

The equipment for prefabricating concrete anti-seepage U-shaped grooves with permeable formwork pads: an outer mold is arranged on the spring support, a vibrator is arranged on the outer mold, and an inner mold is placed inside the outer mold; it is characterized in that the inner wall of the outer mold is provided with The water-permeable template liner is provided with a water pumping hole on the outer mold at the same time, and the water pumping hole is connected with a water pump through a water pipe. The permeable formwork liner of the optimized scheme is composed of geotextile and geogrid; or composed of gauze composite porous plate. The vibrator can be an attached vibrator; the suction pipe can be provided with a valve; the water pump can be a concrete vacuum suction machine. The utility model can improve the compactness, strength and impermeability of the concrete U-shaped anti-seepage groove, improve the quality of the finished product, and can also reduce the cost; the U-shaped channel steel outer mold and the permeable template liner can be removed immediately after pouring, and the steel outer mold can be removed immediately. The reuse rate of the permeable formwork liner is improved, and the prefabrication production efficiency is improved.

Description

利用透水模板衬垫预制混凝土防渗U型槽的设备 Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner

技术领域 technical field

本实用新型涉及一种利用透水模板衬垫预制混凝土防渗U型槽的方法,以及这种生产方法所使用的设备。The utility model relates to a method for prefabricating a concrete anti-seepage U-shaped groove by using a permeable template liner, and equipment used in the production method.

背景技术 Background technique

目前国内的农田灌溉渠用的混凝土防渗U型槽由于受到设计、生产工艺、材料成本等多方面因素的影响,成品节长大多数只能做到50cm。混凝土防渗U型槽的节长愈短,现场施工拼装接缝就愈多,输水时渗漏也愈多,这是当前混凝土防渗U型槽存在的明显缺点。同时,由于农田水利基本建设的量大面广,而投资相对较少,混凝土防渗U型槽的利润较低,造成产品的质量不高,难于推广。At present, the concrete anti-seepage U-shaped grooves used in domestic farmland irrigation canals are affected by many factors such as design, production technology, and material costs. Most of the finished product section lengths can only be 50cm. The shorter the joint length of the concrete anti-seepage U-shaped groove, the more joints will be assembled on site, and the more leakage will occur during water delivery. This is an obvious shortcoming of the current concrete anti-seepage U-shaped groove. At the same time, due to the large amount of farmland water conservancy infrastructure construction and the relatively small investment, the profit of the concrete anti-seepage U-shaped groove is low, resulting in low quality products and difficult promotion.

发明内容 Contents of the invention

针对现有技术存在的上述不足,本实用新型的目的是提供一种制作混凝土U型防渗槽的新工艺方法:利用透水模板衬垫预制混凝土防渗U型槽的方法。新工艺采用土工合成材料制作透水模板衬垫,应用于混凝土U型防渗槽预制的真空脱水生产工艺,可提高混凝土U型防渗槽预制生产效率,降低生产成本,并提高产品质量,有效增加成品节长,提高水渠排灌效益。同时新工艺的应用,使混凝土U型防渗槽采用大掺量工业废渣成为可能,在满足混凝土强度和耐久性的前提下,可降低原材料成本,同时有利于环境保护。In view of the above-mentioned deficiencies in the prior art, the purpose of this utility model is to provide a new process for making concrete U-shaped anti-seepage grooves: a method for prefabricating concrete anti-seepage U-shaped grooves by using permeable formwork liners. The new process uses geosynthetic materials to make permeable formwork liners, which are applied to the vacuum dehydration production process of concrete U-shaped anti-seepage tank prefabrication, which can improve the production efficiency of concrete U-shaped anti-seepage tank prefabrication, reduce production costs, and improve product quality. The length of the finished product can improve the drainage and irrigation efficiency of the canal. At the same time, the application of the new technology makes it possible to use a large amount of industrial waste slag in the concrete U-shaped anti-seepage tank. On the premise of satisfying the strength and durability of the concrete, it can reduce the cost of raw materials and is conducive to environmental protection.

完成上述实用新型任务的方案是,利用透水模板衬垫预制混凝土防渗U型槽的方法,步骤如下:The scheme for accomplishing the above-mentioned utility model task is to utilize the permeable form liner to prefabricate the method of the concrete anti-seepage U-shaped groove, and the steps are as follows:

钢模内放置透水模板衬垫;The permeable formwork liner is placed in the steel formwork;

浇注混凝土拌合物;Pouring concrete mixes;

振动密实混凝土;vibration compacted concrete;

开动抽水机进行真空脱水,同时混凝土振动成型;Start the water pump for vacuum dehydration, and at the same time, the concrete is vibrated and formed;

起吊脱除U型槽钢外模;Lift and remove the U-shaped channel steel outer mold;

揭除透水模板衬垫;Remove the permeable form liner;

混凝土养护;Concrete maintenance;

脱除U型槽钢内模,得到混凝土U型防渗槽成品。The U-shaped channel steel inner mold is removed to obtain the finished concrete U-shaped anti-seepage tank.

换言之,本实用新型的工艺方法与传统的工艺相比,增加了以下步骤:In other words, compared with the traditional technology, the process method of the present utility model has increased the following steps:

钢模内放置透水模板衬垫;振动密实混凝土的同时真空脱水;揭除透水模板衬垫。Place the permeable form liner in the steel form; vacuum dehydrate while vibrating and compacting the concrete; remove the permeable form liner.

所述的透水模板衬垫为一层透水阻隔层,可以在真空压力作用下可透水,但又阻挡水泥颗粒和砂石颗粒渗透,其作用是在土工布和钢模之间形成均匀空腔和通道,为真空脱水步骤提供保障,使混凝土中的水被均匀抽取排出,同时挡住混凝土不外流,该透水模板衬垫采用土工布和土工格栅复合而成,或由纱布复合多孔板材构成。The permeable template liner is a layer of permeable barrier layer, which can be permeable under the vacuum pressure, but also prevents the penetration of cement particles and sand particles, and its function is to form a uniform cavity and space between the geotextile and the steel mold. The channel provides guarantee for the vacuum dehydration step, so that the water in the concrete is evenly extracted and discharged, and at the same time blocks the concrete from flowing out. The permeable formwork liner is made of geotextile and geogrid composite, or composed of gauze composite porous plate.

传统技术为满足混凝土拌和要求必须足够的用水量,而混凝土水化凝固只需很低的用水量,多余的水量在混凝土中挥发后形成空隙,降低混凝土强度和混凝土性能。本实用新型真空脱水的目的是将混凝土配料中多余的用水量抽除。Traditional technology requires sufficient water consumption to meet the requirements of concrete mixing, but concrete hydration and solidification only requires a very low water consumption, and the excess water evaporates in the concrete to form voids, reducing the strength and performance of concrete. The purpose of the vacuum dehydration of the utility model is to extract excess water in the concrete batching.

上述利用透水模板衬垫预制混凝土防渗U型槽的方法所使用的设备是:在弹簧支架上设置有外模,外模上设有振动器,外模内放置有内模;其特征在于,在外模的内壁上设有透水模板衬垫,同时该外模上设有抽水孔,所述的抽水孔通过抽水管与抽水机连接。The above-mentioned equipment used in the method of utilizing the permeable template liner to prefabricate the concrete anti-seepage U-shaped groove is: an outer mold is arranged on the spring support, a vibrator is arranged on the outer mold, and an inner mold is placed in the outer mold; it is characterized in that, The inner wall of the outer mold is provided with a water-permeable template liner, and the outer mold is provided with a water pumping hole, and the water pumping hole is connected with a water pump through a water pipe.

所述的透水模板衬垫可以采用土工布,也可以采用土工布和土工格栅复合而成,还可以由纱布或多孔板材等构成;The permeable template liner can be made of geotextile, or composited by geotextile and geogrid, and can also be composed of gauze or porous plate;

所述的振动器可采用附着振动器;The vibrator can be an attached vibrator;

所述的抽水管上可以设有阀门;The water pumping pipe may be provided with a valve;

所述的抽水机可采用混凝土真空吸水机。Described water pump can adopt concrete vacuum suction machine.

混凝土中拌合水被均匀抽除,通过附着振动,一方面可提高混凝土密实性,提高混凝土强度和抗渗性,提高混凝土U型防渗槽成品质量,通过混凝土配合比优化,还可降低混凝土原材料成本;另一方面,混凝土中拌合水被均匀抽除,混凝土可塑性降低,具有一定固结强度,可以立即脱除U型槽钢外模和透水模板衬垫,U型槽钢外模和透水模板衬垫重复使用率提高,混凝土U型防渗槽预制生产效率提高。The mixing water in the concrete is evenly pumped out. Through the attached vibration, on the one hand, the compactness of the concrete can be improved, the strength and impermeability of the concrete can be improved, and the quality of the finished concrete U-shaped anti-seepage tank can be improved. Through the optimization of the concrete mix ratio, the concrete can also be reduced Raw material cost; on the other hand, the mixing water in the concrete is evenly pumped out, the plasticity of the concrete is reduced, and it has a certain consolidation strength. The reuse rate of the permeable formwork liner is improved, and the prefabrication production efficiency of the concrete U-shaped anti-seepage tank is improved.

真空脱水对混凝土抗压强度的影响如下:The effect of vacuum dehydration on the compressive strength of concrete is as follows:

  吸水时间(min)Water absorption time (min)   混凝土含水量(kg/m3)Concrete moisture content (kg/m 3 )   混凝土抗压强度(MPa)Concrete compressive strength (MPa)   7d7d   28d28d   60d60d   90d90d   00   253253   2.72.7   7.37.3   9.39.3   11.411.4   55   191191   7.87.8   13.213.2   18.518.5   22.022.0   1515   186186   9.29.2   16.316.3   22.522.5   26.226.2

附图说明 Description of drawings

图1为本实用新型设备结构示意图。Fig. 1 is the structural schematic diagram of the utility model equipment.

具体实施方式 Detailed ways

实施例1,利用透水模板衬垫预制混凝土防渗U型槽的方法及其设备,见图1:在弹簧支架1上设置有钢外模2,外模2内设置有钢内模3,两模间为混凝土U型槽10。在钢外模2外设有附着振动器4,在钢外模的内壁上附有一层透水模板衬垫5,透水模板衬垫5采用土工布和土工格栅复合而成。钢外模的壁上设有设有抽水孔6,该抽水孔通过水管7和阀门8与真空抽水机9连接。制备步骤如下:在钢模内浇注混凝土拌合物;振动密实混凝土;开动抽水机进行真空脱水,同时混凝土振动成型;起吊脱除U型槽钢外模;揭除透水模板衬垫;混凝土养护;脱除U型槽钢内模,得到混凝土U型防渗槽成品。Embodiment 1, the method and its equipment for prefabricating concrete anti-seepage U-shaped grooves using permeable formwork pads, see Figure 1: a steel outer mold 2 is arranged on the spring support 1, and a steel inner mold 3 is arranged in the outer mold 2, two The mold space is a concrete U-shaped groove 10. An attached vibrator 4 is arranged outside the steel outer mold 2, and a layer of permeable template liner 5 is attached to the inner wall of the steel outer mold. The permeable form liner 5 is composited by geotextile and geogrid. The wall of the steel outer mold is provided with a water pumping hole 6, which is connected with a vacuum pump 9 through a water pipe 7 and a valve 8. The preparation steps are as follows: pouring the concrete mixture in the steel mold; vibrating and compacting the concrete; starting the water pump to carry out vacuum dehydration, and at the same time, the concrete is vibrated into shape; lifting and removing the U-shaped channel steel outer mold; removing the permeable formwork liner; concrete curing; Remove the U-shaped channel steel inner mold to obtain the finished concrete U-shaped anti-seepage tank.

Claims (5)

1.一种利用透水模板衬垫预制混凝土防渗U型槽的设备,该设备的构成是,在弹簧支架上设置有外模,外模上设有振动器,外模内放置有内模;其特征在于,在外模的内壁上设有透水模板衬垫,同时该外模上设有抽水孔,所述的抽水孔通过抽水管与抽水机连接。1. A kind of equipment that utilizes permeable form liner to prefabricate concrete anti-seepage U-groove, the composition of this equipment is, is provided with outer mold on spring support, is provided with vibrator on the outer mold, is placed with inner mold in the outer mold; It is characterized in that a permeable form liner is provided on the inner wall of the outer mold, and at the same time, the outer mold is provided with a water suction hole, and the water suction hole is connected with a water pump through a water suction pipe. 2.按照权利要求1所述的利用透水模板衬垫预制混凝土防渗U型槽的设备,其特征在于,所述的透水模板衬垫采用土工布和土工格栅复合而成;或由纱布复合多孔板材构成。2. The equipment for prefabricating concrete anti-seepage U-shaped grooves according to claim 1, wherein the permeable form liner is composited with geotextile and geogrid; or composited with gauze Perforated sheet construction. 3.按照权利要求1或2所述的利用透水模板衬垫预制混凝土防渗U型槽的设备,其特征在于,所述的振动器采用附着振动器。3. The equipment for prefabricating concrete anti-seepage U-shaped grooves using permeable formwork pads according to claim 1 or 2, wherein the vibrator is an attached vibrator. 4.按照权利要求1或2所述的利用透水模板衬垫预制混凝土防渗U型槽的设备,其特征在于,所述的抽水管上设有阀门。4. According to claim 1 or 2, the equipment for prefabricating the concrete anti-seepage U-shaped groove by using the permeable template liner, is characterized in that, the valve is arranged on the described water pumping pipe. 5.按照权利要求1或2所述的利用透水模板衬垫预制混凝土防渗U型槽的设备,其特征在于,所述的抽水机采用混凝土真空吸水机。5. The equipment for prefabricating concrete anti-seepage U-groove by using permeable template liner according to claim 1 or 2, characterized in that, said water pump adopts concrete vacuum suction machine.
CNU2007200365167U 2007-04-03 2007-04-03 Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner Expired - Lifetime CN201026643Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200365167U CN201026643Y (en) 2007-04-03 2007-04-03 Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200365167U CN201026643Y (en) 2007-04-03 2007-04-03 Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner

Publications (1)

Publication Number Publication Date
CN201026643Y true CN201026643Y (en) 2008-02-27

Family

ID=39130844

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200365167U Expired - Lifetime CN201026643Y (en) 2007-04-03 2007-04-03 Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner

Country Status (1)

Country Link
CN (1) CN201026643Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101037003B (en) * 2007-04-03 2010-11-24 水利部交通部电力工业部南京水利科学研究院 Method and equipment for prefabricating concrete anti-seepage U-shaped groove by using permeable template liner
CN109209433A (en) * 2018-10-31 2019-01-15 上海隧道工程有限公司 The built-in process of section of jurisdiction gasket

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101037003B (en) * 2007-04-03 2010-11-24 水利部交通部电力工业部南京水利科学研究院 Method and equipment for prefabricating concrete anti-seepage U-shaped groove by using permeable template liner
CN109209433A (en) * 2018-10-31 2019-01-15 上海隧道工程有限公司 The built-in process of section of jurisdiction gasket

Similar Documents

Publication Publication Date Title
CN100516133C (en) Wall Slurry Material and Wall Construction Technology of Anti-seepage Wall
CN103396056B (en) A kind of super-size aggregate self-compacting concrete and construction technology thereof
CN101575850A (en) A kind of plastic construction and its maintenance method of using soil curing agent to strengthen soil
CN105178202A (en) Method for reinforcing concrete pier through combination of corrugated steel pipes and fiber reinforced powder concrete
CN103895098A (en) Process for forming vibration and extrusion process prestressed concrete pipe through core mold vibration method
CN109440733B (en) A kind of cementitious sand-gravel dam and its construction technology
CN100387786C (en) Thin-wall steel pipe centrifugal concrete pipe pile and its production method
CN201026643Y (en) Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner
CN101362360B (en) Method for pressing civil engineering block with silt solidified material
CN110565958B (en) Method for removing bleeding in large-volume concrete by vacuum pumping and discharging and preventing structural cracking
CN110423068A (en) A super-high-strength, high-permeability concrete block and its preparation method
CN101037003B (en) Method and equipment for prefabricating concrete anti-seepage U-shaped groove by using permeable template liner
CN108145832B (en) A kind of high-strength, high-permeability concrete forming method
CN110512591A (en) A method for strengthening ultra-soft foundation with vacuum preloading and gas injection carbonization
CN102635112B (en) Controlled construction process for compaction grouting piles
WO2019153407A1 (en) Method for manufacturing artificial mudstone employing in-situ soil modification
CN106592570B (en) A kind of basement process technique using prefabricated compacted sections tailings reinforcing body
CN108863236A (en) Exempt to stir the preparation method of Superlight ceramsites concrete cutting plate and exempts to stir Superlight ceramsites concrete cutting plate
CN105926656B (en) Construction Method of Mass Concrete Foundation
CN204976958U (en) Vacuum vibrating compaction device
CN107795324A (en) A kind of band mould negative pressure mud jacking system and mud jacking method for tunnel double-lining
CN108071173A (en) A kind of construction method of mass concrete
CN219946694U (en) A device for improving the compressive strength of prefabricated blocks
CN203514332U (en) Casing for blocking dewatering tube well of post-cast strip
CN105064712B (en) A kind of environment-friendly type high intensity microdilatancy grouting material without mould construction technology

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20080227

Effective date of abandoning: 20070403