[go: up one dir, main page]

CN105926656B - Construction Method of Mass Concrete Foundation - Google Patents

Construction Method of Mass Concrete Foundation Download PDF

Info

Publication number
CN105926656B
CN105926656B CN201610237895.XA CN201610237895A CN105926656B CN 105926656 B CN105926656 B CN 105926656B CN 201610237895 A CN201610237895 A CN 201610237895A CN 105926656 B CN105926656 B CN 105926656B
Authority
CN
China
Prior art keywords
concrete
pouring area
pouring
slow
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610237895.XA
Other languages
Chinese (zh)
Other versions
CN105926656A (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Guolong Construction Engineering Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810027236.2A priority Critical patent/CN108193690A/en
Priority to CN201810026030.8A priority patent/CN108118711A/en
Priority to CN201810026390.8A priority patent/CN108193689A/en
Priority to CN201810026491.5A priority patent/CN108118712A/en
Priority to CN201610237895.XA priority patent/CN105926656B/en
Priority to CN201810027518.2A priority patent/CN108193691A/en
Publication of CN105926656A publication Critical patent/CN105926656A/en
Application granted granted Critical
Publication of CN105926656B publication Critical patent/CN105926656B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a construction method of a large-volume concrete foundation, which is characterized in that the large-volume foundation is sequentially divided into four pouring areas at equal intervals from left to right, each pouring area is provided with a slow pouring area, the slow pouring area is provided on the right of the pouring area, concrete in the four pouring areas is poured respectively during construction, the concrete in each slow pouring area is poured after the concrete in each area is poured for 10-12 hours, the concrete in the slow pouring area adopts expansive concrete, concrete holes are formed in the large-volume foundation, fly ash is doped into the concrete to reduce the cement consumption, and the cement adopts slag cement with low hydration heat; the wood calcium water reducing agent is doped, after concrete is finally set by trowelling, compacting and pressing, plastic films and straw mats are adopted in time to cover the concrete, and then the concrete is watered and maintained for no less than 7 days.

Description

大体积混凝土基础的施工方法Construction Method of Mass Concrete Foundation

技术领域technical field

本发明涉及一种大体积混凝土基础的施工方法,适用于建筑领域。The invention relates to a construction method of a large-volume concrete foundation, which is suitable for the construction field.

背景技术Background technique

随着现代高层建筑不断涌现,大体积混凝土基础在工程建设中时有出现。大体积混凝土基础由于混凝土方量较大,在混凝土凝结过程中会产生温度应力,如果没有有效的技术措施,大体积基础会出现开裂等现象。从裂缝的形成过程可以看到,砼特别是大体积混凝土基础之所以开裂,主要是混凝土所承受的拉应力和混凝土基础本身的抗拉强度之间的矛盾发展的结果。因而为了控制大体积混凝土基础裂缝,就必须尽最大可能提高混凝土基础本身抗拉强度性能和降低温度应力。With the continuous emergence of modern high-rise buildings, mass concrete foundations appear from time to time in engineering construction. Due to the large amount of concrete in the mass concrete foundation, temperature stress will be generated during the concrete setting process. If there are no effective technical measures, the mass foundation will crack and other phenomena. It can be seen from the formation process of cracks that the cracking of concrete, especially mass concrete foundation, is mainly the result of the contradiction development between the tensile stress of concrete and the tensile strength of concrete foundation itself. Therefore, in order to control the cracks of the mass concrete foundation, it is necessary to improve the tensile strength performance of the concrete foundation itself and reduce the temperature stress as much as possible.

发明内容Contents of the invention

本发明是提供一种大体积混凝土基础的施工方法,解决大体积混凝土基础开裂的问题。The invention provides a construction method for a large-volume concrete foundation and solves the problem of cracking of the large-volume concrete foundation.

本发明从四个方面入手来缓解温度应力问题,一、在大体积基础内部设置孔洞来减少混凝土方量,大体积基础内部设置孔洞后承载性能并不会有大的削弱,同时混凝土材料会有较大的节约;二通过设置混凝土浇筑方式的调整来减少温度应力;三通过结构构造措施来减少温度应力;通过材料合理选用来减少温度应力。The present invention alleviates the problem of temperature stress from four aspects. 1. Set holes inside the large-volume foundation to reduce the amount of concrete. After the holes are set inside the large-volume foundation, the bearing performance will not be greatly weakened. At the same time, the concrete material will have Larger savings; second, reduce temperature stress by setting the adjustment of concrete pouring method; third, reduce temperature stress through structural construction measures; reduce temperature stress through reasonable selection of materials.

根据计算机仿真分析,在大体积基础1/4~1/3区域会出现较大的温度应力带,本发明中大体积基础由左至右依次等距离分为四个浇筑区域,每个浇筑区域留置缓浇区域,缓浇区域留置在浇筑区域的右边,缓浇区域长度为600~800mm,在施工时四个浇筑区域混凝土各自进行浇筑,每个缓浇区域混凝土待每个区域混凝土浇筑完毕10~12小时后再进行浇筑,每个区域混凝土浇筑后会产生水化反应,从而会出现较高的温度,每个区域已浇筑混凝土在缓浇区域会获得温度应力的释放,而每个缓浇区域混凝土和每个区域已浇筑混凝土的间歇期要适宜,防止这个部位新老混凝土没有很好的连接,本发明间歇期是大量试验获得的。缓浇区域混凝土采用膨胀混凝土,膨胀混凝土强度比非缓浇区域混凝土强度提高一个强度等级,在收缩应力较大的区段给予较大的膨胀应力。缓浇区域混凝土掺入缓凝剂,缓浇区域混凝土的缓凝时间比已浇筑混凝土延长4h,以便给缓浇区域混凝土提供邻位侧限,使混凝土内部产生应力能抵消部分混凝土拉应力,从而可减免裂缝的出现。According to computer simulation analysis, larger temperature stress bands will appear in the 1/4 to 1/3 area of the large-volume foundation. In the present invention, the large-volume foundation is divided into four pouring areas at equal distances from left to right. Each pouring area The slow pouring area is reserved, and the slow pouring area is left on the right side of the pouring area. The length of the slow pouring area is 600-800mm. During construction, the concrete in the four pouring areas is poured separately. The concrete in each slow pouring area is 10 ~ 12 hours before pouring, the concrete in each area will produce hydration reaction after pouring, resulting in higher temperature, the concrete that has been poured in each area will obtain the release of temperature stress in the slow pouring area, and each slow pouring The interim period between the regional concrete and the poured concrete in each area should be suitable to prevent the old and new concrete from being well connected in this position. The interim period of the present invention is obtained through a large number of experiments. The concrete in the slow pouring area adopts expansive concrete, and the strength of the expansive concrete is higher than that of the non-slow pouring area by one strength level, and a larger expansion stress is given to the section with a larger shrinkage stress. The concrete in the slow pouring area is mixed with a retarder, and the retarding time of the concrete in the slow pouring area is 4 hours longer than that of the poured concrete, so as to provide an adjacent side limit for the concrete in the slow pouring area, so that the stress generated inside the concrete can offset part of the tensile stress of the concrete, thereby Can reduce the appearance of cracks.

在缓浇区域和非缓浇区域交接处埋设抗拉构造钢筋,抗拉构造钢筋直径为6~8mm,抗拉构造钢筋间距为50~100mm,抗拉构造钢筋沿截面上、下两层均匀对称配置。在缓浇区域和非缓浇区域交接处混凝土因收缩或其他原因产生的拉应力便由抗拉构造钢筋承担,从而能有效地限制裂缝的展开。Bury tensile structural steel bars at the junction of the slow pouring area and the non-slow pouring area. The diameter of the tensile structural steel bars is 6-8mm, and the spacing of the tensile structural steel bars is 50-100mm. The tensile structural steel bars are uniform and symmetrical along the upper and lower layers of the section. configure. At the junction of the slow pouring area and the non-slow pouring area, the tensile stress of the concrete due to shrinkage or other reasons is borne by the tensile structural steel bars, which can effectively limit the expansion of cracks.

大体积基础每个区域转角处放置放射筋,放射筋直径为14~18mm,由于温度变化和混凝土收缩,会产生应力集中而导致裂缝,放射筋可以很好地避免这种现象。Radial ribs are placed at the corners of each area of the large-volume foundation. The diameter of the radial ribs is 14-18 mm. Due to temperature changes and concrete shrinkage, stress concentration will occur and cause cracks. Radial ribs can well avoid this phenomenon.

大体积基础与下面混凝土垫层之间铺设油毡,油毡不仅作为防水层,还可以作为滑动层。由于边界存在约束会产生温度收缩应力,大体积基础在与外约束的接触面上设置滑动面,可以大大减弱外约束,而油毡起到滑动层的作用。Linoleum is laid between the large-volume foundation and the concrete cushion below, and the linoleum not only acts as a waterproof layer, but also as a sliding layer. Due to the temperature shrinkage stress caused by constraints at the boundary, a sliding surface is set on the contact surface with the external constraints on the large-volume foundation, which can greatly weaken the external constraints, and the linoleum acts as a sliding layer.

大体积基础内部设置混凝土孔,混凝土孔采用皮囊充气方式实现,皮囊材料采用5mm厚的橡胶,使其能承受足够的压力。在皮囊一端安装进气嘴,并装有压力表和球阀,有利于控制皮囊内气体压力和控制充气。皮囊在安装前先进行初步充气,皮囊初步充气压力为0.02MPa,皮囊安放好后,再次用气泵进行充气,使皮囊内气压达到终压时停止充气,然后可以继续浇筑至完成。皮囊充气终压根据混凝土孔直径进行确定,当混凝土孔直径为小于或等于75mm时,皮囊充气终压采用0.04MPa;当混凝土孔直径为大于75mm且小于或等于100mm时,皮囊充气终压采用0.05MPa;当混凝土孔直径为大于100mm且小于或等于125mm时,皮囊充气终压采用0.06MPa;当混凝土孔直径为大于125mm且小于或等于150mm时,皮囊充气终压采用0.07MPa;当混凝土孔直径为大于150mm时,皮囊充气终压采用0.08MPa。皮囊表面涂刷新机油,以利于脱模。Concrete holes are set inside the large-volume foundation, and the concrete holes are realized by air bladder inflation. The material of the bladder is rubber with a thickness of 5mm, so that it can withstand sufficient pressure. An air inlet nozzle is installed at one end of the skin bag, and a pressure gauge and a ball valve are installed, which is beneficial to control the gas pressure in the skin bag and control inflation. The skin bag should be preliminarily inflated before installation. The initial inflation pressure of the skin bag is 0.02MPa. After the skin bag is installed, the air pump is used to inflate again, so that the air pressure in the skin bag reaches the final pressure and the inflation is stopped, and then the pouring can be continued until completion. The final pressure of the bladder inflation is determined according to the diameter of the concrete hole. When the diameter of the concrete hole is less than or equal to 75mm, the final pressure of the bladder inflation is 0.04MPa; when the diameter of the concrete hole is greater than 75mm and less than or equal to 100mm, the final pressure of the bladder inflation is 0.05 MPa; when the diameter of the concrete hole is greater than 100mm and less than or equal to 125mm, the final pressure of airbag inflation shall be 0.06MPa; when the diameter of the concrete hole is greater than 125mm and less than or equal to 150mm, the final pressure of airbag inflation shall be 0.07MPa; When it is greater than 150mm, the final inflation pressure of the bladder is 0.08MPa. The surface of the leather bag is coated with new engine oil to facilitate demoulding.

混凝土浇筑完工12h后,即可将皮囊放气、抽出。由于混凝土与皮囊的橡胶之间的粘接及皮囊内的空气不能完全放出,所以皮囊表面大部分还是与混凝土连在一起,很难将其抽出。采用简易钢筋脱囊器进行初步脱模,钢筋脱囊器主杆为直径为2根25mm焊接而成的钢筋,钢筋端头焊接椭圆形钢筋笼,椭圆形钢筋笼所采用的钢筋直径为12mm,钢筋外面包裹胶布,以防止钢筋或者钢筋焊接接头划破皮囊。将钢筋脱囊器插入皮囊与混凝土的结合缝,一边轻轻晃动,一边插入。待皮囊与混凝土初步分开后可以采用人工抽出皮囊。After 12 hours of concrete pouring, the bladder can be deflated and drawn out. Because the bonding between the concrete and the rubber of the bladder and the air in the bladder cannot be released completely, the surface of the bladder is still mostly connected with the concrete, and it is difficult to extract it. A simple steel bar extractor is used for preliminary demoulding. The main rod of the steel bar extractor is two welded steel bars with a diameter of 25mm. The end of the steel bar is welded with an oval steel bar cage. The outside of the steel bar is wrapped with tape to prevent the steel bar or the welded joint of the steel bar from scratching the skin. Insert the steel bar capsule extractor into the joint between the skin capsule and the concrete, and insert it while shaking it slightly. After the skin is initially separated from the concrete, the skin can be extracted manually.

大体积基础混凝土水泥用量不超过350kg/m3,在混凝土中掺入粉煤灰来减少水泥用量,粉煤灰掺入量为水泥质量的5%~10%,水泥采用水化热低的矿渣水泥,以减少混凝土构件的表面裂缝或者贯穿性裂缝。The amount of cement used in large-volume foundation concrete is not more than 350kg/m 3 , and fly ash is added to the concrete to reduce the amount of cement. The amount of fly ash added is 5% to 10% of the cement mass, and the cement uses slag with low heat of hydration Cement to reduce surface cracks or penetrating cracks in concrete elements.

混凝土中水化反应的用水量只需要20%~25%,如用水量过多,这些在混凝土中的水蒸发后,会使混凝土产生大量毛细孔,而增加混凝土的收缩量,也会影响其抗渗能力。为了既可减少用水又可满足混凝土的可泵性及和易性要求,掺入木钙减水剂,木钙减水剂为水泥用量的0.25%。The water consumption of the hydration reaction in concrete only needs 20% to 25%. If the water consumption is too much, after the water in the concrete evaporates, it will cause a large number of capillary pores in the concrete, and increase the shrinkage of the concrete, which will also affect its performance. Impermeability. In order to reduce water consumption and meet the pumpability and workability requirements of concrete, wood calcium water reducer is added, and the wood calcium water reducer is 0.25% of the cement dosage.

混凝土粗骨料采用粒径为5~40mm的碎石。传统粗骨料粒径为5~25mm,较小的粒径要达到混凝土设计强度要求,水泥用量会增加,同样会引起混凝土收缩增加。Coarse aggregate of concrete is crushed stone with a particle size of 5-40mm. The particle size of traditional coarse aggregate is 5-25mm. If the particle size is smaller to meet the design strength requirements of concrete, the amount of cement will increase, which will also increase the shrinkage of concrete.

传统泵送混凝土的坍落度过大,泵送混凝土坍落度为14~16cm,浇筑梁板仅采用振动棒捣固,再用木尺赶平混凝土,楼板存在着振捣不密实,易产生早期混凝土的塑性收缩及沉降收缩裂缝的质量通病。本发明适当减小混凝土的坍落度,泵送混凝土坍落度采用10~12cm,在初凝前用木抹搓平收压两遍,避免塑性收缩及沉降缩裂缝产生。The slump of traditional pumped concrete is too large, and the slump of pumped concrete is 14 to 16 cm. The pouring beams and slabs are only tamped with vibrating rods, and then the concrete is leveled with a wooden ruler. The plastic shrinkage of early concrete and the common quality problems of settlement shrinkage cracks. The invention properly reduces the slump of the concrete. The slump of the pumped concrete is 10-12 cm. Before the initial setting, the concrete is rubbed flat and compressed twice to avoid plastic shrinkage and settlement shrinkage cracks.

不应过早拆模,拆模选用混凝土浇筑7天后进行,养护时要充分浇水使木模浸湿,既可散热又可保温,拆模后应尽早进行边墙外侧的防水施工,并抓紧随时回填夯实土方,这样可利用土中水分继续养护混凝土,以达到防止裂缝产生的目的。The formwork should not be removed prematurely, and the formwork should be removed after 7 days of concrete pouring. During maintenance, the wooden formwork should be fully watered to soak it, which can not only dissipate heat but also keep heat. Backfill the rammed earth at any time, so that the moisture in the soil can be used to continue curing the concrete to prevent cracks.

混凝土用木抹收压终凝后,及时采用塑料薄膜加草垫覆盖后淋水养护不少于7d。混凝土浇注完成后,水化热使内部温度达到一定温度,如不在塑料薄膜上加盖草垫保温,则形成的内部温差,会使混凝土内部产生的应力超过极限,而使混凝土表面产生裂缝;另外,温度在激剧下降时,混凝土会收缩,其所产生的拉应力,随着混凝土龄期的增长以及混凝土本身强度的提高,对降温的收缩应力的约束也愈来愈大,如果此时的混凝土强度不足以抵抗这张收缩应力,也会产生裂缝。塑料薄膜加草垫覆盖后浇水养护,确保混凝土硬化过程中收缩较小,避开失水收缩与温降峰值重叠而产生裂缝。After the concrete is finally set with wooden mop under pressure, it shall be covered with plastic film and straw mat in time, and then watered for curing for no less than 7 days. After the concrete is poured, the heat of hydration makes the internal temperature reach a certain temperature. If the plastic film is not covered with straw mats for heat preservation, the internal temperature difference will cause the stress generated inside the concrete to exceed the limit and cause cracks on the concrete surface; , when the temperature drops sharply, the concrete will shrink, and the tensile stress produced by it, with the increase of the age of the concrete and the increase of the strength of the concrete itself, the constraints on the shrinkage stress of the cooling will become more and more large. If at this time Concrete is not strong enough to resist this shrinkage stress, and cracks can also develop. Cover with plastic film and grass mat and water for curing to ensure that the shrinkage of the concrete is small during the hardening process, and to avoid cracks caused by the overlapping of dehydration shrinkage and temperature drop peaks.

本发明质量可靠,操作方便。The invention has reliable quality and convenient operation.

具体实施方式Detailed ways

本实施例中大体积基础由左至右依次等距离分为四个浇筑区域,每个浇筑区域留置缓浇区域,缓浇区域留置在浇筑区域的右边,缓浇区域长度为600~800mm,在施工时四个浇筑区域混凝土各自进行浇筑,每个缓浇区域混凝土待每个区域混凝土浇筑完毕10~12小时后再进行浇筑,缓浇区域混凝土采用膨胀混凝土,膨胀混凝土强度比非缓浇区域混凝土强度提高一个强度等级,缓浇区域混凝土掺入缓凝剂,缓浇区域混凝土的缓凝时间比已浇筑混凝土延长4h。In this embodiment, the large-volume foundation is divided into four pouring areas at equal distances from left to right. Each pouring area is left with a slow pouring area, and the slow pouring area is left on the right side of the pouring area. The length of the slow pouring area is 600-800mm. During the construction, the concrete in the four pouring areas shall be poured separately, and the concrete in each slow pouring area shall be poured after 10 to 12 hours after the concrete pouring in each area is completed. The strength is increased by one strength level, and the concrete in the slow pouring area is mixed with a retarder, and the retarding time of the concrete in the slow pouring area is 4h longer than that of the poured concrete.

在缓浇区域和非缓浇区域交接处埋设抗拉构造钢筋,抗拉构造钢筋直径为6~8mm,抗拉构造钢筋间距为50~100mm,抗拉构造钢筋沿截面上、下两层均匀对称配置。Bury tensile structural steel bars at the junction of the slow pouring area and the non-slow pouring area. The diameter of the tensile structural steel bars is 6-8mm, and the spacing of the tensile structural steel bars is 50-100mm. The tensile structural steel bars are uniform and symmetrical along the upper and lower layers of the section. configuration.

大体积基础每个区域转角处放置放射筋,放射筋直径为14~18mm。Radial ribs are placed at the corners of each area of the large-volume foundation, and the diameter of the radial ribs is 14-18mm.

大体积基础与下面混凝土垫层之间铺设油毡。Linoleum is laid between the mass foundation and the concrete cushion below.

大体积基础内部设置混凝土孔,混凝土孔采用皮囊充气方式实现,皮囊材料采用5mm厚的橡胶。在皮囊一端安装进气嘴,并装有压力表和球阀。皮囊在安装前先进行初步充气,皮囊初步充气压力为0.02MPa,皮囊安放好后,再次用气泵进行充气,使皮囊内气压达到终压时停止充气,然后可以继续浇筑至完成。皮囊充气终压根据混凝土孔直径进行确定,当混凝土孔直径为小于或等于75mm时,皮囊充气终压采用0.04MPa;当混凝土孔直径为大于75mm且小于或等于100mm时,皮囊充气终压采用0.05MPa;当混凝土孔直径为大于100mm且小于或等于125mm时,皮囊充气终压采用0.06MPa;当混凝土孔直径为大于125mm且小于或等于150mm时,皮囊充气终压采用0.07MPa;当混凝土孔直径为大于150mm时,皮囊充气终压采用0.08MPa。皮囊表面涂刷新机油。Concrete holes are set inside the large-volume foundation, and the concrete holes are realized by inflating bladders, and the material of the bladders is 5mm thick rubber. An air inlet nozzle is installed at one end of the skin bag, and a pressure gauge and a ball valve are housed. The skin bag should be preliminarily inflated before installation. The initial inflation pressure of the skin bag is 0.02MPa. After the skin bag is installed, the air pump is used to inflate again, so that the air pressure in the skin bag reaches the final pressure and the inflation is stopped, and then the pouring can be continued until completion. The final pressure of the bladder inflation is determined according to the diameter of the concrete hole. When the diameter of the concrete hole is less than or equal to 75mm, the final pressure of the bladder inflation is 0.04MPa; when the diameter of the concrete hole is greater than 75mm and less than or equal to 100mm, the final pressure of the bladder inflation is 0.05 MPa; when the diameter of the concrete hole is greater than 100mm and less than or equal to 125mm, the final pressure of airbag inflation shall be 0.06MPa; when the diameter of the concrete hole is greater than 125mm and less than or equal to 150mm, the final pressure of airbag inflation shall be 0.07MPa; When it is greater than 150mm, the final inflation pressure of the bladder is 0.08MPa. Coat the surface of the leather bag with new engine oil.

混凝土浇筑完工12h后,即可将皮囊放气、抽出。由于混凝土与皮囊的橡胶之间的粘接及皮囊内的空气不能完全放出,所以皮囊表面大部分还是与混凝土连在一起,很难将其抽出。采用简易钢筋脱囊器进行初步脱模,钢筋脱囊器主杆为直径为2根25mm焊接而成的钢筋,钢筋端头焊接椭圆形钢筋笼,椭圆形钢筋笼所采用的钢筋直径为12mm,钢筋外面包裹胶布,以防止钢筋或者钢筋焊接接头划破皮囊。将钢筋脱囊器插入皮囊与混凝土的结合缝,一边轻轻晃动,一边插入。待皮囊与混凝土初步分开后可以采用人工抽出皮囊。After 12 hours of concrete pouring, the bladder can be deflated and drawn out. Because the bonding between the concrete and the rubber of the bladder and the air in the bladder cannot be released completely, the surface of the bladder is still mostly connected with the concrete, and it is difficult to extract it. A simple steel bar extractor is used for preliminary demoulding. The main rod of the steel bar extractor is two welded steel bars with a diameter of 25mm. The end of the steel bar is welded with an oval steel bar cage. The outside of the steel bar is wrapped with tape to prevent the steel bar or the welded joint of the steel bar from scratching the skin. Insert the steel bar capsule extractor into the joint between the skin capsule and the concrete, and insert it while shaking it slightly. After the skin is initially separated from the concrete, the skin can be extracted manually.

大体积基础混凝土水泥用量不超过350kg/m3,在混凝土中掺入粉煤灰来减少水泥用量,粉煤灰掺入量为水泥质量的5%~10%,水泥采用水化热低的矿渣水泥。The amount of cement used in large-volume foundation concrete is not more than 350kg/m 3 , and fly ash is added to the concrete to reduce the amount of cement. The amount of fly ash added is 5% to 10% of the cement mass, and the cement uses slag with low heat of hydration cement.

掺入木钙减水剂,木钙减水剂为水泥用量的0.25%。混凝土粗骨料采用粒径为5~40mm的碎石。泵送混凝土坍落度采用10~12cm,在初凝前用木抹搓平收压两遍,避免塑性收缩及沉降缩裂缝产生。Add wood calcium water reducer, wood calcium water reducer is 0.25% of cement dosage. Coarse aggregate of concrete is crushed stone with a particle size of 5-40mm. The slump of the pumped concrete should be 10-12cm. Before the initial setting, rub it flat and compress it twice with a wooden mop to avoid plastic shrinkage and settlement shrinkage cracks.

拆模选用混凝土浇筑7天后进行,养护时要充分浇水使木模浸湿,既可散热又可保温,拆模后应尽早进行边墙外侧的防水施工,并抓紧随时回填夯实土方。Formwork removal should be carried out after 7 days of concrete pouring. During maintenance, it should be fully watered to soak the wooden formwork, which can not only dissipate heat but also keep heat.

混凝土用木抹收压终凝后,及时采用塑料薄膜加草垫覆盖后淋水养护不少于7d。After the concrete is finally set with wooden mop under pressure, it shall be covered with plastic film and straw mat in time, and then watered for curing for no less than 7 days.

Claims (1)

1.一种大体积混凝土基础的施工方法,其特征是大体积基础由左至右依次等距离分为四个浇筑区域,每个浇筑区域留置缓浇区域,缓浇区域留置在浇筑区域的右边,缓浇区域长度为600~800mm,在施工时四个浇筑区域混凝土各自进行浇筑,每个缓浇区域混凝土待每个区域混凝土浇筑完毕10~12小时后再进行浇筑,缓浇区域混凝土采用膨胀混凝土,膨胀混凝土强度比非缓浇区域混凝土强度提高一个强度等级,缓浇区域混凝土掺入缓凝剂,缓浇区域混凝土的缓凝时间比已浇筑混凝土延长4h;大体积基础内部设置混凝土孔;大体积基础混凝土水泥用量不超过350kg/m3,在混凝土中掺入粉煤灰来减少水泥用量,粉煤灰掺入量为水泥质量的5%~10%,水泥采用水化热低的矿渣水泥;掺入木钙减水剂,木钙减水剂为水泥用量的0.25%;混凝土粗骨料采用粒径为5~40mm的碎石;混凝土用木抹收压终凝后,及时采用塑料薄膜加草垫覆盖后淋水养护不少于7d。1. A construction method for a mass concrete foundation, characterized in that the mass foundation is divided into four pouring areas equidistantly from left to right, each pouring area is left with a slow pouring area, and the slow pouring area is left on the right side of the pouring area , the length of the slow pouring area is 600-800mm. During the construction, the concrete in the four pouring areas is poured separately. The concrete in each slow pouring area is poured after 10 to 12 hours after the concrete pouring in each area. The concrete in the slow pouring area uses expansion Concrete, the strength of expansive concrete is higher than that of non-slow pouring area by one strength grade. The concrete in slow pouring area is mixed with retarder, and the retarding time of concrete in slow pouring area is 4h longer than that of poured concrete; concrete holes are set inside the large-volume foundation; The amount of cement used in large-volume foundation concrete is not more than 350kg/m 3 , and fly ash is added to the concrete to reduce the amount of cement. The amount of fly ash added is 5% to 10% of the cement mass, and the cement uses slag with low heat of hydration Cement; mixed with wood calcium water reducer, wood calcium water reducer is 0.25% of the amount of cement; concrete coarse aggregate uses crushed stone with a particle size of 5-40mm; After covering with film and grass mat, watering and curing shall not be less than 7 days.
CN201610237895.XA 2016-03-30 2016-03-30 Construction Method of Mass Concrete Foundation Active CN105926656B (en)

Priority Applications (6)

Application Number Priority Date Filing Date Title
CN201810027236.2A CN108193690A (en) 2016-03-30 2016-03-30 The construction technology of volume of concrete foundation
CN201810026030.8A CN108118711A (en) 2016-03-30 2016-03-30 The anti-crack construction method of volume of concrete foundation
CN201810026390.8A CN108193689A (en) 2016-03-30 2016-03-30 The Anti-cracking Technology of volume of concrete foundation
CN201810026491.5A CN108118712A (en) 2016-03-30 2016-03-30 The construction method on large-sized concrete basis
CN201610237895.XA CN105926656B (en) 2016-03-30 2016-03-30 Construction Method of Mass Concrete Foundation
CN201810027518.2A CN108193691A (en) 2016-03-30 2016-03-30 The construction method of volume of concrete foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610237895.XA CN105926656B (en) 2016-03-30 2016-03-30 Construction Method of Mass Concrete Foundation

Related Child Applications (5)

Application Number Title Priority Date Filing Date
CN201810026491.5A Division CN108118712A (en) 2016-03-30 2016-03-30 The construction method on large-sized concrete basis
CN201810027518.2A Division CN108193691A (en) 2016-03-30 2016-03-30 The construction method of volume of concrete foundation
CN201810027236.2A Division CN108193690A (en) 2016-03-30 2016-03-30 The construction technology of volume of concrete foundation
CN201810026030.8A Division CN108118711A (en) 2016-03-30 2016-03-30 The anti-crack construction method of volume of concrete foundation
CN201810026390.8A Division CN108193689A (en) 2016-03-30 2016-03-30 The Anti-cracking Technology of volume of concrete foundation

Publications (2)

Publication Number Publication Date
CN105926656A CN105926656A (en) 2016-09-07
CN105926656B true CN105926656B (en) 2018-07-03

Family

ID=56839345

Family Applications (6)

Application Number Title Priority Date Filing Date
CN201810027518.2A Pending CN108193691A (en) 2016-03-30 2016-03-30 The construction method of volume of concrete foundation
CN201810027236.2A Pending CN108193690A (en) 2016-03-30 2016-03-30 The construction technology of volume of concrete foundation
CN201810026491.5A Pending CN108118712A (en) 2016-03-30 2016-03-30 The construction method on large-sized concrete basis
CN201610237895.XA Active CN105926656B (en) 2016-03-30 2016-03-30 Construction Method of Mass Concrete Foundation
CN201810026030.8A Pending CN108118711A (en) 2016-03-30 2016-03-30 The anti-crack construction method of volume of concrete foundation
CN201810026390.8A Pending CN108193689A (en) 2016-03-30 2016-03-30 The Anti-cracking Technology of volume of concrete foundation

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201810027518.2A Pending CN108193691A (en) 2016-03-30 2016-03-30 The construction method of volume of concrete foundation
CN201810027236.2A Pending CN108193690A (en) 2016-03-30 2016-03-30 The construction technology of volume of concrete foundation
CN201810026491.5A Pending CN108118712A (en) 2016-03-30 2016-03-30 The construction method on large-sized concrete basis

Family Applications After (2)

Application Number Title Priority Date Filing Date
CN201810026030.8A Pending CN108118711A (en) 2016-03-30 2016-03-30 The anti-crack construction method of volume of concrete foundation
CN201810026390.8A Pending CN108193689A (en) 2016-03-30 2016-03-30 The Anti-cracking Technology of volume of concrete foundation

Country Status (1)

Country Link
CN (6) CN108193691A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107867813A (en) * 2017-10-24 2018-04-03 中交上海航道局有限公司 A kind of method for prefabricating for preventing mass concrete component from ftractureing
CN108911603B (en) * 2018-07-26 2021-02-09 上海石化安东混凝土有限公司 A kind of mass concrete and its preparation and construction technology
CN109723219B (en) * 2019-01-09 2021-07-13 武汉一冶建筑安装工程有限责任公司 Method for simultaneously pouring high-grade and low-grade large-volume concrete

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55119829A (en) * 1979-03-06 1980-09-13 Denki Kagaku Kogyo Kk Simultaneous construction method for foundation and heat-insulating floor
CN204199694U (en) * 2014-09-17 2015-03-11 中铁建大桥工程局集团第一工程有限公司 Concrete preformed hole shaping device
CN104563122A (en) * 2015-02-11 2015-04-29 中国水利水电第四工程局有限公司 Mass concrete construction method

Also Published As

Publication number Publication date
CN105926656A (en) 2016-09-07
CN108193690A (en) 2018-06-22
CN108118711A (en) 2018-06-05
CN108118712A (en) 2018-06-05
CN108193691A (en) 2018-06-22
CN108193689A (en) 2018-06-22

Similar Documents

Publication Publication Date Title
CN105298133B (en) Design and Construction Method of Improving the Crack Resistance of Mass Concrete Floor
WO2019075812A1 (en) Roller compacted concrete dam and construction method therefor
CN108297246A (en) Prevent concrete block from generating fracture unit technique
CN107327137A (en) A kind of heat insulation integrated non-dismantling formworks of STP and its construction technology
CN105619596A (en) Preparation method of foam concrete composite board
CN103396056A (en) Self-compact concrete with oversized-particle aggregate and construction technology thereof
CN104264678B (en) Concrete in mass Anti-cracking construction technology
CN105926656B (en) Construction Method of Mass Concrete Foundation
CN106760552A (en) Thickness of concrete floor and flatness control device and method
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN104499498B (en) A kind of construction method of mass concrete building
CN103835523A (en) Ultra-long extra-large reinforced concrete structure engineering crack prevention process
CN111377682A (en) Anti-cracking concrete and preparation method thereof, and anti-cracking fabricated prefabricated part composite floor slab and preparation method thereof
US2315732A (en) Porous concrete construction and method of making the same
CN108145832A (en) A kind of forming method of high-strength, high pervious concrete
CN111730726A (en) How to make concrete precast column mould
CN106220081B (en) A kind of high fluidity seepage control and crack resistance concrete material
Jin et al. Recent advances in rock-filled concrete dams and self-protected underwater concrete
CN201026643Y (en) Equipment for Prefabricating Concrete Seepage-proof U-shaped Groove Using Permeable Form Liner
CN115717480A (en) Concrete pouring method for narrow space of cavity wall
Tong Cause and Influence of Mass Concrete Crack
CN102758491A (en) Shear wall heat insulation system and construction method thereof
CN113738062A (en) Whole seamless terrace of prestressing force
CN206487153U (en) Thickness of concrete floor and flatness control device
CN106564122A (en) Pre-tensioning method U beam crack control method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190314

Address after: 330200 Jingshan Village, Xiangtang Town, Nanchang County, Nanchang City, Jiangxi Province

Patentee after: Jiangxi Guolong Construction Engineering Co., Ltd.

Address before: 325000 Room 302, 11 Building of Jingshan Group, Wenzhou City, Zhejiang Province

Patentee before: Ye Xiangzhu

TR01 Transfer of patent right