WO2023138040A1 PCT/CN2022/112408 CN2022112408W WO2023138040A1 WO 2023138040 A1 WO2023138040 A1 WO 2023138040A1 CN 2022112408 W CN2022112408 W CN 2022112408W WO 2023138040 A1 WO2023138040 A1 WO 2023138040A1
Authority
WO
WIPO (PCT)
Prior art keywords
flue
water
header
waste heat
heat receiving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/CN2022/112408
Other languages
French (fr)
Chinese (zh)
Inventor
王海俊
段炼
孙薇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wisdri Engineering and Research Incorporation Ltd
Original Assignee
Wisdri Engineering and Research Incorporation Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wisdri Engineering and Research Incorporation Ltd filed Critical Wisdri Engineering and Research Incorporation Ltd
Publication of WO2023138040A1 publication Critical patent/WO2023138040A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/38Removal of waste gases or dust
    • C21C5/40Offtakes or separating apparatus for converter waste gases or dust
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C2100/00Exhaust gas
    • C21C2100/06Energy from waste gas used in other processes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/25Process efficiency

Definitions

  • the invention belongs to the technical field of waste heat boilers, and in particular relates to a waste heat boiler flue of a converter.
  • the converter vaporization flue is to recover the sensible heat of the high-temperature flue gas generated in the converter steelmaking process, and to reduce the flue gas to a certain temperature before sending it to the subsequent dust removal system.
  • the flue gas temperature is usually as high as 2000 ° C, and the reaction in the converter is intense, and there is a risk of slag splashing.
  • the skirt cover adopts a water-cooled structure.
  • the skirt cover and the flue of the furnace mouth section adopt steam seal, nitrogen seal or mechanical seal. Among them, steam seal and nitrogen seal will cause waste of energy.
  • the mechanical seal structure is complex, and the seal is a vulnerable part, and the maintenance workload is heavy.
  • the purpose of the present invention is to provide a converter waste heat boiler flue, which can at least solve some of the defects in the prior art.
  • the present invention adopts the following technical solutions:
  • a converter waste heat boiler flue comprising a flue mouth section flue, a skirt cover and a water cooling ring.
  • the mouth section flue is installed in a high-rise frame above the converter.
  • the water cooling ring has a heat receiving tube 1 arranged in a ring shape. In the gap space reserved between the channel and the first heating tube, the second heating tube can move up and down in the gap space.
  • the water-cooling ring includes a heat receiving pipe 1, a water inlet header 1 and a water outlet header 1, the water inlet header 1 and the water outlet header 1 are arranged outside the heat receiving pipe 1, and the water inlet header 1 and the water outlet header 1 are arranged symmetrically.
  • the heat receiving pipe 1 is an annular structure with the same inner diameter in the height direction, and the inner and outer walls of the heat receiving pipe 1 are smooth walls.
  • the skirt cover includes heating pipe 2, water inlet header 2, water outlet header 2 and a lifting guide assembly.
  • the outlet water header 2 and water inlet header 2 are arranged at intervals up and down, and the diameter of the water inlet header 2 is larger than the diameter of the water outlet header 2.
  • Both the outlet water header 2 and the water inlet header 2 are located outside the heating pipe 1 of the water cooling ring.
  • the heating pipe 2 is arranged vertically. Header two connections.
  • the lifting guide assembly includes a fixed bracket, a lifting driving part and a lifting power transmission part, the heat receiving pipe 2, the water inlet header 2 and the water outlet header 2 are all fixedly connected to the fixing bracket, and the lifting driving part drives the fixed bracket to move up and down along the height direction of the water cooling ring through the lifting power transmission part.
  • the lifting guide assembly further includes a guide wheel, the guide wheel is fixedly installed on the fixed bracket, and the guide wheel is arranged close to the outer wall of the water cooling ring.
  • the top of the heat receiving tube 2 has an outward expansion section extending gradually outward.
  • the flue at the furnace mouth section includes a heating pipe 3, a water inlet header 3 and a water outlet header 3, and the water inlet header 3 and the water outlet header 3 are respectively connected to the lower part and the upper part of the heating pipe 3.
  • the heat receiving pipe three includes a vertical section and an inclined section, the vertical section is located outside the heat receiving pipe one, the inclined section is located inside the heat receiving pipe one, the inclined section has a bell mouth structure, and the inclined section has double walls arranged inside and outside, the outer wall of which is a vertical surface, and the inner wall is an inclined surface.
  • the converter waste heat boiler flue provided by the present invention has a simple structure.
  • the skirt cover is movably arranged between the inner wall of the water cooling ring and the outer wall of the flue mouth section flue.
  • the inner wall of the water cooling ring and the outer wall of the flue mouth section flue can guide the skirt when it is lifted, and can also play a certain role in sealing the flue gas, reducing the overflow of flue gas, and greatly reducing the maintenance workload.
  • Fig. 1 is a schematic diagram of the flue structure of the converter waste heat boiler when the skirt cover is in the down cover position in the embodiment of the present invention
  • Fig. 2 is a schematic diagram of the flue structure of the converter waste heat boiler when the skirt is in the raised position in the embodiment of the present invention
  • Fig. 3 is the structural representation of skirt cover in the embodiment of the present invention.
  • Fig. 4 is the enlarged schematic diagram of part I in Fig. 3;
  • Fig. 5 is the top view of skirt cover in the embodiment of the present invention.
  • Fig. 6 is a schematic structural view of a water cooling ring in an embodiment of the present invention.
  • Figure 7 is an enlarged schematic view of part A in Figure 6;
  • Fig. 8 is an enlarged schematic diagram of part B in Fig. 6;
  • Fig. 9 is a top view of the water cooling ring in the embodiment of the present invention.
  • the present embodiment provides a converter waste heat boiler flue, which includes a flue mouth section flue 3, a skirt cover 1 and a water cooling ring 2.
  • the bottom of the flue 3 is nested in the heat receiving pipe 18 of the water cooling ring 2, and there is a certain gap between the outer wall of the furnace mouth section flue 3 and the inner wall of the heat receiving pipe 18.
  • the skirt cover 1 has a bell-shaped heat receiving pipe 2 8.
  • the bottom of the skirt 1 is covered on the converter mouth 7, which can seal the flue gas to a certain extent, and reduce the overflow of flue gas during the converter smelting process; when the furnace needs to be shaken, the skirt 1 is lifted to the cover position (as shown in Figure 2).
  • the converter waste heat boiler flue provided by this embodiment has a simple structure. Through the design of the skirt structure and arrangement, the sealing problem between the skirt and the flue mouth section is effectively solved, and the maintenance workload is small, safe and reliable.
  • the furnace port camlet 3 includes heating tube 3 5, water entry box 3: 6, and outlets.
  • the water connected box 3: 6 and the outlet box three 4 are connected to the lower and upper parts of the heating tube 3 5 respectively; optimized, the oxygen gun plug in the furnace of the furnace section, the inlet of the vice oxygen gun input, and the addition of the water -cooled fixture can be set to use it. Ensure the cooling effect of oxygen guns, auxiliary oxygen guns and feeding mouths.
  • the third heated pipe 5 includes a vertical section and an inclined section, the vertical section is located outside the heated pipe one 18, the inclined section is located inside the heated pipe one 18, and the inclined section has a bell mouth structure, and the inclined section has double walls arranged inside and outside, the inner wall of which is an inclined surface, and the outer wall is a vertical surface, and a concentric annular chamber is formed between the outer wall and the inner wall of the water cooling ring 2.
  • the water cooling ring 2 includes a heated pipe-18, a water inlet header-17 and a water outlet header-19, the heated pipe-18 is arranged in a ring shape, the inner wall of the heated pipe-18 is vertical, and a concentric annular chamber is formed between the heated pipe-18 and the outer wall of the heated pipe 35 of the flue 3 of the furnace mouth section, and the water inlet-17 and the water outlet-19 are arranged on the heated pipe
  • the outer side of the first 18, and the water inlet header 17 and the water outlet header 19 are arranged symmetrically, the water inlet end of the heating pipe 18 is connected to the water inlet header 17, and the water outlet end of the heating pipe 18 is connected to the water outlet header 19; further, the heating pipe 18 is a ring structure with the same inner diameter in the height direction, and the inner and outer walls of the heating pipe 18 are smooth walls.
  • the skirt 1 includes heating pipe 2 8, water inlet box 2 9, outlets 2 11, and promoting guidance components 10.
  • the interval between the water connecting box 2 11 and the water inlet box 2 9, and the diameter of the water inlet box 2 9 is larger than the diameter of the water joint box 2 11 and the water pilot box 2 9.
  • the water connection box 29 is connected, and the output end of the heating tube 28 is connected to the water connection box 2 11.
  • the promotion of the guidance component 10 is used to control the improvement and decline of the skirt 1.
  • the water inlet end and the water outlet end of the heating pipe 2 8 are located at the bottom of the heating pipe 2 8, and the water inlet end and the water outlet end of the heating pipe 2 8 are provided with an outwardly extending bending section 16, which is connected to the water inlet header 9 and the water outlet header 2 11 through the bending section 16, so that the cooling water in the heating pipe 8 of the skirt cover adopts a way of running up and down to use the waste heat of the high-temperature flue gas, which improves the waste heat utilization rate.
  • the structural design further improves the effect of the skirt cover 1 in sealing smoke.
  • the top of the heat receiving pipe 2 8 has an outward expansion section 15 that gradually expands to the outside.
  • the external expansion section 15 Through the design of the external expansion section 15, a certain distance can be maintained between the heat receiving pipe 2 8 and the inner wall of the water cooling ring 2 and the outer wall of the flue 3 of the furnace mouth section, which further plays a guiding role when the skirt cover 1 is raised and lowered.
  • the lifting guide assembly 10 can be designed into multiple groups, which are arranged at equal intervals along the two to eight circumferential directions of the heat receiving pipes.
  • four groups of lifting guide assemblies 10 are provided; during the lifting or lowering process of the skirt cover 1, multiple groups of lifting guide assemblies 10 simultaneously provide an active force to the skirt cover 1 to ensure the stability of the skirt cover 1 in the process of lifting or lowering.
  • the lifting guide assembly 10 includes a fixed bracket 12, a lifting driver (not shown in the figure) and a lifting power transmission member 13.
  • the heating pipe 2 8, the water inlet header 9 and the water outlet header 11 are all fixedly connected to the fixing bracket 12, and the lifting driver drives the fixing bracket 12 to move up and down along the height direction of the water cooling ring 2 through the lifting power transmission part 13, thereby controlling the lifting and lowering of the skirt 1.
  • the hoisting device or hydraulic device can be selected as the lifting driving part, and the lifting guide chain or lifting rod can be selected as the lifting power transmission part 13, but the specific selection is not limited thereto.
  • the lifting guide assembly 10 further includes a guide wheel 14, the guide wheel 14 is fixedly installed on the fixed bracket 12, and the guide wheel 14 is arranged close to the outer wall of the water cooling ring 2, and the setting of the guide wheel 14 further ensures the stability of the skirt 1 during lifting.
  • the converter waste heat boiler flue provided by the present invention has a simple structure, and the skirt is movably arranged between the inner wall of the water cooling ring and the outer wall of the flue at the furnace mouth section.
  • the inner wall of the water cooling ring and the outer wall of the flue mouth of the furnace mouth section can guide the skirt when it is lifted, and can also play a certain role in sealing the flue gas, reducing the overflow of flue gas, and greatly reducing the maintenance workload.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

A flue of a converter waste heat boiler, the flue comprising a furnace mouth section flue (3), a skirt (1) and a water cooling ring (2), wherein the furnace mouth section flue (3) is mounted in a high-rise frame above a converter, the water cooling ring (2) has a heating tube I (18), which is annularly arranged, the bottom of the furnace mouth section flue (3) is nested in the heating tube I (18) of the water cooling ring, and a certain gap is reserved between an outer side wall of the furnace mouth section flue (3) and an inner side wall of the heating tube I (18); and the skirt (1) has a heating tube II (8) in the shape of a horn mouth, the heating tube II (8) is arranged in the gap reserved between the furnace mouth section flue (3) and the heating tube I (18), and the heating tube II (8) is vertically movable in the gap. In the present invention, the structure of the flue of a converter waste heat boiler is simple, the skirt (1) is movably arranged between an inner wall of the water cooling ring (2) and an outer wall of the furnace mouth section flue (3), and by means of the inner wall of the water cooling ring (2) and the outer wall of the furnace mouth section flue (3), a guide function during the lifting of the skirt (1) can be achieved, and the aim of sealing flue gas to a certain extent can also be achieved, thereby reducing overflow of the flue gas, and greatly reducing the maintenance workload.

Description

一种转炉余热锅炉烟道A converter waste heat boiler flue 技术领域technical field

本发明属于余热锅炉技术领域,具体涉及一种转炉余热锅炉烟道。The invention belongs to the technical field of waste heat boilers, and in particular relates to a waste heat boiler flue of a converter.

背景技术Background technique

转炉汽化烟道是为了回收转炉炼钢过程中产生的高温烟气的显热,将烟气降低到一定温度后送入后续除尘系统。由于转炉吹炼过程中会产生大量高温烟气,烟温通常会高达2000℃,而且转炉内反应激烈,还有溅渣的风险。转炉吹氧的时候为了防止吸入空气造成煤气燃烧需要降下裙罩,在转炉摇炉的时候需要提升裙罩,为了防止裙罩被烧坏并且回收烟气余热,裙罩采用水冷结构。传统裙罩和炉口段烟道采用蒸汽密封、氮气密封或者机械密封,其中,蒸汽密封和氮气密封都会造成能源的浪费,机械密封结构复杂,而且密封件属于易损件,维护工作量大。The converter vaporization flue is to recover the sensible heat of the high-temperature flue gas generated in the converter steelmaking process, and to reduce the flue gas to a certain temperature before sending it to the subsequent dust removal system. Due to the large amount of high-temperature flue gas generated during the converter blowing process, the flue gas temperature is usually as high as 2000 ° C, and the reaction in the converter is intense, and there is a risk of slag splashing. When the converter is blowing oxygen, it is necessary to lower the skirt cover to prevent gas combustion caused by inhaling air, and to lift the skirt cover when the converter is shaking. In order to prevent the skirt cover from being burned and recover the waste heat of the flue gas, the skirt cover adopts a water-cooled structure. Traditionally, the skirt cover and the flue of the furnace mouth section adopt steam seal, nitrogen seal or mechanical seal. Among them, steam seal and nitrogen seal will cause waste of energy. The mechanical seal structure is complex, and the seal is a vulnerable part, and the maintenance workload is heavy.

发明内容Contents of the invention

本发明的目的是提供一种转炉余热锅炉烟道,至少可以解决现有技术中存在的部分缺陷。The purpose of the present invention is to provide a converter waste heat boiler flue, which can at least solve some of the defects in the prior art.

为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:

一种转炉余热锅炉烟道,包括炉口段烟道、裙罩和水冷环,所述炉口段烟道安装在转炉上方的高层框架内,所述水冷环具有呈环形布置的受热管一,所述炉口段烟道的底部嵌套于水冷环的受热管一内,且炉口段烟道外侧壁与受热管一内侧壁之间留有一定间隙,所述裙罩具有呈喇叭口形状的受热管二,所述受热管二布置于炉口段烟道与受热管一之间留有的间隙空间内,且受热管二可在该间隙空间内上下移动。A converter waste heat boiler flue, comprising a flue mouth section flue, a skirt cover and a water cooling ring. The mouth section flue is installed in a high-rise frame above the converter. The water cooling ring has a heat receiving tube 1 arranged in a ring shape. In the gap space reserved between the channel and the first heating tube, the second heating tube can move up and down in the gap space.

进一步的,所述水冷环包括受热管一、进水联箱一和出水联箱一,所述进水联箱一和出水联箱一均设置于受热管一的外侧,且进水联箱一和出 水联箱一对称布置。Further, the water-cooling ring includes a heat receiving pipe 1, a water inlet header 1 and a water outlet header 1, the water inlet header 1 and the water outlet header 1 are arranged outside the heat receiving pipe 1, and the water inlet header 1 and the water outlet header 1 are arranged symmetrically.

进一步的,所述受热管一为高度方向内径一致的环状结构,且受热管一的内外壁均为光滑壁面。Further, the heat receiving pipe 1 is an annular structure with the same inner diameter in the height direction, and the inner and outer walls of the heat receiving pipe 1 are smooth walls.

进一步的,所述裙罩包括受热管二、进水联箱二、出水联箱二和提升导向组件,所述出水联箱二和进水联箱二上下间隔布置,且进水联箱二的直径大于出水联箱二的直径,所述出水联箱二和进水联箱二均位于水冷环的受热管一外侧,所述受热管二竖向布置,受热管二的进水端与进水联箱二连接,受热管二的出水端与出水联箱二连接。Further, the skirt cover includes heating pipe 2, water inlet header 2, water outlet header 2 and a lifting guide assembly. The outlet water header 2 and water inlet header 2 are arranged at intervals up and down, and the diameter of the water inlet header 2 is larger than the diameter of the water outlet header 2. Both the outlet water header 2 and the water inlet header 2 are located outside the heating pipe 1 of the water cooling ring. The heating pipe 2 is arranged vertically. Header two connections.

进一步的,所述提升导向组件设有多组,沿受热管二周向等间距布置。Further, there are multiple sets of lifting guide assemblies arranged at equal intervals along the two circumferential directions of the heat receiving tube.

进一步的,所述提升导向组件包括固定支架、升降驱动件和升降动力传输件,所述受热管二、进水联箱二和出水联箱二均固定连接于固定支架上,所述升降驱动件通过升降动力传输件带动固定支架沿水冷环的高度方向升降运动。Further, the lifting guide assembly includes a fixed bracket, a lifting driving part and a lifting power transmission part, the heat receiving pipe 2, the water inlet header 2 and the water outlet header 2 are all fixedly connected to the fixing bracket, and the lifting driving part drives the fixed bracket to move up and down along the height direction of the water cooling ring through the lifting power transmission part.

进一步的,所述提升导向组件还包括导轮,所述导轮固定安装于固定支架上,且导轮紧贴所述水冷环外壁布置。Further, the lifting guide assembly further includes a guide wheel, the guide wheel is fixedly installed on the fixed bracket, and the guide wheel is arranged close to the outer wall of the water cooling ring.

进一步的,所述受热管二的顶部具有向外侧呈渐扩状延伸的外扩段。Further, the top of the heat receiving tube 2 has an outward expansion section extending gradually outward.

进一步的,所述炉口段烟道包括受热管三、进水联箱三和出水联箱三,所述进水联箱三和出水联箱三分别连接于受热管三的下部和上部。Further, the flue at the furnace mouth section includes a heating pipe 3, a water inlet header 3 and a water outlet header 3, and the water inlet header 3 and the water outlet header 3 are respectively connected to the lower part and the upper part of the heating pipe 3.

进一步的,所述受热管三包括竖直段和倾斜段,所述竖直段位于受热管一外部,所述倾斜段位于受热管一内部,倾斜段呈喇叭口结构,所述倾斜段具有内外布置的双层壁,其外壁为垂直面,内壁为斜面。Further, the heat receiving pipe three includes a vertical section and an inclined section, the vertical section is located outside the heat receiving pipe one, the inclined section is located inside the heat receiving pipe one, the inclined section has a bell mouth structure, and the inclined section has double walls arranged inside and outside, the outer wall of which is a vertical surface, and the inner wall is an inclined surface.

与现有技术相比,本发明的有益效果:Compared with prior art, the beneficial effect of the present invention:

本发明提供的这种转炉余热锅炉烟道结构简单,将裙罩活动设置于水冷环内壁和炉口段烟道外壁之间,通过水冷环内壁和炉口段烟道外壁可以起到对裙罩提升时的导向作用,也可以起到一定密封烟气的作用,减少烟气外溢,大大减小了维护工作量。The converter waste heat boiler flue provided by the present invention has a simple structure. The skirt cover is movably arranged between the inner wall of the water cooling ring and the outer wall of the flue mouth section flue. The inner wall of the water cooling ring and the outer wall of the flue mouth section flue can guide the skirt when it is lifted, and can also play a certain role in sealing the flue gas, reducing the overflow of flue gas, and greatly reducing the maintenance workload.

以下将结合附图对本发明做进一步详细说明。The present invention will be described in further detail below in conjunction with the accompanying drawings.

附图说明Description of drawings

图1是本发明实施例中裙罩位于降罩位时的转炉余热锅炉烟道结构示意图;Fig. 1 is a schematic diagram of the flue structure of the converter waste heat boiler when the skirt cover is in the down cover position in the embodiment of the present invention;

图2是本发明实施例中裙罩位于升罩位时的转炉余热锅炉烟道结构示意图;Fig. 2 is a schematic diagram of the flue structure of the converter waste heat boiler when the skirt is in the raised position in the embodiment of the present invention;

图3是本发明实施例中裙罩的结构示意图;Fig. 3 is the structural representation of skirt cover in the embodiment of the present invention;

图4是图3中I部放大示意图;Fig. 4 is the enlarged schematic diagram of part I in Fig. 3;

图5是本发明实施例中裙罩的俯视图;Fig. 5 is the top view of skirt cover in the embodiment of the present invention;

图6是本发明实施例中水冷环的结构示意图;Fig. 6 is a schematic structural view of a water cooling ring in an embodiment of the present invention;

图7是图6中A部放大示意图;Figure 7 is an enlarged schematic view of part A in Figure 6;

图8是图6中B部放大示意图;Fig. 8 is an enlarged schematic diagram of part B in Fig. 6;

图9是本发明实施例中水冷环的俯视图。Fig. 9 is a top view of the water cooling ring in the embodiment of the present invention.

附图标记说明:1、裙罩;2、水冷环;3、炉口段烟道;4、出水联箱三;5、受热管三;6、进水联箱三;7、转炉口;8、受热管二;9、进水联箱二;10、提升导向组件;11、出水联箱二;12、固定支架;13、升降动力传输件;14、导轮;15、外扩段;16、弯折段;17、进水联箱一;18、受热管一;19、出水联箱一。Explanation of reference numerals: 1, skirt cover; 2, water cooling ring; 3, flue of furnace mouth section; 4, water outlet header three; 5, heating pipe three; 6, water inlet header three; 7, converter mouth; 8, heating pipe two; One water header; 18, one heating pipe; 19, one water outlet header.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方 位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the orientations or positional relationships indicated by the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and so on are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation , and therefore cannot be construed as a limitation of the present invention.

术语“一”、“二”、“三”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“一”、“二”、“三”的特征可以明示或者隐含地包括一个或者更多个该特征;在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。The terms "a", "two", and "three" are used for descriptive purposes only, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Therefore, the features defined as "a", "two", and "three" may explicitly or implicitly include one or more of these features; in the description of the present invention, unless otherwise specified, "plurality" means two or more than two.

如图1、图2、图3和图6所示,本实施例提供了一种转炉余热锅炉烟道,包括炉口段烟道3、裙罩1和水冷环2,所述炉口段烟道3安装在转炉上方的高层框架内,所述水冷环2通过法兰安装在炉口段烟道3底部,所述水冷环2具有呈环形布置的受热管一18,受热管一18的内径稍大于炉口段烟道3外壁的内径,所述炉口段烟道3的底部嵌套于水冷环2的受热管一18内,且炉口段烟道3外侧壁与受热管一18内侧壁之间留有一定间隙,所述裙罩1具有呈喇叭口形状的受热管二8,所述受热管二8布置于炉口段烟道3与受热管一18之间留有的间隙空间内,且受热管二8可在该间隙空间内上下移动;在转炉吹氧时,裙罩1下降至降罩位(如图1所示),裙罩1底部罩盖于转炉口7上,可以起到一定密封烟气的作用,减少转炉冶炼过程中烟气外溢;在需要摇炉时,裙罩1提升至升罩位(如图2所示),由于将裙罩1的受热管二8布置在水冷环2的受热管一18和炉口段烟道3外侧之间,从而可利用水冷环2内壁和炉口段烟道3外壁对裙罩1的升降起到导向作用。本实施例提供的这种转炉余热锅炉烟道结构简单,通过对裙罩结构及布置方式的设计,有效解决了裙罩和炉口段烟道之间密封问题,而且维护工作量小,安全可靠。As shown in Fig. 1, Fig. 2, Fig. 3 and Fig. 6, the present embodiment provides a converter waste heat boiler flue, which includes a flue mouth section flue 3, a skirt cover 1 and a water cooling ring 2. The bottom of the flue 3 is nested in the heat receiving pipe 18 of the water cooling ring 2, and there is a certain gap between the outer wall of the furnace mouth section flue 3 and the inner wall of the heat receiving pipe 18. The skirt cover 1 has a bell-shaped heat receiving pipe 2 8. 1), the bottom of the skirt 1 is covered on the converter mouth 7, which can seal the flue gas to a certain extent, and reduce the overflow of flue gas during the converter smelting process; when the furnace needs to be shaken, the skirt 1 is lifted to the cover position (as shown in Figure 2). The converter waste heat boiler flue provided by this embodiment has a simple structure. Through the design of the skirt structure and arrangement, the sealing problem between the skirt and the flue mouth section is effectively solved, and the maintenance workload is small, safe and reliable.

细化的实施方式,如图1和图2所示,所述炉口段烟道3包括受热管三5、进水联箱三6和出水联箱三4,所述进水联箱三6和出水联箱三4分别连接于受热管三5的下部和上部;优化的,可在炉口段烟道3上的氧枪 插入口、副氧枪插入口以及加料口均设置水冷夹套,以保证氧枪、副氧枪和下料口的冷却效果。具体的,所述受热管三5包括竖直段和倾斜段,所述竖直段位于受热管一18外部,所述倾斜段位于受热管一18内部,倾斜段呈喇叭口结构,所述倾斜段具有内外布置的双层壁,其内壁为斜面,外壁为垂直面,该外壁与水冷环2内壁之间形成同心环状腔室。Refined embodiments, as shown in Figure 1 and Figure 2, the furnace port camlet 3 includes heating tube 3 5, water entry box 3: 6, and outlets. The water connected box 3: 6 and the outlet box three 4 are connected to the lower and upper parts of the heating tube 3 5 respectively; optimized, the oxygen gun plug in the furnace of the furnace section, the inlet of the vice oxygen gun input, and the addition of the water -cooled fixture can be set to use it. Ensure the cooling effect of oxygen guns, auxiliary oxygen guns and feeding mouths. Specifically, the third heated pipe 5 includes a vertical section and an inclined section, the vertical section is located outside the heated pipe one 18, the inclined section is located inside the heated pipe one 18, and the inclined section has a bell mouth structure, and the inclined section has double walls arranged inside and outside, the inner wall of which is an inclined surface, and the outer wall is a vertical surface, and a concentric annular chamber is formed between the outer wall and the inner wall of the water cooling ring 2.

一种具体实施方式,如图6、图7、图8和图9所示,所述水冷环2包括受热管一18、进水联箱一17和出水联箱一19,所述受热管一18呈环形布置,受热管一18的内壁垂直,受热管一18与炉口段烟道3的受热管三5外壁之间形成同心环状腔室,所述进水联箱一17和出水联箱一19均设置于受热管一18的外侧,且进水联箱一17和出水联箱一19对称布置,受热管一18的进水端与进水联箱一17连接,受热管一18的出水端与出水联箱一19连接;进一步的,所述受热管一18为高度方向内径一致的环状结构,且受热管一18的内外壁均为光滑壁面。A specific embodiment, as shown in Fig. 6, Fig. 7, Fig. 8 and Fig. 9, the water cooling ring 2 includes a heated pipe-18, a water inlet header-17 and a water outlet header-19, the heated pipe-18 is arranged in a ring shape, the inner wall of the heated pipe-18 is vertical, and a concentric annular chamber is formed between the heated pipe-18 and the outer wall of the heated pipe 35 of the flue 3 of the furnace mouth section, and the water inlet-17 and the water outlet-19 are arranged on the heated pipe The outer side of the first 18, and the water inlet header 17 and the water outlet header 19 are arranged symmetrically, the water inlet end of the heating pipe 18 is connected to the water inlet header 17, and the water outlet end of the heating pipe 18 is connected to the water outlet header 19; further, the heating pipe 18 is a ring structure with the same inner diameter in the height direction, and the inner and outer walls of the heating pipe 18 are smooth walls.

作为一种具体实施方式,如图3、图4和图5所示,所述裙罩1包括受热管二8、进水联箱二9、出水联箱二11和提升导向组件10,所述出水联箱二11和进水联箱二9上下间隔布置,且进水联箱二9的直径大于出水联箱二11的直径,所述出水联箱二11和进水联箱二9均位于水冷环2的受热管一18外侧,所述受热管二8为若干根,竖直并排周向布置,整体形成上小下大的喇叭口形状结构,受热管二8布置于水冷环2的受热管一18内壁与炉口段烟道3的受热管三5外壁之间形成的同心环状腔室内,受热管二8的进水端与进水联箱二9连接,受热管二8的出水端与出水联箱二11连接,提升导向组件10用于控制裙罩1的提升与下降。As a specific embodiment, as shown in Figure 3, Figure 4, and Figure 5, the skirt 1 includes heating pipe 2 8, water inlet box 2 9, outlets 2 11, and promoting guidance components 10. The interval between the water connecting box 2 11 and the water inlet box 2 9, and the diameter of the water inlet box 2 9 is larger than the diameter of the water joint box 2 11 and the water pilot box 2 9. The outside of the heating tube 1 18, which is located in the water -cooled ring 2. The water connection box 29 is connected, and the output end of the heating tube 28 is connected to the water connection box 2 11. The promotion of the guidance component 10 is used to control the improvement and decline of the skirt 1.

优化的,受热管二8的进水端和出水端均位于受热管二8的底部,且受热管二8的进水端和出水端均设有向外延伸的弯折段16,通过弯折段16与进水联箱二9和出水联箱二11连接,这样冷却水在裙罩的受热管二8内采用上下迂回运行的方式对高温烟气进行余热利用,提高了余热利用率, 同时受热管二8底部这种弯折的结构设计进一步提高了裙罩1密封烟气的作用效果。Optimally, the water inlet end and the water outlet end of the heating pipe 2 8 are located at the bottom of the heating pipe 2 8, and the water inlet end and the water outlet end of the heating pipe 2 8 are provided with an outwardly extending bending section 16, which is connected to the water inlet header 9 and the water outlet header 2 11 through the bending section 16, so that the cooling water in the heating pipe 8 of the skirt cover adopts a way of running up and down to use the waste heat of the high-temperature flue gas, which improves the waste heat utilization rate. The structural design further improves the effect of the skirt cover 1 in sealing smoke.

优化的,所述受热管二8的顶部具有向外侧呈渐扩状延伸的外扩段15,通过外扩段15的设计可使得受热管二8与所述水冷环2内壁和所述炉口段烟道3外壁都保持一定的间距,进一步起到对裙罩1升降时的导向作用,也可以起到一定密封烟气的作用,减少烟气外溢。Optimally, the top of the heat receiving pipe 2 8 has an outward expansion section 15 that gradually expands to the outside. Through the design of the external expansion section 15, a certain distance can be maintained between the heat receiving pipe 2 8 and the inner wall of the water cooling ring 2 and the outer wall of the flue 3 of the furnace mouth section, which further plays a guiding role when the skirt cover 1 is raised and lowered.

具体的,如图5所示,可将所述提升导向组件10设计为多组,分别沿受热管二8周向等间距布置,本实施例中提升导向组件10设有四组;裙罩1在提升或下降过程中,通过多组提升导向组件10同时对裙罩1提供作用力,保证裙罩1提升或下降过程的稳定性。Specifically, as shown in Figure 5, the lifting guide assembly 10 can be designed into multiple groups, which are arranged at equal intervals along the two to eight circumferential directions of the heat receiving pipes. In this embodiment, four groups of lifting guide assemblies 10 are provided; during the lifting or lowering process of the skirt cover 1, multiple groups of lifting guide assemblies 10 simultaneously provide an active force to the skirt cover 1 to ensure the stability of the skirt cover 1 in the process of lifting or lowering.

可选的实施方式,所述提升导向组件10包括固定支架12、升降驱动件(图中未标示)和升降动力传输件13,所述受热管二8、进水联箱二9和出水联箱二11均固定连接于固定支架12上,所述升降驱动件通过升降动力传输件13带动固定支架12沿水冷环2的高度方向升降运动,从而控制裙罩1的提升与下降。其中,升降驱动件可以选用卷扬装置或者液压装置,升降动力传输件13可以选用提升导链或者提升杆,当然其具体选择并不仅限于此。In an optional embodiment, the lifting guide assembly 10 includes a fixed bracket 12, a lifting driver (not shown in the figure) and a lifting power transmission member 13. The heating pipe 2 8, the water inlet header 9 and the water outlet header 11 are all fixedly connected to the fixing bracket 12, and the lifting driver drives the fixing bracket 12 to move up and down along the height direction of the water cooling ring 2 through the lifting power transmission part 13, thereby controlling the lifting and lowering of the skirt 1. Wherein, the hoisting device or hydraulic device can be selected as the lifting driving part, and the lifting guide chain or lifting rod can be selected as the lifting power transmission part 13, but the specific selection is not limited thereto.

优选的,所述提升导向组件10还包括导轮14,所述导轮14固定安装于固定支架12上,且导轮14紧贴所述水冷环2外壁布置,通过导轮14的设置进一步保证裙罩1升降过程中的稳定性。Preferably, the lifting guide assembly 10 further includes a guide wheel 14, the guide wheel 14 is fixedly installed on the fixed bracket 12, and the guide wheel 14 is arranged close to the outer wall of the water cooling ring 2, and the setting of the guide wheel 14 further ensures the stability of the skirt 1 during lifting.

综上所述,本发明提供的这种转炉余热锅炉烟道结构简单,将裙罩活动设置于水冷环内壁和炉口段烟道外壁之间,通过水冷环内壁和炉口段烟道外壁可以起到对裙罩提升时的导向作用,也可以起到一定密封烟气的作用,减少烟气外溢,大大减小了维护工作量。To sum up, the converter waste heat boiler flue provided by the present invention has a simple structure, and the skirt is movably arranged between the inner wall of the water cooling ring and the outer wall of the flue at the furnace mouth section. The inner wall of the water cooling ring and the outer wall of the flue mouth of the furnace mouth section can guide the skirt when it is lifted, and can also play a certain role in sealing the flue gas, reducing the overflow of flue gas, and greatly reducing the maintenance workload.

以上例举仅仅是对本发明的举例说明,并不构成对本发明的保护范围的限制,凡是与本发明相同或相似的设计均属于本发明的保护范围之内。The above examples are only illustrations of the present invention, and do not constitute a limitation to the protection scope of the present invention. All designs that are the same as or similar to the present invention fall within the protection scope of the present invention.

Claims (10)

一种转炉余热锅炉烟道,其特征在于:包括炉口段烟道、裙罩和水冷环,所述炉口段烟道安装在转炉上方的高层框架内,所述水冷环具有呈环形布置的受热管一,所述炉口段烟道的底部嵌套于水冷环的受热管一内,且炉口段烟道外侧壁与受热管一内侧壁之间留有一定间隙,所述裙罩具有呈喇叭口形状的受热管二,所述受热管二布置于炉口段烟道与受热管一之间留有的间隙空间内,且受热管二可在该间隙空间内上下移动。A converter waste heat boiler flue, characterized in that it includes a furnace mouth section flue, a skirt cover and a water cooling ring, the furnace mouth section flue is installed in a high-rise frame above the converter, the water cooling ring has a heat receiving pipe 1 arranged in a ring, the bottom of the furnace mouth section flue is nested in the water cooling ring heat receiving pipe 1, and there is a certain gap between the furnace mouth section flue outer wall and the heat receiving pipe 1 inner wall, the skirt has a trumpet shaped heat receiving pipe 2, and the heat receiving pipe 2 is arranged on the In the gap space left between the flue of the furnace mouth section and the first heating tube, and the second heating tube can move up and down in the gap space. 如权利要求1所述的一种转炉余热锅炉烟道,其特征在于:所述水冷环包括受热管一、进水联箱一和出水联箱一,所述进水联箱一和出水联箱一均设置于受热管一的外侧,且进水联箱一和出水联箱一对称布置。The flue of a converter waste heat boiler according to claim 1, wherein the water-cooling ring includes a heat receiving pipe 1, an inlet water header 1 and an outlet water header 1, and the water inlet header 1 and the water outlet header 1 are arranged outside the heat receiving pipe 1, and the water inlet header 1 and the water outlet header 1 are arranged symmetrically. 如权利要求1或2所述的一种转炉余热锅炉烟道,其特征在于:所述受热管一为高度方向内径一致的环状结构,且受热管一的内外壁均为光滑壁面。A converter waste heat boiler flue as claimed in claim 1 or 2, characterized in that: the heat receiving tube 1 is a ring structure with a uniform inner diameter in the height direction, and the inner and outer walls of the heat receiving tube 1 are smooth walls. 如权利要求1所述的一种转炉余热锅炉烟道,其特征在于:所述裙罩包括受热管二、进水联箱二、出水联箱二和提升导向组件,所述出水联箱二和进水联箱二上下间隔布置,且进水联箱二的直径大于出水联箱二的直径,所述出水联箱二和进水联箱二均位于水冷环的受热管一外侧,所述受热管二竖向布置,受热管二的进水端与进水联箱二连接,受热管二的出水端与出水联箱二连接。The flue of a converter waste heat boiler according to claim 1, characterized in that: the skirt cover includes heating tube 2, water inlet header 2, water outlet header 2 and a lifting guide assembly, the outlet water header 2 and water inlet header 2 are spaced up and down, and the diameter of the water inlet header 2 is larger than the diameter of the water outlet header 2, and the outlet water header 2 and the water inlet header 2 are located outside the heated pipe 1 of the water cooling ring. The second box is connected, and the water outlet end of the second heating pipe is connected with the second water outlet header. 如权利要求1所述的一种转炉余热锅炉烟道,其特征在于:所述提升导向组件设有多组,沿受热管二周向等间距布置。A converter waste heat boiler flue according to claim 1, characterized in that there are multiple sets of lifting guide assemblies arranged at equal intervals along the two circumferential directions of the heat receiving tube. 如权利要求4所述的一种转炉余热锅炉烟道,其特征在于:所述提升导向组件包括固定支架、升降驱动件和升降动力传输件,所述受热管二、进水联箱二和出水联箱二均固定连接于固定支架上,所述升降驱动件通过升降动力传输件带动固定支架沿水冷环的高度方向升降运动。A converter waste heat boiler flue as claimed in claim 4, characterized in that: the lifting guide assembly includes a fixed bracket, a lifting drive part and a lifting power transmission part, the heat receiving pipe 2, the water inlet header 2 and the water outlet header 2 are all fixedly connected to the fixed bracket, and the lifting drive part drives the fixed bracket to move up and down along the height direction of the water cooling ring through the lifting power transmission part. 如权利要求6所述的一种转炉余热锅炉烟道,其特征在于:所述提升导向组件还包括导轮,所述导轮固定安装于固定支架上,且导轮紧贴所 述水冷环外壁布置。A converter waste heat boiler flue according to claim 6, characterized in that: said lifting guide assembly further includes a guide wheel, said guide wheel is fixedly installed on a fixed bracket, and the guide wheel is arranged close to the outer wall of said water cooling ring. 如权利要求1或4所述的一种转炉余热锅炉烟道,其特征在于:所述受热管二的顶部具有向外侧呈渐扩状延伸的外扩段。A converter waste heat boiler flue as claimed in claim 1 or 4, characterized in that: the top of the heat receiving tube 2 has an outward expansion section extending outwards in a gradually expanding shape. 如权利要求1所述的一种转炉余热锅炉烟道,其特征在于:所述炉口段烟道包括受热管三、进水联箱三和出水联箱三,所述进水联箱三和出水联箱三分别连接于受热管三的下部和上部。The flue of a converter waste heat boiler according to claim 1, characterized in that: the flue at the mouth of the furnace includes a heating pipe 3, a water inlet header 3 and a water outlet header 3, and the water inlet header 3 and the water outlet header 3 are respectively connected to the lower part and the upper part of the heating pipe 3. 如权利要求9所述的一种转炉余热锅炉烟道,其特征在于:所述受热管三包括竖直段和倾斜段,所述竖直段位于受热管一外部,所述倾斜段位于受热管一内部,倾斜段呈喇叭口结构,所述倾斜段具有内外布置的双层壁,其外壁为垂直面,内壁为斜面。A converter waste heat boiler flue as claimed in claim 9, characterized in that: said heating tube three includes a vertical section and an inclined section, said vertical section is located outside heating tube one, said inclined section is located inside heating tube one, and the inclined section has a trumpet structure, said inclined section has double-layer walls arranged inside and outside, the outer wall of which is a vertical surface, and the inner wall is an inclined plane.
PCT/CN2022/112408 2022-01-20 2022-08-15 Flue of converter waste heat boiler Ceased WO2023138040A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210065832.6A CN114540570B (en) 2022-01-20 2022-01-20 A converter waste heat boiler flue
CN202210065832.6 2022-01-20

Publications (1)

Publication Number Publication Date
WO2023138040A1 true WO2023138040A1 (en) 2023-07-27

Family

ID=81670854

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/112408 Ceased WO2023138040A1 (en) 2022-01-20 2022-08-15 Flue of converter waste heat boiler

Country Status (2)

Country Link
CN (1) CN114540570B (en)
WO (1) WO2023138040A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117212783A (en) * 2023-09-27 2023-12-12 天津天保能源股份有限公司 An anti-blocking device for boiler slag discharge pipe and its application

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114540570B (en) * 2022-01-20 2023-02-28 中冶南方工程技术有限公司 A converter waste heat boiler flue

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4076223A (en) * 1975-12-31 1978-02-28 Pennsylvania Engineering Corporation Enclosure for steel converting apparatus
US4097029A (en) * 1975-12-31 1978-06-27 Pennsylvania Engineering Corporation Enclosure for steel converting apparatus
CN2910948Y (en) * 2006-06-12 2007-06-13 江阴海陆冶金设备制造有限公司 Sheath-like, water circulation chimney at converter mouth of evaporated cooling flue of steelmaking converter
CN203582891U (en) * 2013-11-27 2014-05-07 中冶东方工程技术有限公司 Movable smoke hood
CN104561438A (en) * 2015-01-29 2015-04-29 江苏永钢集团有限公司 Evaporative cooling flue of converter
CN207091455U (en) * 2017-07-19 2018-03-13 中冶南方工程技术有限公司 Aqueous vapor double containment converter movable hood
CN207091453U (en) * 2017-07-19 2018-03-13 中冶南方工程技术有限公司 Converter movable hood
CN214148863U (en) * 2020-12-08 2021-09-07 苏州海陆重工股份有限公司 Skirt cover in converter waste heat boiler
CN114540570A (en) * 2022-01-20 2022-05-27 中冶南方工程技术有限公司 A converter waste heat boiler flue

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2934251Y (en) * 2006-07-28 2007-08-15 上海梅山钢铁股份有限公司 Revolving furnace movable smoke guard sealing arrangement
DE202013104490U1 (en) * 2013-10-02 2013-10-16 Oschatz Gmbh Device for metal extraction, in particular for copper extraction
CN209759497U (en) * 2019-02-20 2019-12-10 中冶南方工程技术有限公司 Sealing device between skirt cover and moving section flue of converter waste heat boiler
CN112662837B (en) * 2020-12-08 2022-04-15 苏州海陆重工股份有限公司 Skirt cover in converter waste heat boiler

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4076223A (en) * 1975-12-31 1978-02-28 Pennsylvania Engineering Corporation Enclosure for steel converting apparatus
US4097029A (en) * 1975-12-31 1978-06-27 Pennsylvania Engineering Corporation Enclosure for steel converting apparatus
CN2910948Y (en) * 2006-06-12 2007-06-13 江阴海陆冶金设备制造有限公司 Sheath-like, water circulation chimney at converter mouth of evaporated cooling flue of steelmaking converter
CN203582891U (en) * 2013-11-27 2014-05-07 中冶东方工程技术有限公司 Movable smoke hood
CN104561438A (en) * 2015-01-29 2015-04-29 江苏永钢集团有限公司 Evaporative cooling flue of converter
CN207091455U (en) * 2017-07-19 2018-03-13 中冶南方工程技术有限公司 Aqueous vapor double containment converter movable hood
CN207091453U (en) * 2017-07-19 2018-03-13 中冶南方工程技术有限公司 Converter movable hood
CN214148863U (en) * 2020-12-08 2021-09-07 苏州海陆重工股份有限公司 Skirt cover in converter waste heat boiler
CN114540570A (en) * 2022-01-20 2022-05-27 中冶南方工程技术有限公司 A converter waste heat boiler flue

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117212783A (en) * 2023-09-27 2023-12-12 天津天保能源股份有限公司 An anti-blocking device for boiler slag discharge pipe and its application

Also Published As

Publication number Publication date
CN114540570B (en) 2023-02-28
CN114540570A (en) 2022-05-27

Similar Documents

Publication Publication Date Title
WO2023138040A1 (en) Flue of converter waste heat boiler
CN112680560B (en) Waste heat boiler in converter dry dedusting system
CN102466224B (en) Air distribution device for fluidized bed and boiler or gasifier with same
CN110608438B (en) Multistage burner, molten steel tank preheating equipment and use method thereof
CN218454146U (en) Deposition furnace for high-uniformity quartz glass
CN217103959U (en) A converter waste heat boiler flue
CN114317875B (en) Oxygen gun mouth sealing device in converter waste heat boiler
CN216898426U (en) A skirt cover for the flue of a converter waste heat boiler
CN221312484U (en) Ladle baking device based on micro negative pressure technology
CN203451556U (en) Pitch-varying flow guide structural heating pipe of evaporative cooling smoke channel for steel converter
CN218059104U (en) Cast steel pipe slow cooling pit
CN2910956Y (en) Coiled-pipe air-seal type active chimney of evaporated cooling flue of steelmaking converter
CN216047607U (en) Biomass gasification combustion furnace
CN213362642U (en) Environment-friendly high heat accumulation heating stove
CN213300856U (en) Oxygen blows converter stove top inside lining masonry structure to one side
CN212719740U (en) Multi-stage combustor and molten steel tank preheating equipment adopting same
CN210765384U (en) Exhaust-heat boiler furnace mouth section structure
CN211734168U (en) Dredging device for regenerative chamber of glass kiln
WO2021244103A1 (en) Side-blown smelting furnace
CN211451388U (en) Vault structure of hot blast stove
CN207922880U (en) A kind of side-blown converter flue outlet device
CN208067299U (en) A kind of machine side stove for Aluminum press casting apparatus
CN208042782U (en) A kind of open type cathode baking furnace furnace bottom
CN219656582U (en) Side-blown furnace baking temperature rising and slag discharging operation sharing device
CN221526609U (en) Burner and combustion furnace for oxygen-enriched combustion internal heating coal dry distillation

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22921469

Country of ref document: EP

Kind code of ref document: A1

WA Withdrawal of international application
122 Ep: pct application non-entry in european phase

Ref document number: 22921469

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE