[go: up one dir, main page]

WO2020189847A1 - Method for installing and constructing girder bridge of marine bridge - Google Patents

Method for installing and constructing girder bridge of marine bridge Download PDF

Info

Publication number
WO2020189847A1
WO2020189847A1 PCT/KR2019/006563 KR2019006563W WO2020189847A1 WO 2020189847 A1 WO2020189847 A1 WO 2020189847A1 KR 2019006563 W KR2019006563 W KR 2019006563W WO 2020189847 A1 WO2020189847 A1 WO 2020189847A1
Authority
WO
WIPO (PCT)
Prior art keywords
girder bridge
barge
bridge
lifting
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/KR2019/006563
Other languages
French (fr)
Korean (ko)
Inventor
이완복
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jd Engineering Co ltd
Original Assignee
Jd Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jd Engineering Co ltd filed Critical Jd Engineering Co ltd
Publication of WO2020189847A1 publication Critical patent/WO2020189847A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D18/00Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure

Definitions

  • the present invention relates to a method for installing a girder bridge of an offshore bridge, and more particularly, in installing a girder bridge (hanging bridge or steel bridge) between piers of an offshore bridge, it is possible to significantly shorten the number of construction and construction period as well as safe construction.
  • the present invention relates to a method of installing a girder bridge for offshore bridges that can improve workability, economy, and work safety.
  • a bridge consists of an upper structure and a lower structure made of alternating piers, and the upper structure is made of a concrete structure or a steel structure.
  • a plate block and a cross girder are used to support the plate block.
  • cross girders (hereinafter referred to as ⁇ girders'') are connected at both ends by a hanger cable hanging down from the main cable, and plate blocks that are joined to each other are placed on top of the cross girder. It forms the top of the bridge.
  • plate blocks are loaded with a barge, lifted with a huge crane (tower crane), and mounted on a girder and combined.
  • the present invention for solving the above-described conventional problems, when installing a girder bridge (hanging bridge or steel bridge) between piers of an offshore bridge, it is possible to significantly reduce the number of construction and construction period, as well as safe construction. Its purpose is to provide a girder bridge installation and construction method of offshore bridges that can improve economical efficiency and work safety.
  • a girder to be installed on a transport means provided with a loading beam for lifting on an upper surface Preparing to transfer the girder bridge for seating the bridge on the loading beam for lifting;
  • the girder bridge installation and construction method of an offshore bridge when installing a girder bridge (hanging bridge or steel bridge) between the piers of the offshore bridge, it is possible to construct a girder bridge without requiring disassembly or removal of the tower crane. Not only can the number of constructions and construction period be remarkably shortened, but also safe construction is possible, which has the effect of improving constructability, economy, and work safety.
  • FIG. 1 is a flow chart showing the construction process of the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 2 is a plan view schematically showing an implementation process of a transport step in the method for installing a girder bridge for an offshore bridge according to the present invention.
  • FIG 3 is a side view schematically showing an implementation process of a transport step in the method of installing a girder bridge for an offshore bridge according to the present invention.
  • FIG. 4 is a plan view schematically showing an implementation process of a transport step in the method of installing a girder bridge for an offshore bridge according to the present invention
  • FIG. 5 is a side view schematically showing an implementation process of a transport step in the method for installing a girder bridge of an offshore bridge according to the present invention.
  • FIG. 6 is a plan view schematically showing an implementation process of a girder bridge lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 7 is a side view schematically showing an implementation process of a girder bridge lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 8 is a plan view schematically showing an implementation process of a truss structure loading step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 9 is a side view schematically showing an implementation process of a truss structure loading step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 10 is a plan view schematically showing an implementation process of a loading beam cutting step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 11 is a side view schematically showing an implementation process of a loading beam cutting step in the method of installing a girder bridge for an offshore bridge according to the present invention.
  • FIG. 12 is a plan view schematically showing an implementation process of a girder bridge installation preparation step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 13 is a side view schematically showing an implementation process of a girder bridge installation preparation step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 14 is a plan view schematically showing an implementation process of a truss structure lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • 15 is a side view schematically showing an implementation process of a truss structure lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • 16 is a plan view schematically showing an implementation process of an installation location moving step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • 17 is a side view schematically showing an implementation process of an installation location moving step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • FIG. 18 is a side view schematically showing a girder bridge installation process at the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • 19 is a plan view schematically showing a process of moving a barge to a pier in the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • 20 is a side view schematically showing a process of moving a barge to a pier in the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • a construction method of installing a girder bridge between piers of an offshore bridge preparation for transfer of a girder bridge in which a girder bridge to be installed is seated on a loading beam for lifting in a transport means provided with a loading beam for lifting on an upper surface.
  • a girder bridge loading step of transporting the transport means to the wharf, moving to a barge berthed to the wharf, and loading a first structure comprising a loading beam for lifting on which the girder bridge is seated on the barge;
  • a girder bridge lifting step of lifting the first structure to a predetermined height from the top of the barge using a strand jack lift tower installed on the barge;
  • a loading beam for cutting the edge of the loading beam for lifting of the first structure to secure a passage for connecting the wire of the strand jack lift tower to the second structure for lifting of the second structure Cutting step;
  • a girder bridge loading step of transporting the transport means to the wharf, moving to a barge berthed to the wharf,
  • the length and width of the girder bridge are made larger than that of the transporter, which is a transport means, and the loading beam for lifting is provided on the transporter so as to traverse in the width direction of the girder bridge.
  • the girder bridge loading step is made to balance by adjusting the ballast water of the barge as the transporter enters the barge, and in the girder bridge lifting step, the support provided on the barge is positioned under the loading beam of the first structure.
  • the transporter itself descends to settle the first structure on the upper surface of the support, then berth and secure the barge so that the girder bridge is parallel to the pier, and then connect it to the loading beam for lifting using the strand jack lift tower.
  • the first structure is lifted by a predetermined height from the barge, and in the loading of the truss structure, the transport means loaded with the height compensation truss structure is moved to the barge berthed to the pier, and the lower side of the first structure is lifted by a predetermined height.
  • the transporter After the movement is completed, the transporter itself descends and the height compensation truss structure is seated on the upper surface of the support, and in the loading beam cutting step, the first structure is lowered to the upper surface of the truss structure using a strand jack lift tower.
  • a passage for lifting the second structure is secured by cutting both edges of the lifting arm for a predetermined length, and the wire of the strand jack lift tower is connected to the second structure through the secured passage.
  • the height compensation truss structure Consisting of coupling to both ends of the truss structure, is characterized in that it has a design height based on the maximum lifting height of the strand jack lift tower having a height lower than the height of the pier.
  • the preparatory step for installing the girder bridge comprises, after the loading beam cutting step, moving the barge to the side of the pier to install the girder bridge, and balancing the height of the barge to a predetermined height by adjusting the ballast water of the barge.
  • the truss structure lifting step a plurality of winches are connected to both sides of the barge and secured, and then the second structure is lifted using the strand jack lift tower of the barge, but the girder bridge of the second structure is higher than the height of the pier. It can be made to rise to a predetermined height high position.
  • the girder bridge moves the barge to the installation position of the pier while interlocking the winch on one side and the winch on the other side by using a winch connected to both sides of the barge.
  • the second structure is lowered to install both ends of the girder bridge on the installation portions of the two piers, and after separating the girder bridge from the loading beam, the loading beam and the height compensation truss structure are lowered. , It may consist of moving the barge from the installation location.
  • ... unit ... unit
  • ... module a unit that processes at least one function or operation, which is hardware, software, or hardware and It can be implemented as a combination of software.
  • Figure 1 is a flow chart showing the construction process of the girder bridge installation construction method of the offshore bridge according to the present invention
  • Figures 2 and 3 are each an implementation process of the carrying step in the girder bridge installation construction method of the offshore bridge according to the present invention
  • FIGS. 4 and 5 are a plan view and a side view schematically showing an implementation process of a transport step in the girder bridge installation construction method of an offshore bridge according to the present invention, respectively.
  • 6 and 7 are a plan view and a side view schematically showing an implementation process of a girder bridge lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention, respectively, and FIGS.
  • FIGS. 8 and 9 are respectively a sea bridge according to the present invention
  • a plan view and a side view schematically showing an implementation process of a truss structure loading step in the girder bridge installation construction method of, and FIGS. 10 and 11 are each one of a loading beam cutting step in the girder bridge installation construction method of an offshore bridge according to the present invention.
  • It is a plan view and a side view schematically showing the implementation process.
  • 12 and 13 are plan and side views, respectively, schematically showing an implementation process of a girder bridge installation preparation step in the girder bridge installation construction method of an offshore bridge according to the present invention
  • FIGS. 14 and 15 are respectively It is a plan view and a side view schematically showing an implementation process of a truss structure lifting step in the girder bridge installation construction method of a bridge, and FIGS. 16 and 17 are each of the installation location movement step in the girder bridge installation construction method of a marine bridge according to the present invention. It is a plan view and a side view schematically showing an implementation process. 18 is a side view schematically showing a girder bridge installation process at the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention, and FIGS. 19 and 20 are each a girder bridge installation construction method of an offshore bridge according to the present invention It is a plan view and a side view schematically showing the process of moving the barge to the pier in the installation completion stage.
  • the girder bridge installation construction method of an offshore bridge is a construction method of installing a girder bridge between piers of an offshore bridge, as shown in Figs. 1 to 20, in which a loading beam 110 for lifting is provided at the top.
  • a girder bridge transfer preparation step in which the manufactured girder bridge 200 of a predetermined shape is seated on the loading beam 110 for lifting in a transport means (e.g., a self-propelled modular transporter (SPMT) (S)) (S100); After completion of the transfer preparation step (S100), a transport step (S200) of transporting the transport means to the dock (or dock) (see Figs.
  • a transport means e.g., a self-propelled modular transporter (SPMT) (S)
  • S100 self-propelled modular transporter
  • the dock The girder bridge loading step (S300) of moving to the barge (B) berthed on the girder bridge 200 and loading the loading beam 110 for lifting on the barge see FIGS. 4 and 5
  • the girder bridge After completion of the loading step (S300), the girder bridge lifting step (S400) of lifting the loading beam 110 for lifting on which the girder bridge 200 is seated on the barge (B) to a predetermined height (see FIGS.
  • the height compensation truss structure 120 After moving the height compensation truss structure 120 to the lower part of the lifting loading beam 110 for lifting a predetermined height in the girder bridge lifting step (S400), the height compensation truss structure 120 for the lifting loading beam 110
  • the truss structure loading step (S500) (see FIGS. 8 and 9) to be seated on the upper surface of the truss structure; after completion of the truss structure loading step (S500), for the lifting to secure a passage for lifting the height compensation truss structure 120
  • Loading beam cutting step (S600) of cutting the edge of the loading beam 110 see FIGS.
  • a girder bridge installation preparation step (S700) (see FIGS. 12 and 13); the girder bridge installation preparation step (S 700)
  • the truss structure lifting step (S800) of lifting the height compensation truss structure 120 to raise the girder bridge 200 higher than the height of the pier P (see FIGS.
  • the installation position movement step (S900) of moving the barge (B) to the installation position of the girder bridge between the piers (P) (see FIGS. 16 and 17);
  • the height compensation truss structure 300 is lowered to install both ends of the girder bridge 200 between the piers, and then the lowered height compensation truss structure 120 (i.e. ,
  • the loading beam 110 is an installation completion step (S1000) (see Figs. 18 to 20) of moving the barge B having the truss structure 120 located on the upper surface from the installation position.
  • the transporter (S) which is a transport means, is prepared in consideration of the weight of the girder bridge (110), and the total length of the transporter (S) (in the case of a unit transporter, from front to rear)
  • the girder bridge 110 of a length longer than (total length) is raised.
  • the girder bridge 110 is composed of a girder bridge 110 having a length that is installed between the two piers (P), the girder bridge 110 has margins at both ends in the longitudinal direction and a transporter (S ).
  • a plurality of loading beams 110 for lifting crossing in the width direction of the girder bridge 110 are placed on the transporter S, and the girder bridge 110 manufactured thereon is mounted.
  • the loading beam 110 for lifting and the girder bridge 110 (hereinafter referred to as "first structure") seated on the loading beam 110 for lifting have stability in the transport and lifting process described later
  • the loading beam 110 may be temporarily fixed and seated to be easily separated from the girder bridge 110.
  • the barge (B) is transported to the docked pier.
  • the barge (B) is equipped with a plurality of strand jack lift towers (L) with a strand jack installed at the top as a lifting facility at predetermined intervals, wherein the strand jack lift tower (L) is equipped with a girder bridge (110). It is equipped with a strand jack lift tower with a height lower than the height of the pier to be used. This allows the girder bridge 110 to be easily exited in the direction opposite to the entry direction of the barge after the girder bridge 110 is installed on the pier in the installation completion step to be described later.
  • the transporter (S) carrying the first structure is moved between the strand jack lift towers (S) of the barge (B), and then, It is positioned at a predetermined movement completion position.
  • the ballast water of the barge (B) is adjusted so that the upper surface of the land pier and the upper surface of the barge (B) are almost They are on the same plane.
  • the movable support (M) installed on the barge (B) is placed under the loading beam (110) of the first structure, and then the self-propelled platform of the transporter (S) It descends through the teeth to settle the first structure on the upper surface of the movable support (M) (left figure in Fig. 7). Then, the transporter (S) is moved to the land by the barge (B) while the first structure is separated from the upper surface of the barge (B) by the mobile support (M).
  • the movable support (M) is fixed at a position having a space through which the transporter (S) can pass.
  • the barge (B) is anchored to the pier, preferably, as shown in FIG. 6, the barge (B) is docked and anchored so that the girder bridge (110) is parallel to the pier, as shown in the right figure of FIG.
  • the strand jack of the strand jack lift tower (L) is connected to the loading beam (110) to lift the first structure from the barge (B) to a predetermined height.
  • the truss structure loading step (S500) using a transporter (S) loaded with the manufactured height compensation truss structure 120, the barge docked to the pier (B) (barge equipped with a strand jack lift tower (L) having a height lower than the height of the pier) to the lower portion of the first structure (that is, the lower portion of the loading beam 110)
  • the height compensation truss structure 120 is mounted on the upper surface of the movable support M by descending through the self-elevating device of the transporter S.
  • the height compensation truss structure 120 is a structure having a height designed and manufactured in consideration of the maximum elevation height of the strand jack lift tower L having a height lower than the height of the pier.
  • the first structure is lowered using the strand jack lift tower (L), and the truss structure 120 is seated on the upper surface of the movable support (M).
  • Both edges of the lifting loading arm 110 are cut to a predetermined length to secure a passage for lifting of the height compensation truss structure 120, and the strand wire of the strand jack lift tower (L) is connected to the truss structure through the secured passage. It is coupled to both ends of 120 (see Fig. 11).
  • a structure in which a truss structure is coupled to the first structure is referred to as a second structure.
  • the barge (B) is moved toward the side of the pier (P) where the girder bridge 200 is to be installed, and the barge (B) The height of the barge (B) is balanced to a predetermined height by adjusting the ballast water.
  • This girder bridge installation preparation step (S700) may be omitted or may be executed simultaneously with the truss structure lifting step (S800).
  • the truss structure lifting step (S800) is secured by connecting a plurality of winches to both sides of the barge (B) in order to stably move the barge (B) to a position for installing the girder bridge, as shown in FIG.
  • the second structure is lifted using the strand jack lift tower (L) of the barge (B), but the girder bridge 200 of the second structure is raised to a position higher than the height of the pier (P) by a predetermined height.
  • the second structure is raised so that the girder bridge 200 is at a position approximately 2.5M higher than the upper end of the pier P.
  • the height of the strand jack lift tower (L) is lower than the height of the pier (P), but by the height of the height compensation truss structure (120) and the loading beam (110), the girder bridge (200) is the height of the pier (P) It is positioned higher.
  • the second structure is lowered to install both ends of the girder bridge 200 between the piers P and the installation portions of the two piers, and the girder bridge ( After separating 200) and the loading beam 110, the loading beam 110 and the height compensation truss structure 120 are lowered to a predetermined height as shown in FIGS. 19 and 20, that is, the height of the loading beam 110 and the height
  • the compensation truss structure 120 is lowered lower than the height of the strand jack lift tower (L) or seated on a movable support (M). Done.
  • the movement of the barge can be carried out by slowly winding and unwinding by interlocking the winch on one side and the winch on the other side by using a winch connected to both sides of the barge (B). ) It can be executed by moving itself.
  • the present invention compensates for the installation height through a height compensation truss structure even if the height of the strand jack lift tower (L) is lower than the pier, and from the installation position of the girder bridge without being disturbed by the girder bridge after the installation of the girder bridge. You can get away easily.
  • the upper part of the strand jack lift tower (L) can be removed or separated in order to lower the height of the pier, but this increases the number of processes and construction period as mentioned in the problem of the prior art, greatly increasing the cost of the bridge work.
  • the present invention has a problem with the above-described use of a strand jack lift tower (L) lower than the pier (that is, the height of the installed girder bridge). This problem was solved through the process.
  • a height compensation structure or a height of a predetermined shape in which the loading beam for lifting 110 and the height compensation truss structure 120 are integrally formed It can be formed only by the compensation truss structure itself.
  • the process of separately installing the loading beam 110 on the transporter (S) in the girder bridge transfer preparation step (S100), the process of loading the girder bridge thereon, the process of lifting the girder bridge, and loading the truss structure is omitted, and after mounting the height compensation structure on the transporter (S) in the girder bridge transfer preparation step (S100), transporting (S200), and loading the girder bridge (200) thereon.
  • the strand wire of the strand jack lift tower (L) may be connected to a height compensation structure or a height compensation truss structure to perform a girder bridge installation preparation step (S700) and subsequent processes.
  • the girder bridge installation construction method of an offshore bridge in installing a girder bridge (hanging bridge or steel bridge) between piers of an offshore bridge, the girder does not require disassembly or removal of the tower crane. Since the bridge can be constructed, the number of construction and the construction period can be remarkably shortened, as well as safe construction, which has the advantage of improving workability, economy and work safety.
  • the present invention can be used to install a girder bridge (hanging bridge or steel bridge) between the piers of the offshore bridge, the method of installing a girder bridge of an offshore bridge.
  • a girder bridge hanging bridge or steel bridge

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a method for installing and constructing a girder bridge of a marine bridge, which enables significant reduction of the number of times of construction and the period of construction as well as safe construction in installing a girder bridge (a suspension bridge or a steel bridge) between piers of a marine bridge, thereby improving workability, economy, and work safety. The present invention provides, as a construction method for installing a girder bridge between piers of a marine bridge, a method for installing and constructing a girder bridge of a marine bridge, the method including the steps of: preparing transfer of a girder bridge; loading the girder bridge; lifting the girder bridge; loading a truss structure; cutting a loading beam; preparing installation of the girder bridge; lifting the truss structure; moving the installation location; and completing the installation, wherein a strand jack lift tower equipped in a barge has a height lower than the height of the pier.

Description

해상 교량의 거더 브리지 설치 시공방법Girder bridge installation and construction method of offshore bridge

본 발명은 해상 교량의 거더 브리지 설치 시공방법에 관한 것으로, 더욱 상세하게는 해상 교량의 교각 간에 거더 브리지(행교 또는 강교)를 설치함에 있어 시공수와 시공기간을 현저히 단축할 수 있을 뿐만 아니라 안전한 시공이 가능하여 시공성과 경제성 및 작업 안전성을 향상시킬 수 있는 해상 교량의 거더 브리지 설치 시공방법에 관한 것이다.The present invention relates to a method for installing a girder bridge of an offshore bridge, and more particularly, in installing a girder bridge (hanging bridge or steel bridge) between piers of an offshore bridge, it is possible to significantly shorten the number of construction and construction period as well as safe construction. The present invention relates to a method of installing a girder bridge for offshore bridges that can improve workability, economy, and work safety.

일반적으로, 교량은 상부구조와 교각과 교대로 이루어지는 하부구조로 이루어지는데, 상기 상부구조는 콘크리트구조물이나 철골구조물로 이루어진다.In general, a bridge consists of an upper structure and a lower structure made of alternating piers, and the upper structure is made of a concrete structure or a steel structure.

상기 철골구조물로 이루어지는 교량의 경우 플레이트 블럭과 상기 플레이트 블럭을 지지하기 위해서는 크로스 거더(cross girder)로 이루어진다.In the case of a bridge made of the steel structure, a plate block and a cross girder are used to support the plate block.

특히 현수교 및 사장교의 경우 크로스 거더(이하 '거더'라 한다)는 주케이블에 매달려 아래로 드리워지는 행어(hanger) 케이블에 의해 양단이 결합되고 그 위에 서로 맞대어 결합되는 플레이트 블럭들이 얹혀 순차적으로 연결되어 교량 상판을 이루게 된다.In particular, in the case of suspension bridges and cable-stayed bridges, cross girders (hereinafter referred to as ``girders'') are connected at both ends by a hanger cable hanging down from the main cable, and plate blocks that are joined to each other are placed on top of the cross girder. It forms the top of the bridge.

또한, 종래의 현수교 및 사장교의 설치를 위해서는 바지선으로 플레이트 블럭들을 실어와서 거대한 기중기(타워 크레인)로 이를 들어올려 거더에 올려놓고 결합하는 방식을 사용하고 있다.In addition, for the installation of conventional suspension bridges and cable-stayed bridges, plate blocks are loaded with a barge, lifted with a huge crane (tower crane), and mounted on a girder and combined.

그러나 종래 교량 시공 방법에 있어서 교각(pier)과 교각 사이에 거더 브리지(girder bridge: 행교)를 설치할 때, 바지선에 거더 브리지를 싣고 이를 교각 사이에 리프팅하여 설치하기 위해서는 바지선에서 거더를 잭업(Jack Up)하여 올려 설치하거나 바지선에 리프팅 타워를 설치하여 리프팅하여 거더를 설치해야만 한다. 이때 리프팅 타워의 높이가 타워 크레인의 높이가 교각의 높이보다 높아야 하고, 이에 따라 거더 브리지의 설치 후 바지선이 빠져나오기 위해서는 타워 크레인을 교각 높이보다 낮게 제거하거나 분리해야 하며, 이는 결국 공정수와 공사 기간이 증가하고, 이에 따라 교량 작업의 비용을 크게 상승시키는 문제점이 있었다.However, in the conventional bridge construction method, when installing a girder bridge between the pier and the pier, jack up the girder from the barge to install the girder bridge by loading it on the barge and lifting it between the piers. ), or by installing a lifting tower on a barge and lifting to install a girder. At this time, the height of the lifting tower must be higher than the height of the tower crane, and accordingly, in order for the barge to escape after the installation of the girder bridge, the tower crane must be removed or removed lower than the height of the pier. This increases, and thus there is a problem of significantly increasing the cost of the bridge work.

또한, 이러한 해상에서의 리프트 타워의 해제 작업 또는 제거 작업은 해상이라는 특성상 안전사고 발생을 초래할 가능성이 현저히 증가하는 문제점이 있으며, 이에 따라 해상에서의 교량 시공 방법에 대한 보다 효율적인 시공 방법에 대한 연구가 절실한 상황이다.In addition, the lifting or removal of the lift tower at sea has a problem that the possibility of causing a safety accident is significantly increased due to the nature of the sea, and accordingly, research on a more efficient construction method for a bridge construction method at sea It is a desperate situation.

따라서, 상기한 종래의 문제점을 해결하기 위한 본 발명은, 해상 교량의 교각 간에 거더 브리지(행교 또는 강교)를 설치함에 있어 시공수와 시공기간을 현저히 감소시킬 수 있을 뿐만 아니라 안전한 시공이 가능하여 시공성과 경제성 및 작업 안전성을 향상시킬 수 있는 해상 교량의 거더 브리지 설치 시공방법을 제공하는데 그 목적이 있다.Therefore, the present invention for solving the above-described conventional problems, when installing a girder bridge (hanging bridge or steel bridge) between piers of an offshore bridge, it is possible to significantly reduce the number of construction and construction period, as well as safe construction. Its purpose is to provide a girder bridge installation and construction method of offshore bridges that can improve economical efficiency and work safety.

본 발명의 해결과제는 이상에서 언급한 것들에 한정되지 않으며, 언급되지 아니한 다른 해결과제들은 아래의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The problem of the present invention is not limited to those mentioned above, and other problems that are not mentioned will be clearly understood by those skilled in the art from the following description.

상기 본 발명의 목적들 및 다른 특징들을 달성하기 위한 본 발명의 일 관점에 따르면, 해상 교량의 교각 사이에 거더 브리지를 설치하는 시공 방법으로서, 상면에 리프팅용 로딩빔이 마련된 운반 수단에, 설치할 거더브리지를 리프팅용 로딩빔에 안착시키는 거더브리지 이송준비 단계; 상기 거더브리지 이송준비 단계 후, 운반 수단을 부두로 운반하고, 부두에 접안된 바지선으로 이동하여 거더브리지가 안착된 리프팅용 로딩빔으로 이루어지는 제1 구조물을 바지선에 로딩시키는 거더브리지 로딩 단계; 상기 거더브리지 로딩 단계 후, 상기 바지선에 설비된 스트랜드잭 리프트타워를 이용하여 상기 제1 구조물을 바지선 상면에서 소정 높이 리프팅하는 거더브리지 리프팅 단계; 소정 높이 리프팅된 상기 제1 구조물의 하부로 높이보상 트러스구조물을 이동 위치시킨 후, 상기 제1 구조물을 높이보상 트러스 구조물의 상면에 안착시켜 이루어지는 제2 구조물을 로딩하는 트러스구조물 로딩 단계; 상기 트러스구조물 로딩 단계 후, 상기 제2 구조물의 리프팅을 위하여 상기 스트랜드잭 리프트타워의 와이어를 제2 구조물에 연결하기 위한 통로를 확보하도록 상기 제1 구조물의 리프팅용 로딩빔의 가장자리를 컷팅하는 로딩빔 컷팅 단계; 상기 로딩빔 컷팅 단계 후, 거더브리지를 설치할 교각 측으로 바지선을 이동시키고, 이동된 위치에서 바지선을 수면에 대하여 소정 높이로 밸런싱하는 거더브리지 설치 준비 단계; 상기 거더브리지 설치 준비 단계 후, 상기 거더브리지를 교각의 높이보다 높은 위치까지 상기 제2 구조물을 리프팅하는 트러스구조물 리프팅 단계; 상기 트러스구조물 리프팅 단계 후, 바지선을 거더브리지 설치위치로 이동시키는 설치위치 이동 단계; 및 상기 설치위치 이동 단계 후, 상기 제2 구조물을 하강시켜 교각 사이에 거더브리지의 양단부를 두 교각에 설치된 다음, 상기 거더브리지가 제거된 제2 구조물을 갖는 바지선을 설치 위치로부터 이동시키는 설치 완료 단계;를 포함하며, 상기 바지선에 설비되는 스트랜드잭 리프트타워는 상기 교각의 높이보다 낮은 높이를 갖고 이루어지는 것을 특징으로 하는 해상 교량의 거더 브리지 설치 시공방법이 제공된다.According to an aspect of the present invention for achieving the objects and other features of the present invention, as a construction method of installing a girder bridge between piers of a sea bridge, a girder to be installed on a transport means provided with a loading beam for lifting on an upper surface Preparing to transfer the girder bridge for seating the bridge on the loading beam for lifting; After the girder bridge transfer preparation step, a girder bridge loading step of transporting the transport means to the wharf, moving to a barge berthed to the wharf, and loading a first structure comprising a loading beam for lifting on which the girder bridge is seated on the barge; After the loading of the girder bridge, a girder bridge lifting step of lifting the first structure to a predetermined height from the top of the barge using a strand jack lift tower installed on the barge; A truss structure loading step of loading a second structure formed by placing the first structure on the upper surface of the height compensation truss structure after moving and positioning the height compensation truss structure below the first structure lifted by a predetermined height; After the loading of the truss structure, a loading beam for cutting the edge of the loading beam for lifting of the first structure to secure a passage for connecting the wire of the strand jack lift tower to the second structure for lifting of the second structure Cutting step; After the loading beam cutting step, a girder bridge installation preparation step of moving the barge toward the pier to install the girder bridge, and balancing the barge at a predetermined height with respect to the water surface at the moved position; A truss structure lifting step of lifting the second structure to a position higher than the height of the pier after the girder bridge installation preparation step; After the truss structure lifting step, the installation position moving step of moving the barge to the girder bridge installation position; And after the step of moving the installation position, the second structure is lowered to install both ends of the girder bridge between the piers, and then the barge having the second structure from which the girder bridge has been removed is moved from the installation position. Including;, a strand jack lift tower installed in the barge is provided with a method for installing a girder bridge of an offshore bridge, characterized in that it has a height lower than that of the pier.

본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법은, 해상 교량의 교각 간에 거더 브리지(행교 또는 강교)를 설치함에 있어, 타워 크레인의 분해 또는 제거 작업을 필요로 하지 않고 거더 브리지를 시공할 수 있어 시공수와 시공기간을 현저히 단축할 수 있을 뿐만 아니라 안전한 시공이 가능하여 시공성과 경제성 및 작업 안전성을 향상시킬 수 있는 효과가 있다.The girder bridge installation and construction method of an offshore bridge according to the present invention, when installing a girder bridge (hanging bridge or steel bridge) between the piers of the offshore bridge, it is possible to construct a girder bridge without requiring disassembly or removal of the tower crane. Not only can the number of constructions and construction period be remarkably shortened, but also safe construction is possible, which has the effect of improving constructability, economy, and work safety.

본 발명의 효과는 이상에서 언급된 것들에 한정되지 않으며, 언급되지 아니한 다른 해결과제들은 아래의 기재로부터 당업자에게 명확하게 이해되어 질 수 있을 것이다.The effects of the present invention are not limited to those mentioned above, and other problems that are not mentioned will be clearly understood by those skilled in the art from the following description.

도 1은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법의 시공 과정을 나타내는 플로차트이다.1 is a flow chart showing the construction process of the girder bridge installation construction method of an offshore bridge according to the present invention.

도 2는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 운반 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.2 is a plan view schematically showing an implementation process of a transport step in the method for installing a girder bridge for an offshore bridge according to the present invention.

도 3은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 운반 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.3 is a side view schematically showing an implementation process of a transport step in the method of installing a girder bridge for an offshore bridge according to the present invention.

도 4는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 운반 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다4 is a plan view schematically showing an implementation process of a transport step in the method of installing a girder bridge for an offshore bridge according to the present invention

도 5는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 운반 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.5 is a side view schematically showing an implementation process of a transport step in the method for installing a girder bridge of an offshore bridge according to the present invention.

도 6은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 거더브리지 리프팅 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.6 is a plan view schematically showing an implementation process of a girder bridge lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 7은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 거더브리지 리프팅 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.7 is a side view schematically showing an implementation process of a girder bridge lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 8은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 트러스 구조물 로딩 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.8 is a plan view schematically showing an implementation process of a truss structure loading step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 9는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 트러스 구조물 로딩 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.9 is a side view schematically showing an implementation process of a truss structure loading step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 10은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 로딩빔 컷팅 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.10 is a plan view schematically showing an implementation process of a loading beam cutting step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 11은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 로딩빔 컷팅 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.11 is a side view schematically showing an implementation process of a loading beam cutting step in the method of installing a girder bridge for an offshore bridge according to the present invention.

도 12는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 거더브리지 설치 준비 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.12 is a plan view schematically showing an implementation process of a girder bridge installation preparation step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 13은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 거더브리지 설치 준비 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.13 is a side view schematically showing an implementation process of a girder bridge installation preparation step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 14는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 트러스구조물 리프팅 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.14 is a plan view schematically showing an implementation process of a truss structure lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 15는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 트러스구조물 리프팅 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.15 is a side view schematically showing an implementation process of a truss structure lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 16은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치위치 이동 단계의 일 실시 과정을 도식화하여 나타내는 평면도이다.16 is a plan view schematically showing an implementation process of an installation location moving step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 17은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치위치 이동 단계의 일 실시 과정을 도식화하여 나타내는 측면도이다.17 is a side view schematically showing an implementation process of an installation location moving step in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 18은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치 완료 단계의 거더브리지 설치 과정을 도식화하여 나타내는 측면도이다.18 is a side view schematically showing a girder bridge installation process at the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 19는 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치 완료 단계에서 바지선이 교각으로 이동되는 과정을 도식화하여 나타내는 평면도이다.19 is a plan view schematically showing a process of moving a barge to a pier in the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention.

도 20은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치 완료 단계에서 바지선이 교각으로 이동되는 과정을 도식화하여 나타내는 측면도이다.20 is a side view schematically showing a process of moving a barge to a pier in the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention.

본 발명의 일 관점에 따르면, 해상 교량의 교각 사이에 거더 브리지를 설치하는 시공 방법으로서, 상면에 리프팅용 로딩빔이 마련된 운반 수단에, 설치할 거더브리지를 리프팅용 로딩빔에 안착시키는 거더브리지 이송준비 단계; 상기 거더브리지 이송준비 단계 후, 운반 수단을 부두로 운반하고, 부두에 접안된 바지선으로 이동하여 거더브리지가 안착된 리프팅용 로딩빔으로 이루어지는 제1 구조물을 바지선에 로딩시키는 거더브리지 로딩 단계; 상기 거더브리지 로딩 단계 후, 상기 바지선에 설비된 스트랜드잭 리프트타워를 이용하여 상기 제1 구조물을 바지선 상면에서 소정 높이 리프팅하는 거더브리지 리프팅 단계; 소정 높이 리프팅된 상기 제1 구조물의 하부로 높이보상 트러스구조물을 이동 위치시킨 후, 상기 제1 구조물을 높이보상 트러스 구조물의 상면에 안착시켜 이루어지는 제2 구조물을 로딩하는 트러스구조물 로딩 단계; 상기 트러스구조물 로딩 단계 후, 상기 제2 구조물의 리프팅을 위하여 상기 스트랜드잭 리프트타워의 와이어를 제2 구조물에 연결하기 위한 통로를 확보하도록 상기 제1 구조물의 리프팅용 로딩빔의 가장자리를 컷팅하는 로딩빔 컷팅 단계; 상기 로딩빔 컷팅 단계 후, 거더브리지를 설치할 교각 측으로 바지선을 이동시키고, 이동된 위치에서 바지선을 수면에 대하여 소정 높이로 밸런싱하는 거더브리지 설치 준비 단계; 상기 거더브리지 설치 준비 단계 후, 상기 거더브리지를 교각의 높이보다 높은 위치까지 상기 제2 구조물을 리프팅하는 트러스구조물 리프팅 단계; 상기 트러스구조물 리프팅 단계 후, 바지선을 거더브리지 설치위치로 이동시키는 설치위치 이동 단계; 및 상기 설치위치 이동 단계 후, 상기 제2 구조물을 하강시켜 교각 사이에 거더브리지의 양단부를 두 교각에 설치된 다음, 상기 거더브리지가 제거된 제2 구조물을 갖는 바지선을 설치 위치로부터 이동시키는 설치 완료 단계;를 포함하며, 상기 바지선에 설비되는 스트랜드잭 리프트타워는 상기 교각의 높이보다 낮은 높이를 갖고 이루어지는 것을 특징으로 하는 해상 교량의 거더 브리지 설치 시공방법이 제공된다.According to an aspect of the present invention, as a construction method of installing a girder bridge between piers of an offshore bridge, preparation for transfer of a girder bridge in which a girder bridge to be installed is seated on a loading beam for lifting in a transport means provided with a loading beam for lifting on an upper surface. step; After the girder bridge transfer preparation step, a girder bridge loading step of transporting the transport means to the wharf, moving to a barge berthed to the wharf, and loading a first structure comprising a loading beam for lifting on which the girder bridge is seated on the barge; After the loading of the girder bridge, a girder bridge lifting step of lifting the first structure to a predetermined height from the top of the barge using a strand jack lift tower installed on the barge; A truss structure loading step of loading a second structure formed by placing the first structure on the upper surface of the height compensation truss structure after moving and positioning the height compensation truss structure below the first structure lifted by a predetermined height; After the loading of the truss structure, a loading beam for cutting the edge of the loading beam for lifting of the first structure to secure a passage for connecting the wire of the strand jack lift tower to the second structure for lifting of the second structure Cutting step; After the loading beam cutting step, a girder bridge installation preparation step of moving the barge toward the pier to install the girder bridge, and balancing the barge at a predetermined height with respect to the water surface at the moved position; A truss structure lifting step of lifting the second structure to a position higher than the height of the pier after the girder bridge installation preparation step; After the truss structure lifting step, the installation position moving step of moving the barge to the girder bridge installation position; And after the step of moving the installation position, the second structure is lowered to install both ends of the girder bridge between the piers, and then the barge having the second structure from which the girder bridge has been removed is moved from the installation position. Including;, a strand jack lift tower installed in the barge is provided with a method for installing a girder bridge of an offshore bridge, characterized in that it has a height lower than that of the pier.

본 발명에 있어서, 상기 거더브리지 이송준비 단계에서 상기 거더브리지의 길이와 폭은 운반 수단인 트랜스포터보다 크게 이루어지고, 상기 리프팅용 로딩빔은 상기 거더브리지의 폭방향으로 가로지르게 트랜스포터에 구비되고, 상기 거더브리지 로딩 단계는 상기 트랜스포터가 바지선으로 진입됨에 따라 바지선의 평형수를 조절하여 밸런싱하도록 이루어지고, 상기 거더브리지 리프팅 단계는, 바지선에 설비된 지지대를 제1 구조물의 로딩빔 하부에 위치시킨 후, 트랜스포터 자체가 하강하여 제1 구조물을 지지대의 상면에 안착시킨 다음, 거더브리지가 부두에 평행하도록 바지선을 접안하여 고박한 다음, 스트랜드잭 리프트 타워를 이용하여 리프팅용 로딩빔에 연결하여 제1 구조물을 바지선으로부터 소정 높이 리프팅하는 것으로 이루어지고, 상기 트러스구조물 로딩 단계는, 높이보상 트러스구조물을 실은 운반 수단을, 부두에 접안된 바지선으로 이동시켜서 소정 높이 리프팅되어 있는 제1 구조물의 하부 측에 이동 완료 후, 트랜스포터 자체가 하강하여 높이보상 트러스구조물을 지지대의 상면에 안착시키는 것으로 이루어지고, 상기 로딩빔 컷팅 단계는, 스트랜드잭 리프트타워를 이용하여 제1 구조물을 하강시켜 트러스구조물 상면에 안착시켜서 제2 구조물을 형성한 다음, 리프팅용 로딩암의 양 가장자리를 소정 길이 컷팅하여 제2 구조물의 리프팅을 위한 통로를 확보하며, 확보된 통로를 통해 스트랜드잭 리프트타워의 와이어를 제2 구조물의 트러스구조물의 양단부에 결합시키는 것으로 이루어지며, 상기 높이보상 트러스구조물은 교각 높이보다 낮은 높이를 갖는 스트랜드잭 리프트타워의 최대 리프팅 높이를 기초한 설계 높이를 갖는 것을 특징으로 한다.In the present invention, in the girder bridge transfer preparation step, the length and width of the girder bridge are made larger than that of the transporter, which is a transport means, and the loading beam for lifting is provided on the transporter so as to traverse in the width direction of the girder bridge. , The girder bridge loading step is made to balance by adjusting the ballast water of the barge as the transporter enters the barge, and in the girder bridge lifting step, the support provided on the barge is positioned under the loading beam of the first structure. After that, the transporter itself descends to settle the first structure on the upper surface of the support, then berth and secure the barge so that the girder bridge is parallel to the pier, and then connect it to the loading beam for lifting using the strand jack lift tower. The first structure is lifted by a predetermined height from the barge, and in the loading of the truss structure, the transport means loaded with the height compensation truss structure is moved to the barge berthed to the pier, and the lower side of the first structure is lifted by a predetermined height. After the movement is completed, the transporter itself descends and the height compensation truss structure is seated on the upper surface of the support, and in the loading beam cutting step, the first structure is lowered to the upper surface of the truss structure using a strand jack lift tower. After seating to form a second structure, a passage for lifting the second structure is secured by cutting both edges of the lifting arm for a predetermined length, and the wire of the strand jack lift tower is connected to the second structure through the secured passage. Consisting of coupling to both ends of the truss structure, the height compensation truss structure is characterized in that it has a design height based on the maximum lifting height of the strand jack lift tower having a height lower than the height of the pier.

본 발명에 있어서, 상기 거더브리지 설치 준비 단계는, 상기 로딩빔 컷팅 단계 후, 거더브리지를 설치할 교각 측방으로 바지선을 이동시키고, 바지선의 평형수를 조절하여 바지선의 높이를 소정 높이로 밸런싱하는 것으로 이루어지며, 상기 트러스구조물 리프팅 단계는, 바지선의 양측에 복수의 윈치를 연결하여 고박한 다음, 바지선의 스트랜드잭 리프트타워를 이용하여 제2 구조물을 리프팅하되, 제2 구조물의 거더브리지가 교각의 높이보다 소정 높이 높은 위치까지 상승시키도록 이루어질 수 있다.In the present invention, the preparatory step for installing the girder bridge comprises, after the loading beam cutting step, moving the barge to the side of the pier to install the girder bridge, and balancing the height of the barge to a predetermined height by adjusting the ballast water of the barge. In the truss structure lifting step, a plurality of winches are connected to both sides of the barge and secured, and then the second structure is lifted using the strand jack lift tower of the barge, but the girder bridge of the second structure is higher than the height of the pier. It can be made to rise to a predetermined height high position.

본 발명에 있어서, 상기 설치위치 이동 단계는, 바지선의 양측에 윈치로 연결되어 고박된 윈치를 이용하여 일측의 윈치와 타측의 윈치를 서로 연동시키면서 거더브리지가 교각의 설치 위치까지 바지선을 이동시키는 것으로 이루어지며, 상기 설치 완료 단계는, 제2 구조물을 하강시켜 거더브리지의 양단부를 두 교각의 설치부에 설치시키고, 로딩빔으로부터 거더브리지를 분리한 후, 로딩빔과 높이보상 트러스구조물을 하강시킨 다음, 바지선을 설치 위치로부터 이동시키는 것으로 이루어질 수 있다.In the present invention, in the step of moving the installation position, the girder bridge moves the barge to the installation position of the pier while interlocking the winch on one side and the winch on the other side by using a winch connected to both sides of the barge. In the installation completion step, the second structure is lowered to install both ends of the girder bridge on the installation portions of the two piers, and after separating the girder bridge from the loading beam, the loading beam and the height compensation truss structure are lowered. , It may consist of moving the barge from the installation location.

본 발명의 추가적인 목적들, 특징들 및 장점들은 다음의 상세한 설명 및 첨부도면으로부터 보다 명료하게 이해될 수 있다. Additional objects, features, and advantages of the present invention may be more clearly understood from the following detailed description and accompanying drawings.

본 발명의 상세한 설명에 앞서, 본 발명은 다양한 변경을 도모할 수 있고, 여러 가지 실시 예를 가질 수 있는바, 아래에서 설명되고 도면에 도시된 예시들은 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다.Prior to the detailed description of the present invention, the present invention is capable of various modifications and various embodiments, and the examples described below and shown in the drawings are intended to limit the present invention to specific embodiments. It is not to be understood that all changes, equivalents, and substitutes included in the spirit and scope of the present invention are included.

어떤 구성요소가 다른 구성요소에 "연결되어" 있다거나 "접속되어" 있다고 언급된 때에는, 그 다른 구성요소에 직접적으로 연결되어 있거나 또는 접속되어 있을 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떤 구성요소가 다른 구성요소에 "직접 연결되어" 있다거나 "직접 접속되어" 있다고 언급된 때에는, 중간에 다른 구성요소가 존재하지 않는 것으로 이해되어야 할 것이다.When a component is referred to as being "connected" or "connected" to another component, it is understood that it may be directly connected or connected to the other component, but other components may exist in the middle. Should be. On the other hand, when a component is referred to as being "directly connected" or "directly connected" to another component, it should be understood that there is no other component in the middle.

본 명세서에서 사용한 용어는 단지 특정한 실시 예를 설명하기 위해 사용된 것으로, 본 발명을 한정하려는 의도는 아니다. 단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한, 복수의 표현을 포함한다. 본 명세서에서, "포함하다" 또는 "가지다" 등의 용어는 명세서상에 기재된 특징, 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것이 존재함을 지정하려는 것이지, 하나 또는 그 이상의 다른 특징들이나 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.The terms used in the present specification are only used to describe specific embodiments, and are not intended to limit the present invention. Singular expressions include plural expressions unless the context clearly indicates otherwise. In this specification, terms such as "comprise" or "have" are intended to designate the presence of features, numbers, steps, actions, components, parts, or a combination thereof described in the specification, but one or more other features. It is to be understood that the presence or addition of elements or numbers, steps, actions, components, parts, or combinations thereof, does not preclude in advance.

또한, 명세서에 기재된 "...부", "...유닛", "...모듈" 등의 용어는 적어도 하나의 기능이나 동작을 처리하는 단위를 의미하며, 이는 하드웨어나 소프트웨어 또는 하드웨어 및 소프트웨어의 결합으로 구현될 수 있다.In addition, terms such as "... unit", "... unit", and "... module" described in the specification mean a unit that processes at least one function or operation, which is hardware, software, or hardware and It can be implemented as a combination of software.

또한, 첨부 도면을 참조하여 설명함에 있어, 도면 부호에 관계없이 동일한 구성 요소는 동일한 참조부호를 부여하고 이에 대한 중복되는 설명은 생략하기로 한다. 본 발명을 설명함에 있어서 관련된 공지 기술에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명을 생략한다.In addition, in the description with reference to the accompanying drawings, the same reference numerals are assigned to the same components regardless of the reference numerals, and redundant descriptions thereof will be omitted. In describing the present invention, if it is determined that a detailed description of a related known technology may unnecessarily obscure the subject matter of the present invention, a detailed description thereof will be omitted.

이하, 본 발명의 바람직한 실시 예에 따른 해상 교량의 거더 브리지 설치 시공방법에 대하여 첨부 도면을 참조하여 상세히 설명한다.Hereinafter, a method for installing and constructing a girder bridge of an offshore bridge according to a preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법의 시공 과정을 나타내는 플로차트이고, 도 2 및 도 3은 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 운반 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이며, 도 4 및 도 5는 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 운반 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이다. 도 6 및 도 7은 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 거더브리지 리프팅 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이고, 도 8 및 도 9는 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 트러스 구조물 로딩 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이며, 도 10 및 도 11은 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 로딩빔 컷팅 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이다. 도 12 및 도 13은 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 거더브리지 설치 준비 단계의 일 실시 과정을 도식화하여 나타내는 평면도 및 측면도이고, 도 14 및 도 15는 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 트러스구조물 리프팅 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이며, 도 16 및 도 17은 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치위치 이동 단계의 일 실시 과정을 도식화하여 나타내는 평면도와 측면도이다. 도 18은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치 완료 단계의 거더브리지 설치 과정을 도식화하여 나타내는 측면도이며, 도 19 및 도 20은 각각 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에서 설치 완료 단계에서 바지선이 교각으로 이동되는 과정을 도식화하여 나타내는 평면도 및 측면도이다.Figure 1 is a flow chart showing the construction process of the girder bridge installation construction method of the offshore bridge according to the present invention, Figures 2 and 3 are each an implementation process of the carrying step in the girder bridge installation construction method of the offshore bridge according to the present invention A plan view and a side view schematically shown, and FIGS. 4 and 5 are a plan view and a side view schematically showing an implementation process of a transport step in the girder bridge installation construction method of an offshore bridge according to the present invention, respectively. 6 and 7 are a plan view and a side view schematically showing an implementation process of a girder bridge lifting step in the girder bridge installation construction method of an offshore bridge according to the present invention, respectively, and FIGS. 8 and 9 are respectively a sea bridge according to the present invention A plan view and a side view schematically showing an implementation process of a truss structure loading step in the girder bridge installation construction method of, and FIGS. 10 and 11 are each one of a loading beam cutting step in the girder bridge installation construction method of an offshore bridge according to the present invention. It is a plan view and a side view schematically showing the implementation process. 12 and 13 are plan and side views, respectively, schematically showing an implementation process of a girder bridge installation preparation step in the girder bridge installation construction method of an offshore bridge according to the present invention, and FIGS. 14 and 15 are respectively It is a plan view and a side view schematically showing an implementation process of a truss structure lifting step in the girder bridge installation construction method of a bridge, and FIGS. 16 and 17 are each of the installation location movement step in the girder bridge installation construction method of a marine bridge according to the present invention. It is a plan view and a side view schematically showing an implementation process. 18 is a side view schematically showing a girder bridge installation process at the installation completion stage in the girder bridge installation construction method of an offshore bridge according to the present invention, and FIGS. 19 and 20 are each a girder bridge installation construction method of an offshore bridge according to the present invention It is a plan view and a side view schematically showing the process of moving the barge to the pier in the installation completion stage.

본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법은, 해상 교량의 교각 사이에 거더 브리지를 설치하는 시공 방법으로서, 도 1 내지 도 20에 나타낸 바와 같이, 상부에 리프팅용 로딩빔(110)이 마련된 운반 수단(예를 들면, 모듈 트랜스포터(SPMT: Self-Propelled Modular Transporter)(S)에, 제작된 소정 형태의 거더브리지(200)를 리프팅용 로딩빔(110)에 안착시키는 거더브리지 이송준비 단계(S100); 상기 이송준비 단계(S100) 완료 이후, 상기 운반 수단을 부두(또는 선창)로 운반하는 운반 단계(S200)(도 2 및 도 3 참조); 상기 운반 단계(S200) 완료 후, 부두에 접안된 바지선(B)으로 이동하여 거더 브리지(200)가 안착된 리프팅용 로딩빔(110)을 바지선 상에 로딩시키는 거더브리지 로딩 단계(S300)(도 4 및 도 5 참조); 상기 거더브리지 로딩 단계(S300) 완료 후, 거더 브리지(200)가 안착된 리프팅용 로딩빔(110)을 바지선(B) 상에서 소정 높이 리프팅하는 거더브리지 리프팅 단계(S400)(도 6 및 도 7 참조); 상기 거더브리지 리프팅 단계(S400)에서 소정 높이 리프팅된 리프팅용 로딩빔(110)의 하부로 높이보상 트러스구조물(120)을 이동 위치시킨 후, 리프팅용 로딩빔(110)을 높이보상 트러스 구조물(120)의 상면에 안착시키는 트러스구조물 로딩 단계(S500)(도 8 및 도 9 참조); 상기 트러스구조물 로딩 단계(S500) 완료 후, 높이보상 트러스 구조물(120)의 리프팅을 위한 통로 확보를 위하여 상기 리프팅용 로딩빔(110)의 가장자리를 컷팅하는 로딩빔 컷팅 단계(S600)(도 10 및 도 11 참조); 상기 로딩빔 컷팅 단계(S600) 완료 후, 거더 브리지(200)를 설치할 교각(P) 측방으로 바지선(B)을 이동시키고, 바지선(B)을 소정 높이로 밸런싱하는 거더브리지 설치 준비 단계(S700)(도 12 및 도 13 참조); 상기 거더브리지 설치 준비 단계(S700) 완료 후, 높이보상 트러스구조물(120)을 리프팅하여 거더브리지(200)를 교각(P)의 높이보다 높게 상승시키는 트러스구조물 리프팅 단계(S800)(도 14 및 도 15 참조); 상기 트러스구조물 리프팅 단계(S800) 완료 후, 바지선(B)을 교각(P) 사이의 거더브리지 설치위치로 이동시키는 설치위치 이동 단계(S900)(도 16 및 도 17 참조); 및 상기 설치위치 이동 단계(S900) 완료 후, 높이보상 트러스구조물(300)을 하강시켜 교각 사이에 거더브리지(200)의 양단부가 두 교각에 설치된 다음, 하강된 높이보상 트러스구조물(120)(즉, 로딩빔(110)이 상면에 위치된 트러스구조물(120))을 갖는 바지선(B)을 설치 위치로부터 이동시키는 설치 완료 단계(S1000)(도 18 내지 도 20 참조);를 포함한다.The girder bridge installation construction method of an offshore bridge according to the present invention is a construction method of installing a girder bridge between piers of an offshore bridge, as shown in Figs. 1 to 20, in which a loading beam 110 for lifting is provided at the top. A girder bridge transfer preparation step in which the manufactured girder bridge 200 of a predetermined shape is seated on the loading beam 110 for lifting in a transport means (e.g., a self-propelled modular transporter (SPMT) (S)) (S100); After completion of the transfer preparation step (S100), a transport step (S200) of transporting the transport means to the dock (or dock) (see Figs. 2 and 3); After completion of the transport step (S200), the dock The girder bridge loading step (S300) of moving to the barge (B) berthed on the girder bridge 200 and loading the loading beam 110 for lifting on the barge (see FIGS. 4 and 5); the girder bridge After completion of the loading step (S300), the girder bridge lifting step (S400) of lifting the loading beam 110 for lifting on which the girder bridge 200 is seated on the barge (B) to a predetermined height (see FIGS. 6 and 7); After moving the height compensation truss structure 120 to the lower part of the lifting loading beam 110 for lifting a predetermined height in the girder bridge lifting step (S400), the height compensation truss structure 120 for the lifting loading beam 110 The truss structure loading step (S500) (see FIGS. 8 and 9) to be seated on the upper surface of the truss structure; after completion of the truss structure loading step (S500), for the lifting to secure a passage for lifting the height compensation truss structure 120 Loading beam cutting step (S600) of cutting the edge of the loading beam 110 (see FIGS. 10 and 11); After completion of the loading beam cutting step (S600), toward the side of the pier (P) where the girder bridge 200 is to be installed Moving the barge (B) and balancing the barge (B) to a predetermined height, a girder bridge installation preparation step (S700) (see FIGS. 12 and 13); the girder bridge installation preparation step (S 700) After completion, the truss structure lifting step (S800) of lifting the height compensation truss structure 120 to raise the girder bridge 200 higher than the height of the pier P (see FIGS. 14 and 15); After completion of the truss structure lifting step (S800), the installation position movement step (S900) of moving the barge (B) to the installation position of the girder bridge between the piers (P) (see FIGS. 16 and 17); And after completion of the installation position moving step (S900), the height compensation truss structure 300 is lowered to install both ends of the girder bridge 200 between the piers, and then the lowered height compensation truss structure 120 (i.e. , The loading beam 110 is an installation completion step (S1000) (see Figs. 18 to 20) of moving the barge B having the truss structure 120 located on the upper surface from the installation position.

상기 거더브리지 이송준비 단계(S100)에서, 운반수단인 트랜스포터(S)는 거더브리지(110)의 중량을 고려하여 준비되는데, 트랜스포터(S)의 전체 길이(단위 트랜스포터인 경우 전방에서 후방까지의 전체 길이)보다 긴 길이의 거더브리지(110)가 올려진다.In the girder bridge transfer preparation step (S100), the transporter (S), which is a transport means, is prepared in consideration of the weight of the girder bridge (110), and the total length of the transporter (S) (in the case of a unit transporter, from front to rear) The girder bridge 110 of a length longer than (total length) is raised.

다시 말해서, 상기 거더브리지(110)는 두 교각(P) 사이에 설치되는 길이를 갖는 거더브리지(110)로 구성되며, 이 거더브리지(110)는 길이방향의 양단부에 마진부를 갖고 트랜스포터(S)에 놓이게 된다.In other words, the girder bridge 110 is composed of a girder bridge 110 having a length that is installed between the two piers (P), the girder bridge 110 has margins at both ends in the longitudinal direction and a transporter (S ).

여기에서, 상기 트랜스포터(S)에는 거더브리지(110)의 폭방향으로 가로지르는 복수의 리프팅용 로딩빔(110)이 놓여 있고, 그 위에 제작된 거더브리지(110)가 안착되게 된다. 이때, 리프팅용 로딩빔(110)과 이 리프팅용 로딩빔(110)에 안착된 거더브리지(110)(이하, "제1 구조물"이라 함) 간은 후술하는 운반과 리프팅 과정에서 안정성을 가지면서 후술하는 설치 완료 단계에서 로딩빔(110)이 거더브리지(110)와 쉽게 분리될 수 있는 가고정되어 안착될 수 있다.Here, a plurality of loading beams 110 for lifting crossing in the width direction of the girder bridge 110 are placed on the transporter S, and the girder bridge 110 manufactured thereon is mounted. At this time, between the loading beam 110 for lifting and the girder bridge 110 (hereinafter referred to as "first structure") seated on the loading beam 110 for lifting have stability in the transport and lifting process described later In the installation completion step to be described later, the loading beam 110 may be temporarily fixed and seated to be easily separated from the girder bridge 110.

계속해서, 운반 단계(S200)는 운반수단인 트랜스포터(S)에 제1 구조물을 안착시킨 상태를 안정적으로 유지하면서 바지선(B)이 접안된 부두까지 운반하게 된다.Subsequently, in the transport step (S200), while stably maintaining the state in which the first structure is seated on the transporter (S), which is a transport means, the barge (B) is transported to the docked pier.

상기 바지선(B)에는 상단에 리프팅 설비로서 스트랜드잭이 설치된 스트랜드잭 리프트타워(L)가 소정 간격을 갖고 복수 설비되어 있으며, 여기에서 상기 스트랜드잭 리프트타워(L)는 거더브리지(110)가 설치될 교각의 높이보다 낮은 높이를 갖는 스트랜드잭 리프트타워로 설비된다. 이는 후술하는 설치 완료 단계에서 거더브리지(110)가 교각에 설치된 후 바지선의 진입방향과 반대방향으로 용이하게 빠져나올 수 있게 된다.The barge (B) is equipped with a plurality of strand jack lift towers (L) with a strand jack installed at the top as a lifting facility at predetermined intervals, wherein the strand jack lift tower (L) is equipped with a girder bridge (110). It is equipped with a strand jack lift tower with a height lower than the height of the pier to be used. This allows the girder bridge 110 to be easily exited in the direction opposite to the entry direction of the barge after the girder bridge 110 is installed on the pier in the installation completion step to be described later.

다음으로, 상기 거더브리지 로딩 단계(S300)는 도 4 및 도 5에 나타낸 바와 같이 제1 구조물이 실려있는 트랜스포터(S)를 바지선(B)의 스트랜드잭 리프트타워(S) 사이로 이동시킨 다음, 소정 이동 완료 위치에 위치되게 된다.Next, in the girder bridge loading step (S300), as shown in FIGS. 4 and 5, the transporter (S) carrying the first structure is moved between the strand jack lift towers (S) of the barge (B), and then, It is positioned at a predetermined movement completion position.

이러한 거더브리지 로딩 단계(S300)의 트랜스포터(S) 이동 과정에서, 트랜스포터(S)가 진입됨에 따라 바지선(B)의 평형수를 조절하여 육상 부두의 상면과 바지선(B)의 상면이 거의 동일 평면 상에 있도록 하게 된다.In the process of moving the transporter (S) in the girder bridge loading step (S300), as the transporter (S) enters, the ballast water of the barge (B) is adjusted so that the upper surface of the land pier and the upper surface of the barge (B) are almost They are on the same plane.

다음으로, 상기 거더브리지 리프팅 단계(S400)는, 먼저 바지선(B)에 설비된 이동식 지지대(M)를 제1 구조물의 로딩빔(110) 하부에 위치시킨 다음, 트랜스포터(S)의 자체 승강장치를 통해 하강하여 제1 구조물을 이동식 지지대(M)의 상면에 안착시킨다(도 7의 좌측 그림). 그런 다음, 제1 구조물이 이동식 지지대(M)에 의해 바지선(B)의 상면으로부터 이격된 상태에서 트랜스포터(S)를 바지선(B)으로 육상으로 이동시킨다. 상기 이동식 지지대(M)는 트랜스포터(S)가 통과가능한 간격을 갖는 위치에 고정된다.Next, in the girder bridge lifting step (S400), first, the movable support (M) installed on the barge (B) is placed under the loading beam (110) of the first structure, and then the self-propelled platform of the transporter (S) It descends through the teeth to settle the first structure on the upper surface of the movable support (M) (left figure in Fig. 7). Then, the transporter (S) is moved to the land by the barge (B) while the first structure is separated from the upper surface of the barge (B) by the mobile support (M). The movable support (M) is fixed at a position having a space through which the transporter (S) can pass.

이후, 바지선(B)을 부두에 고박, 바람직하게는 도 6에 나타낸 바와 같이 거더브리지(110)가 부두에 평행하도록 바지선(B)을 접안하여 고박한 다음, 도 7의 우측 그림에 나타낸 바와 같이 스트랜드잭 리프트 타워(L)의 스트랜드잭을 로딩빔(110)에 연결하여 제1 구조물을 바지선(B)으로부터 소정 높이 리프팅한다.Thereafter, the barge (B) is anchored to the pier, preferably, as shown in FIG. 6, the barge (B) is docked and anchored so that the girder bridge (110) is parallel to the pier, as shown in the right figure of FIG. The strand jack of the strand jack lift tower (L) is connected to the loading beam (110) to lift the first structure from the barge (B) to a predetermined height.

다음으로, 트러스구조물 로딩 단계(S500)는, 도 8 및 도 9의 좌측 그림에 나타낸 바와 같이, 제작된 높이보상 트러스구조물(120)을 실은 트랜스포터(S)를 이용하여, 부두에 접안된 바지선(B)(교각 높이보다 낮은 높이를 갖는 스트랜드잭 리프트타워(L)가 설비된 바지선)으로 이동시켜서, 소정 높이 리프팅되어 있는 제1 구조물의 하부(즉, 로딩빔(110)의 하부) 측에 이동 완료 후, 도 9의 우측 그림에 나타낸 바와 같이, 트랜스포터(S)의 자체 승강장치를 통해 하강하여 높이보상 트러스구조물(120)을 이동식 지지대(M)의 상면에 안착시킨다.Next, the truss structure loading step (S500), as shown in the left figure of Figs. 8 and 9, using a transporter (S) loaded with the manufactured height compensation truss structure 120, the barge docked to the pier (B) (barge equipped with a strand jack lift tower (L) having a height lower than the height of the pier) to the lower portion of the first structure (that is, the lower portion of the loading beam 110) After completing the movement, as shown in the right figure of FIG. 9, the height compensation truss structure 120 is mounted on the upper surface of the movable support M by descending through the self-elevating device of the transporter S.

여기에서, 높이보상 트러스구조물(120)은 교각 높이보다 낮은 높이를 갖는 스트랜드잭 리프트타워(L)의 최대 상승 높이를 고려하여 설계 제작된 높이를 갖는 구조물이다.Here, the height compensation truss structure 120 is a structure having a height designed and manufactured in consideration of the maximum elevation height of the strand jack lift tower L having a height lower than the height of the pier.

다음으로, 상기 로딩빔 컷팅 단계(S600)는, 스트랜드잭 리프트타워(L)를 이용하여 제1 구조물을 하강시켜, 이동식 지지대(M)의 상면에 안착된 트러스구조물(120) 상면에 안착시킨 다음, 리프팅용 로딩암(110)의 양 가장자리를 소정 길이 컷팅하여 높이보상 트러스 구조물(120)의 리프팅을 위한 통로를 확보하며, 확보된 통로를 통해 스트랜드잭 리프트타워(L)의 스트랜드 와이어를 트러스구조물(120)의 양단부에 결합시킨다(도 11 참조). 이하, 제1 구조물에 트러스구조물이 결합된 구조물을 제2 구조물이라 칭한다.Next, in the loading beam cutting step (S600), the first structure is lowered using the strand jack lift tower (L), and the truss structure 120 is seated on the upper surface of the movable support (M). , Both edges of the lifting loading arm 110 are cut to a predetermined length to secure a passage for lifting of the height compensation truss structure 120, and the strand wire of the strand jack lift tower (L) is connected to the truss structure through the secured passage. It is coupled to both ends of 120 (see Fig. 11). Hereinafter, a structure in which a truss structure is coupled to the first structure is referred to as a second structure.

다음으로, 상기 거더브리지 설치 준비 단계(S700)는, 상기 로딩빔 컷팅 단계(S600) 완료 후, 거더브리지(200)를 설치할 교각(P) 측방으로 바지선(B)을 이동하고, 바지선(B)의 평형수를 조절하여 바지선(B)의 높이를 소정 높이로 밸런싱하게 된다. 이러한 거더브리지 설치 준비 단계(S700)는 생략되거나, 트러스구조물 리프팅 단계(S800)와 동시에 실행될 수 있다.Next, in the girder bridge installation preparation step (S700), after the loading beam cutting step (S600) is completed, the barge (B) is moved toward the side of the pier (P) where the girder bridge 200 is to be installed, and the barge (B) The height of the barge (B) is balanced to a predetermined height by adjusting the ballast water. This girder bridge installation preparation step (S700) may be omitted or may be executed simultaneously with the truss structure lifting step (S800).

다음으로, 상기 트러스구조물 리프팅 단계(S800)는, 도 14에 나타낸 바와 같이 바지선(B)을 거더브리지 설치를 위한 위치로 안정적으로 이동시키기 위하여 바지선(B)의 양측에 복수의 윈치를 연결하여 고박한 다음, 바지선(B)의 스트랜드잭 리프트타워(L)를 이용하여 제2 구조물을 리프팅하되, 제2 구조물의 거더브리지(200)가 교각(P)의 높이보다 소정 높이 높은 위치까지 상승시킨다. 바람직하게는, 거더브리지(200)가 교각(P)의 상단보다 약 2.5M 정도 높은 위치에 있도록 제2 구조물을 상승시킨다.Next, the truss structure lifting step (S800) is secured by connecting a plurality of winches to both sides of the barge (B) in order to stably move the barge (B) to a position for installing the girder bridge, as shown in FIG. Then, the second structure is lifted using the strand jack lift tower (L) of the barge (B), but the girder bridge 200 of the second structure is raised to a position higher than the height of the pier (P) by a predetermined height. Preferably, the second structure is raised so that the girder bridge 200 is at a position approximately 2.5M higher than the upper end of the pier P.

여기에서, 스트랜드잭 리프트타워(L)의 높이는 교각(P)의 높이보다 낮으나, 높이보상 트러스구조물(120) 및 로딩빔(110)의 높이에 의해 거더브리지(200)가 교각(P)의 높이보다 높게 위치되는 것이다.Here, the height of the strand jack lift tower (L) is lower than the height of the pier (P), but by the height of the height compensation truss structure (120) and the loading beam (110), the girder bridge (200) is the height of the pier (P) It is positioned higher.

다음으로, 상기 설치위치 이동 단계(S900)는, 도 16 및 도 17에 나타낸 바와 같이, 바지선(B)의 양측에 연결되어 고박된 윈치를 이용하여 일측의 윈치와 타측의 윈치를 서로 연동시켜 천천히 감고 풀면서 거더브리지(200)가 교각(P)의 설치 위치까지 바지선(B)을 이동시키게 된다.Next, the installation position moving step (S900), as shown in Figs. 16 and 17, by using a winch connected to both sides of the barge (B) and fixed by interlocking the winch of one side and the winch of the other side slowly While winding and unwinding, the girder bridge 200 moves the barge B to the installation position of the pier P.

다음으로, 상기 설치 완료 단계(S1000)는, 도 18에 나타낸 바와 같이 제2 구조물을 하강시켜 교각(P) 사이에 거더브리지(200)의 양단부를 두 교각의 설치부에 설치시키고, 거더브리지(200)와 로딩빔(110)을 분리한 후, 도 19 및 도 20에 나타낸 바와 같이 로딩빔(110)과 높이보상 트러스구조물(120)을 소정 높이 하강시킨 다음, 즉 로딩빔(110)과 높이보상 트러스구조물(120)을 스트랜드잭 리프트타워(L)의 높이보다 낮게 하강시킨 상태 또는 이동식 지지대(M)에 안착시킨 상태에서 바지선을 설치 위치로부터 이동시켜서 거더브리지(200)의 설치 시공을 완료하도록 이루어진다.Next, in the installation completion step (S1000), as shown in FIG. 18, the second structure is lowered to install both ends of the girder bridge 200 between the piers P and the installation portions of the two piers, and the girder bridge ( After separating 200) and the loading beam 110, the loading beam 110 and the height compensation truss structure 120 are lowered to a predetermined height as shown in FIGS. 19 and 20, that is, the height of the loading beam 110 and the height To complete the installation and construction of the girder bridge 200 by moving the barge from the installation position in a state in which the compensation truss structure 120 is lowered lower than the height of the strand jack lift tower (L) or seated on a movable support (M). Done.

상기 설치 완료 후 바지선의 이동은 바지선(B)의 양측에 연결되어 고박된 윈치를 이용하여 일측의 윈치와 타측의 윈치를 서로 연동시켜 천천히 감고 풀면서 실행할 수 있으며, 설치 후 고박을 풀고 바지선(B) 자체를 이동시켜서 실행할 수 있다.After the installation is completed, the movement of the barge can be carried out by slowly winding and unwinding by interlocking the winch on one side and the winch on the other side by using a winch connected to both sides of the barge (B). ) It can be executed by moving itself.

예를 들면, 바지선(B)에 설비된 스트랜드잭 리프트타워(L)가 교각의 높이보다 높을 경우, 거더브리지(200)의 설치 후 그 거더브리지(200)로 인하여 교각으로부터 벗어날 수 없었으나, 상기와 같이 본 발명은 스트랜드잭 리프트타워(L)의 높이가 교각보다 낮더라도 높이보상 트러스구조물을 통해 설치 높이를 보상하고, 거더브리지의 설치 후 거더브리지에 의해 방해받는 일 없이 거더브리지의 설치 위치로부터 쉽게 벗어날 수 있게 된다.For example, if the strand jack lift tower (L) installed in the barge (B) is higher than the height of the pier, after the girder bridge 200 is installed, the girder bridge 200 could not escape from the pier, but the above As described above, the present invention compensates for the installation height through a height compensation truss structure even if the height of the strand jack lift tower (L) is lower than the pier, and from the installation position of the girder bridge without being disturbed by the girder bridge after the installation of the girder bridge. You can get away easily.

물론, 스트랜드잭 리프트타워(L)의 높이를 교각보다 낮추기 위하여 상단부를 제거하거나 분리할 수 있으나, 이는 종래 기술의 문제점에서 언급한 바와 같이 공정수와 공사 기간이 증가하여 교량 작업의 비용을 크게 상승시킬 뿐만 아니라, 해상의 특성상 제거 또는 분해 과정에서 안전사고가 발생되는 문제점이 있었으며, 본 발명은 교각보다 낮은(다시 말해서, 설치된 거더브리지의 높이보다 낮은 스트랜드잭 리프트타워(L)를 이용하더라도 상기한 과정을 거쳐 이러한 문제점을 해결한 것이다.Of course, the upper part of the strand jack lift tower (L) can be removed or separated in order to lower the height of the pier, but this increases the number of processes and construction period as mentioned in the problem of the prior art, greatly increasing the cost of the bridge work. In addition, there was a problem that safety accidents occurred in the removal or disassembly process due to the nature of the sea, and the present invention has a problem with the above-described use of a strand jack lift tower (L) lower than the pier (that is, the height of the installed girder bridge). This problem was solved through the process.

한편, 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법의 다른 실시 예로서, 상기한 리프팅용 로딩빔(110)과 높이보상 트러스구조물(120)가 일체로 형성되는 높이보상 구조물 또는 소정 형상의 높이보상 트러스구조물 자체만으로 형성될 수 있다.On the other hand, as another embodiment of the installation construction method of the girder bridge of the offshore bridge according to the present invention, a height compensation structure or a height of a predetermined shape in which the loading beam for lifting 110 and the height compensation truss structure 120 are integrally formed It can be formed only by the compensation truss structure itself.

이 경우, 거더브리지 이송 준비 단계(S100)에서 트랜스포터(S)에 로딩빔(110)을 별도로 설비시킨 과정, 그 위에 거더브리지를 로딩하는 과정, 거더브리지를 리프팅하는 과정, 트러스구조물을 로딩하는 과정, 로딩빔을 컷팅하는 과정은 생략되며, 거더브리지 이송 준비 단계(S100)에서 트랜스포터(S)에 높이보상 구조물을 안착시킨 후, 운반하고(S200), 그 위에 거더브리지(200)를 로딩한 다음(S300), 스트랜드잭 리프트타워(L)의 스트랜드 와이어를 높이보상 구조물 또는 높이보상 트러스구조물에 연결하여 거더브리지 설치 준비 단계(S700) 및 이후 과정을 실행하도록 이루어질 수 있다.In this case, the process of separately installing the loading beam 110 on the transporter (S) in the girder bridge transfer preparation step (S100), the process of loading the girder bridge thereon, the process of lifting the girder bridge, and loading the truss structure. The process, the process of cutting the loading beam is omitted, and after mounting the height compensation structure on the transporter (S) in the girder bridge transfer preparation step (S100), transporting (S200), and loading the girder bridge (200) thereon Then (S300), the strand wire of the strand jack lift tower (L) may be connected to a height compensation structure or a height compensation truss structure to perform a girder bridge installation preparation step (S700) and subsequent processes.

이상에서 설명한 바와 같은 본 발명에 따른 해상 교량의 거더 브리지 설치 시공방법에 의하면, 해상 교량의 교각 간에 거더 브리지(행교 또는 강교)를 설치함에 있어, 타워 크레인의 분해 또는 제거 작업을 필요로 하지 않고 거더 브리지를 시공할 수 있어 시공수와 시공기간을 현저히 단축할 수 있을 뿐만 아니라 안전한 시공이 가능하여 시공성과 경제성 및 작업 안전성을 향상시킬 수 있는 이점이 있다.According to the girder bridge installation construction method of an offshore bridge according to the present invention as described above, in installing a girder bridge (hanging bridge or steel bridge) between piers of an offshore bridge, the girder does not require disassembly or removal of the tower crane. Since the bridge can be constructed, the number of construction and the construction period can be remarkably shortened, as well as safe construction, which has the advantage of improving workability, economy and work safety.

상기한 바와 같은 실시 예들은 비록 한정된 도면에 의해 설명되었으나, 해당 기술분야에서 통상의 지식을 가진 자라면 상기를 기초로 다양한 기술적 수정 및 변형을 적용할 수 있다. 예를 들어, 설명된 기술들이 설명된 방법과 다른 순서로 수행되거나, 및/또는 설명된 시스템, 구조, 장치, 회로 등의 구성요소들이 설명된 방법과 다른 형태로 결합 또는 조합되거나, 다른 구성요소 또는 균등물에 의하여 대치되거나 치환되더라도 적절한 결과가 달성될 수 있다.Although the above-described embodiments have been described by the limited drawings, a person of ordinary skill in the art can apply various technical modifications and variations based on the above. For example, the described techniques are performed in a different order from the described method, and/or components such as a system, structure, device, circuit, etc. described are combined or combined in a form different from the described method, or other components Alternatively, even if substituted or substituted by an equivalent, an appropriate result can be achieved.

본 명세서에서 설명되는 실시 예와 첨부된 도면은 본 발명에 포함되는 기술적 사상의 일부를 예시적으로 설명하는 것에 불과하다. 따라서, 본 명세서에 개시된 실시 예는 본 발명의 기술적 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이므로, 이러한 실시 예에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아님은 자명하다. 본 발명의 명세서 및 도면에 포함된 기술적 사상의 범위 내에서 당업자가 용이하게 유추할 수 있는 변형 예와 구체적인 실시 예는 모두 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.The embodiments described in the present specification and the accompanying drawings are merely illustrative of some of the technical ideas included in the present invention. Accordingly, it is obvious that the embodiments disclosed in the present specification are not intended to limit the technical idea of the present disclosure, but to explain the technical idea, and thus the scope of the technical idea of the present disclosure is not limited by these embodiments. Modification examples and specific embodiments that can be easily inferred by those skilled in the art within the scope of the technical idea included in the specification and drawings of the present invention should be interpreted as being included in the scope of the present invention.

본 발명은 해상 교량의 거더 브리지 설치 시공방법은, 해상 교량의 교각 간에 거더 브리지(행교 또는 강교)를 설치하는데 이용될 수 있다.The present invention can be used to install a girder bridge (hanging bridge or steel bridge) between the piers of the offshore bridge, the method of installing a girder bridge of an offshore bridge.

Claims (4)

해상 교량의 교각 사이에 거더 브리지를 설치하는 시공 방법으로서,As a construction method of installing a girder bridge between the piers of an offshore bridge, 상면에 리프팅용 로딩빔이 마련된 운반 수단에, 설치할 거더브리지를 리프팅용 로딩빔에 안착시키는 거더브리지 이송준비 단계;A girder bridge transfer preparation step of seating a girder bridge to be installed on a loading beam for lifting in a transportation means provided with a loading beam for lifting on an upper surface; 상기 거더브리지 이송준비 단계 후, 운반 수단을 부두로 운반하고, 부두에 접안된 바지선으로 이동하여 거더브리지가 안착된 리프팅용 로딩빔으로 이루어지는 제1 구조물을 바지선에 로딩시키는 거더브리지 로딩 단계;After the girder bridge transfer preparation step, a girder bridge loading step of transporting the transport means to the wharf, moving to a barge berthed to the wharf, and loading a first structure comprising a loading beam for lifting on which the girder bridge is seated on the barge; 상기 거더브리지 로딩 단계 후, 상기 바지선에 설비된 스트랜드잭 리프트타워를 이용하여 상기 제1 구조물을 바지선 상면에서 소정 높이 리프팅하는 거더브리지 리프팅 단계;After the loading of the girder bridge, a girder bridge lifting step of lifting the first structure to a predetermined height from the top of the barge using a strand jack lift tower installed on the barge; 소정 높이 리프팅된 상기 제1 구조물의 하부로 높이보상 트러스구조물을 이동 위치시킨 후, 상기 제1 구조물을 높이보상 트러스 구조물의 상면에 안착시켜 이루어지는 제2 구조물을 로딩하는 트러스구조물 로딩 단계;A truss structure loading step of loading a second structure formed by placing the first structure on the upper surface of the height compensation truss structure after moving and positioning the height compensation truss structure below the first structure lifted by a predetermined height; 상기 트러스구조물 로딩 단계 후, 상기 제2 구조물의 리프팅을 위하여 상기 스트랜드잭 리프트타워의 와이어를 제2 구조물에 연결하기 위한 통로를 확보하도록 상기 제1 구조물의 리프팅용 로딩빔의 가장자리를 컷팅하는 로딩빔 컷팅 단계;After the loading of the truss structure, a loading beam for cutting the edge of the loading beam for lifting of the first structure to secure a passage for connecting the wire of the strand jack lift tower to the second structure for lifting of the second structure Cutting step; 상기 로딩빔 컷팅 단계 후, 거더브리지를 설치할 교각 측으로 바지선을 이동시키고, 이동된 위치에서 바지선을 수면에 대하여 소정 높이로 밸런싱하는 거더브리지 설치 준비 단계;After the loading beam cutting step, a girder bridge installation preparation step of moving the barge toward the pier to install the girder bridge, and balancing the barge at a predetermined height with respect to the water surface at the moved position; 상기 거더브리지 설치 준비 단계 후, 상기 거더브리지를 교각의 높이보다 높은 위치까지 상기 제2 구조물을 리프팅하는 트러스구조물 리프팅 단계;A truss structure lifting step of lifting the second structure to a position higher than the height of the pier after the girder bridge installation preparation step; 상기 트러스구조물 리프팅 단계 후, 바지선을 거더브리지 설치위치로 이동시키는 설치위치 이동 단계; 및After the truss structure lifting step, the installation position moving step of moving the barge to the girder bridge installation position; And 상기 설치위치 이동 단계 후, 상기 제2 구조물을 하강시켜 교각 사이에 거더브리지의 양단부를 두 교각에 설치된 다음, 상기 거더브리지가 제거된 제2 구조물을 갖는 바지선을 설치 위치로부터 이동시키는 설치 완료 단계;를 포함하며,After the installation position moving step, the second structure is lowered to install both ends of the girder bridge between the piers, and then the barge having the second structure from which the girder bridge is removed is moved from the installation position; Including, 상기 바지선에 설비되는 스트랜드잭 리프트타워는 상기 교각의 높이보다 낮은 높이를 갖고 이루어지는 것을 특징으로 하는The strand jack lift tower installed on the barge is characterized in that it has a height lower than the height of the pier 해상 교량의 거더 브리지 설치 시공방법.How to install and construct a girder bridge for offshore bridges. 제1항에 있어서,The method of claim 1, 상기 거더브리지 이송준비 단계에서 상기 거더브리지의 길이와 폭은 운반 수단인 트랜스포터보다 크게 이루어지고, 상기 리프팅용 로딩빔은 상기 거더브리지의 폭방향으로 가로지르게 트랜스포터에 구비되고,In the girder bridge transfer preparation step, the length and width of the girder bridge is made larger than that of the transporter, which is a transportation means, and the loading beam for lifting is provided on the transporter so as to traverse in the width direction of the girder bridge, 상기 거더브리지 로딩 단계는 상기 트랜스포터가 바지선으로 진입됨에 따라 바지선의 평형수를 조절하여 밸런싱하도록 이루어지고,The loading of the girder bridge is performed to balance the ballast water of the barge as the transporter enters the barge, 상기 거더브리지 리프팅 단계는, 바지선에 설비된 지지대를 제1 구조물의 로딩빔 하부에 위치시킨 후, 트랜스포터 자체가 하강하여 제1 구조물을 지지대의 상면에 안착시킨 다음, 거더브리지가 부두에 평행하도록 바지선을 접안하여 고박한 다음, 스트랜드잭 리프트 타워를 이용하여 리프팅용 로딩빔에 연결하여 제1 구조물을 바지선으로부터 소정 높이 리프팅하는 것으로 이루어지고,In the lifting of the girder bridge, after placing the support provided on the barge under the loading beam of the first structure, the transporter itself descends to place the first structure on the upper surface of the support, and then the girder bridge is parallel to the pier. The barge is docked and secured, and then the first structure is lifted from the barge by a predetermined height by connecting to the loading beam for lifting using a strand jack lift tower, 상기 트러스구조물 로딩 단계는, 높이보상 트러스구조물을 실은 운반 수단을, 부두에 접안된 바지선으로 이동시켜서 소정 높이 리프팅되어 있는 제1 구조물의 하부 측에 이동 완료 후, 트랜스포터 자체가 하강하여 높이보상 트러스구조물을 지지대의 상면에 안착시키는 것으로 이루어지고,In the loading step of the truss structure, the transport means loaded with the height compensation truss structure is moved to the barge berthed to the pier, and after completing the movement to the lower side of the first structure that is lifted a predetermined height, the transporter itself descends and the height compensation truss It consists of seating the structure on the upper surface of the support, 상기 로딩빔 컷팅 단계는, 스트랜드잭 리프트타워를 이용하여 제1 구조물을 하강시켜 트러스구조물 상면에 안착시켜서 제2 구조물을 형성한 다음, 리프팅용 로딩암의 양 가장자리를 소정 길이 컷팅하여 제2 구조물의 리프팅을 위한 통로를 확보하며, 확보된 통로를 통해 스트랜드잭 리프트타워의 와이어를 제2 구조물의 트러스구조물의 양단부에 결합시키는 것으로 이루어지며,In the loading beam cutting step, the first structure is lowered using a strand jack lift tower and seated on the upper surface of the truss structure to form a second structure, and then both edges of the lifting loading arm are cut to a predetermined length to form a second structure. A passage for lifting is secured, and the wire of the strand jack lift tower is coupled to both ends of the truss structure of the second structure through the secured passage. 상기 높이보상 트러스구조물은 교각 높이보다 낮은 높이를 갖는 스트랜드잭 리프트타워의 최대 리프팅 높이를 기초한 설계 높이를 갖는 것을 특징으로 하는The height compensation truss structure is characterized in that it has a design height based on the maximum lifting height of the strand jack lift tower having a height lower than the pier height. 해상 교량의 거더 브리지 설치 시공방법.How to install and construct a girder bridge for offshore bridges. 제1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 거더브리지 설치 준비 단계는, 상기 로딩빔 컷팅 단계 후, 거더브리지를 설치할 교각 측방으로 바지선을 이동시키고, 바지선의 평형수를 조절하여 바지선의 높이를 소정 높이로 밸런싱하는 것으로 이루어지며,The preparatory step for installing the girder bridge includes moving the barge to the side of the pier to install the girder bridge after the loading beam cutting step and balancing the height of the barge to a predetermined height by adjusting the ballast water of the barge, 상기 트러스구조물 리프팅 단계는, 바지선의 양측에 복수의 윈치를 연결하여 고박한 다음, 바지선의 스트랜드잭 리프트타워를 이용하여 제2 구조물을 리프팅하되, 제2 구조물의 거더브리지가 교각의 높이보다 소정 높이 높은 위치까지 상승시키도록 이루어지는 것을 특징으로 하는In the lifting of the truss structure, a plurality of winches are connected to both sides of the barge and secured, and then the second structure is lifted using the strand jack lift tower of the barge, and the girder bridge of the second structure is a predetermined height than the height of the pier. Characterized in that it is made to rise to a high position 해상 교량의 거더 브리지 설치 시공방법.How to install and construct a girder bridge for offshore bridges. 제3항에 있어서,The method of claim 3, 상기 설치위치 이동 단계는, 바지선의 양측에 윈치로 연결되어 고박된 윈치를 이용하여 일측의 윈치와 타측의 윈치를 서로 연동시키면서 거더브리지가 교각의 설치 위치까지 바지선을 이동시키는 것으로 이루어지며,The step of moving the installation location comprises moving the barge to the installation location of the pier while the winch on one side and the winch on the other side are interlocked using a winch connected to both sides of the barge and secured, 상기 설치 완료 단계는, 제2 구조물을 하강시켜 거더브리지의 양단부를 두 교각의 설치부에 설치시키고, 로딩빔으로부터 거더브리지를 분리한 후, 로딩빔과 높이보상 트러스구조물을 하강시킨 다음, 바지선을 설치 위치로부터 이동시키는 것으로 이루어지는 것을 특징으로 하는In the step of completing the installation, the second structure is lowered to install both ends of the girder bridge on the installation portions of the two piers, the girder bridge is separated from the loading beam, and the loading beam and the height compensation truss structure are lowered, and then the barge is installed. Characterized in that consisting of moving from the installation position 해상 교량의 거더 브리지 설치 시공방법.How to install and construct a girder bridge for offshore bridges.
PCT/KR2019/006563 2019-03-19 2019-05-31 Method for installing and constructing girder bridge of marine bridge Ceased WO2020189847A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2019-0030972 2019-03-19
KR1020190030972A KR102039305B1 (en) 2019-03-19 2019-03-19 Construction method for installing girder bridge of marine bridge

Publications (1)

Publication Number Publication Date
WO2020189847A1 true WO2020189847A1 (en) 2020-09-24

Family

ID=68420914

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2019/006563 Ceased WO2020189847A1 (en) 2019-03-19 2019-05-31 Method for installing and constructing girder bridge of marine bridge

Country Status (2)

Country Link
KR (1) KR102039305B1 (en)
WO (1) WO2020189847A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114197329A (en) * 2021-12-15 2022-03-18 中交路桥华南工程有限公司 Main beam erecting method
CN115652792A (en) * 2022-10-28 2023-01-31 中铁四局集团第二工程有限公司 Steel trestle bridge bench method construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113186836A (en) * 2021-06-01 2021-07-30 中铁七局集团第三工程有限公司 Construction method of brand-new prestress integral bridge falsework
CN119514006B (en) * 2025-01-23 2025-04-18 中铁四局集团有限公司 Optimization method and system for load transmission structure of cable-stayed bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0594151A1 (en) * 1992-10-21 1994-04-27 Giorgio Zuccolo Arrigoni Method and device for erecting long spanning girders, particularly on viaducts
KR19990080475A (en) * 1998-04-17 1999-11-05 김형벽 Offshore bridge and fixed offshore structure installation device and method
JP2004115174A (en) * 2002-09-25 2004-04-15 Mitsubishi Heavy Ind Ltd Movable carriage for member erection, and bridging member erection method using it
KR101026014B1 (en) * 2010-11-25 2011-03-30 (주) 한국비계 Bridge deck construction method using lifting jack in water
KR101289426B1 (en) * 2011-12-27 2013-07-24 주식회사 한진중공업 Constructing method for cantilever structure and cantilever structure constructed by the method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101192052B1 (en) 2011-01-18 2012-10-17 주식회사 벤트코리아 Method for constructing temporary bridge using movable boxgirder
KR101232704B1 (en) 2011-04-15 2013-02-13 브이에스엘코리아 주식회사 The installation and dismantlement method of main girder for bridge temporary
KR101624627B1 (en) 2016-01-14 2016-05-26 주식회사 성화씨앤비 Girder and bridge construction method thereof
KR101744437B1 (en) 2016-02-23 2017-06-07 이종란 Construction method of temporary bridge using camber

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0594151A1 (en) * 1992-10-21 1994-04-27 Giorgio Zuccolo Arrigoni Method and device for erecting long spanning girders, particularly on viaducts
KR19990080475A (en) * 1998-04-17 1999-11-05 김형벽 Offshore bridge and fixed offshore structure installation device and method
JP2004115174A (en) * 2002-09-25 2004-04-15 Mitsubishi Heavy Ind Ltd Movable carriage for member erection, and bridging member erection method using it
KR101026014B1 (en) * 2010-11-25 2011-03-30 (주) 한국비계 Bridge deck construction method using lifting jack in water
KR101289426B1 (en) * 2011-12-27 2013-07-24 주식회사 한진중공업 Constructing method for cantilever structure and cantilever structure constructed by the method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
BUSINESS PROPOSAL FOR MUNBAI BRIDGE INSTALLATION PROJECT, 25 February 2019 (2019-02-25) *
BUSINESS PROPOSAL FOR MUNBAI BRIDGE INSTALLATION PROJECT, 9 January 2019 (2019-01-09) *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114197329A (en) * 2021-12-15 2022-03-18 中交路桥华南工程有限公司 Main beam erecting method
CN114197329B (en) * 2021-12-15 2024-02-06 中交路桥华南工程有限公司 Main girder erection method
CN115652792A (en) * 2022-10-28 2023-01-31 中铁四局集团第二工程有限公司 Steel trestle bridge bench method construction method
CN115652792B (en) * 2022-10-28 2023-12-22 中铁四局集团有限公司 Steel trestle bench method construction method

Also Published As

Publication number Publication date
KR102039305B1 (en) 2019-10-31

Similar Documents

Publication Publication Date Title
WO2020189847A1 (en) Method for installing and constructing girder bridge of marine bridge
WO2020162665A1 (en) Apparatus for installation and disassembly of wind turbine and construction method using same
US6318931B1 (en) Method and apparatus for the offshore installation of multi-ton packages such as deck packages and jackets
CN106320182A (en) Suspension bridge bank slope beam section long sling swing-shifting mounting device and method
WO1998010145A2 (en) Method and apparatus for the offshore installation of multi-ton packages
WO1999013164A9 (en) Method and apparatus for the offshore installation of multi-ton packages such as deck packages and jackets
CN109680616B (en) Construction method for hoisting main beam by using cable crane and reverse lifting equipment
WO2018133045A1 (en) Method for mounting self-anchored suspension bridge
CN206052568U (en) The long hoist cable of suspension bridge bank slope beam section swings shifting erecting device
CN214935269U (en) Multifunctional lifting appliance for large-section lifting
CN111039206A (en) Method for hoisting steel box girder of cable-stayed bridge
CN113106866B (en) Counterweight type mounting method of main beam
CN216474531U (en) Water steel box girder lifting, sliding and installing system with existing bridge penetrating downwards
CN118498225A (en) Construction method for storing large-section beam in low position in cable-less area under tower and integrally lifting large-section beam
CN112982183A (en) Counterweight type mounting system of main beam
CN118207797A (en) A double-segment hoisting device and method for a large-scale suspension bridge steel box girder in deep waters
CN214783346U (en) Counterweight type mounting system of main beam
CN114525739B (en) Long heavy cable hanging installation method for multi-point hanging of under-bridge span cables
CN112482224B (en) Construction method for installing steel truss inspection vehicle track
CN115162184A (en) Suspension bridge steel truss erecting system and method
CN113718625B (en) Construction method for cable-free beam section of tower area of composite beam cable-stayed bridge
JP2022138334A (en) Sliding swivel device
CN215714701U (en) Kajinsi construction device
CN114108479B (en) Construction method for multi-machine collaborative hoisting of stiffening beam of large-tonnage suspension bridge
CN216920054U (en) Long heavy cable hanging installation device for multipoint hanging of underbridge expansion cable

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19919729

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 19919729

Country of ref document: EP

Kind code of ref document: A1