WO2018177306A1 - Fabricated underground wall and construction method thereof - Google Patents
Fabricated underground wall and construction method thereof Download PDFInfo
- Publication number
- WO2018177306A1 WO2018177306A1 PCT/CN2018/080790 CN2018080790W WO2018177306A1 WO 2018177306 A1 WO2018177306 A1 WO 2018177306A1 CN 2018080790 W CN2018080790 W CN 2018080790W WO 2018177306 A1 WO2018177306 A1 WO 2018177306A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- wall
- chain
- walls
- cutter
- adjacent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
Definitions
- the invention relates to a prefabricated underground wall and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
- the existing underground continuous wall technology uses a trenching machine on the ground to excavate a long and narrow deep trough under the condition of mud retaining wall, hoist the steel cage in the trough, and pour the underwater concrete into a unit trough section. This is done piece by piece.
- the main defects are as follows: 1) The underwater construction quality in the tank is difficult to control and detect, and the construction period is long; 2) The interface between the groove sections is difficult to construct and easy to seep; 3) The slotting machine is high and moves along the circumference. Applications are limited.
- the invention provides a prefabricated underground wall and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantage thereof is that the assembly of the adjacent two walls 1 is embedded and welded by the concave and convex, and the connection is safe and reliable.
- the sealing is good; the wall 1 itself has a chain knife for excavating the bottom of the rock, the factory prefabricated wall, the block is divided or the whole is lowered after the site is spliced, the construction is simple, the construction period is short, and the cost is low.
- the underground wall 1 is assembled by the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, convexity of one wall
- the platform is embedded in the groove of another wall, and is divided into two structures: A and B: A.
- the interface of the same wall has both a groove and a boss, and the other wall is reversed;
- B a wall is a groove, and the other wall It is a boss;
- the bottom and sides of the wall 1 are provided with a track 2
- the track 2 is provided with a chain knife 3
- the chain knife 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1, the chain
- the upper plane of the lower wall 1 is lowered to the height set at the ground with the chain cutter, and then the upper part is assembled.
- Wall 1-2 the interface of the adjacent two walls is welded before entering the underground to make it integrated.
- the invention has the advantages that the assembly of the adjacent two walls 1 adopts the concave-convex embedded welding and splicing, and the connection is safe and reliable, and the wall 1 itself has a chain cutter for excavating the bottom rock of the wall, and the factory prefabricated wall 1 is divided into blocks or the whole is dropped after the site is spliced.
- the construction is simple, the construction period is short, and the cost is low.
- Figure 1 is a schematic view showing a structure in which the splicing joints of the adjacent two walls 1 are respectively provided with a concave and convex sub-port of a steel structure, that is, a boss of one wall is embedded in a groove of the other wall;
- Figure 2 is a view of the A-A of Figure 1, and is also a structural schematic diagram of the welding of the bottom wall 1-1 and the upper wall 1-2 rows.
- Figure 3 is a B-direction view of Figure 1, and is also a structural schematic diagram of the chain cutter driving device 5 composed of the driving power device 5-1, the spoil processing device 5-2 and the frame 5-3, and is also a chain knife 3 and a chain knife.
- Figure 4 is a C-C view of Figure 3, also a cross-sectional view of the middle portion of the wall 1;
- Figure 5 is an enlarged view of a portion I of Figure 2, which is also a schematic structural view of the rail 2 at the bottom of the bottom wall 1-1, and is also a mud nozzle 6-1 and a mud pipeline 6 of the mud pipeline device 6 on the bottom wall 1-1.
- Figure 6 is an enlarged view of a portion II of Figure 2, that is, one wall of the adjacent two walls 1 is a groove, and the other wall is a boss, and a plurality of holes are provided at the same position of the adjacent two walls, and the holes are formed at the time of splicing.
- a schematic structural view of the pin 7 is inserted therein, and is also a structural schematic view in which the connecting steel plate 8 is welded at the interface of the adjacent two walls 1 and the thickness after welding is not greater than the thickness of the underground wall 1;
- FIG. 8 is a schematic structural view of another space-curable chain cutter 3, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;
- Figure 9 is a structural schematic view showing the assembly of the chain cutter 3 and the driving device 5 by assembling the bottom wall 1-1 and welding it into a whole;
- Figure 10 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated rock to the top, the wall 1-1 and the bottom of the chain knife 3 together to drop to the set position Schematic diagram of the structure;
- Figure 11 is a structural schematic view showing the removal of the driving device 5 after the upper chain cutter 3 is disconnected;
- Figure 12 is a view of the A-A of Figure 11, which is also a schematic structural view of the bottom wall 1-1, and is a structural schematic view of the bottom wall 1-1 on which the plane is lowered to a height position set from the ground;
- Figure 13 is a schematic view showing the structure after assembling the splicing upper wall 1-2, installing the chain cutter 3 and the driving device 5;
- Figure 14 is a view of the A-A of Figure 13, and is also a structural schematic view in which the pin 7 is inserted into the hole during splicing, and the interface is welded by the steel plate 8 to be integrated;
- Figure 15 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated geotechnical to the top, the welded wall 1 and the bottom of the chain knife 3 down to a schematic diagram of the structure of the set position;
- Figure 16 is a schematic structural view of the assembly and splicing construction of all the walls 1;
- Fig. 17 is a view taken along the line A in Fig. 16, and is a schematic view showing the structure in which the temporary tooling 4 is taken out after the wall 1 is constructed.
- 1 is the underground wall, which is assembled from the bottom wall 1-1 and several walls 1-2; 1-1 is the bottom wall of the underground wall 1; 1-2 is the wall above the bottom wall of the underground wall 1; It is a rail provided on the bottom and sides of the wall 1; 3 is a chain cutter for excavating rock and soil, consisting of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1; 3-1 is a chain cutter 3 3-2 is a cutter constituting the chain cutter 3; 4 is a temporary tooling during construction; 5 is a chain cutter driving device, which is driven by the power unit 5-1, the spoil handling device 5-2, and the frame 5-3.
- composition Composition
- 5-1 is the driving power device
- 5-2 is the spoil handling device
- 5-3 is the frame
- 6 is the mud pipeline device
- 6-1 is the mud nozzle on the bottom of the wall 1
- 6-2 is the wall 1 internal mud pipeline
- 7 is the pin inserted in the hole when the wall 1 is spliced
- 8 is the steel plate welded when the wall 1 is spliced.
- the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembly joints of the adjacent two walls 1 are respectively provided with concave and convex ports of steel structure, that is, the bosses of one wall are embedded in the concave of the other wall In the trough, there are two structures A and B: A. The interface of the same wall has both grooves and bosses, and the other wall is opposite; B, one wall is a groove, the other wall is a boss; wall 1 A rail 2 is arranged on the bottom and both sides, and a chain cutter 3 is arranged on the rail 2 during construction. The chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1.
- One wall of the adjacent two wall interfaces is a groove, and the other wall is a boss.
- a plurality of holes are arranged at the same position of the adjacent two walls, and a pin is inserted into the hole during the splicing.
- the interface between the adjacent two walls is welded with a connecting steel plate, and the thickness after welding is not greater than the thickness of the underground wall.
- the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, a wall
- the boss is embedded in the groove of the other wall, and is divided into two structures: A and B: A.
- the interface of the same wall has both a groove and a boss, and the other wall is reversed; B, a wall is a groove, and another One wall is a boss.
- the bottom of the wall 1 and the two sides are provided with a track 2, and the track 2 is provided with a chain cutter 3, the width of the chain cutter 3 is smaller than the width of the groove mouth at the interface, and the chain cutter 3 is connected by the chain 3-1 and the chain 3
- the tool 3-2 is composed of -1, and the driving power device 5-1 drives the chain cutter 3.
- the rock belt is brought up to the upper side, and the device 5-2 separates the rock soil brought by the chain cutter 3 from the bottom of the wall 1 with the chain cutter 3, and the wall 1 and the bottom chain cutter 3 simultaneously run downward, and the upper plane of the lower wall 1-1 follows
- the upper wall 1-2 is assembled and the interface of the adjacent two walls is welded before entering the ground to make it integrated; a wall at the interface between the adjacent two walls
- the groove is the groove, the other wall is a boss, and a plurality of holes are arranged at the same position of the adjacent two walls, and the pin 7 is inserted into the hole during the splicing; the connecting steel plate 8 is welded at the interface of the adjacent two walls, and the welding is performed.
- the thickness afterwards is not greater than the thickness of the underground wall.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
本发明涉及的是一种装配式地下墙及其施工法,属于土木工程基础施工技术领域。The invention relates to a prefabricated underground wall and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
现有地下连续墙技术是在地面上利用挖槽机械,在泥浆护壁的条件下,开挖岀一条狭长的深槽,在槽内吊放钢筋笼,浇筑水下混凝土筑成一个单元槽段,如此逐段进行。其主要缺陷:1)槽内水下施工质量难以控制和检测、施工周期长;2)槽段之间的接口施工困难且易渗水;3)开槽机械较高,且要沿着周长移动应用场合受到限制。The existing underground continuous wall technology uses a trenching machine on the ground to excavate a long and narrow deep trough under the condition of mud retaining wall, hoist the steel cage in the trough, and pour the underwater concrete into a unit trough section. This is done piece by piece. The main defects are as follows: 1) The underwater construction quality in the tank is difficult to control and detect, and the construction period is long; 2) The interface between the groove sections is difficult to construct and easy to seep; 3) The slotting machine is high and moves along the circumference. Applications are limited.
发明内容Summary of the invention
本发明提出的是一种装配式地下墙及其施工法,其目的旨在克服现有技术存在的缺陷,其主要优点:相邻两墙1的装配处采用凹凸嵌入焊接拼接,连接安全可靠,密封性好;墙1自身带有挖掘其底部岩土的链刀,工厂预制墙,现场拼接后分块或者整体下降,施工简单,施工周期短,成本低。The invention provides a prefabricated underground wall and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantage thereof is that the assembly of the adjacent two
本发明的技术解决方案:地下墙1由底墙1-1和若干墙1-2装配而成;相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台;墙1的底部和两侧设有轨道2,施工时轨道2上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,墙1和底部的链刀3同时向下运行,下部墙1的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙1-2,相邻两墙的接口处在进入地下前先进行焊接,使之成为一体。The technical solution of the invention is that the
本发明的优点:邻两墙1的装配处采用凹凸嵌入焊接拼接,连接安全可靠,墙1自身带有挖掘其底部岩土的链刀,工厂预制墙1,现场拼接后分块或者整体下降,施工简单,施工周期短,成本低。The invention has the advantages that the assembly of the adjacent two
图1是相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内的结构示意图;Figure 1 is a schematic view showing a structure in which the splicing joints of the adjacent two
图2是图1的A-A视图,也是底墙1-1和上部墙1-2行焊接成为一体的结构示意图Figure 2 is a view of the A-A of Figure 1, and is also a structural schematic diagram of the welding of the bottom wall 1-1 and the upper wall 1-2 rows.
图3是图1的B向视图,也是由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成的链刀驱动装置5的结构示意图,也是链刀3、链刀驱动装置5和墙1组成施工状态的结构示意图;Figure 3 is a B-direction view of Figure 1, and is also a structural schematic diagram of the chain
图4是图3的C-C视图,也是墙1中间部分的剖视图;Figure 4 is a C-C view of Figure 3, also a cross-sectional view of the middle portion of the
图5是图2的Ⅰ局部的放大视图,也是底墙1-1底部的轨道2的结构示意图,也是泥浆管路装置6在底墙1-1上的泥浆喷嘴6-1和泥浆管路6-2的结构示意图;Figure 5 is an enlarged view of a portion I of Figure 2, which is also a schematic structural view of the
图6是图2的Ⅱ局部的放大视图,也是相邻两墙1接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴7的结构示意图,也是相邻两墙1的接口处焊接有连接钢板8,且焊接后的厚度不大于地下墙1的厚度的结构示意图;Figure 6 is an enlarged view of a portion II of Figure 2, that is, one wall of the adjacent two
图7是链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图;7 is a schematic structural view of the
图8是另一种可空间弯曲链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图;FIG. 8 is a schematic structural view of another space-
图9是拼装底部墙1-1,通过焊接使之成为一整体,安装链刀3和驱动装置5的结构示意图;Figure 9 is a structural schematic view showing the assembly of the
图10是墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方,墙1-1和底部的链刀3一起下降至设定位置的结构示意图;Figure 10 is the bottom of the wall 1-1
图11是拆除驱动装置5,上部链刀3断开后的结构示意图;Figure 11 is a structural schematic view showing the removal of the
图12是图11的A-A视图,也是底墙1-1的结构示意图,也是底墙1-1上平面下降到距地面设定的高度位置的结构示意图;Figure 12 is a view of the A-A of Figure 11, which is also a schematic structural view of the bottom wall 1-1, and is a structural schematic view of the bottom wall 1-1 on which the plane is lowered to a height position set from the ground;
图13是装配拼接上部墙1-2,安装链刀3和驱动装置5后的结构示意图;Figure 13 is a schematic view showing the structure after assembling the splicing upper wall 1-2, installing the
图14是图13的A-A视图,也是拼接时在孔内插入销轴7,接口处利用钢板8焊接使之成为一体的结构示意图;Figure 14 is a view of the A-A of Figure 13, and is also a structural schematic view in which the
图15是墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方,已焊接成一体的墙1和底部的链刀3一起下降到设定位置的结构示意图;Figure 15 is the bottom of the wall 1-1
图16是完成全部墙1的装配拼接施工的结构示意图;Figure 16 is a schematic structural view of the assembly and splicing construction of all the
图17是图16的A向视图,也是墙1施工完后抽出临时工装4的结构示意图。Fig. 17 is a view taken along the line A in Fig. 16, and is a schematic view showing the structure in which the
图中的1是地下墙,由底墙1-1和若干墙1-2装配而成;1-1是地下墙1的底墙;1-2是地下墙1的底墙以上的墙;2是墙1的底部和两侧设有的轨道;3是挖掘岩土的链刀,由链条3-1和安装在链条3-1上的刀具3-2组成;3-1是组成链刀3的链条;3-2是组成链刀3的刀具;4是施工时的临时工装;5是链刀驱动装置,由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成;5-1是驱动动力装置;5-2是弃土处理装置;5-3是机架;6是泥浆管路装置;6-1是墙1底部上的泥浆喷嘴;6-2是墙1内部的泥浆管路;7是墙1拼接时在孔内插的销轴;8是墙1拼接时焊接的钢板。1 is the underground wall, which is assembled from the bottom wall 1-1 and several walls 1-2; 1-1 is the bottom wall of the
地下墙1由底墙1-1和若干墙1-2装配而成;相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台;墙1的底部和两侧设有轨道2,施工时轨道2上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,墙1和底部的链刀3同时向下运行,下部墙1的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙1-2,相邻两墙的接口处在进入地下前先进行焊接,使之成为一体。The
所述的相邻两墙接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴。One wall of the adjacent two wall interfaces is a groove, and the other wall is a boss. A plurality of holes are arranged at the same position of the adjacent two walls, and a pin is inserted into the hole during the splicing.
所述的相邻两墙的接口处焊接有连接钢板,且焊接后的厚度不大于地下墙的厚度。The interface between the adjacent two walls is welded with a connecting steel plate, and the thickness after welding is not greater than the thickness of the underground wall.
所述的具体施工法分如下步骤:The specific construction method described is divided into the following steps:
1)预制墙1-1和墙1-2各模块;1) Prefabricated wall 1-1 and wall 1-2 modules;
2)清理现场,使之满足施工条件;2) Clean up the site to meet the construction conditions;
3)将预制的墙1-1和墙1-2的各模块运至现场;3) transport the prefabricated walls 1-1 and 1-2 modules to the site;
4)拼装底部墙1-1,通过焊接使之成为一整体,安装链刀3和驱动装置等;4) Assembling the bottom wall 1-1, making it a whole by welding, installing the
5)启动驱动装置,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;5) Start the driving device, the
6)墙1-1和底部的链刀3一起下降;6) Wall 1-1 and the
7)墙1-1的上平面下降到距地面设定的高度,停止驱动装置;7) The upper plane of the wall 1-1 is lowered to a height set from the ground, and the driving device is stopped;
8)装配拼接上部墙1-2,接口处焊接,使之成为一体;8) Assembling and splicing the upper wall 1-2, the joint is welded to make it integrated;
9)启动驱动装置,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;9) Start the driving device, the
10)已焊接成一体的墙1和底部的链刀3一起下降;10) the
11)已焊接成一体的墙1的上平面下降到距地面设定的高度,停止驱动装置;11) The upper plane of the
12)装配拼接上部墙1-2,接口处焊接,使之成为一体;12) Assembling and splicing the upper wall 1-2, welding at the interface to make it integrated;
重复上述9)至12)的施工,直至完成全部墙1的装配拼接施工。Repeat the above construction of 9) to 12) until the assembly and splicing of all the
下面结合附图进一步描述本发明的技术方案:The technical solution of the present invention is further described below with reference to the accompanying drawings:
如图1~图8所示,地下墙1由底墙1-1和若干墙1-2装配而成;相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台。墙1的底部和两侧设有轨道2,施工时轨道2上装有链刀3,链刀3的宽度小于接口处凹槽口部的宽度,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,驱动动力装置5-1驱动链刀3,链刀3工作时仅挖掘墙1底部的岩土,由下向上运行的链刀3将墙1底部已挖掘的岩土带至上方,装置5-2将链刀3从墙1底部带上来的岩土与链刀3分离,墙1和底部链刀3同时向下运行,下部墙1-1的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙1-2,相邻两墙的接口处在进入地下前先进行焊接,使之成为一体;相邻两墙接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴7;相邻两墙的接口处焊接有连接钢板8,且焊接后的厚度不大于地下墙的厚度。As shown in FIG. 1 to FIG. 8 , the
如图9~图17所示,具体施工法分如下步骤:As shown in Figure 9 to Figure 17, the specific construction method is divided into the following steps:
1)预制墙1-1和墙1-2各模块;1) Prefabricated wall 1-1 and wall 1-2 modules;
2)清理现场,使之满足施工条件;2) Clean up the site to meet the construction conditions;
3)将预制的墙1-1和墙1-2的各模块运至现场;3) transport the prefabricated walls 1-1 and 1-2 modules to the site;
4)拼装底部墙1-1,通过焊接使之成为一整体,安装链刀3和驱动装置5等;4) Assembling the bottom wall 1-1, making it a whole by welding, installing the
5)启动驱动装置5,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3 将已挖掘的岩土带至上方;5) Start the
6)墙1-1和底部的链刀3一起下降;6) Wall 1-1 and the
7)墙1-1的上平面下降到距地面设定的高度,停止驱动装置5;7) The upper plane of the wall 1-1 is lowered to a height set from the ground, and the
8)装配拼接上部墙1-2,接口处焊接,使之成为一体;8) Assembling and splicing the upper wall 1-2, the joint is welded to make it integrated;
9)启动驱动装置5,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;9) Start the
10)已焊接成一体的墙1和底部的链刀3一起下降;10) the welded
11)已焊接成一体的墙1的上平面下降到距地面设定的高度,停止驱动装置5;11) The upper plane of the welded
12)装配拼接上部墙1-2,接口处焊接,使之成为一体;12) Assembling and splicing the upper wall 1-2, welding at the interface to make it integrated;
重复上述9)至12)的施工,直至完成全部墙1的装配拼接施工。Repeat the above construction of 9) to 12) until the assembly and splicing of all the
Claims (4)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710195875.5A CN106836192A (en) | 2017-03-29 | 2017-03-29 | A kind of assembled subterranean wall and its construction method |
| CN201710195875.5 | 2017-03-29 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2018177306A1 true WO2018177306A1 (en) | 2018-10-04 |
Family
ID=59141351
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CN2018/080790 Ceased WO2018177306A1 (en) | 2017-03-29 | 2018-03-28 | Fabricated underground wall and construction method thereof |
Country Status (2)
| Country | Link |
|---|---|
| CN (1) | CN106836192A (en) |
| WO (1) | WO2018177306A1 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106836192A (en) * | 2017-03-29 | 2017-06-13 | 王燏斌 | A kind of assembled subterranean wall and its construction method |
| CN108035338A (en) * | 2017-11-24 | 2018-05-15 | 上海市机械施工集团有限公司 | Prefabricated ground walls and its construction method |
| CN114108797A (en) * | 2021-10-21 | 2022-03-01 | 王树生 | Wall foundation and construction device and method thereof |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5985021A (en) * | 1982-11-05 | 1984-05-16 | Kajima Corp | Method and apparatus for construction of underground continuous wall |
| JPS62233328A (en) * | 1986-04-01 | 1987-10-13 | Fusao Sakano | Method and apparatus for setting retaining wall by excavator |
| JPH04179726A (en) * | 1990-11-13 | 1992-06-26 | Kazutoshi Isachi | Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same |
| CN2260103Y (en) * | 1996-08-05 | 1997-08-20 | 郭同元 | Pile |
| CN103334422A (en) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof |
| CN105887806A (en) * | 2016-06-13 | 2016-08-24 | 上海强劲地基工程股份有限公司 | Prefabricated underground diaphragm wall and its construction method |
| CN106836192A (en) * | 2017-03-29 | 2017-06-13 | 王燏斌 | A kind of assembled subterranean wall and its construction method |
-
2017
- 2017-03-29 CN CN201710195875.5A patent/CN106836192A/en active Pending
-
2018
- 2018-03-28 WO PCT/CN2018/080790 patent/WO2018177306A1/en not_active Ceased
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5985021A (en) * | 1982-11-05 | 1984-05-16 | Kajima Corp | Method and apparatus for construction of underground continuous wall |
| JPS62233328A (en) * | 1986-04-01 | 1987-10-13 | Fusao Sakano | Method and apparatus for setting retaining wall by excavator |
| JPH04179726A (en) * | 1990-11-13 | 1992-06-26 | Kazutoshi Isachi | Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same |
| CN2260103Y (en) * | 1996-08-05 | 1997-08-20 | 郭同元 | Pile |
| CN103334422A (en) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof |
| CN105887806A (en) * | 2016-06-13 | 2016-08-24 | 上海强劲地基工程股份有限公司 | Prefabricated underground diaphragm wall and its construction method |
| CN106836192A (en) * | 2017-03-29 | 2017-06-13 | 王燏斌 | A kind of assembled subterranean wall and its construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106836192A (en) | 2017-06-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110043264B (en) | Construction method for jacking prefabricated rectangular vertical shaft structural type | |
| CN107059877A (en) | Basis and its construction method of the bottom with chain knife during a kind of construction | |
| JP5235748B2 (en) | Wall metal fittings and underground continuous wall construction method | |
| WO2018177306A1 (en) | Fabricated underground wall and construction method thereof | |
| WO2018133740A1 (en) | Underground building and construction method for same | |
| WO2018177307A1 (en) | Fabricated underground building and construction method thereof | |
| CN104452804B (en) | Wall telephone is made in tunneling boring stirring cutting | |
| WO2018133711A1 (en) | Pier foundation and construction method therefor | |
| WO2018133746A1 (en) | Underground building formed of piles and walls, and method for constructing same | |
| CN109914477B (en) | Prefabricated pipeline of assembling of utility tunnel | |
| WO2018177304A1 (en) | Fabricated underground building and construction method thereof | |
| CN207727550U (en) | A kind of assembled subterranean wall | |
| CN103243763B (en) | Rectification mechanism of slotting machine | |
| WO2018177305A1 (en) | Groove pile for fabricated underground building and construction method thereof | |
| CN207228156U (en) | A kind of underground structure being made of stake and wall | |
| CN105569572A (en) | Square drill bit | |
| CN207419440U (en) | A kind of groove stake for assembled hypogee | |
| CN207714369U (en) | A kind of assembled hypogee | |
| WO2018177308A1 (en) | Fabricated underground building interface structure and construction method thereof | |
| WO2018166523A1 (en) | Deep-water foundation and construction device and construction method therefor | |
| CN105926582A (en) | Prefabricated hollow component underground tunneling construction combined body, continuous wall and construction method | |
| CN108824523B (en) | Chain saw type cutting box | |
| CN207727613U (en) | A kind of assembled hypogee | |
| CN113756366A (en) | Novel pipe curtain-box culvert integrated tunnel structure and construction method | |
| CN218175904U (en) | Sinking construction device for bottom on-site construction of upper assembled underground building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 18777826 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 18777826 Country of ref document: EP Kind code of ref document: A1 |