[go: up one dir, main page]

WO2018177306A1 - Fabricated underground wall and construction method thereof - Google Patents

Fabricated underground wall and construction method thereof Download PDF

Info

Publication number
WO2018177306A1
WO2018177306A1 PCT/CN2018/080790 CN2018080790W WO2018177306A1 WO 2018177306 A1 WO2018177306 A1 WO 2018177306A1 CN 2018080790 W CN2018080790 W CN 2018080790W WO 2018177306 A1 WO2018177306 A1 WO 2018177306A1
Authority
WO
WIPO (PCT)
Prior art keywords
wall
chain
walls
cutter
adjacent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/CN2018/080790
Other languages
French (fr)
Chinese (zh)
Inventor
王燏斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of WO2018177306A1 publication Critical patent/WO2018177306A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Definitions

  • the invention relates to a prefabricated underground wall and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
  • the existing underground continuous wall technology uses a trenching machine on the ground to excavate a long and narrow deep trough under the condition of mud retaining wall, hoist the steel cage in the trough, and pour the underwater concrete into a unit trough section. This is done piece by piece.
  • the main defects are as follows: 1) The underwater construction quality in the tank is difficult to control and detect, and the construction period is long; 2) The interface between the groove sections is difficult to construct and easy to seep; 3) The slotting machine is high and moves along the circumference. Applications are limited.
  • the invention provides a prefabricated underground wall and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantage thereof is that the assembly of the adjacent two walls 1 is embedded and welded by the concave and convex, and the connection is safe and reliable.
  • the sealing is good; the wall 1 itself has a chain knife for excavating the bottom of the rock, the factory prefabricated wall, the block is divided or the whole is lowered after the site is spliced, the construction is simple, the construction period is short, and the cost is low.
  • the underground wall 1 is assembled by the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, convexity of one wall
  • the platform is embedded in the groove of another wall, and is divided into two structures: A and B: A.
  • the interface of the same wall has both a groove and a boss, and the other wall is reversed;
  • B a wall is a groove, and the other wall It is a boss;
  • the bottom and sides of the wall 1 are provided with a track 2
  • the track 2 is provided with a chain knife 3
  • the chain knife 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1, the chain
  • the upper plane of the lower wall 1 is lowered to the height set at the ground with the chain cutter, and then the upper part is assembled.
  • Wall 1-2 the interface of the adjacent two walls is welded before entering the underground to make it integrated.
  • the invention has the advantages that the assembly of the adjacent two walls 1 adopts the concave-convex embedded welding and splicing, and the connection is safe and reliable, and the wall 1 itself has a chain cutter for excavating the bottom rock of the wall, and the factory prefabricated wall 1 is divided into blocks or the whole is dropped after the site is spliced.
  • the construction is simple, the construction period is short, and the cost is low.
  • Figure 1 is a schematic view showing a structure in which the splicing joints of the adjacent two walls 1 are respectively provided with a concave and convex sub-port of a steel structure, that is, a boss of one wall is embedded in a groove of the other wall;
  • Figure 2 is a view of the A-A of Figure 1, and is also a structural schematic diagram of the welding of the bottom wall 1-1 and the upper wall 1-2 rows.
  • Figure 3 is a B-direction view of Figure 1, and is also a structural schematic diagram of the chain cutter driving device 5 composed of the driving power device 5-1, the spoil processing device 5-2 and the frame 5-3, and is also a chain knife 3 and a chain knife.
  • Figure 4 is a C-C view of Figure 3, also a cross-sectional view of the middle portion of the wall 1;
  • Figure 5 is an enlarged view of a portion I of Figure 2, which is also a schematic structural view of the rail 2 at the bottom of the bottom wall 1-1, and is also a mud nozzle 6-1 and a mud pipeline 6 of the mud pipeline device 6 on the bottom wall 1-1.
  • Figure 6 is an enlarged view of a portion II of Figure 2, that is, one wall of the adjacent two walls 1 is a groove, and the other wall is a boss, and a plurality of holes are provided at the same position of the adjacent two walls, and the holes are formed at the time of splicing.
  • a schematic structural view of the pin 7 is inserted therein, and is also a structural schematic view in which the connecting steel plate 8 is welded at the interface of the adjacent two walls 1 and the thickness after welding is not greater than the thickness of the underground wall 1;
  • FIG. 8 is a schematic structural view of another space-curable chain cutter 3, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;
  • Figure 9 is a structural schematic view showing the assembly of the chain cutter 3 and the driving device 5 by assembling the bottom wall 1-1 and welding it into a whole;
  • Figure 10 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated rock to the top, the wall 1-1 and the bottom of the chain knife 3 together to drop to the set position Schematic diagram of the structure;
  • Figure 11 is a structural schematic view showing the removal of the driving device 5 after the upper chain cutter 3 is disconnected;
  • Figure 12 is a view of the A-A of Figure 11, which is also a schematic structural view of the bottom wall 1-1, and is a structural schematic view of the bottom wall 1-1 on which the plane is lowered to a height position set from the ground;
  • Figure 13 is a schematic view showing the structure after assembling the splicing upper wall 1-2, installing the chain cutter 3 and the driving device 5;
  • Figure 14 is a view of the A-A of Figure 13, and is also a structural schematic view in which the pin 7 is inserted into the hole during splicing, and the interface is welded by the steel plate 8 to be integrated;
  • Figure 15 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated geotechnical to the top, the welded wall 1 and the bottom of the chain knife 3 down to a schematic diagram of the structure of the set position;
  • Figure 16 is a schematic structural view of the assembly and splicing construction of all the walls 1;
  • Fig. 17 is a view taken along the line A in Fig. 16, and is a schematic view showing the structure in which the temporary tooling 4 is taken out after the wall 1 is constructed.
  • 1 is the underground wall, which is assembled from the bottom wall 1-1 and several walls 1-2; 1-1 is the bottom wall of the underground wall 1; 1-2 is the wall above the bottom wall of the underground wall 1; It is a rail provided on the bottom and sides of the wall 1; 3 is a chain cutter for excavating rock and soil, consisting of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1; 3-1 is a chain cutter 3 3-2 is a cutter constituting the chain cutter 3; 4 is a temporary tooling during construction; 5 is a chain cutter driving device, which is driven by the power unit 5-1, the spoil handling device 5-2, and the frame 5-3.
  • composition Composition
  • 5-1 is the driving power device
  • 5-2 is the spoil handling device
  • 5-3 is the frame
  • 6 is the mud pipeline device
  • 6-1 is the mud nozzle on the bottom of the wall 1
  • 6-2 is the wall 1 internal mud pipeline
  • 7 is the pin inserted in the hole when the wall 1 is spliced
  • 8 is the steel plate welded when the wall 1 is spliced.
  • the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembly joints of the adjacent two walls 1 are respectively provided with concave and convex ports of steel structure, that is, the bosses of one wall are embedded in the concave of the other wall In the trough, there are two structures A and B: A. The interface of the same wall has both grooves and bosses, and the other wall is opposite; B, one wall is a groove, the other wall is a boss; wall 1 A rail 2 is arranged on the bottom and both sides, and a chain cutter 3 is arranged on the rail 2 during construction. The chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1.
  • One wall of the adjacent two wall interfaces is a groove, and the other wall is a boss.
  • a plurality of holes are arranged at the same position of the adjacent two walls, and a pin is inserted into the hole during the splicing.
  • the interface between the adjacent two walls is welded with a connecting steel plate, and the thickness after welding is not greater than the thickness of the underground wall.
  • the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, a wall
  • the boss is embedded in the groove of the other wall, and is divided into two structures: A and B: A.
  • the interface of the same wall has both a groove and a boss, and the other wall is reversed; B, a wall is a groove, and another One wall is a boss.
  • the bottom of the wall 1 and the two sides are provided with a track 2, and the track 2 is provided with a chain cutter 3, the width of the chain cutter 3 is smaller than the width of the groove mouth at the interface, and the chain cutter 3 is connected by the chain 3-1 and the chain 3
  • the tool 3-2 is composed of -1, and the driving power device 5-1 drives the chain cutter 3.
  • the rock belt is brought up to the upper side, and the device 5-2 separates the rock soil brought by the chain cutter 3 from the bottom of the wall 1 with the chain cutter 3, and the wall 1 and the bottom chain cutter 3 simultaneously run downward, and the upper plane of the lower wall 1-1 follows
  • the upper wall 1-2 is assembled and the interface of the adjacent two walls is welded before entering the ground to make it integrated; a wall at the interface between the adjacent two walls
  • the groove is the groove, the other wall is a boss, and a plurality of holes are arranged at the same position of the adjacent two walls, and the pin 7 is inserted into the hole during the splicing; the connecting steel plate 8 is welded at the interface of the adjacent two walls, and the welding is performed.
  • the thickness afterwards is not greater than the thickness of the underground wall.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A fabricated underground wall, constituted by splicing multiple walls (1). The wall (1) is formed by assembling a bottom wall (1-1) and an upper wall (1-2); a concave-convex sub-port of a steel structure is provided at the slicing joint of adjacent two walls (1), that is, a protrusion on one of the walls is embedded into a recess on the other of the walls; the bottom and side surfaces of the walls (1) are provided with tracks (2); a chain cutter (3) is mounted on the track (2) during construction; the chain cutter (3) is composed of a chain (3-1) and a cutter (3-2) mounted on the chain (3-1); during construction, the chain cutter (3) merely excavates rock at the bottom of the wall (1); the wall (1) and the bottom chain cutter (3) move downwards simultaneously; after an upper plane of a lower wall (1) is lowered with the chain cutter to a set height with respect to the ground, the upper wall (1-2) is assembled and spliced; and welding is performed at the joint between the upper and lower walls before the walls are sent underground, thereby integrating the walls into a whole. Also disclosed is a construction method of the fabricated underground wall.

Description

一种装配式地下墙及其施工法Assembled underground wall and construction method thereof 技术领域Technical field

本发明涉及的是一种装配式地下墙及其施工法,属于土木工程基础施工技术领域。The invention relates to a prefabricated underground wall and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.

背景技术Background technique

现有地下连续墙技术是在地面上利用挖槽机械,在泥浆护壁的条件下,开挖岀一条狭长的深槽,在槽内吊放钢筋笼,浇筑水下混凝土筑成一个单元槽段,如此逐段进行。其主要缺陷:1)槽内水下施工质量难以控制和检测、施工周期长;2)槽段之间的接口施工困难且易渗水;3)开槽机械较高,且要沿着周长移动应用场合受到限制。The existing underground continuous wall technology uses a trenching machine on the ground to excavate a long and narrow deep trough under the condition of mud retaining wall, hoist the steel cage in the trough, and pour the underwater concrete into a unit trough section. This is done piece by piece. The main defects are as follows: 1) The underwater construction quality in the tank is difficult to control and detect, and the construction period is long; 2) The interface between the groove sections is difficult to construct and easy to seep; 3) The slotting machine is high and moves along the circumference. Applications are limited.

发明内容Summary of the invention

本发明提出的是一种装配式地下墙及其施工法,其目的旨在克服现有技术存在的缺陷,其主要优点:相邻两墙1的装配处采用凹凸嵌入焊接拼接,连接安全可靠,密封性好;墙1自身带有挖掘其底部岩土的链刀,工厂预制墙,现场拼接后分块或者整体下降,施工简单,施工周期短,成本低。The invention provides a prefabricated underground wall and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantage thereof is that the assembly of the adjacent two walls 1 is embedded and welded by the concave and convex, and the connection is safe and reliable. The sealing is good; the wall 1 itself has a chain knife for excavating the bottom of the rock, the factory prefabricated wall, the block is divided or the whole is lowered after the site is spliced, the construction is simple, the construction period is short, and the cost is low.

本发明的技术解决方案:地下墙1由底墙1-1和若干墙1-2装配而成;相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台;墙1的底部和两侧设有轨道2,施工时轨道2上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,墙1和底部的链刀3同时向下运行,下部墙1的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙1-2,相邻两墙的接口处在进入地下前先进行焊接,使之成为一体。The technical solution of the invention is that the underground wall 1 is assembled by the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, convexity of one wall The platform is embedded in the groove of another wall, and is divided into two structures: A and B: A. The interface of the same wall has both a groove and a boss, and the other wall is reversed; B, a wall is a groove, and the other wall It is a boss; the bottom and sides of the wall 1 are provided with a track 2, and the track 2 is provided with a chain knife 3, and the chain knife 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1, the chain When the knife 3 is working, only the rock at the bottom of the wall 1 is excavated, and the wall 1 and the bottom chain cutter 3 are simultaneously operated downward. The upper plane of the lower wall 1 is lowered to the height set at the ground with the chain cutter, and then the upper part is assembled. Wall 1-2, the interface of the adjacent two walls is welded before entering the underground to make it integrated.

本发明的优点:邻两墙1的装配处采用凹凸嵌入焊接拼接,连接安全可靠,墙1自身带有挖掘其底部岩土的链刀,工厂预制墙1,现场拼接后分块或者整体下降,施工简单,施工周期短,成本低。The invention has the advantages that the assembly of the adjacent two walls 1 adopts the concave-convex embedded welding and splicing, and the connection is safe and reliable, and the wall 1 itself has a chain cutter for excavating the bottom rock of the wall, and the factory prefabricated wall 1 is divided into blocks or the whole is dropped after the site is spliced. The construction is simple, the construction period is short, and the cost is low.

附图说明DRAWINGS

图1是相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内的结构示意图;Figure 1 is a schematic view showing a structure in which the splicing joints of the adjacent two walls 1 are respectively provided with a concave and convex sub-port of a steel structure, that is, a boss of one wall is embedded in a groove of the other wall;

图2是图1的A-A视图,也是底墙1-1和上部墙1-2行焊接成为一体的结构示意图Figure 2 is a view of the A-A of Figure 1, and is also a structural schematic diagram of the welding of the bottom wall 1-1 and the upper wall 1-2 rows.

图3是图1的B向视图,也是由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成的链刀驱动装置5的结构示意图,也是链刀3、链刀驱动装置5和墙1组成施工状态的结构示意图;Figure 3 is a B-direction view of Figure 1, and is also a structural schematic diagram of the chain cutter driving device 5 composed of the driving power device 5-1, the spoil processing device 5-2 and the frame 5-3, and is also a chain knife 3 and a chain knife. A schematic structural view of the driving device 5 and the wall 1 in a construction state;

图4是图3的C-C视图,也是墙1中间部分的剖视图;Figure 4 is a C-C view of Figure 3, also a cross-sectional view of the middle portion of the wall 1;

图5是图2的Ⅰ局部的放大视图,也是底墙1-1底部的轨道2的结构示意图,也是泥浆管路装置6在底墙1-1上的泥浆喷嘴6-1和泥浆管路6-2的结构示意图;Figure 5 is an enlarged view of a portion I of Figure 2, which is also a schematic structural view of the rail 2 at the bottom of the bottom wall 1-1, and is also a mud nozzle 6-1 and a mud pipeline 6 of the mud pipeline device 6 on the bottom wall 1-1. Schematic diagram of -2;

图6是图2的Ⅱ局部的放大视图,也是相邻两墙1接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴7的结构示意图,也是相邻两墙1的接口处焊接有连接钢板8,且焊接后的厚度不大于地下墙1的厚度的结构示意图;Figure 6 is an enlarged view of a portion II of Figure 2, that is, one wall of the adjacent two walls 1 is a groove, and the other wall is a boss, and a plurality of holes are provided at the same position of the adjacent two walls, and the holes are formed at the time of splicing. A schematic structural view of the pin 7 is inserted therein, and is also a structural schematic view in which the connecting steel plate 8 is welded at the interface of the adjacent two walls 1 and the thickness after welding is not greater than the thickness of the underground wall 1;

图7是链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图;7 is a schematic structural view of the chain cutter 3, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;

图8是另一种可空间弯曲链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图;FIG. 8 is a schematic structural view of another space-curable chain cutter 3, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;

图9是拼装底部墙1-1,通过焊接使之成为一整体,安装链刀3和驱动装置5的结构示意图;Figure 9 is a structural schematic view showing the assembly of the chain cutter 3 and the driving device 5 by assembling the bottom wall 1-1 and welding it into a whole;

图10是墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方,墙1-1和底部的链刀3一起下降至设定位置的结构示意图;Figure 10 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated rock to the top, the wall 1-1 and the bottom of the chain knife 3 together to drop to the set position Schematic diagram of the structure;

图11是拆除驱动装置5,上部链刀3断开后的结构示意图;Figure 11 is a structural schematic view showing the removal of the driving device 5 after the upper chain cutter 3 is disconnected;

图12是图11的A-A视图,也是底墙1-1的结构示意图,也是底墙1-1上平面下降到距地面设定的高度位置的结构示意图;Figure 12 is a view of the A-A of Figure 11, which is also a schematic structural view of the bottom wall 1-1, and is a structural schematic view of the bottom wall 1-1 on which the plane is lowered to a height position set from the ground;

图13是装配拼接上部墙1-2,安装链刀3和驱动装置5后的结构示意图;Figure 13 is a schematic view showing the structure after assembling the splicing upper wall 1-2, installing the chain cutter 3 and the driving device 5;

图14是图13的A-A视图,也是拼接时在孔内插入销轴7,接口处利用钢板8焊接使之成为一体的结构示意图;Figure 14 is a view of the A-A of Figure 13, and is also a structural schematic view in which the pin 7 is inserted into the hole during splicing, and the interface is welded by the steel plate 8 to be integrated;

图15是墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方,已焊接成一体的墙1和底部的链刀3一起下降到设定位置的结构示意图;Figure 15 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated geotechnical to the top, the welded wall 1 and the bottom of the chain knife 3 down to a schematic diagram of the structure of the set position;

图16是完成全部墙1的装配拼接施工的结构示意图;Figure 16 is a schematic structural view of the assembly and splicing construction of all the walls 1;

图17是图16的A向视图,也是墙1施工完后抽出临时工装4的结构示意图。Fig. 17 is a view taken along the line A in Fig. 16, and is a schematic view showing the structure in which the temporary tooling 4 is taken out after the wall 1 is constructed.

图中的1是地下墙,由底墙1-1和若干墙1-2装配而成;1-1是地下墙1的底墙;1-2是地下墙1的底墙以上的墙;2是墙1的底部和两侧设有的轨道;3是挖掘岩土的链刀,由链条3-1和安装在链条3-1上的刀具3-2组成;3-1是组成链刀3的链条;3-2是组成链刀3的刀具;4是施工时的临时工装;5是链刀驱动装置,由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成;5-1是驱动动力装置;5-2是弃土处理装置;5-3是机架;6是泥浆管路装置;6-1是墙1底部上的泥浆喷嘴;6-2是墙1内部的泥浆管路;7是墙1拼接时在孔内插的销轴;8是墙1拼接时焊接的钢板。1 is the underground wall, which is assembled from the bottom wall 1-1 and several walls 1-2; 1-1 is the bottom wall of the underground wall 1; 1-2 is the wall above the bottom wall of the underground wall 1; It is a rail provided on the bottom and sides of the wall 1; 3 is a chain cutter for excavating rock and soil, consisting of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1; 3-1 is a chain cutter 3 3-2 is a cutter constituting the chain cutter 3; 4 is a temporary tooling during construction; 5 is a chain cutter driving device, which is driven by the power unit 5-1, the spoil handling device 5-2, and the frame 5-3. Composition; 5-1 is the driving power device; 5-2 is the spoil handling device; 5-3 is the frame; 6 is the mud pipeline device; 6-1 is the mud nozzle on the bottom of the wall 1; 6-2 is the wall 1 internal mud pipeline; 7 is the pin inserted in the hole when the wall 1 is spliced; 8 is the steel plate welded when the wall 1 is spliced.

具体实施方式detailed description

地下墙1由底墙1-1和若干墙1-2装配而成;相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台;墙1的底部和两侧设有轨道2,施工时轨道2上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,墙1和底部的链刀3同时向下运行,下部墙1的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙1-2,相邻两墙的接口处在进入地下前先进行焊接,使之成为一体。The underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembly joints of the adjacent two walls 1 are respectively provided with concave and convex ports of steel structure, that is, the bosses of one wall are embedded in the concave of the other wall In the trough, there are two structures A and B: A. The interface of the same wall has both grooves and bosses, and the other wall is opposite; B, one wall is a groove, the other wall is a boss; wall 1 A rail 2 is arranged on the bottom and both sides, and a chain cutter 3 is arranged on the rail 2 during construction. The chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1. When the chain cutter 3 works, only the wall is excavated. 1 At the bottom of the rock, the wall 1 and the bottom chain knife 3 run downward at the same time. The upper plane of the lower wall 1 is lowered to the height set at the ground with the chain cutter, and then the upper wall 1-2 is assembled and adjacent. The joints of the two walls are welded before entering the ground to make them integrated.

所述的相邻两墙接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴。One wall of the adjacent two wall interfaces is a groove, and the other wall is a boss. A plurality of holes are arranged at the same position of the adjacent two walls, and a pin is inserted into the hole during the splicing.

所述的相邻两墙的接口处焊接有连接钢板,且焊接后的厚度不大于地下墙的厚度。The interface between the adjacent two walls is welded with a connecting steel plate, and the thickness after welding is not greater than the thickness of the underground wall.

所述的具体施工法分如下步骤:The specific construction method described is divided into the following steps:

1)预制墙1-1和墙1-2各模块;1) Prefabricated wall 1-1 and wall 1-2 modules;

2)清理现场,使之满足施工条件;2) Clean up the site to meet the construction conditions;

3)将预制的墙1-1和墙1-2的各模块运至现场;3) transport the prefabricated walls 1-1 and 1-2 modules to the site;

4)拼装底部墙1-1,通过焊接使之成为一整体,安装链刀3和驱动装置等;4) Assembling the bottom wall 1-1, making it a whole by welding, installing the chain cutter 3 and the driving device;

5)启动驱动装置,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;5) Start the driving device, the bottom chain knife 3 of the wall 1-1 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up to bring the excavated rock soil to the top;

6)墙1-1和底部的链刀3一起下降;6) Wall 1-1 and the chain cutter 3 at the bottom are lowered together;

7)墙1-1的上平面下降到距地面设定的高度,停止驱动装置;7) The upper plane of the wall 1-1 is lowered to a height set from the ground, and the driving device is stopped;

8)装配拼接上部墙1-2,接口处焊接,使之成为一体;8) Assembling and splicing the upper wall 1-2, the joint is welded to make it integrated;

9)启动驱动装置,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;9) Start the driving device, the bottom chain knife 3 of the wall 1-1 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up to bring the excavated rock soil to the top;

10)已焊接成一体的墙1和底部的链刀3一起下降;10) the welded wall 1 and the bottom chain cutter 3 are lowered together;

11)已焊接成一体的墙1的上平面下降到距地面设定的高度,停止驱动装置;11) The upper plane of the welded wall 1 is lowered to a height set from the ground, and the driving device is stopped;

12)装配拼接上部墙1-2,接口处焊接,使之成为一体;12) Assembling and splicing the upper wall 1-2, welding at the interface to make it integrated;

重复上述9)至12)的施工,直至完成全部墙1的装配拼接施工。Repeat the above construction of 9) to 12) until the assembly and splicing of all the walls 1 is completed.

下面结合附图进一步描述本发明的技术方案:The technical solution of the present invention is further described below with reference to the accompanying drawings:

如图1~图8所示,地下墙1由底墙1-1和若干墙1-2装配而成;相邻两墙1的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台。墙1的底部和两侧设有轨道2,施工时轨道2上装有链刀3,链刀3的宽度小于接口处凹槽口部的宽度,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,驱动动力装置5-1驱动链刀3,链刀3工作时仅挖掘墙1底部的岩土,由下向上运行的链刀3将墙1底部已挖掘的岩土带至上方,装置5-2将链刀3从墙1底部带上来的岩土与链刀3分离,墙1和底部链刀3同时向下运行,下部墙1-1的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙1-2,相邻两墙的接口处在进入地下前先进行焊接,使之成为一体;相邻两墙接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴7;相邻两墙的接口处焊接有连接钢板8,且焊接后的厚度不大于地下墙的厚度。As shown in FIG. 1 to FIG. 8 , the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, a wall The boss is embedded in the groove of the other wall, and is divided into two structures: A and B: A. The interface of the same wall has both a groove and a boss, and the other wall is reversed; B, a wall is a groove, and another One wall is a boss. The bottom of the wall 1 and the two sides are provided with a track 2, and the track 2 is provided with a chain cutter 3, the width of the chain cutter 3 is smaller than the width of the groove mouth at the interface, and the chain cutter 3 is connected by the chain 3-1 and the chain 3 The tool 3-2 is composed of -1, and the driving power device 5-1 drives the chain cutter 3. When the chain cutter 3 works, only the rock soil at the bottom of the wall 1 is excavated, and the bottom of the wall 1 is excavated by the chain cutter 3 running downward and upward. The rock belt is brought up to the upper side, and the device 5-2 separates the rock soil brought by the chain cutter 3 from the bottom of the wall 1 with the chain cutter 3, and the wall 1 and the bottom chain cutter 3 simultaneously run downward, and the upper plane of the lower wall 1-1 follows After the chain knife is lowered to the height set by the ground, the upper wall 1-2 is assembled and the interface of the adjacent two walls is welded before entering the ground to make it integrated; a wall at the interface between the adjacent two walls The groove is the groove, the other wall is a boss, and a plurality of holes are arranged at the same position of the adjacent two walls, and the pin 7 is inserted into the hole during the splicing; the connecting steel plate 8 is welded at the interface of the adjacent two walls, and the welding is performed. The thickness afterwards is not greater than the thickness of the underground wall.

如图9~图17所示,具体施工法分如下步骤:As shown in Figure 9 to Figure 17, the specific construction method is divided into the following steps:

1)预制墙1-1和墙1-2各模块;1) Prefabricated wall 1-1 and wall 1-2 modules;

2)清理现场,使之满足施工条件;2) Clean up the site to meet the construction conditions;

3)将预制的墙1-1和墙1-2的各模块运至现场;3) transport the prefabricated walls 1-1 and 1-2 modules to the site;

4)拼装底部墙1-1,通过焊接使之成为一整体,安装链刀3和驱动装置5等;4) Assembling the bottom wall 1-1, making it a whole by welding, installing the chain cutter 3 and the driving device 5, etc.;

5)启动驱动装置5,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3 将已挖掘的岩土带至上方;5) Start the driving device 5, the bottom chain knife 3 of the wall 1-1 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up to bring the excavated rock soil to the top;

6)墙1-1和底部的链刀3一起下降;6) Wall 1-1 and the chain cutter 3 at the bottom are lowered together;

7)墙1-1的上平面下降到距地面设定的高度,停止驱动装置5;7) The upper plane of the wall 1-1 is lowered to a height set from the ground, and the driving device 5 is stopped;

8)装配拼接上部墙1-2,接口处焊接,使之成为一体;8) Assembling and splicing the upper wall 1-2, the joint is welded to make it integrated;

9)启动驱动装置5,墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;9) Start the driving device 5, the bottom chain knife 3 of the wall 1-1 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up to bring the excavated rock soil to the top;

10)已焊接成一体的墙1和底部的链刀3一起下降;10) the welded wall 1 and the bottom chain cutter 3 are lowered together;

11)已焊接成一体的墙1的上平面下降到距地面设定的高度,停止驱动装置5;11) The upper plane of the welded wall 1 is lowered to a height set from the ground, and the driving device 5 is stopped;

12)装配拼接上部墙1-2,接口处焊接,使之成为一体;12) Assembling and splicing the upper wall 1-2, welding at the interface to make it integrated;

重复上述9)至12)的施工,直至完成全部墙1的装配拼接施工。Repeat the above construction of 9) to 12) until the assembly and splicing of all the walls 1 is completed.

Claims (4)

一种装配式地下墙,其特征是地下墙(1)由底墙(1-1)和若干墙(1-2)装配而成;相邻两墙(1)的装配拼接处分别设有钢结构的凹凸子口,即一墙的凸台嵌入另一墙的凹槽内,分A、B两种结构:A、同一墙的接口处既有凹槽又有凸台,另一墙反之;B、一墙为凹槽,另一墙为凸台;墙(1)的底部和两侧设有轨道(2),施工时轨道(2)上装有链刀(3),链刀(3)由链条(3-1)和安装在链条(3-1)上的刀具(3-2)组成,链刀(3)工作时仅挖掘墙(1)底部的岩土,墙(1)和底部的链刀(3)同时向下运行,下部墙(1)的上平面随着链刀下降到距地面设定的高度后,再装配拼接上部墙(1-2),相邻两墙的接口处在进入地下前先进行焊接,使之成为一体。A prefabricated underground wall, characterized in that the underground wall (1) is assembled from the bottom wall (1-1) and a plurality of walls (1-2); the assembly joints of the adjacent two walls (1) are respectively provided with steel The concave and convex mouth of the structure, that is, the boss of one wall is embedded in the groove of the other wall, and is divided into two structures A and B: A. The interface of the same wall has both a groove and a boss, and the other wall is opposite; B. One wall is a groove, the other wall is a boss; the bottom (2) of the wall (1) is provided with a track (2), and the track (2) is provided with a chain knife (3), a chain knife (3) It consists of a chain (3-1) and a cutter (3-2) mounted on the chain (3-1). The chain cutter (3) works only to dig the rock, wall (1) and bottom at the bottom of the wall (1). The chain cutter (3) runs downward at the same time, and the upper plane of the lower wall (1) is assembled with the upper wall (1-2) and the interface of the adjacent two walls after the chain cutter is lowered to the height set at the ground. Before welding into the ground, weld it and make it one. 根据权利要求1所述的一种装配式地下墙,其特征是所述的相邻两墙接口处一墙为凹槽,另一墙为凸台,在相邻两墙的相同位置设有若干孔,拼接时在孔内插有销轴。A fabricated underground wall according to claim 1, wherein one wall of the adjacent two wall interfaces is a groove, and the other wall is a boss, and a plurality of positions are provided at the same position of the adjacent two walls. Hole, when the splicing is inserted into the hole with a pin. 根据权利要求1所述的一种装配式地下墙,其特征是所述的相邻两墙的接口处焊接有连接钢板,且焊接后的厚度不大于地下墙的厚度。A fabricated underground wall according to claim 1, wherein said adjacent two walls are welded with a connecting steel plate at an interface, and the thickness after welding is not greater than the thickness of the underground wall. 根据权利要求1所述的一种装配式地下墙,其特征是所述的具体施工法分如下步骤:A fabricated underground wall according to claim 1, wherein said specific construction method is divided into the following steps: 1)预制墙(1-1)和墙(1-2)各模块;1) Prefabricated wall (1-1) and wall (1-2) modules; 2)清理现场,使之满足施工条件;2) Clean up the site to meet the construction conditions; 3)将预制的墙(1-1)和墙(1-2)的各模块运至现场;3) transport the prefabricated wall (1-1) and wall (1-2) modules to the site; 4)拼装底部墙(1-1),通过焊接使之成为一整体,安装链刀(3)和驱动装置等;4) Assembling the bottom wall (1-1), making it a whole by welding, installing the chain cutter (3) and the driving device; 5)启动驱动装置,墙(1-1)底部链刀(3)挖掘岩土,侧面由下向上运行的链刀(3)将已挖掘的岩土带至上方;5) Start the driving device, the bottom chain knife (3) of the wall (1-1) excavates the rock and soil, and the side of the chain knife (3) running from the bottom up to bring the excavated rock soil to the top; 6)墙(1-1)和底部的链刀(3)一起下降;6) The wall (1-1) and the chain knife (3) at the bottom are lowered together; 7)墙(1-1)的上平面下降到距地面设定的高度,停止驱动装置;7) The upper plane of the wall (1-1) is lowered to a height set from the ground to stop the driving device; 8)装配拼接上部墙(1-2),接口处焊接,使之成为一体;8) Assembling the upper wall (1-2) and welding the joint to make it integrated; 9)启动驱动装置,墙(1-1)底部链刀(3)挖掘岩土,侧面由下向上运行的链刀(3)将已挖掘的岩土带至上方;9) Start the drive device, the bottom chain knife (3) of the wall (1-1) excavates the rock and soil, and the side of the chain knife (3) running from the bottom up to bring the excavated rock and soil to the top; 10)已焊接成一体的墙(1)和底部的链刀(3)一起下降;10) The welded wall (1) and the bottom chain knife (3) are lowered together; 11)已焊接成一体的墙(1)的上平面下降到距地面设定的高度,停止驱动装置;11) The upper plane of the welded wall (1) is lowered to a height set at the ground, and the driving device is stopped; 12)装配拼接上部墙(1-2),接口处焊接,使之成为一体;12) Assemble the upper wall (1-2) and weld the joint to make it integrated; 重复上述9)至12)的施工,直至完成全部墙(1)的装配拼接施工。Repeat the above construction of 9) to 12) until the assembly and splicing of the entire wall (1) is completed.
PCT/CN2018/080790 2017-03-29 2018-03-28 Fabricated underground wall and construction method thereof Ceased WO2018177306A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710195875.5A CN106836192A (en) 2017-03-29 2017-03-29 A kind of assembled subterranean wall and its construction method
CN201710195875.5 2017-03-29

Publications (1)

Publication Number Publication Date
WO2018177306A1 true WO2018177306A1 (en) 2018-10-04

Family

ID=59141351

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/080790 Ceased WO2018177306A1 (en) 2017-03-29 2018-03-28 Fabricated underground wall and construction method thereof

Country Status (2)

Country Link
CN (1) CN106836192A (en)
WO (1) WO2018177306A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836192A (en) * 2017-03-29 2017-06-13 王燏斌 A kind of assembled subterranean wall and its construction method
CN108035338A (en) * 2017-11-24 2018-05-15 上海市机械施工集团有限公司 Prefabricated ground walls and its construction method
CN114108797A (en) * 2021-10-21 2022-03-01 王树生 Wall foundation and construction device and method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5985021A (en) * 1982-11-05 1984-05-16 Kajima Corp Method and apparatus for construction of underground continuous wall
JPS62233328A (en) * 1986-04-01 1987-10-13 Fusao Sakano Method and apparatus for setting retaining wall by excavator
JPH04179726A (en) * 1990-11-13 1992-06-26 Kazutoshi Isachi Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
CN2260103Y (en) * 1996-08-05 1997-08-20 郭同元 Pile
CN103334422A (en) * 2013-06-26 2013-10-02 中国建筑股份有限公司 Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof
CN105887806A (en) * 2016-06-13 2016-08-24 上海强劲地基工程股份有限公司 Prefabricated underground diaphragm wall and its construction method
CN106836192A (en) * 2017-03-29 2017-06-13 王燏斌 A kind of assembled subterranean wall and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5985021A (en) * 1982-11-05 1984-05-16 Kajima Corp Method and apparatus for construction of underground continuous wall
JPS62233328A (en) * 1986-04-01 1987-10-13 Fusao Sakano Method and apparatus for setting retaining wall by excavator
JPH04179726A (en) * 1990-11-13 1992-06-26 Kazutoshi Isachi Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
CN2260103Y (en) * 1996-08-05 1997-08-20 郭同元 Pile
CN103334422A (en) * 2013-06-26 2013-10-02 中国建筑股份有限公司 Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof
CN105887806A (en) * 2016-06-13 2016-08-24 上海强劲地基工程股份有限公司 Prefabricated underground diaphragm wall and its construction method
CN106836192A (en) * 2017-03-29 2017-06-13 王燏斌 A kind of assembled subterranean wall and its construction method

Also Published As

Publication number Publication date
CN106836192A (en) 2017-06-13

Similar Documents

Publication Publication Date Title
CN110043264B (en) Construction method for jacking prefabricated rectangular vertical shaft structural type
CN107059877A (en) Basis and its construction method of the bottom with chain knife during a kind of construction
JP5235748B2 (en) Wall metal fittings and underground continuous wall construction method
WO2018177306A1 (en) Fabricated underground wall and construction method thereof
WO2018133740A1 (en) Underground building and construction method for same
WO2018177307A1 (en) Fabricated underground building and construction method thereof
CN104452804B (en) Wall telephone is made in tunneling boring stirring cutting
WO2018133711A1 (en) Pier foundation and construction method therefor
WO2018133746A1 (en) Underground building formed of piles and walls, and method for constructing same
CN109914477B (en) Prefabricated pipeline of assembling of utility tunnel
WO2018177304A1 (en) Fabricated underground building and construction method thereof
CN207727550U (en) A kind of assembled subterranean wall
CN103243763B (en) Rectification mechanism of slotting machine
WO2018177305A1 (en) Groove pile for fabricated underground building and construction method thereof
CN207228156U (en) A kind of underground structure being made of stake and wall
CN105569572A (en) Square drill bit
CN207419440U (en) A kind of groove stake for assembled hypogee
CN207714369U (en) A kind of assembled hypogee
WO2018177308A1 (en) Fabricated underground building interface structure and construction method thereof
WO2018166523A1 (en) Deep-water foundation and construction device and construction method therefor
CN105926582A (en) Prefabricated hollow component underground tunneling construction combined body, continuous wall and construction method
CN108824523B (en) Chain saw type cutting box
CN207727613U (en) A kind of assembled hypogee
CN113756366A (en) Novel pipe curtain-box culvert integrated tunnel structure and construction method
CN218175904U (en) Sinking construction device for bottom on-site construction of upper assembled underground building

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18777826

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18777826

Country of ref document: EP

Kind code of ref document: A1