WO2015169352A1 - Utilisation de contrôleurs flexibles dans un système de commande de processus - Google Patents
Utilisation de contrôleurs flexibles dans un système de commande de processus Download PDFInfo
- Publication number
- WO2015169352A1 WO2015169352A1 PCT/EP2014/059346 EP2014059346W WO2015169352A1 WO 2015169352 A1 WO2015169352 A1 WO 2015169352A1 EP 2014059346 W EP2014059346 W EP 2014059346W WO 2015169352 A1 WO2015169352 A1 WO 2015169352A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- controllers
- physical
- control
- virtual
- controller
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B19/41845—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by system universality, reconfigurability, modularity
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F11/00—Error detection; Error correction; Monitoring
- G06F11/07—Responding to the occurrence of a fault, e.g. fault tolerance
- G06F11/16—Error detection or correction of the data by redundancy in hardware
- G06F11/20—Error detection or correction of the data by redundancy in hardware using active fault-masking, e.g. by switching out faulty elements or by switching in spare elements
- G06F11/202—Error detection or correction of the data by redundancy in hardware using active fault-masking, e.g. by switching out faulty elements or by switching in spare elements where processing functionality is redundant
- G06F11/2023—Failover techniques
- G06F11/203—Failover techniques using migration
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F9/00—Arrangements for program control, e.g. control units
- G06F9/06—Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
- G06F9/46—Multiprogramming arrangements
- G06F9/50—Allocation of resources, e.g. of the central processing unit [CPU]
- G06F9/5005—Allocation of resources, e.g. of the central processing unit [CPU] to service a request
- G06F9/5027—Allocation of resources, e.g. of the central processing unit [CPU] to service a request the resource being a machine, e.g. CPUs, Servers, Terminals
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F9/00—Arrangements for program control, e.g. control units
- G06F9/06—Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
- G06F9/46—Multiprogramming arrangements
- G06F9/50—Allocation of resources, e.g. of the central processing unit [CPU]
- G06F9/5083—Techniques for rebalancing the load in a distributed system
- G06F9/5088—Techniques for rebalancing the load in a distributed system involving task migration
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/20—Pc systems
- G05B2219/22—Pc multi processor system
- G05B2219/2239—Reallocate, reschedule execution of controlled functions if one processor fails
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/30—Nc systems
- G05B2219/31—From computer integrated manufacturing till monitoring
- G05B2219/31264—Control, autonomous self learn knowledge, rearrange task, reallocate resources
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/30—Nc systems
- G05B2219/31—From computer integrated manufacturing till monitoring
- G05B2219/31355—Fault, if one station defect, stop it, other stations take over
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/30—Nc systems
- G05B2219/33—Director till display
- G05B2219/33334—Load balancing, distribution between processors
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02D—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
- Y02D10/00—Energy efficient computing, e.g. low power processors, power management or thermal management
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Definitions
- the embodiments described herein relate generally to process control systems and in particular to devices and methods that allows for flexible controller utilization in a process control system.
- Computer controlled process control systems are used for controlling and/or monitoring of industrial processes in many different types of industries and utilities such as automotive, chemical, pharmaceutical, food, metal, mines, steel mills, consumer products, power generation, power distribution, pure and waste water handling, oil refineries, gas pipe-lines and off-shore platforms.
- Field devices which are instruments or actuators such as motors, valves, valve positioners and sensors of different types perform functions within the process such as driving conveyor belts, opening or closing valves, and measuring process control parameters. Controllers perform control functions to monitor and control the field devices. Such control functions may involve receiving signals indicating process control measurements, processing the received information and generating control signals that are transmitted to the field device(s) to control and/or monitor the operation of the process.
- An operator is generally able to perform desired operations with respect to the process by means of an operator workstation that is communicatively connected to receive process information from field devices and controllers.
- the operator may e.g. be able to view the current state of the process via a user interface, perform evaluations of the process and modify the operation of the process by using the operator workstation.
- a primary digital controller is responsible for operating the control logic and a backup digital controller receives process inputs from the primary controller and executes the control algorithm in parallel to the primary controller according to a synchronous execution method.
- logic runs on dedicated controllers and redundancy is managed locally, close to the controlled hardware.
- Input/output (I/O) signals from field instruments and actuators are typically terminated in local I/O units and controllers.
- I/O Input/output
- fault tolerance is implemented by means of adding redundant counterparts to each controller and/or I/O unit, but this also restrains the extent of where recovery can take place and how faults can be detected and reverted.
- An object of the present invention is to provide an improved process control system and method which at least partly overcome some of the above mentioned problems.
- a first embodiment provides a process control system comprising a plurality of physical controllers for controlling a plurality of field devices and a field network interconnecting the plurality of physical controllers and the plurality of field devices.
- the process control system also comprises a control function manager for setting-up and managing a set of virtual controllers, allocating control functions for controlling the field devices to the set of virtual controllers and allocating physical controllers for executing the control functions allocated to the set of virtual controllers.
- the field network is configured to provide a communication connection between any one of the plurality of physical controllers and any one of the plurality of field devices.
- the plurality of physical controllers are configured as a shared pool of hardware resources of the set of virtual controllers such that any one of the physical controllers is capable of executing one or several control functions allocated to any one or several virtual controller of the set of virtual controllers in accordance with an allocation instruction from the control function manager to control any of the plurality of field devices.
- a second embodiment provides a method to be carried out in a process control system comprising a plurality of physical controllers for controlling a plurality of field devices, a field network (D3) interconnecting the plurality of physical controllers and the plurality of field devices and a control function manager for setting-up and managing a set of virtual controllers.
- the field network is configured to provide a communication connection between any one of the plurality of physical controllers and any one of the plurality of field devices.
- the plurality of physical controllers are configured as a shared pool of hardware resources of said set of virtual controllers such that any one of the physical controllers is capable of executing one or several control functions allocated to any one or several virtual controller of the set of virtual controllers in accordance with an allocation instruction from the control function manager to control any of the plurality of field devices.
- the control function manager allocates control functions for controlling the plurality of field devices to the set of virtual controllers and allocates physical controllers for executing the control functions allocated to the set of virtual controllers.
- a third embodiment provides a computer program product on a computer readable medium comprising computer program code instructions configured, when said program code is loaded into and executed by a processor provided in a process control system, to cause the method according to the second embodiment to be carried out.
- An advantage of embodiments of this disclosure is that a flexible controller utilization and flexible controller redundancy may be provided in process control systems that allow for easy operation and maintenance, and reallocation of computational resources,
- Another advantage of some embodiments is that hot-swapping of components during production is enabled.
- some embodiments provide for a possibility for extended maintenance interval e.g., in subsea applications.
- Fig. 1 is a schematic diagram of a process and a process control system according to prior art.
- Fig. 2 is a schematic diagram of a process control system according to an embodiment of the invention.
- Fig. 3 is a schematic diagram illustrating allocation of control functions to virtual controllers and physical controllers according to an embodiment of the invention.
- Figs. 4a and 4b are schematic diagrams illustrating reallocation of control functions to another physical controller according to an embodiment of the invention.
- Figs. 5a and 5b are schematic diagrams illustrating reallocation of control functions to another physical controller according to another embodiment of the invention.
- Figs. 6a and 6b are schematic diagrams illustrating reallocation of control functions to another physical controller according to yet another embodiment of the invention.
- Figs. 7a and 7b are schematic diagrams illustrating reallocation of control functions to another physical controller according to a further embodiment of the invention.
- Fig. 8 is a schematic diagram illustrating allocation of control functions to physical controllers according to an embodiment of the invention.
- Fig. 9 is a flow diagram illustrating an embodiment of a method to be carried out in a process control system.
- Fig. 10 is a flow diagram illustrating an alternative embodiment of a method to be carried out in a process control system.
- Fig. 1 1 is a schematic block diagram illustrating an exemplary embodiment of a control function manager and a computer program product.
- Fig. 1 shows schematically a control system 20 for a process 30, i.e. a process control system.
- the process control system 20 is a computerized process control system for controlling an industrial process 30.
- the process 30 may comprise a number of different sub-processes and process sections.
- the process may be monitored through one or more process monitoring computers, which communicate with a server handling monitoring and control of the process.
- the process control system 20 includes a number of operator workstations or terminals 27, 28 connected to a first data bus D1 .
- a wireless gateway 25 is connected to a wireless network and is also connected to the first data bus D1 and configured such that portable workstations such as workstation 26 may access the control system 20 wirelessly.
- the process 30 may comprise process controllers 31 , 32 and monitored equipment collectively referred to as field devices such as a motor 36, valves 34, 38, and measuring equipment such as sensors 35, 37.
- the controller 31 , motor 36, valve 38, and sensor 37 are part of a first process section, and the controller 32, valve 34 and sensor 35 are part of a second process section.
- process interface units also referred to as I/O units 64 and 66 for providing a communicative connection between the process 30 and the process control system 20. It should however be realized that there may be more or fewer of each of these interface units 64, 66. It should here also be realized that some of these may only be provided for control, some only for measurements and some for both control and measurements. It should be realized that one or more of sensor units 35, 37 may be connected to such process interface units. Such units are involved in controlling the process 30 and in doing this also involved in measuring physical properties related to the process.
- the measured properties may here comprise properties of the process itself such as measurements of temperature or pressure in a pulp and paper process, a steel mill, an oil & gas production site, a petrochemical process, a pharmaceutical process or measurements such as current and voltage in electrical power process measurements of generation, transmission and distribution processes.
- the controllers 31 and 32 would typically be provided in redundant pairs such that another controller is provided to execute the respective control algorithms of controllers 31 and 32 in parallel according to a synchronous execution method.
- Fig. 1 it can be seen from Fig. 1 that there is a limited flexibility in the arrangement of the controllers. If the controller 31 would become overloaded or fail, control function resources available in the controller 32 cannot assist in the control of the motor 36 or valve 38.
- FIG. 2 is a schematic diagram illustrating a process control system 220 which has been configured to implement flexible controller utilization according to an embodiment as described in this disclosure. Those elements disclosed in Fig. 2 which correspond exactly to already described elements in Fig. 1 have been given the same reference numerals as in Fig. 1 .
- the process control system 220 monitors and controls a process 230.
- the process control system 2 comprises field devices such as actuators and instruments that are connected to the process control system via a field network D3 either directly or via I/O units such as I/O units 67 and 68 shown in Fig. 2.
- the field devices of the process 230 comprises valves 34, 38, a motor 36 and sensors 35, 37 and 39 as schematically illustrated in Fig. 2, but it should be understood that the process 230 may comprise a much larger number of field devices of different types.
- the process control system 220 comprises a number of physical controllers 1 1 configured to interact with the field devices 230 and execute control functions in order to monitor and control the process 230.
- the physical controllers are hardware units that comprise interfaces for input and output of signals from/to the field devices via the field network D3 and from/to overhead system units such as a server 21 and workstations 26, 27, 28 via data buses D1 and D2.
- the physical controllers also comprise processing means, e.g. processors configured to process received input signals, generate output signals and process software code instructions in order to execute control functions.
- the field network D3 is configured to provide a communication connection between any one of the physical controllers 1 1 and any one of the field devices 34-39. Depending on e.g. the location of the process 230 and delay requirements the field network may be implemented by means of many different types of communication networks using different types of communication protocols. According to an example embodiment the field network D3 is implemented as a PROFINET network.
- the process control system 230 also comprises a control function manager 10.
- the control function manager is a functional entity responsible for setting-up and managing a set of virtual controllers, allocating control functions for controlling the field devices to the set of virtual controllers and allocating physical controllers for executing the control functions allocated to the set of virtual controllers.
- the control function manager would typically be implemented in software arranged to execute in a dedicated processing unit such as schematically illustrated in Fig. 2 or arranged in a distributed fashion to e.g. execute in the processing means of the physical controllers 1 1 .
- a virtual controller may be set-up by software logic to emulate a hardware controller according from the view point of overhead control system units such as the server 21 hus the introduction of the control function manager does not require any modification of overhead control system units such as servers and/or workstations.
- the virtual controllers serve to functionally separate control logic from controller hardware resources to allow for flexible and efficient allocation of controller hardware resources for executing the desired control functions.
- the virtual controllers make it possible to keep complexity low since control functions that depend on each other may be grouped and allocated to the same virtual controller which make it possible to hide to overhead control system units that a large number of physical controllers are in fact involved in executing a group of control functions.
- Fig. 3 is a diagram schematically illustrating allocation of control functions to virtual controllers VC1 , VC2, VC3 and physical controllers 1 1 a, 1 1 b, 1 1 c, 1 1 1 d, 1 1 e.
- Fig. 3 illustrates the overall layout of the process control system comprising overhead control system 29, the control function manager 10, the virtual controllers VC1 , VC2, VC3 managed by the control function manager 10, physical controllers 1 1 a-e and the field network D3 for providing connection to field devices 31 .
- the control function manager 10 and the virtual controllers VC1 - VC3 form a virtualization layer between the upper-most control nodes of the system, i.e.
- the lower-most layers of the process control system may be regarded as a shared pool of resources that the overhead control system 29 can allocate control functions and control loops to dynamically.
- the dynamicity of the system will yield increased robustness and reliability as it takes away the need for low-level and complex hardware to deal with fault-tolerance and redundancy.
- this architecture has the potential to improve the overall performance of the system significantly, as computation and processing can be distributed more evenly amongst the available controllers and thus reduce the risk of hotspots in the system.
- the control function manager 10 In terms of redundancy and modularity, the system also enables hot-swapping of faulty or defect components without this having any noticeable impact on the rest of the system.
- the control function manager 10 regardless of where it resides, such as inside every one of the physical controllers 1 1 a-e or in support hardware separated from the physical controllers, is responsible for spawning virtual controllers and allocating system-wide control functions to the physical controllers depending on availability, load, etc. Say for instance, as illustrated in Fig. 3, that the control function manager allocates control functions F(1 ) through F(n) to the virtual controller VC1 that, say run on a dual pair of physical controllers 1 1 a and 1 1 b.
- the control function manager 10 may decide to allocate m of the functions to one of the controllers and the rest (n-m) to the other one. Assume likewise that control functions G(1 ) through G(n) are allocated to the virtual controller VC2 and control functions H(1 ) though H(n) are allocated to the virtual controller VC3.
- the physical controllers 1 1 c and 1 1 d are allocated to execute the control functions allocated to the virtual controller VC2 and the physical controller 1 1 e is allocated to execute the control functions allocated to the virtual controller VC3. Additional redundant controllers may be allocated analogously to synchronously execute the same control functions as the physical controllers 1 1 a-e but this is not described in detail here for simplicity.
- Figs. 4a and 4b are schematic diagrams illustrating reallocation of functionality in the event of a failure of a physical controller.
- the virtual controller VC1 controls field devices 34, 35 and 39 by means of the physical controllers 1 1 a and 1 1 b that execute control functions F(1 ) - F(n).
- the control function manager has allocated the physical controllers such that 1 1 a executes control functions F(1 )-F(m) while the physical controller 1 1 b executes control functions F(m+1 ) - F(n) as illustrated in Fig. 4a.
- the physical controller 1 1 c might be either idle or executing control functions allocated to another virtual controller.
- Fig. 4b illustrates a scenario where the virtual controller 1 1 a fails.
- the control function manager reallocates the physical controllers used by the virtual controller VC1 such that control functions F(1 )-F(k) now are executed by the physical controller 1 1 c and control functions F(k+1 )-F(n) are executed by the physical controller 1 1 b.
- the control function manager may decide that the physical controller 1 1 c replaces the physical controller 1 1 a and executes the same control functions that the physical controller 1 1 a executed before failing. But if e.g.
- the control function manager may decide to let the physical controller 1 1 c execute less or more control functions than the physical controller 1 1 a did. This reallocation of physical controllers is transparent to the overhead control system.
- Figs. 4a and 4b illustrates reallocation triggered by a failure of a physical controller 1 1 a, but the controller function manager may be configured to reallocate physical controllers assigned to execute a particular set of control functions for a variety of reasons such as load sharing between physical controllers and communication links or in response to an operator reallocation command. If e.g. the hardware is to be updated it is possible to reallocate the control functions to make a physical controller that is to be updated idle before it is replaced.
- control functions allocated to a virtual controller are executed by a single or a plurality of physical controllers.
- a physical controller is allocated to execute control functions allocated to a plurality of different virtual controllers.
- the physical controllers are configured to execute control functions allocated to any virtual controller but the physical controllers are only allocated to one virtual controller at a time.
- the physical controllers are configured into subsets serving a respective virtual controller. If one physical controller of a particular subset fails the control function manager performs a reallocation of the physical controllers within the particular subset.
- Figs. 5a and 5b illustrate how redundant pairs may be handled according to an exemplary embodiment.
- Fig. 5a shows that the control function manager has allocated the physical controllers such that the physical controllers 1 1 a and 1 1 b are redundant pairs which both execute control functions F(1 )-F(m). If one of the physical controllers 1 1 a or 1 1 b fails the control operation can continue uninterrupted since one of the controllers is still working. The control function manager can then reallocate the physical controllers such that e.g. the physical controllers 1 1 b and 1 1 c forms a new redundant pair (assuming that it was the physical controller 1 1 a that failed) as illustrated in Fig. 5b.
- Figs. 6a and 6b illustrate an embodiment in which the physical controllers are divided into subsets and allocated to a respective virtual controller.
- the physical controllers 1 1 a, 1 1 b and 1 1 c have been allocated to the virtual controller VC1 . If one of the physical controllers of the subset would fail such as the physical controller 1 1 a, the control function manager would perform a reallocation of control functions allocated to the physical controllers of the subset of controllers allocated to the virtual controller VC1 as illustrated in Fig. 6b.
- Figs. 7a and 7b illustrates an exemplary scenario where the physical controllers 1 1 a and 1 1 b first are allocated to execute control functions allocated to the virtual controller VC1 , but after a reallocation (e.g. due to failure of the physical controller 1 1 a) the physical controllers 1 1 b and 1 1 c execute the control functions allocated to the virtual controller VC1 .
- Fig. 8 illustrates a scenario with a more complex allocation scheme according to which some physical controllers execute control functions allocated to a single virtual controller while other physical controllers execute control functions allocated to more than one virtual controller.
- Fig. 8 shows that the physical controller 1 1 b executes control functions allocated to the virtual controller VC1 , the physical controllers 1 1 c and 1 1 d executes control functions allocated to the virtual controller VC2 and the physical controller 1 1 a executes control functions allocated to both the virtual controller VC1 and the virtual controller VC2.
- the physical controllers 1 1 e and 1 1 f are spare controllers which may be reallocated to execute control functions of either the virtual controller VC1 or VC2 as desired in accordance with allocation instructions from the control function manager.
- Fig. 9 is a flow diagram illustrating a method to be carried out in a process control system according to an embodiment as described above. The method comprises a step 51 according to which the control function manager allocates control functions for controlling the field devices to the set of virtual controllers and a step
- control function manager allocates physical controllers for executing the control functions allocated to the set of virtual controllers.
- Fig. 10 is a flow diagram of an alternative embodiment of a method to be carried out in a process control system.
- the method illustrated in Fig. 10 comprises steps 51 and 52 corresponding to the steps of the method of Fig. 9 and also a step 54 of the control function manager reallocating a physical controller by changing the physical controller that is assigned to execute a particular control function.
- the step 54 is performed in response to a step
- Such an event may according to different embodiments be:
- control functions F(1 )-F(n) which are assigned to the virtual controller VC1 are safety critical control functions which if not performed might impact the safety of personnel, process equipment and/or the environment.
- the control functions G(1 )-G(n) allocated to the virtual controller VC2 are assumed to be production related control functions which if not performed have a negative impact on the production of the process but without risking the safety of personnel or equipment.
- control functions H(1 )-H(n) allocated to the virtual controller VC3 are assumed to be control functions that relate to functions that are nice to have but which do not have a direct impact on the current performance of the process, such as control functions related to condition-based maintenance, collection of statistics etc.
- the control function manager can easily control the process to run in a reduced mode by deactivating control functions with a lower priority first, in this example by deactivating the control functions allocated to the virtual controller VC3, in order to ensure that there are enough controller resources for executing control functions with a higher priority, namely those allocated to the virtual controllers VC1 and VC2 in the present example.
- Fig. 1 1 is a schematic block diagram illustrating an exemplary embodiment of a control function manager 10.
- the control function manager 10 comprises software as well as dedicated hardware of a unit separate from the physical controllers but as mentioned above it is according to other embodiments possible that the control function manager comprises software that is distributed and executed in the physical controllers.
- the control function manager may also according to some embodiments comprise a central part separate from the physical controllers and local parts comprising software executed in processors of the physical controllers.
- 1 1 comprises one or several interfaces 73 for communicating with the physical control units and overhead control system, one or several processors 74 for executing software code instructions, a memory 76 and a computer program product 75 loaded into the memory 76 and comprising computer program code instructions configured, when the program code is loaded into and executed by the processor(s) 74, to cause the method shown in Fig. 9 or Fig. 10 to be carried out.
- the computer program product may also be stored on other types of computer readable media, both volatile and non-volatile, such as portable memory devices e.g. USB-sticks, CD-ROM discs and portable harddiscs which may be loaded into and executed by processors of the process control system.
- Embodiments described herein may be particularly advantageous to use in subsea applications in which either the field devices or the field devices and the controllers are installed subsea. Since it is particularly difficult and costly to replace or maintain hardware that is placed subsea the possibility for an extended maintenance interval that is provided by the flexible redundancy of the disclosed embodiments is very beneficial for subsea applications. Furthermore the disclosed embodiments makes it easy to provide an overcapacity in terms of controller hardware resources and to allow for such redundant hardware to be used as efficiently as possible to improve system performance. Consider e.g. an example scenario where there is a real requirement of 40 physical controllers to execute the desired control functions but 50 physical controllers are provided to give spare capacity.
- the control function manager may e.g. allocate the control functions such that 45 of the 50 physical controllers are used to execute control functions as long as all physical controllers are working in order to not overload any of the physical controllers to ensure best possible performance.
- the control function manager may be implemented to allocate the control functions to the set of virtual controllers in different ways. It is beneficial to group control functions that are mutually dependent within the same virtual controller. Assume for instance that a first control function F(x) implies reading measurements of pressure before and after a pump and computing the differential pressure. A second control function F(y) uses the differential pressure and a detected rotation speed of a motor driving the pump, computes how the rotation speed needs to be changed in order to get the desired pressure conditions for the pump and controls the power supplied to the motor accordingly. Since the first and second control function F(y) depends on the control function F(x) it is appropriate that these control functions are allocated to the same virtual controller.
- One virtual controller may e.g.
- Physical controllers according to prior art are usually configured to receive instructions regarding which field devices to control and if software required to communicate with and control these devices are not already present in the physical controller it is common to download such software via a communication network. Such programmable physical controllers are already provided with the properties necessary for interacting with the control function manager. Accordingly implementation of the above described embodiments will generally not require any adaptation of the hardware of the physical controllers. The only requirement is that the physical controllers are connected to the field network interconnecting the plurality of physical controllers and the plurality of field devices and that the physical controllers are configured as a shared pool of hardware resources of the set of virtual controllers. As is apparent from the above description there are numerous advantages associated with different ones of the above described embodiments. Example embodiments:
- Virtualization can simplify the engineering process for achieving fault-tolerance and high availability.
Landscapes
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Software Systems (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Quality & Reliability (AREA)
- Manufacturing & Machinery (AREA)
- Automation & Control Theory (AREA)
- Hardware Redundancy (AREA)
Abstract
La présente invention concerne un système de commande de processus (220), un procédé et un produit programme d'ordinateur. Le système de commande de processus (220) comprend une pluralité de contrôleurs (CTRL) physiques (11) pour commander une pluralité de dispositifs de terrain (34 à 39), un réseau de terrain (D3) interconnectant la pluralité de contrôleurs physiques (11) et la pluralité de dispositifs de terrain (34 à 39), et un gestionnaire de fonction de commande (CFM) (10) pour configurer et gérer un ensemble de contrôleurs virtuels, attribuer des fonctions de commande pour commander les dispositifs de terrain (34 à 39) à l'ensemble de contrôleurs virtuels (VC1, VC2, VC3), et attribuer des contrôleurs physiques (11) pour exécuter les fonctions de commande attribuées à l'ensemble de contrôleurs virtuels. Le réseau de terrain (D3) est configuré pour assurer une connexion de communication entre n'importe quel contrôleur physique parmi la pluralité de contrôleurs physiques (11) et n'importe quel dispositif de terrain parmi la pluralité de dispositifs de terrain (34 à 39). La pluralité de contrôleurs physiques (11) sont configurés sous la forme d'un groupe partagé de ressources matérielles de l'ensemble de contrôleurs virtuels.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PCT/EP2014/059346 WO2015169352A1 (fr) | 2014-05-07 | 2014-05-07 | Utilisation de contrôleurs flexibles dans un système de commande de processus |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PCT/EP2014/059346 WO2015169352A1 (fr) | 2014-05-07 | 2014-05-07 | Utilisation de contrôleurs flexibles dans un système de commande de processus |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2015169352A1 true WO2015169352A1 (fr) | 2015-11-12 |
Family
ID=50680042
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/EP2014/059346 Ceased WO2015169352A1 (fr) | 2014-05-07 | 2014-05-07 | Utilisation de contrôleurs flexibles dans un système de commande de processus |
Country Status (1)
| Country | Link |
|---|---|
| WO (1) | WO2015169352A1 (fr) |
Cited By (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2017166692A (ja) * | 2016-02-26 | 2017-09-21 | ネル ハイドロジェン アクティーゼルスカブ | 水素燃料補給システム用通信システム |
| CN107783414A (zh) * | 2016-08-25 | 2018-03-09 | 通用汽车环球科技运作有限责任公司 | 具有动态容错要求的系统的协调多模式分配和运行时切换 |
| GB2566603A (en) * | 2017-08-21 | 2019-03-20 | Fisher Rosemount Systems Inc | High performance control server system |
| CN110582732A (zh) * | 2017-05-01 | 2019-12-17 | 费希尔-罗斯蒙特系统公司 | 开放式架构工业控制系统 |
| WO2020047951A1 (fr) * | 2018-09-06 | 2020-03-12 | 天奇自动化工程股份有限公司 | Système de commande de redondance de sécurité à niveaux multiples pour système de monorail électrifié |
| CN111427688A (zh) * | 2020-03-23 | 2020-07-17 | 武汉轻工大学 | 云任务多目标调度方法、装置、电子设备及存储介质 |
| EP3715970A1 (fr) * | 2019-03-29 | 2020-09-30 | Honeywell International Inc. | Organes de commande redondants ou passerelles d'entrée-sortie sans matériel dédié |
| EP3722897A1 (fr) * | 2019-04-07 | 2020-10-14 | Honeywell International Inc. | Efficacité d'ingénierie d'architecture hive de commande pour un système d'automatisation industrielle |
| EP4174651A1 (fr) | 2021-10-26 | 2023-05-03 | Abb Schweiz Ag | Orchestration d'exécution de charge de travail déterministe |
| EP4198663A1 (fr) * | 2021-12-16 | 2023-06-21 | Schneider Electric Industries SAS | Procédé de calcul reparti des taches de calcul |
| DE102022105472A1 (de) | 2022-03-09 | 2023-09-14 | Endress+Hauser SE+Co. KG | System der Automatisierungstechnik |
| US11762742B2 (en) | 2020-03-31 | 2023-09-19 | Honeywell International Inc. | Process control system with different hardware architecture controller backup |
| US11874938B2 (en) | 2020-11-03 | 2024-01-16 | Honeywell International Inc. | Admittance mechanism |
| US11989084B2 (en) | 2020-09-23 | 2024-05-21 | Honeywell International Inc. | Self-healing process control system |
| US12164283B2 (en) | 2019-08-30 | 2024-12-10 | Phoenix Contact Gmbh & Co. Kg | Method and industrial controller for the synchronized calling of a function block in a control program having OPC UA |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2000062135A1 (fr) | 1999-04-09 | 2000-10-19 | Abb Automation Inc. | Redondance de controleur numerique par detection de defaillance sur reseau neuronal |
| US20080208361A1 (en) * | 2007-02-27 | 2008-08-28 | Rockwell Automation Technologies, Inc. | Dynamic load balancing using virtual controller instances |
| EP2048561A2 (fr) * | 2007-09-18 | 2009-04-15 | Fisher-Rosemount Systems, Inc. | Procédés et appareils pour mettre à niveau des installations de traitement et leur fournir une redondance de commande |
| WO2012047654A1 (fr) * | 2010-09-27 | 2012-04-12 | Fisher-Rosemount Systems, Inc. | Procédés et appareil pour virtualiser un système de contrôle de processus |
| EP2506098A1 (fr) * | 2011-03-31 | 2012-10-03 | Siemens Aktiengesellschaft | Agencement et procédé pour le fonctionnement d'un agencement d'automatisation industriel doté d'une multitude de composants d'automatisation programmables et d'une multitude de programmes d'automatisation |
| EP2682829A2 (fr) * | 2012-07-03 | 2014-01-08 | Yokogawa Electric Corporation | Dispositif, système et procédé de commande de processus |
-
2014
- 2014-05-07 WO PCT/EP2014/059346 patent/WO2015169352A1/fr not_active Ceased
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2000062135A1 (fr) | 1999-04-09 | 2000-10-19 | Abb Automation Inc. | Redondance de controleur numerique par detection de defaillance sur reseau neuronal |
| US20080208361A1 (en) * | 2007-02-27 | 2008-08-28 | Rockwell Automation Technologies, Inc. | Dynamic load balancing using virtual controller instances |
| EP2048561A2 (fr) * | 2007-09-18 | 2009-04-15 | Fisher-Rosemount Systems, Inc. | Procédés et appareils pour mettre à niveau des installations de traitement et leur fournir une redondance de commande |
| WO2012047654A1 (fr) * | 2010-09-27 | 2012-04-12 | Fisher-Rosemount Systems, Inc. | Procédés et appareil pour virtualiser un système de contrôle de processus |
| EP2506098A1 (fr) * | 2011-03-31 | 2012-10-03 | Siemens Aktiengesellschaft | Agencement et procédé pour le fonctionnement d'un agencement d'automatisation industriel doté d'une multitude de composants d'automatisation programmables et d'une multitude de programmes d'automatisation |
| EP2682829A2 (fr) * | 2012-07-03 | 2014-01-08 | Yokogawa Electric Corporation | Dispositif, système et procédé de commande de processus |
Non-Patent Citations (1)
| Title |
|---|
| ANONYMOUS: "Industrial Control Solutions Guide", INTERNET CITATION, 26 January 2007 (2007-01-26), XP002475491, Retrieved from the Internet <URL:http://www.archive.org/web/20070126043519/http://rtcmagazine.com/pdfs/ICSGv3.pdf> [retrieved on 20080408] * |
Cited By (29)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2017166692A (ja) * | 2016-02-26 | 2017-09-21 | ネル ハイドロジェン アクティーゼルスカブ | 水素燃料補給システム用通信システム |
| CN107783414A (zh) * | 2016-08-25 | 2018-03-09 | 通用汽车环球科技运作有限责任公司 | 具有动态容错要求的系统的协调多模式分配和运行时切换 |
| JP2020518921A (ja) * | 2017-05-01 | 2020-06-25 | フィッシャー−ローズマウント システムズ,インコーポレイテッド | オープンアーキテクチャ産業制御システム |
| CN110582732A (zh) * | 2017-05-01 | 2019-12-17 | 费希尔-罗斯蒙特系统公司 | 开放式架构工业控制系统 |
| GB2608035A (en) * | 2017-05-01 | 2022-12-21 | Fisher Rosemount Systems Inc | Open architecture industrial control system |
| CN110582732B (zh) * | 2017-05-01 | 2023-06-02 | 费希尔-罗斯蒙特系统公司 | 开放式架构工业控制系统 |
| JP7257329B2 (ja) | 2017-05-01 | 2023-04-13 | フィッシャー-ローズマウント システムズ,インコーポレイテッド | オープンアーキテクチャ産業制御システム |
| GB2575758B (en) * | 2017-05-01 | 2023-04-12 | Fisher Rosemount Systems Inc | Open architecture industrial control system |
| GB2608035B (en) * | 2017-05-01 | 2023-03-22 | Fisher Rosemount Systems Inc | Open architecture industrial control system |
| GB2605871B (en) * | 2017-05-01 | 2023-02-08 | Fisher Rosemount Systems Inc | Open architecture industrial control system |
| GB2605871A (en) * | 2017-05-01 | 2022-10-19 | Fisher Rosemount Systems Inc | Open architecture industrial control system |
| US10620613B2 (en) | 2017-08-21 | 2020-04-14 | Fisher-Rosemount Systems, Inc. | High performance control server system |
| GB2566603B (en) * | 2017-08-21 | 2022-06-22 | Fisher Rosemount Systems Inc | High performance control server system |
| GB2566603A (en) * | 2017-08-21 | 2019-03-20 | Fisher Rosemount Systems Inc | High performance control server system |
| WO2020047951A1 (fr) * | 2018-09-06 | 2020-03-12 | 天奇自动化工程股份有限公司 | Système de commande de redondance de sécurité à niveaux multiples pour système de monorail électrifié |
| US11481282B2 (en) | 2019-03-29 | 2022-10-25 | Honeywell International Inc. | Redundant controllers or input-output gateways without dedicated hardware |
| CN111752139A (zh) * | 2019-03-29 | 2020-10-09 | 霍尼韦尔国际公司 | 不具有专用硬件的冗余控制器或输入-输出网关 |
| EP3715970A1 (fr) * | 2019-03-29 | 2020-09-30 | Honeywell International Inc. | Organes de commande redondants ou passerelles d'entrée-sortie sans matériel dédié |
| EP3722897A1 (fr) * | 2019-04-07 | 2020-10-14 | Honeywell International Inc. | Efficacité d'ingénierie d'architecture hive de commande pour un système d'automatisation industrielle |
| CN111796563A (zh) * | 2019-04-07 | 2020-10-20 | 霍尼韦尔国际公司 | 工业自动化系统的控制蜂巢架构工程效率 |
| US12164283B2 (en) | 2019-08-30 | 2024-12-10 | Phoenix Contact Gmbh & Co. Kg | Method and industrial controller for the synchronized calling of a function block in a control program having OPC UA |
| CN111427688B (zh) * | 2020-03-23 | 2023-08-11 | 武汉轻工大学 | 云任务多目标调度方法、装置、电子设备及存储介质 |
| CN111427688A (zh) * | 2020-03-23 | 2020-07-17 | 武汉轻工大学 | 云任务多目标调度方法、装置、电子设备及存储介质 |
| US11762742B2 (en) | 2020-03-31 | 2023-09-19 | Honeywell International Inc. | Process control system with different hardware architecture controller backup |
| US11989084B2 (en) | 2020-09-23 | 2024-05-21 | Honeywell International Inc. | Self-healing process control system |
| US11874938B2 (en) | 2020-11-03 | 2024-01-16 | Honeywell International Inc. | Admittance mechanism |
| EP4174651A1 (fr) | 2021-10-26 | 2023-05-03 | Abb Schweiz Ag | Orchestration d'exécution de charge de travail déterministe |
| EP4198663A1 (fr) * | 2021-12-16 | 2023-06-21 | Schneider Electric Industries SAS | Procédé de calcul reparti des taches de calcul |
| DE102022105472A1 (de) | 2022-03-09 | 2023-09-14 | Endress+Hauser SE+Co. KG | System der Automatisierungstechnik |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2015169352A1 (fr) | Utilisation de contrôleurs flexibles dans un système de commande de processus | |
| CN101393430B (zh) | 在过程设备中升级及提供控制冗余的方法及设备 | |
| CN111752139B (zh) | 不具有专用硬件的冗余控制器或输入-输出网关 | |
| US12190217B2 (en) | Industrial process control system as a data center of an industrial process plant | |
| US11681278B2 (en) | High availability for container based control execution | |
| US8132042B2 (en) | Method and device for exchanging data on the basis of the OPC communications protocol between redundant process automation components | |
| JP4405511B2 (ja) | 複数のサービス・ポイントを有する自律コンピューティングにおける動的に構成可能な耐障害性 | |
| CN106980529B (zh) | 基板管理控制器资源管理的电脑系统 | |
| CN102117225B (zh) | 一种工业自动化多点集群系统及其任务管理方法 | |
| KR20150124642A (ko) | 병렬 연결식 서버시스템의 통신 장애 복구방법 | |
| GB2609089A (en) | Visualization of a software defined process control system for industrial process plants | |
| CN111796563A (zh) | 工业自动化系统的控制蜂巢架构工程效率 | |
| CN113253635A (zh) | 初级自动化设备与多个次级设备的多重同步 | |
| WO2013098633A2 (fr) | Module d'interface relais destiné à un système de commande réparti | |
| US20160320762A1 (en) | Automation Equipment and Method for Operating Automation Equipment | |
| JP7349416B2 (ja) | 分散制御システム | |
| EP2811354A1 (fr) | Système d'automatisation de processus avec une unité de calcul centrale | |
| US20220350311A1 (en) | Multi-cloud industrial controller | |
| CN120019632A (zh) | 以太网高级物理层上的负载分配和高可用性 | |
| JP2016015065A (ja) | プロセス監視制御システム | |
| EP1966660A1 (fr) | Unite de traitement et procede pour la configuration d'un systeme d'automatisation en reseau | |
| JP2014215622A (ja) | プラント監視システム及びプラント監視方法 | |
| CN107885099A (zh) | 仿真及增强仿真2oo2安全平台设备、安全平台维护方法 | |
| CN116009381A (zh) | 用于过程控制系统中的故障处理的方法和装置 | |
| KR20100044428A (ko) | 다중서버 상위구조를 갖는 선박자동화 시스템 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 14722210 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 14722210 Country of ref document: EP Kind code of ref document: A1 |