[go: up one dir, main page]

WO2013039315A2 - Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same - Google Patents

Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same Download PDF

Info

Publication number
WO2013039315A2
WO2013039315A2 PCT/KR2012/007280 KR2012007280W WO2013039315A2 WO 2013039315 A2 WO2013039315 A2 WO 2013039315A2 KR 2012007280 W KR2012007280 W KR 2012007280W WO 2013039315 A2 WO2013039315 A2 WO 2013039315A2
Authority
WO
WIPO (PCT)
Prior art keywords
row
segment
strand
fixing
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/KR2012/007280
Other languages
French (fr)
Korean (ko)
Other versions
WO2013039315A3 (en
Inventor
마상준
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CMER CO LTD
Korea Institute of Civil Engineering and Building Technology KICT
Original Assignee
CMER CO LTD
Korea Institute of Construction Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMER CO LTD, Korea Institute of Construction Technology filed Critical CMER CO LTD
Priority to CN201280044802.1A priority Critical patent/CN103797216B/en
Publication of WO2013039315A2 publication Critical patent/WO2013039315A2/en
Publication of WO2013039315A3 publication Critical patent/WO2013039315A3/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Definitions

  • the present invention relates to a segment structure having a longitudinal strand and a transverse shear key and a method for constructing a shield tunnel using the same. More specifically, the present invention relates to a segment structure having two center passages and two end passages. Arrange sequentially in each row adjacently in the longitudinal direction, with four rows of longitudinal segments as one unit to insert, tension, and anchor the strands, and to ensure that only one strand is anchored in each segment so that only those segments are fixed and fixed.
  • the remaining three strands are settled and fixed sequentially in the same way as the segments located in the other rows through the passageway, thereby forming a segment-based reaction wall through which all four strands penetrate, and at the same time structurally stable foundation reaction wall Segment of different columns by the remaining three strands Fixation and fixation are facilitated sequentially, and by repeating the above process, fixation and fixation of the segment foundation reaction wall and thus other columns is sequentially performed with excavation.
  • the assembly of the segments is efficient and economical, which is a useful invention for shield tunnels.
  • the shield tunnel method is a method of assembling and dismantling segments by a shield tunnel drilling device and at the same time assembling a supporter.
  • the shield tunnel method is excavated by the rotation of the tip cutter head of the shield tunnel excavator, and the soil produced by the excavation is disposed of and discharged out through a screw conveyor provided in the shield tunnel excavator. It is a process consisting of a series of systems for assembling segments that are supported by space.
  • Shield tunnel excavators are generally well known.
  • the shield tunnel excavator 10 is largely composed of a cutter head 16, a head portion 22, a shield body 12, and a tail portion 24.
  • An opening 86 is formed at an upper portion of the partition 30, and a lid 88 hinged to the partition 30 is disposed at the opening 86.
  • the lid 88 is connected to the piston rod 92 of the cylinder 90 attached to the diaphragm 32 via the arm 94.
  • the lid 88 normally closes the opening portion 86 by the cylinder 90, but the earth pressure applied to the space portion between the partition 30 and the cutter head 16 is set in the cylinder 90. When the pressure is exceeded, the opening 86 is opened to be driven toward the diaphragm 32 against the pressure of the cylinder 90 so as to introduce the sand into the grinding chamber 28.
  • the rotor 96 and the stator 98 which comprise the crusher which crushes the comparatively large gravel which entered the grinding chamber 28 are arrange
  • the rotor 96 is attached to the rotation shaft 68, and the stator 98 is attached to the partition wall 30 below the rotor 96.
  • High pressure water is also sent to the grinding chamber (28) via the feed pipe (100), and the supplied water is discharged to the rear of the shield body (12) via the discharge pipe (102) together with the soil in the grinding chamber (28). do.
  • the propulsion jacks 14 of the drilling device 10 have the piston rods 46 and 48 being retracted into the cylinder 40.
  • the excavator 10 receives the propulsion force of the shield body 12 by the propulsion jacks 14, and each motor 70 of the rotating mechanism 18 is rotated, and the rotation of each motor 70 is reduced.
  • the cutter head 16 is rotated by being transmitted to the face plate 58 via the 72, the tooth 74, the tooth 76 and the rotation shaft 68. It is pushed while being excavated by the rotation of the cutter head 16.
  • the excavated earth and sand enters the space in front of the partition wall 30, and then enters into the grinding chamber 28 via the opening 86 of the partition wall 30 and then discharges the discharge pipe 102 from the grinding chamber 28. It is discharged with water via diesel.
  • the segment 104 is disposed in the space formed behind the shield body 12.
  • Circular shield support ball (10) consists of seven segments and is fixed by the key (K) segment.
  • each segment Four sides of each segment have a drainage flow path 16 and a drainage structure provided with a water stop 18 before and after the drainage flow path 16.
  • a water stop 18 before and after the drainage flow path 16.
  • Patent No. 10-0936471 is a structure having a cross-sectional joint where all the end joints of 7 segments meet in one plane, even though the permeation prevention and treatment are perfectly achieved by the drainage structure. Since there is no longitudinal binding structure (e.g., steel wire structure) to connect and bind, there is a problem that the cross-section joint is easily shifted up and down even by the biasing caused by the ground. The impact of the earthquake is greater and more serious than the problem of partial pressure. Absolute preparations for earthquakes are required. Legally mandatory seismic design is considered to reflect the seriousness of this problem.
  • longitudinal binding structure e.g., steel wire structure
  • Shear stress and stranded wires are formed by forming shear keys in the transverse direction of each segment, arranging segments in each row in a zigzag shape, and arranging strands to form segment-based reaction walls.
  • the overlap stiffness is increased to provide a rigid segment structure with high durability against earthquakes, etc.
  • the configuration of the present invention is as follows. (See Figs. 4, 5, 6, and 7)
  • two center passages (10) and two end passages (20) are formed at right angles to the cross-section joint, but the two center passages (10) are provided with stranded wire passages (F3, F4) and strands. While the fixing units G1 and G2 are formed, the strand wire fixing units G1 and G2 are located in the direction of the tunnel excavation, and the two end passages 20 include the strand wire inserting and fixing space portions E1 and E2.
  • segment structure having a longitudinal strand and a transverse shear key.
  • the strand anchoring unit G1, G2 has a conical hole corresponding to the tip male cone of the strand, and the strand insertion / fixing space portions E1, E2 have a space portion corresponding to the trailing edge of the strand.
  • a segment structure having a directional strand and a transverse shear key.
  • the shield tunnel of the present invention has a circular cross section as shown in FIG.
  • the number of segments forming a circular cross section is an odd number. Seven or five are preferred.
  • the odd columns are arranged in the same position, and the even columns of the second column, the second column, and the sixth column are located in the center line of the A segment. That is, it is located down by 1/2 of A.
  • the K segment is assembled wedge-shaped as a key segment.
  • the K segment is the same as the basic segment A, but is formed shorter by Qd than Qa in the upper and lower Qa of the Q straight line.
  • the B and C segments are adjacent to the K segment and differ only from the basic segment A only in the adjacent plane.
  • the B segment is formed at the lower Qa of the Q straight line, and the C segment is longer than Qa at the upper Qa of the Q straight line.
  • Zigzag assembly of the segments is made by two adjacent segments at Qc and Pc.
  • two Qa are assembled adjacent to each other in Qc (see Fig. 9).
  • each segment is only slightly different from the K segment and the adjacent B and C segments, the segment is easy to manufacture because it is not significantly different from the basic A segment.
  • two center passages 10 and two end passages 20 are formed parallel to each other at right angles to the cross-sectional joint.
  • the two center passages 10 are close to the center line of the segment, and the two end passages 20 are symmetrical about the center line while being close to the ends. Since the strand should pass through the center passage 10 through the end passage 20, the distance between the center line and the end is the same.
  • the stranded wire starting from the insertion / fixed space portions E1 and E2 of the end passage 20 passes through the stranded wire anchoring portions G1 and G2 of the center passage 10 as shown in FIGS. 9 and 10. It is a zigzag connection structure settled at (G1, G2).
  • the closer the strand line fixing portions G1 and G2 of the center passage 10 are to the center line the more the eccentric bending moment due to earth pressure can be minimized, and a rigid structure of the segment can be formed.
  • the insertion / fixed space portions E1 and E2 are formed on one side of the end passage 20, and the strand wire fixing portions G1 and G2 are formed on one side of the center passage 10, and are located in opposite directions.
  • the strand wire insertion / fixing space portions E1 and E2 are spaces into which a new strand wire is inserted.
  • the water-expandable index member may be formed around the channel grooves in the center at all the contact portions where the segments and the segments contact each other.
  • Shear stress and strand due to shear key are formed by forming shear key in the transverse direction of each segment, and arranging the segments in each row in a zigzag form and forming a stranded reaction wall to form a segment-based reaction wall. Overlap stiffness is increased, resulting in a strong segment structure having high durability against earthquakes.
  • FIG. 1 is a cross-sectional state diagram of a shield tunnel excavator generally used.
  • FIG. 2 is a perspective view of a conventional shield segment
  • 3 is a circular cross-sectional view of the shield segment of the present invention.
  • FIG. 4 is a perspective view of the basic segment A of the present invention.
  • FIG. 5 is a perspective view of the B segment of the present invention.
  • FIG. 6 is a perspective view of the C segment of the present invention.
  • FIG. 7 is a perspective view of the K segment of the present invention.
  • FIG. 8 is an enlarged view of FIG.
  • FIG. 9 is a plan view showing a state in which the segments of the present invention are arranged in a zigzag form
  • FIG. 10 is a schematic diagram illustrating passage and settling of a stranded wire for an A1 segment in a fourth row in FIG.
  • FIG. 11 is a perspective view of a segment used in the conventional bolt method
  • FIG. 12 is a cross-sectional view of the joints of FIG. 11 joined by bolts.
  • the length of the strand is approximately equal to the length of four longitudinal segments arranged. This is because the stranded wire connects and fixes the four longitudinal segments in one unit.
  • One unit of the strand is a four segment row.
  • FIG. 10 is a schematic diagram of four strands for A1 in the fourth row in the segment assembly of FIG.
  • the stranded ship starting from the first row E2 in Fig. 10 is tensioned and settled in the fourth row G1.
  • Four strands pass through A1 in the fourth row.
  • the starting point and the fixation point of the four strands passing through A1 in the fourth column are different.
  • Settled in column A1 of the fourth row is the only stranded ship starting from the first row. This strand secures A1 in the fourth row first.
  • A1 of the fourth column is fixed in this manner, the strands start in the second row, the third row, and the fourth row.
  • the strands of the second, third, and fourth columns cannot pass through A1 of the fourth column. This is because it is virtually impossible to pass through the A2 in the fifth row, where the second strand of the strand is not fixed.
  • A1 of the fourth row must be fixed by the stranded ship starting from the first row E2, so that the stranded ship starting from the second row passes through A1 of the fourth row and is then settled in the fifth row. This is because the fifth column is possible only when the fourth column is fixed.
  • the fifth row and the fourth row may be fixed at the same time.
  • segment foundation reaction wall is made by the settlement of the strand, and then another foundation reaction wall is repeatedly formed in the direction of excavation while strengthening the foundation reaction wall by the three strands.
  • the four strands in the fourth row are the strands starting from the first row, the second row, the third row, and the fourth row.
  • the stranded ship that has been tensed and settled in the fourth row G1 starting from the first row E2 and has left the second row E2 is the stranded ship that has been tensed and settled in the fifth row G1.
  • the stranded wire is tensioned and settled in the third row E1 to the sixth row G2, and tensioned and settled in the fourth row E1 to the seventh row G2.
  • the strands inserted into the four throughways of the fourth row are the strands starting from the first row, the second row, the third row, and the fourth row, and at the same time relying on the fourth row, the fifth row, the sixth row, and the seventh row. It is a supporting member which fixes and fixes heat sequentially. It is for this reason that A1 in the fourth column is called the base reaction wall.
  • the shear stress of the shear key increases as the segments of each row are arranged in a zigzag, and the four strands are fixed and fixed only one for each row. Therefore, the overlapping stiffness of the strands increases, which is robust against earth pressure and earthquake. Construction is facilitated because it serves as a foundation reaction wall for the segments that are subsequently constructed while forming the structure.
  • the length of the strand is the length at which the tensile force is maximized while the loss is minimized.
  • the foundation reaction wall is not provided. This is inevitable because the segments and strands are assembled in a zigzag.
  • the conventional bolt method and the assembly method of the present invention will be performed in parallel. Since the conventional bolt method is a widely used method, only the outline thereof will be described briefly by Korean Patent Laid-Open Publication No. 10-2004-0026598.
  • the vertical bolt box 13 and the horizontal bolt box 12 are formed in the segment of JP-A-10-2004-0026598. Only the transverse bolt box 12 is connected in the transverse direction and the longitudinal bolt box 13 is omitted and the longitudinal strand line passage of the present invention is formed in the longitudinal direction. First, the lateral bolt box 12 is bolted, and then the stranded wire is tensioned and fixed to the longitudinal stranded wire passage in the same manner as above.
  • FIG. 12 shows a state in which the lateral bolt boxes 12 are in contact with each other and fixed as the fixing bolts 7 and the nuts 8.
  • the strands After passing through (F3-G1) in the fifth row, the strands are tensioned and fixed to the strand anchorage part G1 of each segment (A1, A2, B, K, C, A3, A4) located in the fifth row, While the segments are fixed, the strands are inserted into the strands and fixed space portions E1 of each segment in the order of the third row and the fourth row in the same manner as described above, and the sixth and seventh rows are placed in the sixth and seventh rows, respectively.
  • Segman The step of fixing the respective segments in the sixth column and the seventh column in tension and fixing the strand in the strand fixing portion G2 of (A1, A2, B, K, C, A3, A4);
  • Each segment of the fifth row is fixed by the insertion and tension of the strand in the second row, and each segment of the sixth row is fixed by the insertion and tension of the third row. Fixing each segment located in the eighth row in the same manner as the first row by inserting and stretching the fifth strand of the strand in the state where the segments are fixed;
  • Each segment fixing in column 9 is by inserting / tensioning in the sixth row, and each segment fixing in column 10 is fixed by inserting / tensioning in the seventh row.
  • the shield tunnel construction method using the segment structure having the directional strand and the transverse shear key is included.
  • a segment male having a directional strand and a transverse shear key characterized in that a male tip of the strand is fixed in a conical hole formed in the strand anchoring portions G1 and G2, and the rear fixed portion of the strand is fixed to the strand insertion / fixing space portions E1 and E2.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention enables each segment, in which two center through-paths and two end through-paths are formed, to be sequentially and adjacently arranged at each column in a vertical direction, wherein: horizontal segments at four columns are set as one unit such that strands are inserted, strained, and settled therein; only one strand is settled in each segment such that only the corresponding segment is settled and fixed; the segments, by the remaining three strands, located at the other columns are sequentially settled and fixed in the same manner as above via through-paths, thereby forming a foundation reaction wall through which all the four strands pass, and at the same time, segments at the other columns are also sequentially and easily settled and fixed by the remaining three strands with respect to structurally-stabilized foundation reaction wall; and the foundation reaction wall of the segments is formed and the other columns in accordance with the foundation reaction wall are sequentially settled and fixed together with a drilling operation by repeating the above steps. Thus, through said features, the invention allows the segments to be assembled in an efficient and economical manner.

Description

종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체 및 이를 이용한 실드터널의 구축공법Segment Structure with Longitudinal Strand and Transverse Shear Key and Construction Method of Shield Tunnel

본 발명은 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체 및 이를 이용한 실드터널의 구축공법에 관한 것으로 이를 좀 더 구체적으로 말하면, 2개의 센터관통로와, 그리고 2개의 단부관통로가 형성된 각 세그먼트를 종방향으로 인접되게 각각의 열로 순차적으로 배열하되 4개열의 종방향 세그먼트를 한 단위로 하여 강연선을 삽입ㆍ긴장ㆍ정착되게 하고, 각 세그먼트에는 하나의 강연선만 정착되게 하여 그 세그먼트만 정착ㆍ고정되게 하며, 나머지 3개의 강연선은 관통로를 거쳐 다른 열에 위치한 세그먼트를 위와 같은 방식으로 순차적으로 정착ㆍ고정되게 함으로써 4개의 강연선이 모두 관통된 세그먼트 기초 반력벽이 형성되도록 함과 동시에 구조적으로 안정된 기초 반력벽을 중심으로 나머지 3개의 강연선에 의하여 다른 열의 세그먼트도 순차적으로 정착ㆍ고정이 용이하게 되고, 이와 같은 과정의 반복에 의하여 세그먼트 기초 반력벽과 이에 따른 다른 열의 정착ㆍ고정이 순차적으로 굴진과 함께 이루어진다. The present invention relates to a segment structure having a longitudinal strand and a transverse shear key and a method for constructing a shield tunnel using the same. More specifically, the present invention relates to a segment structure having two center passages and two end passages. Arrange sequentially in each row adjacently in the longitudinal direction, with four rows of longitudinal segments as one unit to insert, tension, and anchor the strands, and to ensure that only one strand is anchored in each segment so that only those segments are fixed and fixed. The remaining three strands are settled and fixed sequentially in the same way as the segments located in the other rows through the passageway, thereby forming a segment-based reaction wall through which all four strands penetrate, and at the same time structurally stable foundation reaction wall Segment of different columns by the remaining three strands Fixation and fixation are facilitated sequentially, and by repeating the above process, fixation and fixation of the segment foundation reaction wall and thus other columns is sequentially performed with excavation.

세그먼트의 조립이 효율적이고 경제적이어서 실드터널에 유용한 발명이다.The assembly of the segments is efficient and economical, which is a useful invention for shield tunnels.

실드터널공법은 실드터널 굴진장치에 의해 굴진ㆍ배토하면서 동시에 지보공인 세그먼트를 조립해나가는 공법이다.The shield tunnel method is a method of assembling and dismantling segments by a shield tunnel drilling device and at the same time assembling a supporter.

좀 더 구체적으로 말하면, 실드터널공법은 실드터널 굴진장치의 선단 커터헤드의 회전에 의해 굴진되고, 굴진에 의해 생성된 흙은 실드터널 굴진장치내에 구비된 스크류 컨베이어를 통해 밖으로 배토 처리되고, 배토된 공간에 지보공인 세그먼트를 조립하는 일련의 시스템으로 이루어진 공법이다.More specifically, the shield tunnel method is excavated by the rotation of the tip cutter head of the shield tunnel excavator, and the soil produced by the excavation is disposed of and discharged out through a screw conveyor provided in the shield tunnel excavator. It is a process consisting of a series of systems for assembling segments that are supported by space.

실드터널 굴진장치는 일반적으로 널리 알려져 있다. Shield tunnel excavators are generally well known.

그중에서 특허공보 공고번호 제93-006410호에 기재된 실드터널 굴진장치에 대하여 설명하면 다음과 같다. (도1참조)Among them, the shield tunnel drilling apparatus described in Patent Publication No. 93-006410 is as follows. (See Fig. 1)

실드터널 굴진장치(10)는 크게 커터헤드(16)와, 헤드부(22)와, 실드본체(12)와, 그리고 테일부(24)로 이루어진 구성이다.The shield tunnel excavator 10 is largely composed of a cutter head 16, a head portion 22, a shield body 12, and a tail portion 24.

격벽(30)의 상부에는 개방부(86)가 형성되어 있으며, 이 개방부(86)에는 격벽(30)에 힌지 결합된 뚜껑(88)이 배치되어 있다. 뚜껑(88)은 격막(32)에 부착된 실린더(90)의 피스톤로드(92)에 아암(94)을 개재하여 연결되어 있다.An opening 86 is formed at an upper portion of the partition 30, and a lid 88 hinged to the partition 30 is disposed at the opening 86. The lid 88 is connected to the piston rod 92 of the cylinder 90 attached to the diaphragm 32 via the arm 94.

이 뚜껑(88)은 평상시는 실린더(90)에 의해 개방부(86)를 폐쇄하고 있으나, 격벽(30)과 커터헤드(16) 사이의 공간부에 받아들여진 토사압력이 실린더(90)에 설정된 압력을 초과할 때 실린더(90)의 압력에 대항하여 격막(32)측으로 구동되어 토사를 분쇄실(28)내로 유입시키도록 개방부(86)를 개방한다.The lid 88 normally closes the opening portion 86 by the cylinder 90, but the earth pressure applied to the space portion between the partition 30 and the cutter head 16 is set in the cylinder 90. When the pressure is exceeded, the opening 86 is opened to be driven toward the diaphragm 32 against the pressure of the cylinder 90 so as to introduce the sand into the grinding chamber 28.

분쇄실(28)에는 이 분쇄실(28)내로 들어온 비교적 큰 자갈을 파쇄하는 크러셔(crusher)를 구성하는 로터(96) 및 스테이터(98)가 배치되어 있다. 로터(96)는 회전축(68)에 부착되며, 스테이터(98)는 로터(96)의 아래쪽에 있는 격벽(30)에 부착되어 있다. 분쇄실(28)에는 또 고압수가 급수파이프(100)를 경유해 보내지며, 공급된 물은 분쇄실(28)내의 토사와 함께 배출파이프(102)를 경유하여 실드본체(12)의 뒤쪽으로 배출된다. 굴진개시 시에 굴진장치(10)의 각 추진잭(14)은 피스톤로드(46), (48)가 실린더(40)내로 후퇴되어 있다.In the grinding chamber 28, the rotor 96 and the stator 98 which comprise the crusher which crushes the comparatively large gravel which entered the grinding chamber 28 are arrange | positioned. The rotor 96 is attached to the rotation shaft 68, and the stator 98 is attached to the partition wall 30 below the rotor 96. High pressure water is also sent to the grinding chamber (28) via the feed pipe (100), and the supplied water is discharged to the rear of the shield body (12) via the discharge pipe (102) together with the soil in the grinding chamber (28). do. At the start of drilling, the propulsion jacks 14 of the drilling device 10 have the piston rods 46 and 48 being retracted into the cylinder 40.

이 상태에서 굴진장치(10)는 각 추진잭(14)에 의해 실드본체(12)에 추진력을 받으면서 회전기구(18)의 각 모터(70)가 회전되고, 각 모터(70)의 회전이 감속기(72), 치차(74), 대치차(76) 및 회전축(68)을 경유하여 면판(58)으로 전달되는 것에 의해 커터헤드(16)가 회전된다. 커터헤드(16)의 회전에 의해 굴삭되면서 추진된다. 굴삭된 토사는 격벽(30)의 앞쪽의 공간으로 들어가며, 그후 격벽(30)의 개방부(86)를 경유하여 분쇄실(28)내로 유입된 다음 분쇄실(28)로부터 배출파이프(102)를 경유하여 물과 같이 배출된다. 실드본체(12)가 전진됨으로써 실드본체(12)의 뒤쪽에 형성된 공간에는 세그먼트(104)가 배치되게 된다.In this state, the excavator 10 receives the propulsion force of the shield body 12 by the propulsion jacks 14, and each motor 70 of the rotating mechanism 18 is rotated, and the rotation of each motor 70 is reduced. The cutter head 16 is rotated by being transmitted to the face plate 58 via the 72, the tooth 74, the tooth 76 and the rotation shaft 68. It is pushed while being excavated by the rotation of the cutter head 16. The excavated earth and sand enters the space in front of the partition wall 30, and then enters into the grinding chamber 28 via the opening 86 of the partition wall 30 and then discharges the discharge pipe 102 from the grinding chamber 28. It is discharged with water via diesel. As the shield body 12 is advanced, the segment 104 is disposed in the space formed behind the shield body 12.

상기와 같은 실드터널 굴진장치에 의해 시공된 종래기술인 등록 특허 제10-0936471호의 문제점에 대하여 살펴본다. (도2참조)It looks at the problem of the prior art Patent No. 10-0936471 constructed by the shield tunnel drilling device as described above. (See Fig. 2)

등록 특허 제10-0936471호의 발명자 및 출원인이 본원 발명자 및 출원인과 동일하다. The inventors and applicants of registered patent 10-0936471 are the same as the inventors and applicants of the present application.

원형 실드지보공(10)이 7개의 세그먼트로 이루어지면서 키(K) 세그멘트에 의하여 고정된다.Circular shield support ball (10) consists of seven segments and is fixed by the key (K) segment.

모든 각 세그먼트의 4변에는 배수유도로(16)와, 그리고 배수유도로(16) 전후에 지수제(18)가 설치된 배수 구조를 갖는다. 지수제를 설치함으로써 접합부를 통해 침투수가 침투되지 못하도록 하면서 설령 접합부를 통해 침투되었다하더라도 배수유도로(16)를 통해 밖으로 배출되도록 한 구조이다.Four sides of each segment have a drainage flow path 16 and a drainage structure provided with a water stop 18 before and after the drainage flow path 16. By installing the water repellent agent, even if penetrated through the junction while preventing the penetration of the infiltration through the drainage flow path 16 is a structure that is to be discharged out.

이와 같이 등록 특허 제10-0936471호는 배수구조에 의하여 침투수의 방지 및 처리가 가 완벽하게 이루어지고 있다하더라도 7개의 세그먼트의 끝단 접합부가 한 평면에서 모두 만나는 횡단면 접합부를 갖는 구조인데다 횡단면 접합부를 서로 연결ㆍ결속시키는 종방향의 결속구조(예컨대, 강선구조)가 없기 때문에 지반으로 인한 편압에 의해서도 쉽게 횡단면 접합부가 상하로 어긋나게 되는 문제점이 있다. 지진의 영향은 편압의 문제보다 크고 심각하다. 내진에 대한 절대적인 대비가 요망된다. 내진설계를 법적으로 의무화하는 것도 이러한 문제의 심각성을 반영한 것이라고 생각된다. As described above, Patent No. 10-0936471 is a structure having a cross-sectional joint where all the end joints of 7 segments meet in one plane, even though the permeation prevention and treatment are perfectly achieved by the drainage structure. Since there is no longitudinal binding structure (e.g., steel wire structure) to connect and bind, there is a problem that the cross-section joint is easily shifted up and down even by the biasing caused by the ground. The impact of the earthquake is greater and more serious than the problem of partial pressure. Absolute preparations for earthquakes are required. Legally mandatory seismic design is considered to reflect the seriousness of this problem.

등록 특허 제10-0936471호의 배구구조도 세그먼트 접합부가 지그재그형태로 배열되지 않음을 전제한 것이므로 무엇보다도 횡단면 접합부를 서로 연결ㆍ결속하는 것이 최우선 과제라고 생각된다.Since the volleyball structure of Patent No. 10-0936471 also assumes that the segment joints are not arranged in a zigzag form, it is considered to be the first priority to connect and bind the cross-sectional joints with each other.

(a) 본 발명은 2개의 센터관통로와, 그리고 2개의 단부관통로가 형성된 각 세그먼트를 종방향으로 인접되게 각각의 열로 순차적으로 배열하되 4개열의 종방향 세그먼트를 한 단위로 하여 강연선을 삽입ㆍ긴장ㆍ정착되게 하고, 각 세그먼트에는 하나의 강연선만 정착되게 하여 그 세그먼트만 정착ㆍ고정되게 하며, 나머지 3개의 강연선은 관통로를 거쳐 다른 열에 위치한 세그먼트를 위와 같은 방식으로 순차적으로 정착ㆍ고정되게 함으로써 4개의 강연선이 모두 관통된 세그먼트 기초 반력벽이 형성되도록 함과 동시에 구조적으로 안정된 기초 반력벽을 중심으로 나머지 3개의 강연선에 의하여 다른 열의 세그먼트도 순차적으로 정착ㆍ고정이 용이하게 되고, 이와 같은 과정의 반복에 의하여 세그먼트 기초 반력벽과 이에 따른 다른 열의 정착ㆍ고정이 순차적으로 굴진과 함께 이루어짐으로써 세그먼트의 조립이 효율적이 되도록 함에 그 목적이 있고,(a) In the present invention, two center passages, and two end passages, are arranged in sequence in each row of adjacent segments longitudinally adjacent to each other, and a strand is inserted using four rows of longitudinal segments as a unit. ㆍ Tension and fixation are allowed, and only one strand is settled in each segment so that only the segment is settled and fixed.The remaining three strands are settled and fixed sequentially in the same way as the segments located in the other column through the passageway. As a result, a segment foundation reaction wall through which all four strands penetrate is formed, and at the same time, the other three strands make it easier to fix and fix segments of other rows sequentially based on structurally stable foundation reaction walls. The repetition of sequential ordering and fixation of the segment foundation reaction wall and subsequent heat Its purpose is to make the assembly of the segment more efficient by being done with drilling.

(b) 각 세그먼트의 횡방향으로는 전단키를 형성하고, 종방향으로는 각 열의 세그먼트를 지그재그형태로 배열함과 동시에 세그먼트 기초 반력벽이 형성되도록 강연선을 배열함으로써 전단키에 의한 전단응력 및 강연선에 의한 중첩강성이 증대되어 지진 등에 대한 내구성이 큰 견고한 세그먼트 구조체가 되도록 함에 다른 목적이 있으며,(b) Shear stress and stranded wires are formed by forming shear keys in the transverse direction of each segment, arranging segments in each row in a zigzag shape, and arranging strands to form segment-based reaction walls. The overlap stiffness is increased to provide a rigid segment structure with high durability against earthquakes, etc.

(c) 2개의 센터관통로를 센터라인에, 그리고 2개의 단부관통로를 양단부에 근접시킴으로써 토압의 편압으로 인한 편심 모멘트를 최소화시킬 수 있도록 함에 또 다른 목적이 있다.(c) Another aim is to minimize the eccentric moment due to the bias of earth pressure by placing two center passages close to the center line and two end passages close to both ends.

본 발명의 구성은 다음과 같다. (도4, 도5, 도6, 도7 참조)The configuration of the present invention is as follows. (See Figs. 4, 5, 6, and 7)

본 발명은, 횡단면 접합부에 대하여 직각으로 2개의 센터관통로(10)와 2개의 단부관통로(20)가 형성되어있되 2개의 센터관통로(10)에는 강연선 통행구(F3, F4)와 강연선 정착부(G1, G2)가 형성되어있으면서 강연선 정착부(G1, G2)가 터널 굴진 방향 쪽에 위치되어있고, 또 2개의 단부관통로(20)에는 강연선 삽입ㆍ고정공간부(E1, E2)와 강연선 통행구(F1, F2)가 형성되어있으면서 강연선 삽입ㆍ고정공간부(E1, E2)와 강연선 정착부(G1, G2)는 서로 반대방향에 위치되어있는 한편, P, Q직선에 대하여 Qa=Pa, Qb=Pb, Qc=Pc=2Qa=2Pa의 관계를 갖는 전단키가 형성된 기본 세트먼트 A(A1=A2=A3=A4)가 형성되어있고, A1과 A4를 하단부에 접면시킨 상태에서 A1위에 A2→B와, 그리고 A4위에 A3→C를 순서대로 배열하고, B와 C사이에 K 세그먼트를 삽입하되 B, C, K 세그먼트는 기본 세트먼트 A와 동일하되 B 세그먼트는 Q 직선의 하부 Qa에서, 그리고 C 세그먼트는 Q 직선의 상부 Qa에서 Qa보다 Qd 만큼 더 길게 형성되어있고, 이에 대응된 K 세그먼트는 Q 직선의 상ㆍ하부 Qa에서 Qa보다 Qd 만큼 짧게 형성되어있음을 특징으로 하는 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체이다. In the present invention, two center passages (10) and two end passages (20) are formed at right angles to the cross-section joint, but the two center passages (10) are provided with stranded wire passages (F3, F4) and strands. While the fixing units G1 and G2 are formed, the strand wire fixing units G1 and G2 are located in the direction of the tunnel excavation, and the two end passages 20 include the strand wire inserting and fixing space portions E1 and E2. While the strand line passages F1 and F2 are formed, the strand line insertion / fixing space portions E1 and E2 and the strand line fixing portions G1 and G2 are located in opposite directions, while Qa = Basic set-up A (A1 = A2 = A3 = A4) with a shear key having the relation Pa, Qb = Pb, Qc = Pc = 2Qa = 2Pa is formed, and A1 and A4 are in contact with the lower end and placed on A1. Arrange A2 → B and A3 → C on A4 in this order, and insert a K segment between B and C, but the B, C, and K segments are the same as the basic set A. The segment is formed at the lower Qa of the Q straight line, and the C segment is formed at the upper Qa of the Q straight line by Qd longer than Qa, and the corresponding K segment is formed at the upper and lower Qa of the Q straight line by Qd shorter than Qa. Segment structure having a longitudinal strand and a transverse shear key.

여기에다 강연선 정착부 G1, G2에는 강연선의 선단 숫콘에 대응되는 원추형 홀이 형성되어있고, 강연선 삽입ㆍ고정공간부 E1, E2에는 강연선의 후단 고정부에 대응되는 공간부가 형성되어있음을 특징으로 하는 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체이다. In addition, the strand anchoring unit G1, G2 has a conical hole corresponding to the tip male cone of the strand, and the strand insertion / fixing space portions E1, E2 have a space portion corresponding to the trailing edge of the strand. A segment structure having a directional strand and a transverse shear key.

또 각 세그먼트 4면 접합부에 유로홈과 수팽창 지수제가 형성되어있음을 특징으로 하는 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체이다.A segment structure having a longitudinal strand and a transverse shear key, wherein a flow path groove and a water-expansion index agent are formed at each segment four-faced joint.

본 발명의 실드터널은 도3에서와 같이 원형단면이다. 원형단면을 이루는 세그먼트의 개수는 홀수개로 이루어진다. 7개 또는 5개가 바람직하다. The shield tunnel of the present invention has a circular cross section as shown in FIG. The number of segments forming a circular cross section is an odd number. Seven or five are preferred.

설명의 편의상 7개의 세그먼트로 설명하기로 한다.For convenience of description, it will be described with seven segments.

먼저, 각 세그먼트의 형상에 대하여 설명한다.First, the shape of each segment is demonstrated.

본 발명은 기본 세그먼트 A와, 키 세그먼트인 K와, K 세그먼트에 인접되는 B, C 세그먼트로 이루어진 구성이다. (A1=A2=A3=A4이다.)The present invention is composed of a basic segment A, a key segment K, and a B and C segment adjacent to the K segment. (A1 = A2 = A3 = A4.)

기본 세그먼트 A는 도4에서와 같이 P, Q직선에 대하여 Qa=Pa, Qb=Pb, Qc=Pc=2Qa=2Pa의 관계를 갖는 전단키가 서로 요홈과 요철형태로 형성된 구조이다.As shown in Fig. 4, the basic segment A has a structure in which shear keys having a relationship of Qa = Pa, Qb = Pb, and Qc = Pc = 2Qa = 2Pa with respect to P and Q lines are formed in grooves and irregularities.

도9에서와 같이 각 열의 세그먼트가 지그재그 형태로 조립ㆍ배열된다.As shown in Fig. 9, the segments of each row are assembled and arranged in a zigzag form.

제1열과 제3열과 제5열과 같이 홀수 열은 동일한 위치에 배열되고, 제2열과 제2열과 제6열의 짝수 열은 A 세그먼트의 센타 라인에 위치되어있다. 즉, A의 1/2 만큼 아래에 위치되어있다. Like the first column, the third column, and the fifth column, the odd columns are arranged in the same position, and the even columns of the second column, the second column, and the sixth column are located in the center line of the A segment. That is, it is located down by 1/2 of A.

K 세그먼트는 키 세그먼트로서 쐐기형태로 조립된다.The K segment is assembled wedge-shaped as a key segment.

K 세그먼트는 기본 세그먼트 A와 동일하나 Q 직선의 상ㆍ하부 Qa에서 Qa보다 Qd 만큼 짧게 형성되어있다.The K segment is the same as the basic segment A, but is formed shorter by Qd than Qa in the upper and lower Qa of the Q straight line.

B, C 세그먼트는 K 세그먼트에 인접되는 것으로서 인접면에서만 기본 세그먼트 A와 다를 뿐이다. B 세그먼트는 Q 직선의 하부 Qa에서, 그리고 C 세그먼트는 Q 직선의 상부 Qa에서 Qa보다 Qd 만큼 더 길게 형성되어있다.The B and C segments are adjacent to the K segment and differ only from the basic segment A only in the adjacent plane. The B segment is formed at the lower Qa of the Q straight line, and the C segment is longer than Qa at the upper Qa of the Q straight line.

세그먼트의 지그재그 조립은 Qc와 Pc에서 2개의 인접된 세그먼트에 의하여 이루어진다. 예컨대, Qc에 2개의 Qa가 서로 인접되어 조립된다.(도9 참조)Zigzag assembly of the segments is made by two adjacent segments at Qc and Pc. For example, two Qa are assembled adjacent to each other in Qc (see Fig. 9).

이와 같이 각 세그먼트의 구조가 K 세그먼트와 이에 인접되는 B, C 세그먼트만 그 구조가 약간 다르다할지라도 기본 A 세그먼트와 크게 다르지 않아 세그먼트 제작이 간편하다.As described above, although the structure of each segment is only slightly different from the K segment and the adjacent B and C segments, the segment is easy to manufacture because it is not significantly different from the basic A segment.

다음으로, 각 세그먼트의 강연선 관통로에 대하여 설명한다.Next, the twisted line penetration path of each segment is demonstrated.

각 세그먼트에는 횡단면 접합부에 대하여 직각으로 2개의 센터관통로(10)와 2개의 단부관통로(20)가 서로 평행되게 형성되어있다.In each segment, two center passages 10 and two end passages 20 are formed parallel to each other at right angles to the cross-sectional joint.

2개의 센터관통로(10)는 세그먼트의 센터라인에 근접되어있고, 2개의 단부관통로(20)는 단부에 근접되어있으면서 센터라인을 중심으로 각각대칭이다. 강연선이 센터관통로(10)를 통해 단부관통로(20)로 관통해야하기 때문에 센터라인과의 거리와 단부와의 거리가 동일하다.The two center passages 10 are close to the center line of the segment, and the two end passages 20 are symmetrical about the center line while being close to the ends. Since the strand should pass through the center passage 10 through the end passage 20, the distance between the center line and the end is the same.

단부관통로(20)의 삽입ㆍ고정공간부(E1, E2)에서 출발한 강연선은 도9 및 도10에서와 같이 센터관통로(10)의 강연선 정착부(G1, G2)를 거쳐 강연선 정착부(G1, G2)에서 정착되는 지그재그 형태의 연결구조이다. 여기에다 센터관통로(10)의 강연선 정착부(G1, G2)가 센터라인에 근접되게 할수록 토압으로 인한 편심 휨모멘트를 최소화할 수 있고, 세그먼트의 견고한 구조체를 형성할 수 있다.The stranded wire starting from the insertion / fixed space portions E1 and E2 of the end passage 20 passes through the stranded wire anchoring portions G1 and G2 of the center passage 10 as shown in FIGS. 9 and 10. It is a zigzag connection structure settled at (G1, G2). In addition, the closer the strand line fixing portions G1 and G2 of the center passage 10 are to the center line, the more the eccentric bending moment due to earth pressure can be minimized, and a rigid structure of the segment can be formed.

삽입ㆍ고정공간부(E1, E2)은 단부관통로(20)의 한쪽에, 강연선 정착부(G1, G2)는 센터관통로(10)의 한쪽에 형성되어있으면서 서로 반대방향에 위치되어있다.The insertion / fixed space portions E1 and E2 are formed on one side of the end passage 20, and the strand wire fixing portions G1 and G2 are formed on one side of the center passage 10, and are located in opposite directions.

강연선 삽입ㆍ고정공간부 E1, E2는 새로운 강연선이 삽입이 되는 공간이다.The strand wire insertion / fixing space portions E1 and E2 are spaces into which a new strand wire is inserted.

강연선 정착부 G1, G2의 원추형 홀에는 강연선의 선단 숫콘이 정착되고, 강연선 삽입ㆍ고정공간부 E1, E2에는 강연선의 후단 고정부가 고정된다.In the conical holes of the stranded wire anchoring sections G1 and G2, the male cone of the stranded wire is fixed, and the trailing edge of the stranded wire is fixed to the stranded wire insertion / fixing spaces E1 and E2.

세그먼트와 세그먼트가 접면되는 모든 접면부에는 중앙부의 유로홈을 중심으로 수팽창지수재를 형성할 수도 있다.The water-expandable index member may be formed around the channel grooves in the center at all the contact portions where the segments and the segments contact each other.

(a) 본 발명은 2개의 센터관통로와, 그리고 2개의 단부관통로가 형성된 각 세그먼트를 종방향으로 인접되게 각각의 열로 순차적으로 배열하되 4개열의 종방향 세그먼트를 한 단위로 하여 강연선을 삽입ㆍ긴장ㆍ정착되게 하고, 각 세그먼트에는 하나의 강연선만 정착되게 하여 그 세그먼트만 정착ㆍ고정되게 하며, 나머지 3개의 강연선은 관통로를 거쳐 다른 열에 위치한 세그먼트를 위와 같은 방식으로 순차적으로 정착ㆍ고정되게 함으로써 4개의 강연선이 모두 관통된 세그먼트 기초 반력벽이 형성되도록 함과 동시에 구조적으로 안정된 기초 반력벽을 중심으로 나머지 3개의 강연선에 의하여 다른 열의 세그먼트도 순차적으로 정착ㆍ고정이 용이하게 되고, 이와 같은 과정의 반복에 의하여 세그먼트 기초 반력벽과 이에 따른 다른 열의 정착ㆍ고정이 순차적으로 굴진과 함께 이루어지는 구성이므로 세그먼트의 조립이 효율적이고 경제적인 효과가 있다.(a) In the present invention, two center passages, and two end passages, are arranged in sequence in each row of adjacent segments longitudinally adjacent to each other, and a strand is inserted using four rows of longitudinal segments as a unit. ㆍ Tension and fixation are allowed, and only one strand is settled in each segment so that only the segment is settled and fixed.The remaining three strands are settled and fixed sequentially in the same way as the segments located in the other column through the passageway. As a result, a segment foundation reaction wall through which all four strands penetrate is formed, and at the same time, the other three strands make it easier to fix and fix segments of other rows sequentially based on structurally stable foundation reaction walls. The repetition of sequential ordering and fixation of the segment foundation reaction wall and subsequent heat Since the configuration is made with the excavation, the assembly of the segment has an efficient and economical effect.

(b) 각 세그먼트의 횡방향으로는 전단키를 형성하고, 종방향으로는 각 열의 세그먼트를 지그재그형태로 배열함과 동시에 세그먼트 기초 반력벽이 형성되도록 강연선을 배열한 구성이므로 전단키에 의한 전단응력 및 강연선에 의한 중첩강성이 증대되어 지진 등에 대한 내구성이 큰 견고한 세그먼트 구조체가 된다.(b) Shear stress and strand due to shear key are formed by forming shear key in the transverse direction of each segment, and arranging the segments in each row in a zigzag form and forming a stranded reaction wall to form a segment-based reaction wall. Overlap stiffness is increased, resulting in a strong segment structure having high durability against earthquakes.

(c) 2개의 센터관통로를 센터라인에, 그리고 2개의 단부관통로를 양단부에 근접시킨 것이므로 토압의 편심으로 인한 편심 모멘트가 최소화되어 구조적으로 안정적이다.(c) Since the two center passages are close to the center line and the two end passages are close to both ends, the eccentric moment due to eccentricity of earth pressure is minimized and structurally stable.

[도1] 통상적으로 사용되고 있는 실드터널굴진장치의 단면상태도 1 is a cross-sectional state diagram of a shield tunnel excavator generally used.

[도2] 종래의 실드세그먼트의 사시도2 is a perspective view of a conventional shield segment

[도3] 본 발명의 실드세그먼트가 이루고 있는 원형 단면도 3 is a circular cross-sectional view of the shield segment of the present invention.

[도4] 본 발명의 기본 세그먼트 A의 사시도4 is a perspective view of the basic segment A of the present invention.

[도5] 본 발명의 B 세그먼트의 사시도5 is a perspective view of the B segment of the present invention.

[도6] 본 발명의 C 세그먼트의 사시도6 is a perspective view of the C segment of the present invention.

[도7] 본 발명의 K 세그먼트의 사시도7 is a perspective view of the K segment of the present invention.

[도8] 도4의 확대도8 is an enlarged view of FIG.

[도9] 본 발명의 세그먼트가 지그재그 형태로 배열된 상태를 보인 평면도9 is a plan view showing a state in which the segments of the present invention are arranged in a zigzag form

[도10] 도9중 제4열의 A1 세그먼트에 대한 강연선의 통과 및 정착을 도식화한 도식도FIG. 10 is a schematic diagram illustrating passage and settling of a stranded wire for an A1 segment in a fourth row in FIG.

[도11] 종래의 볼트방식에 사용된 세그먼트의 사시도11 is a perspective view of a segment used in the conventional bolt method

[도12] 도11의 이음매를 볼트에 의하여 결합한 단면상태도 12 is a cross-sectional view of the joints of FIG. 11 joined by bolts.

<도면부호의 간단한 설명><Brief Description of Drawings>

G1, G2; 강연선 정착부 G1, G2; Stranded anchorage

E1, E2; 강연선 삽입ㆍ고정공간부E1, E2; Strand insertion and fixed space part

F1, F2, F3, F4; 강연선 통행구 F1, F2, F3, F4; Stranded passage

10; 센터관통로10; Center passage

20; 단부관통로20; End passage

본 발명의 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체를 이용한 실드터널의 구축공법을 도면과 함께 구체적으로 설명하면 다음과 같다.The construction method of the shield tunnel using the segment structure having the longitudinal strand and the transverse shear key of the present invention will be described in detail with reference to the accompanying drawings.

먼저 본 발명의 지그재그로 조립된 세그먼트에 강연선의 삽입ㆍ정착에 대한 기본개념을 설명하면 다음과 같다.First, the basic concept for the insertion and fixing of the stranded wire in the zigzag segment of the present invention will be described.

강연선의 길이는 4개의 종방향 세그먼트가 배열된 길이와 거의 같다. 4개의 종방향 세그먼트를 한 단위로 강연선이 연결ㆍ정착시키는 구조이기 때문이다. 강연선의 한 단위는 4개의 세그먼트 열이다. 도10에 도시된 바와 같다. 도10은 도9의 세그먼트 조립에서 제4열의 A1에 대한 4개의 강연선을 도식화한 것이다.The length of the strand is approximately equal to the length of four longitudinal segments arranged. This is because the stranded wire connects and fixes the four longitudinal segments in one unit. One unit of the strand is a four segment row. As shown in FIG. FIG. 10 is a schematic diagram of four strands for A1 in the fourth row in the segment assembly of FIG.

예컨대, 도10의 제1열 E2에서 출발한 강연선은 제4열 G1에서 긴장ㆍ정착된다. 4개의 강연선은 제4열의 A1을 모두 통과한다. 이때 제4열의 A1을 통과한 4개의 강연선의 출발점과 정착점은 각기 다르다. 제4열의 A1에 정착되는 것은 제1열에서 출발한 단 하나의 강연선이다. 이 강연선이 제4열의 A1을 맨 먼저 고정시킨다. 제4열의 A1이 이와 같이 고정된 상태에서 순차적으로 제2열, 제3열, 제4열에서 강연선이 출발하게 된다. 제4열의 A1이 고정되지 않은 상태에서 제2열, 제3열, 제4열의 강연선이 제4열의 A1을 통과할 수가 없다. 제2열의 강연선이 고정되지도 않은 제5열의 A2를 통과하기가 사실상 불가능하기 때문이다. For example, the stranded ship starting from the first row E2 in Fig. 10 is tensioned and settled in the fourth row G1. Four strands pass through A1 in the fourth row. At this time, the starting point and the fixation point of the four strands passing through A1 in the fourth column are different. Settled in column A1 of the fourth row is the only stranded ship starting from the first row. This strand secures A1 in the fourth row first. In the state where A1 of the fourth column is fixed in this manner, the strands start in the second row, the third row, and the fourth row. In the state where A1 of the fourth column is not fixed, the strands of the second, third, and fourth columns cannot pass through A1 of the fourth column. This is because it is virtually impossible to pass through the A2 in the fifth row, where the second strand of the strand is not fixed.

제4열의 A1이 제1열 E2에서 출발한 강연선에 의해 고정된 상태가 되어야 제2열에서 출발한 강연선이 제4열의 A1을 통과한 다음 제5열의 정착이 가능하다. 제5열은 제4열이 고정된 상태에서만 가능하기 때문이다. 그리고 제3열에서 출발한 강연선이 제6열의 정착이 가능하기 위해서는 제5열과 제4열이 동시에 고정된 상태이어야 가능하다.A1 of the fourth row must be fixed by the stranded ship starting from the first row E2, so that the stranded ship starting from the second row passes through A1 of the fourth row and is then settled in the fifth row. This is because the fifth column is possible only when the fourth column is fixed. In addition, in order for the stranded ship starting from the third row to be able to settle the sixth row, the fifth row and the fourth row may be fixed at the same time.

모든 세그먼트는 4개의 강연선이 모두 통과하되 단 하나의 강연선만이 그 세그먼트에 정착되고, 나머지 3개의 강연선은 제4열의 A1을 통과한 다음 순차적으로 다음 열에 정착되는 방식이다. 다시 말하면 강연선의 정착에 의하여 세그먼트 기초 반력벽을 만든 다음 3개의 강연선에 의하여 기초 반력벽을 강화시키면서 또 다른 기초 반력벽을 굴진방향을 향하여 반복적으로 형성해나가는 방식이다.All segments pass through all four strands, but only one strand is settled in that segment, and the remaining three strands pass through A1 in the fourth row and are subsequently settled in the next row. In other words, segment foundation reaction wall is made by the settlement of the strand, and then another foundation reaction wall is repeatedly formed in the direction of excavation while strengthening the foundation reaction wall by the three strands.

도10에 의하면, 제4열의 4개의 강연선은, 제1열, 제2열, 제3열, 제4열에서 출발한 강연선이다. 즉, 제1열 E2에서 출발하여 제4열 G1에서 긴장ㆍ정착되고, 제2열 E2을 출발한 강연선은 제5열 G1에서 긴장ㆍ정착된 강연선이다. 이와 마찬가지로 제3열 E1→제6열 G2에서 긴장ㆍ정착되고, 제4열 E1→제7열 G2에서 긴장ㆍ정착된 강연선이다. According to Fig. 10, the four strands in the fourth row are the strands starting from the first row, the second row, the third row, and the fourth row. In other words, the stranded ship that has been tensed and settled in the fourth row G1 starting from the first row E2 and has left the second row E2 is the stranded ship that has been tensed and settled in the fifth row G1. Similarly, the stranded wire is tensioned and settled in the third row E1 to the sixth row G2, and tensioned and settled in the fourth row E1 to the seventh row G2.

이와 같이 제4열의 4개의 관통로에 삽입된 강연선은 제1열, 제2열, 제3열, 제4열에서 출발한 강연선이면서 동시에 제4열에 의지하여 제5열, 제6열, 제7열을 순차적으로 정착ㆍ고정시키는 지지부재이다. 제4열의 A1을 기초 반력벽이라 부르는 것도 이러한 이유에서다.As described above, the strands inserted into the four throughways of the fourth row are the strands starting from the first row, the second row, the third row, and the fourth row, and at the same time relying on the fourth row, the fifth row, the sixth row, and the seventh row. It is a supporting member which fixes and fixes heat sequentially. It is for this reason that A1 in the fourth column is called the base reaction wall.

또한 각 열의 세그먼트가 지그재그로 배열됨으로써 전단키에 의한 전단응력이 증대될 뿐만 아니라 4개의 강연선이 각 열에 대하여 하나씩만 정착ㆍ고정시키는 구조이므로 강연선의 중첩강성이 증대되어 토압으로 인한 편압 및 지진에 견고한 조립구조를 이루면서 이에 연이어 축조되는 세그먼트에 대하여 기초 반력벽으로서 역할을 하기 때문에 축조가 용이하게 된다. 그뿐만 아니라 강연선의 길이는 로스가 최소화되면서 인장력이 최대로 발휘되는 길이이다.In addition, the shear stress of the shear key increases as the segments of each row are arranged in a zigzag, and the four strands are fixed and fixed only one for each row. Therefore, the overlapping stiffness of the strands increases, which is robust against earth pressure and earthquake. Construction is facilitated because it serves as a foundation reaction wall for the segments that are subsequently constructed while forming the structure. In addition, the length of the strand is the length at which the tensile force is maximized while the loss is minimized.

설명의 편의상 7개의 세그먼트에 대하여 설명하였으나 세그먼트의 개수가 홀수면 5개이든 7개이든 위와 동일한 개념이다.For convenience of description, seven segments have been described, but the number of segments is the same concept as the above, whether the number of segments is five or seven.

그런데 도10의 제1열, 제2열, 제3열에는 기초 반력벽이 마련되지 못한 상태이다. 이는 세그먼트와 강연선이 지그재그로 조립되기 때문에 불가피하게 생기는 현상이다.However, in the first column, the second column, and the third column of FIG. 10, the foundation reaction wall is not provided. This is inevitable because the segments and strands are assembled in a zigzag.

제1열, 제2열, 제3열에 대해서는 종래의 볼트방식과 본 발명의 조립방식을 병행하기로 한다. 종래의 볼트방식은 이미 널리 사용되는 방식이므로 공개특허공보 공개번호 제10-2004-0026598호에 의하여 그 개요만 간단히 설명하기로 한다. For the first row, the second row, and the third row, the conventional bolt method and the assembly method of the present invention will be performed in parallel. Since the conventional bolt method is a widely used method, only the outline thereof will be described briefly by Korean Patent Laid-Open Publication No. 10-2004-0026598.

도11에서 보는 바와 같이 공개특허공보 공개번호 제10-2004-0026598호의 세그먼트에는 종방향 볼트박스(13)과 횡방향 볼트박스(12)가 형성되어있다. 횡방향 볼트박스(12)만으로 횡방향으로 연결이음하고 종방향 볼트박스(13)를 생략하고 본 발명의 종방향 강연선 관통로를 종방향으로 형성하는 방식이다. 먼저 횡방향 볼트박스(12)을 볼트 고정한 다음 종방향 강연선 관통로에 강연선을 위에서와 같은 방식으로 긴장ㆍ정착하면 된다.As shown in FIG. 11, the vertical bolt box 13 and the horizontal bolt box 12 are formed in the segment of JP-A-10-2004-0026598. Only the transverse bolt box 12 is connected in the transverse direction and the longitudinal bolt box 13 is omitted and the longitudinal strand line passage of the present invention is formed in the longitudinal direction. First, the lateral bolt box 12 is bolted, and then the stranded wire is tensioned and fixed to the longitudinal stranded wire passage in the same manner as above.

도12는 횡방향 볼트박스(12)을 서로 접면시키고 고정볼트(7)와 너트(8)로서 고정하고 있는 상태를 보인 것이다.FIG. 12 shows a state in which the lateral bolt boxes 12 are in contact with each other and fixed as the fixing bolts 7 and the nuts 8.

이제 본 발명의 방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체를 이용한 실드터널의 구축공법을 설명하면 다음과 같다. Now, a method for constructing a shield tunnel using a segment structure having a direction strand and a transverse shear key according to the present invention will be described.

(a) 굴진터널공간부내에 7개의 세그먼트가 청구항 1의 형상과 구조가 동일한 세그먼트를 배치시키되 A1과 A4를 하단부에 접면시킨 상태에서 A1→A2→B를, 그리고 A4→A3→C를 각각 순서대로 원형상태가 되도록 배열ㆍ위치시키고, B와 C사이에 K 세그먼트를 삽입ㆍ고정하여 제1열을 형성하는 단계;(a) In the drilling tunnel space, seven segments are arranged in the same shape and structure as in claim 1, and A1 → A2 → B and A4 → A3 → C, respectively, with A1 and A4 in contact with the lower end. Arranging and positioning them in a circular state, and inserting and fixing a K segment between B and C to form a first row;

(b) 제1열에 인접되게 제2열의 각 세그먼트를 제1열과 같이 원형상태가 되도록 배열ㆍ위치시키되 제1열의 A1의 센터라인에 제2열의 A1의 끝단이 오도록 하여 A1의 절반만큼 제1열과 제2열이 서로 엇갈리게 배열한 다음, 제1열과 제2열의 횡방향 볼트박스(13)에 고정볼트를 삽입하여 각 세그먼트를 고정하는 단계;(b) Arrange and position each segment of the second column adjacent to the first column so as to have a circular state as in the first column, with the end of A1 of the second row in the center line of A1 of the first row so that the end of A1 of the second row is equal to half of the first row. Arranging the second rows staggered with each other, and then fixing the segments by inserting fixing bolts into the transverse bolt boxes 13 of the first row and the second row;

(c) 제2열에 인접되게 제3열의 각 세그먼트를 제1열과 똑같은 높이를 갖도록 하면서 원형상태로 배열ㆍ위치시키되 제2열과 제3열은 A1의 절반만큼 서로 엇갈린 상태가 되게 한 다음, 제2열과 제3열의 횡방향 볼트박스(13)에 고정볼트를 삽입하여 각 세그먼트를 고정하는 단계; (c) Arrange and position each segment of the third row adjacent to the second row with the same height as the first row, with the second row and the third row staggered by one half of A1, and then Fixing each segment by inserting fixing bolts into the horizontal bolt boxes 13 of rows and columns;

(d) 제1열의 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 삽입ㆍ고정공간부 E2에 강연선을 삽입하고, 제2열의 (F3-G1)→제3열의 (E2-F2)→제4열의 (F3-G1)을 통과한 다음, 제4열에 위치한 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 정착부G1에 강연선을 긴장ㆍ정착하여 제4열에 위치한 각 세그먼트를 고정시킨 후, 제2열의 각 세그먼트의 강연선 삽입ㆍ고정공간부 E2에 강연선을 삽입하고, 제3열의 (F3-G1)→제4열의 (E2-F2)→제5열의 (F3-G1)을 통과한 다음, 제5열에 위치한 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 정착부G1에 강연선을 긴장ㆍ정착하여 제5열에 위치한 각 세그먼트를 고정시키는 한편, 상기와 동일한 방법으로 제3열과 제4열의 순으로 각 세그먼트의 강연선 삽입ㆍ고정공간부 E1에 강연선을 삽입하여 제6열과 제7열의 순으로 제6열과 제7열에 위치한 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 정착부 G2에 강연선을 긴장ㆍ정착하여 제6열과 제7열에 위치한 각 세그먼트를 고정하는 단계; (d) Insert the strand into the strand insertion / fixing space portion E2 of each segment (A1, A2, B, K, C, A3, A4) of the first row, and then (F3-G1) → E2-F2) → After passing through (F3-G1) in the fourth row, tension and anchor the strand to the strand anchorage part G1 of each segment (A1, A2, B, K, C, A3, A4) located in the fourth row. To fix each segment located in the fourth column, and insert the strand into the strand-inserting / fixing space portion E2 of each segment in the second column, and (F3-G1) in the third column → (E2-F2) in the fourth column. After passing through (F3-G1) in the fifth row, the strands are tensioned and fixed to the strand anchorage part G1 of each segment (A1, A2, B, K, C, A3, A4) located in the fifth row, While the segments are fixed, the strands are inserted into the strands and fixed space portions E1 of each segment in the order of the third row and the fourth row in the same manner as described above, and the sixth and seventh rows are placed in the sixth and seventh rows, respectively. Segman The step of fixing the respective segments in the sixth column and the seventh column in tension and fixing the strand in the strand fixing portion G2 of (A1, A2, B, K, C, A3, A4);

(e) 제2열의 강연선 삽입ㆍ긴장에 의하여 제5열의 각 세그먼트 고정하고, 제3열의 강연선 삽입ㆍ긴장에 의하여 제6열의 각 세그먼트 고정하고, 제4열의 강연선 삽입ㆍ긴장에 의하여 제7열의 각 세그먼트의 고정이 이루어진 상태에서 다시 제5열의 강연선 삽입ㆍ긴장에 의하여 제1열과 똑같은 방식으로 제8열에 위치한 각 세그먼트를 고정하는 단계; (e) Each segment of the fifth row is fixed by the insertion and tension of the strand in the second row, and each segment of the sixth row is fixed by the insertion and tension of the third row. Fixing each segment located in the eighth row in the same manner as the first row by inserting and stretching the fifth strand of the strand in the state where the segments are fixed;

(f) 제9열에 위치한 각 세그먼트 고정은 제6열의 강연선 삽입ㆍ긴장에 의하여, 제10열에 위치한 각 세그먼트 고정은 제7열의 강연선 삽입ㆍ긴장에 의하여,ㆍㆍㆍㆍ제n열에 위치한 각 세그먼트 고정은 제n-3열의 강연선 삽입ㆍ긴장에 의하여, 순차적으로 실드터널의 조립이 이루어지는 단계;를 포함함을 특징으로 하는 방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체를 이용한 실드터널의 구축공법이다.(f) Each segment fixing in column 9 is by inserting / tensioning in the sixth row, and each segment fixing in column 10 is fixed by inserting / tensioning in the seventh row. Is a step of assembling the shield tunnel sequentially by inserting and tensioning the strand wire of the n-th column. The shield tunnel construction method using the segment structure having the directional strand and the transverse shear key is included.

여기에다 강연선 정착부 G1, G2에 형성된 원추형 홀에 강연선의 선단 숫콘이 정착되고, 강연선의 후단 고정부는 강연선 삽입ㆍ고정공간부 E1, E2에 고정됨을 특징으로 하는 방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체를 이용한 실드터널의 구축공법이다.In addition, a segment male having a directional strand and a transverse shear key, characterized in that a male tip of the strand is fixed in a conical hole formed in the strand anchoring portions G1 and G2, and the rear fixed portion of the strand is fixed to the strand insertion / fixing space portions E1 and E2. Shield tunnel construction method using

Claims (5)

횡단면 접합부에 대하여 직각으로 2개의 센터관통로(10)와 2개의 단부관통로(20)가 형성되어있되 2개의 센터관통로(10)에는 강연선 통행구(F3, F4)와 강연선 정착부(G1, G2)가 형성되어있으면서 강연선 정착부(G1, G2)가 터널 굴진 방향 쪽에 위치되어있고, 또 2개의 단부관통로(20)에는 강연선 삽입ㆍ고정공간부(E1, E2)와 강연선 통행구(F1, F2)가 형성되어있으면서 강연선 삽입ㆍ고정공간부(E1, E2)와 강연선 정착부(G1, G2)는 서로 반대방향에 위치되어있는 한편, P, Q직선에 대하여 Qa=Pa, Qb=Pb, Qc=Pc=2Qa=2Pa의 관계를 갖는 전단키가 형성된 기본 세트먼트 A(A1=A2=A3=A4)가 형성되어있고, A1과 A4를 하단부에 접면시킨 상태에서 A1위에 A2→B와, 그리고 A4위에 A3→C를 순서대로 배열하고, B와 C사이에 K 세그먼트를 삽입하되 B, C, K 세그먼트는 기본 세트먼트 A와 동일하되 B 세그먼트는 Q 직선의 하부 Qa에서, 그리고 C 세그먼트는 Q 직선의 상부 Qa에서 Qa보다 Qd 만큼 더 길게 형성되어있고, 이에 대응된 K 세그먼트는 Q 직선의 상ㆍ하부 Qa에서 Qa보다 Qd 만큼 짧게 형성되어있음을 특징으로 하는 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체 Two center passages (10) and two end passages (20) are formed at right angles to the cross-section junction, and the two center passages (10) are provided with the strand line passages (F3, F4) and the strand anchorage portion (G1). , G2) is formed, and the strand wire anchoring portions G1 and G2 are located in the direction of the tunnel excavation, and the two end passage passages 20 include the strand wire insertion / fixing space portions E1 and E2 and the strand wire passageway. While the F1 and F2 are formed, the strand insertion and fixing space portions E1 and E2 and the strand anchor fixing portions G1 and G2 are located in opposite directions, while Qa = Pa and Qb = with respect to the P and Q straight lines. A basic piece A (A1 = A2 = A3 = A4) having a shear key having a relationship of Pb, Qc = Pc = 2Qa = 2Pa is formed, and A1 → A4 is contacted on the lower end with A2 → B and Arrange A3 → C on A4 in order, and insert K segment between B and C, but B, C, and K segments are the same as basic set A, but B segment In the lower Qa of the Q straight line, and the C segment is formed by Qd longer than Qa in the upper Qa of the Q straight line, and the corresponding K segment is formed by Qd shorter than Qa in the upper and lower Qa of the Q straight line. Segment structure having a longitudinal strand and a transverse shear key 청구항 제1항에 있어서The method of claim 1 강연선 정착부 G1, G2에는 강연선의 선단 숫콘에 대응되는 원추형 홀이 형성되어있고, 강연선 삽입ㆍ고정공간부 E1, E2에는 강연선의 후단 고정부에 대응되는 공간부가 형성되어있음을 특징으로 하는 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체 Longitudinal direction characterized by a conical hole corresponding to the male cone of the stranded wire in the strand anchoring parts G1 and G2, and a space corresponding to the rear fixed part of the stranded wire in the strand insertion and fixing space parts E1 and E2. Segment Structure with Strands and Transverse Shear Keys 청구항 제1항 또는 제2항에 있어서The method according to claim 1 or 2 각 세그먼트 4면 접합부에 유로홈과 수팽창 지수제가 형성되어있음을 특징으로 하는 종방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체A segment structure having a longitudinal strand and a transverse shear key characterized in that a flow path groove and a water-expansion index agent are formed at each segment four-sided junction. (a) 굴진터널공간부내에 7개의 세그먼트가 청구항 1의 형상과 구조가 동일한 세그먼트를 배치시키되 A1과 A4를 하단부에 접면시킨 상태에서 A1→A2→B를, 그리고 A4→A3→C를 각각 순서대로 원형상태가 되도록 배열ㆍ위치시키고, B와 C사이에 K 세그먼트를 삽입ㆍ고정하여 제1열을 형성하는 단계;(a) In the drilling tunnel space, seven segments are arranged in the same shape and structure as in claim 1, and A1 → A2 → B and A4 → A3 → C, respectively, with A1 and A4 in contact with the lower end. Arranging and positioning them in a circular state, and inserting and fixing a K segment between B and C to form a first row; (b) 제1열에 인접되게 제2열의 각 세그먼트를 제1열과 같이 원형상태가 되도록 배열ㆍ위치시키되 제1열의 A1의 센터라인에 제2열의 A1의 끝단이 오도록 하여 A1의 절반만큼 제1열과 제2열이 서로 엇갈리게 배열한 다음, 제1열과 제2열의 횡방향 볼트박스(13)에 고정볼트를 삽입하여 각 세그먼트를 고정하는 단계; (b) Arrange and position each segment of the second column adjacent to the first column so as to have a circular state as in the first column, with the end of A1 of the second row in the center line of A1 of the first row so that the end of A1 of the second row is equal to half of the first row. Arranging the second rows staggered with each other, and then fixing the segments by inserting fixing bolts into the transverse bolt boxes 13 of the first row and the second row; (c) 제2열에 인접되게 제3열의 각 세그먼트를 제1열과 똑같은 높이를 갖도록 하면서 원형상태로 배열ㆍ위치시키되 제2열과 제3열은 A1의 절반만큼 서로 엇갈린 상태가 되게 한 다음, 제2열과 제3열의 횡방향 볼트박스(13)에 고정볼트를 삽입하여 각 세그먼트를 고정하는 단계; (c) Arrange and position each segment of the third row adjacent to the second row with the same height as the first row, with the second row and the third row staggered by one half of A1, and then Fixing each segment by inserting fixing bolts into the horizontal bolt boxes 13 of the row and the third row; (d) 제1열의 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 삽입ㆍ고정공간부 E2에 강연선을 삽입하고, 제2열의 (F3-G1)→제3열의 (E2-F2)→제4열의 (F3-G1)을 통과한 다음, 제4열에 위치한 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 정착부G1에 강연선을 긴장ㆍ정착하여 제4열에 위치한 각 세그먼트를 고정시킨 후, 제2열의 각 세그먼트의 강연선 삽입ㆍ고정공간부 E2에 강연선을 삽입하고, 제3열의 (F3-G1)→제4열의 (E2-F2)→제5열의 (F3-G1)을 통과한 다음, 제5열에 위치한 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 정착부G1에 강연선을 긴장ㆍ정착하여 제5열에 위치한 각 세그먼트를 고정시키는 한편, 상기와 동일한 방법으로 제3열과 제4열의 순으로 각 세그먼트의 강연선 삽입ㆍ고정공간부 E1에 강연선을 삽입하여 제6열과 제7열의 순으로 제6열과 제7열에 위치한 각 세그먼트(A1, A2, B, K, C, A3, A4)의 강연선 정착부 G2에 강연선을 긴장ㆍ정착하여 제6열과 제7열에 위치한 각 세그먼트를 고정하는 단계; (d) Insert the strand into the strand insertion / fixing space portion E2 of each segment (A1, A2, B, K, C, A3, A4) of the first row, and then (F3-G1) → E2-F2) → After passing through (F3-G1) in the fourth row, tension and anchor the strand to the strand anchorage part G1 of each segment (A1, A2, B, K, C, A3, A4) located in the fourth row. To fix each segment located in the fourth column, and insert the strand into the strand-inserting / fixing space portion E2 of each segment in the second column, and (F3-G1) in the third column → (E2-F2) in the fourth column. After passing through (F3-G1) in the fifth row, the strands are tensioned and fixed to the strand anchorage part G1 of each segment (A1, A2, B, K, C, A3, A4) located in the fifth row, While the segments are fixed, the strands are inserted into the strands and fixed space portions E1 of each segment in the order of the third row and the fourth row in the same manner as described above, and the sixth and seventh rows are placed in the sixth and seventh rows, respectively. Segman The step of fixing the respective segments in the sixth column and the seventh column in tension and fixing the strand in the strand fixing portion G2 of (A1, A2, B, K, C, A3, A4); (e) 제2열의 강연선 삽입ㆍ긴장에 의하여 제5열의 각 세그먼트 고정하고, 제3열의 강연선 삽입ㆍ긴장에 의하여 제6열의 각 세그먼트 고정하고, 제4열의 강연선 삽입ㆍ긴장에 의하여 제7열의 각 세그먼트의 고정이 이루어진 상태에서 다시 제5열의 강연선 삽입ㆍ긴장에 의하여 제1열과 똑같은 방식으로 제8열에 위치한 각 세그먼트를 고정하는 단계; (e) Each segment of the fifth row is fixed by the insertion and tension of the strand in the second row, and each segment of the sixth row is fixed by the insertion and tension of the third row. Fixing each segment located in the eighth row in the same manner as the first row by inserting and stretching the fifth strand of the strand in the state where the segments are fixed; (f) 제9열에 위치한 각 세그먼트 고정은 제6열의 강연선 삽입ㆍ긴장에 의하여, 제10열에 위치한 각 세그먼트 고정은 제7열의 강연선 삽입ㆍ긴장에 의하여,ㆍㆍㆍㆍ제n열에 위치한 각 세그먼트 고정은 제n-3열의 강연선 삽입ㆍ긴장에 의하여, 순차적으로 실드터널의 조립이 이루어지는 단계;를 포함함을 특징으로 하는 방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체를 이용한 실드터널의 구축공법(f) Each segment fixing in column 9 is by inserting / tensioning in the sixth row, and each segment fixing in column 10 is fixed by inserting / tensioning in the seventh row. Is a step of assembling the shield tunnel sequentially by inserting and tensioning the strand wire of column n-3; and a method of constructing a shield tunnel using a segment structure having a direction strand and a transverse shear key 청구항 제4항에 있어서The method according to claim 4 강연선 정착부 G1, G2에 형성된 원추형 홀에 강연선의 선단 숫콘이 정착되고, 강연선의 후단 고정부는 강연선 삽입ㆍ고정공간부 E1, E2에 고정됨을 특징으로 하는 방향 강연선과 횡방향 전단키를 갖는 세그먼트 구조체를 이용한 실드터널의 구축공법A segment structure having a directional strand and a transverse shear key is characterized in that a male tip of the strand is fixed in a conical hole formed in the strand anchoring portions G1 and G2, and the rear fixed portion of the strand is fixed to the strand insertion / fixing space portions E1 and E2. Construction method of shield tunnel using
PCT/KR2012/007280 2011-09-15 2012-09-11 Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same Ceased WO2013039315A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201280044802.1A CN103797216B (en) 2011-09-15 2012-09-11 Segment structure with longitudinal strands and transverse shear keys and method of using same for constructing shield tunnel

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2011-0092822 2011-09-15
KR1020110092822A KR101470056B1 (en) 2011-09-15 2011-09-15 Segment body with the prestressed strand cables of a longitudinal direction and the shear keys of a horizontal direction

Publications (2)

Publication Number Publication Date
WO2013039315A2 true WO2013039315A2 (en) 2013-03-21
WO2013039315A3 WO2013039315A3 (en) 2013-05-10

Family

ID=47883875

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2012/007280 Ceased WO2013039315A2 (en) 2011-09-15 2012-09-11 Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same

Country Status (3)

Country Link
KR (1) KR101470056B1 (en)
CN (1) CN103797216B (en)
WO (1) WO2013039315A2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107023306A (en) * 2017-06-09 2017-08-08 中南大学 A kind of screw type assembled tunnel structure and its construction method
CN108915723A (en) * 2018-07-27 2018-11-30 中铁第四勘察设计院集团有限公司 A kind of shield tunnel chip architecture for passing through vertical fault active fault
CN117145522A (en) * 2023-10-27 2023-12-01 北京建工土木工程有限公司 Underwater bottom sealing method for mechanical vertical excavation of tunnel pump house

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160075901A (en) 2014-12-19 2016-06-30 한국건설기술연구원 Segment structure having shear key of island type and longitudinal strand for shield tunnel
CN105257321B (en) * 2015-09-28 2018-05-04 上海市基础工程集团有限公司 Shield tunnel construction at initial stage section of jurisdiction sockets device and construction method
CN105401957B (en) * 2015-10-23 2017-07-28 济南轨道交通集团有限公司 A kind of duct pieces of shield tunnel two dimension prestressing bracing means and construction method
CN120798371B (en) * 2025-09-12 2025-11-14 中铁第六勘察设计院集团有限公司 Bidirectional cooperative reinforcement structure for shield tunnel segments and construction method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07252996A (en) * 1994-03-11 1995-10-03 Nippon Steel Corp Steel segment
JP4707308B2 (en) * 2002-07-26 2011-06-22 東京地下鉄株式会社 Precast member wall structure and its joint
JP2007270473A (en) * 2006-03-31 2007-10-18 Ishikawajima Constr Materials Co Ltd Joint structure of composite segment and composite segment
KR100936471B1 (en) * 2007-03-09 2010-01-13 한국건설기술연구원 Circular support structure by segment with drainage structure and method of constructing shield tunnel using the same
CN201301715Y (en) * 2008-11-20 2009-09-02 中铁十六局集团有限公司 Shear pin of molding segment
CN201705365U (en) * 2010-04-07 2011-01-12 中国石油天然气集团公司 Duct piece structure of shield tunnel through mouth
CN201650307U (en) * 2010-04-16 2010-11-24 北京工业大学 Connection structure of longitudinal split joints between fabricated plastic pipe segments in soil

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107023306A (en) * 2017-06-09 2017-08-08 中南大学 A kind of screw type assembled tunnel structure and its construction method
CN108915723A (en) * 2018-07-27 2018-11-30 中铁第四勘察设计院集团有限公司 A kind of shield tunnel chip architecture for passing through vertical fault active fault
CN108915723B (en) * 2018-07-27 2023-06-27 中铁第四勘察设计院集团有限公司 Shield tunnel segment structure crossing vertical dislocation movable fault
CN117145522A (en) * 2023-10-27 2023-12-01 北京建工土木工程有限公司 Underwater bottom sealing method for mechanical vertical excavation of tunnel pump house
CN117145522B (en) * 2023-10-27 2024-01-26 北京建工土木工程有限公司 Underwater bottom sealing method for mechanical vertical excavation of tunnel pump house

Also Published As

Publication number Publication date
WO2013039315A3 (en) 2013-05-10
KR20130029524A (en) 2013-03-25
CN103797216B (en) 2016-06-29
KR101470056B1 (en) 2014-12-05
CN103797216A (en) 2014-05-14

Similar Documents

Publication Publication Date Title
WO2013039315A2 (en) Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same
WO2017090975A1 (en) Tunnel construction method using pre-support and post-support and apparatus suitable for same
WO2017047984A1 (en) Steel tube girder having adjustable length, dual installation system for steel tunnel support using rigidity-reinforced cft steel tube girders filled therein, dual construction method for steel tunnel support using system, and steel tube girder structure for dual installation
WO2018221933A1 (en) Casing guide apparatus for ground excavator, and excavation method using same
WO2021182795A1 (en) Construction method for underwater concrete block structure
WO2016093432A1 (en) Facing member for reinforced-soil retaining-wall, reinforced-soil retaining-wall structure using facing member, and construction method for band type fiber reinforcing material for reinforced-soil retaining-wall
WO2018070634A1 (en) Pc wall panel for reinforcing earthquake resistance of reinforced concrete frame, structure for reinforcing earthquake resistance of reinforced concrete frame by using pc wall panel, and method for constructing same
WO2009102119A1 (en) Bridge-raising device incorporating a raising guide, and a bridge-raising work method using the said bridge-raising device
KR20130124262A (en) Method constructing the shield tunnel using segments with the prestressed strand cables of a longitudinal direction and the shear keys of a horizontal direction
WO2014069971A1 (en) Pretension masonry wall reinforcement apparatus using steel wires, and masonry wall reinforcement method using same
EP1021640B1 (en) Arched support structure
WO2017057804A1 (en) Driven concrete pile having open bottom and construction method thereof
WO2011059145A1 (en) Structure using steel pile
WO2019076055A1 (en) Interjack station-based box culvert jacking system having jacking frame assembly
WO2017043709A1 (en) Driven concrete pile and construction method thereof
WO2013005944A2 (en) Protective structure for the mouth of an unfinished tunnel
WO2016021854A1 (en) Method for constructing underground structure using movable temporary support
WO2019017598A1 (en) Arch assembly having outriggers, arch structure using same and construction method therefor
WO2009142397A2 (en) A block for building a revetment and a construction method thereof
WO2021225261A1 (en) Variable assembly pc member
WO2024085509A1 (en) Seismic reinforcement pc reinforcement block assembly and method for constructing same
WO2018190444A1 (en) Prefabricated double composite plate girder bridge and construction method therefor
WO2015009125A1 (en) Structure for coupling earth retaining wall with wales
WO2019076056A1 (en) Box culvert relay jacking system having movable mechanism
WO2011108858A2 (en) Reinforced lattice girder

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 12832143

Country of ref document: EP

Kind code of ref document: A2

NENP Non-entry into the national phase

Ref country code: DE

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A, DATED 21-08-2014)

122 Ep: pct application non-entry in european phase

Ref document number: 12832143

Country of ref document: EP

Kind code of ref document: A2