WO2011111474A1 - Continuous steel wall and method for constructing same - Google Patents
Continuous steel wall and method for constructing same Download PDFInfo
- Publication number
- WO2011111474A1 WO2011111474A1 PCT/JP2011/053020 JP2011053020W WO2011111474A1 WO 2011111474 A1 WO2011111474 A1 WO 2011111474A1 JP 2011053020 W JP2011053020 W JP 2011053020W WO 2011111474 A1 WO2011111474 A1 WO 2011111474A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- steel sheet
- sheet pile
- stiffener
- steel
- guide member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/06—Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
Definitions
- the present invention relates to a steel wall with steel sheet piles used for retaining walls, such as earth retaining walls, underground structure walls, river and harbor revetments and quay walls, road works, etc. It is related with the construction method of a continuous wall and steel continuous walls.
- steel sheet piles are generally used as steel materials for underground walls used for earth retaining walls, river revetments, road retaining walls, etc. to prevent the collapse of earth and sand.
- box-shaped steel sheet pile two U-shaped steel sheet piles are integrated into a box shape by welding
- this combined steel sheet pile has excellent cross-sectional performance, it is difficult to stack a large number of combined steel sheet piles on a vehicle at the time of transportation because it is complicated and cannot be stacked compactly and is bulky. Thus, there are problems such as high transportation costs. Therefore, from the viewpoint of emphasizing the convenience of transportation, there is also a method in which the steel sheet pile and the supplementary steel material are transported separately to the construction site and integrated on the site. However, since work such as full length welding is difficult at the construction site, it is difficult to integrate such that a large cross-sectional performance can be obtained. It may also be necessary to correct the thermal distortion of the steel sheet pile due to full length welding.
- an underground continuous wall having a structure in which a steel sheet pile web and an H-shaped steel flange are restrained only at one end on the ground side has been proposed (for example, see Patent Document 1).
- Patent Document 1 As an example of the construction method of this underground continuous wall, in order to prevent the steel sheet pile web and the H-shaped steel flange from separating in the ground during the installation process, the steel sheet pile web and the H-shaped steel flange It has been proposed to temporarily fix one end on the ground side opposite to one end on the ground side.
- a structure has been proposed in which a fitting member (angle, guide) is provided on one side of a steel sheet pile and fitted to a flange of an H-shaped steel that is a reinforcing steel material (stiffening material) (for example, Patent Documents 2 and 3). reference).
- a fitting member is provided in the steel sheet pile full length, and it builds in the state in which the steel sheet pile and the H-shaped steel were fitted.
- a fitting member is provided only on the steel sheet pile full length (may be discontinuous) or only at the upper end, and after placing the steel sheet pile first, a method of placing H-shaped steel using the fitting member as a guide. Has been proposed.
- JP 2008-267069 A Japanese Examined Patent Publication No. 2-57163 JP 2005-299202 A
- the present invention separately separates the steel sheet pile and the stiffener from the ground without welding the steel sheet pile and the stiffener full length and without providing a fitting member over the entire length of the steel sheet pile or stiffener
- An object of the present invention is to provide a steel continuous wall construction method and a steel continuous wall that can reliably bring the steel sheet pile and the stiffener into contact with each other even when the steel sheet is placed.
- the construction method of the continuous steel wall according to claim 1 is longitudinal in the longitudinal direction of the steel sheet pile on at least one surface side of a wall body formed by connecting steel sheet piles.
- a steel continuous wall construction method comprising a long stiffener in contact with the steel sheet pile along the direction, and fitted to the stiffener in contact with the steel sheet pile at the lower end of the steel sheet pile.
- the steel sheet pile is provided with a first guide member that can move along the longitudinal direction of the stiffener, and the lower end of the stiffener is adjacent to the steel sheet pile in contact with the stiffener.
- a second guide member is provided that is fitted to an existing steel sheet pile placed on the steel sheet and is capable of moving the stiffener along the longitudinal direction of the existing steel sheet pile, and the stiffener is connected to the existing steel sheet.
- the second guide member is fitted to the sheet pile, and the existing steel sheet pile is positioned and guided.
- the steel sheet pile is connected to the existing steel sheet pile, and the first guide member is fitted to the previously stiffened stiffener and guided to the stiffener. It is characterized in that it is placed on the ground.
- the construction method of the continuous wall made of steel according to claim 2 is the invention according to claim 1, wherein the steel sheet pile includes joints respectively connected to left and right steel sheet piles, and a cross section of the second guide member.
- the shape is the same as a cross-sectional shape of the steel sheet pile or a partial cross-sectional shape having at least one joint portion of the cross-sectional shape of the steel sheet pile, and corresponds to the steel sheet pile joint of the second guide member.
- the portion to be fitted is fitted to the joint of the existing steel sheet pile.
- the construction method of the steel continuous wall according to claim 3 is the invention according to claim 1 or claim 2, wherein the second guide is fitted to the existing steel sheet pile when the stiffener is placed. Before the member is detached from the lower end of the existing steel sheet pile, the placement of the stiffener is terminated.
- the construction method of the steel continuous wall according to claim 4 is the invention according to claim 1, wherein the lower end of the steel sheet pile contacts the second guide member of the stiffener when the steel sheet pile is driven. By pushing the second guide member down, the steel sheet pile is driven on the ground until the stiffener moves down.
- the steel continuous wall according to claim 5 is a length in contact with the steel sheet pile along the longitudinal direction of the steel sheet pile on at least one surface side of the wall body formed by connecting the steel sheet piles. It is a steel continuous wall provided with a scale stiffener, and is fitted to the stiffener in contact with the steel sheet pile at the lower end of the steel sheet pile when the steel sheet pile is placed, and the steel sheet pile is A first guide member is provided that is movable along the longitudinal direction of the stiffener, and is adjacent to the steel sheet pile in contact with the stiffener at the lower end of the stiffener. The position of the stiffener relative to the existing steel sheet pile by being fitted to the existing steel sheet pile previously placed and allowing the stiffener to move along the longitudinal direction of the existing steel sheet pile. A second guide member for determining the above is provided.
- the continuous steel wall according to claim 6 is the invention according to claim 5, wherein the steel sheet pile includes joints respectively connected to the left and right adjacent steel sheet piles, and the cross-sectional shape of the second guide member is the steel.
- the cross-sectional shape of the sheet pile or the cross-sectional shape of the steel sheet pile is formed to be the same as a partial cross-sectional shape having at least one joint portion.
- the stiffener is placed prior to the steel sheet pile contacting the stiffener, and the stiffener fits the second guide member to the existing steel sheet pile. In this state, it is driven at a predetermined position while being guided by the existing steel sheet pile. Subsequently, since the steel sheet pile is driven while being guided by the stiffener in a state where the first guide member is fitted to the stiffener thus placed, the lower end of the steel sheet pile during the placement. The part is always in contact with the stiffener. Therefore, if the steel sheet pile and the stiffener previously placed are in contact with each other until the placement is completed on the ground side, stiffening is performed over the entire length of the stiffener and steel sheet pile. The material and the steel sheet pile are substantially in contact.
- the steel sheet pile includes a joint for connecting the steel sheet piles, and is placed on the ground in a state where the joint is connected to the joint of the existing steel sheet pile.
- the stiffener may be selected appropriately according to the required cross-sectional performance, and can be selected from various shapes such as H-section steel, and has a joint that can be engaged with the guide member. Can be used, and the degree of freedom in design is great.
- the second guide member and the first guide member can be attached to the stiffener and the steel sheet pile, for example, by welding or bolt joining, as long as sufficient strength can be secured. Alternatively, it may be performed at a factory or the like. Therefore, a joining method can be selected according to the construction environment. For example, in a construction environment where welding is difficult, bolt joining can be selected. Even in places where there are restrictions on the sky, such as under the bridge girder, the joining method can be selected according to the situation.
- the cross-sectional shape of the second guide member is formed to be the same as the cross-sectional shape of the steel sheet pile or a partial cross-sectional shape including one joint portion of the steel sheet pile.
- the position of the stiffener can be correctly determined by driving the stiffener with the portion corresponding to the joint of the steel sheet pile of the second guide member fitted to the joint of the existing steel sheet pile. At this time, the position where the stiffener of the second guide member having the same or part of the same cross-sectional shape as the steel sheet pile is attached is the same position as the position where the stiffener of the cross-sectional shape of the steel sheet pile contacts. .
- the stiffener when the stiffener is placed, if the second guide member is detached from the existing steel sheet pile, the stiffener may be displaced from the optimum position.
- the second guide member is preferably not detached from the existing steel sheet pile even when the stiffening material is placed.
- the stiffener can be positioned with high accuracy by ending the placement of the stiffener before the second guide member moves downward from the lower end of the existing steel sheet pile.
- the second guide member is the lower end of the steel sheet pile or its length from the length of the steel sheet pile, the length of the stiffener, the attachment position of the second guide member to the stiffener, and the vertical width of the second guide member.
- the value of the difference in height between the upper end of the steel sheet pile and the upper end of the stiffener when it falls off can be determined. Therefore, the second guide member is moved downward from the steel sheet pile by finishing the placement of the stiffener before the difference in height between the upper end of the steel sheet pile and the upper end of the stiffener becomes the determined value. It can be prevented from coming off.
- the steel sheet pile when the steel sheet pile is driven in a state where the first guide member of the steel sheet pile is correctly fitted to the stiffener, the steel sheet pile is at the lower end of the stiffener at the end of the steel sheet pile driving.
- the second guide member hits the second guide member provided in the section and is pushed down.
- the stiffener moves downward.
- the upper end of the stiffener will be confirmed to sink slightly. Therefore, by placing the steel sheet pile until the upper end of the stiffener sinks slightly, the first guide member of the steel sheet pile is detached from the stiffener, or the first guide member is detached from the steel sheet pile, It can be confirmed whether the lower end side of the steel sheet pile is not separated from the stiffener.
- the present invention without welding a steel sheet pile and a stiffener by full length welding or the like, and without providing a fitting member for fitting the steel sheet pile and the stiffener over substantially the entire length, Even if the sheet pile and the stiffener are separately placed on the ground, the cross-sectional performance can be reliably improved with the steel sheet pile and the stiffener substantially in contact with each other.
- (A), (b), (c) is a schematic plan view which shows the modification of the 1st guide member in the said steel continuous wall, respectively.
- (A), (b) is a schematic plan view which shows the modification of the stiffener in the said steel continuous wall, respectively.
- (A), (b), (c) is a schematic plan view which shows the modification of the steel sheet pile in the said steel continuous wall, respectively.
- (A) is a schematic plan view of the said steel continuous wall shown in FIG. 1, (b) is a schematic plan view which shows the modification of the said steel continuous wall.
- the steel continuous wall 1 shown in FIG. 1 has a structure in which the steel sheet pile 2 and the H-shaped steel 3 are brought into contact with each other without integrally joining the hat-shaped steel sheet pile 2 and the H-shaped steel 3 as the stiffener. It is.
- the hat-shaped steel sheet pile 2 includes a web 21, a flange 22 that is provided obliquely from the left and right ends of the web 21 so that the distal ends of the web 21 spread from each other, and the web 21 from the front end of each flange 22.
- An arm 23 extending in parallel and a joint (not shown) provided at the tip of the arm 23 are provided.
- the joint is, for example, a well-known joint, and has a shape that is curved and folded back to the inner peripheral side with an interval. In addition, the direction of folding back by the left and right joints is reversed, and the joints in opposite directions are fitted to each other.
- the steel sheet pile 2 includes a first guide member 24 at its lower end. The first guide member 24 is fitted into a flange 32 (to be described later) of the H-section steel 3 as a stiffener.
- the first guide member 24 is combined with the first guide member 24 and the web 21 so as to form a substantially plate-like space in which the flange 32 of the H-section steel 3 can be inserted between the web 21 of the steel sheet pile 2.
- the first guide member 24 is provided with a slit through which the web 31 of the H-section steel 3 can be inserted.
- the first guide member 24 is composed of a pair of right and left angle members (L-shaped steel) 24a having an L-shaped cross section.
- the first guide member 24 is provided at the lower end of the side surface on the valley side of the web 21 of the steel sheet pile 2.
- one flat plate portion of the two flat plate portions constituting each angle member 24a is arranged at right angles to the web 21 and joined (welded) to the web 21, and the other
- the flat plate portion is arranged in parallel with the web 21 and the other flat plate portions are arranged so as to face each other with a gap therebetween.
- the flange 32 of the H-section steel 3 is disposed so as to substantially contact the web 21, and the angle member The web 31 of the H-section steel 3 is arranged between the other flat plate portions of 24a.
- the vertical width of the first guide member 24 is considerably shorter than the vertical length of the steel sheet pile 2.
- the first guide member 24 is fitted to one flange 32 of the H-section steel 3 so as to be movable up and down, and the first guide member 24 of the H-section steel 3 on which the first guide member 24 has already been placed.
- the pair of angle members 24a constituting the first guide member 24 can be attached, for example, by welding.
- a portion that becomes a flange is provided on the angle member 24a to become a flange. May be fastened and fixed to the web 21 with bolts.
- the H-section steel 3 serving as a stiffener includes a web 31 and flanges 32 provided at both ends of the web 31 so as to be orthogonal to the web 31.
- the H-shaped steel 3 is configured to substantially come into surface contact with the web 21 of the steel sheet pile 2 with one flange 32 engaged with the guide member 24 of the steel sheet pile 2.
- a second guide member 33 that is adjacent to the steel sheet pile 2 in contact with the H-section steel 3 and that fits into the existing steel sheet pile 2 a that is the steel sheet pile 2 that has been previously placed is provided at the lower end of the H-section steel 3. ing.
- the second guide member 33 is made by processing the same steel sheet pile 2 as the steel sheet pile 2 and cuts the steel sheet pile 2 short and cuts at the boundary between the web 21 and the flange 22 on one side. . That is, the second guide member 33 includes the web 21 in the cross-sectional shape of the steel sheet pile 2, one flange 22, an arm 23 provided at the tip of the flange 22, and a joint provided at the tip of the arm 23. However, the other flange 22, the other arm 23 and the other joint are not provided.
- the vertical width of the second guide member 33 is considerably shorter than the length of the H-section steel 3.
- the second guide member 33 and the flange 32 of the H-shaped steel 3 are fixed by a known means such as welding or bolting.
- FIG. 1 The steel continuous wall 1 constructed by the construction method will be described.
- one steel sheet pile 2 is placed.
- the steel sheet pile 2 which is adjacent to the steel sheet pile 2 before or during placement and has already been cast on the ground.
- the cast steel sheet pile 2 is referred to as an existing steel sheet pile for the sake of convenience, and its reference numeral is 2a.
- Shape steel 3 is cast.
- the steel sheet pile 2 and the H-shaped steel 3 can be placed by using various well-known methods such as hitting, press-fitting, and press-fitting vibration.
- the joint of the steel sheet pile 2a is stopped by stopping the placing of the H-section steel 3 in a state where the height of the upper end of the H-section steel 3 is slightly higher than the height of the upper end of the steel sheet pile 2a. Therefore, the placement of the H-section steel 3 can be finished before the joint of the second guide member 33 is released downward.
- the second guide member 33 of the H-section steel 3 is fitted to the existing steel sheet pile 2a, and the state in which the H-section steel 3 is positioned.
- the H-section steel 3 and the existing steel sheet pile 2a are maintained in a parallel state.
- a steel sheet pile 2 is placed. That is, the first guide member 24 at the lower end of the steel sheet pile 2 is in a state in which one flange 32 of the H-section steel 3 previously placed as described above is fitted, and the existing steel sheet pile 2 a The steel sheet pile 2 is driven in a state where the joint of the steel sheet pile 2 is fitted to one joint. As a result, the steel sheet pile 2 is placed on the ground while being guided by the H-shaped steel 3 and the existing steel sheet pile 2a that have been previously placed. Note that some deviation between the existing steel sheet pile 2 a and the H-section steel 3 is absorbed by the play of the first guide member 24.
- the steel sheet pile 2 If the H-section steel 3 and the steel sheet pile 2 are in contact with each other on the ground side during the placement of the steel sheet pile 2, the lower end portion of the steel sheet pile 2 contacts the H-section steel 3 by the first guide member 24. Since the steel sheet pile 2 and the H-section steel 3 are in contact with each other, the steel sheet pile 2 is driven.
- the second guide member 33 of the H-section steel 3 is fitted in the lower end portion of the existing steel sheet pile 2a.
- the position of the upper end is slightly higher than the lower end of the existing steel sheet pile 2a. Therefore, when the steel sheet pile 2 is driven until the upper end of the steel sheet pile 2 becomes the same height as the upper end of the existing steel sheet pile 2a, the lower end of the steel sheet pile 2 hits the second guide member 33, and the second guide member 33 is slightly lowered. Will be pressed.
- the H-section steel 3 to which the second guide member 33 is fixed also moves slightly downward. At this time, it is confirmed that the upper end portion of the H-section steel 3 slightly sinks on the ground side. If it does so, it can be estimated that the steel sheet pile 2 was driven in the state which the 1st guide member 24 of the lower end part of the steel sheet pile 2 was fitted to the H-section steel to the last. If the lower end of the steel sheet pile 2 is separated from the H-shaped steel 3 due to damage to the guide member 33 or detachment from the steel sheet pile 2 in the middle of the placement, the lower end of the steel sheet pile 2 becomes the second guide member.
- the 2nd guide member 33 will just remove
- the second guide member is A problem does not occur even if it is detached from the existing steel sheet pile 2a.
- the steel sheet pile 2 placed in this way becomes the existing steel sheet pile 2a, and the next H-section steel 3 and the steel sheet pile 2 are placed on the existing steel sheet pile 2a as described above, and this is repeated.
- the steel continuous wall 1 is constructed as a laminated beam type sheet pile wall in which the steel sheet piles 2 in contact with the H-section steel 3 are connected, and the steel continuous wall 1 is provided to the set length. The construction of the continuous wall 1 is completed.
- the steel continuous wall 1 constructed in this way is in a state in which the H-section steel 3 is in contact with the side surface that becomes the valley side of the steel sheet piles 2 that are connected, for example, as shown in FIG. Has been placed.
- the one flange 32 of the H-section steel 3 is substantially in contact with one surface of the web 21 of the steel sheet pile 2, and the first guide member 24 at the lower end of the steel sheet pile 2 is in the state of the flange 32 of the H-section steel 3. Although fitted to the lower end, the steel sheet pile 2 and the H-shaped steel 3 are not joined or fitted in other portions.
- the H-section steel 3 that contacts the steel sheet pile 2 is driven prior to the steel sheet pile 2
- the H-section steel 3 is made of the steel sheet pile 2 by the second guide member 33 with respect to the existing steel sheet pile 2 a. In a state where it is arranged at a correct position corresponding to the placement position, it is placed in parallel with the existing steel sheet pile 2.
- the steel sheet pile 2 is fitted to the joint of the existing steel sheet pile 2a and the first guide member 24 is fitted to the H-shaped steel 3 so that the steel sheet pile 2 is guided by these. Can be placed.
- the steel sheet pile 2 can be driven in the correct position.
- the steel sheet pile 2 and the H-shaped steel 3 are placed in contact with each other, the steel sheet pile 2 and the H-shaped steel 3 function as a laminated beam, and the steel continuous wall 1 with improved cross-sectional performance is provided. Can be obtained.
- the steel sheet pile 2 and the H-shaped steel 3 are driven separately, the resistance from the ground is smaller than that when the steel sheet pile 2 and the H-shaped steel 3 are integrated, and the driving force is small. Since the steel sheet pile 2 and the H-shaped steel 3 can be driven, it is possible to drive with a driving machine having a small output, and the equipment cost at the time of construction can be reduced.
- the steel sheet pile 2 and the H-shaped steel 3 when transporting the steel sheet pile 2 and the H-shaped steel 3, they can be transported separately, loading them so that they are not bulky, and efficiently transporting them, thereby reducing transportation costs. can do.
- the attachment of the first guide member 24 to the steel sheet pile 2 and the attachment of the second guide member 33 to the H-section steel 3 are such that the first guide member 24 and the second guide member 33 are short. Compared with the full length welding between No. 2 and the H-section steel 3, etc., it is extremely easy and can be performed in the field or in the factory. If it is performed at the factory, the steel sheet pile 2 and the H-section steel 3 may become somewhat bulky. However, the transportation efficiency can be improved as compared with the case where the steel sheet pile and the H-section steel are integrated. it can.
- the above-mentioned embodiment demonstrated the case where the H-section steel 3 as a stiffener was arrange
- the H-section steel 3 may be arranged on the surfaces on both sides.
- the angle member (L-shaped steel) 24a is used as the first guide member 24.
- a T-shaped steel (CT steel) 24b may be used.
- a lip groove steel (C-shaped steel) 24c may be used.
- a pair of T-shaped steel 24b is used similarly to the angle member 24a, and in the case of the lip groove shaped steel 24c, one guide member 24 can be configured.
- the 1st guide member 24 was provided in the side surface used as the trough side of the steel sheet pile 2, as shown in FIG.2 (c)
- the 1st guide member 24 may be provided in the side of the mountain side of the steel sheet pile 2, and the H-section steel 3 as a stiffener may be arrange
- the steel continuous wall 1 it is possible to select various types of stiffeners and types of steel sheet piles according to the required cross-sectional performance and other conditions, and the design freedom is wide. It has become. Therefore, in the steel continuous wall 1, another type of stiffener or steel sheet pile can be used instead of the H-section steel 3 (stiffener) or steel sheet pile 2 of the above-described embodiment.
- a steel pipe sheet pile 4 can be used as a stiffener.
- the steel pipe sheet pile 4 includes a steel pipe 42 and a T-shaped joint 41 having a T-shaped cross section into which the first guide member 24 of the steel sheet pile 2 is fitted. Since the T-shaped joint 41 has the same cross-sectional shape as the T-shaped cross-section when the H-section steel 3 is cut at the portion of the web 31, the first guide of the above example fitted to the flange 32 of the H-shape steel 3.
- the first guide member having the same shape as the member 24 or the first guide member 24 can be fitted.
- this steel pipe sheet pile 4 is only a general T-shaped joint 41 as one of the pair of joints. Is provided. Moreover, the 2nd guide member 33 will be attached to the part of the T-shaped coupling 41 of the lower end part of the steel pipe sheet pile 4 with the form substantially the same as the case of the H-section steel 3.
- the steel pipe sheet pile 4 having only one T-shaped joint 41 of the pair of joints is used as a stiffener, but the T-shaped joint 41 and the T-shaped joint 41 are fitted. You may use the general steel pipe sheet pile provided with both the joint which has a shape.
- two channel steels (C-shaped steel (no lip)) 5 may be used as a stiffener.
- the cross-sectional shape is substantially the same H shape as the H-shaped steel 3.
- the two channel steels 5 can be fitted to the first guide member 24 of the steel sheet pile 2 or the first guide member having substantially the same shape as the first guide member 24 as in the case of the H-shaped steel 3.
- the second guide member 33 is attached to the two grooved steels 5 having substantially the same shape as the H-shaped steel 3 in the same manner as the H-shaped steel 3.
- Fig.4 (a) it may replace with the hat-shaped steel sheet pile 2 of the above-mentioned embodiment, and may use the Z-shaped steel sheet pile 6 as a steel sheet pile.
- the Z-shaped steel sheet pile 6 has a Z-shaped cross-sectional shape by providing flanges 62 that are oblique to the web 61 and opposite to each other at both ends of the web 61.
- the shape of the hat-shaped steel sheet pile 2 is substantially the same, and the hat-shaped steel sheet pile 2 is joined to the portion where the flanges 62 of the two Z-shaped steel sheet piles 6 are joined.
- the first guide member 24 in the same manner as the web 21, it can be used in the same manner as the hat-shaped steel sheet pile 2.
- the two Z-shaped steel sheet piles 6 may be constructed in the same manner as the hat-shaped steel sheet pile 2 after the joints 27 are previously fitted and joined, or the pair of angle members 24a Each one is regarded as a first guide member, and the Z-shaped steel sheet piles 6 are driven one by one so that the angle members 24a are fitted to the flanges 32 of the H-shaped steel 3 previously placed. It is good to do.
- FIG. 4 FIG. 5, although the joint 27 of each steel sheet pile 2,6,7,8 is illustrated by the white circle, the flanges 62 of the two Z-shaped steel sheet piles 6 were joined. Since the joint portion of the joint 27 is disposed in the portion, the flange 32 of the H-section steel 3 fitted to the first guide member 24 comes into contact with the joint 27 portion protruding from the side surface of the flange 62. Become.
- FIG.4 (b) it may replace with the hat-shaped steel sheet pile 2 of the above-mentioned embodiment, and may use the linear steel sheet pile 7.
- FIG. The linear steel sheet pile 7 has a shape in which joints 27 are provided on both the left and right sides of the flat steel 71. By providing the first guide member 24 at the lower end of the flat steel 71 portion of the linear steel sheet pile 7, the linear steel sheet pile 7 can be fitted to the H-section steel 3.
- FIG.4 (c) it may replace with the hat-shaped steel sheet pile 2 of the above-mentioned embodiment, and may use the U-shaped steel sheet pile 8.
- FIG.4 (c) it may replace with the hat-shaped steel sheet pile 2 of the above-mentioned embodiment, and may use the U-shaped steel sheet pile 8.
- the U-shaped steel sheet pile 8 is provided with flanges 82 each having an obliquely widening shape at both ends of a web 81 and a joint 27 provided at the tip of the flange 82.
- the U-shaped steel sheet pile 8 basically has a shape in which the arm 23 of the hat-shaped steel sheet pile 2 is eliminated, and the first guide member 24 is provided at the lower end portion of the web 81 as in the case of the hat-shaped steel sheet pile 2. Like the hat-shaped steel sheet pile 2, it can be fitted to the H-shaped steel 3.
- FIG. 5A and 5B are views showing steel continuous walls 1 and 9 made of steel sheet piles 2 and 8 and H-section steel 3.
- FIG. 5A shows the steel continuous wall 1 made of the hat-shaped steel sheet pile 2 and the H-shaped steel 3 shown in the above-described embodiment, and H is formed on one side of the steel continuous wall 1. The state where the shape steel 3 is arranged in a substantially contacted state is shown.
- FIG. 5 (b) is a diagram showing an example of a continuous steel wall 9 using the U-shaped steel sheet pile 8, and a plurality of U-shaped steel sheet piles 8 are connected by joints 27 and the continuous steel wall 9.
- the H-shaped steel is arranged in a state of being substantially in contact with the U-shaped steel sheet pile 8 on one side.
- the steel sheet pile wall having the same cross-sectional shape as that of the hat-shaped steel sheet pile 2 can be constructed by arranging the directions that are generally mountain side (valley side) alternately.
- the U-shaped steel sheet piles 8 are alternately arranged so that the peaks and valleys are repeated on one side of the continuous steel wall 9.
- the first guide members 24 are arranged so as to alternate between the valley side surface and the mountain side surface of the U-shaped steel sheet pile 8, thereby the steel continuous wall.
- the first guide member 24 is disposed only on one side surface side
- the H-section steel 3 fitted to the first guide member 24 is disposed only on one side surface side of the steel continuous wall 9. .
- the H-section steel 3 may be arranged on both sides of the steel continuous wall 9 depending on the purpose of use of the steel continuous wall 9 and the situation of the construction site.
- the first guide member 24 may be provided only on the side surface on the valley side or only on the side surface on the mountain side.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
本発明は、土木建築工事において土砂などの崩落を防ぐ土留め壁、地下構造物の壁、河川や港湾の護岸・岸壁、道路工事などの擁壁等に用いられる、鋼矢板を連結した鋼製連続壁および鋼製連続壁の施工方法に関するものである。 The present invention relates to a steel wall with steel sheet piles used for retaining walls, such as earth retaining walls, underground structure walls, river and harbor revetments and quay walls, road works, etc. It is related with the construction method of a continuous wall and steel continuous walls.
土木建築分野において、土砂などの崩落を防ぐ土留め壁や河川護岸、道路擁壁などに用いられる地中連続壁用鋼材として、一般的に鋼矢板が使用されている。この鋼矢板には、直線形鋼矢板、U形鋼矢板、Z形鋼矢板、ハット形鋼矢板、ボックス形鋼矢板(U形鋼矢板2枚を溶接で一体化させ箱状にしたもの)等の種類がある。このような鋼矢板に、この鋼矢板を連結した壁体の断面性能を高める目的で、H形鋼やCT鋼等の補剛材を全長溶接して一体化された組合せ鋼矢板が知られている。 In the field of civil engineering and construction, steel sheet piles are generally used as steel materials for underground walls used for earth retaining walls, river revetments, road retaining walls, etc. to prevent the collapse of earth and sand. For this steel sheet pile, straight steel sheet pile, U-shaped steel sheet pile, Z-shaped steel sheet pile, hat-shaped steel sheet pile, box-shaped steel sheet pile (two U-shaped steel sheet piles are integrated into a box shape by welding), etc. There are different types. In order to improve the cross-sectional performance of the wall body in which this steel sheet pile is connected to such a steel sheet pile, there is known a combined steel sheet pile integrated by full length welding of a stiffener such as H-section steel or CT steel. Yes.
この組合せ鋼矢板は、断面性能は非常に優れているものの、複雑な形状であることからコンパクトに積み重ねることができず嵩張るので、運搬時に一度に多数の組合せ鋼矢板を車両に積載することが困難となり、運送コストが高くなるなどの問題がある。
そこで、運搬の利便性を重視する観点から、工事現場までは鋼矢板と補鋼材を一体化せず別々に運搬して、現場で一体化するという方法もある。ただし、工事現場では全長溶接のような作業が難しいので、大きな断面性能が得られるような一体化は難しい。また、全長溶接による鋼矢板の熱歪みを修正する必要が生じることもある。
Although this combined steel sheet pile has excellent cross-sectional performance, it is difficult to stack a large number of combined steel sheet piles on a vehicle at the time of transportation because it is complicated and cannot be stacked compactly and is bulky. Thus, there are problems such as high transportation costs.
Therefore, from the viewpoint of emphasizing the convenience of transportation, there is also a method in which the steel sheet pile and the supplementary steel material are transported separately to the construction site and integrated on the site. However, since work such as full length welding is difficult at the construction site, it is difficult to integrate such that a large cross-sectional performance can be obtained. It may also be necessary to correct the thermal distortion of the steel sheet pile due to full length welding.
一方、全長溶接などにより鋼矢板と補剛材とが完全に一体化されていなくても、鋼矢板と補剛材とがいわゆる重ね梁のような挙動をすれば、鋼矢板だけの場合と比較して断面性能が向上する。このように機能させるには、地盤に打設された鋼矢板と補剛材とが実質的に接していなければならない。 On the other hand, even if the steel sheet pile and the stiffener are not completely integrated by full length welding, etc., if the steel sheet pile and the stiffener behave like a so-called overlapped beam, it is compared with the case of only the steel sheet pile. As a result, the cross-sectional performance is improved. In order to function in this way, the steel sheet pile placed on the ground and the stiffener must be substantially in contact.
このような鋼矢板壁として、鋼矢板のウェブとH形鋼のフランジとが地上側の一端のみで拘束された構造の地中連続壁が提案されている(例えば、特許文献1参照)。この地中連続壁の施工方法の一例として、さらに、設置過程で鋼矢板のウェブとH形鋼のフランジが地中内で離れてしまうのを防ぐために、鋼矢板のウェブとH形鋼のフランジとの地上側の一端の反対側となる地中側の一端を仮止めすることが提案されている。 As such a steel sheet pile wall, an underground continuous wall having a structure in which a steel sheet pile web and an H-shaped steel flange are restrained only at one end on the ground side has been proposed (for example, see Patent Document 1). As an example of the construction method of this underground continuous wall, in order to prevent the steel sheet pile web and the H-shaped steel flange from separating in the ground during the installation process, the steel sheet pile web and the H-shaped steel flange It has been proposed to temporarily fix one end on the ground side opposite to one end on the ground side.
また、鋼矢板の片面に嵌合部材(アングル、ガイド)を備え、補強鋼材(補剛材)であるH形鋼のフランジと嵌合する構造が提案されている(例えば、特許文献2,3参照)。
特許文献2では、嵌合部材が鋼矢板全長に設けられ、鋼矢板とH形鋼が嵌合された状態で建て込まれる。特許文献3では、嵌合部材が鋼矢板全長(不連続でもよい)または上端部のみに設けられ、鋼矢板を先に打設した後、嵌合部材をガイドとしてH形鋼を打設する方法が提案されている。
In addition, a structure has been proposed in which a fitting member (angle, guide) is provided on one side of a steel sheet pile and fitted to a flange of an H-shaped steel that is a reinforcing steel material (stiffening material) (for example,
In
しかしながら、鋼矢板は一般的には10mを超える長尺な場合が多いので、特許文献1に示されるような鋼矢板の上下端のみの仮止めでは、吊って所定位置におろす時などに、仮止め部の破損や変形が生じる可能性が高く、地盤への打設時に、鋼矢板とH形鋼とが離れてしまう虞がある。その為、単なる仮止めにとどまらず、鋼矢板とH形鋼の上端部および下端部の一体化が必要となり、結果として加工費が上昇したり、前述の全長溶接の場合と同様の課題が生じることが考えられる。
However, since steel sheet piles generally have a length exceeding 10 m in many cases, the temporary fixing of only the upper and lower ends of the steel sheet piles as shown in
また、特許文献2,3に示される鋼矢板壁においては、全長にガイド部材を設けるのは、材料・加工等のコスト面で大きく不利である。
また、特許文献3においては、鋼矢板を先に地盤に打ち込んだ後に、鋼矢板に設けられた嵌合部材に案内させてH形鋼を打ち込むことにより、それぞれ小さい打ち込み力で打ち込めるので小型の打設機の使用が可能になるというメリットがあるが、全長にガイド部材を設けた場合には、上述のようにコスト的に問題がある。また、鋼矢板の上端部にのみ嵌合部材を設けた場合には、地中部で鋼材同士が接しているかどうかの確認ができず、もし鋼矢板とH形鋼が離れていれば必要とされる断面性能が発揮できない。
Moreover, in the steel sheet pile wall shown by
In
本発明は、鋼矢板と補剛材とを全長溶接することなく、かつ、鋼矢板もしくは補剛材の全長に渡る嵌合部材を設けることなく、鋼矢板と補剛材とを別々に地盤に打設しても、確実に鋼矢板と補剛材とを互いに接した状態とすることが可能な鋼製連続壁の施工方法および鋼製連続壁を提供することを目的とする。 The present invention separately separates the steel sheet pile and the stiffener from the ground without welding the steel sheet pile and the stiffener full length and without providing a fitting member over the entire length of the steel sheet pile or stiffener An object of the present invention is to provide a steel continuous wall construction method and a steel continuous wall that can reliably bring the steel sheet pile and the stiffener into contact with each other even when the steel sheet is placed.
前記課題を解決するために、請求項1に記載の鋼製連続壁の施工方法は、鋼矢板を連結して形成される壁体の少なくとも一方の面側に、前記鋼矢板の長手方向に長手方向を沿わせて前記鋼矢板に接する長尺な補剛材を備える鋼製連続壁の施工方法であって、前記鋼矢板の下端部に、この鋼矢板に接する前記補剛材に嵌合されて、当該鋼矢板を前記補剛材の長手方向に沿って移動可能とする第1ガイド部材を設け、前記補剛材の下端部に、この補剛材と接する前記鋼矢板に隣接して先に打設されている既設鋼矢板に嵌合されて、当該補剛材をこの既設鋼矢板の長手方向に沿って移動可能とする第2ガイド部材を設け、前記補剛材を、前記既設鋼矢板に前記第2ガイド部材を嵌合させて、前記既設鋼矢板に位置決めさせるとともに案内させながら地盤に打設し、次いで、前記鋼矢板を、前記既設鋼矢板に連結させ、かつ先に打設された前記補剛材に前記第1ガイド部材を嵌合させて、前記補剛材に案内させながら地盤に打設することを特徴とする。
In order to solve the above-mentioned problem, the construction method of the continuous steel wall according to
請求項2に記載の鋼製連続壁の施工方法は、請求項1に記載の発明において、前記鋼矢板は、左右に隣接する鋼矢板とそれぞれ連結する継手を備え、前記第2ガイド部材の断面形状を、前記鋼矢板の断面形状もしくは前記鋼矢板の断面形状のうちの少なくとも一方の継手部分を有する一部の断面形状と同じに形成し、前記第2ガイド部材の前記鋼矢板の継手に対応する部分を、前記既設鋼矢板の継手に嵌合させることを特徴とする。
The construction method of the continuous wall made of steel according to
請求項3に記載の鋼製連続壁の施工方法は、請求項1または請求項2に記載の発明において、前記補剛材を打設するに際し、前記既設鋼矢板に嵌合する前記第2ガイド部材が前記既設鋼矢板の下端から外れる前に、前記補剛材の打設を終了することを特徴とする。
The construction method of the steel continuous wall according to
請求項4に記載の鋼製連続壁の施工方法は、請求項1に記載の発明において、前記鋼矢板を打設するに際し、前記鋼矢板の下端が前記補剛材の第2ガイド部材に接触して前記第2ガイド部材を下に押すことにより、前記補剛材が下に移動するまで前記鋼矢板を地盤に打設することを特徴とする。
The construction method of the steel continuous wall according to
請求項5に記載の鋼製連続壁は、鋼矢板を連結して形成される壁体の少なくとも一方の面側に、前記鋼矢板の長手方向に長手方向を沿わせて前記鋼矢板に接する長尺な補剛材を備える鋼製連続壁であって、前記鋼矢板の下端部に、当該鋼矢板の打設時にこの鋼矢板に接する前記補剛材に嵌合されて、当該鋼矢板を前記補剛材の長手方向に沿って移動可能とする第1ガイド部材が設けられ、前記補剛材の下端部に、当該補剛材の打設時にこの補剛材と接する前記鋼矢板に隣接して先に打設されている既設鋼矢板に嵌合されて、当該補剛材をこの既設鋼矢板の長手方向に沿って移動可能とすることにより、この既設鋼矢板に対する前記補剛材の位置を決める第2ガイド部材が設けられていることを特徴とする。
The steel continuous wall according to
請求項6に記載の鋼製連続壁は、請求項5に記載の発明において、前記鋼矢板は左右に隣接する鋼矢板とそれぞれ連結する継手を備え、前記第2ガイド部材の断面形状が前記鋼矢板の断面形状もしくは前記鋼矢板の断面形状のうちの少なくとも一方の継手部分を有する一部の断面形状と同じに形成されていることを特徴とする。
The continuous steel wall according to
請求項1および請求項5に記載の発明においては、補剛材をこの補剛材に接する鋼矢板より先に打設するもので、補剛材は第2ガイド部材を既設鋼矢板に嵌合させた状態で、既設鋼矢板に案内されながら、所定の位置に打設される。続いて、このように打設された補剛材に、第1ガイド部材を嵌合させた状態で補剛材に案内されながら鋼矢板が打設されるので、打設中は鋼矢板の下端部が常に補剛材に接した状態となる。したがって、地上側で打設終了まで鋼矢板と先に打設された補剛材とが接していることを確認しながら打設すれば、補剛材および鋼矢板の略全長に渡って補剛材と鋼矢板とが実質的に接していることになる。鋼矢板は、鋼矢板どうしを連結するための継手を備えており、既設鋼矢板の継手に継手を連結させた状態で地盤に打設される。
In the inventions according to
また、鋼矢板と補剛材とが別々に打設されるので、鋼矢板と補剛材とをそれぞれ別々にコンパクトにまとめて保管および運送することが可能となる。これにより、鋼矢板と補剛材とを一体に形成した後に嵩張った状態で保管および運送した場合に比較して、物流コストを低減することができる。
この補剛材は、必要とされる断面性能に応じて適切なものを選べばよく、H形鋼等の各種形鋼から選択可能であるとともに、ガイド部材に係合可能な継手を有する鋼管矢板を用いることも可能であり、設計の自由度は大きい。
Moreover, since the steel sheet pile and the stiffener are driven separately, it becomes possible to store and transport the steel sheet pile and the stiffener separately in a compact manner. Thereby, compared with the case where the steel sheet pile and the stiffener are integrally formed and then stored and transported in a bulky state, the distribution cost can be reduced.
The stiffener may be selected appropriately according to the required cross-sectional performance, and can be selected from various shapes such as H-section steel, and has a joint that can be engaged with the guide member. Can be used, and the degree of freedom in design is great.
なお、補剛材への第2ガイド部材の取り付けと、鋼矢板への第1ガイド部材の取り付けは、十分な強度が確保できるならば、例えば、溶接でもボルト接合でも良く、また、現場で行っても、工場等で行ってもよい。したがって、施工環境に合わせて接合方法を選択することができる。例えば、溶接が困難な施工環境では、ボルト接合を選択することができる。橋の桁下部などの上空制限がある場所でも、状況に応じて接合方法を選択することができる。 Note that the second guide member and the first guide member can be attached to the stiffener and the steel sheet pile, for example, by welding or bolt joining, as long as sufficient strength can be secured. Alternatively, it may be performed at a factory or the like. Therefore, a joining method can be selected according to the construction environment. For example, in a construction environment where welding is difficult, bolt joining can be selected. Even in places where there are restrictions on the sky, such as under the bridge girder, the joining method can be selected according to the situation.
請求項2および請求項6に記載の発明においては、第2ガイド部材の断面形状が鋼矢板の断面形状もしくは鋼矢板の一方の継手部分を含む一部の断面形状と同じに形成されているので、第2ガイド部材の鋼矢板の継手に対応する部分を既設鋼矢板の継手に嵌合した状態で補剛材を打設することで、補剛材の位置を正しく決めることができる。なお、この際に、鋼矢板と同じもしくは一部同じ断面形状を有する第2ガイド部材の補剛材が取り付けられる位置は、鋼矢板の断面形状の補剛材が接する位置と同じ位置とされる。
In the invention according to
また、補剛材の下端部に設けられる第2ガイド部材としては、鋼矢板を長手方向に短く切断したものを用いることができる。
さらに、第2ガイド部材は、既設鋼矢板の継手にだけ嵌合すればよいので、鋼矢板全体の断面形状のうちの補剛材が取り付けられる部分から既設鋼矢板の継手に嵌合する継手部分まであればよく、他方の継手側を切断した断面形状で十分に第2ガイド部材として機能することになる。また、このように第2ガイド部材の断面形状を鋼矢板の断面形状のうちの一部の断面形状とすることで、補剛材に第2ガイド部材を取り付けた状態で運搬するような場合に、補剛材をよりコンパクトにまとめて配置することができる。
Moreover, what cut | disconnected the steel sheet pile short to the longitudinal direction can be used as a 2nd guide member provided in the lower end part of a stiffener.
Further, since the second guide member only needs to be fitted to the joint of the existing steel sheet pile, the joint portion to be fitted to the joint of the existing steel sheet pile from the portion where the stiffener is attached in the cross-sectional shape of the entire steel sheet pile. The cross-sectional shape obtained by cutting the other joint side sufficiently functions as the second guide member. In addition, by making the cross-sectional shape of the second guide member a partial cross-sectional shape of the cross-sectional shape of the steel sheet pile in this way, when transporting with the second guide member attached to the stiffener The stiffeners can be arranged in a more compact manner.
請求項3に記載の発明においては、補剛材を打設する際に、第2ガイド部材が既設鋼矢板から外れてしまうと、補剛材の位置が最適な位置からずれる虞れがあるので、補剛材の打設終了時も第2ガイド部材が既設鋼矢板から外れていないことが好ましい。第2ガイド部材が既設鋼矢板の下端から下側に外れる前に、補剛材の打設を終了することにより、補剛材を高い精度で位置決めすることができる。
In the invention according to
なお、鋼矢板の長さと、補剛材の長さと、第2ガイド部材の補剛材への取り付け位置と、第2ガイド部材の上下幅とから、第2ガイド部材が鋼矢板の下端かその下側に外れる際の、鋼矢板の上端と補剛材の上端の高さの差の値を求めることができる。したがって、鋼矢板の上端と補剛材の上端の高さの差が、求められた値となる前に補剛材の打設を終了することで、第2ガイド部材が鋼矢板から下側に外れるのを防止できる。 It should be noted that the second guide member is the lower end of the steel sheet pile or its length from the length of the steel sheet pile, the length of the stiffener, the attachment position of the second guide member to the stiffener, and the vertical width of the second guide member. The value of the difference in height between the upper end of the steel sheet pile and the upper end of the stiffener when it falls off can be determined. Therefore, the second guide member is moved downward from the steel sheet pile by finishing the placement of the stiffener before the difference in height between the upper end of the steel sheet pile and the upper end of the stiffener becomes the determined value. It can be prevented from coming off.
請求項4に記載の発明においては、鋼矢板の第1ガイド部材が補剛材に正しく嵌合した状態で鋼矢板を打設すると、鋼矢板の打設終了時に鋼矢板が補剛材の下端部に設けられた第2ガイド部材に当たり、第2ガイド部材を下に押すことになる。これにより、補剛材が下に移動する。地上側から見た場合に、補剛材の上端が少し沈み込むのが確認されることになる。
したがって、補剛材の上端が少し沈み込むまで、鋼矢板を打設することにより、鋼矢板の第1ガイド部材が補剛材から外れたり、鋼矢板から第1ガイド部材が外れたりして、鋼矢板の下端部側が補剛材から離れていなかどうかを確認することができる。
In the invention according to
Therefore, by placing the steel sheet pile until the upper end of the stiffener sinks slightly, the first guide member of the steel sheet pile is detached from the stiffener, or the first guide member is detached from the steel sheet pile, It can be confirmed whether the lower end side of the steel sheet pile is not separated from the stiffener.
本発明によれば、鋼矢板と補剛材とを全長溶接等で溶接することなく、かつ、鋼矢板と補剛材とを略全長に渡って嵌合させる嵌合部材を設けることなく、鋼矢板と補剛材とを別々に地盤に打設するものとしても、鋼矢板と補剛材とが実質的に接した状態として、確実に断面性能の向上を図ることができる。 According to the present invention, without welding a steel sheet pile and a stiffener by full length welding or the like, and without providing a fitting member for fitting the steel sheet pile and the stiffener over substantially the entire length, Even if the sheet pile and the stiffener are separately placed on the ground, the cross-sectional performance can be reliably improved with the steel sheet pile and the stiffener substantially in contact with each other.
以下、本発明の実施の形態を図面に基づいて説明する。
図1に示す鋼製連続壁1は、ハット形の鋼矢板2と補剛材としてのH形鋼3とを一体に接合せずに、鋼矢板2とH形鋼3とを接触させた構造である。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
The steel
ハット形の鋼矢板2は、周知のように、ウェブ21と、このウェブ21の左右両端部からそれぞれ互いに先端側が広がるように斜めに設けられたフランジ22と、各フランジ22の先端からウェブ21と平行に延出するアーム23と、アーム23の先端部に設けられた図示しない継手とを備えるものである。なお、継手は、例えば、周知のものであり、湾曲して内周側に間隔をあけて折り返された形状となっている。また、左右の継手で折り返される方向が逆となっており、逆向きの継手が互いに嵌合するようになっている。
この鋼矢板2は、その下端部に第1ガイド部材24を備えている。この第1ガイド部材24は、補剛材としてのH形鋼3の後述のフランジ32に嵌合するものである。
As is well known, the hat-shaped
The
第1ガイド部材24は、鋼矢板2のウェブ21との間にH形鋼3のフランジ32を挿入可能な概略板状の空間を形成するように、第1ガイド部材24とウェブ21と合わせて矩形枠状の構造となっているとともに、第1ガイド部材24側にH形鋼3のウェブ31を挿通可能なスリットを設けた形状となっている。
この第1ガイド部材24は、左右一対の断面L字状のアングル材(L形鋼)24aからなる。第1ガイド部材24は、鋼矢板2のウェブ21の谷側の側面の下端部に設けられている。すなわち、第1ガイド部材24は、各アングル材24aを構成する二つの平板部のうちの一方の平板部がウェブ21に対して直角に配置されてウェブ21に接合(溶接)され、そして他方の平板部がウェブ21と平行に配置されるとともに、他方の平板部どうしが間隔をあけて対向するように配置されている。
The
The
この第1ガイド部材24の両アングル材24aの他方の平板部と、鋼矢板2のウェブ21との間に、H形鋼3のフランジ32がウェブ21に略接触するように配置され、アングル材24aの他方の平板部どうしの間に、H形鋼3のウェブ31が配置されている。この第1ガイド部材24の上下幅は、鋼矢板2の上下長さに対してかなり短いものとなっている。また、第1ガイド部材24は、H形鋼3の一方のフランジ32に対して上下動自在に嵌合するようになっており、第1ガイド部材24を既に打設されたH形鋼3のフランジ32に嵌合させた状態で鋼矢板2を打設した際に、第1ガイド部材24がH形鋼3のフランジ32に案内される。
Between the other flat plate portion of the two
第1ガイド部材24を構成する一対のアングル材24aは、上述のように、例えば、溶接により取り付けることができるが、このほかに例えば、アングル材24aにフランジとなる部分を設けてフランジとなる部分をボルトでウェブ21に締結して固定するようにしてもよい。なお、ボルトを用いる場合には、第1ガイド部材24とH形鋼3のフランジ32との嵌合や、嵌合した状態での上下動の邪魔にならないようにする。
As described above, the pair of
補剛材となるH形鋼3は、周知のように、ウェブ31と、このウェブ31の両端にそれぞれウェブ31と直交するように設けられたフランジ32を備えるものである。このH形鋼3は、一方のフランジ32が鋼矢板2のガイド部材24に係合した状態で、鋼矢板2のウェブ21に略面接触するようになっている。
H形鋼3の下端部には、H形鋼3に接する鋼矢板2に隣接するとともに先に打設された鋼矢板2である既設鋼矢板2aに嵌合する第2ガイド部材33が設けられている。
As is well known, the H-
A
この第2ガイド部材33は、鋼矢板2と同じ鋼矢板2を加工して作られるもので、鋼矢板2を短く切断するとともに、ウェブ21と片側のフランジ22との境目で切断したものである。すなわち、第2ガイド部材33は、鋼矢板2の断面形状のうちのウェブ21と一方のフランジ22とこのフランジ22の先端に設けられたアーム23とアーム23の先端に設けられた継手とからなるもので、他方のフランジ22と、その先の他方のアーム23および他方の継手が無いものである。第2ガイド部材33の上下幅は、H形鋼3の長さに対してかなり短いものとなっている。第2ガイド部材33とH形鋼3のフランジ32とは、溶接やボルト締め等の周知の手段で固定されている。
The
次に、以上のような第1ガイド部材24を備える鋼矢板2と、第2ガイド部材33を備える補剛材としてのH形鋼3とからなる鋼製連続壁1の施工方法を説明するとともに、当該施工方法により構築される鋼製連続壁1を説明する。
鋼製連続壁1の施工においては、まず、1つの鋼矢板2を打設する。
ここで、これから打設される鋼矢板2または打設中の鋼矢板2に対して、この打設前または打設中の鋼矢板2に隣接するとともに、既に地盤に打設されている鋼矢板2を区別するために、この打設済みの鋼矢板2を便宜的に既設鋼矢板と称するとともに、その符号を2aとする。
次いで、図1の(a)に示されるように、既設鋼矢板2aの一方のアーム23先端部の継手に、第2ガイド部材33のアーム23先端部の継手を嵌合させた状態で、H形鋼3を打設する。
なお、鋼矢板2およびH形鋼3の打設は、打撃によるものや、圧入によるものや、圧入に振動を加えたものなど、周知の各種方法を任意に用いることができる。
Next, while explaining the construction method of the steel
In the construction of the steel
Here, with respect to the
Next, as shown in FIG. 1 (a), in a state where the joint at the tip of the
The
図1の(b)に示されるように、既設鋼矢板2aの一方の継手の下端部に、第2ガイド部材33の継手の上端部が嵌合している状態で、H形鋼3の打設を終了する。このとき、第2ガイド部材33の上端部を除く部分は、既設鋼矢板2aの下端より低い位置に来ることになるので、鋼矢板2aとH形鋼3の上端の高さを合わせる場合には、鋼矢板2aの長さよりH形鋼3の長さを第2ガイド部材33の上下幅程度だけ長くする必要がある。
As shown in FIG. 1B, in the state where the upper end of the joint of the
この場合に、鋼矢板2aの上端高さに対してH形鋼3の上端の高さが少し高くなっている状態で、H形鋼3の打設を停止することにより、鋼矢板2aの継手から第2ガイド部材33の継手が下側に外れる前にH形鋼3の打設を終了することができる。
これにより、H形鋼3を打設している間、H形鋼3の第2ガイド部材33が既設鋼矢板2aに嵌合していることになり、H形鋼3が位置決めされた状態が保持され、H形鋼3と既設鋼矢板2aが平行な状態に維持される。
In this case, the joint of the
Thereby, while the H-
なお、第2ガイド部材33が既設鋼矢板2aより下となって、これらの嵌合が解除されたにもかかわらず、さらにH形鋼3を打設してしまうと、H形鋼3の下部の位置がずれて、H形鋼3と既設鋼矢板2aとが所定距離より離れたり近づいたりしてしまう虞がある。この場合に、後述するように、既設鋼矢板2aの継手と、H形鋼3のフランジ32との両方に嵌合した状態で打設される鋼矢板2を最後まで打設することが困難になる虞がある。
In addition, even if the
次いで、図1の(c)に示されるように、鋼矢板2を打設する。すなわち、鋼矢板2の下端部の第1ガイド部材24に、上述のように先に打設されたH形鋼3の一方のフランジ32を嵌合させた状態とし、かつ、既設鋼矢板2aの一方の継手に鋼矢板2の継手を嵌合させた状態として、鋼矢板2を打設する。これにより、鋼矢板2は、先に打設済みのH形鋼3と既設鋼矢板2aとに案内されながら地盤に打設される。
なお、既設鋼矢板2aと、H形鋼3の多少のずれは、第1ガイド部材24の遊びにより吸収される。
この鋼矢板2の打設中に地上側でH形鋼3と鋼矢板2とが接触した状態となっていれば、鋼矢板2の下端部が第1ガイド部材24によりH形鋼3に接触した状態に保持されるので、鋼矢板2とH形鋼3とが接触した状態で鋼矢板2が打設されることになる。
Next, as shown in FIG. 1C, a
Note that some deviation between the existing
If the H-
このようにして、図1の(d)に示されるように、鋼矢板2の打設が終了する。
このとき、既設鋼矢板2aと鋼矢板2とは、長さも通常同じなので、これらの上端の高さを同じとした場合に、既設鋼矢板2aと鋼矢板2との下端の高さ位置も同じとなる。
In this way, the placement of the
At this time, since the existing
打設完了の少し前の状態では、前述したように、既設鋼矢板2aの下端部では、H形鋼3の第2ガイド部材33が嵌合した状態となっており、第2ガイド部材33の上端の位置が既設鋼矢板2aの下端より少し高くなっている。したがって、鋼矢板2の上端が既設鋼矢板2aの上端と同じ高さとなるまで鋼矢板2を打設すると、鋼矢板2の下端が第2ガイド部材33に当たって、第2ガイド部材33を少しだけ下方に押すことになる。
In a state just before the completion of placing, as described above, the
第2ガイド部材33が下方に押されて移動すると、第2ガイド部材33が固定されたH形鋼3も少し下に移動する。このとき、地上側でH形鋼3の上端部が少し沈み込むのが確認されることになる。そうすると、鋼矢板2の下端部の第1ガイド部材24が最後までH形鋼に嵌合した状態で鋼矢板2が打設されたものと推測可能である。
なお、万が一、ガイド部材33が損傷したり、鋼矢板2から打設途中で外れるなどして、鋼矢板2の下端部がH形鋼3から離れると、鋼矢板2の下端が第2ガイド部材33に当たらずに、鋼矢板2の上端が既設鋼矢板2aの上端と同じ高さとなっても、H形鋼3の上端が沈み込まず、施工に問題があることを知ることが可能となる。これにより、鋼矢板2の施工のし直しや、補強などによる対応が可能となる。
When the
If the lower end of the
なお、第2ガイド部材33が下方に押されると、鋼矢板2の長さが既設鋼矢板2aと同じであれば、第2ガイド部材33が既設鋼矢板2aからちょうど外れることになる。この場合には、既に、鋼矢板2の打設が終了するとともに、鋼矢板2の下端部の第1ガイド部材24がH形鋼3の下端部に嵌合した状態なので、第2ガイド部材が既設鋼矢板2aから外れても問題が生じない。
In addition, if the length of the
このように打設された鋼矢板2が既設鋼矢板2aとなり、この既設鋼矢板2aに対して次のH形鋼3と鋼矢板2の打設を上述のように行い、そしてこれを繰り返すことにより、H形鋼3が接触した鋼矢板2を連結した重ね梁型鋼矢板壁としての鋼製連続壁1を構築していき、設定された長さまで鋼製連続壁1を設けた段階で、鋼製連続壁1の施工が終了する。
このようにして構築された鋼製連続壁1は、例えば、図5(a)に示すように、複数連結された鋼矢板2の谷側となる側面側にH形鋼3が接触した状態に配置されている。鋼矢板2のウエブ21の一方の面にH形鋼3の一方のフランジ32が略接触した状態となっており鋼矢板2の下端部の第1ガイド部材24がH形鋼3のフランジ32の下端部に嵌合しているが、それ以外の部分で、鋼矢板2とH形鋼3とは接合されたり、嵌合されたりしていない。
The
The steel
また、鋼矢板2に接触するH形鋼3をこの鋼矢板2より先に打設するものとしても、既設鋼矢板2aに対してH形鋼3が第2ガイド部材33により、鋼矢板2の打設位置に対応した正しい位置に配置された状態で、既設鋼矢板2と平行に打設されることになる。
Moreover, even if the H-
この状態で、鋼矢板2をその継手を既設鋼矢板2aの継手に嵌合させるとともに、H形鋼3に第1ガイド部材24を嵌合させることで、これらに案内された状態で鋼矢板2を打設することができる。この際にH形鋼3が上述のように正しい位置に既設鋼矢板2aと平行に打設されているので、鋼矢板2を正しい位置に打設できる。
また、鋼矢板2とH形鋼3とが接触した状態に打設されているので、鋼矢板2とH形鋼3とが重ね梁として機能し、断面性能が向上した鋼製連続壁1を得ることが可能となる。
In this state, the
Moreover, since the
また、鋼矢板2とH形鋼3とを別々に打設することから、鋼矢板2とH形鋼3とを一体とした後に打設するよりも地盤からの抵抗が小さく、小さな打ち込み力で鋼矢板2とH形鋼3とを打設できるので、出力が小さな打設機でも打設が可能となり、施工時の設備コストの低減を図ることができる。
Moreover, since the
また、鋼矢板2とH形鋼3とを運搬する際も、これらを別々に運搬することができ、これらが嵩張らないように荷積みして、効率的に運搬することにより、運送費を低減することができる。
また、鋼矢板2への第1ガイド部材24の取り付けと、H形鋼3への第2ガイド部材33の取り付けは、これら第1ガイド部材24や第2ガイド部材33が短いものなので、鋼矢板2とH形鋼3との全長溶接などに比較して極めて容易であり、現場で行うことも工場で行うことも可能である。工場で行った場合には、鋼矢板2およびH形鋼3が多少嵩張る状態となる虞があるが、それでも、鋼矢板とH形鋼を一体とした場合よりも、運送効率を向上することができる。
In addition, when transporting the
In addition, the attachment of the
なお、上述の実施の形態では、鋼製連続壁1の一方の面側に、補剛材としてのH形鋼3が配置される場合について説明したが、状況に応じて、鋼製連続壁1の両側の面にH形鋼3が配置されるようにしてもよい。
また、上述の実施の形態では、第1ガイド部材24としてアングル材(L形鋼)24aを用いたが、図2(a)に示すように、T形鋼(CT鋼)24bを用いてもよいし、図2(b)に示すように、リップ溝形鋼(C形鋼)24cを用いてもよい。T形鋼24bの場合には、アングル材24aと同様に一対のT形鋼24bを用い、リップ溝形鋼24cの場合には、1つでガイド部材24を構成することができる。
また、上述の実施の形態や、図2(a)、(b)では、鋼矢板2の谷側となる側面に第1ガイド部材24を設けたが、図2(c)に示すように、鋼矢板2の山側の側面に第1ガイド部材24を設け、鋼矢板2の山側に補剛材としてのH形鋼3が配置されるようにしてもよい。
In addition, although the above-mentioned embodiment demonstrated the case where the H-
In the above-described embodiment, the angle member (L-shaped steel) 24a is used as the
Moreover, in the above-mentioned embodiment and FIG. 2 (a), (b), although the
また、鋼製連続壁1においては、求められる断面性能やその他の条件に応じて、補剛材の種類および鋼矢板の種類を種々選択することが可能であり、設計の自由度が広いものとなっている。
したがって、鋼製連続壁1においては、上述の実施の形態のH形鋼3(補剛材)や鋼矢板2に代えて、別の種類の補剛材や鋼矢板を用いることができる。
Moreover, in the steel
Therefore, in the steel
以下に、鋼製連続壁で用いられる補剛材と鋼矢板の変形例について説明する。
例えば、図3(a)に示すように、補剛材として鋼管矢板4を用いることができる。この鋼管矢板4は、鋼管42と、鋼矢板2の第1ガイド部材24が嵌合する断面T形のT形継手41とを備えている。
T型継手41は、H形鋼3をウェブ31の部分で切断した際のT形の断面形状と同じ断面形状を有することから、H型鋼3のフランジ32に嵌合する上記例の第1ガイド部材24もしくはこの第1ガイド部材24と略同形状の第1ガイド部材に勘合可能である。なお、一般的な鋼管矢板は、鋼管に連結用の一対の継手を設けたものであるが、この鋼管矢板4は、一対の継手のうちの一方の継手として一般的なT形継手41だけが設けられている。
また、第2ガイド部材33は、鋼管矢板4の下端部のT形継手41の部分にH形鋼3の場合とほぼ同様の形態で取り付けられることになる。なお、この例では、一対の継手のうちの一方のT形継手41だけを有する形状の鋼管矢板4を補剛材として用いたが、T形継手41と、このT形継手41に嵌合する形状を有する継手との両方を備えた一般的な鋼管矢板を用いてもよい。
Below, the modified example of the stiffener and steel sheet pile used with a steel continuous wall is demonstrated.
For example, as shown in FIG. 3A, a steel
Since the T-shaped joint 41 has the same cross-sectional shape as the T-shaped cross-section when the H-
Moreover, the
また、図3(b)に示すように、補剛材として2つの溝形鋼(C形鋼(リップなし))5を用いてもよい。リップの無い2つの溝形鋼5を開放側を外側に向けて反対向きに背中合わせに接合した場合に、その断面形状が、略H形鋼3と同じH形となる。したがって、この2つの溝形鋼5は、H形鋼3の場合と同様に鋼矢板2の第1ガイド部材24またはこの第1ガイド部材24と略同形状の第1ガイド部材に嵌合可能となる。また、第2ガイド部材33は、H形鋼3と略同様の形状となった2本の溝形鋼5にH形鋼3の場合と同様に取り付けられる。
Also, as shown in FIG. 3B, two channel steels (C-shaped steel (no lip)) 5 may be used as a stiffener. When two
また、図4(a)に示すように、上述の実施の形態のハット形鋼矢板2に代えて、鋼矢板としてZ形鋼矢板6を用いてもよい。Z形鋼矢板6は、ウェブ61の両端部にそれぞれウェブ61に対して斜めで、互いに反対向きとなるフランジ62を備えることによりZ字状の断面形状を有するものとなっている。Z形鋼矢板6を二枚組み合わせると、形状的には、ハット形の鋼矢板2ほぼ同形状となり、2つのZ形鋼矢板6のフランジ62どうしが接合された部分にハット形の鋼矢板2のウェブ21と同様に第1ガイド部材24を設けることで、ハット形の鋼矢板2と同様に用いることができる。
Moreover, as shown to Fig.4 (a), it may replace with the hat-shaped
なお、この場合に、例えば、二つのZ形鋼矢板6を予め継手27どうしを嵌合させて接合した後に、ハット形鋼矢板2と同様に施工してもよいし、一対のアングル材24aの1つ1つを第1ガイド部材とみなして、アングル材24aをそれぞれ先に打設されたH形鋼3のフランジ32に嵌合させるようにして、Z形鋼矢板6を1つずつ打設するものとしてもよい。
また、図4、図5においては、各鋼矢板2,6,7,8の継手27を白抜きの丸で図示しているが、2つのZ形鋼矢板6のフランジ62どうしが接合された部分には、継手27の接合部分が配置されるため、第1ガイド部材24に嵌合するH形鋼3のフランジ32は、フランジ62の側面から突出した状態の継手27部分に接触することになる。
In this case, for example, the two Z-shaped steel sheet piles 6 may be constructed in the same manner as the hat-shaped
Moreover, in FIG. 4, FIG. 5, although the joint 27 of each
また、図4(b)に示すように、上述の実施の形態のハット形鋼矢板2に代えて、直線形鋼矢板7を用いても良い。直線形鋼矢板7は、平鋼71の左右両側部にそれぞれ継手27を設けた形状となっている。この直線形鋼矢板7の平鋼71部分の下端部に第1ガイド部材24を設けることで、H形鋼3と嵌合可能となっている。
また、図4(c)に示すように、上述の実施の形態のハット形鋼矢板2に代えて、U形鋼矢板8を用いてもよい。U形鋼矢板8は、ウェブ81の両端にそれぞれ斜めで互いに広がる形状のフランジ82を設け、このフランジ82の先端に継手27を設けたものである。U形鋼矢板8は、基本的にハット形鋼矢板2のアーム23を無くした形状であり、ハット形鋼矢板2の場合と同様にウェブ81の下端部に第1ガイド部材24を設けることで、ハット形鋼矢板2と同様にH形鋼3に嵌合させることができる。
Moreover, as shown in FIG.4 (b), it may replace with the hat-shaped
Moreover, as shown in FIG.4 (c), it may replace with the hat-shaped
図5(a)、(b)は、鋼矢板2,8とH形鋼3とからなる鋼製連続壁1,9を示す図である。
図5(a)は、上述の実施の形態で示したハット形鋼矢板2とH形鋼3からなる鋼製連続壁1を示すものであり、鋼製連続壁1の一方の側面側にH形鋼3が略接触した状態に配置された状態を示している。
5A and 5B are views showing steel
FIG. 5A shows the steel
図5(b)は、U形鋼矢板8を用いた鋼製連続壁9の例を示す図であり、複数のU形鋼矢板8が継手27により連結されているとともに、鋼製連続壁9の一方側にH形鋼がU形鋼矢板8に略接した状態で配置されている。U形鋼矢板8では、一般的に山側(谷側)となる向きが互い違いに配置されることで、ハット形鋼矢板2の場合と同様の断面形状の鋼矢板壁を構築可能となっており、図5(b)においても、鋼製連続壁9の一方の側で山と谷が繰り返されるように、U形鋼矢板8が向きを互い違いにして配置されている。
FIG. 5 (b) is a diagram showing an example of a
このような鋼製連続壁9においては、U形鋼矢板8の谷側の側面と山側の側面とに互い違いとなるように、第1ガイド部材24が配置されており、これにより鋼製連続壁9の一方の側面側だけに第1ガイド部材24が配置されるとともに、この第1ガイド部材24に嵌合するH形鋼3が鋼製連続壁9の一方の側面側だけに配置されている。
In such a steel
なお、鋼製連続壁9の使用目的や施工場所の状況等によっては、鋼製連続壁9の両方の側面にH形鋼3が配置されるようにしてもよい。この場合に、山側と谷側とを互い違いに配置されているU形鋼矢板壁において、第1ガイド部材24を谷側の側面だけ、もしくは山側の側面だけに設けるものとしてもよい。
The H-
1 鋼製連続壁
2 ハット形鋼矢板
2a 既設鋼矢板
3 H形鋼(補剛材)
4 鋼管矢板(補剛材)
5 溝形鋼(補剛材)
6 Z形鋼矢板
7 直線形鋼矢板
8 U形鋼矢板
24 第1ガイド部材
27 継手
33 第2ガイド部材
1 Steel
4 Steel pipe sheet pile (stiffener)
5 Channel steel (stiffener)
6 Z-shaped
Claims (6)
前記鋼矢板の下端部に、この鋼矢板に接する前記補剛材に嵌合されて、当該鋼矢板を前記補剛材の長手方向に沿って移動可能とする第1ガイド部材を設け、
前記補剛材の下端部に、この補剛材と接する前記鋼矢板に隣接して先に打設されている既設鋼矢板に嵌合されて、当該補剛材をこの既設鋼矢板の長手方向に沿って移動可能とする第2ガイド部材を設け、
前記補剛材を、前記既設鋼矢板に前記第2ガイド部材を嵌合させて、前記既設鋼矢板に位置決めさせるとともに案内させながら地盤に打設し、
次いで、前記鋼矢板を、前記既設鋼矢板に連結させ、かつ先に打設された前記補剛材に前記第1ガイド部材を嵌合させて、前記補剛材に案内させながら地盤に打設することを特徴とする鋼製連続壁の施工方法。 A steel continuous wall provided with a long stiffener in contact with the steel sheet pile along the longitudinal direction of the steel sheet pile on at least one surface side of the wall body formed by connecting the steel sheet piles. A construction method,
The lower end portion of the steel sheet pile is provided with a first guide member that is fitted to the stiffener in contact with the steel sheet pile and is movable along the longitudinal direction of the stiffener.
The lower end of the stiffener is fitted to an existing steel sheet pile previously placed adjacent to the steel sheet pile in contact with the stiffener, and the stiffener is placed in the longitudinal direction of the existing steel sheet pile. A second guide member that is movable along
The stiffener is driven into the ground while guiding the second guide member to the existing steel sheet pile, and positioning and guiding the existing steel sheet pile,
Next, the steel sheet pile is connected to the existing steel sheet pile, and the first guide member is fitted to the previously stiffened stiffener and is guided to the ground while being guided by the stiffener. A method for constructing a continuous wall made of steel.
前記第2ガイド部材の断面形状を、前記鋼矢板の断面形状もしくは前記鋼矢板の断面形状のうちの少なくとも一方の継手部分を有する一部の断面形状と同じに形成し、前記第2ガイド部材の前記鋼矢板の継手に対応する部分を、前記既設鋼矢板の継手に嵌合させることを特徴とする請求項1に記載の鋼製連続壁の施工方法。 The steel sheet pile includes a joint to be connected to each of the left and right adjacent steel sheet piles,
A cross-sectional shape of the second guide member is formed to be the same as a cross-sectional shape of the steel sheet pile or a partial cross-sectional shape having at least one joint portion of the cross-sectional shape of the steel sheet pile, and the second guide member The construction method for a continuous steel wall according to claim 1, wherein a portion corresponding to the joint of the steel sheet pile is fitted into the joint of the existing steel sheet pile.
前記鋼矢板の下端部に、当該鋼矢板の打設時にこの鋼矢板に接する前記補剛材に嵌合されて、当該鋼矢板を前記補剛材の長手方向に沿って移動可能とする第1ガイド部材が設けられ、
前記補剛材の下端部に、当該補剛材の打設時にこの補剛材と接する前記鋼矢板に隣接して先に打設されている既設鋼矢板に嵌合されて、当該補剛材をこの既設鋼矢板の長手方向に沿って移動可能とすることにより、この既設鋼矢板に対する前記補剛材の位置を決める第2ガイド部材が設けられていることを特徴とする鋼製連続壁。 A steel continuous wall provided with a long stiffener that contacts the steel sheet pile along the longitudinal direction of the steel sheet pile on at least one surface side of the wall body formed by connecting the steel sheet piles. There,
The lower end portion of the steel sheet pile is fitted to the stiffener that comes into contact with the steel sheet pile when the steel sheet pile is placed, and the steel sheet pile can be moved along the longitudinal direction of the stiffener. A guide member is provided,
The lower end portion of the stiffener is fitted to an existing steel sheet pile previously placed adjacent to the steel sheet pile in contact with the stiffener when the stiffener is placed, and the stiffener A steel continuous wall characterized in that a second guide member for determining the position of the stiffener relative to the existing steel sheet pile is provided by making the steel sheet movable along the longitudinal direction of the existing steel sheet pile.
前記第2ガイド部材の断面形状が前記鋼矢板の断面形状もしくは前記鋼矢板の断面形状のうちの少なくとも一方の継手部分を有する一部の断面形状と同じに形成されていることを特徴とする請求項5に記載の鋼製連続壁。 The steel sheet pile includes a joint that connects to the left and right adjacent steel sheet piles,
The cross-sectional shape of the second guide member is formed to be the same as a partial cross-sectional shape having at least one joint portion of the cross-sectional shape of the steel sheet pile or the cross-sectional shape of the steel sheet pile. Item 6. The steel continuous wall according to Item 5.
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| HK12110268.0A HK1169689B (en) | 2010-03-12 | 2011-02-14 | Continuous steel wall and method for constructing same |
| CN201180002847.8A CN102472031B (en) | 2010-03-12 | 2011-02-14 | Continuous steel wall and method for constructing same |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2010056124A JP5282984B2 (en) | 2010-03-12 | 2010-03-12 | Steel continuous wall construction method and steel continuous wall |
| JP2010-056124 | 2010-03-12 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2011111474A1 true WO2011111474A1 (en) | 2011-09-15 |
Family
ID=44563300
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP2011/053020 Ceased WO2011111474A1 (en) | 2010-03-12 | 2011-02-14 | Continuous steel wall and method for constructing same |
Country Status (4)
| Country | Link |
|---|---|
| JP (1) | JP5282984B2 (en) |
| CN (1) | CN102472031B (en) |
| TW (1) | TWI421394B (en) |
| WO (1) | WO2011111474A1 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104285010A (en) * | 2012-05-16 | 2015-01-14 | 杰富意钢铁株式会社 | Combined steel wall |
| WO2015050207A1 (en) * | 2013-10-04 | 2015-04-09 | 新日鐵住金株式会社 | Continuous wall installation method and continuous wall installation jig |
| CN114991187A (en) * | 2022-06-28 | 2022-09-02 | 安徽省公路桥梁工程有限公司 | Deepwater steel sheet pile and steel pipe pile combined cofferdam structure and construction method thereof |
Families Citing this family (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2013113074A (en) * | 2011-12-01 | 2013-06-10 | Nippon Steel & Sumitomo Metal | Wall body |
| JP2014051820A (en) * | 2012-09-07 | 2014-03-20 | Nippon Steel & Sumitomo Metal | Combined steel wall |
| CN103088831A (en) * | 2013-01-24 | 2013-05-08 | 东南大学 | Overall assembly-type double-row steel pile foundation pit supporting structure |
| JP6763221B2 (en) * | 2016-07-12 | 2020-09-30 | 日本製鉄株式会社 | Reinforcement structure of embankment |
| CN106284371A (en) * | 2016-10-11 | 2017-01-04 | 周峰 | A kind of combination type foundation pit supporting construction |
| CN111188344B (en) * | 2020-01-16 | 2021-04-20 | 江苏建能建设科技有限公司 | Foundation pit supporting device adopting steel sheet piles and construction method |
| CN111851468B (en) * | 2020-07-28 | 2021-11-02 | 上海市基础工程集团有限公司 | Underground water soil steel wall continuous inserting verticality control construction method |
| CN112832256A (en) * | 2021-02-22 | 2021-05-25 | 上海铁能建设工程有限公司 | A PHW Construction Method of Foundation Pit Enclosure |
| CN113756286A (en) * | 2021-08-09 | 2021-12-07 | 上海市基础工程集团有限公司 | Construction method for implementing underground water soil continuous steel wall by TRD method |
| JP7084668B1 (en) | 2022-01-12 | 2022-06-15 | 株式会社小澤土木 | Construction processing method of steel sheet pile |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US1985795A (en) * | 1931-03-09 | 1934-12-25 | Vereinigte Stahlwerke Ag | Sheet piling |
| JP2008038490A (en) * | 2006-08-07 | 2008-02-21 | Nippon Steel Corp | Processed sheet pile for underground continuous wall and manufacturing method thereof |
| JP2009249885A (en) * | 2008-04-04 | 2009-10-29 | Nippon Steel Corp | Method, structure and member for reinforcing existing steel sheet pile |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| TWM359551U (en) * | 2009-02-11 | 2009-06-21 | China Steel Corp | Steel sheet pile unit and steel sheet pile module |
| CN101581097A (en) * | 2009-05-22 | 2009-11-18 | 中交第一航务工程局有限公司 | Vibration sinking technology method of large-sized combined steel plate pile |
-
2010
- 2010-03-12 JP JP2010056124A patent/JP5282984B2/en not_active Expired - Fee Related
-
2011
- 2011-02-14 WO PCT/JP2011/053020 patent/WO2011111474A1/en not_active Ceased
- 2011-02-14 CN CN201180002847.8A patent/CN102472031B/en active Active
- 2011-02-18 TW TW100105413A patent/TWI421394B/en active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US1985795A (en) * | 1931-03-09 | 1934-12-25 | Vereinigte Stahlwerke Ag | Sheet piling |
| JP2008038490A (en) * | 2006-08-07 | 2008-02-21 | Nippon Steel Corp | Processed sheet pile for underground continuous wall and manufacturing method thereof |
| JP2009249885A (en) * | 2008-04-04 | 2009-10-29 | Nippon Steel Corp | Method, structure and member for reinforcing existing steel sheet pile |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104285010A (en) * | 2012-05-16 | 2015-01-14 | 杰富意钢铁株式会社 | Combined steel wall |
| CN104285010B (en) * | 2012-05-16 | 2016-01-20 | 杰富意钢铁株式会社 | Combined steel plate wall |
| WO2015050207A1 (en) * | 2013-10-04 | 2015-04-09 | 新日鐵住金株式会社 | Continuous wall installation method and continuous wall installation jig |
| JPWO2015050207A1 (en) * | 2013-10-04 | 2017-03-09 | 新日鐵住金株式会社 | Continuous wall casting method and continuous wall casting jig |
| CN114991187A (en) * | 2022-06-28 | 2022-09-02 | 安徽省公路桥梁工程有限公司 | Deepwater steel sheet pile and steel pipe pile combined cofferdam structure and construction method thereof |
| CN114991187B (en) * | 2022-06-28 | 2023-09-26 | 安徽省公路桥梁工程有限公司 | Deepwater steel sheet pile and steel pipe pile combined cofferdam structure and construction method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102472031B (en) | 2014-04-09 |
| TW201207196A (en) | 2012-02-16 |
| HK1169689A1 (en) | 2013-02-01 |
| CN102472031A (en) | 2012-05-23 |
| JP5282984B2 (en) | 2013-09-04 |
| JP2011190586A (en) | 2011-09-29 |
| TWI421394B (en) | 2014-01-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5282984B2 (en) | Steel continuous wall construction method and steel continuous wall | |
| CN103797196B (en) | The connected structure of beam and column and mating part | |
| JP2008267069A (en) | Steel material for underground continuous wall, underground continuous wall, and method for constructing underground continuous wall | |
| JP4903744B2 (en) | Existing steel sheet pile reinforcement structure, existing steel sheet pile reinforcement member | |
| JP6375995B2 (en) | Steel sheet pile longitudinal structure and steel sheet pile wall structure | |
| KR101769255B1 (en) | Steel Pipe Assembly for Roof Structure | |
| JP2014020129A (en) | Steel sheet pile and steel sheet pile wall body | |
| JP4754397B2 (en) | H-shaped steel joint structure and joining method | |
| JP6515293B2 (en) | Steel sheet pile wall | |
| JP7149868B2 (en) | Synthetic segments, toroids, structures and skin plates | |
| JP2017180047A (en) | Reinforcement structure and reinforcement method for existing steel pile wall | |
| JP6917402B2 (en) | Segment pieces, segment structures, corner segments, rings and structures | |
| JP4650255B2 (en) | Steel slab reinforcement structure and existing steel slab reinforcement method | |
| JP6766468B2 (en) | Segment wall and tunnel lining | |
| JP5434845B2 (en) | Steel structure and steel sheet pile structure | |
| HK1169689B (en) | Continuous steel wall and method for constructing same | |
| JP5867326B2 (en) | Steel sheet pile and wall body using the same | |
| JP2017180046A (en) | Reinforcement structure and reinforcement method for existing steel sheet pile wall | |
| JP6119879B2 (en) | Combined steel sheet pile installation jig and combined steel sheet pile installation method | |
| JP7219529B2 (en) | Combination structure of steel materials, shoring structure and construction method | |
| JP4953654B2 (en) | Water stop structure of tunnel segment | |
| JP5635383B2 (en) | Existing pile position adjustment jig | |
| JP4760948B2 (en) | Combination steel sheet pile and steel sheet pile wall using the combination steel sheet pile | |
| JP5312231B2 (en) | Steel arc placing method | |
| JP4798251B2 (en) | Combination steel sheet pile and steel sheet pile wall using the combination steel sheet pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| WWE | Wipo information: entry into national phase |
Ref document number: 201180002847.8 Country of ref document: CN |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11753136 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 11753136 Country of ref document: EP Kind code of ref document: A1 |