[go: up one dir, main page]

WO2009007889A2 - Formwork carrier platform system - Google Patents

Formwork carrier platform system Download PDF

Info

Publication number
WO2009007889A2
WO2009007889A2 PCT/IB2008/052691 IB2008052691W WO2009007889A2 WO 2009007889 A2 WO2009007889 A2 WO 2009007889A2 IB 2008052691 W IB2008052691 W IB 2008052691W WO 2009007889 A2 WO2009007889 A2 WO 2009007889A2
Authority
WO
WIPO (PCT)
Prior art keywords
formwork
carrier platform
platform system
concrete
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/IB2008/052691
Other languages
French (fr)
Other versions
WO2009007889A3 (en
Inventor
F. Nihat Akyildiz
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MESA IMALAT SANAYI VE TICARET AS
Original Assignee
MESA IMALAT SANAYI VE TICARET AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MESA IMALAT SANAYI VE TICARET AS filed Critical MESA IMALAT SANAYI VE TICARET AS
Publication of WO2009007889A2 publication Critical patent/WO2009007889A2/en
Publication of WO2009007889A3 publication Critical patent/WO2009007889A3/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete

Definitions

  • the present invention relates to a formwork carrier platform which enables carrying formworks used in reinforced concrete construction to an upper application environment.
  • Formwork carrier climbing platform systems basically comprise carrier anchorages fastened to the holes provided in the concrete, and rings and apparatuses that connect to the said anchorages after disengaging from the formwork concrete.
  • the system is carried from a lower floor to an upper floor via a crane. After connecting ropes to the lifting apparatuses provided on the system, the system is lifted from the anchorage it is located and it is placed on the upper floor. During this operation, the system becomes free as soon as it is disengaged from the anchorage on which it was located. It is carried freely to the upper
  • the objective of the present invention is to realize separation of a form work carrier platform system from the wall concrete to which it is connected to, during carrying the same to an upper floor, without having any employee on the system and such that it will not be affected by the external factors such as wind.
  • Figure 1 is the perspective view of the formwork carrier platform system.
  • the inventive formwork carrier platform system (1) essentially comprises at least one suspension member (2) required for carrying the said system, at least one form work back profile (3) which carries the concrete form work piece and also supports the concrete, at least one prop (4) which connects the formwork back profiles (3) to the prop moving mechanism (5), at least one suspension head (6) mounted to the anchorages provided on the concrete, at least one upper platform (7) which provides a working area on the formwork carrier platform system (1), at least one rail (8) on which the formwork carrier platform system (1) moves, at least one triangular leg (9) located between the upper platform (7) and the rail (8), at least one leg wheel (10) which enables movement on the rail (8) and also provides support to the concrete, at least one lower platform (11) located at the lowermost part of the formwork carrier platform system (1) and at least one drop head (12) which performs locking and which is supported on the suspension head.
  • suspension head (6), rail (8) and the drop head (12) at the end of the main system work one within the other. Thanks to this mechanism with parts operating one within the other, the formwork carrier -platform system (1) can be carried to an upper floor in a safe and controllable manner without getting disengaged from the rail (8).
  • anchorages which will be provided on the concrete are arranged on the surface of the formwork.
  • the formworks are closed and the concrete is poured.
  • the formworks are opened and it is started to carry the system to the upper floor.
  • New suspension heads (12) are mounted at the upper floor to the anchorages provided at the new concrete.
  • the rails (8) are pulled to the upper floor by means of the crane.
  • the drop head (12) at the end of Lhe formwork carrier platform system (1) is supported on the suspension head (6) located on the lower floor by means of the stoppers and the rail (8) is pulled to the upper floor by sliding through this mechanism.
  • the crane is connected to the suspension member (2) to lift the formwork carrier platform system (l).
  • the drop head (12) within the main system is pulled to the upper floor tlirough the rail (8).
  • the drop head (12) hits the suspension head (6), it rotates clockwise at the center of the pin where it is connected to the main system, disengages from the suspension head (6) and rises above the same, it switches to horizontal position due to its non-symmetrical center of gravity, the fitting opening at the end thereof fits into the suspension head (6).
  • the main system abuts on the suspension head (6) and it is thus supported.
  • the rail (8) and the main system are carried to an upper floor without getting disengaged from each other.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Warehouses Or Storage Devices (AREA)

Abstract

The present invention relates to a formwork carrier platform which enables carrying formworks used in reinforced concrete construction to an upper application environment.

Description

FORMWORK CARRIER PLATFORM SYSTEM
Field of the Invention
The present invention relates to a formwork carrier platform which enables carrying formworks used in reinforced concrete construction to an upper application environment.
Background of the Invention
Formwork carrier climbing platform systems known in the art basically comprise carrier anchorages fastened to the holes provided in the concrete, and rings and apparatuses that connect to the said anchorages after disengaging from the formwork concrete. The system is carried from a lower floor to an upper floor via a crane. After connecting ropes to the lifting apparatuses provided on the system, the system is lifted from the anchorage it is located and it is placed on the upper floor. During this operation, the system becomes free as soon as it is disengaged from the anchorage on which it was located. It is carried freely to the upper
• - anchorage and suspended. When the system is moved to the upper floor by means of the crane, uncontrollable environmental factors gain importance. In this type of formwork systems employed especially in high buildings, the wind load can make it difficult to control the system during carrying. For the system to be suspended to the anchorage on the upper floor, assistance of the employees located on the system is required. It is dangerous to have a person on a suspended system during carrying with a. crane.
The USA patent application No. US42882V7, an applicaliυn within the state of the art, discloses a formwork carrier system movable with a work platform. Summary of the Invention
The objective of the present invention is to realize separation of a form work carrier platform system from the wall concrete to which it is connected to, during carrying the same to an upper floor, without having any employee on the system and such that it will not be affected by the external factors such as wind.
Detailed Description of the Invention
The formwork carrier platform system realized to fulfill the objective of the present invention is illustrated in Figure 1.
Figure 1 is the perspective view of the formwork carrier platform system.
The parts shown in the figures are each given reference numerals as follows:
1. Formwork carrier platform system
2. Suspension member
3. Formwork back profiles 4. Prop
5. Prop moving mechanism
6. Suspension heads
7. Upper platform
8. Rail 9. Triangular leg
10. Leg wheels
11. Lower platform
12. Drop head
The inventive formwork carrier platform system (1) essentially comprises at least one suspension member (2) required for carrying the said system, at least one form work back profile (3) which carries the concrete form work piece and also supports the concrete, at least one prop (4) which connects the formwork back profiles (3) to the prop moving mechanism (5), at least one suspension head (6) mounted to the anchorages provided on the concrete, at least one upper platform (7) which provides a working area on the formwork carrier platform system (1), at least one rail (8) on which the formwork carrier platform system (1) moves, at least one triangular leg (9) located between the upper platform (7) and the rail (8), at least one leg wheel (10) which enables movement on the rail (8) and also provides support to the concrete, at least one lower platform (11) located at the lowermost part of the formwork carrier platform system (1) and at least one drop head (12) which performs locking and which is supported on the suspension head.
In this invention, suspension head (6), rail (8) and the drop head (12) at the end of the main system work one within the other. Thanks to this mechanism with parts operating one within the other, the formwork carrier -platform system (1) can be carried to an upper floor in a safe and controllable manner without getting disengaged from the rail (8).
Before pouring of the concrete, anchorages which will be provided on the concrete are arranged on the surface of the formwork. The formworks are closed and the concrete is poured. Upon expiration of the setting time, the formworks are opened and it is started to carry the system to the upper floor. New suspension heads (12) are mounted at the upper floor to the anchorages provided at the new concrete. First of all, the rails (8) are pulled to the upper floor by means of the crane. During this pulling operation, the drop head (12) at the end of Lhe formwork carrier platform system (1) is supported on the suspension head (6) located on the lower floor by means of the stoppers and the rail (8) is pulled to the upper floor by sliding through this mechanism. Afterwards, the crane is connected to the suspension member (2) to lift the formwork carrier platform system (l).This time, the drop head (12) within the main system is pulled to the upper floor tlirough the rail (8). When the drop head (12) hits the suspension head (6), it rotates clockwise at the center of the pin where it is connected to the main system, disengages from the suspension head (6) and rises above the same, it switches to horizontal position due to its non-symmetrical center of gravity, the fitting opening at the end thereof fits into the suspension head (6). As soon as it fits in, the main system abuts on the suspension head (6) and it is thus supported. Thus the rail (8) and the main system are carried to an upper floor without getting disengaged from each other.
These kinds of formwork systems are generally used in high buildings. High buildings are especially exposed to wind loads as external factors. In free formwork systems which are climbed/raised without being connected to a rail, the wind load causes the system to turn and oscillate in the air in an uncontrollable manner.
It is a very difficult and dangerous process to align and mount a formwork system, which is connected to a crane and suspended in the air, to a suspension head located in the upper floor. In order to perform this operation at a construction site, the system is usually tried to be controlled by having an employee located on the formwork. However in the present invention, since the system does not disengage from the rail, there is no need for a human power or assistance on the platform during the operation of pulling upwards and suspending. This makes the system reliable and easy to apply.

Claims

1. A formwork carrier platform system (1) essentially comprising at least one suspension member
(2) required for carrying a formwork carrier platform system (1), at least one formwork back profile
(3) which carries the concrete formwork piece and also supports the concrete, at least one prop
(4) which connects the formwork back profiles (3) to the prop moving mechanism
(5), at least one suspension head
(6) mounted to the anchorages provided on the concrete, at least one upper platform
(7) which provides a working area on the formwork carrier platform system (1), at least one rail
(8) on which the formwork carrier platform system (1) moves, at least one triangular leg (9) located between the upper platform (7) and the rail (8), at least one leg wheel (10) which enables movement on the rail (8) and also provides support to the concrete, at least one lower platform (11) located at the lowermost part of the formwork carrier platform system (1) and characterized by at least one drop head (12) which performs locking and which is supported on the suspension head.
PCT/IB2008/052691 2007-07-06 2008-07-04 Formwork carrier platform system Ceased WO2009007889A2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
TR2007/04739A TR200704739A2 (en) 2007-07-06 2007-07-06 A formwork platform system
TR2007/04739 2007-07-06

Publications (2)

Publication Number Publication Date
WO2009007889A2 true WO2009007889A2 (en) 2009-01-15
WO2009007889A3 WO2009007889A3 (en) 2009-03-05

Family

ID=40032419

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/IB2008/052691 Ceased WO2009007889A2 (en) 2007-07-06 2008-07-04 Formwork carrier platform system

Country Status (2)

Country Link
TR (1) TR200704739A2 (en)
WO (1) WO2009007889A2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130082505A1 (en) * 2010-08-10 2013-04-04 Ass-Einrichtungssysteme Gmbh Seating furniture
CN109025258A (en) * 2018-07-04 2018-12-18 中国建筑第八工程局有限公司 Template movement device and its construction method for creeping formwork

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3844977C2 (en) * 1988-12-14 1997-10-23 Peri Werk Schwoerer Kg Artur Stepping moving platform on building wall
DE4302197A1 (en) * 1993-01-27 1994-07-28 Peri Gmbh Climbing device, in particular for a climbing frame
US6557817B2 (en) * 2000-01-18 2003-05-06 Wilian Holding Company Wall climbing form hoist
AU2003282129A1 (en) * 2003-11-27 2005-06-24 Ulma C Y E, S. Coop. Rigging system for formwork, scaffolding or moving loads in general

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130082505A1 (en) * 2010-08-10 2013-04-04 Ass-Einrichtungssysteme Gmbh Seating furniture
US8757725B2 (en) * 2010-08-10 2014-06-24 Ass-Einrichtungssysteme Gmbh Seating furniture
CN109025258A (en) * 2018-07-04 2018-12-18 中国建筑第八工程局有限公司 Template movement device and its construction method for creeping formwork
CN109025258B (en) * 2018-07-04 2021-08-10 中国建筑第八工程局有限公司 Formwork moving device for creeping formwork and construction method thereof

Also Published As

Publication number Publication date
WO2009007889A3 (en) 2009-03-05
TR200704739A2 (en) 2009-01-21

Similar Documents

Publication Publication Date Title
CN113994059B (en) Assembly of climbing rail and climbing lifting rail for rail-guided climbing systems
US10435896B2 (en) Apparatus and method for lifting and sliding a structure attached to the wall
CN102587645B (en) Climbing supporting mechanism having expansion and automatic meshing functions, and construction method thereof
CN113167072B (en) Construction site equipment with climbing formwork and hoist systems
PH12015502857B1 (en) Fall prevention device for a platform
US10914083B2 (en) Wall-climbing concrete form lifting system
CN102777030A (en) Method for building up formwork construction platform of lift shaft
CN209052240U (en) A kind of tool for super high-rise building duplex elevator vertical transport
EP2412894B1 (en) A climbing screen support system
WO2012056435A1 (en) Telescopic tower crane and scaffold
CN108708542A (en) Feasible walking aerial working suspension platform and construction method for anti-collision wall construction
CN102733608B (en) Construction method for spray head layer of granulation tower
CN109184190A (en) It climbs and carries integrated beam type hydraulic climbing platform and its installation method
KR20090020246A (en) Freestanding auto climbing system and method using the same
CN208122245U (en) Truss operating platform suitable for large space construction
WO2009007889A2 (en) Formwork carrier platform system
CN102168484A (en) External hanging scaffold and application method thereof
WO2011010178A1 (en) Carrier head with bolt mechanism for ram actuated climbing systems
CN103922231B (en) The method of climbing of high-rise building Inner climbing tower machine
CN107268971B (en) A double self-elevating external climbing frame of a super high-rise building and its application method
CN203247829U (en) Movable slope construction platform for working at heights
CN216157124U (en) High altitude faces limit post construction operating means
CN112554074A (en) Self-climbing type installation system of steel cable tower
CN207684735U (en) It covers and wears installation guide frame into formula double flange bolt is blind
CN220432195U (en) Ladder type device for dismounting anti-falling device of elevator

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 08789189

Country of ref document: EP

Kind code of ref document: A2

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 08789189

Country of ref document: EP

Kind code of ref document: A2