WO2007121536A1 - Contrôle de pression dans un procédé de fusion directe - Google Patents

Contrôle de pression dans un procédé de fusion directe Download PDF

Info

Publication number
WO2007121536A1
WO2007121536A1 PCT/AU2007/000542 AU2007000542W WO2007121536A1 WO 2007121536 A1 WO2007121536 A1 WO 2007121536A1 AU 2007000542 W AU2007000542 W AU 2007000542W WO 2007121536 A1 WO2007121536 A1 WO 2007121536A1
Authority
WO
WIPO (PCT)
Prior art keywords
gas
direct smelting
vessel
idle
operating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/AU2007/000542
Other languages
English (en)
Inventor
Neil John Goodman
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Technological Resources Pty Ltd
Original Assignee
Technological Resources Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2006902130A external-priority patent/AU2006902130A0/en
Application filed by Technological Resources Pty Ltd filed Critical Technological Resources Pty Ltd
Priority to US12/298,349 priority Critical patent/US20100011908A1/en
Priority to CN2007800226472A priority patent/CN101473050B/zh
Publication of WO2007121536A1 publication Critical patent/WO2007121536A1/fr
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D17/00Arrangements for using waste heat; Arrangements for using, or disposing of, waste gases
    • F27D17/10Arrangements for using waste heat
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B13/00Making spongy iron or liquid steel, by direct processes
    • C21B13/0006Making spongy iron or liquid steel, by direct processes obtaining iron or steel in a molten state
    • C21B13/0013Making spongy iron or liquid steel, by direct processes obtaining iron or steel in a molten state introduction of iron oxide into a bath of molten iron containing a carbon reductant
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B13/00Making spongy iron or liquid steel, by direct processes
    • C21B13/0073Selection or treatment of the reducing gases
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B13/00Making spongy iron or liquid steel, by direct processes
    • C21B13/14Multi-stage processes processes carried out in different vessels or furnaces
    • C21B13/143Injection of partially reduced ore into a molten bath
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/56Manufacture of steel by other methods
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27BFURNACES, KILNS, OVENS OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
    • F27B3/00Hearth-type furnaces, e.g. of reverberatory type; Electric arc furnaces ; Tank furnaces
    • F27B3/10Details, accessories or equipment, e.g. dust-collectors, specially adapted for hearth-type furnaces
    • F27B3/22Arrangements of air or gas supply devices
    • F27B3/225Oxygen blowing
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27BFURNACES, KILNS, OVENS OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
    • F27B3/00Hearth-type furnaces, e.g. of reverberatory type; Electric arc furnaces ; Tank furnaces
    • F27B3/10Details, accessories or equipment, e.g. dust-collectors, specially adapted for hearth-type furnaces
    • F27B3/26Arrangements of heat-exchange apparatus
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D19/00Arrangements of controlling devices
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B2100/00Handling of exhaust gases produced during the manufacture of iron or steel
    • C21B2100/40Gas purification of exhaust gases to be recirculated or used in other metallurgical processes
    • C21B2100/44Removing particles, e.g. by scrubbing, dedusting
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B2100/00Handling of exhaust gases produced during the manufacture of iron or steel
    • C21B2100/60Process control or energy utilisation in the manufacture of iron or steel
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B2100/00Handling of exhaust gases produced during the manufacture of iron or steel
    • C21B2100/60Process control or energy utilisation in the manufacture of iron or steel
    • C21B2100/64Controlling the physical properties of the gas, e.g. pressure or temperature
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B2100/00Handling of exhaust gases produced during the manufacture of iron or steel
    • C21B2100/60Process control or energy utilisation in the manufacture of iron or steel
    • C21B2100/66Heat exchange
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C2100/00Exhaust gas
    • C21C2100/02Treatment of the exhaust gas
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C2100/00Exhaust gas
    • C21C2100/06Energy from waste gas used in other processes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/10Reduction of greenhouse gas [GHG] emissions
    • Y02P10/134Reduction of greenhouse gas [GHG] emissions by avoiding CO2, e.g. using hydrogen

Definitions

  • the present invention relates to a molten bath- based direct smelting process and plant for producing molten metal in a direct smelting vessel.
  • the present invention relates to controlling pressure in a direct smelting vessel .
  • the present invention relates particularly, although by no means exclusively, to molten bath-based direct smelting processes for producing molten iron from iron-containing metalliferous feed material, such as iron ores, partly reduced iron ores and iron-containing waste streams (for example, from steelmaking plants) .
  • a known molten bath-based direct smelting process is generally referred to as the HIsmelt process .
  • the HIsmelt process includes the steps of:
  • a metalliferous feed material typically iron ore in the form of fines
  • a solid carbonaceous material typically coal, which acts as a reductant of the metalliferous feed material and a source of energy
  • melting is herein understood to mean thermal processing wherein chemical reactions that reduce metal oxides take place to produce molten metal .
  • metalliferous feed material and solid carbonaceous material are injected into the molten bath through a number of lances/tuyeres which are inclined to the vertical so as to extend downwardly and inwardly through the side wall of the direct smelting vessel and into a lower region of the vessel so as to deliver at least part of the solids material into the metal layer in the bottom of the vessel.
  • a blast of hot oxygen- containing gas is injected into an upper region of the vessel through a downwardly extending lance to cause post-combustion of reaction gases released from the molten bath in the upper region of the vessel.
  • the hot air or oxygen-enriched air is at a temperature of the order of 1200°C and is generated in hot blast stoves .
  • Off-gases resulting from the post-combustion of reaction gases in the vessel are taken away from the upper region of the vessel through an off-gas duct.
  • the vessel includes refractory-lined water cooled panels in the side wall and the roof of the vessel, and water is circulated continuously through the panels in a continuous circuit.
  • the HIsmelt process enables large quantities of molten iron, typically at least 0.5 Mt/a, to be produced by direct smelting in a single compact vessel.
  • HIsmelt plant that includes (a) a pressurised direct smelting vessel and ancillary equipment such as lock hoppers for supplying solid feed materials to the vessel and pressure control equipment on the off-gas duct of the vessel, (b) stoves that produce the high flow rate of hot air or oxygen-enriched air for the vessel, and ( ⁇ ) off-gas treatment equipment that is capable of processing large quantities of off-gas discharged from the vessel.
  • One HIsmelt process flowsheet currently proposed is designed to operate in a number of ⁇ states" that have different operating conditions during a smelting campaign, including by way of example the following process states:
  • hot metal production i.e. supplying pretreated metalliferous feed material such as hot ore, solid carbonaceous material such as coal, and hot blast air;
  • the volumetric flow rates of off-gas produced in the direct smelting vessel in the above process states are different.
  • the flow rate of off-gas is relatively high during a hot metal production state and relatively low during an idle state.
  • the present invention provides a process for direct smelting metalliferous feed material in a direct smelting vessel and producing process outputs of molten metal, molten slag, and an off-gas from the vessel that includes controlling pressure in the direct smelting vessel by controlling off-gas pressure in an off-gas stream supplied to a fluidised bed pretreatment apparatus while the process is operating in the "hold" and "idle” process states described above.
  • the present invention provides a process for direct smelting metalliferous feed material in a direct smelting vessel that forms part of a direct smelting plant and producing process outputs of molten metal, molten slag, and an off-gas from the vessel in a "hot metal production" state of the process , which process includes :
  • the process includes controlling the pressure in the direct smelting vessel whilst operating in the "hot metal production” state by controlling the flow of off-gas in the other off-gas stream supplied to the plant for use as a fuel gas .
  • the present invention is based on the realisation that pressure control in the "hold” and “idle” process states is best achieved by controlling the off-gas pressure in the off-gas stream supplied to the fluidised bed pretreatment apparatus .
  • the present invention is also based on the realisation that pressure control during the "hot metal production” state is best achieved through an alternate off-gas stream to the one supplied to the fluidised bed pre-treatment apparatus .
  • the process includes supplying at least one stream of off-gas as a fuel gas to at least one of (i) a waste heat recovery unit for generating steam for use in the process and (ii) stoves for producing a hot blast of air for use in the process.
  • the "hold" state comprises supplying a hot blast of air or oxygen-enriched air, solid carbonaceous material and fluxes to the direct smelting vessel without supply of metalliferous material.
  • the "idle” state comprises supplying a hot blast of air or oxygen-enriched air to the direct smelting vessel without supply of metalliferous material and solid carbonaceous material.
  • the process includes cooling and removing particulate material and soluble gaseous species and metal vapours from the off-gas stream supplied to the fluidised bed pretreatment apparatus in a water scrubber downstream of the pretreatment apparatus .
  • step (d) includes controlling pressure in the direct smelting vessel while the process is operating in the "hold” and “idle” process states by controlling the flow of off-gas flowing through the scrubber described in the preceding paragraph, hereinafter referred to as "the pressure control scrubber", by opening or closing an off-gas control valve in the scrubber.
  • step (c) includes supplying at least substantially all of the off-gas stream released from the direct smelting vessel as the off-gas stream to the fluidised bed pretreatment apparatus and thereby minimising any splitting of off-gas while the process is operating in the "hold” and "idle” process states.
  • the process includes supplying another fuel gas , such as natural gas , to the stoves for generating the hot blast of air or oxygen-enriched air for the process while the process is operating in the "hold” and "idle” process states.
  • another fuel gas such as natural gas
  • the process includes cooling and removing particulate material and soluble gaseous species and metal vapours from the other off-gas stream in a water scrubber upstream of the stoves and the waste heat recovery apparatus when the process is operating in the "hot metal production” state .
  • the scrubber described in the preceding paragraph includes an off-gas flow control valve.
  • the process includes at least substantially closing the valve in the stream scrubber described in the two preceding paragraph at the commencement of the "hold” and "idle” process states.
  • the process includes supplying off-gas from the pretreatment apparatus to the waste heat recovery apparatus for use as the fuel gas for generating steam for the process .
  • the process includes recycling a portion of the off-gas stream supplied to the fluidised bed pretreatment apparatus within the pretreatment apparatus during the "hold” and "idle” process states .
  • the process includes supplying the hot blast of air or oxygen-enriched air to the direct smelting vessel at a first volumetric flow rate while the process is operating in the "hot metal production” state and at a second lower volumetric flow rate while the process is operating in the "hold” and the “idle” process states.
  • the process includes controlling the pressure in the direct smelting vessel to a first pressure set point while the process is operating in the "hot metal production” state and to a lower pressure set point while the process is operating in the "hold” and "idle” process states .
  • the process includes monitoring the molten metal temperature in the direct smelting vessel during the "idle” process state and supplying a fuel gas to the vessel and combusting the fuel gas in the vessel as required to maintain the molten metal temperature in the vessel .
  • the process includes reducing the level of molten slag in the direct smelting vessel while the process is operating in the "idle” state and the process is combusting the fuel gas in the vessel.
  • the present invention also provides a process for operating a direct smelting plant with a direct smelting vessel that operates under pressure and a fluidised bed pre-treatment unit for pre-treating metalliferous material subsequently fed to the direct smelting vessel, the plant producing outputs of molten metal, molten slag, and off-gas wherein the process includes :
  • process states including a "hot metal production” state wherein metalliferous feed material is smelted in the vessel to produce molten metal, and "hold” and “idle” states wherein a bath of molten material is maintained in the direct smelting vessel in a molten state without additional molten metal being produced;
  • the present invention also provides a direct smelting plant for direct smelting a metalliferous feed material and producing molten metal that includes :
  • a direct smelting vessel for producing molten metal by way of a process for direct smelting preheated metalliferous feed material in the vessel, the process including a number of process states including "start-up”, “hot metal production”, “hold”, “idle”, and “off-wind”, as described herein;
  • the present invention provides a direct smelting plant for direct smelting a metalliferous feed material and producing molten metal that includes :
  • a direct smelting vessel for producing molten metal by way of a process for direct smelting preheated metalliferous feed material in the vessel, the process including a number of process states including "start-up”, “hot metal production”, “hold”, “idle”, and “off-wind”, as described above;
  • an off-gas duct for taking away off-gas generated in the direct smelting vessel and splitting the off-gas into two off-gas streams, one of which is supplied by way of a first duct section to the pretreatment apparatus and the other of which is supplied to a second duct section;
  • the process controller is also capable of controlling pressure in the direct smelting vessel by controlling off-gas pressure in the off-gas stream supplied to the second duct section while the process is operating in the "hot metal production” state, as described above.
  • Figure 1 is a diagrammatic view of one embodiment of a direct smelting plant in accordance with the present invention .
  • Figure 2 is an enlarged view of the wet cone scrubber and off-gas cooler in the off-gas stream that supplies off-gas to the waste heat recovery unit and the stoves shown in Figure 1.
  • the process is based on the use of a direct smelting vessel 3.
  • the vessel 3 is of the type described in detail in International applications PCT/AU2004/000472 and PCT/AU2004/000473 in the name of the applicant. The disclosure in the patent specifications lodged with these applications is incorporated herein by cross-reference .
  • the vessel 3 has a hearth that incudes a base and sides formed from refractory bricks, side walls which form a generally cylindrical barrel extending upwardly from the sides of the hearth and include an upper barrel section and a lower barrel section, a roof, an off-gas duct 9 in an upper section of the vessel 3, a forehearth 67 for discharging molten metal continuously from the vessel 3, and a tap hole for discharging molten slag periodically from the vessel 3.
  • the vessel 3 is fitted with a downwardly extending water-cooled hot air blast ("HAB") lance 7 extending into a top space of the vessel 3 and eight water- cooled solids injection lances 5 extending downwardly and inwardly through a side wall and into the slag.
  • HAB water-cooled hot air blast
  • the vessel 3 contains a molten iron bath.
  • Iron-containing feed material such as iron ore fines, iron-bearing steel plant wastes or DRI fines
  • coal and fluxes limestone and dolomite
  • one set of lances 5 is used for injecting iron-containing feed material and fluxes and another set of lances 5 is used for injecting coal and fluxes .
  • the lances 5 are water cooled to protect them from the high temperatures inside the vessel 3.
  • the lances 5 are typically lined with a high wear resistant material in order to protect them from abrasion by the gas/solids mixture being injected at high velocity.
  • Iron-containing feed material is pretreated by being preheated to a temperature in the range of 600-700 0 C and prereduced in a fluidised bed preheater 17 before being injected into the bath.
  • Coal and fluxes are stored in a series of lock hoppers 25 before being injected at ambient temperatures into the bath.
  • the coal is supplied to the lock hoppers 25 via a coal drying and milling plant 71.
  • the injected coal de-volatilises in the bath, thereby liberating H 2 and CO. These gases act as reductants and sources of energy.
  • the carbon in the coal is rapidly dissolved in the bath.
  • the dissolved carbon and the solid carbon also act as reductants, producing CO as a product of reduction.
  • the injected iron-containing feed material is smelted to molten iron in the bath and is discharged continuously via the forehearth 67. Molten slag produced in the process is discharged periodically via the slag tap hole (not shown) .
  • the typical reduction reactions involved in smelting injected iron-containing feed material to molten iron that occur in the bath are endothermic.
  • the energy required to sustain the process and, more particularly these endothermic reactions, is provided by reacting CO and H 2 released from the bath with oxygen-enriched air injected at high temperatures, typically 1200 0 C, into the vessel 3 via the HAB lance 7.
  • the hot, oxygen-enriched air injected into the vessel 3 via the HAB lance 7 is generated in hot blast stoves 11 by passing a stream of oxygen-enriched air (nominally containing 30 to 35% by volume O 2 ) through the stoves 11 and heating the air and thereafter transferring the hot oxygen-enriched air to the HAB lance 7 via a hot blast main 41.
  • a stream of oxygen-enriched air nominally containing 30 to 35% by volume O 2
  • the operation of the stoves 11 is coordinated to ensure that there is a continuous, uninterrupted flow of hot, oxygen-enriched air at a constant straight line temperature in the main 41 to the HAB lance 7.
  • Each stove 11 operates in accordance with a repeating sequence of phases that comprises a heating phase, a bottling phase, and a heat exchange phase that is a longer time period than the heating phase.
  • the stoves 11 are heated during heating phases of the stoves 11 by combusting (a) cooled and cleaned off-gas from the vessel 3 and/or (b) optionally another fuel gas such as natural gas, and (c) combustion air in burner assemblies (not shown) of the stoves 11 and thereafter passing the combustion products through the stoves 11.
  • oxygen from an oxygen plant 29 is mixed into streams of pressurised air generated by a blower 31. These oxygen- enriched air streams are passed through the stoves 11 and are heated in the stoves 11 and thereby produce the hot, oxygen-enriched pressurised air streams for the vessel 3. These hot, oxygen-enriched air streams are often referred to as "hot blast” or "hot air blast”.
  • the bottling phases of the stoves 11 are phases in which one of the stoves is essentially closed and is neither heated by combusted off-gas (and other fuel gas, such as natural gas) nor cooled by heat exchange with air streams .
  • the duration of the bottling phases of a given stove 11 is at least the amount of time required to open and close the valves necessary to change-over off-gas and hot air streams so as to switch over (a) the given stove from a heating phase to a heat exchange phase and (b) the other stove from a heat exchange phase to a heating phase.
  • FGD flue gas desulphurisation
  • combustion products released from the stoves 11 during heating phases of the stoves 11 may pass through heat exchangers (not shown) and preheat cooled and cleaned off- gas from the vessel 3 and combustion air before the heated off-gas and combustion air is supplied as feed materials to the burners of the stoves 11 during heating phases.
  • the vessel off-gas and combustion air may be preheated to a temperature of around 180°C.
  • Off-gas is released from the vessel 3 via the off-gas duct 9 in the upper section of the vessel 3 and passes initially through a radiation cooler, hereinafter referred to as an "off-gas hood", 15.
  • the off- gas leaves the vessel and enters the hood at a temperature of the order of 1450 0 C.
  • the off-gas is cooled as it passes through the off-gas hood 15 and thereby results in the generation of steam which accumulates in steam drum 35.
  • the off-gas hood may be of a type described in US patent 6,585,929 that cools and partially cleans off-gas .
  • the off-gas stream leaving the off-gas hood 15 is at a temperature of approximately 1000 0 C and is split into two streams.
  • the scrubber 21 quenches and removes particulate material and soluble gaseous species and metal vapours from off ⁇ gas flowing through the scrubber .
  • the off-gas temperature drop in the scrubber is from approximately 1000 0 C to below 100 0 C and typically between 65°C and 90 0 C.
  • the scrubber 21 includes an upper chamber 71, a lower chamber 73, and a vertically extending pipe 75 that interconnects the chambers 71, 73.
  • the scrubber 21 includes an off-gas flow control valve 77 in the lower end of the pipe 75.
  • the control valve 77 includes an hydraulically operated cone element 79 that can move vertically to open or close the lower end of the pipe 75.
  • the scrubber 21 includes water sprays 69 in the upper chamber 71 and further water sprays (not shown) positioned in relation to the pipe 75 and the control element 79. Re- circulating water within the scrubber and make-up water are supplied to the sprays .
  • the control valve 77 controls the flow rate of off-gas through the scrubber 21. This is the first variable flow rate constraint on off-gas from the vessel 3. Consequently, the control valve 77 controls the pressure in the direct smelting vessel 3, preferably to 0.8 bar gauge while the process is producing molten iron.
  • the off-gas from the scrubber 21 leaves the scrubber 21 via an outlet 81 in the lower chamber 73 and passes through an off-gas cooler 23 that further cools the off-gas to below 50 0 C, typically between 30 0 C and 45 0 C, to remove sufficient moisture from the off-gas for it to be used as a fuel gas .
  • the off-gas leaving the cooler has 5% or less H 2 O and a mist content of less than 10 mg/Nm 3 and typically 5.0 mg/Nm 3 .
  • the resulting off-gas is suitable for use as a fuel gas in (a) the stoves 11 (as described above) and (b) the WHR system 25.
  • the scrubbed and cooled off-gas is suitable for drying coal in the drying and milling plant 71.
  • the off-gas from the off- gas cooler 23 is split into three streams, with one stream being passed to the stoves 11, another stream being passed to the WHR system 25, and the third stream being passed to the drying and milling plant 71.
  • the off-gas stream from off-gas cooler 23 is a relatively rich off-gas .
  • the stream that is passed to the WHR system 25 is mixed with cooled and cleaned off-gas that has passed through the preheater 17 as described hereinafter, which is a relatively lean off-gas , due to some pre-reduction of the iron-containing feed material in the pre-heater by CO and H 2 in the off-gas .
  • the combined off-gas stream has a calorific value that makes it suitable for combustion as a fuel gas .
  • the combined off-gas stream, an additional source of fuel gas in the form of natural gas (indicated by the numeral 83 in Figure 1) , and air are supplied to and combusted in the WHR system 25.
  • the combined off-gas stream is combusted within the WHR system 25 in a manner that maximises CO destruction, while minimising NO x formation.
  • the off-gas released from the WHR system 25 is combined with off-gas gas from the stoves 11 and then passes to the FGD system 13. SO 2 is removed in the FGD system 23 and the exhaust gas is released to the atmosphere via a stack 45.
  • the other split stream which contains approximately 35-45% by volume of the off-gas stream, is passed through the fluidised bed preheater 17 for iron- containing feed material .
  • the preheater 17 removes moisture from and preheats and prereduces the iron- containing feed material.
  • the off-gas is a source of energy and a fluidising gas in the preheater 17.
  • a process controller of the plant controls the off-gas flow to the preheater 17 (a) to be above a minimum flow rate to maintain fluidising conditions in the preheater 17 and (b) to preheat iron-containing feed material to a substantially constant temperature, in the range of 600-700°C while the process is producing molten metal .
  • the off-gas released from the preheater 17 is passed through a cyclone 61 and entrained dust is separated from the off-gas .
  • the off-gas then passes through a wet cone scrubber 63 that removes particulate material and soluble gaseous species and metal vapours from the off-gas and cools the off-gas from between 500 0 C and 200 0 C to below 100 0 C and typically between 65 0 C and 90 0 C.
  • the scrubber 63 is the same basic construction as the wet cone scrubber 21 described above.
  • the scrubber 63 quenches and removes particulate material and soluble gaseous species and metal vapours from off-gas flowing through the scrubber.
  • the scrubber 63 includes an off-gas flow control valve that has an hydraulically operated cone element that can move vertically to open or close the valve and thereby control flow of off-gas through the scrubber .
  • the off-gas from the scrubber 63 then passes through an off-gas cooler 65 that further cools the off-gas to below 50 0 C, typically between 30 0 C and 45°C, to remove sufficient moisture from the off-gas for it to be used as a fuel gas .
  • the off-gas leaving the cooler has 5% or less H 2 O and a mist content of less than 10 mg/Nm 3 and typically 5.0 mg/Nm 3 .
  • the cooled and cleaned off-gas is then combined with a stream of off-gas from cooler 23 and used as a fuel gas in a waste heat recovery (WHR) system 25.
  • WHR waste heat recovery
  • the WHR system 25 includes:
  • heat exchange equipment such as superheat coils and a demineralised water economiser.
  • the WHR system 25 produces saturated steam.
  • the saturated steam is combined with the saturated steam from the steam drum 35 of the off-gas hood 15 and the superheat coils of the WHR system 25 generates superheated steam from the saturated steam.
  • the steam raising equipment of the WHR system 25 comprises :
  • a main evaporator section consisting of three modules of conve ⁇ tive coils ;
  • the steam raised in the WHR system 25 and the off-gas hood 15 is used to drive the HAB blower 31 and the main air compressor (not shown) of oxygen plant 29, with the remainder being passed through a turbo-alternator that generates electrical power required to operate the plant.
  • the turbo-generator system includes a condensing turbine designed to receive superheated steam.
  • the discharge from the turbine passes through a surface condenser operating at vacuum with the resultant condensate being pumped to the de-aerator via condensate pumps .
  • off-gas as a fuel gas within a plant offsets an amount of electrical power that would otherwise need to be obtained from an external electricity supply grid, which makes the plant generally self sufficient in terms of electrical power.
  • the burner assembly 37 of the WHR system 25 is a cylindrical carbon steel shell, with internal refractory and insulation .
  • the process is designed to operate in a number of
  • the calorific value of the off-gas can vary between being relatively lean and being relatively rich .
  • the calorific value depends on the feed rate of coal into the bath and the feed rate of hot air blast into the vessel 3. These parameters affect the level of carbon in the off-gas and the levels of CO and CO 2 in the off-gas .
  • the calorific value of the off-gas during an idle state is relatively low. Typically only hot air blast is supplied to the vessel 3 (along with nitrogen purge gas supplied through the solids injection lances 5) and so the off-gas has a composition similar to air.
  • a fuel gas such as natural gas
  • This fuel gas is combusted in the hot air blast. This assists with heating the vessel 3 and the molten bath .
  • the operators of the vessel may either tap slag to a minimum level or may even perform a slag drain.
  • a slag tap leaves a certain minimum level of slag in the vessel 3 whereas a slag drain removes substantially all of the slag from the vessel. Reducing the level of slag in the vessel 3 allows the metal to be heated directly by the combustion. Slag acts as an insulator in these circumstances and reduces the amount of heat seen by the metal .
  • the volumetric flow rates and calorific values of off-gas produced in the vessel 3 in the above process states are different.
  • the flow rate and calorific value of off-gas are relatively high during a hot metal production state and relatively low during an idle state .
  • volumetric flow rates and calorific values of off-gas produced in the vessel 3 during the course of a given process state are also different as a. consequence of variations in operating conditions .
  • the volumetric flow rate of fuel gas that is available for the WHR system 25 varies with the phases of the stoves 11.
  • the split off-gas stream to the WHR system 25 has a substantially higher flow rate when the stoves 11 are operating in the bottling phases of the stoves.
  • substantially lower amounts of off-gas are required by the stoves 11 during bottling phases of the stoves 11 than is required during heating phases of the stoves 11.
  • the steam (and electricity) requirements of the plant are different in different states of the process.
  • the steam (and electricity) requirements of the plant are typically of the order of 40- 60% higher during a hot metal production state than during a start-up state.
  • the fuel gas requirements of the stoves 11 are different in different states of the process. For example, larger amounts of fuel gas are required during a hot metal production state than during an idle state.
  • an alternative fuel gas such as natural gas (or other fuel gas other than off-gas)
  • an alternative fuel gas such as natural gas (or other fuel gas other than off-gas)
  • there is a need for varying flow rates of an alternative fuel gas, such as natural gas (or other fuel gas other than off-gas) to be supplied to the burner assembly 37 of the WHR system 25 in order to compensate for varying flow rates and calorific values of off-gas from the vessel 3 during a given state of the smelting campaign to meet the steam requirements of the plant.
  • the process controller of the plant operates the burner assembly 37 of the WHR system 25 with varying flow rates of natural gas as an additional fuel gas to provide required flow rates and calorific values of fuel gas at any point in the process.
  • the process controller of the plant operates the burner assembly 37 of the WHR system 25 with varying flow rates of air to combust the varying flow rates of off-gas and natural gas to ensure optimum combustion.
  • the process controller of the plant operates the burner assemblies of the stoves 11 with varying flow rates of natural gas as an additional fuel gas to provide required flow rates and calorific values of fuel gas at any point in the process .
  • the process controller of the plant operates the burner assemblies of the stoves 11 with varying flow rates of air to combust the varying flow rates of off-gas and natural gas to ensure optimum combustion.
  • the process controller of the plant commences ramping up the air flow rate to the burner assembly 37 of the WHR system 25 a predetermined time period, typically 30 seconds, before there is an increase in off-gas to the burner assembly 37 due to a decrease in demand for off-gas in the stoves 11.
  • the process controller of the plant commences ramping down the air flow rate to the burner assembly 37 of the WHR system 25 a predetermined time period, typically 30 seconds, before there is a decrease in off-gas to the burner assembly 37 due to an increase in demand for off-gas in the stoves 11.
  • the calorific value of off-gas at different points in the plant is an important parameter in determining the flow rates of natural gas required for the burner assembly 37 of the WHR system 25 and the burner assemblies of the stoves 11 at any point in time.
  • the plant includes mass spectrometers CVl, CV2 , and CV3 at selected locations of the plant to determine the calorific values of the off-gas at these locations .
  • the measured values of calorific values are processed by the process control for the plant as part of the process of determining required flow rates of off-gas and natural gas .
  • the selected locations are in the off-gas hood 15
  • the preheater 17 has certain minimum flow gas requirements in order to maintain the iron- containing feed material in a fluidised state. Gas flow through the preheater 17 is controlled by the control valve in the wet cone scrubber 63 that is downstream of the preheater 17.
  • vessel pressure control is via the control valve 77 of the wet cone scrubber 21 when the process is producing molten iron, i.e. when operating in a hot metal production state.
  • the plant includes a pressure sensor Pl in the off-gas hood 15 that monitors the pressure in off-gas flowing through the hood on a continuous basis .
  • the process controller of the plant is responsive to the monitored pressure and operates the control valve 77 of the wet cone scrubber 21 to adjust the pressure as required, preferably to maintain a constant vessel pressure, when the process is operating in a hot metal production state.
  • the time constant of the control circuit of the control valve 77 is considerably faster than the time constant of the control circuit of the control valve in the scrubber 63 downstream of the preheater 17. Hence, as between the control of pressure in the vessel 3 and the control of gas flow rate through the preheater 17, during the metal production state, the control of vessel pressure dominates.
  • control valve 77 of the wet cone scrubber 21 is at least substantially closed so that there is no or at most a minimal flow of off-gas through the scrubber 21 and thereafter to the stoves 11 and the WHR system 25 from this source. Consequently, the control valve in the wet cone scrubber 63 becomes the dominant pressure controller during the hold and idle states. This also ensures gas flow through the pre-heater so that the metalliferous material is maintained in a fluidised state.
  • the process controller operates to reduce the flow rate set point of hot air blast that is supplied to the vessel 3 from the stove 11.
  • the pressure set point of the vessel may also be reduced. Typically the set point is reduced from 0.8 bar gauge to 0.4 bar gauge.
  • a portion of the off-gas that has passed through the preheater 17 is recycled and combined with the off-gas from the vessel 3 so as to assist with maintaining fluidising conditions within the preheater 17.
  • the stoves 11 produce a reduced amount of hot air blast.
  • the total energy of the fuel gas supplied to the stoves 11 is reduced compared with the total energy of the fuel gas supplied to the stoves during hot metal production. In this way f the energy input to the stoves 11 is reduced during hold and idle states so as to match the reduced energy requirements of the reduced hot air blast flow.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Environmental & Geological Engineering (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

L'invention concerne un procédé de fusion directe de substances de base métallifères dans une cuve de fusion directe et de production permettant de produire du métal en fusion, du laitier en fusion, et des dégagements gazeux provenant de la cuve. Le procédé consiste à contrôler la pression dans la cuve de fusion directe grâce au contrôle de la pression des dégagements gazeux dans un flux de dégagement gazeux alimentant un appareil de pré-traitement à lit fluidisé lorsque le procédé est en phase« d'attente » ou « de ralenti».
PCT/AU2007/000542 2006-04-24 2007-04-24 Contrôle de pression dans un procédé de fusion directe Ceased WO2007121536A1 (fr)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US12/298,349 US20100011908A1 (en) 2006-04-24 2007-04-24 Pressure control in direct smelting process
CN2007800226472A CN101473050B (zh) 2006-04-24 2007-04-24 直接熔炼工艺中的压力控制

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AU2006902130 2006-04-24
AU2006902130A AU2006902130A0 (en) 2006-04-24 Off-gas processing in direct smelting process

Publications (1)

Publication Number Publication Date
WO2007121536A1 true WO2007121536A1 (fr) 2007-11-01

Family

ID=38624477

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/AU2007/000542 Ceased WO2007121536A1 (fr) 2006-04-24 2007-04-24 Contrôle de pression dans un procédé de fusion directe

Country Status (3)

Country Link
US (1) US20100011908A1 (fr)
CN (2) CN101473050B (fr)
WO (1) WO2007121536A1 (fr)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2616562B1 (fr) * 2010-09-15 2020-11-25 Tata Steel Limited Procédé de fusion directe
UA113295C2 (uk) 2011-12-06 2017-01-10 Текнолоджікал Рісорсес Пті. Лімітед Спосіб запуску процесу плавки
UA113296C2 (uk) * 2011-12-06 2017-01-10 Текнолоджікал Рісорсес Пті. Лімітед Спосіб запуску процесу плавки
JP5818704B2 (ja) * 2012-01-25 2015-11-18 三菱日立パワーシステムズ株式会社 ガス化炉、ガス化発電プラント
CN104870656B (zh) * 2012-11-12 2018-05-04 技术资源有限公司 一种两阶段熔炼工艺及设备
CN103409576B (zh) * 2013-08-14 2015-10-14 北京首钢国际工程技术有限公司 一种直接熔炼炉煤气能量回收和干法除尘工艺
CN103468847B (zh) * 2013-08-14 2015-04-15 北京首钢国际工程技术有限公司 铁浴法高温煤气余热余能利用和干法除尘工艺
CN107532223A (zh) * 2015-02-03 2018-01-02 技术资源有限公司 低热值废气的加工
US10787717B2 (en) * 2015-07-23 2020-09-29 Narong LIMASTIAN Method of utilizing furnace off-gas for reduction of iron oxide pellets
NL2023109B1 (en) 2019-05-10 2020-11-30 African Rainbow Minerals Ltd Process for the smelting of a metalliferous feedstock material
US20240279757A1 (en) * 2023-02-21 2024-08-22 Nucor Corporation Direct bath smelting process with fast quench of molten material in hot offgas

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4224109A (en) * 1977-04-07 1980-09-23 Bergwerksverband Gmbh Process and apparatus for the recovery of waste heat from a coke oven operation
SU1013490A1 (ru) * 1981-09-07 1983-04-23 Украинский Государственный Институт По Проектированию Металлургических Заводов Способ производства стали в кислородном конвертере
FR2576607A1 (fr) * 1985-01-25 1986-08-01 Montereau Acieries Procede de prechauffage de ferrailles et riblons
EP0541269A1 (fr) * 1991-11-06 1993-05-12 Li Wu Ebenfelt Procédé et installation pour la fabrication en continu d'acier au semi-acier
JPH0743081A (ja) * 1993-07-30 1995-02-10 Sumitomo Metal Mining Co Ltd 自熔炉の炉内圧の制御方法
WO2001011091A1 (fr) * 1999-08-05 2001-02-15 Technological Resources Pty Ltd Procede de fusion directe
US6402808B1 (en) * 1998-07-24 2002-06-11 Technological Resources Pty. Ltd. Direct smelting process
WO2005083130A1 (fr) * 2004-02-27 2005-09-09 Technological Resources Pty. Limited Usine et procede de fusion directe

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AUPQ083599A0 (en) * 1999-06-08 1999-07-01 Technological Resources Pty Limited Direct smelting vessel
AUPQ152299A0 (en) * 1999-07-09 1999-08-05 Technological Resources Pty Limited Start-up procedure for direct smelting process
AUPQ213099A0 (en) * 1999-08-10 1999-09-02 Technological Resources Pty Limited Pressure control
AUPQ346399A0 (en) * 1999-10-15 1999-11-11 Technological Resources Pty Limited Stable idle procedure
US6602321B2 (en) * 2000-09-26 2003-08-05 Technological Resources Pty. Ltd. Direct smelting process
US6519942B2 (en) * 2001-01-23 2003-02-18 Reginald Wintrell Systems and methods for harvesting energy from direct iron-making off gases

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4224109A (en) * 1977-04-07 1980-09-23 Bergwerksverband Gmbh Process and apparatus for the recovery of waste heat from a coke oven operation
SU1013490A1 (ru) * 1981-09-07 1983-04-23 Украинский Государственный Институт По Проектированию Металлургических Заводов Способ производства стали в кислородном конвертере
FR2576607A1 (fr) * 1985-01-25 1986-08-01 Montereau Acieries Procede de prechauffage de ferrailles et riblons
EP0541269A1 (fr) * 1991-11-06 1993-05-12 Li Wu Ebenfelt Procédé et installation pour la fabrication en continu d'acier au semi-acier
JPH0743081A (ja) * 1993-07-30 1995-02-10 Sumitomo Metal Mining Co Ltd 自熔炉の炉内圧の制御方法
US6402808B1 (en) * 1998-07-24 2002-06-11 Technological Resources Pty. Ltd. Direct smelting process
WO2001011091A1 (fr) * 1999-08-05 2001-02-15 Technological Resources Pty Ltd Procede de fusion directe
WO2005083130A1 (fr) * 2004-02-27 2005-09-09 Technological Resources Pty. Limited Usine et procede de fusion directe

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
DATABASE WPI Week 198409, Derwent World Patents Index; Class M24, AN 1984-054668 *
DATABASE WPI Week 198637, Derwent World Patents Index; Class M24, AN 1986-240393 *
DATABASE WPI Week 199516, Derwent World Patents Index; Class Q77, AN 1995-119325 *

Also Published As

Publication number Publication date
CN101473050B (zh) 2013-07-03
CN101473050A (zh) 2009-07-01
US20100011908A1 (en) 2010-01-21
CN103060503A (zh) 2013-04-24

Similar Documents

Publication Publication Date Title
US20100011908A1 (en) Pressure control in direct smelting process
US20090308205A1 (en) Direct smelting plant with waste heat recovery unit
EP1114194B1 (fr) Procede et appareil de fusion directe
US7976610B2 (en) Pressure control in direct smelting process
CN1926248B (zh) 直接熔炼设备及方法
CA2857684C (fr) Demarrage d'un processus de fusion
US7828873B2 (en) Forehearth
AU2005217667B2 (en) Direct smelting plant and process
AU2005215826B2 (en) Direct smelting plant and process
AU768255B2 (en) A direct smelting process and apparatus
AU2006239733B2 (en) Forehearth
GB2428428A (en) Methods of operating a zinc-producing blast furnace
NZ626933B2 (en) Starting a smelting process

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 200780022647.2

Country of ref document: CN

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 07718789

Country of ref document: EP

Kind code of ref document: A1

DPE1 Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101)
WWE Wipo information: entry into national phase

Ref document number: 8976/DELNP/2008

Country of ref document: IN

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 12298349

Country of ref document: US

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PRUSUANT TO RULE 112(1) EPC - EPO FORM 1205A OF 12.03.09

122 Ep: pct application non-entry in european phase

Ref document number: 07718789

Country of ref document: EP

Kind code of ref document: A1