WO2006030092A2 - Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing same - Google Patents
Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing same Download PDFInfo
- Publication number
- WO2006030092A2 WO2006030092A2 PCT/FR2005/002188 FR2005002188W WO2006030092A2 WO 2006030092 A2 WO2006030092 A2 WO 2006030092A2 FR 2005002188 W FR2005002188 W FR 2005002188W WO 2006030092 A2 WO2006030092 A2 WO 2006030092A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- anode
- measuring system
- replacement
- gripping member
- generator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- C—CHEMISTRY; METALLURGY
- C25—ELECTROLYTIC OR ELECTROPHORETIC PROCESSES; APPARATUS THEREFOR
- C25C—PROCESSES FOR THE ELECTROLYTIC PRODUCTION, RECOVERY OR REFINING OF METALS; APPARATUS THEREFOR
- C25C3/00—Electrolytic production, recovery or refining of metals by electrolysis of melts
- C25C3/06—Electrolytic production, recovery or refining of metals by electrolysis of melts of aluminium
-
- C—CHEMISTRY; METALLURGY
- C25—ELECTROLYTIC OR ELECTROPHORETIC PROCESSES; APPARATUS THEREFOR
- C25C—PROCESSES FOR THE ELECTROLYTIC PRODUCTION, RECOVERY OR REFINING OF METALS; APPARATUS THEREFOR
- C25C7/00—Constructional parts, or assemblies thereof, of cells; Servicing or operating of cells
- C25C7/06—Operating or servicing
Definitions
- the invention relates to the production of aluminum by igneous electrolysis according to the Hall-Héroult method. It relates more particularly to anode changes and service units intended to effect anode changes in aluminum production plants.
- Aluminum is produced industrially by igneous electrolysis in electrolysis cells according to the well-known Hall-Héroult process.
- French patent application FR 2 806 742 (corresponding to US Pat. No. 6,409,894) describes installations of an electrolysis plant intended for the production of aluminum.
- the electrolysis cells comprise a plurality of so-called "precooked" anodes of carbonaceous material which are consumed during the electrolytic reduction reactions of aluminum.
- the gradual consumption of the anodes requires interventions on the electrolysis cells, including, in particular, the replacement of the spent anodes with new anodes.
- the new anode In order to limit the disturbance of the operation of an electrolysis cell during an anode change, it is preferable to place the new anode so that its lower surface is at the same level as that of the other anodes of the anode. the cell. It is known to operate as follows to ensure a correct leveling of new anodes.
- the worn anode rod is marked with a chalk mark at a location corresponding to a specific mark on the anode frame.
- the spent anode is extracted from the cell and deposited on a reference surface, which is typically a metal tray.
- the level of the chalk line on the rod is raised, the spent anode is removed and a new anode is placed on the reference surface.
- a chalk line is drawn on the stem of the new anode at the raised level.
- the new anode is placed on the anode frame so that the chalk line is located at the determined mark on the anode frame.
- the anode handling tool with a position sensor.
- the distance traveled by the tool during the taking of the spent anode is measured, the worn anode is deposited on a reference surface and the distance traveled by the tool at the moment when the anode is measured. rests on the reference surface.
- the spent anode is removed, a new anode is deposited on the reference surface and the distance traveled by the tool is measured at the moment when the anode rests on the reference surface.
- the difference between the last two measured distances is added to the first measured distance in order to determine the distance to be traveled to the handling tool when positioning the new anode in the electrolysis cell.
- the subject of the invention is an anode changing method of an igneous electrolysis aluminum production cell comprising a plurality of anodes, said cell containing an electrolytic bath and comprising at least one cathode block, each anode comprising at least one minus an anode block and a metal rod and being removably attached to a movable metal frame by mechanical fixing means, each anode block having a reference surface, the method of replacing at least one spent anode determined by an anode of replacing using at least one anode handling tool comprising a positioning member, a gripping member and a vertical position sensor of the gripping member, and wherein the position sensor of the or each tool is used.
- anode handling for measuring the distances traveled vertically by the or each gripping member with respect to a reference level Nce, characterized in that at least one sound or electromagnetic wave beam is produced in a given axis or reference plane, and in that for each determined spent anode:
- a gripping member is placed in the gripping position of the metal rod of the spent anode and the vertical distance A traversed by the gripping member to reach said position is measured;
- the used anode is removed from the electrolysis cell, the anode block of this anode is passed through the said beam in a vertical movement and the vertical distance B traversed by the gripping member is measured at the moment when the surface reference of this anode passes through said beam;
- the metal rod of a replacement anode is grasped with the aid of a gripping member, the anode block of this anode is passed through the beam in a vertical movement and the vertical distance C traversed by the gripping member at the moment when the reference surface of this anode passes through said beam; the vertical position of the replacement anode in the cell is determined from the values obtained for said distances traveled A, B and C, and the replacement anode is placed at this position in the location initially occupied by the worn anode. 5
- the invention makes it possible to carry out the measurements necessary for the positioning of a replacement anode during the handling movements necessary for the replacement of an anode (namely typically the taking of an anode used on an electrolysis cell, the deposit worn anode on a pallet or a vehicle, taking
- the invention thus makes it possible to avoid, in particular, an extension of the opening time of an electrolysis cell.
- the beam or beams of sound or electromagnetic waves are advantageously placed beforehand at a place that allows the passage of a worn anode or a replacement anode through the beam (s) during the movements of the
- the measurement taken can be manual, that is to say, an operator records t data obtained at each process step, or automated in whole or in part, that is to say, a computerized device performs automatically all or part of the measurements.
- the invention also relates to a measuring system comprising a position sensor for measuring the vertical distances traveled by an anode gripping member, a sonic or electromagnetic wave beam generator, capable of producing at least one beam of sound or electromagnetic waves in a given axis or reference plane, at least one sound or electromagnetic wave detector capable of detecting the passage of a determined part of an anode through said beam and at least one positioning member to which is fixed said generator and / or said detector.
- the invention further relates to a service machine for anode change operations of a series of aluminum production cells by igneous electrolysis, said machine comprising at least one anode handling tool comprising an organ positioning device, a gripping member and a vertical position sensor of the gripping member, and being characterized in that it further comprises said measuring system.
- the invention also relates to a service unit of an igneous electrolysis aluminum production plant comprising a movable bridge and at least one
- Figure 1 illustrates, in section, a typical electrolysis room for the production of aluminum and comprising a service unit shown schematically.
- Figure 2 illustrates, in cross-sectional view, a typical electrolysis cell for the production of aluminum.
- Figure 3 shows, schematically, a service machine viewed from the side.
- FIGS 4 and 7 illustrate an embodiment of the anode changing method according to the invention.
- Electrolysis plants for aluminum production include a liquid aluminum production zone that includes one or more electrolysis rooms (1). As illustrated in Figure I 3 each electrolysis room (1) comprises electrolysis cells (2) and at least one service unit (4). Service units are often referred to as "electrolysis service machines" or “MSEs"("PTAs” or “Pot Tending Assemblies” or “PTMs” or “Pot Tending Machines” in English).
- MSEs electrolysis service machines
- the electrolysis cells (2) are normally arranged in rows or rows, each row or line typically having more than one hundred cells, and electrically connected in series by means of connecting conductors.
- the cells (2) are arranged in such a way as to clear the circulation paths (3) between the cells and along the electrolysis room (1).
- each electrolysis cell (2) comprises a tank (2 '), a support structure (35) called “superstructure” and a plurality of anodes (2O 5
- the tank (2 ') comprises a box (26) of steel, an inner lining (27,
- the anodes (20, 20 ') comprise at least one anode block (21, 21') of precured carbon material and a metal rod (22, 22 ').
- the anode blocks (21, 21 ') typically have a parallelepiped shape.
- anode block (s) 21, 21 '
- a fastener 22a, 22a 1
- multipode which is anchored in the (s) Anode block (s) (typically using cast iron).
- the anodes (20, 20 ') are removably attached to a movable metal frame (23), referred to as the "anode frame", by mechanical fastening means (24, 25) typically comprising
- An electrolysis cell (2) generally comprises a cowling system (36), typically comprising a series of cowls, for confining the effluents inside the cell, and means (not shown) for discharging effluents and wastewater. direct to a treatment center.
- cowling system typically comprising a series of cowls, for confining the effluents inside the cell, and means (not shown) for discharging effluents and wastewater. direct to a treatment center.
- the inner lining (27, 28) and the cathode blocks (29) form, inside the tank (2 '), a crucible adapted to contain the electrolyte bath (33) and a sheet of liquid metal (32). ) when the cell is in operation.
- a cover of alumina and solidified bath (34) covers the electrolyte bath and all or part of the anodes.
- the anodes (20, 20 '), and more precisely anode blocks (21, 21'), are partially immersed in the electrolyte bath (33), which contains dissolved alumina.
- the bottom surface (21a, 21a ') of the anodes is typically substantially planar and parallel to the top surface (29') of the cathode blocks (29), which is generally horizontal.
- the distance between the lower surface of the anodes and the upper surface of the cathode blocks, called “anode-cathode distance" is an important parameter in the regulation of the electrolysis cells.
- the anode-cathode distance is generally controlled with great precision.
- the anode blocks (21, 21 ') are gradually consumed in use. To compensate for this wear, it is common practice to gradually lower the anodes (20, 20 ') by moving the movable frame (23) downwards regularly. In addition, as illustrated in FIG. 2, the anode blocks (21, 21 ') are generally at different degrees of wear. Therefore, the position of the replacement anode (20 "), commonly referred to as” new anode ", relative to the movable frame (23) is generally adjusted at each anode change, more specifically, the position of the anodes is adjusted.
- the so-called “lower” surface (21a, 21a 1 , 21a ") of the anode blocks (21, 21 ', 21") that is to say the surface of the anode blocks which is intended to be immersed in the electrolytic bath (33) contained in the electrolysis cell (2) and to be parallel to the upper surface (29 ') of the cathode blocks (29).
- the replacement anode (20 ) is placed so that, after reaching its operating temperature, its lower surface (2Ia") is located at the lower surface (21a 1 ) of the worn anode (20 ') that it replaces.
- Said lower surface (21a, 21a ', 21a ") of the anode blocks (21, 21', 214) is generally substantially planar.
- the service unit (4) is used to carry out operations on the cells (2) such as the anode changes or the filling of the ground bath supply hoppers and the AlF 3 of the electrolysis cells. It can also be used to handle various loads, such as tank elements, pockets of liquid metal or anodes.
- the service unit (4) comprises a movable bridge (5) which can be translated over the electrolysis cells (2) and a service machine (6).
- the service machine (6) comprises a mobile carriage (7) and a service module (8) equipped with several handling and intervention devices (10), such as tools (shovels, keys, stitches, etc.). ).
- the service module (8) typically comprises a turret (8 ') mounted on the carriage (7) so as to be pivotable about a vertical axis V in use.
- the handling and intervention members (10) are typically attached to the turret.
- the service module (8) may also include a control cabin (16) for the operators.
- the movable bridge (5) rests and circulates on raceways (9, 9 ') arranged parallel to each other and to the main axis of the hall (and the queue of cells).
- the mobile bridge (5) can thus be moved along the electrolysis room (1).
- the movable carriage (7) can be moved along the movable bridge (5).
- the service machines (6) used for the anode changing operations are equipped with a set of tools (10), typically a picker (11a), a shovel bucket (12a), an anode gripping member (called “anode gripper”) (13a) and a hopper (14) provided with a retractable duct (15).
- a set of tools (10 typically a picker (11a), a shovel bucket (12a), an anode gripping member (called “anode gripper”) (13a) and a hopper (14) provided with a retractable duct (15).
- the piercer (l ia) serves to break the crust of alumina and bath solidified (34) which generally covers all or part of the anodes of the cell;
- the bucket shovel (12a) serves to clear the location of the anode, after removal of the spent anode, by removal of solids (such as pieces of crust and alumina) therein ;
- the anode clamp (13a) serves to grip and manipulate the anodes by their rod, in particular for the removal of spent anodes from an electrolysis cell and the placement of new anodes in the electrolysis cell;
- the retractable duct (15) is used to introduce alumina and / or ground bath in the electrolysis cell, so as to reform a coating layer, after the establishment of a new anode.
- the breaker (11a), the bucket shovel (12a) and the anode clamp (13a) are typically mounted at the lower end of a positioning member (Hb, 12b, 13b), such as a mast or a telescopic arm.
- a positioning member Hb, 12b, 13b
- the expression “anode handling tool” (13) denotes the assembly comprising an anode gripping member (13a) and a positioning member (13b).
- the service machine (6) comprises at least one anode handling tool (13) provided with a positioning member (13b), a gripping member (13a) and a vertical position sensor (13c) of the gripping member.
- the method of changing an anode of an electrolytic aluminum production cell (2) having a plurality of anodes (20, 20 ') typically comprises the following basic steps:
- a service machine is placed near the determined spent anode (20 ');
- the covers (36) are removed near the worn anode (20 '); the moving frame (23) to which the anodes (20, 20 ') are fixed;
- the metal rod of the spent anode (20 ') is grasped with the aid of an anode handling tool (13), and more precisely with the aid of a gripping member (13a);
- the used anode (20 ') is removed from the electrolysis cell by means of said handling tool (13);
- the used anode (20 ') is deposited in a determined location; - It takes a replacement anode (20 ") with a handling tool (13), usually the same tool that used to handle the used anode;
- the replacement anode (20 ) is fixed on the mobile frame (23) by means of a mechanical fixing means (24).
- a vertical position is determined for the replacement anode (20 ") by means of measurements made during the handling of the anodes, These measurements relate, firstly, to the position of the tool. anode handling and, secondly, the passage of the anodes through a given axis or a specific plane outside the electrolysis cell.To this end, on the one hand, we create an axis or a plane immaterial reference, delimited by sound or electromagnetic waves, and the passage of the anodes through this axis or this plane is detected by means of a sound or electromagnetic wave detection system.
- an anode handling tool (13) comprising a vertical position sensor (13c) of the gripper (13a), and measuring the movements of the gripper during the anode handling operations.
- the vertical position of the replacement anode from the measurements of movement of the gripping member at predetermined times, namely the taking of the spent anode, the passage of the spent anode through the determined axis or plane and the passage of the replacement anode through the axis or plane determined.
- At least one sonic or electromagnetic wave beam (51) is produced in a given axis or a determined reference plane (50) (FIG. 4);
- an anode handling tool (13) comprising a vertical position sensor (13c) of the gripping member (13a) at a determined spent anode (20 ') and placing a gripping member (13a) in the gripping position of the metal rod (22 ') of this anode (20') ( Figure 4); the metal rod (22 ') of a given spent anode (20') is grasped by means of the gripping member (13a) of an anode handling tool (13) and, at the using the position sensor, measuring a first vertical distance A traveled by the gripping member ( Figure 4); the mechanical fastener (24) of the spent anode (20 ') is defeated, the used anode (20') is removed from the electrolysis cell by means of said handling tool (13), the anode block (s) (21 ') of this anode through said beam in a vertical movement and, with the aid of said position sensor, measuring a second vertical distance B traveled by the member gripping at the moment when the reference surface (21a 1 ) of the
- the metal rod (22 ") of a replacement anode (20") is grasped by means of a gripping member (13a), the anode block (s) are passed through ( 21 ") of said anode through said beam in a vertical movement and, with the aid of said position sensor, measuring a third vertical distance C traversed by the gripping member at the moment when the reference surface (2Ia") anode passes through said beam ( Figure 6);
- the vertical position of the replacement anode (20 ") in the cell is determined from the values obtained for said first, second and third distances traveled (A, B and C), and the replacement anode is placed ( 20 ") at this vertical position in the location initially occupied by the spent anode (FIG.
- the replacement anode (20 ) is fixed on the mobile frame (23) by means of a mechanical fixing means (24).
- Said distance measurements can be made during normal operations of replacing worn anodes.
- the invention thus makes it possible to substantially limit the handling operations required to determine the position of the replacement anode.
- the same gripping member (13a) is used to handle a determined spent anode (20 ') and the replacement anode (20 ") intended to replace it.
- This variant makes it possible to avoid a calibration of the sensors. separate tools and differences in distance measurement inherent in the use of separate tools.
- the used anode (20 ') is deposited in a determined location before the metal rod (22 ") of the replacement anode (20") is gripped with the gripping member (13a).
- Said first distance (A) can be measured before or after grasping the rod (22 ') of the spent anode (20'). This distance is preferably measured after grasping the rod (22 ') and after putting the handling tool (13) under mechanical tension, in order to make up for any mechanical play and improve the accuracy of the measurement.
- the reference surface (21a, 21a ', 21a ") of the anodes is preferably the so-called" lower "surface of the anode block (s) (21, 21', 21").
- said vertical distance B is preferably measured during a downward movement of a spent anode (20 '), typically during the deposition of the anode in the determined location, which is usually a pallet or a vehicle (40, 40 ') for its evacuation.
- said beam is disposed at a predetermined height above said determined location.
- said vertical distance C during an upward movement of a replacement anode (20 "), typically during the removal of the anode of a temporary storage place, which is usually a pallet or vehicle (40, 40 ") used for its supply.
- said beam is disposed at a predetermined height above said storage location.
- the vertical position of a replacement anode (20 ") corresponds to a vertical distance A 'traveled by the gripping member (13a) during the placement of the replacement anode in the location initially occupied by a
- a 'traveled by the gripping member 13a
- the worn anodes (20 ') are replaced one by one by replacement anodes (20 ").
- At least two worn anodes (20 ') are replaced at a time by replacement anodes (20 ")
- said distances A, B and C are measured.
- This embodiment of the invention is advantageously implemented by using a service machine (6) comprising a number of anode handling tools (13) at least equal to the number of worn anodes which are replaced simultaneously.
- the position sensor (13c) is used to measure the distance traveled vertically by the gripping member (13a) during handling of anodes.
- the distances are given with respect to a reference level N, which may be arbitrary.
- the reference level N is preferably the same for all the distance measurements during the same anode change in order to simplify the calculations and to avoid introducing uncertainties in the determination of the final position of the anode. of substitution.
- the position sensor (13c) may be, for example, a cable encoder or a laser range finder.
- the position sensor is advantageously integrated with the anode handling tool (13).
- the position sensor (13c) is rigidly attached to the fixed part of the positioning member (13b) of the anode handling tool (13); it makes it possible to measure the relative distance of a determined point integral with the gripping member.
- the position sensor can be attached to the sliding arm or telescopic mast which is fixed the gripping member.
- anode handling tool (13) with a means for measuring the tension in the tool, such as an axial dynamometer, which makes it possible to know the moment when the kinematic chain of the tool is in tension and to determine the moment when the mechanical games are all taken in the same direction.
- Said sound waves are typically ultrasonic waves.
- the electromagnetic waves are typically visible light, infrared or radio waves. It is advantageous to generate said beam (51) using a laser.
- the lower surface (21a, 21a ', 21a ") of the anodes, in particular worn anodes, may have irregularities resulting in particular from surface defects, irregular wear of the anodes or deposits of material (such as alumina) when using the anodes
- two or more (typically three) are preferably generated.
- This variant of the invention is typically implemented with the aid of a generator comprising two or more sources of sound or electromagnetic waves, that is to say that each beam (51) is generated by a source of distinct waves (in the case of electromagnetic waves, each source is typically a laser).
- the distances traveled (B and C) are advantageously given by the average of the distances traveled measured for each beam (after possibly eliminating one or more values deemed aberrant).
- Said determined axis or the determined reference plane (50) is preferably substantially horizontal.
- the angle between the horizontal and said determined reference axis or plane (50) is preferably less than about 10 °, and more preferably less than about 5 °.
- FIG. 8 there is a sound or electromagnetic wave detector (54) facing a sound or electromagnetic wave beam generator (52). ) so that the detector can detect the beam produced by the generator ( Figure 8a).
- the method according to the invention can be implemented using a measuring system comprising a position sensor (13c) for measuring the vertical distances traveled by a gripping member (13a) of a handling tool. 'anode
- a sound or electromagnetic wave beam generator capable of producing at least one sound or electromagnetic wave beam (51) in a given axis or reference plane (50), at least one sound or electromagnetic wave detector (54) adapted to detect the passage of a determined part (21a,
- the position sensor (13c) is preferably integrated with the anode handling tool
- the generator (52) typically includes a source for each sound or electromagnetic wave beam (52).
- the generator advantageously comprises at least one laser.
- the or each positioning member (53) of the measuring system is, directly or indirectly, attached to or placed on a traffic lane (3).
- the measurement system is integrated with a service unit (4) for anode change operations. This embodiment of the invention facilitates the movement and positioning of the measuring system. It also makes it possible to carry out the measurements necessary for the positioning of a replacement anode during normal handling movements of a used anode and a replacement anode.
- the measuring system according to the invention is preferably integrated in the service machine (6) of said service unit (4), and more preferably in the module (8) of said service machine (6).
- the vertical position sensor (13c) of the gripping member (13a) of the measuring system is typically that which is provided with the anode handling tool (13).
- the or each positioning member (53) of the measuring system is, directly or indirectly, fixed to a service unit (4), to a service machine (6) or to a service module (8) .
- the or each positioning member (53) of the measuring system is typically an arm or a telescopic mast.
- the generator (52) and / or the detector (54) are typically fixed in the lower part of the positioning member (53).
- the measurements of distance traveled can be carried out with or without the intervention of an operator.
- the detector may emit an electrical, light or sound signal when the determined reference surface of an anode passes through the said beam (s) and an operator can record the distance value traveled by the gripping member given by the sensor. position at the time of transmission of said signal. Determining the distance A 'corresponding to the position of the replacement anode can also be performed by an operator using the values obtained for the first, second and third distances traveled (A, B and C).
- the measurement of said distances (A, B, C, A ') is advantageously carried out wholly or partly in a computer manner.
- the passage of the reference surface (21a, 21a ', 21a ") of the anodes through said beam can electrically or electronically trigger the measurement of the position sensor and the recording of the corresponding distance.
- the measuring system advantageously comprises a device for recording the measurements made and for determining said vertical position of the replacement anode (20 ").
- the generator (52) and the detector (54) can be located on the same positioning member (53) or on separate positioning members.
- the generator (52) and detector (54) may optionally be integrated in the same device.
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Materials Engineering (AREA)
- Metallurgy (AREA)
- Organic Chemistry (AREA)
- Electrolytic Production Of Metals (AREA)
Abstract
Description
PROCÉDÉ DE CHANGEMENT D'ANODE DANS UNE CELLULE DE METHOD FOR CHANGING ANODE IN A CELL
PRODUCTION D'ALUMINIUM PAR ÉLECTROLYSE INCLUANT UNALUMINUM PRODUCTION BY ELECTROLYSIS INCLUDING
AJUSTEMENT DE LA POSITION DE L'ANODE ET DISPOSITIF POUR LEADJUSTING THE POSITION OF THE ANODE AND DEVICE FOR THE
METTRE EN OEUVREENFORCE
Domaine de l'inventionField of the invention
L'invention concerne la production d'aluminium par électrolyse ignée selon le procédé de Hall-Héroult. Elle concerne plus particulièrement les changements d'anode et les unités de service destinées à effectuer les changements d'anode dans les usines de production d'aluminium.The invention relates to the production of aluminum by igneous electrolysis according to the Hall-Héroult method. It relates more particularly to anode changes and service units intended to effect anode changes in aluminum production plants.
Etat de la techniqueState of the art
L'aluminium est produit industriellement par électrolyse ignée dans des cellules d'électrolyse suivant le procédé bien connu de Hall-Héroult. La demande de brevet français FR 2 806 742 (correspondant au brevet américain US 6 409 894) décrit des installations d'une usine d'électrolyse destinée à la production d'aluminium.Aluminum is produced industrially by igneous electrolysis in electrolysis cells according to the well-known Hall-Héroult process. French patent application FR 2 806 742 (corresponding to US Pat. No. 6,409,894) describes installations of an electrolysis plant intended for the production of aluminum.
Selon la technologie la plus répandue, les cellules d'électrolyse comportent une pluralité d'anodes dites "précuites" en matériau carboné qui sont consommées lors des réactions de réduction électrolytique de l'aluminium. La consommation progressive des anodes nécessite des interventions sur les cellules d'électrolyse parmi lesquelles figure, notamment, le remplacement des anodes usées par des anodes neuves.According to the most widespread technology, the electrolysis cells comprise a plurality of so-called "precooked" anodes of carbonaceous material which are consumed during the electrolytic reduction reactions of aluminum. The gradual consumption of the anodes requires interventions on the electrolysis cells, including, in particular, the replacement of the spent anodes with new anodes.
Afin de limiter la perturbation du fonctionnement d'une cellule d'électrolyse lors d'un changement d'anode, il est préférable de placer l'anode neuve de manière à ce que sa surface inférieure soit au même niveau que celle des autres anodes de la cellule. II est connu d'opérer comme suit pour assurer une mise à niveau correcte des anodes neuves. La tige de l'anode usée est marquée d'un trait de craie à un endroit correspondant à un repère déterminé sur le cadre anodique. L'anode usée est extraite de la cellule et déposée sur une surface de référence, qui est typiquement un plateau métallique. Le niveau du trait de craie sur la tige est relevé, l'anode usée est retirée et une anode neuve est placée sur la surface de référence. Un trait de craie est tracé sur la tige de l'anode neuve au niveau relevé. L'anode neuve est placée sur le cadre anodique de façon à ce que le trait de craie soit situé au niveau du repère déterminé sur le cadre anodique. Ces opérations, essentiellement manuelles, nécessitent l'intervention d'un opérateur dans la zone d'action des outils de manutention des anodes et l'exposent aux risques inhérents à ces opérations, tels que les risques de décrochement de la charge et les projections de métal liquide.In order to limit the disturbance of the operation of an electrolysis cell during an anode change, it is preferable to place the new anode so that its lower surface is at the same level as that of the other anodes of the anode. the cell. It is known to operate as follows to ensure a correct leveling of new anodes. The worn anode rod is marked with a chalk mark at a location corresponding to a specific mark on the anode frame. The spent anode is extracted from the cell and deposited on a reference surface, which is typically a metal tray. The level of the chalk line on the rod is raised, the spent anode is removed and a new anode is placed on the reference surface. A chalk line is drawn on the stem of the new anode at the raised level. The new anode is placed on the anode frame so that the chalk line is located at the determined mark on the anode frame. These operations, which are essentially manual, require the intervention of an operator in the action zone of the anode handling tools and expose him to the risks inherent to these operations, such as the risks of load shifting and the projections of liquid metal.
Il est également connu de munir l'outil de manutention des anodes d'un capteur de position. Dans ce cas, on mesure la distance parcourue par l'outil lors de la prise de l'anode usée, on dépose l'anode usée sur une surface de référence et on mesure la distance parcourue par l'outil au moment où l'anode repose sur la surface de référence. On retire l'anode usée, on dépose une anode neuve sur la surface de référence et on mesure la distance parcourue par l'outil au moment où l'anode repose sur la surface de référence. L'écart entre les deux dernières distances mesurées est ajouté à la première distance mesurée afin de déterminer la distance à faire parcourir à l'outil de manutention lors du positionnement de l'anode neuve dans la cellule d'électrolyse.It is also known to provide the anode handling tool with a position sensor. In this case, the distance traveled by the tool during the taking of the spent anode is measured, the worn anode is deposited on a reference surface and the distance traveled by the tool at the moment when the anode is measured. rests on the reference surface. The spent anode is removed, a new anode is deposited on the reference surface and the distance traveled by the tool is measured at the moment when the anode rests on the reference surface. The difference between the last two measured distances is added to the first measured distance in order to determine the distance to be traveled to the handling tool when positioning the new anode in the electrolysis cell.
Ces différentes façons de procéder nécessitent de multiples manipulations d'anode et le déplacement de la surface de référence d'une zone de travail à une autre. Le temps passé à ces opérations allonge considérablement les temps de cycle d'intervention sur les cellules d'électrolyse et la période de temps pendant laquelle les capots des cuves restent ouverts, ce qui réduit l'efficacité des moyens de captation des effiuents produits par les cellules d'électrolyse. La demanderesse a donc recherché une procédure et des moyens qui permettent d'éviter ces inconvénients.These different procedures require multiple anode manipulations and moving the reference surface from one work area to another. The time spent on these operations considerably extends the cycle times of intervention on the electrolysis cells and the period of time during which the hoods of the tanks remain open, which reduces the efficiency of the means of capturing the effiuents produced by the cells. electrolysis cells. The plaintiff has therefore sought a procedure and means to avoid these disadvantages.
Description de l'inventionDescription of the invention
L'invention a pour objet un procédé de changement d'anode d'une cellule de production d'aluminium par électrolyse ignée comportant une pluralité d'anodes, ladite cellule contenant un bain électrolytique et comprenant au moins un bloc cathodique, chaque anode comprenant au moins un bloc anodique et une tige métallique et étant fixée de manière amovible à un cadre métallique mobile par des moyens de fixation mécaniques, chaque bloc anodique possédant une surface de référence, procédé par lequel on remplace au moins une anode usée déterminée par une anode de remplacement en utilisant au moins un outil de manutention d'anode comprenant un organe de positionnement, un organe de préhension et un capteur de position verticale de l'organe de préhension, et dans lequel on utilise le capteur de position du ou de chaque outil de manutention d'anode pour mesurer les distances parcourues verticalement par le ou chaque organe de préhension par rapport à un niveau de référence N, caractérisé en ce qu'on produit au moins un faisceau d'ondes sonores ou électromagnétiques dans un axe ou un plan de référence déterminé, et en ce que, pour chaque anode usée déterminée :The subject of the invention is an anode changing method of an igneous electrolysis aluminum production cell comprising a plurality of anodes, said cell containing an electrolytic bath and comprising at least one cathode block, each anode comprising at least one minus an anode block and a metal rod and being removably attached to a movable metal frame by mechanical fixing means, each anode block having a reference surface, the method of replacing at least one spent anode determined by an anode of replacing using at least one anode handling tool comprising a positioning member, a gripping member and a vertical position sensor of the gripping member, and wherein the position sensor of the or each tool is used. anode handling for measuring the distances traveled vertically by the or each gripping member with respect to a reference level Nce, characterized in that at least one sound or electromagnetic wave beam is produced in a given axis or reference plane, and in that for each determined spent anode:
- on place un organe de préhension en position de saisie de la tige métallique de l'anode usée et on mesure la distance verticale A parcourue par l'organe de préhension pour atteindre ladite position ;a gripping member is placed in the gripping position of the metal rod of the spent anode and the vertical distance A traversed by the gripping member to reach said position is measured;
- on retire l'anode usée de la cellule d'électrolyse, on fait passer le bloc anodique de cette anode à travers ledit faisceau en un mouvement vertical et on mesure la distance verticale B parcourue par l'organe de préhension au moment où la surface de référence de cette anode traverse ledit faisceau ;the used anode is removed from the electrolysis cell, the anode block of this anode is passed through the said beam in a vertical movement and the vertical distance B traversed by the gripping member is measured at the moment when the surface reference of this anode passes through said beam;
- on saisit la tige métallique d'une anode de remplacement à l'aide d'un organe de préhension, on fait passer le bloc anodique de cette anode à travers ledit faisceau en un mouvement vertical et on mesure la distance verticale C parcourue par l'organe de préhension au moment où la surface de référence de cette anode traverse ledit faisceau ; - on détermine la position verticale de l'anode de remplacement dans la cellule à partir des valeurs obtenues pour lesdites distances parcourues A, B et C, et on place l'anode de remplacement à cette position dans l'emplacement initialement occupé par l'anode usée. 5the metal rod of a replacement anode is grasped with the aid of a gripping member, the anode block of this anode is passed through the beam in a vertical movement and the vertical distance C traversed by the gripping member at the moment when the reference surface of this anode passes through said beam; the vertical position of the replacement anode in the cell is determined from the values obtained for said distances traveled A, B and C, and the replacement anode is placed at this position in the location initially occupied by the worn anode. 5
L'invention permet d'effectuer les mesures nécessaires au positionnement d'une anode de remplacement lors des mouvements de manutention nécessaires au remplacement d'une anode (à savoir typiquement la prise d'une anode usée sur une cellule d'électrolyse, le dépôt de l'anode usée sur une palette ou un véhicule, la priseThe invention makes it possible to carry out the measurements necessary for the positioning of a replacement anode during the handling movements necessary for the replacement of an anode (namely typically the taking of an anode used on an electrolysis cell, the deposit worn anode on a pallet or a vehicle, taking
10 d'une anode de remplacement sur une palette ou un véhicule et la mise en place de l'anode de remplacement dans la cellule), ce ι qui présente l'avantage de ne pas nécessiter des mouvements de manutention supplémentaires. L'invention permet ainsi d'éviter, notamment, un allongement du temps d'ouverture d'une cellule d'électrolyse.10 an anode replacement on a pallet or a vehicle and the establishment of the replacement anode in the cell), ι which has the advantage of not requiring additional handling movements. The invention thus makes it possible to avoid, in particular, an extension of the opening time of an electrolysis cell.
1515
Le ou les faisceaux d'ondes sonores ou électromagnétiques sont avantageusement préalablement placés à un endroit qui permet le passage d'une anode usée ou d'une anode de remplacement au travers du ou des faisceaux lors des mouvements deThe beam or beams of sound or electromagnetic waves are advantageously placed beforehand at a place that allows the passage of a worn anode or a replacement anode through the beam (s) during the movements of the
" '*" "" "manutention ""normaux" "de" ces" "anddës,~~par "exemple" au-dessus "d'une" "cellule "*""" "Handling""normal" "of" these "" anddës, ~~ by "example" above "a" "cell
20 d'électrolyse, d'une palette ou d'un véhicule.20 electrolysis, a pallet or a vehicle.
Les prises de mesure peuvent être manuelles, c'est-à-dire qu'un opérateur enregistre t les données obtenues à chaque étape du procédé, ou automatisées en tout ou partie, c'est-à-dire qu'un appareil informatisé effectue de manière automatique tout ou partie 25 des mesures.The measurement taken can be manual, that is to say, an operator records t data obtained at each process step, or automated in whole or in part, that is to say, a computerized device performs automatically all or part of the measurements.
L'invention a aussi pour objet un système de mesure comprenant un capteur de position pour mesurer les distances verticales parcourues par un organe de préhension d'anode, un générateur de faisceau d'ondes sonores ou 30 électromagnétiques, apte à produire au moins un faisceau d'ondes sonores ou électromagnétiques dans un axe ou un plan de référence déterminé, au moins un détecteur d'ondes sonores ou électromagnétiques apte à détecter le passage d'une partie déterminée d'une anode à travers ledit faisceau et au moins un organe de positionnement auquel est fixé ledit générateur et/ou ledit détecteur.The invention also relates to a measuring system comprising a position sensor for measuring the vertical distances traveled by an anode gripping member, a sonic or electromagnetic wave beam generator, capable of producing at least one beam of sound or electromagnetic waves in a given axis or reference plane, at least one sound or electromagnetic wave detector capable of detecting the passage of a determined part of an anode through said beam and at least one positioning member to which is fixed said generator and / or said detector.
L'invention a encore pour objet une machine de service destinée aux opérations de changement d'anode d'une série de cellules de production d'aluminium par électrolyse ignée, ladite' machine comportant au moins un outil de manutention d'anode comprenant un organe de positionnement, un organe de préhension et un capteur de position verticale de l'organe de préhension, et étant caractérisée en ce qu'elle comporte en outre ledit système de mesure.The invention further relates to a service machine for anode change operations of a series of aluminum production cells by igneous electrolysis, said machine comprising at least one anode handling tool comprising an organ positioning device, a gripping member and a vertical position sensor of the gripping member, and being characterized in that it further comprises said measuring system.
L'invention a encore pour objet une unité de service d'une usine de production d'aluminium par électrolyse ignée comprenant un pont mobile et au moins uneThe invention also relates to a service unit of an igneous electrolysis aluminum production plant comprising a movable bridge and at least one
1 machine de service selon l'invention.1 service machine according to the invention.
L'invention est décrite plus en détail ci-après à l'aide des figures annexées.The invention is described in more detail below with the aid of the appended figures.
La figure 1 illustre, vue en section, une salle d'électrolyse typique destinée à la production d'aluminium et comprenant une unité de service représentée de manière schématique. "" " " * " ~" " """ " " " * * " " ~" Figure 1 illustrates, in section, a typical electrolysis room for the production of aluminum and comprising a service unit shown schematically. """" * " ~ """"""""**""~"
La figure 2 illustre, vue en section transversale, une cellule d'électrolyse typique destinée à la production d'aluminium.Figure 2 illustrates, in cross-sectional view, a typical electrolysis cell for the production of aluminum.
La figure 3 représente, de manière schématique, une machine de service vue de côté.Figure 3 shows, schematically, a service machine viewed from the side.
Les figures 4 et 7 illustrent un mode de réalisation du procédé de changement d'anode selon l'invention.Figures 4 and 7 illustrate an embodiment of the anode changing method according to the invention.
Les figures 8 à 10 représentent, de manière schématique, des modes de réalisation des moyens de détection de la position d'une anode selon l'invention. Les usines d'électrolyse destinées à la production d'aluminium comprennent une zone de production d'aluminium liquide qui comprend une ou plusieurs salles d'électrolyse (1). Tel qu'illustré à la figure I3 chaque salle d'électrolyse (1) comporte des cellules d'électrolyse (2) et au moins une unité de service (4). Les unités de 5 service sont souvent appelées "machines de service électrolyse" ou "M.S.E" ("PTA" ou "Pot Tending Assembly" ou "PTM" ou "Pot Tending Machine" en langue anglaise).Figures 8 to 10 show, schematically, embodiments of the means for detecting the position of an anode according to the invention. Electrolysis plants for aluminum production include a liquid aluminum production zone that includes one or more electrolysis rooms (1). As illustrated in Figure I 3 each electrolysis room (1) comprises electrolysis cells (2) and at least one service unit (4). Service units are often referred to as "electrolysis service machines" or "MSEs"("PTAs" or "Pot Tending Assemblies" or "PTMs" or "Pot Tending Machines" in English).
Les cellules d'électrolyse (2) sont,normalement disposées en rangées ou files, chaque 10 rangée ou file comportant typiquement plus d'une centaine de cellules, et raccordées électriquement en série à l'aide de conducteurs de liaison. Les cellules (2) sont disposées de manière à dégager des voies de circulation (3) entre les cellules et le long de la salle d'électrolyse (1).The electrolysis cells (2) are normally arranged in rows or rows, each row or line typically having more than one hundred cells, and electrically connected in series by means of connecting conductors. The cells (2) are arranged in such a way as to clear the circulation paths (3) between the cells and along the electrolysis room (1).
15 Tel qu'illustré à la figure 2, chaque cellule d'électrolyse (2) comprend une cuve (2'), une structure de support (35) appelée "superstructure" et une pluralité d'anodes (2O5 15 As shown in Figure 2, each electrolysis cell (2) comprises a tank (2 '), a support structure (35) called "superstructure" and a plurality of anodes (2O 5
20'). La cuve (2') comprend un caisson (26) en acier, un revêtement intérieur (27,20 '). The tank (2 ') comprises a box (26) of steel, an inner lining (27,
28), qui est généralement formé par des blocs en matériaux réfractaires, et un28), which is generally formed by blocks made of refractory materials, and a
- - - ensemble- cathodique (29, 30)r qui' comprend des blocs en matériau* carboné (29)/- - - Cathodic together- (29, 30) which r 'comprises blocks carbonaceous material * (29) /
20 appelés "blocs cathodiques", et des barres de raccordement métalliques (30) auxquelles sont fixés les conducteurs électriques (31) servant à l'acheminement du courant d'électrolyse. Les anodes (20, 20') comportent au moins un bloc anodique (21, 21') en matériau carboné précuit et une tige métallique (22, 22'). Les blocs anodiques (21, 21') ont typiquement une forme parallélépipédique. La tige (22, 22')20 referred to as "cathode blocks", and metal connecting bars (30) to which are attached the electrical conductors (31) for routing the electrolysis current. The anodes (20, 20 ') comprise at least one anode block (21, 21') of precured carbon material and a metal rod (22, 22 '). The anode blocks (21, 21 ') typically have a parallelepiped shape. The rod (22, 22 ')
25 est typiquement fixée au(x) bloc(s) anodique(s) (21, 21') par l'intermédiaire d'un élément de fixation (22a, 22a1), généralement appelé "multipode", qui est ancré dans le(s) bloc(s) anodique(s) (typiquement à l'aide de fonte). Les anodes (20, 20') sont fixées de manière amovible à un cadre métallique mobile (23), appelé "cadre anodique", par des moyens de fixation mécaniques (24, 25) comprenant typiquement25 is typically attached to the anode block (s) (21, 21 ') via a fastener (22a, 22a 1 ), generally referred to as a "multipode", which is anchored in the (s) Anode block (s) (typically using cast iron). The anodes (20, 20 ') are removably attached to a movable metal frame (23), referred to as the "anode frame", by mechanical fastening means (24, 25) typically comprising
30 un connecteur (24) et des crochets (25). Le cadre mobile (23) est porté par la superstructure (35) et fixé à des conducteurs électriques (non illustrés) servant à l'acheminement du courant d'électrolyse. Une cellule d'électrolyse (2) comporte généralement un système de capotage (36), comprenant typiquement une série de capots, pour confiner les effluents à l'intérieur de la cellule, et des moyens (non illustrés) pour évacuer les effluents et les diriger vers un centre de traitement.A connector (24) and hooks (25). The movable frame (23) is carried by the superstructure (35) and attached to electrical conductors (not shown) for routing the electrolysis current. An electrolysis cell (2) generally comprises a cowling system (36), typically comprising a series of cowls, for confining the effluents inside the cell, and means (not shown) for discharging effluents and wastewater. direct to a treatment center.
Le revêtement intérieur (27, 28) et les blocs cathodiques (29) forment, à l'intérieur de la cuve (2'), un creuset apte à contenir le bain d'électrolyte (33) et une nappe de métal liquide (32) lorsque la cellule est en fonctionnement. En général, une couverture d'alumine et de bain solidifié (34) recouvre le bain d'électrolyte et tout ou partie des anodes.The inner lining (27, 28) and the cathode blocks (29) form, inside the tank (2 '), a crucible adapted to contain the electrolyte bath (33) and a sheet of liquid metal (32). ) when the cell is in operation. In general, a cover of alumina and solidified bath (34) covers the electrolyte bath and all or part of the anodes.
Les anodes (20, 20'), et plus précisément des blocs anodiques (21, 21'), sont partiellement immergées dans le bain d'électrolyte (33), qui contient de l'alumine dissoute. La surface inférieure (21a, 21a') des anodes est typiquement essentiellement plane et parallèle à la surface supérieure (29') des blocs cathodiques (29), qui est généralement horizontale. La distance entre la surface inférieure des anodes et la surface supérieure des blocs cathodiques, dite "distance anode-cathode", est un paramètre important dans la régulation des cellules d'électrolyse. La distance anode- cathode est généralement contrôlée avec une grande précision.The anodes (20, 20 '), and more precisely anode blocks (21, 21'), are partially immersed in the electrolyte bath (33), which contains dissolved alumina. The bottom surface (21a, 21a ') of the anodes is typically substantially planar and parallel to the top surface (29') of the cathode blocks (29), which is generally horizontal. The distance between the lower surface of the anodes and the upper surface of the cathode blocks, called "anode-cathode distance", is an important parameter in the regulation of the electrolysis cells. The anode-cathode distance is generally controlled with great precision.
Les blocs anodiques (21, 21') sont progressivement consommés en utilisation. Afin de compenser cette usure, il est de pratique courante d'abaisser progressivement les anodes (20, 20') en déplaçant régulièrement le cadre mobile (23) vers le bas. En outre, tel qu'illustré à la figure 2, les blocs anodiques (21, 21') sont généralement à des degrés d'usure différents. Par conséquent, la position de l'anode de remplacement (20"), communément appelé "anode neuve", par rapport au cadre mobile (23) est généralement ajustée à chaque changement d'anode. Plus précisément, la position des anodes est ajustée de façon à mettre sur un plan commun la surface dite "inférieure" (21a, 21a1, 21a") des blocs anodiques (21, 21', 21"), c'est-à-dire la surface des blocs anodiques qui est destinée à être immergée dans le bain électrolytique (33) contenu dans la cellule d'électrolyse (2) et à être parallèle à la surface supérieure (29') du ou des blocs cathodiques (29). En pratique, l'anode de remplacement (20") est placée de manière à ce que, après avoir atteint sa température de fonctionnement, sa surface inférieure (2Ia") se situe au niveau de la surface inférieure (21a1) de l'anode usée (20') qu'elle remplace. Ladite surface inférieure (21a, 21a', 21a") des blocs anodiques (21, 21'. 21") est généralement essentiellement plane.The anode blocks (21, 21 ') are gradually consumed in use. To compensate for this wear, it is common practice to gradually lower the anodes (20, 20 ') by moving the movable frame (23) downwards regularly. In addition, as illustrated in FIG. 2, the anode blocks (21, 21 ') are generally at different degrees of wear. Therefore, the position of the replacement anode (20 "), commonly referred to as" new anode ", relative to the movable frame (23) is generally adjusted at each anode change, more specifically, the position of the anodes is adjusted. so as to put on a common plane the so-called "lower" surface (21a, 21a 1 , 21a ") of the anode blocks (21, 21 ', 21"), that is to say the surface of the anode blocks which is intended to be immersed in the electrolytic bath (33) contained in the electrolysis cell (2) and to be parallel to the upper surface (29 ') of the cathode blocks (29). In practice, the replacement anode (20 ") is placed so that, after reaching its operating temperature, its lower surface (2Ia") is located at the lower surface (21a 1 ) of the worn anode (20 ') that it replaces. Said lower surface (21a, 21a ', 21a ") of the anode blocks (21, 21', 21") is generally substantially planar.
L'unité de service (4) sert à effectuer des opérations sur les cellules (2) telles que les changements d'anode ou le remplissage des trémies d'alimentation en bain broyé et en AlF3 des cellules d'électrolyse. Elle peut également servir à manutentionner des charges diverses, telles que des éléments de cuve, des poches de métal liquide ou des anodes.The service unit (4) is used to carry out operations on the cells (2) such as the anode changes or the filling of the ground bath supply hoppers and the AlF 3 of the electrolysis cells. It can also be used to handle various loads, such as tank elements, pockets of liquid metal or anodes.
Tel qu'illustré aux figures 1 et 3, l'unité de service (4) comprend un pont mobile (5) qui peut être translaté au-dessus des cellules d'électrolyse (2) et une machine de service (6). La machine de service (6) comporte un chariot mobile (7) et un module de service (8) équipé de plusieurs organes de manutention et d'intervention (10), tels que des outils (pelles, clés, piqueurs,...). Tel qu'illustré à la figure 3, le module de service (8) comporte typiquement une tourelle (8') montée sur le chariot (7) de manière à pouvoir pivoter autour d'un axe vertical V en utilisation. Les organes de manutention et d'intervention (10) sont typiquement fixés à la tourelle. Le module de service (8) peut également comporter une cabine de contrôle (16) pour les opérateurs.As illustrated in Figures 1 and 3, the service unit (4) comprises a movable bridge (5) which can be translated over the electrolysis cells (2) and a service machine (6). The service machine (6) comprises a mobile carriage (7) and a service module (8) equipped with several handling and intervention devices (10), such as tools (shovels, keys, stitches, etc.). ). As illustrated in Figure 3, the service module (8) typically comprises a turret (8 ') mounted on the carriage (7) so as to be pivotable about a vertical axis V in use. The handling and intervention members (10) are typically attached to the turret. The service module (8) may also include a control cabin (16) for the operators.
Le pont mobile (5) repose et circule sur des chemins de roulement (9, 9') disposés parallèlement l'un à l'autre et à l'axe principal du hall (et de la file de cellules). Le pont mobile (5) peut ainsi être déplacé le long de la salle d'électrolyse (1). Le chariot mobile (7) peut être déplacé le long du pont mobile (5).The movable bridge (5) rests and circulates on raceways (9, 9 ') arranged parallel to each other and to the main axis of the hall (and the queue of cells). The mobile bridge (5) can thus be moved along the electrolysis room (1). The movable carriage (7) can be moved along the movable bridge (5).
Tel qu'illustré à la figure 3, les machines de service (6) utilisées pour les opérations de changement d'anode sont équipées d'un ensemble déterminé d'outils (10), à savoir typiquement un piqueur (l ia), une pelle à godets (12a), un organe de préhension d'anode (appelé "pince à anodes") (13a) et une trémie (14) munie d'un conduit escamotable (15). Le piqueur (l ia) sert à briser la croûte d'alumine et de bain solidifié (34) qui couvre généralement tout ou partie des anodes de la cellule ; la pelle à godets (12a) sert à dégager l'emplacement de l'anode, après le retrait de l'anode usée, par enlèvement des matières solides (telles que des morceaux de croûte et de l'alumine) qui s'y trouvent ; la pince à anodes (13a) sert à saisir et à manipuler les anodes par leur tige, notamment pour l'enlèvement des anodes usées d'une cellule d'électrolyse et la mise en place d'anodes neuves dans la cellule d'électrolyse ; le conduit escamotable (15) sert à introduire de l'alumine et/ou du bain broyé dans la cellule d'électrolyse, de manière à reformer une couche de revêtement, après la mise en place d'une anode neuve. Le piqueur (l ia), la pelle à godets (12a) et la pince à anodes (13a) sont typiquement montés à l'extrémité inférieure d'un organe de positionnement (Hb, 12b, 13b), tel qu'un mât ou un bras télescopique. L'expression "outil de manutention d'anode" (13) désigne l'ensemble comprenant un organe de préhension d'anode (13a) et un organe de positionnement (13b).As illustrated in FIG. 3, the service machines (6) used for the anode changing operations are equipped with a set of tools (10), typically a picker (11a), a shovel bucket (12a), an anode gripping member (called "anode gripper") (13a) and a hopper (14) provided with a retractable duct (15). The piercer (l ia) serves to break the crust of alumina and bath solidified (34) which generally covers all or part of the anodes of the cell; the bucket shovel (12a) serves to clear the location of the anode, after removal of the spent anode, by removal of solids (such as pieces of crust and alumina) therein ; the anode clamp (13a) serves to grip and manipulate the anodes by their rod, in particular for the removal of spent anodes from an electrolysis cell and the placement of new anodes in the electrolysis cell; the retractable duct (15) is used to introduce alumina and / or ground bath in the electrolysis cell, so as to reform a coating layer, after the establishment of a new anode. The breaker (11a), the bucket shovel (12a) and the anode clamp (13a) are typically mounted at the lower end of a positioning member (Hb, 12b, 13b), such as a mast or a telescopic arm. The expression "anode handling tool" (13) denotes the assembly comprising an anode gripping member (13a) and a positioning member (13b).
Pour la mise en oeuvre de l'invention, la machine de service (6) comporte au moins un outil de manutention d'anode (13) muni d'un organe de positionnement (13b), d'un organe de préhension (13a) et d'un capteur de position verticale (13c) de l'organe de préhension.For the implementation of the invention, the service machine (6) comprises at least one anode handling tool (13) provided with a positioning member (13b), a gripping member (13a) and a vertical position sensor (13c) of the gripping member.
Le procédé de changement d'une anode d'une cellule (2) de production d'aluminium par électrolyse comportant une pluralité d'anodes (20, 20') comporte typiquement les étapes de base suivantes :The method of changing an anode of an electrolytic aluminum production cell (2) having a plurality of anodes (20, 20 ') typically comprises the following basic steps:
- on place une machine de service à proximité de l'anode usée déterminée (20') ;a service machine is placed near the determined spent anode (20 ');
- on retire les capots (36) situés à proximité de l'anode usée (20') ; - on immobilise le cadre mobile (23) auquel sont fixées les anodes (20, 20') ;the covers (36) are removed near the worn anode (20 '); the moving frame (23) to which the anodes (20, 20 ') are fixed;
- on saisit la tige métallique de l'anode usée (20') à l'aide d'un outil de manutention d'anode (13), et plus précisément à l'aide d'un organe de préhension (13a) ;the metal rod of the spent anode (20 ') is grasped with the aid of an anode handling tool (13), and more precisely with the aid of a gripping member (13a);
- on défait la fixation mécanique (24) de l'anode usée ;the mechanical fastener (24) of the worn anode is undone;
- on retire l'anode usée (20') de la cellule d'électrolyse à l'aide dudit outil de manutention (13) ;the used anode (20 ') is removed from the electrolysis cell by means of said handling tool (13);
- on dépose l'anode usée (20') dans un endroit déterminé ; - on saisit une anode de remplacement (20") à l'aide d'un outil de manutention (13), généralement le même outil que celui qui a servi à manutentionner l'anode usée ;the used anode (20 ') is deposited in a determined location; - It takes a replacement anode (20 ") with a handling tool (13), usually the same tool that used to handle the used anode;
- on détermine une position verticale pour l'anode de remplacement (20") ;a vertical position is determined for the replacement anode (20 ");
- on place l'anode de remplacement (20") à la position verticale déterminée dans l'emplacement initialement occupé par l'anode usée ;placing the replacement anode (20 ") at the determined vertical position in the location initially occupied by the spent anode;
- on fixe l'anode de remplacement (20") sur le cadre mobile (23) à l'aide d'un moyen fixation mécanique (24).- The replacement anode (20 ") is fixed on the mobile frame (23) by means of a mechanical fixing means (24).
Selon l'invention, on détermine une position verticale pour l'anode de remplacement (20") à l'aide de mesures effectuées lors de la manutention des anodes. Ces mesures portent, d'une part, sur la position de l'outil de manutention d'anode et, d'autre part, sur le passage des anodes à travers un axe déterminé ou un plan déterminé hors de la cellule d'électrolyse. A cette fin, d'une part, on crée un axe ou un plan de référence immatériel, délimités par des ondes sonores ou électromagnétiques, et on détecte le passage des anodes à travers cet axe ou ce plan à l'aide d'un système de détection d'ondes sonores ou électromagnétiques. D'autre part, on utilise un outil de manutention d'anode (13) comprenant un capteur de position verticale (13c) de l'organe de préhension (13a), et on mesure les déplacements de l'organe de préhension au cours des opérations de manutention des anodes. On détermine la position verticale de l'anode de remplacement à partir des mesures de déplacement de l'organe de préhension à des moments déterminés, à savoir la prise de l'anode usée, le passage de l'anode usée à travers l'axe ou le plan déterminé et le passage de l'anode de remplacement à travers l'axe ou le plan déterminé.According to the invention, a vertical position is determined for the replacement anode (20 ") by means of measurements made during the handling of the anodes, These measurements relate, firstly, to the position of the tool. anode handling and, secondly, the passage of the anodes through a given axis or a specific plane outside the electrolysis cell.To this end, on the one hand, we create an axis or a plane immaterial reference, delimited by sound or electromagnetic waves, and the passage of the anodes through this axis or this plane is detected by means of a sound or electromagnetic wave detection system. an anode handling tool (13) comprising a vertical position sensor (13c) of the gripper (13a), and measuring the movements of the gripper during the anode handling operations. determines the vertical position of the replacement anode from the measurements of movement of the gripping member at predetermined times, namely the taking of the spent anode, the passage of the spent anode through the determined axis or plane and the passage of the replacement anode through the axis or plane determined.
Dans le mode de réalisation de l'invention qui est illustré aux figures 4 à 7, on procède comme suit :In the embodiment of the invention which is illustrated in FIGS. 4 to 7, the procedure is as follows:
- on produit au moins un faisceau d'ondes sonores ou électromagnétiques (51) dans un axe déterminé ou un plan de référence déterminé (50) (figure 4) ;at least one sonic or electromagnetic wave beam (51) is produced in a given axis or a determined reference plane (50) (FIG. 4);
- on positionne un outil de manutention d'anodes (13) comportant un capteur de position verticale (13c) de l'organe de préhension (13a) au niveau d'une anode usée déterminée (20') et on place un organe de préhension (13a) en position de saisie de la tige métallique (22') de cette anode (20') (figure 4) ; - on saisit la tige métallique (22') d'une anode usée déterminée (20') à l'aide de l'organe de préhension (13a) d'un outil de manutention d'anode (13) et, à l'aide du capteur de position, on mesure une première distance verticale A parcourue par l'organe de préhension (figure 4) ; - on défait la fixation mécanique (24) de l'anode usée (20'), on retire l'anode usée (20') de la cellule d'électrolyse à l'aide dudit outil de manutention (13), on fait passer le(s) bloc(s) anodique(s) (21') de cette anode à travers ledit faisceau en un mouvement vertical et, à l'aide dudit capteur de position, on mesure une deuxième distance verticale B parcourue par l'organe de préhension au moment où la surface de référence (21a1) de l'anode traverse ledit faisceau (figure 5) ;positioning an anode handling tool (13) comprising a vertical position sensor (13c) of the gripping member (13a) at a determined spent anode (20 ') and placing a gripping member (13a) in the gripping position of the metal rod (22 ') of this anode (20') (Figure 4); the metal rod (22 ') of a given spent anode (20') is grasped by means of the gripping member (13a) of an anode handling tool (13) and, at the using the position sensor, measuring a first vertical distance A traveled by the gripping member (Figure 4); the mechanical fastener (24) of the spent anode (20 ') is defeated, the used anode (20') is removed from the electrolysis cell by means of said handling tool (13), the anode block (s) (21 ') of this anode through said beam in a vertical movement and, with the aid of said position sensor, measuring a second vertical distance B traveled by the member gripping at the moment when the reference surface (21a 1 ) of the anode passes through said beam (FIG. 5);
- on saisit la tige métallique (22") d'une anode de remplacement (20") à l'aide d'un organe de préhension (13a), on fait passer le(s) bloc(s) anodique(s) (21") de cette anode à travers ledit faisceau en un mouvement vertical et, à l'aide dudit capteur de position, on mesure une troisième distance verticale C parcourue par l'organe de préhension au moment où la surface de référence (2Ia") de l'anode traverse ledit faisceau (figure 6) ;the metal rod (22 ") of a replacement anode (20") is grasped by means of a gripping member (13a), the anode block (s) are passed through ( 21 ") of said anode through said beam in a vertical movement and, with the aid of said position sensor, measuring a third vertical distance C traversed by the gripping member at the moment when the reference surface (2Ia") anode passes through said beam (Figure 6);
- on détermine la position verticale de l'anode de remplacement (20") dans la cellule à partir des valeurs obtenues pour lesdites première, deuxième et troisième distances parcourues (A, B et C), et on place l'anode de remplacement (20") à cette position verticale dans l'emplacement initialement occupé par l'anode usée (figurethe vertical position of the replacement anode (20 ") in the cell is determined from the values obtained for said first, second and third distances traveled (A, B and C), and the replacement anode is placed ( 20 ") at this vertical position in the location initially occupied by the spent anode (FIG.
7) ;7);
- on fixe l'anode de remplacement (20") sur le cadre mobile (23) à l'aide d'un moyen fixation mécanique (24).- The replacement anode (20 ") is fixed on the mobile frame (23) by means of a mechanical fixing means (24).
Lesdites mesures de distance peuvent être effectuées pendant les manipulations normales de remplacement des anodes usées. L'invention permet ainsi de limiter sensiblement les opérations de manutention requises pour déterminer la position de l'anode de remplacement.Said distance measurements can be made during normal operations of replacing worn anodes. The invention thus makes it possible to substantially limit the handling operations required to determine the position of the replacement anode.
De préférence, on utilise le même organe de préhension (13a) pour manutentionner une anode usée déterminée (20') et l'anode de remplacement (20") destinée à la remplacer. Cette variante permet d'éviter un étalonnage des capteurs d'outils distincts et les différences de mesure de distance inhérentes à l'utilisation d'outils distincts. Dans ce cas, on dépose l'anode usée (20') dans un endroit déterminé avant de saisir la tige métallique (22") de l'anode de remplacement (20") avec l'organe de préhension (13a).Preferably, the same gripping member (13a) is used to handle a determined spent anode (20 ') and the replacement anode (20 ") intended to replace it.This variant makes it possible to avoid a calibration of the sensors. separate tools and differences in distance measurement inherent in the use of separate tools. In this case, the used anode (20 ') is deposited in a determined location before the metal rod (22 ") of the replacement anode (20") is gripped with the gripping member (13a).
Ladite première distance (A) peut être mesurée avant ou après avoir saisi la tige (22') de l'anode usée (20'). Cette distance est de préférence mesurée après avoir saisi la tige (22') et après avoir mis l'outil de manutention (13) sous tension mécanique, afin de rattraper les éventuels jeux mécaniques et d'améliorer la précision de la mesure.Said first distance (A) can be measured before or after grasping the rod (22 ') of the spent anode (20'). This distance is preferably measured after grasping the rod (22 ') and after putting the handling tool (13) under mechanical tension, in order to make up for any mechanical play and improve the accuracy of the measurement.
La surface de référence (21a, 21a', 21a") des anodes est de préférence la surface dite "inférieure" du (des) bloc(s) anodique(s) (21, 21', 21").The reference surface (21a, 21a ', 21a ") of the anodes is preferably the so-called" lower "surface of the anode block (s) (21, 21', 21").
Afin de limiter les mouvements de manutention des anodes, on mesure de préférence ladite distance verticale B lors d'un mouvement vers le bas d'une anode usée (20'), typiquement lors du dépôt de l'anode dans l'endroit déterminé, qui est généralement une palette ou un véhicule (40, 40') destinés à son évacuation. Dans ce but, ledit faisceau est disposé à une hauteur déterminée au-dessus dudit endroit déterminé.In order to limit anode handling movements, said vertical distance B is preferably measured during a downward movement of a spent anode (20 '), typically during the deposition of the anode in the determined location, which is usually a pallet or a vehicle (40, 40 ') for its evacuation. For this purpose, said beam is disposed at a predetermined height above said determined location.
Afin de limiter les mouvements de manutention des anodes, on mesure de préférence ladite distance verticale C lors d'un mouvement vers le haut d'une anode de remplacement (20"), typiquement lors de l'enlèvement de l'anode d'un endroit de stockage temporaire, qui est généralement une palette ou un véhicule (40, 40") utilisés pour sa fourniture. Dans ce but, ledit faisceau est disposé à une hauteur déterminée au-dessus dudit endroit de stockage.In order to limit the anode handling movements, it is preferably measured said vertical distance C during an upward movement of a replacement anode (20 "), typically during the removal of the anode of a temporary storage place, which is usually a pallet or vehicle (40, 40 ") used for its supply. For this purpose, said beam is disposed at a predetermined height above said storage location.
La position verticale d'une anode de remplacement (20") correspond à une distance verticale A' parcourue par l'organe de préhension (13a) lors de la mise en place de l'anode de remplacement dans l'emplacement initialement occupé par une anode usée déterminée. En pratique, lors de la mise en place de l'anode de remplacement, on stoppe le mouvement de descente de l'organe de préhension lorsque la distance parcourue par celui-ci est égale à A'. La distance verticale A1 est typiquement donnée par la relation A' = A - B + C + D, où D est un terme de correction pour prendre en compte la mise en régime de fonctionnement de l'anode de remplacement dans la cellule.The vertical position of a replacement anode (20 ") corresponds to a vertical distance A 'traveled by the gripping member (13a) during the placement of the replacement anode in the location initially occupied by a In practice, when setting up the replacement anode, the downward movement of the gripping member is stopped when the distance traversed by it is equal to A. The vertical distance A 1 is typically given by the relation A '= A - B + C + D, where D is a correction term to take into account the operating mode of the replacement anode in the cell.
Selon un mode de réalisation du procédé selon l'invention, on remplace les anodes usées (20') une à une par des anodes de remplacement (20").According to one embodiment of the method according to the invention, the worn anodes (20 ') are replaced one by one by replacement anodes (20 ").
Selon un autre mode de réalisation du procédé selon l'invention, on remplace au moins deux anodes usées (20') à la fois par des anodes de remplacement (20"). Dans ce cas, lesdites distances A, B et C sont mesurées, et ladite distance A' déterminée, pour chacun des couples anode usée (20') / anode de remplacement (20"). Ce mode de réalisation de l'invention est avantageusement mis en oeuvre en utilisant une machine de service (6) comportant un nombre d'outils de manutention d'anode (13) au moins égal au nombre des anodes usées qui sont remplacées simultanément.According to another embodiment of the method according to the invention, at least two worn anodes (20 ') are replaced at a time by replacement anodes (20 ") In this case, said distances A, B and C are measured. , and said determined distance A ', for each of the used anode (20') / replacement anode (20 ") pairs. This embodiment of the invention is advantageously implemented by using a service machine (6) comprising a number of anode handling tools (13) at least equal to the number of worn anodes which are replaced simultaneously.
Le capteur de position (13c) sert à mesurer la distance parcourue verticalement par l'organe de préhension (13a) lors des manutentions d'anodes. Les distances sont données par rapport à un niveau de référence N, qui peut être quelconque. Le niveau de référence N est de préférence le même pour toutes les mesures de distance lors d'un même changement d'anode afin de simplifier les calculs et d'éviter d'introduire des incertitudes dans la détermination de la position finale de l'anode de remplacement.The position sensor (13c) is used to measure the distance traveled vertically by the gripping member (13a) during handling of anodes. The distances are given with respect to a reference level N, which may be arbitrary. The reference level N is preferably the same for all the distance measurements during the same anode change in order to simplify the calculations and to avoid introducing uncertainties in the determination of the final position of the anode. of substitution.
Le capteur de position (13c) peut-être, par exemple, un encodeur à câble ou un télémètre laser. Le capteur de position est avantageusement intégré à l'outil de manutention d'anode (13). Typiquement, le capteur de position (13c) est fixé rigidement à la partie fixe de l'organe de positionnement (13b) de l'outil de manutention d'anode (13) ; il permet de mesurer la distance relative d'un point déterminé solidaire de l'organe de préhension. Par exemple, le capteur de position peut être fixé au coulissant d'un bras ou mât télescopique auquel est fixé l'organe de préhension. Afin de compenser les jeux éventuels entre les composants de l'outil de manutention d'anode (13) et entre l'organe de préhension d'anode (13a) et une tige d'anode (22, 22'), il est avantageux d'effectuer ladite première mesure de distance parcourue A en traction, c'est-à-dire après avoir mis en tension la chaîne cinématique de l'outil (avant desserrement du connecteur (24) qui maintient la tige de l'anode sur le cadre mobile (23)), car les autres mesures de distance sont faites en traction dans le cadre de l'invention (l'axe ou le plan de référence étant immatériels et l'anode de remplacement étant suspendue à l'organe de préhension lors de l'ajustement de sa position dans la cellule). Afin de pouvoir tenir compte desdits jeux, il est avantageux de munir l'outil de manutention d'anode (13) d'un moyen de mesure de la tension dans l'outil, tel qu'un dynamomètre axial, qui permet de connaître le moment où la chaîne cinématique de l'outil est en traction et de déterminer le moment où les jeux mécaniques sont tous repris dans le même sens.The position sensor (13c) may be, for example, a cable encoder or a laser range finder. The position sensor is advantageously integrated with the anode handling tool (13). Typically, the position sensor (13c) is rigidly attached to the fixed part of the positioning member (13b) of the anode handling tool (13); it makes it possible to measure the relative distance of a determined point integral with the gripping member. For example, the position sensor can be attached to the sliding arm or telescopic mast which is fixed the gripping member. In order to compensate for any gaps between the components of the anode handling tool (13) and between the anode gripping member (13a) and an anode rod (22, 22 '), it is advantageous to to perform said first measurement of distance traveled A in tension, that is to say after having tensioned the kinematic chain of the tool (before loosening of the connector (24) which holds the rod of the anode on the mobile frame (23)), because the other distance measurements are made in traction in the context of the invention (the axis or the reference plane being immaterial and the replacement anode being suspended from the gripping member when the adjustment of its position in the cell). In order to take account of said clearances, it is advantageous to provide the anode handling tool (13) with a means for measuring the tension in the tool, such as an axial dynamometer, which makes it possible to know the moment when the kinematic chain of the tool is in tension and to determine the moment when the mechanical games are all taken in the same direction.
Lesdites ondes sonores sont typiquement des ondes ultrasonores.Said sound waves are typically ultrasonic waves.
Lesdites ondes électromagnétiques sont typiquement de la lumière visible, des infrarouges ou des ondes radio. Il est avantageux de générer ledit faisceau (51) à l'aide d'un laser.The electromagnetic waves are typically visible light, infrared or radio waves. It is advantageous to generate said beam (51) using a laser.
La surface inférieure (21a, 21a', 21a") des anodes, notamment des anodes usées, peuvent posséder des irrégularités qui proviennent notamment de défauts de surface, d'une usure irrégulière des anodes ou de dépôts de matière (telle que de l'alumine) lors de l'utilisation des anodes. Afin d'éviter les fausses mesures de distance parcourue provenant d'irrégularités de la surface de référence (21a, 21a', 21a"), on génère de préférence deux ou plusieurs (typiquement trois) faisceaux d'ondes sonores ou électromagnétiques (51) de façon à former un plan de référence déterminé (50). Cette variante de l'invention est typiquement mise en oeuvre à l'aide d'un générateur comportant deux ou plusieurs sources d'ondes sonores ou électromagnétiques, c'est- à-dire que chaque faisceau (51) est généré par une source d'ondes distincte (dans le cas des ondes électromagnétiques, chaque source est typiquement un laser). Dans cette variante, les distances parcourues (B et C) sont avantageusement données par la moyenne des distances parcourues mesurées pour chacun des faisceaux (après avoir éventuellement éliminé une ou des valeurs jugées aberrantes).The lower surface (21a, 21a ', 21a ") of the anodes, in particular worn anodes, may have irregularities resulting in particular from surface defects, irregular wear of the anodes or deposits of material (such as alumina) when using the anodes In order to avoid false measurements of distance traveled from irregularities of the reference surface (21a, 21a ', 21a "), two or more (typically three) are preferably generated. sonic or electromagnetic wave beams (51) to form a determined reference plane (50). This variant of the invention is typically implemented with the aid of a generator comprising two or more sources of sound or electromagnetic waves, that is to say that each beam (51) is generated by a source of distinct waves (in the case of electromagnetic waves, each source is typically a laser). In this variant, the distances traveled (B and C) are advantageously given by the average of the distances traveled measured for each beam (after possibly eliminating one or more values deemed aberrant).
Ledit axe déterminé ou le plan de référence déterminé (50) est de préférence sensiblement horizontal. L'angle entre l'horizontale et ledit axe ou plan de référence déterminé (50) est de préférence inférieur à environ 10°, et de préférence encore inférieur à environ 5°.Said determined axis or the determined reference plane (50) is preferably substantially horizontal. The angle between the horizontal and said determined reference axis or plane (50) is preferably less than about 10 °, and more preferably less than about 5 °.
Le moment où la surface de référence (21a1, 21a") d'une anode traverse ledit faisceau peut être déterminé de différentes manières. Selon une manière avantageuse de procéder, qui peut être aisément informatisée, on utilise un générateur (ou émetteur) d'ondes sonores ou électromagnétiques pour produire ledit faisceau et un détecteurThe moment when the reference surface (21a 1 , 21a ") of an anode passes through said bundle can be determined in different ways. <br /><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/> In an advantageous manner, which can be easily computerized, a generator (or transmitter) is used. sound or electromagnetic waves to produce said beam and a detector
(ou récepteur) pour détecter ledit faisceau. Selon un premier mode de réalisation de cette manière de procéder, qui est représenté schématiquement à la figure 8, on dispose un détecteur d'ondes sonores ou électromagnétiques (54) en regard d'un générateur de faisceau d'ondes sonores ou électromagnétiques (52) de manière à ce que le détecteur puisse détecter le faisceau produit par le générateur (figure 8a). On détecte le moment où la surface de référence (21a1, 21a") d'une anode (20', 20") traverse ledit faisceau lorsque le bloc anodique (21', 21") interrompt la transmission dudit faisceau au détecteur (figure 8b).(or receiver) for detecting said beam. According to a first embodiment of this procedure, which is shown diagrammatically in FIG. 8, there is a sound or electromagnetic wave detector (54) facing a sound or electromagnetic wave beam generator (52). ) so that the detector can detect the beam produced by the generator (Figure 8a). The moment when the reference surface (21a 1 , 21a ") of an anode (20 ', 20") passes through said beam is detected when the anode block (21', 21 ") interrupts the transmission of said beam to the detector (FIG. 8b).
Selon un autre mode de réalisation de cette manière de procéder, qui est représenté schématiquement à la figure 9, on dispose un détecteur d'ondes sonores ou électromagnétiques (54) et un générateur de faisceau d'ondes sonores ou électromagnétiques (52) en regard d'une surface réfléchissante (55), tel qu'un miroir, de manière à ce que le détecteur puisse détecter le faisceau produit par le générateur et réfléchi par la surface réfléchissante (55) (figure 9a). Ces éléments peuvent être disposés en triangle de manière à former un plan. On détecte le moment où la surface de référence (21a1, 21a") d'une anode (20', 20") traverse ledit faisceau lorsque le bloc anodique (21', 21 ") interrompt la transmission dudit faisceau au détecteur (figure 9b). Selon encore un autre mode de réalisation de cette manière de procéder, qui est représenté schématiquement à la figure 10, on dispose un détecteur d'ondes sonores ou électromagnétiques (54) et un générateur de faisceau d'ondes sonores ou électromagnétiques (52) de manière à ce que le détecteur puisse détecter le faisceau produit par le générateur et réfléchi par le bloc anodique (21', 21") (figure 10a). On détecte le moment où la surface de référence (21a1, 21a") d'une anode (20', 20") traverse ledit faisceau lorsque le bloc anodique (21', 21") réfléchit tout ou partie dudit faisceau vers le détecteur (figure 10b). Des essais ont montré que la réflectivité de la surface d'une anode neuve ou usée était suffisante pour permettre un fonctionnement satisfaisant de ce mode de réalisation. Ce mode de réalisation présente l'avantage de permettre de regrouper aisément le détecteur et le générateur sur un même organe de positionnement (53).According to another embodiment of this procedure, which is shown diagrammatically in FIG. 9, there is a sound or electromagnetic wave detector (54) and a sound or electromagnetic wave beam generator (52) facing each other. a reflecting surface (55), such as a mirror, so that the detector can detect the beam produced by the generator and reflected by the reflective surface (55) (Figure 9a). These elements can be arranged in a triangle so as to form a plane. The moment when the reference surface (21a 1 , 21a ") of an anode (20 ', 20") passes through said beam is detected when the anode block (21', 21 ") interrupts the transmission of said beam to the detector (FIG. 9b). According to yet another embodiment of this manner of proceeding, which is shown diagrammatically in FIG. 10, there is provided a sound or electromagnetic wave detector (54) and a sound or electromagnetic wave beam generator (52) of in such a way that the detector can detect the beam produced by the generator and reflected by the anode block (21 ', 21 ") (Figure 10a), the moment when the reference surface (21a 1 , 21a") of an anode (20 ', 20 ") passes through said beam when the anode block (21', 21") reflects all or part of said beam towards the detector (Figure 10b). Tests have shown that the reflectivity of the surface of a new or used anode is sufficient to allow satisfactory operation of this embodiment. This embodiment has the advantage of allowing to easily group the detector and the generator on the same positioning member (53).
Le procédé selon l'invention peut être mis en oeuvre à l'aide d'un système de mesure comprenant un capteur de position (13c) pour mesurer les distances verticales parcourues par un organe de préhension (13a) d'un outil de manutention d'anodeThe method according to the invention can be implemented using a measuring system comprising a position sensor (13c) for measuring the vertical distances traveled by a gripping member (13a) of a handling tool. 'anode
(13), un générateur de faisceau d'ondes sonores ou électromagnétiques (52), apte à produire au moins un faisceau d'ondes sonores ou électromagnétiques (51) dans un axe ou un plan de référence déterminé (50), au moins un détecteur d'ondes sonores ou électromagnétiques (54) apte à détecter le passage d'une partie déterminée (21a,(13), a sound or electromagnetic wave beam generator (52), capable of producing at least one sound or electromagnetic wave beam (51) in a given axis or reference plane (50), at least one sound or electromagnetic wave detector (54) adapted to detect the passage of a determined part (21a,
21a', 21a") d'une anode (20, 20', 20") à travers ledit faisceau et au moins un organe de positionnement (53) auquel est fixé ledit générateur et/ou ledit détecteur. Le capteur de position (13c) est de préférence intégré à l'outil de manutention d'anode21a ', 21a ") of an anode (20, 20', 20") through said beam and at least one locating member (53) to which said generator and / or detector is attached. The position sensor (13c) is preferably integrated with the anode handling tool
(13). Le générateur (52) comporte typiquement une source pour chaque faisceau d'ondes sonores ou électromagnétiques (52). Dans la variante de l'invention où les faisceaux sont formés d'ondes électromagnétiques, le générateur comporte avantageusement au moins un laser.(13). The generator (52) typically includes a source for each sound or electromagnetic wave beam (52). In the variant of the invention where the beams are formed of electromagnetic waves, the generator advantageously comprises at least one laser.
Dans un mode de réalisation de l'invention, le ou chaque organe de positionnement (53) du système de mesure est, directement ou indirectement, fixé à une voie de circulation (3) ou posé sur celle-ci. Dans un autre mode de réalisation de l'invention, le système de mesure est intégré à une unité de service (4) destinée aux opérations de changement d'anodes. Ce mode de réalisation de l'invention facilite le déplacement et le positionnement du système de mesure. Il permet en outre d'effectuer les mesures nécessaires au positionnement d'une anode de remplacement lors des mouvements de manutention normaux d'une anode usée et d'une anode de remplacement. Le système de mesure selon l'invention est de préférence intégré à la machine de service (6) de ladite unité de service (4), et de préférence encore au module (8) de ladite machine de service (6). Dans ces cas, le capteur de position verticale (13c) de l'organe de préhension (13a) du système de mesure est typiquement celui dont est muni l'outil de manutention d'anode (13). Dans ces variantes, le ou chaque organe de positionnement (53) du système de mesure est, directement ou indirectement, fixé à une unité de service (4), à une machine de service (6) ou à un module de service (8).In one embodiment of the invention, the or each positioning member (53) of the measuring system is, directly or indirectly, attached to or placed on a traffic lane (3). In another embodiment of the invention, the measurement system is integrated with a service unit (4) for anode change operations. This embodiment of the invention facilitates the movement and positioning of the measuring system. It also makes it possible to carry out the measurements necessary for the positioning of a replacement anode during normal handling movements of a used anode and a replacement anode. The measuring system according to the invention is preferably integrated in the service machine (6) of said service unit (4), and more preferably in the module (8) of said service machine (6). In these cases, the vertical position sensor (13c) of the gripping member (13a) of the measuring system is typically that which is provided with the anode handling tool (13). In these variants, the or each positioning member (53) of the measuring system is, directly or indirectly, fixed to a service unit (4), to a service machine (6) or to a service module (8) .
Le ou chaque organe de positionnement (53) du système de mesure est typiquement un bras ou un mât télescopique. Lorsque le système de mesure est intégré à une unité de service (4), le générateur (52) et/ou le détecteur (54) sont typiquement fixés dans la partie basse de l'organe de positionnement (53).The or each positioning member (53) of the measuring system is typically an arm or a telescopic mast. When the measuring system is integrated with a service unit (4), the generator (52) and / or the detector (54) are typically fixed in the lower part of the positioning member (53).
Les mesures de distance parcourue (A, B, C, A') peuvent être effectuées avec ou sans l'intervention d'un opérateur. Par exemple, le détecteur peut émettre un signal électrique, lumineux ou sonore lorsque la surface de référence déterminée d'une anode traverse le ou les dits faisceaux et un opérateur peut enregistrer la valeur de distance parcourue par l'organe de préhension donnée par le capteur de position au moment de l'émission dudit signal. La détermination de la distance A' correspondant à la position de l'anode de remplacement peut également être effectuée par un opérateur à l'aide des valeurs obtenues pour les première, deuxième et troisième distances parcourues (A, B et C). Afin d'alléger la tâche des opérateurs et d'éviter les erreurs de calcul, la mesure des dites distances (A, B, C, A') est avantageusement effectuée en tout ou partie de manière informatique. Par exemple, le passage de la surface de référence (21a, 21a', 21a") des anodes à travers ledit faisceau peut déclencher électriquement ou électroniquement la mesure du capteur de position et l'enregistrement de la distance correspondante. Le système de mesure comporte avantageusement un dispositif pour enregistrer les mesures effectuées et pour déterminer ladite position verticale de l'anode de remplacement (20").The measurements of distance traveled (A, B, C, A ') can be carried out with or without the intervention of an operator. For example, the detector may emit an electrical, light or sound signal when the determined reference surface of an anode passes through the said beam (s) and an operator can record the distance value traveled by the gripping member given by the sensor. position at the time of transmission of said signal. Determining the distance A 'corresponding to the position of the replacement anode can also be performed by an operator using the values obtained for the first, second and third distances traveled (A, B and C). In order to lighten the task of the operators and to avoid calculation errors, the measurement of said distances (A, B, C, A ') is advantageously carried out wholly or partly in a computer manner. For example, the passage of the reference surface (21a, 21a ', 21a ") of the anodes through said beam can electrically or electronically trigger the measurement of the position sensor and the recording of the corresponding distance. The measuring system advantageously comprises a device for recording the measurements made and for determining said vertical position of the replacement anode (20 ").
Le générateur (52) et le détecteur (54) peuvent se situer sur un même organe de positionnement (53) ou sur des organes de positionnement distincts. Le générateur (52) et détecteur (54) peuvent éventuellement être intégrés dans un même dispositif. The generator (52) and the detector (54) can be located on the same positioning member (53) or on separate positioning members. The generator (52) and detector (54) may optionally be integrated in the same device.
Claims
Priority Applications (5)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP05800606.5A EP1819847B1 (en) | 2004-09-08 | 2005-09-02 | Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing the same |
| CA2577921A CA2577921C (en) | 2004-09-08 | 2005-09-02 | Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing same |
| CN200580037476.1A CN101052749B (en) | 2004-09-08 | 2005-09-02 | Anode replacement method of electrolytic aluminum pool including anode position adjustment and device for implementing the method |
| BRPI0515060-4A BRPI0515060A (en) | 2004-09-08 | 2005-09-02 | anode change process in an electrolysis aluminum production cell, including an anode position adjustment and device for using it |
| AU2005284068A AU2005284068B2 (en) | 2004-09-08 | 2005-09-02 | Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing same |
Applications Claiming Priority (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US60775604P | 2004-09-08 | 2004-09-08 | |
| US60/607,756 | 2004-09-08 | ||
| FR0409508A FR2874934B1 (en) | 2004-09-08 | 2004-09-08 | METHOD FOR CHANGING ANODE IN AN ELECTROLYTIC ALUMINUM PRODUCTION CELL INCLUDING ANODE POSITION ADJUSTMENT AND DEVICE FOR IMPLEMENTING THE SAME |
| FR0409508 | 2004-09-08 |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| WO2006030092A2 true WO2006030092A2 (en) | 2006-03-23 |
| WO2006030092A3 WO2006030092A3 (en) | 2006-12-07 |
| WO2006030092A8 WO2006030092A8 (en) | 2007-04-05 |
Family
ID=35911091
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/FR2005/002188 Ceased WO2006030092A2 (en) | 2004-09-08 | 2005-09-02 | Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing same |
Country Status (7)
| Country | Link |
|---|---|
| EP (1) | EP1819847B1 (en) |
| AR (1) | AR054403A1 (en) |
| AU (1) | AU2005284068B2 (en) |
| BR (1) | BRPI0515060A (en) |
| CA (1) | CA2577921C (en) |
| RU (1) | RU2375502C2 (en) |
| WO (1) | WO2006030092A2 (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2902113A1 (en) * | 2006-06-09 | 2007-12-14 | Ecl Soc Par Actions Simplifiee | METHOD OF MEASURING THE RISE OF THE HEIGHT OF AN ELECTROLYSIS ANODE |
| CN102400181A (en) * | 2011-11-22 | 2012-04-04 | 中国铝业股份有限公司 | Method for replacing aluminum electrolysis cell electrode |
| CN102400184A (en) * | 2011-11-22 | 2012-04-04 | 中国铝业股份有限公司 | Method for realizing accurate replacement of electrode of aluminum electrolytic cell |
| FR3016891A1 (en) * | 2014-01-27 | 2015-07-31 | Rio Tinto Alcan Int Ltd | DEVICE FOR STORING A CHARGE ABOVE AN ELECTROLYSIS TANK |
| EP4293141A1 (en) | 2022-06-13 | 2023-12-20 | Dubai Aluminium PJSC | Anode servicing assembly for an aluminium electrolysis plant, and methods for operating the same |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2021035356A1 (en) * | 2019-08-28 | 2021-03-04 | Elysis Limited Partnership | Apparatus and method for operating an electrolytic cell |
Family Cites Families (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5549682B2 (en) * | 1974-04-05 | 1980-12-13 | ||
| DE2819351A1 (en) * | 1978-04-03 | 1979-10-04 | Alusuisse | METHOD FOR MEASURING ELECTRODES TO BE REPLACED, ARRANGEMENT FOR IMPLEMENTING THE METHOD AND DETECTOR FOR REGISTERING THE REACHER OF A PRESET POSITION |
| US4540474A (en) * | 1984-06-04 | 1985-09-10 | Aluminum Company Of America | Light level electrode setting gauge and method of use |
| IT1221994B (en) * | 1987-07-09 | 1990-08-31 | Techmo Car Spa | EQUIPMENT FOR THE MECHANIZED CHANGE OF THE ANODES IN THE ELECTROLYTIC CELLS FOR THE PRODUCTION OF ALUMINUM |
| US4992146A (en) * | 1987-12-30 | 1991-02-12 | Norsk Hydro, A.S. | Method for setting electrodes in aluminum electrolysis cells |
| NO162975C (en) * | 1987-12-30 | 1990-03-14 | Norsk Hydro As | PROCEDURE FOR SETTING ELECTRODES IN ELECTROLYCLE CELLS. |
| US5152408A (en) * | 1988-05-18 | 1992-10-06 | Hans Tax | Container crane installation |
| RU2081945C1 (en) * | 1994-11-04 | 1997-06-20 | Акционерное общество открытого типа "Всероссийский алюминиево-магниевый институт" | Method of replacing anodes in electrolyzers with baked anode to produce aluminium |
| SI1028084T1 (en) * | 1999-02-12 | 2003-10-31 | Reel S.A. | Hoisting device for the replacement of the anodes in the electrolytic cells for aluminium production |
| RU27383U1 (en) * | 2001-12-25 | 2003-01-27 | Открытое акционерное общество "Братский алюминиевый завод" | DEVICE FOR MOVING ANODE OF ALUMINUM ELECTROLYZER |
| US7001497B2 (en) * | 2003-04-25 | 2006-02-21 | Alcoa,Inc. | Process and apparatus for positioning replacement anodes in electrolytic cells |
-
2005
- 2005-09-02 CA CA2577921A patent/CA2577921C/en not_active Expired - Fee Related
- 2005-09-02 AU AU2005284068A patent/AU2005284068B2/en not_active Ceased
- 2005-09-02 RU RU2007112948/02A patent/RU2375502C2/en not_active IP Right Cessation
- 2005-09-02 EP EP05800606.5A patent/EP1819847B1/en not_active Expired - Lifetime
- 2005-09-02 WO PCT/FR2005/002188 patent/WO2006030092A2/en not_active Ceased
- 2005-09-02 BR BRPI0515060-4A patent/BRPI0515060A/en not_active IP Right Cessation
- 2005-09-06 AR ARP050103722A patent/AR054403A1/en not_active Application Discontinuation
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2902113A1 (en) * | 2006-06-09 | 2007-12-14 | Ecl Soc Par Actions Simplifiee | METHOD OF MEASURING THE RISE OF THE HEIGHT OF AN ELECTROLYSIS ANODE |
| WO2007141412A3 (en) * | 2006-06-09 | 2008-09-12 | Ecl | Method of measuring, on the fly, the height of an electrolysis anode |
| CN102400181A (en) * | 2011-11-22 | 2012-04-04 | 中国铝业股份有限公司 | Method for replacing aluminum electrolysis cell electrode |
| CN102400184A (en) * | 2011-11-22 | 2012-04-04 | 中国铝业股份有限公司 | Method for realizing accurate replacement of electrode of aluminum electrolytic cell |
| FR3016891A1 (en) * | 2014-01-27 | 2015-07-31 | Rio Tinto Alcan Int Ltd | DEVICE FOR STORING A CHARGE ABOVE AN ELECTROLYSIS TANK |
| EP3099843A4 (en) * | 2014-01-27 | 2017-11-08 | Rio Tinto Alcan International Limited | Device for storing a load above an electrolytic cell |
| AU2019202943B2 (en) * | 2014-01-27 | 2020-05-21 | Rio Tinto Alcan International Limited | Device for storing a load above an electrolytic cell |
| EP4293141A1 (en) | 2022-06-13 | 2023-12-20 | Dubai Aluminium PJSC | Anode servicing assembly for an aluminium electrolysis plant, and methods for operating the same |
Also Published As
| Publication number | Publication date |
|---|---|
| BRPI0515060A (en) | 2008-07-01 |
| RU2007112948A (en) | 2008-10-20 |
| AR054403A1 (en) | 2007-06-27 |
| CA2577921A1 (en) | 2006-03-23 |
| RU2375502C2 (en) | 2009-12-10 |
| WO2006030092A3 (en) | 2006-12-07 |
| EP1819847A2 (en) | 2007-08-22 |
| WO2006030092A8 (en) | 2007-04-05 |
| AU2005284068B2 (en) | 2010-07-29 |
| EP1819847B1 (en) | 2017-11-29 |
| AU2005284068A1 (en) | 2006-03-23 |
| CA2577921C (en) | 2014-05-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA2583471C (en) | Method for changing anode in an electrolytic aluminium production cell including adjusting the position of the anode and servicing machine therefor | |
| FR2874934A1 (en) | METHOD FOR CHANGING ANODE IN AN ELECTROLYTIC ALUMINUM PRODUCTION CELL INCLUDING ANODE POSITION ADJUSTMENT AND DEVICE FOR IMPLEMENTING THE SAME | |
| EP2027308A2 (en) | Method of measuring, on the fly, the height of an electrolysis anode | |
| EP0288397A1 (en) | Process and apparatus for monitoring the solid electrolyte additions to electrolysis vats for the production of aluminium | |
| EP1819847B1 (en) | Method of changing an anode of a cell for the production of aluminium by means of electrolysis, including an adjustment of the position of the anode, and device for performing the same | |
| CA2591495C (en) | Handling device for hoods of a cell for electrolytic aluminium production | |
| FR2953862A1 (en) | DEVICE FOR COLLECTING SOLID DEBRIS IN AN ELECTROLYSIS TANK FOR ALUMINUM PRODUCTION | |
| CA2560675C (en) | Compact service module which is intended for electrolytic aluminium production plants | |
| CN101052749B (en) | Anode replacement method of electrolytic aluminum pool including anode position adjustment and device for implementing the method | |
| EP2761061B1 (en) | Compact service module and use thereof in a plant for producing aluminum by electrolysis | |
| FR3065014B1 (en) | METHOD FOR ESTABLISHING ANODE COVERAGE IN AN ELECTROLYSIS CELL, SERVICE MACHINE SUITABLE FOR CARRYING OUT SAID METHOD, AND COMPUTER PROGRAM PRODUCT FOR IMPLEMENTING SUCH A METHOD |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AK | Designated states |
Kind code of ref document: A2 Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KM KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NG NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SM SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW |
|
| AL | Designated countries for regional patents |
Kind code of ref document: A2 Designated state(s): GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LT LU LV MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
| WWE | Wipo information: entry into national phase |
Ref document number: 2577921 Country of ref document: CA |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2005284068 Country of ref document: AU |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| REEP | Request for entry into the european phase |
Ref document number: 2005800606 Country of ref document: EP |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2005800606 Country of ref document: EP |
|
| ENP | Entry into the national phase |
Ref document number: 2005284068 Country of ref document: AU Date of ref document: 20050902 Kind code of ref document: A |
|
| WWP | Wipo information: published in national office |
Ref document number: 2005284068 Country of ref document: AU |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2007112948 Country of ref document: RU Ref document number: 1432/CHENP/2007 Country of ref document: IN |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 200580037476.1 Country of ref document: CN |
|
| WWP | Wipo information: published in national office |
Ref document number: 2005800606 Country of ref document: EP |
|
| ENP | Entry into the national phase |
Ref document number: PI0515060 Country of ref document: BR |