WO2003104562A1 - Element beton prefabrique et procede - Google Patents
Element beton prefabrique et procede Download PDFInfo
- Publication number
- WO2003104562A1 WO2003104562A1 PCT/DE2003/000156 DE0300156W WO03104562A1 WO 2003104562 A1 WO2003104562 A1 WO 2003104562A1 DE 0300156 W DE0300156 W DE 0300156W WO 03104562 A1 WO03104562 A1 WO 03104562A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- concrete
- formwork
- railway
- sleeper
- connecting piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B3/00—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails
- E01B3/28—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone
- E01B3/32—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone with armouring or reinforcement
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B15/00—General arrangement or layout of plant ; Industrial outlines or plant installations
- B28B15/002—Mobile plants, e.g. on vehicles or on boats
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
- B28B23/20—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the shaping being effected by centrifugal or rotational moulding
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/08—Moulds provided with means for tilting or inverting
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/08—Moulds provided with means for tilting or inverting
- B28B7/087—Moulds provided with means for tilting or inverting using rocker or rolling means
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/22—Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/50—Anchored foundations
Definitions
- the present invention relates to what is claimed in the preamble and is therefore concerned with the rotary formwork of precast concrete parts, in particular with railway sleepers.
- elongated precast concrete parts each of which can be installed in large numbers for a building without changing one another.
- These include ram piles for the foundation formation, noise protection wall elements, crosswise sleeper rib constructions, transoms for high-bay warehouses etc. and in particular track sleepers, which are laid in large numbers for modern railway lines.
- the object of the present invention is to provide something new for commercial use.
- the present invention thus proposes, in a first basic concept, a railway concrete sleeper with spaced-apart track support areas and a concrete connecting piece in between, in which it is provided that the concrete connecting piece is reinforced with slack.
- a first essential aspect of the present invention therefore lies in the knowledge that the spaced-apart track support areas can be held securely in their position by a slack-reinforced concrete connecting piece, regardless of their high dynamic load due to trains traveling over them.
- This longitudinal reinforcement allows tensile forces to be transmitted between the rails and ensures the stability of the track position.
- connection piece is reinforced in one layer, which simplifies production and lowers production costs.
- Single-layered also means reinforcement elements that are directly one above the other but are provided without stirrups.
- the reinforcement will typically be made of corrugated steel, which prevents the reinforcement from shaking loose under the dynamic load.
- the static crack behavior can already be calculated exactly according to DIN 1045. There is no longer any reason to fear that problems will arise from the slack reinforcement of the concrete connector during continuous operation, since extensive experience exists, particularly in the area of limited steel stresses, for example below 18 kN / cm 2 . This also applies to the support blocks.
- reinforcement mats or baskets can be formed and used by means of helical spot welding
- a dynamic mat i.e. a steel insert mat, which is formed only from crossing bars, which are only in certain crossing points , which are preferably in the area of low tractive force coverage, but are not welded to one another at all crossing points.
- the arrangement of additional bars can then be provided at welding points on the edge.
- Such reinforcement is inexpensive and ensures that even with very high load changes the steel stresses at the welding points do not endanger the load-bearing capacity.
- Comparatively small steel diameters of, for example, 6 to 8 mm in diameter or less are preferred, which reduces the undesirable crack expansion and distributes the cracks more finely, even without having to resort to the expensive demands of a CEM for a minimum torque without cracks.
- the concrete bridge ensures that the tracks are easier to walk on by construction and maintenance staff, which represents a further advantage in operation.
- the concrete connector has a floor clearance during operation, especially if the sleeper is laid on a ballast track bed.
- the floor spacing of the concrete connection piece at least in a partial area prevents the threshold from spreading i.e. As a result, there can no longer be any bearing pressure in the middle of the threshold, which leads to different bearing pressures that are difficult and / or expensive to control, that is to say essentially bending moments with changing signs.
- the threshold is formed from two sides, namely on the track support areas on the top side and on the floor side in the area of the concrete connecting piece.
- This can be achieved when manufacturing in the rotary formwork process in a horizontal position by using an insert in a formwork that is different from the is poured under the laterally applied concrete.
- a concrete mass suitable for flowing under a formwork in particular self-compacting concrete and / or easily compactable concrete and / or at least concrete with a liquid consistency, for example KF according to DIN 1045, is used. It is obvious that precisely where technologically more complex types of concrete are not available, the comparatively simpler flow concrete can be used, for example in emerging or developing countries.
- the lateral support blocks or swell blocks of the railway concrete sleeper are preferably also reinforced with only one mat, in particular a dynamic mat, and thus absorb the tensile forces from an explosive device on the sleeper river.
- the reinforcement can be basket-shaped, in particular two baskets can be bent, which in particular overlap at the ends at the top inside. Alternatively, there can be bars converging on the inside at the bottom.
- stirrup or basket reinforcements or suspensions may in particular be required in addition, but should be limited due to the effort involved in laying them.
- the formwork can be made considerably easier if the vertical walls of the sleepers have an inclination of about 1:20. If the incline is over 1:40, the formwork is not made much easier; if it is below 1:10, there is no further relief, but an unhelpful change in shape due to walls that are too flat does.
- the elongated precast concrete parts can be manufactured face to face and / or long side to long side in a rotary mold.
- the rotary formwork preferably has an asymmetrical rolling foot, opposite from which it can be lifted with a crane.
- a corresponding asymmetrical shape in relation to the direction of rolling or rolling can, unlike in the case of a circular or elliptically symmetrical shape, reliably avoid instability when turning, since the point of attachment, the center of gravity of the concrete part and the anchorage point of the crane lie vertically in a line.
- this is particularly preferred when tower cranes or mobile cranes are to be used for shifting using the same method.
- Such a procedure is again advantageous because mobile cranes are inexpensive and are readily available everywhere.
- the mobile truck crane can, in particular, move in the direction of rotation without a claw to rotate the usually heavy formwork and thus shorten the lever arm.
- there are alternative turning options such as a so-called Rotomat. It is preferred if, when turning, an end position securing of the parts in the formwork is provided, in particular by means of an entanglement. This prevents the concrete parts from coming loose during turning. It avoids devices on the intermediate webs that either thicken them and make them harder to clean, or that create problems when stripping over joints and edges.
- the formwork can be spindle-supported.
- simple stripping without pressure loading by hammers etc. is achieved, for example, using impact wrenches or the like.
- Threshold Such a procedure makes it easier to evenly fill and / or clear excess concrete of the form, especially in the case of railway sleepers with a formwork element, and still allows drafty work.
- top formwork is provided on the formwork from above, that is to say an insert which can be flowed under, control holes being provided in particular on the top formwork or the insert means, through which there can be a visual inspection in order to check whether actually Concrete has poured under the formwork.
- a free flowing concrete such as flowing concrete, self-compacting concrete and / or easily compactable concrete with formwork to be used together. This ensures that there is good mold filling.
- the formwork form can be slightly inclined with an actuator to facilitate the inflow of concrete under a cover formwork and / or vibrated with a vibrating actuator.
- the actuator is preferably attacked on one side of the formwork form while it can sit opposite. In this way, a flow of the concrete "downhill" is supported.
- long thresholds are replaced by short ones, there is usually no need to rework the embankment shoulder with mineral mixture, etc., as a rule.
- the shape can be cleared from the top, which ensures that a sufficiently uniform surface is also achieved on the top areas that are not under a formwork, which moreover ensures that the shape is completely filled. It should be noted that it is also possible to use a profiled clearing blade without cover formwork, so that the use of stiffer concrete consistencies with large tolerances of the profiling may be necessary.
- the clearing arrangement can be provided with a storage drum or the like, via which concrete is selectively added during clearing can be used to achieve the exact form filling especially in the final process.
- a movable broaching system can be provided which serves for clearing off excess concrete and / or in particular when the clearing blade is folded away, for inserting reinforcement and / or for selectively adding concrete in the final call from a storage drum or the like, which can be tilted into an open position and / or in the case of threshold production or the like is used for the assembly of swell sets, especially by means of
- the clearing blade can preferably be folded back or dismantled for inserting reinforcement and is otherwise arranged on a sliding yoke to enable tilting, clearing clearing movements.
- the multifunctionality reduces the reinforcement transport costs on the construction site and / or the total transport costs of the material to be brought to the construction site, which also contributes if the drive motor of the clearing unit is removable and is designed to drive further units such as lifting traverses etc.
- the sleeper blocks in particular can be rectangular and only separated by a thin web.
- a formwork form which has a stable, preferably also torsionally stiff turning frame, on which two asymmetrical roller feet are provided and on which several formwork chambers are provided in an independent form.
- These formwork chambers are preferably assembled modularly, which enables the production of smaller series even in conventional building construction with the arrangement described. In this way, purlins, beams or long supporting pieces can be produced if buildings made of appropriately arranged, repetitive structures are used.
- the formwork elements can be combined in various ways, which allows flexible pre-assembly of a rotary mold, for example in a warehouse for component formwork modules, after which it is possible to manufacture exactly the required, different parts from one another at the construction site.
- Fig. 1 shows a railroad tie according to the present
- FIG. 2 shows a top view of a form of formwork for precast concrete sleepers
- FIG. 2a shows a detail of the formwork
- FIG. 3 shows a top view of a correspondingly designed, modular formwork form for a small building series
- FIG. 4 shows a sectional view of FIG. 2
- FIG. 5 shows a turning grate as a formwork frame
- 7 shows a multifunction device which can be used in the method for inserting reinforcement, clearing excess concrete, for metering concrete in the final call and for assembling concrete part equipment.
- a railway concrete sleeper 1 generally designated 1, comprises two spaced-apart track support blocks 2a, 2b for supporting the two rails 3a, 3b and a concrete connecting piece 4 in between, which has a slack reinforcement 5.
- the railroad concrete sleeper 1 in FIG. 1 is generally straight-edged at the foot, which allows smaller chamber distances and reduces the cleaning effort after concreting, the foot surface is larger than the top, with a fall of about 1:20.
- the track support areas 2 or track support blocks serve to support the rails 3 on a track bed 6 and are provided in their interior with a single dynamic reinforcement mat 7a, 7b.
- the wheel load is transferred to the mat's tension support via a pressure explosive device.
- This dynamic reinforcement mat consists of a steel braid, whereby the braid-forming wires are not welded to each other at each crossing point of the braid, but only at the edges where the weakening of the fatigue strength can be accepted, especially if dimensioning takes place in such a way that the Edge bar is lost.
- the attachment of the rails three to the track support areas is conventional per se and need no longer be described here. It should be noted that fastening can take place via elements which engage in cast-in anchoring means.
- the concrete connecting piece 4 is spaced from the ballast-formed track bed 6 over the entire width, the clear height H being approximately 60-70 mm. This distance is sufficient to avoid spreading and a central pressure.
- the upper side 4a of the concrete connecting piece which is at the top during operation, is lower than the upper sides of the track 2al, 2bl of the track support areas 2a, 2b to save material.
- a single dynamic reinforcement mat 5 is provided, which has additional bars attached to the edge areas with welding points and is thus able to provide sufficient rigidity and, in the event of the inevitable changing bending moments, for example from changes in position Ensure crack limitation.
- the dynamic mat 5 in the concrete connecting piece 4 is also made of corrugated structural steel.
- the concrete thickness is sufficient for long-term corrosion-preventing structural steel covering.
- the rotary formwork 8 can be rotated about the axis 9 by means of a crane acting on a lifting point 10.
- This lifting point 10 is placed on a lever arm to reduce the crane hook load, which places it at a distance from the formwork.
- the lever arm is optionally attached to one of the two side edges, which allows it to be turned around both edges.
- the rotary formwork is designed so that - a large number of railway concrete sleepers are manufactured at the same time can be, in the illustrated embodiment, two concrete sleepers adjoin each other on the longitudinal side.
- the rolling foot 9 of the rotary formwork 8 is formed in such a way that "striking through the formwork" in an approximately vertical position is avoided due to the turning. To prevent the striking through, the foot has an asymmetry which is not clearly recognizable in the corresponding FIG. 5 for reasons of drawing;
- This figure shows a turning grate 120 with a detachable lifting arm for the crane hook attack and lateral unrolling roller feet 125.
- the asymmetry is to be selected so that in the critical load state after concreting, the hook point 10, the center of gravity and the unwinding point lie in one line when passing through the vertical.
- a carrier grate 130 transmits the hook load 10 to the opposing unrolling feet 125a, the top and bottom plates 140 constructively ensure torsional rigidity when centering.
- the formwork chambers fastened thereon are shown in FIG.
- FIG. 2a The corresponding parts or areas of the railroad tie of FIG. 1 are also drawn in as far as is necessary for a better understanding of the invention.
- the walls 2a2, 2a3 and 2b3, 2a3 of the railway sleeper are beveled and accordingly the formwork 8 also has corresponding bevels 8a2, 8a3.
- an outer wall consists of a straight sheet or a sheet bent only around one axis.
- the floor plate is also made from just one sheet that is bent and axis that is otherwise straight. It should be noted that only one side of the track support area is drawing.
- the free area is effected here by a cover formwork 11 which extends over the entire length of the rotary formwork.
- a ventilation hole 11a is provided in the cover formwork 11, through which it can be checked whether concrete has penetrated the entire area of the concrete web.
- the cover formwork is also designed to serve as a position lock when turning.
- the entire rotary formwork is seated on one side on an actuator 12, as indicated in FIG. 2a, which produces a gradient from chamber 9 to chamber 10 on the concreting side of the parallel concrete mixer.
- the railway concrete sleeper of Fig. 1 is manufactured as follows:
- the dynamic reinforcement mats 5, 7 are inserted.
- Fig. 1 shows these as separate mat pieces;
- Fig. 2a shows as an alternative how only a curved mat can be used. This requires the use of spacers for formwork, as is known per se.
- the threshold dowels 13 are plugged onto bulges 14 as required.
- the formwork 11 is attached and anchored to the rotary formwork.
- Flowable concrete is then poured into the areas of the track support areas.
- the actuator 12 is lifted and thus the concrete is evenly brought under the cover formwork 11 to flow in the direction of chamber 10.
- the uniform inflow is controlled through the control opening 11a.
- the compaction is supported by an external vibrator (not shown).
- FIG. 7 show the clearing device 100 which can also be used for inserting reinforcements and for mounting sleeper equipment.
- the clearing blade (FIG. 7c) which can be folded up for inserting reinforcements can be seen, which is arranged on a slide yoke 102 with play for pushing clearing movement without tilting is.
- a drum that can be filled with concrete is arranged so that concrete flows selectively into the formwork for the final call on its tilting.
- the undercarriage is driven and connected to a portal so high that it is possible to insert reinforcement, cf.
- Fig. 7c. 7b shows the introduction of concrete equipment.
- the time required for the concrete to harden is waited for. Then a hook of the mobile crane is attached to the attachment point 10 and the shape is raised. This is done with a short crane boom while simultaneously moving the mobile crane in the direction of turn, while the rotary tion form is rolled over the roll-off foot 9.
- the asymmetrical shape of the roll-off foot 9 prevents striking through in the area of the almost vertical position and thus ensures a high level of work safety.
- the cover formwork prevents the precast concrete parts from falling out of the rotary formwork, with additional and / or alternatively reinforcements for securing the position (not shown).
- formwork removal can be achieved by inserting formwork means, for example with impact wrenches, or by actuating external vibrators.
- formwork means for example with impact wrenches, or by actuating external vibrators.
- the railway concrete sleepers now lie with their upper side, ie the track support areas 2al, 2bl, towards the upper side and only need to be driven essentially horizontally to the installation site. This facilitates further handling at the site, where the sleeper set can also be fitted. Otherwise, the assembly can take place at the manufacturing site with the support of the impact wrenches hanging on the multifunction device.
- FIG. 3 shows that in the rotary formwork frame 120 it is not absolutely necessary to exclusively manufacture railway sleepers, the variety of the finished part geometry 220 only being indicated. While it is possible to manufacture railway concrete sleepers in solid forms due to their large number of pieces required, it may also be possible to provide a rotary formwork frame on which modular formwork forms, for example also made from cold-formed plastic molded parts produced using the rotational process, are also provided are interchangeable to produce different shapes, which is particularly useful with changing threshold geometries and designs.
- the tolerance-sensitive self-adjusting Entrainment points for attaching the threshold anchors are preferably not replaced on a rigid and rigid floor construction.
- modular formwork forms 100 to formwork module 101 with spacings 102a, b (104) of the lower edge to frame 103, which are caused by spacer sleeves 106, can be spaced apart from frame 103, as well as the difference - Loan widths 108.
- This also shows how load-bearing plates 107 can be provided between different precast concrete parts in such a way that they transfer the load onto the turning frame.
- the spacing of the side plates 107 is variable, the support area 110 for the pull-off level of the clearing blade remains 1-2 cm, which facilitates easy cleaning. It should be noted that in 'simple applications, the parts 105 and 107 can be made of wood.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Manufacturing & Machinery (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
Priority Applications (9)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE10391057T DE10391057D2 (de) | 2002-09-16 | 2003-01-20 | Betonfertigteil und Verfahren |
| AU2003210128A AU2003210128A1 (en) | 2002-06-10 | 2003-01-20 | Precast concrete part and method |
| DE112004000013T DE112004000013D2 (de) | 2003-01-20 | 2004-01-20 | Mobile, kompakte und flexible Feldfabrik |
| EP04703344A EP1587655A2 (fr) | 2003-01-20 | 2004-01-20 | Usine de chantier mobile, compacte et flexible |
| EP04703346A EP1587656A2 (fr) | 2003-01-20 | 2004-01-20 | Coffrage rabattable |
| DE202004021403U DE202004021403U1 (de) | 2003-01-20 | 2004-01-20 | Klappschalung |
| DE112004000547T DE112004000547D2 (de) | 2003-01-20 | 2004-01-20 | Klappschalung |
| PCT/DE2004/000080 WO2004065086A2 (fr) | 2003-01-20 | 2004-01-20 | Usine de chantier mobile, compacte et flexible |
| PCT/DE2004/000070 WO2004065087A2 (fr) | 2003-01-20 | 2004-01-20 | Coffrage rabattable |
Applications Claiming Priority (12)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE10225766 | 2002-06-10 | ||
| DE10225766.3 | 2002-06-10 | ||
| EPPCT/EP02/08144 | 2002-07-02 | ||
| PCT/EP2002/008144 WO2003012225A2 (fr) | 2001-07-20 | 2002-07-22 | Structure et procede de construction |
| DE10243083 | 2002-09-16 | ||
| DE10243083.7 | 2002-09-16 | ||
| DE10247596.2 | 2002-10-11 | ||
| DE10247596 | 2002-10-11 | ||
| DE10250283.8 | 2002-10-28 | ||
| DE10250283 | 2002-10-28 | ||
| DE10251850.5 | 2002-11-07 | ||
| DE10251850 | 2002-11-07 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2003104562A1 true WO2003104562A1 (fr) | 2003-12-18 |
Family
ID=29741161
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/DE2003/000156 Ceased WO2003104562A1 (fr) | 2002-06-01 | 2003-01-20 | Element beton prefabrique et procede |
Country Status (1)
| Country | Link |
|---|---|
| WO (1) | WO2003104562A1 (fr) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2007062799A1 (fr) * | 2005-12-01 | 2007-06-07 | Voestalpine Bwg Gmbh & Co.Kg. | Poutre en beton |
| DE102007025034A1 (de) | 2007-05-29 | 2008-12-04 | Bwg Gmbh & Co. Kg | Betonschwelle |
| DE102007063455A1 (de) * | 2007-12-27 | 2009-07-02 | Institut für Fertigteiltechnik und Fertigbau Weimar e.V. | Beton und Bahnschwelle aus Beton |
| DE102008037171A1 (de) | 2008-08-06 | 2010-02-11 | Institut für Fertigteiltechnik und Fertigbau Weimar e.V. | Beton und Bahnschwelle aus Beton |
| EP2722439A4 (fr) * | 2011-06-16 | 2014-12-10 | Nam Hun Kang | Procédé de fabrication d'un bloc de béton tridimensionnel plein et procédé permettant de déposer des voies de béton à l'aide du bloc de béton fabriqué au moyen du procédé |
| CN106945164A (zh) * | 2017-03-22 | 2017-07-14 | 中交二公局铁路工程有限公司 | 适应高温及高湿环境用的混凝土轨枕的生产系统及其方法 |
| CN108252321A (zh) * | 2018-01-26 | 2018-07-06 | 中国冶集团有限公司 | 一种设备轨道整体安装方法 |
| CN111086105A (zh) * | 2019-12-30 | 2020-05-01 | 西藏藏建科技股份有限公司 | 一种墙板多工位连续生产系统 |
| WO2023159747A1 (fr) * | 2022-02-24 | 2023-08-31 | 福建群峰机械有限公司 | Procédé de production de prémoulé |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR540457A (fr) * | 1921-05-19 | 1922-07-11 | Organe perfectionné d'appui-rails en général | |
| CH237752A (fr) * | 1942-08-29 | 1945-05-31 | Laruelle Joseph | Procédé de fabrication de pièces moulées et dispositif pour sa mise en oeuvre. |
| DE830063C (de) * | 1948-09-21 | 1952-01-31 | Dyckerhoff & Widmann Ag | Eisenbahnschwelle aus Beton |
| DE1083169B (de) * | 1956-06-07 | 1960-06-09 | Betoma Meyer Farion & Co K G | Verfahren und Vorrichtung zum Herstellen von Spannbetonteilen |
| CA997536A (en) * | 1973-05-04 | 1976-09-28 | Andre Pilish | Mobile concrete manufacturing plant |
| DE4427401A1 (de) * | 1994-08-03 | 1996-02-08 | Wayss & Freytag Ag | Vorrichtung zur Herstellung von im wesentlichen stabförmigen Spannbetonfertigteilen, vornehmlich Schwellen |
-
2003
- 2003-01-20 WO PCT/DE2003/000156 patent/WO2003104562A1/fr not_active Ceased
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR540457A (fr) * | 1921-05-19 | 1922-07-11 | Organe perfectionné d'appui-rails en général | |
| CH237752A (fr) * | 1942-08-29 | 1945-05-31 | Laruelle Joseph | Procédé de fabrication de pièces moulées et dispositif pour sa mise en oeuvre. |
| DE830063C (de) * | 1948-09-21 | 1952-01-31 | Dyckerhoff & Widmann Ag | Eisenbahnschwelle aus Beton |
| DE1083169B (de) * | 1956-06-07 | 1960-06-09 | Betoma Meyer Farion & Co K G | Verfahren und Vorrichtung zum Herstellen von Spannbetonteilen |
| CA997536A (en) * | 1973-05-04 | 1976-09-28 | Andre Pilish | Mobile concrete manufacturing plant |
| DE4427401A1 (de) * | 1994-08-03 | 1996-02-08 | Wayss & Freytag Ag | Vorrichtung zur Herstellung von im wesentlichen stabförmigen Spannbetonfertigteilen, vornehmlich Schwellen |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2007062799A1 (fr) * | 2005-12-01 | 2007-06-07 | Voestalpine Bwg Gmbh & Co.Kg. | Poutre en beton |
| KR101079566B1 (ko) | 2005-12-01 | 2011-11-04 | 파우아에 게엠베하 | 콘크리트 침목 |
| DE102007025034A1 (de) | 2007-05-29 | 2008-12-04 | Bwg Gmbh & Co. Kg | Betonschwelle |
| DE102007063455A1 (de) * | 2007-12-27 | 2009-07-02 | Institut für Fertigteiltechnik und Fertigbau Weimar e.V. | Beton und Bahnschwelle aus Beton |
| DE102007063455B4 (de) * | 2007-12-27 | 2010-08-19 | Institut für Fertigteiltechnik und Fertigbau Weimar e.V. | Leichtverdichtbare oder selbstverdichtende Betonmischung, Verwendung solcher Mischungen und Bahnschwelle aus Beton |
| DE102008037171A1 (de) | 2008-08-06 | 2010-02-11 | Institut für Fertigteiltechnik und Fertigbau Weimar e.V. | Beton und Bahnschwelle aus Beton |
| EP2722439A4 (fr) * | 2011-06-16 | 2014-12-10 | Nam Hun Kang | Procédé de fabrication d'un bloc de béton tridimensionnel plein et procédé permettant de déposer des voies de béton à l'aide du bloc de béton fabriqué au moyen du procédé |
| CN106945164A (zh) * | 2017-03-22 | 2017-07-14 | 中交二公局铁路工程有限公司 | 适应高温及高湿环境用的混凝土轨枕的生产系统及其方法 |
| CN106945164B (zh) * | 2017-03-22 | 2019-05-31 | 中交二公局铁路工程有限公司 | 适应高温及高湿环境用的混凝土轨枕的生产系统及其方法 |
| CN108252321A (zh) * | 2018-01-26 | 2018-07-06 | 中国冶集团有限公司 | 一种设备轨道整体安装方法 |
| CN111086105A (zh) * | 2019-12-30 | 2020-05-01 | 西藏藏建科技股份有限公司 | 一种墙板多工位连续生产系统 |
| WO2023159747A1 (fr) * | 2022-02-24 | 2023-08-31 | 福建群峰机械有限公司 | Procédé de production de prémoulé |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2088244B1 (fr) | Pont en béton armé ou pont de construction composite et methode pour sa fabrication | |
| DE69913977T2 (de) | Methode zum herstellen eines plattenbodens und ein plattenboden | |
| EP2623670B1 (fr) | Voie sans ballast pour véhicules ferroviaires | |
| EP1026320B1 (fr) | Méthode pour la fabrication d'une voie ferrée sans ballast | |
| DE69108246T2 (de) | Verfahren zur errichtung einer gründungsstruktur für eine gebäude-unterkonstruktion. | |
| WO2003104562A1 (fr) | Element beton prefabrique et procede | |
| EP1882777B1 (fr) | Procédé pour fabriquer une voie ferrée sans ballast | |
| DE10004194C2 (de) | Verfahren zur Fertigung einer festen Schienenfahrbahn auf einer Brücke | |
| DE4430769C2 (de) | Eisenbahnoberbau mit einem auf einer durchgehenden Tragplatte aus Stahlbeton aufgelagerten Gleisrost | |
| DE4205192A1 (de) | Bahnsteig | |
| EP1048783A1 (fr) | Voie ferrée et sa méthode de réalisation | |
| EP2166149B1 (fr) | Unité de pièce de structure de voie ferrée | |
| AT520614B1 (de) | Verfahren zur Herstellung einer Fahrbahnplatte mit untenliegenden Fertigteilplatten | |
| DE10261641A1 (de) | Verfahren zum Herstellen einer Festen Fahrbahn und Fahrweg | |
| EP1738027B1 (fr) | Traverse de support pour voie ferree a ballast et procede de realisation | |
| DE19629029A1 (de) | Verfahren zur rationellen Herstellung von Brückentragwerken für Verkehrswege aller Art einschl. biegesteifer Rahmeneckverbindungen zwischen Fertigteil- und örtlich hergestellten Elementen | |
| AT500876B1 (de) | Verfahren zum herstellen einer festen fahrbahn für schienenfahrzeuge | |
| DE878702C (de) | Stahlbeton-Fertigbauteil in Dielen- oder Bohlenform | |
| DE3203980C2 (de) | Unterführungsbauwerk sowie Verfahren zu seiner Herstellung | |
| DE29917553U1 (de) | Gleisanlagen-Tragplatte, Gleisanlagen-Unterbau und Gleisanlage | |
| DE19944783A1 (de) | Feste-Fahrbahn-System | |
| AT344780B (de) | Spannbeton-fahrbahnplatte | |
| DE2649132A1 (de) | Laermschutzwand | |
| DE692207C (de) | Hohlsteinbalken fuer Hohlsteindecken mit zwischen Stahlprofiltraegern verlegten Hohlsteinbalken | |
| DE19814538A1 (de) | Verfahren zur Herstellung eines gekrümmten, eine Länge überspannenden Bauwerks |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AK | Designated states |
Kind code of ref document: A1 Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ OM PH PL PT RO RU SC SD SE SG SK SL TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW |
|
| AL | Designated countries for regional patents |
Kind code of ref document: A1 Designated state(s): MZ SD SL AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LU MC NL PT SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
| REF | Corresponds to |
Ref document number: 10391057 Country of ref document: DE Date of ref document: 20041111 Kind code of ref document: P |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 10391057 Country of ref document: DE |
|
| REG | Reference to national code |
Ref country code: DE Ref legal event code: 8607 |
|
| 122 | Ep: pct application non-entry in european phase | ||
| NENP | Non-entry into the national phase |
Ref country code: JP |
|
| WWW | Wipo information: withdrawn in national office |
Ref document number: JP |