WO2003002817A1 - Panels or beams for tubular railway track - Google Patents

Panels or beams for tubular railway track Download PDF

Info

Publication number
WO2003002817A1
WO2003002817A1 PCT/ZA2002/000075 ZA0200075W WO03002817A1 WO 2003002817 A1 WO2003002817 A1 WO 2003002817A1 ZA 0200075 W ZA0200075 W ZA 0200075W WO 03002817 A1 WO03002817 A1 WO 03002817A1
Authority
WO
WIPO (PCT)
Prior art keywords
lengths
tubular
concrete
gap
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/ZA2002/000075
Other languages
French (fr)
Inventor
Peter Gunter Kusel
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of WO2003002817A1 publication Critical patent/WO2003002817A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B19/00Machines or methods for applying the material to surfaces to form a permanent layer thereon
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B3/00Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails
    • E01B3/28Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone
    • E01B3/38Longitudinal sleepers; Longitudinal sleepers integral or combined with tie-rods; Combined longitudinal and transverse sleepers; Layers of concrete supporting both rails
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/10Making longitudinal or transverse sleepers or slabs in situ or embedding them

Definitions

  • This invention relates to panels or beams for tubular railway track.
  • the concept comprises the steps of preparing longitudinal trenches for the rails and then laying flexible tubes in the trenches followed to filling these tubes with concrete.
  • the resulting structure accepts the feet of the rails and suitable pads or the like may be used to dampen the forces on the concrete-filled tubes.
  • the tubular track concept provides full and continuous support below the rails, resulting in lower stresses and possible smaller rail size. There is also a fixed geometry with a resultant reduction in maintenance.
  • the steel components for holding the gauge and also the rail to the tubes are formed around the tubes as opposed to being cast into a beam.
  • the total structure is flexible and eliminates the normal shear forces created when cast in concrete. All forces created by trains are transferred to the tubes in compression which is the desirable situation for concrete.
  • a method of forming tubular track includes the steps of filling short open lengths of tubular material with a settable composition, allowing the composition to set, in a predetermined shape or configuration, closing the lengths and inverting them for use as panels for laying tubular track
  • the concept of the invention has been derived from the observation that the top zone of cured concrete has a very low compression strength whereas the middle and lower zones have far greater strength.
  • the short lengths of tubular material may be laid in a former of the desired curvature or shape and the edges thereof provided with means to fasten them together when the concrete or other settable composition has set.
  • the edges may be provided with hooks and loops type of connection.
  • the short lengths are formed as above, but the last filling before complete closing of the short lengths includes a final pumping of concrete.
  • the short lengths are located in position and adjustments are made in relation to their location, height and the like and then fixing them in position and locating rails thereon.
  • the invention also extends to such short lengths of tubular structure which are preferably provided in pairs of the correct gauge.
  • These short lengths may be easily transported to the required work site without the rails, and stacked in layers; after which they can be laid end to end in pre-prepared trenches or like formations. After this the correct alignment can be achieved, firstly by lifting and aligning the lengths and filling the gap between the trench or any formations in the trench, and the bottom of the lengths with a coarse material such as sand. Then the final alignment can be achieved by filling the remaining gap with fibre reinforced concrete of other durable material which should also have resilient properties.
  • another final alignment may be accomplished by using the original tubular track concept - for example by placing a tube or bag in the gap and pumping it full of concrete or other suitable material to take up the shape of the gap.
  • the individual lengths may have protruding reinforcing and the adjacent reinforcing may overlap. This may be joined using the original method of using a bag and filling it with concrete or the like.
  • the individual lengths may also be designed to interlock to form a continuous support for the rails.
  • the individual lengths may also include hoops or straps to assist in retaining the shape or configuration. These hoops also serve to accept the transverse forces which occur during use.
  • Figure 1 is a cross section view of tubular elements in their final position
  • Figure 2 is a similar view of a tubular element showing the formers used to shape the tubular elements
  • Figure 3 is a sectional view of an arrangement for forming the tubular elements and showing the inversion operation
  • Figure 4 is a sectional view of tubular track where the beam is formed to fill the gap between the bottom of the rails and the soil formation therebelow;
  • Figure 5 is a similar view but showing the filling of the gap between the bottom of the rails and the soil formation therebelow.
  • formers 10 which receive and retain a length of a tubular member for supporting a rail.
  • This member takes the form of an elongated bag 11 of flexible material which has been filled with concrete.
  • Suitable transverse (12) and longitudinal (13) reinforcing rods are provided.
  • the formers 10 are designed to correspond with the desired shape of the tubular element, which as shown in Figure 1 comprises connecting means 14, for example hooks and loops attachment (such as Velcro Trade Mark).
  • the rails 17 are secured by means of clips 16.
  • the length of material 11 is located in the shuttering 19 which is positioned to achieve a particular cross sectional shape of the element and is held in place by toggle clamps .
  • Concrete is applied either by being pumped in from a side or end or poured from a top position as indicated by -x- until full when the tubular element is formed by closing the connections means 14.
  • a final filling operation is carried out before the final connection is made.
  • the aggregate is then allowed to set and is then inverted and then placed in position using suitable guide means to assure correct geometry.
  • suitable guide means are shown as reference 22 which is an I-beam and 23 which is guide member.
  • the rails 17 are shown in dotted line.
  • the inversion results in the bottom surface of the element to be straight and smooth, while the top surface may be irregular because it becomes the bottom surface in use.
  • the former 24 which is applied by press screws 25 may include a grid pattern, which also serves to improve traction with the earth base.
  • the tubular element is located in hoops 27 and which have rail clips 16.
  • the tubular element rests on a layer 28 of soil.
  • Backfill 29 is applied and a layer 30 of concrete is formed between the members. This layer may comprise a drain.
  • tubular members are located as shown but with the gap between the bottom of the tubular elements and the surface 31 of the soil being filled with a filler material 32.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

Tubular track is produced by using short lengths of tubular material (11) which are filled with a settable composition such as concrete, allowing it to set in a required shape and configuration, closing the lengths and then inverting them so that the lower zone with high compression strength becomes the upper zone. The short lengths are located in position and adjustments carried out and then fixed in positions.

Description

PANELS OR BEAMS FOR TUBULAR RAILWAY TRACK
TECHNICAL FIELD OF THE INVENTION
This invention relates to panels or beams for tubular railway track.
BACKGROUND ART
The concept of tubular track for railways was first mooted in my RSA Patent No.
97/11696. The concept comprises the steps of preparing longitudinal trenches for the rails and then laying flexible tubes in the trenches followed to filling these tubes with concrete. The resulting structure accepts the feet of the rails and suitable pads or the like may be used to dampen the forces on the concrete-filled tubes.
The tubular track concept provides full and continuous support below the rails, resulting in lower stresses and possible smaller rail size. There is also a fixed geometry with a resultant reduction in maintenance. In addition, the steel components for holding the gauge and also the rail to the tubes are formed around the tubes as opposed to being cast into a beam. The total structure is flexible and eliminates the normal shear forces created when cast in concrete. All forces created by trains are transferred to the tubes in compression which is the desirable situation for concrete.
While the system of laying the tubular track as described in the patent is satisfactory, it has been realised that it would be convenient if the time taken for the assembling and construction is shortened. Thus, one of the major time - taking steps is the curing of the concrete and also the logistics of construction including the transport of heavy machinery for filling the tubes with concrete.
It is an object of the present invention to provide a method and integers for effecting time saving and therefore reducing the costs for construction and reconstruction. Another object of the present invention is to improve the compressive strength of the tubular track
DISCLOSURE OF THE INVENTION
According to the invention a method of forming tubular track includes the steps of filling short open lengths of tubular material with a settable composition, allowing the composition to set, in a predetermined shape or configuration, closing the lengths and inverting them for use as panels for laying tubular track
The concept of the invention has been derived from the observation that the top zone of cured concrete has a very low compression strength whereas the middle and lower zones have far greater strength.
In a preferred form of the invention the short lengths of tubular material may be laid in a former of the desired curvature or shape and the edges thereof provided with means to fasten them together when the concrete or other settable composition has set. Thus the edges may be provided with hooks and loops type of connection.
In an example of the invention, the short lengths are formed as above, but the last filling before complete closing of the short lengths includes a final pumping of concrete.
In operation the short lengths are located in position and adjustments are made in relation to their location, height and the like and then fixing them in position and locating rails thereon.
The invention also extends to such short lengths of tubular structure which are preferably provided in pairs of the correct gauge.
These short lengths may be easily transported to the required work site without the rails, and stacked in layers; after which they can be laid end to end in pre-prepared trenches or like formations. After this the correct alignment can be achieved, firstly by lifting and aligning the lengths and filling the gap between the trench or any formations in the trench, and the bottom of the lengths with a coarse material such as sand. Then the final alignment can be achieved by filling the remaining gap with fibre reinforced concrete of other durable material which should also have resilient properties.
If required, another final alignment may be accomplished by using the original tubular track concept - for example by placing a tube or bag in the gap and pumping it full of concrete or other suitable material to take up the shape of the gap.
The individual lengths may have protruding reinforcing and the adjacent reinforcing may overlap. This may be joined using the original method of using a bag and filling it with concrete or the like.
The individual lengths may also be designed to interlock to form a continuous support for the rails.
The individual lengths may also include hoops or straps to assist in retaining the shape or configuration. These hoops also serve to accept the transverse forces which occur during use.
It will be appreciated that if there is any subsidence or settlement of the soil, some panels may be lifted, filler material; from under the element being removed, the elements being returned to their desired position and the gap filled with aggregate. In the event that elements need to be replaced because of damage the same operation may be carried out.
BRIEF DESCRIPTION OF THE DRA WINGS
An embodiment of the invention is described below with reference to the accompanying drawings, in which:
Figure 1 is a cross section view of tubular elements in their final position; Figure 2 is a similar view of a tubular element showing the formers used to shape the tubular elements;
Figure 3 is a sectional view of an arrangement for forming the tubular elements and showing the inversion operation; Figure 4 is a sectional view of tubular track where the beam is formed to fill the gap between the bottom of the rails and the soil formation therebelow; and
Figure 5 is a similar view but showing the filling of the gap between the bottom of the rails and the soil formation therebelow.
BEST MODE FOR CARRYING OUT THE INVENTION
Referring first to Figures 1 and 2, formers 10 are shown which receive and retain a length of a tubular member for supporting a rail. This member takes the form of an elongated bag 11 of flexible material which has been filled with concrete. Suitable transverse (12) and longitudinal (13) reinforcing rods are provided.
The formers 10 are designed to correspond with the desired shape of the tubular element, which as shown in Figure 1 comprises connecting means 14, for example hooks and loops attachment (such as Velcro Trade Mark). The rails 17 are secured by means of clips 16.
In Figure 1 the formers 10 have been removed and the parallel tracks are joined by means of ties 15.
Referring now to Figure 3 the length of material 11 is located in the shuttering 19 which is positioned to achieve a particular cross sectional shape of the element and is held in place by toggle clamps . Concrete is applied either by being pumped in from a side or end or poured from a top position as indicated by -x- until full when the tubular element is formed by closing the connections means 14. As mentioned above a final filling operation is carried out before the final connection is made. The aggregate is then allowed to set and is then inverted and then placed in position using suitable guide means to assure correct geometry. These latter means are shown as reference 22 which is an I-beam and 23 which is guide member. The rails 17 are shown in dotted line.
It will be appreciated that the inversion results in the bottom surface of the element to be straight and smooth, while the top surface may be irregular because it becomes the bottom surface in use. Thus the former 24 which is applied by press screws 25 may include a grid pattern, which also serves to improve traction with the earth base.
In Figure 4 the tubular element is located in hoops 27 and which have rail clips 16. The tubular element rests on a layer 28 of soil. Backfill 29 is applied and a layer 30 of concrete is formed between the members. This layer may comprise a drain.
In Figure 5 the tubular members are located as shown but with the gap between the bottom of the tubular elements and the surface 31 of the soil being filled with a filler material 32.

Claims

CLAIMS:
1. A method of forming tubular track characterised by the steps of filling short open lengths of tubular material with a settable composition, allowing the composition to set, in a predetermined shape or configuration, closing the lengths and inverting them for use as panels for laying tubular track.
2. The method according to claim 1 characterised in that the short lengths of tubular material are laid in a former of the desired curvature or shape and the edges thereof provided with means to fasten them together when the concrete or other settable composition has set.
3. The method according to claim 2 characterised in that the edges of the tubular material are provided with hooks and loops type of connection.
4. The method according to any of the above claims characterised in that the short lengths are located in position and adjustments are made in relation to their location, height and the like and then fixing them in position and locating rails thereon.
5. The method according to any of the above claims characterised in that the correct alignment is achieved firstly by lifting and aligning the lengths and filling the gap between the trench or any formation in the trench, and the bottom of the lengths with a coarse material such as sand, and then a final alignment can be achieved by filling the remaining gap with fibre reinforced concrete of other durable material which should also have resilient properties.
6. The method according to claim 5 characterised in that another final adjustment is achieved by placing a tube or bag in the gap and pumping it full of concrete or other suitable material to take up the shape of the gap.
7. The method according to any of the above claims characterised in that the lengths 5 of tubular structure are joined by the method of utilising a bag located therebetween and the bag is filled with concrete.
8. Short lengths of tubular structure prepared by the method of any of the above claims.
9. Lengths of tubular structure according to claim 8 provided in pairs of the correct 10 gauge.
10. The lengths of tubular structure according to claims 8 or 9 characterised in that protruding reinforcing is provided, the adjacent reinforcing being adapted to overlap.
11. The lengths according to any of claims 8 to 10 characterised in that interlocking means is provided to form a continuous support for the rails.
15 12. The lengths according to any of claims 8 to 11 charaterised in that hoops or straps are provided to assist in retaining the shape and configuration, the hoops also serving to accept the transverse forces during use.
PCT/ZA2002/000075 2001-05-16 2002-05-14 Panels or beams for tubular railway track Ceased WO2003002817A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
ZA200103972 2001-05-16
ZA2001/3972 2001-05-16

Publications (1)

Publication Number Publication Date
WO2003002817A1 true WO2003002817A1 (en) 2003-01-09

Family

ID=25589162

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/ZA2002/000075 Ceased WO2003002817A1 (en) 2001-05-16 2002-05-14 Panels or beams for tubular railway track

Country Status (1)

Country Link
WO (1) WO2003002817A1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1112613A (en) * 1914-02-18 1914-10-06 Frank O Hellstrom Rail-support.
US4947756A (en) * 1988-08-18 1990-08-14 Peter G. Kusel Laying railway track
DE19855350A1 (en) * 1998-12-01 2000-06-15 Bahnbau Wels Gmbh Wels Method to construct railway track on base plates of permanent ways uses setting stabilizer asphalt etc. to stabilizer sleepers, to which rails are fastened after setting

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1112613A (en) * 1914-02-18 1914-10-06 Frank O Hellstrom Rail-support.
US4947756A (en) * 1988-08-18 1990-08-14 Peter G. Kusel Laying railway track
DE19855350A1 (en) * 1998-12-01 2000-06-15 Bahnbau Wels Gmbh Wels Method to construct railway track on base plates of permanent ways uses setting stabilizer asphalt etc. to stabilizer sleepers, to which rails are fastened after setting

Similar Documents

Publication Publication Date Title
US7114305B2 (en) Hybrid arched overfilled structure
JP6061154B2 (en) Foundation systems for bridges and other structures
CN207452594U (en) A kind of urban track traffic prestressing force slab track
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN108286210B (en) A kind of rapid constructing method of embedded railway points system
CN101775772B (en) Sloping tensioning method two-way prestressed concrete pavement construction method
TW201704594A (en) Module for structure
CN101333801A (en) Cast-in-situ beam-making construction method of assembled support
CN101701439A (en) Steel reinforcement cage track skeleton method construction process of steel spring floating plate track
CN109235292A (en) Railroad bridge changes beam process and changes girder system system
CN110005169A (en) A kind of cracking resistance process with stressed seamless terrace
CN110747903A (en) Porous frame bridge and assembling construction method thereof
CN108842597A (en) A kind of municipal construction temporary concrete steel structure bridge and its installation method
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
CN108842624A (en) High pier Cast-in-place Bent Cap combined type overhanging formwork system and construction method
KR102097122B1 (en) Precast mold for platform on piles system and concrete slab track construction method therewith
CN113494055A (en) Double-locking structure for closure section of long-span bridge and construction method
CN109972519A (en) The construction method of precast hollow pier mounting structure
CN110258217A (en) The horizontal lift beam overhead transmission line construction method of prestressing force
CN105442457A (en) Construction structure and method for extending bridge floor plate bridge filled with fine sand
US4576510A (en) Technique for the location of expansion joints when casting a concrete bed
CN104612142B (en) Integral abutment bridge structure based on composite flexible piles and construction method thereof
CA2637208A1 (en) Method for producing a ballastless track
CN110777635A (en) Side arch rib construction method and side arch rib
CN111851155A (en) Steel spring floating plate construction method based on concentric tunnel of line tunnel

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ OM PH PL PT RO RU SD SE SG SI SK SL TJ TM TN TR TT TZ UA UG US UZ VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
121 Ep: the epo has been informed by wipo that ep was designated in this application
WWE Wipo information: entry into national phase

Ref document number: 2003/08457

Country of ref document: ZA

Ref document number: 200308457

Country of ref document: ZA

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 69(1) EPC FORM 1205A DATED 02-06-2004

122 Ep: pct application non-entry in european phase
NENP Non-entry into the national phase

Ref country code: JP

WWW Wipo information: withdrawn in national office

Country of ref document: JP