WO1994020791A1 - Four a fusion de plasma et mode de fonctionnement de ce four - Google Patents

Four a fusion de plasma et mode de fonctionnement de ce four Download PDF

Info

Publication number
WO1994020791A1
WO1994020791A1 PCT/JP1994/000362 JP9400362W WO9420791A1 WO 1994020791 A1 WO1994020791 A1 WO 1994020791A1 JP 9400362 W JP9400362 W JP 9400362W WO 9420791 A1 WO9420791 A1 WO 9420791A1
Authority
WO
WIPO (PCT)
Prior art keywords
slag
plasma
furnace
gas
exhaust gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/JP1994/000362
Other languages
English (en)
French (fr)
Inventor
Tomio Suzuki
Yasuo Higashi
Shigeyoshi Tagashira
Motoo Yamada
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kansai Electric Power Co Inc
Kobe Steel Ltd
Original Assignee
Kansai Electric Power Co Inc
Kobe Steel Ltd
Kansai Denryoku KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP7520093A external-priority patent/JPH06257725A/ja
Priority claimed from JP7875793A external-priority patent/JPH06265134A/ja
Priority claimed from JP10992093A external-priority patent/JPH06300234A/ja
Priority claimed from JP5109919A external-priority patent/JP3032400B2/ja
Priority claimed from JP5120790A external-priority patent/JP3039590B2/ja
Priority claimed from JP1993031300U external-priority patent/JP2591142Y2/ja
Priority to EP19940908506 priority Critical patent/EP0645584B1/en
Priority to DE69411835T priority patent/DE69411835T2/de
Application filed by Kansai Electric Power Co Inc, Kobe Steel Ltd, Kansai Denryoku KK filed Critical Kansai Electric Power Co Inc
Priority to CA 2135204 priority patent/CA2135204C/en
Priority to DK94908506T priority patent/DK0645584T3/da
Publication of WO1994020791A1 publication Critical patent/WO1994020791A1/ja
Anticipated expiration legal-status Critical
Priority to US08/556,022 priority patent/US5579705A/en
Ceased legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05HPLASMA TECHNIQUE; PRODUCTION OF ACCELERATED ELECTRICALLY-CHARGED PARTICLES OR OF NEUTRONS; PRODUCTION OR ACCELERATION OF NEUTRAL MOLECULAR OR ATOMIC BEAMS
    • H05H1/00Generating plasma; Handling plasma
    • H05H1/24Generating plasma
    • H05H1/26Plasma torches
    • H05H1/32Plasma torches using an arc
    • H05H1/34Details, e.g. electrodes, nozzles
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B3/00Charging the melting furnaces
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B5/00Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
    • C03B5/005Melting in furnaces; Furnaces so far as specially adapted for glass manufacture of glass-forming waste materials
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B5/00Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
    • C03B5/02Melting in furnaces; Furnaces so far as specially adapted for glass manufacture in electric furnaces, e.g. by dielectric heating
    • C03B5/025Melting in furnaces; Furnaces so far as specially adapted for glass manufacture in electric furnaces, e.g. by dielectric heating by arc discharge or plasma heating
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B5/00Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
    • C03B5/16Special features of the melting process; Auxiliary means specially adapted for glass-melting furnaces
    • C03B5/235Heating the glass
    • C03B5/237Regenerators or recuperators specially adapted for glass-melting furnaces
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B5/00Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
    • C03B5/16Special features of the melting process; Auxiliary means specially adapted for glass-melting furnaces
    • C03B5/26Outlets, e.g. drains, siphons; Overflows, e.g. for supplying the float tank, tweels
    • C03B5/265Overflows; Lips; Tweels
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B13/00Making spongy iron or liquid steel, by direct processes
    • C21B13/12Making spongy iron or liquid steel, by direct processes in electric furnaces
    • C21B13/125By using plasma
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/08Incineration of waste; Incinerator constructions; Details, accessories or control therefor having supplementary heating
    • F23G5/085High-temperature heating means, e.g. plasma, for partly melting the waste
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J9/00Preventing premature solidification of molten combustion residues
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27BFURNACES, KILNS, OVENS OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
    • F27B3/00Hearth-type furnaces, e.g. of reverberatory type; Electric arc furnaces ; Tank furnaces
    • F27B3/08Hearth-type furnaces, e.g. of reverberatory type; Electric arc furnaces ; Tank furnaces heated electrically, with or without any other source of heat
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27BFURNACES, KILNS, OVENS OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
    • F27B3/00Hearth-type furnaces, e.g. of reverberatory type; Electric arc furnaces ; Tank furnaces
    • F27B3/10Details, accessories or equipment, e.g. dust-collectors, specially adapted for hearth-type furnaces
    • F27B3/18Arrangements of devices for charging
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27BFURNACES, KILNS, OVENS OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
    • F27B3/00Hearth-type furnaces, e.g. of reverberatory type; Electric arc furnaces ; Tank furnaces
    • F27B3/10Details, accessories or equipment, e.g. dust-collectors, specially adapted for hearth-type furnaces
    • F27B3/19Arrangements of devices for discharging
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D17/00Arrangements for using waste heat; Arrangements for using, or disposing of, waste gases
    • F27D17/30Arrangements for extraction or collection of waste gases; Hoods therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D3/00Charging; Discharging; Manipulation of charge
    • F27D3/15Tapping equipment; Equipment for removing or retaining slag
    • F27D3/1545Equipment for removing or retaining slag
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G2202/00Combustion
    • F23G2202/10Combustion in two or more stages
    • F23G2202/102Combustion in two or more stages with supplementary heating
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G2202/00Combustion
    • F23G2202/10Combustion in two or more stages
    • F23G2202/103Combustion in two or more stages in separate chambers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G2204/00Supplementary heating arrangements
    • F23G2204/20Supplementary heating arrangements using electric energy
    • F23G2204/201Plasma
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D99/00Subject matter not provided for in other groups of this subclass
    • F27D99/0001Heating elements or systems
    • F27D99/0006Electric heating elements or system
    • F27D2099/0031Plasma-torch heating
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D99/00Subject matter not provided for in other groups of this subclass
    • F27D99/0001Heating elements or systems
    • F27D2099/006Auxiliary heating, e.g. in special conditions or at special times
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D99/00Subject matter not provided for in other groups of this subclass
    • F27D2099/0085Accessories
    • F27D2099/0095Means to collect the slag or spilled metal, e.g. vessels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/10Reduction of greenhouse gas [GHG] emissions
    • Y02P10/134Reduction of greenhouse gas [GHG] emissions by avoiding CO2, e.g. using hydrogen
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/50Glass production, e.g. reusing waste heat during processing or shaping

Definitions

  • the present invention relates to a plasma melting furnace for melting municipal solid waste, industrial waste, automobile shredder dust, sludge, or exhaust gas such as incinerated ash with a plasma arc generated by a plasma torch and converting it into slag, and a method of operating the same. Get involved.
  • it relates to a material capable of realizing stable slag removal, efficiently melting the slag, and making exhaust gas as clean as possible.
  • incinerated ash includes: These harmful substances and metals remain. Therefore, there is a problem that the landfill disposal of the incinerated ash pollutes the groundwater. Since the incinerated ash has a low specific gravity, a large volume of landfill is required. In addition, landfills made with incinerated ash have weak ground, making it difficult to use the site.
  • the plasma melting furnace includes a melting furnace in which a pool of molten slag is formed in a furnace body having a supply hole for incinerated ash and a discharge hole for slag, and a plasma arc generator for generating a plasma arc on the slag. It is equipped with a plasma torch.
  • the incineration ash supplied from the supply hole is melted by the plasma arc, and a pool of molten slag is formed in the furnace body, and the slag overflowing from the pool is continuously discharged from the discharge hole and solidified by cooling.
  • the plasma torch In a conventional melting furnace used for metal melting, the plasma torch is located at the center of the cylindrical furnace, and as shown in British Patent 1,390,351 / 3, the plasma torch is rotated around the center of the furnace. Some are free to roll. In addition, as shown in the report of the Tohoku University Mineral Processing Research Institute Vol. 41, No. 2, P170-171 (1985), in a plasma melting furnace for direct reduction of chromite ore, the plasma torch was kept tilted. Some rotate and heat evenly over a large area.
  • the incinerated ash to be melted is a fine particle having a particle size of several micrometers.
  • the incineration ash is operated under a negative pressure from the supply hole side of the incineration ash to the discharge hole of the slag to prevent leakage to the atmosphere outside the furnace body.
  • the exhaust gas discharged from the plasma melting furnace is a high-temperature gas at around 130 ° C.
  • it is passed through a flue lined with refractories. It is quenched by a cooler such as a water spray cooling chamber and released to the atmosphere via a dust collector.
  • a heat exchanger may be connected to the flue to recover waste heat.
  • the structure of the plasma torch provided in such a plasma melting furnace includes an anode 651, a cathode 652, and a cathode, as shown in the sectional views of FIGS. 22 (a) and 22 (b). It has a water cooling jacket 653 and a plasma gas injection port 655.
  • the plasma torch has two operation modes depending on how the electrodes are connected. As shown in FIG. 22 (a), a non-transfer mode in which a plasma arc 654 is generated between the inner electrode 651 of the torch and the cathode 652 at the tip of the torch, 22 As shown in Fig. 22 (b), this is a transfer mode in which a plasma arc 654 is generated between the separator 651 inside the torch and the cathode provided on the furnace body side.
  • a plasma gas supply device (not shown) is surrounded by the plasma gas inlet 655.
  • the plasma torch for generating plasma has a multi-tube structure having a water cooling jacket 653, mainly from the viewpoint of preventing thermal damage to the anode.
  • a molten slag reservoir is provided at the furnace bottom, and the furnace bottom brick is directed downward.
  • a waste boiler comprising a nozzle is provided, and an overflow is provided between the slag reservoir and the waste outlet, and a cut is provided in the overflow weir in a direction away from the ash supply opening;
  • the proposed municipal solid waste incineration ash treatment device which has a divergent hole at the lower end of the nozzle, prevents clogging of the molten slag discharge port.
  • Exhaust gas is extracted from the upper part of the furnace, and the slag discharge furnace is located at the furnace bottom where the temperature is highest in the furnace, and a cough is provided in the furnace. Once the cough is melted or broken, there is a security problem in which slag in the furnace flows out instantaneously.
  • Japanese Patent Application Laid-Open No. 3-55411 discloses a plasma torch disposed in a melting furnace for generating a plasma arc, a driving device for moving and adjusting the plasma torch in a vertical direction of the torch, and a plasma torch.
  • a tilting device that changes and adjusts the tilt of the plasma torch in order to change the irradiation direction, such that the irradiation area of the plasma arc from the plasma torch blocks the slag discharge of the melting furnace by driving the tilting device.
  • a plasma melting furnace configured to change the direction of the plasma torch is proposed.
  • the slag When discharging slag continuously, the slag is cooled and solidified at the slag discharge port, closing the discharge hole, preventing the slag from flowing out and stopping the melting furnace. Irradiation amount
  • the plasma torch is tilted to the center of the fulcrum so that a force bar can be applied from the surface of the molten slag in the main furnace to the tip of the slag discharge hole, and the slag in the discharge hole is directly heated by a plasma arc, It is intended to prevent cooling and allow continuous outflow, and discloses that it is better to place a plasma torch above the exhaust hole inlet.
  • the slag near the supply hole of the cold waste becomes the lowest temperature from the viewpoint of melting of the waste, and in some cases, remains unmelted. Waste is deposited near the drop point, causing unstable melting. In particular, the unstable melting problem becomes prominent when melting with high efficiency while minimizing the power consumption unit.
  • Negative pressure operation by the above-mentioned inducing fan is performed before the incineration ash of the particulates reaches the slag pool in the furnace along the flow in the furnace body from the incineration ash supply hole to the slag discharge hole by the inducing fan.
  • the gas may be diffused from the discharge hole to the outside of the furnace body. In this case, it goes without saying that the efficiency of converting the incinerated ash into slag decreases, but the incinerated ash accumulates in the flue from the exhaust ⁇ * outside the main furnace, causing troubles in the equipment.
  • Japanese Patent Application Laid-Open No. 2-122109 discloses that when incinerated ash is melted at a high temperature, coke, coal, charcoal, flammable An operation method has been proposed in which carbon or carbohydrate sources such as garbage and sewage sludge are separately charged and added, and incineration ash is melted in a reducing atmosphere to achieve low NOx. In order to reduce low NOx by this operation method, it is necessary to stabilize the inside of the furnace in a reducing atmosphere. Therefore, there is a problem that a large amount of a carbon source or a carbohydrate source must be supplied. That is, the injected coke, coal, charcoal, etc.
  • amorphous solids which are supplied on the surface of the molten slag and then heated and melted to gasify, or gasified simultaneously with the fall. Since the amount of reducing gas generated tends to be unstable, it is necessary to supply a large amount of a carbon or carbohydrate source to ensure that the inside of the furnace body is kept in a reducing atmosphere.
  • low melting substances such as Hg, As, Na, K, Cu, Pb and Zn in the waste evaporate and volatilize in exhaust gas.
  • the proportion of this low-melting substance can be as high as 10 to 25% by weight of the waste supply.
  • valuable substances such as Cu, Pb, and Zn are contained in these low-melting substances, but they cannot be recovered effectively.
  • the electrode surface where the plasma arc is generated is exposed to extremely high temperatures, and is gradually eroded during operation. And when the service life is reached, the anode Pinholes occur at the tip of the torch, and in the worst case, the torch breaks and a large amount of cooling water gushes into the furnace, causing disasters such as steam explosions.
  • the tip of the plasma torch is visually inspected during each operation to reduce or reduce unevenness, abnormalities, and leakage of cooling water from the plasma torch. I was examining.
  • the first object of the present invention is to provide a plasma melting furnace capable of stably removing slag and an operation method thereof. Melt is efficiently melted into slag while ensuring stable slag.In addition, incinerated ash surely reaches the slag bath on the hearth, and
  • a plasma melting furnace and a method of operating the same that can efficiently recover valuable materials contained in exhaust gas with low NOX generation, and can also immediately detect and notify of abnormalities in the plasma torch that occurs during operation
  • the plasma melting furnace of the present invention that achieves the above object ensures a stable slag
  • a refractory guide tube that guides the exhaust gas in the downward direction of the slag flowing out of the slag discharge hole is arranged. It is forcibly heated and heated.
  • the tilting center of the plasma torch in the plasma melting furnace is characterized in that the tilting center of the plasma torch is located between the waste supply hole outlet and the slag discharge hole inlet. It is located between the distance L and 0.2 L to 0.45 L from the supply hole outlet.
  • the operation method is such that the operation is performed by intermittently tilting toward the discharge port inlet or the supply port outlet.
  • the above means applies the plasma heat to the vicinity of the waste supply hole to rapidly melt the waste. Then, when the slag discharge hole starts to clog, the plasma torch is slightly tilted toward the discharge hole, and instead of directly irradiating the plasma arc to the discharge hole from the viewpoint of preventing refractory meltdown, the flow pattern is optimized By flowing a high-temperature gas of 1 ⁇ 00 “C in the same direction as the direction of the slag discharge hole, the discharge hole is heated to prevent the discharge hole from being clogged.
  • the plasma melting furnace of the present invention uses a gas nozzle that blows a gas such as air toward the slag bath of the hearth. If the plasma torch is tilted by a driving device, the gas nozzle blow angle should be linked to the driving device of the plasma torch.
  • the molten iron is equipped with a drive device that changes by moving it.It is operated by constantly blowing gas such as air from the supply hole toward the slag bath located at the irradiation destination of the plasma torch. Things.
  • the flow of gas such as air blown from the supply hole toward the slag located at the irradiation destination of the plasma torch induces incineration ash, and the furnace body moves from the supply hole to the discharge hole by the inducing fan.
  • the incineration ash is prevented from escaping from the discharge hole to the outside of the furnace body before landing on the molten slag along the internal flow.
  • the surface temperature of the molten slag located at the irradiation destination of the plasma torch is always high, the incinerated ash always lands on the high temperature area of the slag, and is efficiently melted and turned into slag.
  • the method for operating the plasma melting furnace of the present invention is based on blowing fuel into the exhaust gas of the melting furnace.
  • the injection position is preferably an exhaust hole or a slag discharge hole that also serves as an exhaust hole.
  • the exhaust gas temperature at the injection position is preferably 500 ° C. or higher, and when the plasma gas amount fluctuates, the amount of the fuel is reduced. It is preferable that the fuel should be able to be blown in.
  • gas fuel such as city gas or butane gas is optimal, and even liquid fuel with good combustibility such as kerosene or heavy oil A is used. It may be mixed with some powdered fuel.
  • N 0 X a blow the combustion air to the exhaust gas from the exhaust hole after reduction, the reducing gas by complete combustion CO, to suppress the discharge of reducing gas such as H 2.
  • the plasma melting furnace of the present invention is provided with a valuable resource recovery device.
  • the valuable resource recovery device connects a water cooling pipe to a flue that guides exhaust gas flowing out of the discharge hole, starts the water cooling pipe within 30 degrees with respect to a vertical axis, and places a valuable resource downstream of the water cooling pipe.
  • a water-cooled cyclone for collecting dust is provided. It is preferable to connect a dilution air pipe upstream of the water cooling pipe or downstream of the flue, or to connect a circulation path for returning a part of the valuable material dust of the water cooling cycle port.
  • the method for recovering valuable resources in the plasma melting furnace of the present invention includes a step of cooling the exhaust gas discharged together with the slag through a pipe raised within 30 degrees with respect to a vertical axis; A step of separating valuable dust while cooling, so that the temperature of the exhaust gas after the separation step is reduced to not more than 65O 0 C.
  • the recovery rate rises, and when it exceeds 650 degrees, it remains volatile and almost unrecoverable.
  • the plasma melting furnace of the present invention is provided with a plasma torch operation monitoring device so that an abnormality of the plasma torch occurring during operation can be immediately found and notified.
  • the operation monitoring device for the plasma torch includes a pressure sensor for detecting a change in the furnace pressure or a change in the supply pressure of the plasma gas, and a spectrum integration of a signal waveform from the pressure sensor in a predetermined frequency band.
  • First comparing means for generating an abnormal signal when the integrated value from the integrating means is larger than a predetermined reference value, a voltage sensor for detecting a change in the source voltage of the plasma torch, A second comparing means for detecting a voltage drop of the power supply by comparing the voltage signal of the sensor with a predetermined reference value, and detecting a voltage drop signal from the second comparing means and an abnormal signal from the first comparing means.
  • Determining means for issuing a signal to stop the operation of the plasma torch when received, wherein the integration reference value changes according to a gas flow rate from the plasma torch.
  • a pressure sensor detects fluctuations in the furnace pressure due to leakage of cooling water from the plasma torch, or fluctuations in the supply pressure of the plasma gas
  • a voltage sensor detects fluctuations in the power supply voltage of the plasma torch
  • integration means for the pressure sensor The first comparator compares the waveform of the signal with a predetermined reference value and outputs an abnormal signal when the integrated value is larger than a predetermined reference value.
  • the voltage signal from the first comparing means is compared with a predetermined reference value to detect a voltage drop of the power supply.
  • the control unit Upon receiving the abnormal signal from the second comparing means, issues a signal for stopping the operation of the plasma torch, and immediately detects and informs the abnormality of the plasma torch occurring during the operation.
  • FIG. 1 is a cross-sectional view of the plasma melting furnace of the present invention
  • FIG. 2 is a cross-sectional view taken along line XX of FIG. 1
  • FIG. 3 is a structure of another plasma melting furnace of the present invention.
  • FIG. 4 is a view showing a state in which waste is actively melted in the plasma melting furnace of FIG. 3, and
  • FIG. 5 is an intermittently taken state of the plasma melting furnace of FIG.
  • Fig. 6 is a structural diagram of another type of plasma melting furnace, and Fig. 7 is the effect of the tilting center position of the plasma torch on the power consumption and slag conversion rate.
  • FIG. 8 is a structural view of still another plasma melting furnace of the present invention, and FIG.
  • FIG. 9 is a view for explaining an operation method for reducing the generation of NOX in the present invention.
  • Fig. 10 (a) and Fig. 10 (b) show the changes in CO concentration and NOX reduction rate due to the amount of fuel injected.
  • FIG. 11 is another graph for explaining an operation method for reducing the generation of NOx in the present invention.
  • FIG. 12 is a graph showing valuable resources in the plasma melting furnace of the present invention.
  • Fig. 13 is a structural drawing of the recovery device, Fig. 13 is a cross-sectional view taken along X5-X5 in Fig. 1, and Fig. 14 shows the relationship between the exhaust gas temperature at the water-cooled cycle outlet and the recovery rate.
  • FIG. 13 is a structural drawing of the recovery device
  • Fig. 13 is a cross-sectional view taken along X5-X5 in Fig. 1
  • Fig. 14 shows the relationship between the exhaust gas temperature at the water-cooled cycle outlet and the recovery rate.
  • FIG. 15 is a graph showing an operation monitoring device for a plasma torch in the plasma melting furnace of the present invention.
  • FIG. 16 (a) and FIG. 16 (b) show pressure signal waveforms.
  • FIG. 17 (a) and FIG. 17 (b) are graphs showing pressure signal waveforms obtained by spectral decomposition with respect to frequency, and
  • FIG. 19 is a graph showing a criterion for determining an abnormal state based on the integrated value of the spectrum. value
  • FIG. 20 is a diagram showing another apparatus for monitoring the operation of a plasma torch in a plasma melting furnace of the present invention, and
  • FIG. 21 is a combination diagram of judgment criteria.
  • FIG. 22 (a) and FIG. 22 (b) are cross-sectional views of main parts of the plasma torch.
  • FIGS. 1 and 2 The plasma melting furnace 100 of the present invention shown in FIGS. 1 and 2 is for securing stable slag outflow, and FIG. 1 is a sectional view of the plasma melting furnace 100 of the present invention. FIG. 2 is a sectional view taken along line XX of FIG.
  • the furnace body 1 has a water-cooled outer wall and a refractory structure on the inside to minimize the heat dissipated from the furnace wall and extend the life of the furnace.
  • a slag reservoir 15 is formed inside the furnace body 1, and a supply hole 12 for supplying waste 4 to the slag reservoir 15 and a discharge hole 7 for discharging slag 6 overflowing from the slag reservoir 15 are formed.
  • Furnace body 1 is provided.
  • the plasma torch 2 is inserted into the furnace from the upper part of the furnace body 1 and faces the slag reservoir 15 to generate a high-temperature plasma arc 3.
  • the waste 4 is supplied into the furnace body through a supply hole 12 by a general supply device such as a screw feeder or a belt conveyor (not shown).
  • the waste 4 is heated and melted by the plasma arc 3 to form a slag pool 15. Further, when the waste 4 is continuously supplied into the furnace body 1, the slag 6 overflows from the discharge hole 7 and is discharged out of the furnace body 1. High-temperature exhaust gas 5 is also discharged from the exhaust hole 7 toward the flue 11.
  • the discharged slag 6 is cooled by water or air, transported by a conveyor 9 or the like, and stored in a container bag or a storage bin (not shown).
  • the guide cylinder 10 has an inverted L-shaped cross section on the side surface and a concave cross section on the upper surface (see FIG. 2). It has a downward opening 10 a for directing the exhaust gas 5, and together with a part of the furnace main body 1, forms a cylindrical part whose upper side is closed and opened downward.
  • the exhaust gas 5 discharged together with the slag 6 from the discharge hole 7 flows further downward from the part A of the discharge hole 7 as shown by the arrow a to pass through the downward opening 10a, and along the slag 6 flowing down. After that, it is released from the guide cylinder 10 and changes its direction to flow upward.
  • Exhaust gas 5 of the plasma melting furnace is guided from inside the furnace body 1 to the outlet of the discharge hole 7, then flows down the slag 6 by the guide cylinder 10, and then changes direction and rises in the flue 11 I do. Since the high-temperature exhaust gas 5 flows downward in the guide cylinder 10, the slag 6 itself in the portion A of the discharge hole 7 is heated and kept at a high temperature.
  • the present inventors have examined the cause in detail, and as a result, in particular, the amount of exhaust gas of the plasma melting furnace 1 is about 1/30 or less of that of the combustion melting furnace, and since the amount of sensible heat of the exhaust gas is small, the induction cylinder 10 In the absence of power, the temperature of the refractory in the area A of the discharge hole 7 was reduced due to the heat dissipated from the vicinity of the discharge hole 7 and the suction of cold air from the seal of the slag conveying means 9, and the slag was solidified. It has been found.
  • a guide tube 10 having a refractory structure is attached to the outlet of the discharge hole 7 so as to cover the vicinity of the outlet of the discharge hole 7 to minimize the heat dissipated and raise the temperature near the outlet of the discharge hole 7. .
  • the opening 10a at the lower end of the guide cylinder 10 is located below the outlet of the discharge It was arranged so that it might extend to one side.
  • the temperature at the portion A of the discharge hole 7 was about 115 O'C in the prior art, but rose to 132 O'C, and the slag did not solidify, and stable slag was possible. It became.
  • the plasma melting furnace 200 of the present invention shown in FIGS. 3 to 7 is for melting waste efficiently into slag while ensuring stable outflow of slag.
  • components having the same functions as those in FIG. 1 are denoted by the same reference numerals, and description thereof is omitted.
  • the plasma melting furnace 200 is of a transfer type, in which electrodes are provided on the plasma torch 2 and the bottom of the furnace body 1, respectively.
  • this figure shows an example of a reverse pole type in which the plasma torch 2 side is the anode (+) and the bottom of the furnace body 1 is the cathode (1).
  • the present invention is not limited to this embodiment, and can be applied to a non-transfer type or a positive electrode type.
  • a driving device 8 for the plasma torch 2 is provided on the upper part of the furnace main body 1.
  • the plasma chip 2 can move in the direction of the torch as shown by the arrow a2, and the outlet point P2 and the discharge hole 7 of the supply hole 12 as shown by the arrow b2 around the point P1. It can be tilted along a straight line connecting the entrance point P3.
  • the plasma torch 2 is provided so that S / L-0.2 to 0.45. It is provided shifted to the side of the supply hole 12.
  • the feature is that the tilting center P1 of the plasma torch 2 is brought closer to the supply hole P2 in this way, and the waste supplied from the supply hole 4 with the brass torch 2 is directly irradiated and melted. Fast and stable melting of waste.
  • this plasma melting furnace is performed as follows. First, the current supplied to the plasma torch 2 was kept constant, and the tip of the plasma torch 2 was The voltage is controlled by controlling the distance II of the pool 15 to the molten surface to control the voltage, and finally the output. Then, the plasma torch 2 is intermittently tilted toward the inlet of the discharge hole 7 and the outlet of the supply hole 12.
  • FIG. 4 shows the state of the plasma melting furnace that actively melts waste.
  • FIG. 5 shows the state of the plasma melting furnace that is intermittently taken when signs of slag solidification appear at the discharge hole 7.
  • the plasma arc 3 directly heats the surface of the slag reservoir 15 where the waste 4 falls. Therefore, normal temperature waste 4 is rapidly heated by the ultra-high temperature plasma arc 3.
  • a slag pool ⁇ 5 is formed.
  • waste 4 is put into the slag reservoir 15 and the waste 4 is melted by receiving heat from the molten slag, so the melting rate is relatively low and some porcelain fragments Such wastes flowed over the surface of the slag reservoir 15 without being melted, and flowed out of the discharge holes 7 as they were.
  • the waste 4 can be completely melted.
  • the heat transfer efficiency is very high because the low-temperature waste 4 and the ultra-high temperature plasma arc 3 are directly heat-exchanged.
  • a flow pattern in the plasma melting furnace will be described.
  • the plasma torch 2 is slightly tilted toward the supply hole 12, a strong swirling flow A 2 is generated in the vicinity of the supply hole 12, and the efficiency of slag formation can be increased. That is, the ejection speed of the plasma gas at the tip of the torch 2 is 300 to 50 Om / s, and the waste is wound in and the large-particle waste is accumulated in the slag while being rapidly heated and melted. To the surface. The fine particles melt instantaneously and collide with the slag reservoir 15 to become slag. Furthermore, the ultrafine particles ride on the flow of the circulating flow A2, and coalesce or adhere to the inner surface of the furnace body to form slag.
  • the ultrafine particles that have carried over are again entrained in the circulation stream B2, and most of the particles become slag.
  • high-speed plasma gas 2 1 2 By discharging the slag toward the discharge hole 7, the slag pool 15 has an effect of stirring, and the molten state becomes more stable.
  • the plasma torch 2 is tilted about the fulcrum P, by the tilt angle ⁇ , and the high-temperature plasma gas 2 Actively let 1 2 flow to the discharge hole 7.
  • the high-temperature plasma gas 212 is in a high-temperature range of more than 170 ⁇ ⁇ , and if this operation state is maintained for several minutes, the slag discharge hole 7 is cleanly cleaned and the blockage of the discharge hole 7 is eliminated. .
  • the sign of slag solidification at the discharge hole 7 is detected based on the pressure rise in the furnace body or the difference between the pressure in the furnace body and the pressure in the flue.
  • FIG. 6 is a diagram showing another type of a plasma melting furnace, and shows an example of a square melting furnace having a plasma torch output of 1.5 MW or more.
  • the irradiation diameter of the plasma arc is not so large even if the size of the plasma torch and the melting furnace is increased, and a rotary furnace is necessary in a cylindrical furnace, so a square furnace is preferable.
  • stable melting can be achieved only by swinging without using a rotating torch, and the fulcrum position ,, of the plasma torch is similarly optimal at 2 to 0.45.
  • FIG. 7 is a graph showing the effect of the center position of the tilt of the plasma torch on the power consumption unit and the slag conversion rate.
  • the slag conversion ratio indicates the ratio of the weight of slag produced to the amount of incinerated ash supplied.
  • the waste supply hole 12 and the strong circulating flow B2 as shown in Fig. 4 separate, and the residence time of the plasma gas 2 12 in the furnace Slag flows out of the furnace at a high temperature and is short, so the slag conversion rate decreases and the relative power consumption deteriorates.
  • the circulating flow A2 as shown in Fig. 4 becomes too small, the furnace wall becomes locally high temperature, and the heat loss increases. The unit gets a little worse. Therefore, the S / L with a slag ratio of about 92% or more and a relative power consumption of 0.87 or less is in the range of 0.2 to 0.45.
  • the state shown in FIG. 4 can be realized without increasing the tilt angle, and the slag can be stably removed.
  • the plasma melting furnace 300 of the present invention shown in FIG. 8 ensures stable outflow of slag and efficient slag conversion, while ensuring that scattered and scattered waste such as incineration ash is particularly ensured. It blows into the slag pool.
  • the furnace body 1 has a cylindrical shape and the outer wall is water-cooled, and the inside is a refractory structure.
  • a plasma torch 2 is inserted into a corner from the upper surface to the side wall of the furnace body 1.
  • a supply nozzle 12a for incinerated ash and a gas nozzle 312 are inserted into a supply hole 12 provided on the upper surface of the furnace body 1.
  • a gas nozzle 312 is provided around the outer periphery of the supply nozzle 12a, and has a double cylindrical shape.
  • the incineration ash 4 is the incineration ash It is supplied to the inside of the furnace body 1 through the flange 300, the screw feeder 310, the supply nozzle 12a, and the supply hole 12.
  • a slag discharge hole 7 is provided on the side wall of the furnace body 1, and the molten slag 6 that has overflowed is discharged outside the furnace through the discharge hole 7.
  • the cooled slag becomes stone-like and is carried out by conveyor 9.
  • the plasma torch 2 can be moved in the direction of the arrow of the torch by the drive device 3 1 1 provided on the upper part of the furnace
  • the plasma torch is tilted about the fulcrum P13 so that the area where the plasma arc can be irradiated is from the slag reservoir 15 in the furnace body 1 to the tip of the discharge port 7, and the slag of the discharge hole 7 is removed. It is heated directly by a plasma arc to prevent cooling of the slag so that it can be discharged continuously. Therefore, it is desirable that the plasma torch 2 be disposed above the discharge hole 7.
  • the gas nozzle 312 provided in the supply line 12 has a cylindrical shape coaxial with the supply nozzle 12a, and gas is supplied to the gas supply hole 312a.
  • Gas such as air is supplied from the line 314, and gas is blown from the waste supply hole 12 side to the slag reservoir 15 located at the irradiation destination of the plasma torch, and incineration is supplied from the supply hole 12
  • the direction of the ash 4 is directed to the irradiation direction of the plasma torch.
  • a driving device 313 for changing the blowing angle from the gas nozzle 312 is provided at the upper part of the furnace main body 1 and tilts the gas nozzle 312 in the direction of arrow c3 around the fulcrum P43. To change the gas blowing angle.
  • This drive device 3 1 3 The blow angle of the gas nozzle 3 1 2 in order to blow the incinerated ash together with the gas to the slag reservoir 15 located at the irradiation destination of the plasma torch 2 To change.
  • the supply nozzle 12a When the blowing angle of the gas nozzle 312 changes, the supply nozzle 12a also moves about ⁇ . Therefore, the upper part of the supply nozzle 12a is connected to the screw feeder 106 via the flexible pot 315. It should be noted that the blowing strength of the gas is stronger than the flow of the trigger gas described below, and that the temperature drop of the furnace body 1 due to the blowing of the gas does not affect the melting of the incineration ash 4. There is. Therefore, in order to prevent the temperature of the furnace body 1 from dropping due to gas blowing, it is desirable to use a recycle gas described later.
  • the control device 3 2 2 controls the driving device 3 11 of the plasma torch 2 and the driving device 3 13 of the gas nozzle 3 12 in conjunction with each other.
  • the gas blowing direction of the gas nozzle 3 12 is moved rightward as indicated by an arrow c3
  • the plasma torch 2 is moved to the supply hole 1 2
  • the gas blowing direction from the gas nozzle 3 12 is moved to the left of the arrow c 3. That is, the direction of the gas spray from the gas nozzles 3 12 is always controlled so as to face the slag reservoir 15 located at the plasma arc irradiation position of the plasma torch 2.
  • the inducing fan 3 19 forms a flow from the supply hole 12 to the discharge hole 7 to operate the furnace body 1 under a negative pressure. This is to prevent the incineration ash 4 of the fine particles from leaking into the atmosphere outside the furnace body 1 when the ash 4 is injected into the furnace body 1 or until it is melted. Therefore, the inducing gas from the inducing fan 3 19 is discharged from the discharge hole 7 together with the molten slag 6, and the inducing gas rises in the flue 11 provided in the discharge hole 7.
  • the trigger gas that has risen up the flue 11 is filtered by the bag filter 3 20 and contains fine particles contained in the trigger gas.
  • the offspring are collected and released to the atmosphere via the inducing fan 319 and Damba 318.
  • the exhaust gas when the exhaust gas is supplied as a recycled gas to the gas supply line 314 described later, the exhaust gas is introduced into the gas supply line 314 through the gas circulation line 317.
  • the dambar 318 adjusts the amount of gas released to the atmosphere. If exhaust gas is used as recycled gas, the amount of gas supplied to the gas circulation line 317 is adjusted.
  • Gases such as air supplied from the gas supply line 314 include two types, a new gas supplied from the gas blower 316 and an exhaust gas from the gas circulation line 317 described above. It is desirable to use them accordingly.
  • the advantage of using the exhaust gas as a recycled gas is that the temperature is relatively higher than that of the new gas supplied from the gas blower 316 because the exhaust gas is discharged from the furnace body 1.
  • the temperature of the recycled gas is relatively low, and the temperature of the furnace body 1 decreases little due to gas spraying, and does not affect the melting of the incinerated ash. Therefore, the supply of new gas from the gas blower 316 should be performed only when the amount of the blowing gas is reduced.
  • the operation of such a plasma melting furnace is performed as follows.
  • the incinerated ash is supplied to the inside of the furnace body 1 through the incinerated ash hopper 300, the screw feeder 303, the supply nozzle 12a, and the supply hole 12 provided at the upper part of the furnace body 1.
  • the incineration ash 4 is supplied into the furnace body 1 together with the blowing gas from the gas nozzles 3 12, so that the incineration ash is sprayed on the slag reservoir 15 along with the flow of the blowing gas.
  • the incinerated ash does not diffuse out of the furnace along with the flow of the exhaust gas in the furnace from the supply hole 12 to the discharge hole 7, and the slag pool 15 located at the irradiation destination of the plasma torch 2 15 Drops surely toward.
  • the drive device 3 13 of the gas nozzle 3 12 works in conjunction with the drive device 3 11 of the plasma torch 2 and constantly blows incineration ash toward the slag reservoir 15 located at the irradiation destination of the plasma torch 2.
  • the gas nozzle 3 12 is moved in the direction of the arrow c 3 in accordance with the tilt of the plasma torch 2 in the direction of the arrow b 3 so as to be turned on.
  • the incineration ash 4 is blown into the slag reservoir 15 in the high-temperature region located at the irradiation destination of the plasma torch, and is efficiently melted and turned into slag.
  • the slag 6 that has overflowed in the slag reservoir 15 is discharged out of the furnace through the discharge hole 7 in the side wall of the furnace body 1, cooled and formed into a stone, and carried out by the conveyor 9.
  • the exhaust gas induced by the inducing fan 3 19 rises in the flue 11 and is discharged through the bag filter 3 20 and the inducing fan 3 19.
  • Part of the exhaust gas is supplied to the gas supply line through the gas circulation line 317 as recycled gas.
  • the gas enters the gas nozzle 3 12 from the gas supply hole 3 12 a and is blown again toward the slag reservoir 15 located at the irradiation destination of the plasma torch of the furnace body 1.
  • a swirl vane may be provided in the tip of the gas nozzle 312 to swirl the blowing gas.
  • the surrounding gas flow is entrapped and the dissipation of the incineration ash 4 can be prevented, and at the same time, the fine particles of the incineration ash 4 can have a moment and the slag accumulation 1 Promote mixing in 5.
  • the plasma melting furnace 300 of the present invention and the method of operating the same are provided with a gas nozzle 3 12 for blowing gas such as air toward the slag reservoir 15 of the hearth in the supply hole 12 of the melting furnace 1,
  • a gas nozzle 3 12 for blowing gas such as air toward the slag reservoir 15 of the hearth in the supply hole 12 of the melting furnace 1
  • the driving device 3 2 2 that changes the blowing angle of the gas nozzle 3 12 in conjunction with the driving device 3 1 1 of the plasma torch 2 is connected to the melting furnace 1. It has a structure to provide.
  • And supply holes for gas such as air 1 From 2 always operate by blowing into the slag reservoir 15 located at the irradiation destination of the plasma torch 2 from the supply hole 1 2 toward the slag reservoir 15 located at the irradiation destination of the plasma torch 2
  • the incineration ash 4 is guided by the flow of gas such as air blown into the slag reservoir 15 along with the flow of exhaust gas in the furnace from the supply hole 12 to the discharge hole 7 by the inducing fan 3 19 Prevents emission from the vent hole 7 outside the furnace before.
  • the incineration ash 4 is surely mixed into the slag pool 15 of the hearth.
  • the incineration ash 4 always mixes with the slag pool 15 in the high-temperature region located at the irradiation destination of the plasma torch 2, so that it is efficiently melted and turned into slag.
  • the recycled gas is discharged from the furnace body 1 and has a relatively high temperature. It does not affect the melting of incineration ash 4 without lowering the temperature of 1.
  • the operation method of the plasma melting furnace of the present invention shown in FIGS. 9 to 11 reduces the generation of NOx.
  • exhaust gas 4 13 from the furnace body 1 passes through an exhaust hole 4 16 to become exhaust gas 4 14, and is emitted to the atmosphere from above the flue 11 through a dust collector (not shown).
  • an injection hole for fuel 405 that can be injected such as gas (city gas, butane gas, etc.) or liquid (kerosene or heavy oil A) to reduce NOx Is provided.
  • the fuel 405 from the injection hole 408 is injected into the exhaust gas 413 and uniformly mixed and burned. Then, the exhaust gas 413 becomes a reducing gas atmosphere and reduces NOX.
  • the reducing gas remaining in the exhaust gas 4 13 from the exhaust holes 4 16 is completely burned by the combustion air blowing nozzle or burner 4 10 provided in the flue 11 and the clean exhaust gas 4 1 4 and the flue 1 Released to the atmosphere through no dust collectors.
  • the plasma torch 2 there are various types, plasma gases A r, N 2, a variety of gases such as air are used. Air is widely used because it is cheapest to use air as the plasma gas in terms of cost. In this case, to generate a reaction to a high concentration of the NO X in the N 2 and 0 2 is the high temperature plasma flame in air (arc flame). This NO X is a pollutant such as photochemical smog and acid rain, and is emitted as it is contained in the exhaust gas 4 13. Therefore, gaseous or liquid fuel, preferably gaseous fuel 405, is injected into the exhaust gas 413 from the injection hole 408 and uniformly mixed to make a reducing gas in a combustion state, and NOx is reduced and reduced.
  • gaseous or liquid fuel preferably gaseous fuel 405
  • a 8 0 to 1 2 0 Nm 3 Bruno H about at 5 MW, 0 2 is waste gas 4 1 3 If there is no flammable component, it is about 21%.
  • reducing gas in consideration of the exhaust gas amount and the 0 2 concentration may be put blow a gaseous or liquid fuel to generate. Blowing amount of a 1 3 A city gas as a gaseous fuel blown when the above conditions example, only 1 to 3 Nm 3 Bruno H at 300 kw class, 8 to 1 2 Nm 3 / H of about at 1.
  • the position of the fuel injection hole 408 should be provided inside the furnace (inlet portion) of the exhaust hole 416 so as to maintain good mixing with the exhaust gas 413 and perform high-temperature combustion, as shown in FIG. However, it may be provided in the flue 11.
  • the temperature of the exhaust gas at the gas or liquid fuel injection position should be at least the ignition temperature of each fuel, and is preferably 500 or more.
  • the effect of reducing N 0 X To increase the fruits, combusting blowing fuel heavily blow than consume residual oxygen content, CO, so to generate a reducing gas such as H 2, from the flue 1 1 In the air nozzle 4 1 0 It is necessary to blow in the working air to completely burn.
  • the exhaust gas temperature must be 800 ° C. or higher in order to suppress the concentration of C 0 emitted to the atmosphere to 100 Pm or lower.
  • the ultra-high temperature air easily oxidizes the copper electrode and the like of the plasma torch 2. Therefore, in order to keep the life of the torch 2 long, the amount of plasma gas air is periodically changed. That is, if the amount of plasma gas is periodically changed, the point of generation of the ultra-high temperature plasma moves within the electrode, so that the consumption of the electrode becomes uniform and the life of the electrode is prolonged.
  • a carbon source or a carbohydrate source of an amorphous solid When a carbon source or a carbohydrate source of an amorphous solid is separately added and added to a plasma furnace as in the past, it takes a long time for the amorphous solid to be gasified and melted to generate a reducing gas, and the solid Since the rate of reducing gas generation varies greatly depending on the type or size, it is necessary to add a large amount of a solid carbon source or carbohydrate source to enhance the ⁇ 0X reduction effect, resulting in low responsiveness.
  • a fuel 405 such as a gas having a reducing gas such as city gas is used, and the ⁇ 0X can be reduced at the same time as the blowing, so that the ⁇ 0X reduction effect is very small. Large and easy to handle. Therefore, it is also possible to easily inject the fuel 405 linked with the periodic fluctuation of the plasma gas amount, and it is possible to reduce NO X to a lower level by appropriately maintaining the reducing gas amount.
  • a plasma melting furnace 1 shown in Fig. 9 Municipal solid waste incineration ash 250 kg / H was melted with a non-transfer-type plasma torch output of 300 kw. Air is used as the plasma gas, and the amount of gas is periodically fluctuated by ⁇ 20% with an average value of 21 Nm 3 ZH.
  • Fig. 10 (a) and Fig. 10 (b) show the results of examining how the C 0 concentration and the N 0 X reduction rate change depending on the amount of injected fuel.
  • city gas 13A (methane 88%, ethane 6%, propane 4%, butane 2%) was injected as fuel 405 from the injection hole 408 into the exhaust gas 413, and the city gas injection rate was 1 Nm 3 / H.
  • the CO concentration is less than 1 ppm and the NO x reduction rate is about 46%.
  • the city gas injection rate is further increased from 2 Nm 3 / H to 4 Nm 3 / H, (A) the CO concentration rises and the NO x It increases to about 90%.
  • the air is sucked into the flue to reduce the CO concentration, but it is still quite high.
  • FIG. 11 is a cross-sectional view of a plasma melting furnace in which the structure of the furnace 1 is different from that of FIG.
  • the difference from FIG. 9 is that the slag discharge hole 7 is also used as the exhaust gas 413 discharge hole. Also in this case, an injection hole 408 for the fuel 405 is provided at the inlet of the discharge hole 7.
  • the exhaust gas 13 is reduced to a reducing atmosphere to reduce NOx, and the exhaust hole 7 can be heated at the same time, so that a stable outflow of the slag 6 can be secured.
  • plasma melting furnaces have a small amount of exhaust gas, about 30 times less than that of combustion melting furnaces. For this reason, it is difficult to keep the temperature near the outlet of the discharge hole 7 of the plasma melting furnace high, and the slag at the outlet of the discharge hole 7 has become unable to slag out, and the furnace pressure in the furnace cannot be controlled, and it is floating. Dust is released into the atmosphere, which degrades the environment. However, the fuel injected from the injection holes 408 mixes well with the exhaust gas 413 in the discharge holes 7 and burns in the gouging space, thereby generating high heat. Emit.
  • the fuel injection hole 408 is provided at the inlet of the discharge hole 7.
  • the flow rate of the city gas to be blown was kept constant, so that the degree of reduction was low when the amount of plasma gas was large, and the NO x low rate was small.
  • the degree of reduction was high, the NO x reduction rate was large, and the temporal variation was large. Therefore, when a city gas with a time average of 3. ON m 3 / H was blown from the injection hole 408 in synchronization with the change in the plasma gas amount, the NOX reduction rate was 96 on a time average. High values of 4% were obtained.
  • the slag 6 when city gas was not injected into the discharge hole 7, the slag 6 was solidified at the outlet of the discharge hole 7, so that maintenance was required about once every 5 hours. However, when city gas was blown into the exhaust holes 7, the slag 6 was hardened and the maintenance was no longer necessary. Furthermore, since the slag flows out at a high temperature, the quality of the slag 6 is very good, and it can be widely used for aggregates.
  • the method of driving a plasma melting furnace of the present invention since by blowing fuel into a reducing gas atmosphere in the exhaust gas, NO X contained in the exhaust gas Since the fuel is reduced and the fuel is used effectively for reduction, NOX can be easily reduced with a small amount of fuel injection. In other words, since it is a gas or liquid fuel that can be blown, it is easier to handle than a solid fuel, and it can be blown in synchronization with the fluctuation cycle of the plasma gas, and optimally maintains excess or deficiency of reducing gas. it can. In addition, since the inside of the furnace is not made to have a reducing gas atmosphere, the risk that harmful substances are contained in exhaust gas leaking from the furnace is reduced.
  • FIGS. 12 to 14 show a valuable material recovery apparatus and a recovery method in the plasma melting furnace of the present invention.
  • high-temperature plasma gas is generated along with the plasma arc 3 and becomes exhaust gas and flows out of the discharge hole 7 into the flue (secondary combustion chamber) 11 as shown by an arrow.
  • This exhaust gas contains evaporated low-melting substances.
  • the temperature at point A is 1300. It is around C and high temperature.
  • the exhaust gas passes through a water-cooled pipe 5 12, and the valuable dust is separated from the exhaust gas by a water-cooled cyclone 5 13.
  • a dilution air pipe 514 is connected downstream of the flue 11 (above the drawing), and a dust circulation path 515 is connected upstream of the water cooling pipe 5 (below the drawing).
  • the water cooling pipe 5 12 is a double pipe in which the inner pipe 5 20 is housed in the outer pipe 5 2 2 through the step 5 2 1, and the exhaust gas passage 5 2 3 and a cooling water passage 5 2 4 are formed.
  • the rising angle 5 of the water cooling tube 5 12 with respect to the vertical axis is zero, and it is preferable that the water cooling tube 5 12 be vertical. However, if it is not possible to make it vertical due to the layout, etc., start up so that is within 30 degrees from the viewpoint of dust accumulation prevention.
  • the horizontal distance L from the water-cooled tube 512 to the water-cooled cyclone 513 is desirably the shortest as far as the layout allows.
  • the water-cooled cyclone 5 13 is provided with a water-cooled jacket 5 26 on the outer periphery of a vessel 5 25 that generates a swirling flow, and dust collected below the center of the vessel 5 25 After that, it is dropped into box 528.
  • the exhaust gas from which the dust has been separated is discharged from the upper part of the container 525.
  • Part of the valuable dust in the box 528 is returned to the upstream side of the water cooling tube 512 via the dust circulation path 515.
  • the valuable dust is further concentrated, and for example, it is possible to increase the Zn concentration in the particles up to 2-3 times.
  • Exhaust gas cooling by the water-cooled pipes 5 12 and the water-cooled cyclones 5 13 is important for collecting valuables dust, and the exhaust gas temperature at the water-cooled cyclone 5 13 exit must be kept at 65 0 ° C or less. It is effective to connect a dilution air pipe 5 14 downstream of the flue 11 in order to efficiently cool the wandering gas, and the exhaust gas is rapidly cooled at the inlet of the water cooling pipe 5 12. Agglomeration of material is performed efficiently.
  • nucleus particles are particles that carry over from the plasma melting furnace without becoming slag, and are distributed in the size of several ⁇ m to several tens // m.
  • valuable materials with relatively high melting and boiling points such as Cu, evaporate in areas directly heated by a plasma flame of about 3000 'C or more, but are enclosed in slag in other areas. 3Evaporated and volatilized valuables are collected
  • Plasma output 30 O Kwh (transfer type)
  • Melted material fly ash from incineration of municipal waste
  • the valuable resource recovery apparatus or method in the plasma melting furnace of the present invention allows particles of a low melting point substance such as Pb, Zn. Cu, etc. to grow without being deposited in a rising pipe, and to be efficiently used as valuable substance dust. I'm going to catch you Valuables can be recovered and recycled as resources without causing trouble in the passage of the wastewater treatment equipment, and pollution caused by releasing sub-micron valuables into the atmosphere can be prevented.
  • FIGS. 15 to 20 show a device for monitoring the operation of a plasma torch in a plasma melting furnace of the present invention.
  • the operation monitoring device of the plasma torch in the plasma melting furnace of the present invention includes a pressure sensor 604 provided on the furnace wall of the melting furnace 1, and a voltage sensor 605 provided in a power device 603 of the plasma torch. It comprises an integrating means 606, a first comparing means 607, a second comparing means 608 and a judging means 609 provided in the melting furnace operation control box 611 and the like.
  • the pressure sensor 604 is for detecting pressure fluctuation in the furnace body 1 due to leakage of cooling water from the plasma torch 2 and sends a pressure signal waveform to the integrating means 606.
  • the pressure signal waveform from the pressure sensor 604 is as shown in FIG. 16 (a) and FIG. 16 (b).
  • Fig. 16 (a) shows the signal waveform during stable operation
  • Fig. 16 (b) shows the signal waveform being distorted due to the leakage of cooling water from the plasma torch.
  • the integration means 606 extracts a predetermined frequency range from the pressure signal waveform from the pressure sensor 604 through the band filter 606a, and performs a vector spectrum integration (hereinafter, referred to as a “band spectrum integration”) in the frequency band. This is referred to as spectral integration, and the integrated value is sent to the first comparing means 607.
  • a vector spectrum integration hereinafter, referred to as a “band spectrum integration”
  • spectral integration a vector spectrum integration
  • the integrated value is sent to the first comparing means 607.
  • FIGS. 17 (a) and 17 (b) shows the reason why the spectrum integration is performed by extracting a predetermined frequency range. This is because the disturbance of the signal waveform due to appears in a region different from the frequency region of the signal waveform during stable operation.
  • FIG. 17 (a) shows the 11 wave number region of the signal waveform during stable operation
  • FIG. 17 (b) shows the cooling wave leakage from the plasma torch, This is a frequency region where the shape is disturbed.
  • the first comparing means 7 sends an abnormal signal to the judging means 609 when the integrated value integrated by the integrating means 606 is larger than a predetermined first reference value. It emits.
  • the predetermined first reference value is a value of a spectrum integral during a stable operation in a frequency region where disturbance of a signal waveform due to leakage of cooling water from the plasma torch appears.
  • this spectrum integral value varies depending on the flow rate of the plasma gas of the plasma torch. Therefore, the predetermined first reference value is determined according to the flow rate of the plasma gas. 19 It is set to change like the dashed line in Fig. 19.
  • the voltage sensor 605 is for detecting a fluctuation of the power supply voltage of the plasma torch
  • the second comparing means 608 is configured to compare the voltage signal of the voltage sensor with a predetermined second reference value and This is to detect the voltage drop of the signal and send a voltage drop signal to the judgment means 609. Focusing on the fact that when the cooling water leaks from the plasma torch, the power supply voltage of the plasma torch drops, the abnormality of the plasma torch is used together with the abnormality signal from the first comparing means 7 to ensure the reliability. At the same time, abnormalities of the plasma torch are detected to prevent malfunction of the plasma torch operation monitoring device.
  • the judging means 609 makes an appropriate judgment based on the signals from the second comparing means 608 and the first comparing means 607, and sends an emergency stop signal to the plasma torch power supply device 603 or the like. Or an alarm signal to the alarm lamp 610.
  • FIG. 21 shows an example of the criterion of the judging means 609.
  • the signal from the first comparing means 607 is an abnormal signal and not the voltage drop signal from the second comparing means 608, a warning signal is sent to the hairpin lamp 6 1 in a state in which cooling water leakage is suspected. Send to 0, etc. to call attention of workers.
  • the operation of the plasma torch 2 is directly performed.
  • the pressure sensor 604 detects fluctuations in the furnace pressure, and furthermore, the power supply voltage of the plasma torch 2 is reduced. The fluctuation is detected by the voltage sensor 605. Then, integrating means 606 performs spectral integration of the signal waveform from the pressure sensor 604 in a predetermined frequency band, and the first comparison means 607 compares the integrated value with a predetermined first reference value. An abnormal signal is issued when the value is larger than the comparison.
  • the second comparing means 608 compares the voltage signal from the voltage sensor 605 with a predetermined second reference value to detect a voltage drop of the power supply.
  • the judging means 609 receives the voltage drop signal from the second comparing means 608 and the abnormal signal from the first comparing means 607, it outputs a signal for stopping the operation of the plasma torch 2. Detects abnormalities in the plasma torch that occur during operation.
  • FIGS. 22 (a) and 22 (b) the plasma torch 2 has a hollow cylindrical electrode as shown in FIG. 22 (a) and FIG. 22 (b). And rises and fluctuates due to water vapor.
  • the pressure fluctuation in the plasma torch 2 can be detected by the fluctuation of the plasma gas supply pressure. Therefore, instead of detecting an abnormality due to cooling water leakage from the plasma torch 2 based on fluctuations in the furnace pressure as in the embodiment shown in FIG. 15, it is detected based on fluctuations in the plasma gas supply pressure.
  • FIG. 20 shows another plasma torch operation monitoring device in the plasma melting apparatus of the present invention shown in FIG.
  • a pressure gauge 6 17 for measuring the supply pressure of the plasma gas is provided by a plasma gas supply device 6. It is connected between 16 and the Brass Torch 2.
  • the pressure signal waveform has the same pattern as that of the plasma torch operation monitoring device shown in Fig. 15 except that the frequency at which an abnormality due to leakage of cooling water in the furnace is integrated and the reference value are different. Since it appears, the processing of the signal waveform from the pressure gauge 6 17 is performed in the same manner as the operation monitoring device of the plasma torch shown in FIG. 15 by changing only the frequency for integration and the reference value.
  • the judging means 609 receives the voltage drop signal from the second comparing means 608 and the abnormal signal from the first comparing means 607, it issues a signal for stopping the operation of the plasma torch 2. To immediately detect abnormalities in the plasma torch that occur during operation.
  • the operation monitoring device of the plasma torch in the plasma melting furnace of the present invention can immediately detect an abnormality of the plasma torch occurring during operation, and operate without noticing the cooling water leak due to the deterioration of the plasma torch. It does not continue and does not inject large amounts of cooling water into the furnace and cause disasters such as steam explosions.
  • an induction cylinder made of a refractory that guides exhaust gas along a flow direction of slag flowing out from a slag discharge hole is disposed, Slag that flows down due to the sensible heat of high-temperature exhaust gas and those that forcibly heat the vicinity of the outlet of the discharge hole and raise the temperature Blockage due to solidification of the slag near the outlet of the discharge hole is less likely to occur, making it the most suitable as a plasma melting furnace capable of stable operation and its operation method.
  • the tilting center of the plasma torch is located between the distance L between the slag discharge hole inlet and the waste supply hole outlet and in the range of 0.2 L to 0.45 L from the waste supply hole. If the slag discharge hole begins to clog, the plasma torch can be slightly tilted toward the discharge hole by applying plasma heat to the vicinity of the waste supply hole to quickly melt the waste. It is the most suitable as a plasma melting furnace and its operation method, which can optimize the operation of slag, secure the stable slag, and improve the performance of power consumption and slag conversion rate.
  • a gas nozzle for blowing gas such as air toward the slag reservoir is provided coaxially with the incineration ash supply hole of the melting furnace, and when the plasma torch is tilted by the driving device, the gas nozzle blowing angle is set to the plasma torch.
  • the melting furnace is equipped with a driving device that changes in conjunction with the moving device of the furnace, and operation is performed by blowing gas such as air from the incineration ash supply hole toward the slag pool always located at the irradiation destination of the plasma torch.
  • This method is most suitable as a plasma melting furnace and a method of operating the plasma smelting furnace, which ensures the incineration ash is mixed into the slag reservoir while ensuring stable slag outflow and efficient slag conversion.
  • An operation that basically operates by injecting fuel into the exhaust gas of the melting furnace is the most suitable operation method for reducing the generation of NOX.
  • a device equipped with a valuable resource recovery device is the most suitable as a plasma melting device for efficiently recovering valuable materials contained in wandering gas without closing the passage of the exhaust gas treatment equipment, and its operating method.
  • a plasma torch operation monitoring device is ideal for a plasma melting furnace that will continue to operate without noticing the leakage of cooling water due to the deterioration of the brass torch and will not cause a disaster such as steam explosion. .

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Plasma & Fusion (AREA)
  • Physics & Mathematics (AREA)
  • Manufacturing & Machinery (AREA)
  • Environmental & Geological Engineering (AREA)
  • Spectroscopy & Molecular Physics (AREA)
  • Metallurgy (AREA)
  • Gasification And Melting Of Waste (AREA)
  • Manufacture And Refinement Of Metals (AREA)
  • Crystals, And After-Treatments Of Crystals (AREA)
  • Incineration Of Waste (AREA)
  • Feeding, Discharge, Calcimining, Fusing, And Gas-Generation Devices (AREA)
  • Glass Compositions (AREA)
  • Discharge Heating (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Description

明 細 書 ブラズマ溶融炉及びその運転方法 技術分野
本発明は、 都市ごみ、 産業廃棄物、 自動車シュレッダーダスト、 汚泥 、 またはこれらの焼却灰などの排気物をプラズマトーチによって発生す るプラズマアークで溶融し、 スラグにするブラズマ溶融炉及びその運転 方法に係わる。
特に、 スラグの安定的な出滓を実現し、 スラグを効率良く溶融し、 排 ガスをできるだけクリーンにすることができるものに関する。
背景技術
近年、 地球環境問題および資源リサイクル問題が注目されている。 特 に都市ごみや産業廃棄物は年々増加しており、 そのまま埋立処分するた めの処分地の確保が大都市圏を中心に難しくなつている。 そこで都市ご みや産業廃棄物を焼却して、 减容化して埋立処分するのが一般的となつ ている。
しかしながら、 これらの都市ごみや産業廃棄物の中にはさまざまな有 害物質や金属が舍まれている場合が多く、 焼却後の灰や不燃物 (以下焼 却灰と称す) の中には、 これらの有害物質や金属が残存する。 このため 焼却灰を埋立処分すると地下水を汚染するという問題がある。 また焼却 灰は比重が小さくために、 埋立処分地の容積を多く必要する。 また焼却 灰による埋立地は地盤が弱いため、 跡地利用が困難になる。
そこで、 これらの焼却灰をプラズマアークで溶融し、 その後冷却して 固化することが行われつつある。 この溶融固化したスラグの中にはク口 ームなどの重金属が封じ込められ、 重金属が水に溶出しないため、 埋立 処分後の地下水の汚染が生じない。 またスラグを建設用骨材や路盤材な どにも利用することができるため、 埋立処分地が不要となり資源リサィ クルにもなる。
焼却灰をプラズマアークで溶融するためのブラズマ溶融炉として、 例 えば特開平 3— 5 5 4 1 1号公報に記載のものが知られている。 このプ ラズマ瑢融炉は、 焼却灰の供給孔とスラグの排出孔とを有する炉本体内 に溶融したスラグの溜まりが形成される溶融炉と、 このスラグに対して プラズマアークを発生させるためのプラズマトーチとを備えたものであ る。 供給孔から供給される焼却灰はプラズマアークで溶融され、 炉本体 内に溶融したスラグの溜まりが形成され、 溜まりから溢れたスラグは排 出孔から連続的に排出され、 冷却固化される。 金属溶融に使用される通 常の溶融炉において、 プラズマトーチは円筒炉の中心に位置しており、 英国特許 1 3 9 0 3 5 1 / 3に示されるように、 炉中心を支点にして回 転自在なものもある。 さらに東北大学選鉱製鍊研究所報告書 Vol . 41,No. 2, P170- 171 (1985〉に示されるように、 クロマイ ト鉱石の直接還元用ブラ ズマ溶融炉において、 プラズマトーチを傾斜させたまま回転し、 広い面 積で均等に加熱するものもある。
また、 上記のようなプラズマ溶融炉において、 溶融される焼却灰は、 粒子径が数ミク口ンと微粒子であるので、 この微粒子の焼却灰が炉内投 入時や溶融されるまでの間に、 炉本体外の大気へ洩れないように、 焼却 灰の供給孔側からスラグの排出孔へ誘因フ 7ンにより負圧運転されるこ とが一般的である。
そして、 一般にプラズマ溶融炉から排出された排ガスは 1 3 0 0 ° C 前後の高温ガスであるため、 耐火物でライニングされた煙道を通過させ 、 水噴霧クーリ ングチャンバ等の冷却器で急冷され、 集塵機を経て大気 に放出される。 更に熱回収する場合には、 煙道に熱交換器を接続し廃熱 を回収する場合もある。
このようなプラズマ溶融炉に設けられるプラズマトーチの構造は、 第 2 2図 ( a ) 及び第 2 2図 ( b ) の断面図に示すように、 陽極 6 5 1と 、 陰極 6 5 2と、 水冷用ジャケッ ト 6 5 3と、 プラズマガス注入口 6 5 5とを備えたものである。 プラズマトーチは電極の接続の仕方によって 、 二種の運転モードがある。 第 2 2図 (a ) に示すように、 トーチの内 部の賜極 6 5 1とトーチの先端の陰極 6 5 2との間でプラズマアーク 6 5 4が発生するノ ントランスファモードと、 第 2 2図 (b ) に示すよう に、 トーチ内部の隔極 6 5 1と炉本体側に設けられた陰極との間にブラ ズマアーク 6 5 4が発生する トランスファモードである。 尚、 プラズマ ガス注入口 6 5 5には、 図示されていないプラズマガス供給装置が接繞 される。
プラズマの発生の仕方としては、 前者では高温のプラズマアークが賜 極と陰極のそれぞれに付着するのに対して、 後者はプラズマトーチ側で は陽極のみに付着し、 陰極側の付着は溶融炉側になる。 熱プラズマは、 温度が 3 , 0 0 0〜1 0 , 0 0 0 Kの解離したガス休である。 そのため 、 プラズマトーチに熱損傷が起こる。 熱損傷としては、 プラズマトーチ のプラズマアークが付着するボイン卜が最も激しく、 その次にプラズマ アーク近傍である。 従って、 プラズマを発生させるプラズマトーチは、 主に陽極の熱損傷防止の観点から、 水冷用のジャケッ ト 6 5 3を有する 多重管構造となっている。
このようなプラズマ溶融炉は、 約 1万度の高温のプラズマアークを用 いるのでダイォキシンなどの有害物質の分解が容易に行えると共に、 燃 焼法に比べて排ガス量が 3 0分の 1以下であるために、 排ガス処理設備 がコンパク トになる利点がある。 ところが、 このような利点を有するプラズマ溶融炉である力;、 廃棄物 の溶融に使用すると、 スラグの排出孔が閉塞したり、 排気物が部分的に 溶融しないまま排出孔から流出したりして安定的な操業ができないとい う問題点や、 排ガス中に N 0 Xや重金属が舍まれるという問題点があつ た。 これらの問題点に対応する課題を以下に詳細に説明する。
(第 1課題)
溶融炉を焼却灰の溶融に使用し、 スラグ排出孔から連続的にスラグを 排出する場合、 スラグ排出孔でスラグが冷却固化して湯口を閉塞させ、 スラグが流出しなくなるという現象が発生する。
そこで、 排出孔に補助パーナや補助プラズマアークを設けて加熱する ことが提案されている。 し力、し、 捕助バーナゃ捕助プラズマアークを設 けるために、 構造が複雑になる。
また、 特開平 1一 2 7 3 9 0 8号では、 都市ごみの焼却処理によって 発生する焼却灰をプラズマ発生装置により溶融する装置において、 炉底 に溶融スラグ溜めを設け、 炉底れんが内に下向きノズルから成る排滓ロ を配設し、 該スラグ溜めと排滓口との間に溢流堪を設けると共に該溢流 堰には灰供給口から隔離する方位に切込みを設け、 かつ、 前記下向きの ノズル下端には末拡がり孔を形成したことを特徴とする都市ごみ焼却灰 の処理装置を提案し、 溶融スラグの排出口の閉塞トラブルを防止してい る。 し力、し、 排ガスを炉上部から抜き出し、 スラグ排出ロを炉内におい て最も温度の高い炉底に位置させて、 炉内にせきを設けているので、 こ の方法によるとせきの強度が問題となり、 一旦せきが溶損したり、 壊れ ると炉内のスラグが一瞬に流出する保安上の問題がある。
(第 2課題) プラズマ瑢融炉がプラズマ出力 1 MW以上、 炉内寸法 1 . 5 m以上の 大型炉になると、 熱効率の高いトランスファーモードで運転する場合に プラズマ炎の不安定と電力原単位の悪化の問題を生じる。 即ち、 トラン スファーモードで運転する場合には、 逆極タイプの例では、 スラグ浴を 負電極としトーチを正電極として、 一定電流条件下でスラグ面とトーチ 間の距離を調節して電圧コントロールし、 プラズマ出力を調節する。 この場合のスラグ面とトーチ間の距離は 1 0〜3 0 c m程度となり、 プラズマアークの広がりを考慮して、 プラズマトーチをスラグの排出孔 の上部に取りつけた場合には、 排出孔近傍を局部加熱し耐火物を溶損す る危険性がある。 またプラズマアークの照射域を排出孔の反対側へ移動 させると傾動角度が大きくなるため、 特に飛びやすい灰や揮散金属の多 い廃棄物を溶融する場合には、 プラズマトーチ外面からアークを発生す るダブルアークの問題を生じる。 また、 プラズマトーチを傾けた場合、 スラグ面と トーチ面の距離を電圧コントロールのために近づける必要が あるので、 結局トーチの炉本体内へ突き出している部分が長くなり、 ト ーチの冷却損失が大きくなる問題がある。
そこで、 特開平 3— 5 5 4 1 1号公報では、 瑢融炉に配置されたブラ ズマアークを発生させるプラズマトーチ、 該プラズマトーチをトーチの 蚰方向に移動調節する駆動装置、 及び該プラズマトーチの照射方向を変 更するため前記プラズマトーチの傾きを変更調節する傾動装置から成り 、 該傾動装置の駆動により前記プラズマトーチからのプラズマアークの 照射領域が前 §3溶融炉のスラグ排出ロを舍むように前記プラズマトーチ の方向を変更可能に構成したプラズマ溶融炉を提案している。
スラグを連続的に排出させる場合に、 スラグ排出口でスラグが冷却固 化して排出孔を閉塞させ、 スラグが流出しなくなり、 溶融炉を停止させ ざるを得なくなる問題を解決するため、 プラズマアークの照射できる額 域を炉本休内の溶融スラグ面からスラグの排出孔の先端までを力バーで きるようにプラズマトーチを支点の中心に傾動させて、 排出孔のスラグ をプラズマアークで直接加熱させ、 スラグの冷却を防ぎ、 連続的に流出 できるようにしたものであり、 プラズマトーチを排出孔入口の上方に配 置するのが良いと開示している。
し力、し、 プラズマトーチを排出孔入口の上方に配置する場合、 廃棄物 の溶融という観点から考えると、 冷たい廃棄物の供袷孔近傍のスラグが 最も低温になり、 場合によっては溶融しないまま落下点近傍で廃棄物が 堆積して不安定溶融の問題を生じる。 特に電力原単位を最小限にして高 効率で溶融する場合に不安定溶融問題が顕著となる。
(第 3課題)
上記誘因ファンにより負圧運転は、 微粒子の焼却灰が誘因ファンによ る焼却灰の供給孔からスラグの排出孔への炉本体内の流れに沿つて、 炉 内のスラグ溜まりに着床する以前に排出孔から炉本体外へ放散してしま うことがあるという問題を有している。 この場合、 焼却灰をスラグ化す る効率が低下することはいうまでもないが、 炉本休外の排出^ *からの煙 道にかけて焼却灰が堆積して設備上のトラブルが生じる。
(第 4課題)
プラズマアークが高温になるため N 0 Xを多量に発生する問題があり 、 特にプラズマガスとして空気を使用した場合には数 1 ϋ 0 0 P p mの 髙濃度の N O Xを発生する。
そこで、 多量に 生する N O Xを低城するために、 特開平 2 - 1 2 2 1 0 9号公報では、 焼却灰を高温下で溶融処理するに当たり、 溶融炉に コークス、 石炭、 木炭、 可燃性ごみ、 下水汚泥などの炭素源または炭水 化物源を別途に投入添加し、 還元性雰囲気にて焼却灰を溶融し、 低 N O Xを実現する運転方法が提案されている。 この運転方法によって低 N O xを低滅するためには、 炉内を安定して 還元性雰囲気にする必要があるため、 多量の炭素源または炭水化物源を 投入せざるを得ないという問題点がある。 即ち、 投入されたコークス、 石炭、 木炭などは不定型の固体であり、 溶融したスラグの表面上に供給 された後で加熱され溶融しながらガス化されたり、 落下と同時にガス化 されたりするので還元性ガスの発生量が不安定になり易いため、 炉本体 内を還元性雰囲気に確実に保っためには多量の炭素源または炭水化物源 を供給する必要がある。
また、 コークス、 石炭、 木炭などの不定型固体を別途の供給装置を設 けて炉内へ投入することは設備費が高くなり、 定量供給も難しい。 更に 、 溶融炉と移動するプラズマトーチの間に隙間ができ易く、 溶融炉のシ ールを完全にすることは難しいため、 隙閟からの C 0等の還元性ガスの 外部への排出が問題となる。
(第 5課題)
焼却灰等の廃棄物を溶融処理すると、 廃棄物中の H g , A s , N a , K, C u , P b , Z n等の低融点物質が蒸発し、 排ガス中に揮散する。 この低融点物質の割合は、 廃棄物の種類にもよるが、 廃棄物供給量の 1 0〜2 5重量%にも達する場合がある。 この場合、 低融点物質が排ガス 処理設備の冷却器や熱交換器内で凝縮し堆積して、 通路を閉塞するとい う トラブルが多発するという問題点がある。 またこの低融点物質には C u , P b , Z nのように有価物が舍まれているが、 これを有効に回収す ることができない。
(第 6課題)
プラズマを発生させるプラズマトーチは、 水冷されているといっても プラズマアークが発生する電極表面は非常な高温に曝されているため、 運転中徐々に侵食される。 そして、 寿命に達したところで陽極、 若しく はトーチ先端部へのピンホールの発生、 最悪の場合にはトーチが破断し 、 多量の冷却水が炉内へ噴出し、 水蒸気爆発などの災害を招く。
そこで、 プラズマトーチ先端の侵食によるビンホールの発生、 水蒸気 爆発などの災害を防止するために、 運転毎にプラズマトーチの先端を目 視により観察し、 偏減りや異常、 またプラズマトーチからの冷却水漏れ を調べていた。
しかし、 実際に、 プラズマトーチ先端の浸食を事前の目視によって判 断するのは困難であり、 更に運転中には冷却水漏れを的確に検出できず に運転を続行してしまうという問題点を有している。 プラズマトーチの 劣化による冷却水漏れに気がつかずに炉を運転し続けること、 多量の冷 却水が炉内へ噴出して水蒸気爆発などの災害を招く。 このように、 廃棄物をプラズマ溶融炉でスラグにする場合、 従来の技 術では完全な解决策になっておらず、 実用化の障害となっていた。 本発 明はこのような種々の問題点に鑑みなされたもので、 その第 1の目的と するところは、 安定出滓が可能なプラズマ溶融炉及びその運転法を提供 するところにあり、 更に、 安定出滓を確保しつつ、 効率良く溶融してス ラグ化し、 加えて、 焼却灰が確実に炉床のスラグ浴に着床し、 そして、
N O X発生の少ない、 更には、 排ガスに舍まれる有価物を効率良く回収 でき、 その上、 運転中に起こるプラズマトーチの異常を即時に発見して 知らせることが可能なプラズマ溶融炉及びその運転法を提供するところ にある。
発明の開示
上記目的を達成する本発明のプラズマ溶融炉は、 安定出滓を確保する ために、 スラグ排出孔から流出するスラグの流下方向に ¾つて排ガスを 誘導する耐火物製の誘導筒を配置したもので、 その運転方法は、 高温の 排ガスにより流下スラグ及びスラグ排出孔出口近傍を強制的に加熱し昇 温するものである。
高温の排ガスをスラグの流下方向に向けると、 高温の排ガスの顕熱に よって、 流下スラグ及び排出孔出口近傍を強制的且つ有効に加熱し昇温 する。 そのため、 スラグの閉塞が生じにく くなる。 更に、 安定出滓を確保しつつ、 効率良く溶融してスラグ化するために 、 本発明のプラズマ溶融炉は、 プラズマトーチの傾動中心が、 廃棄物の 供給孔出口とスラグの排出孔入口との距離 Lの間にあって、 供給孔出口 から 0 · 2 L〜0 . 4 5 Lの位置に設けられているものである。 そして 、 その運転方法は、 間欠的に排出孔入口、 又は、 供給口出口に向かって 傾動させて運転するものである。
上記手段は、 プラズマ熱を廃棄物供給孔近傍に与えて廃棄物を高速溶 融する。 そして、 スラグの排出孔がつまり始めたらプラズマトーチを排 出孔に向けて少し傾動し、 耐火物溶損防止の観点からプラズマアークを 直接排出孔へ照射するのでなく、 フローパターンを最適化して約 1 Ί 0 0 "Cの高温ガスをスラグの排出孔方向と同一方向に流すことにより排出 孔を高温にし、 排出孔の閉塞を防止する。 加えて、 安定出滓及び効率の良い溶融スラグ化を確保しつつ、 焼却灰 を確実に炉床のスラグ浴に着床させるために、 本発明のプラズマ溶融炉 は、 空気等のガスを炉床のスラグ浴に向けて吹き込むガスノズルを溶融 炉の焼却灰供袷孔に設け、 プラズマトーチが駆動装置により傾動する場 合は、 ガスノズルの吹き込み角度を前記プラズマトーチの駆動装置と連 動して変化させる駆動装置を溶融伊に備えさせたもので、 その運転方法 は、 空気等のガスを供給孔から、 常に、 プラズマトーチの照射先に位置 するスラグ浴に向けて吹き込んで運転するものである。
上記手段によると、 供給孔からプラズマトーチの照射先に位置するス ラグに向けて吹き込まれる空気等のガスの流れが、 焼却灰を誘導し、 誘 因ファンによる供給孔から排出孔への炉本体内の流れに沿って、 焼却灰 が溶融スラグに着床する以前に排出孔から炉本体外へ放散してしまうこ とを防ぐ。 又、 プラズマトーチの照射先に位置する溶融スラグは常に表 面温度が高いので、 焼却灰はスラグの高温領域に常に着床し、 効率良く 溶融されスラグ化する。 そして、 N O Xの発生を低减するために、 本発明のプラズマ溶融炉の 運転方法は、 溶融炉の排ガス中に燃料を吹き込むことを基本として運転 するものである。 吹き込み位置は好ましくは排気孔又は排気孔兼用のス ラグ排出孔であり、 吹き込み位置の排ガス温度は好ましく 5 0 0 " C以 上であり、 プラズマガス量が変動する場合には前記燃料の量を連動させ て変動させることが好ましい。 ここで燃料は吹き込み可能なものであれ ばよく、 都市ガス、 ブタンガス等の気体燃料が最適であり、 灯油や A重 油等の燃焼性の良好な液体燃料でもよく、 多少の粉体燃料が混じったも のでもよい。
また、 プラズマ炉の排気孔に燃料を吹き込み、 更にその下流で燃焼用 空気を吹き込み、 この燃焼用空気の吹き込み位置の排ガス温度を好まし くは 8 0 0 ° C以上とする方法がある。
N 0 Xを大量に含んだ排ガスは排気孔又は排気孔兼用のスラグ排出孔 から流出するので、 この排気孔又は排気孔兼用のスラグ排出孔に例えば C 0を含む都市ガスを吹き込むと、 この排気孔又は排気孔兼用のスラグ 排出孔は還元性ガスである C O , H 2 の燃焼状態となり、 N O x力く還元 される。 吹き込み位置の排ガス温度が 5 0 0 ° C以上であると、 燃料が 着火し、 還元性ガスとなる。
また、 N 0 Xを還元後の排出孔からの排ガスに燃焼用空気を吹込み、 還元性ガスを完全燃焼させて C O、 H 2 などの還元性ガスの排出を抑制 する。 吹き込み位置の排ガス温度が 8 0 0 ° C以上であると、 大気放出 される C O濃度が 1 0 0 P p m以下に抑制される。 更には、 排ガスに舍まれる有価物を効率良く回収するために、 本発明 のプラズマ溶融炉は、 有価物回収装置を備えたものである。 その有価物 回収装置は、 排出孔から流出する排ガスを導く煙道に、 水冷管を接続し 、 該水冷管を垂直軸に対して 3 0度以内に立ち上げ、 前記水冷管の下流 に有価物ダストを捕集する水冷サイクロンを設けたものである。 そして 前記水冷管の上流又は前記煙道の下流に、 希釈空気管を接続したり、 前 記水冷サイク口ンの有価物ダス卜の一部を戻す循環路を接続することが 好ましい。
また、 本発明のプラズマ溶融炉における有価物回収方法は、 スラグと 共に排出される排ガスを垂直軸に対して 3 0度以内に立ち上げた管を通 して冷却する工程と、 この排ガスを更に冷却しながら有価物ダストを分 離する工程とを含んでなり、 分離工程を経た排ガス温度を 6 5 0度以下 にするものである。
排ガスを垂直蚰に対して 3 0度以内の管で立ち上げると、 排ガスと有 価物粒子との間又は粒子間に相対速度差が生じ、 粒子の衝突機会が増大 し、 粒子が成長して捕集可能な粒子まで成長し、 また管内面に粒子が付 着して堆積層が形成されても、 3 0度以内の立ち上げで自然な剝離が発 生する。 希釈空気管を接続すると、 徘ガス温度を急速に下げることがで き、 ダスト循環路を接続すると、 排ガス中の有価物の濃縮度が高くなる また、 水冷サイク口ンでの分離工程出口の排ガス温度を 6 5 0度以下 にすると、 揮散した有価物が凝集して回収率が上昇し、 6 5 0度を越え ると揮散したままになって殆ど回収できなくなる。 最後に、 運転中に起こるプラズマトーチの異常を即時に発見して知ら せることを可能にするために、 本発明のプラズマ溶融炉は、 プラズマト ーチの運転監視装置が設けられたものである。 そのプラズマトーチの運 転監視装置は、 前記炉内圧力の変動又は前記プラズマガスの供給圧の変 動を検出する圧力センサと、 該圧力センサからの信号波形を所定周波数 帯域でスぺク トル積分する積分手段と、 該積分手段からの積分値を所定 の基準値と比較して大きいと異常信号を発する第 1比較手段と、 ブラズ マトーチの鼋源電圧の変動を検出する電圧センサと、 該電圧センサの電 圧信号を所定の基準値と比較して電源の電圧降下を検出する第 2比較手 段と、 該第 2比較手段からの電圧降下信号と前記第 1比較手段からの異 常信号を受けた時に、 プラズマトーチの運転を停止させる信号を発する 判断手段とを備え、 前記積分基準値が、 プラズマトーチからのガス流量 によって変化するものである。
プラズマトーチからの冷却水漏れによる炉内圧力の変動、 又はブラズ マガスの供給圧の変動を圧力センサが検出し、 プラズマトーチの電源電 圧の変動を電圧センサが検出し、 積分手段が前記圧力センサからの信号 波形を所定周波数带域でスぺク トル積分し、 その積分値を第 1比較手段 が所定の基準値と比較して大きい場合に異常信号を発し、 第 2比較手段 が前記電圧センサからの電圧信号を所定の基準値と比較して電源の電圧 降下を検出し、 判断手段が前記第 1比較手段からの電圧降下信号と前記 第 2比較手段からの異常信号を受けると、 プラズマトーチの運転を停止 させる信号を発して、 運転中に起こるプラズマトーチの異常を即時に発 見し知らせる。 図面の簡単な説明
第 1図は、 本発明のプラズマ溶融炉の断面図であり、 第 2図は、 第 1 図の X— X断面図であり、 第 3図は、 本発明の他のプラズマ溶融炉の構 造図であり、 第 4図は、 第 3図のプラズマ溶融炉において廃棄物を積極 的に溶融する状態を示す図であり、 第 5図は、 第 3図のプラズマ溶融炉 の間欠的にとられる非定常状態の状態図であり、 第 6図は、 他の形式の プラズマ溶融炉の構造図であり、 第 7図は、 プラズマトーチの傾劻中心 位置の電力原単位およびスラグ化率に及ぼす影響を示すグラフ図であり 、 第 8図は、 本発明の更に他のプラズマ溶融炉の構造図であり、 第 9図 は、 本発明における N O Xの発生を低減する運転方法を説明する図であ り、 第 1 0図 (a ) および第 1 0図 (b ) は、 燃料の吹き込み量による C O濃度及び N O X低減率の変化を示すグラフ図であり、 第 1 1図は、 本発明における N 0 Xの発生を低減する運転方法を説明する他の図であ り、 第 1 2図は、 本発明のプラズマ溶融炉における有価物回収装置の構 造図であり、 第 1 3図は、 第 1図の X 5— X 5断面図であり、 第 1 4図 は、 水冷サイク口ン出口の排ガス温度と回収率の関係を示すグラフ図で あり、 第 1 5図は、 本発明のプラズマ溶融炉におけるプラズマトーチの 運転監視装置を示す図であり、 第 1 6図 (a ) および第 1 6図 (b ) は 、 圧力信号波形を示すグラフであり、 第 1 7図 (a ) および第 1 7図 ( b ) は、 周波数に対してスぺク トル分解された圧力信号波形を示すダラ フであり、 第 1 8図は、 スぺク トル積分値による異常状態の判断基準を 示すグラフであり、 第 1 9図は、 プラズマガス流量に対する積分基準値 の設定の仕方を示すグラフであり、 第 2 0図は、 本発明のプラズマ瑢融 炉における他のプラズマトーチの運転監視装置を示す図であり、 第 2 1 図は、 判断基準の組合せ図であり、 第 2 2図 (a ) 及び第 2 2図 (b ) はプラズマトーチの要部断面図である。
発明を実施するための最良の形態
以下、 上述した本発明のプラズマ溶融炉及びその運転方法の一例を図 面に従って説明する。
第 1図及び第 2図に示す本発明のプラズマ溶融炉 1 0 0は、 安定的な スラグの流出を確保するもので、 図 1は本発明のプラズマ溶融炉 1 0 0 の断面図を示しており、 図 2は図 1の X— X断面図である。
まず最初に本発明のプラズマ溶融炉 1 0 0の要部の構造を説明し、 次 にその運転方法を説明する。
第 1図において、 炉本体 1は外壁を水冷し、 内側を耐火物構造として 炉壁放散熱を最小限化すると共に炉寿命を延長させて 、る。 この炉本体 1の内部にはスラグ溜まり 1 5が形成され、 スラグ溜まり 1 5に廃棄物 4を供給するための供給孔 1 2とスラグ溜まり 1 5から溢れたスラグ 6 を排出する排出孔 7が炉本体 1に設けられている。 プラズマトーチ 2は 、 炉本体 1の上部から炉内に挿入され、 スラグ溜まり 1 5に対向し、 高 温のプラズマアーク 3を発生させる。 廃棄物 4は、 図示されないスクリ ュ一フィ一ダ一やベルトコンベアなどの一般的な供給装置により供給孔 1 2を経て炉本体内に供給される。 この廃棄物 4は、 プラズマアーク 3 により加熱されて溶け、 スラグの溜まり 1 5を形成する。 更に廃棄物 4 を炉本体 1の内へ供給し続けるとスラグ 6が排出孔 7からオーバーフ口 —して炉本体 1の外へ排出される。 また排出孔 7から高温の排ガス 5も 煙道 1 1に向けて排出される。 排出されたスラグ 6は水または空気で冷 却されて、 コンベア等の搬送手段 9で輪送されて、 図示されないコンテ ナバッグ又は貯蔵ビンに貯えられる。
スラグの排出孔 7の出口には耐火物製の誘導筒 1 0が取り付けられて レ、る点が重要である。 この誘導筒 1 0は側面の断面 逆 L字型であって 、 上面の断面が凹字型 (第 2図参照) であって、 スラグ 6の流下方向に 排ガス 5を向ける下向きの開口 1 0 aを有しており、 炉本体 1の一部と 共に上側が閉じ下向きに開口した筒部を形成している。 排出孔 7からス ラグ 6と共に排出される排ガス 5はこの下向き開口 1 0 a内を通るため に、 矢印 aのように排出孔 7の A部から更に下向きに流れ、 流下するス ラグ 6に沿つた後に誘導筒 1 0から開放され方向転換して上向きに流れ 煙道 1 1を上昇する本来の流れとなる。
つぎに、 上述した本発明のプラズマ溶融炉による運転方法を説明する 。 プラズマ溶融炉の排ガス 5は、 炉本体 1の中から排出孔 7の出口まで 導かれ、 次いで誘導筒 1 0によってスラグ 6の流下方向に流れ、 その後 は方向転換して煙道 1 1内を上昇する。 誘導筒 1 0内では高温の排ガス 5が下向きに流れるため、 排出孔 7の A部ゃスラグ 6自体が加熱されて 高温に保たれる。
このように排出孔 Ίの A部の加熱が重要であるというのは下記の知見 に基づく。 誘導筒 1 0が無い場合、 排ガス 5は、 排出孔 7の出口でスラ グ 6と直ちに離れ、 そのまま上昇していた。 その結果、 排出孔 7の出口 の A部は温度が低下してスラグ 6が固まり、 徐々に堆積して排出孔 7を 閉塞する問題を生じていた。 本発明者等はこの原因について詳細に検討 した結果、 特にプラズマ溶融炉 1の排ガス量は、 燃焼瑢融炉の約 3 0分 の 1以下であり、 排ガス顕熱量が少ないため、 誘導筒 1 0力無い場合に は、 排出孔 7周辺からの放散熱とスラグ搬送手段 9のシール部からの冷 風吸い込みにより排出孔 7の A部の耐火物温度が低下してスラグ力く固ま つていたことが判明した。
そこで、 本発明では排出孔 7の出口に耐火物構造の誘導筒 1 0を取り 付け、 排出孔 7の出口付近を覆い放散熱を最少限にし、 排出孔 7の出口 近傍の温度を上昇させた。 また、 排ガス 5を強制的に温度が低い A部に 流れるように、 誘導筒 1 0の下端の開口 1 0 aが排出孔 7の出口より下 方に延在するように配置した。 このことにより、 排出孔 7の A部の温度 力従来技術では 1 1 5 O 'C程度であったものが、 1 3 2 O 'Cまで上昇し 、 スラグが固まることはなくなり安定出滓が可能となった。 更に、 第 3図乃至第 7に示す本発明のプラズマ溶融炉 2 0 0は、 安定 的なスラグの流出を確保しつつ、 廃棄物を効率良く溶融してスラグとす るものである。 第 3図において、 第 1図と同様の働きをするものには同 —の符号を付してその説明を省略する。
このプラズマ溶融炉 2 0 0はトランスファータイプであり、 プラズマ トーチ 2及び炉本体 1の底部のそれぞれに電極を設けている。 例えば本 図ではプラズマトーチ 2側がアノード (+ ) , 炉本体 1の底部がカソー ド (一) となる逆極タイプの例を示している。 し力、し、 本発明が本実施 例に限定されるものでなく、 ノントランスファータイプあるいは電極が 正極タイプにも応用できる。
また、 炉本体 1の上部にプラズマトーチ 2の駆動装置 8が設けられる 。 このブラズマト一チ 2は矢印 a 2のようにトーチの蚰方向で移動可能 であると共に、 P 1点を中心にして矢印 b 2のように供給孔 1 2の出口 点 P 2と排出孔 7の入口点 P 3を結ぶ直線に沿って傾動可能となってい る。 そして P 2〜P 3間の距離をしとし、 P 2〜P 1間の距離を Sとす ると、 S / L - 0 . 2〜0 . 4 5となるように、 プラズマトーチ 2は供 給孔 1 2の側にずらされて設けられている。 このようにプラズマトーチ 2の傾動中心 P 1を供給孔 P 2に近づけている点が特徴であり、 ブラズ マトーチ 2で供袷孔 4から供給された廃棄物を直接的に照射し溶融する ので、 廃棄物を高速且つ安定して溶融する。
このプラズマ溶融炉の運転は以下のように行われる。 まずプラズマト ーチ 2に供袷する電流値を一定に保ち、 プラズマトーチ 2の先端とスラ グ溜まり 1 5の溶融面との距離 IIをコントロールして電圧を制御し、 最 終的には出力を調節する。 そして、 プラズマトーチ 2を間欠的に排出孔 7の入口、 又、 供耠孔 1 2の出口に向かって傾動させる。
第 4図は、 廃棄物を積極的に溶融するブラズマ溶融炉の状態を示す。 第 5図は、 排出孔 7においてスラグが固まる徴候が現れた場合に、 間欠 的にとられるプラズマ溶融炉の状態を示す。
第 4図の溶融状態において、 プラズマアーク 3が廃棄物 4の落下する スラグ溜まり 1 5の表面を直接加熱している。 このため常温の廃棄物 4 は超高温のプラズマアーク 3で急速加熱される。 超高温によって廃棄物 4が溶融するとスラグ溜まり 丄 5が形成される。 従来技術ではスラグ溜 まり 1 5に廃棄物 4が投入され、 廃棄物 4は溶けたスラグから熱を受け て溶融されるため、 溶融速度が比較的に低かったり、 また一部の陶器破 片の如き廃棄物は溶かされないままスラグ溜まり 1 5の表面を浮いて流 れ、 排出孔 7からそのまま流出していた。 しかし、 本発明では廃棄物 4 を完全に溶融することができる。 特に低温の廃棄物 4と超高温のブラズ マアーク 3が直接熱交換されるので伝熱効率が非常に高くなる。
更にプラズマ溶融炉内のフローパターンを説明する。 プラズマトーチ 2を少し供給孔 1 2に向かって傾動させると、 供耠孔 1 2近傍に強い旋 回流 A 2を発生し、 スラグ化の効率を高めることが可能である。 即ち、 トーチ 2の先端部でのプラズマガスの噴出速度は 3 0 0〜5 0 O m/ s であり、 廃棄物を卷込み、 急速加熱溶融しながら大粒子の廃棄物はスラ グ溜まり 1 5の表面へ衝突させる。 また微粉粒子は瞬間に溶融し、 スラ グ溜まり 1 5に衝突してスラグとなる。 更に超微粉粒子は循環流 A 2の 流れに乗り、 合体したり炉本体の内面に付着してスラグとなる。 更にキ ャリ一オーバーした超微粉粒子は再度循環流 B 2に巻き込まれ、 ほとん どの粒子がスラグになる。 また高速のプラズマガス 2 1 2を炉内の端か ら排出孔 7に向けて噴出させることによりスラグ溜まり 1 5の傥拌効果 があり、 溶融状態がより安定となる。
第 5図の間欠的にとられる非定常状態において、 排出孔 7でスラグが 固まる徴候が現れた場合、 プラズマトーチ 2を支点 P , を中心に傾動角 度 αだけ傾動させ、 高温のプラズマガス 2 1 2を積極的に排出孔 7へ流 すようにする。 この高温のプラズマガス 2 1 2は 1 7 0 Ο ΐ以上の高温 域にあり、 数分間この運転状態を保てばスラグ排出孔 7はきれいにクリ 一ユングされ、 排出孔 7の閉塞が解消される。 排出孔 7でスラグが固ま る徴候の検知は、 炉本体内の圧力の上昇値、 または炉本体内の圧力と煙 道内の圧力の差圧の上舁値で行う。 傾動角度 を 5 β 程度にとれば、 約 1万度のプラズマアーク 3はいったんスラグ溜まり 1 5に衝突し、 スラ グを加熱しながら排出孔 7へと流れるので排出孔 7近傍のスラグ溜まり 1 5の表面が高温になり、 かつ高温のプラズマガス 2 1 2で押し出され るように排出孔 5へとスラグが流れるので、 排出孔 7は健全に保たれ安 定的なスラグ流出が可能となる。 また第 4図及び第 5図において、 ブラ ズマトーチ 2の傾動角度は一 1 5〜1 5度で十分であり、 ダブルアーク の問題も起こらない。
第 6図はプラズマ溶融炉の他の形式を示す図であり、 プラズマトーチ 出力 1 . 5 MW以上の角形溶融炉の例を示す。 プラズマアークの照射径 は、 プラズマトーチおよび溶融炉が大型化されても余り広がらないため に、 円筒炉では回転トーチが必要となるため角形炉が好ましい。 角形炉 の場合には、 回転トーチでなくとも首振りのみで安定溶融が可能となり 、 プラズマトーチの支点位置 Ρ , は同様に 2〜0 . 4 5が 最適である。
つぎに実験例を以下に説明する。 第 3図に示すプラズマ溶融炉 1を使 用して、 都市ごみ焼却灰 3 0 0 k g / Hをトランスファ一タイププラズ マトーチ 3 0 0 k wの出力で溶融した。 プラズマトーチ 2の傾動角度は 各位置で ± 5度以内でコントールし、 最も安定なプラズマアーク力く形成 され安定的なスラグ流出が可能な場合のデータ、 および電力原単位の低 いデータを求めた。 第 7図はプラズマトーチの傾勳中心位置の電力原単 位およびスラグ化率に及ぼす影響を示すグラフ図である。 スラグ化率は 焼却灰供給量に対する製造されたスラグ重量の割合を示す。 プラズマト —チ 2をスラグ排出孔 7に近づけると、 廃棄物供給孔 1 2と第 4図に示 されるような強い循環流 B 2とが離れ、 またプラズマガス 2 1 2の炉内 滞留時間が短く高温のまま炉外へ流出するのでスラグ化率が低下し、 相 対電力原単位も悪化する。 一方、 プラズマトーチ 2を供給孔に近づける と第 4図に示されるような循環流 A 2が小さくなり過ぎ、 炉壁も局部的 に高温になり熱損失が増加するのでスラグ化率および相対電力原単位が 少し悪くなる。 従って、 スラグ化率が約 9 2 %以上で相対電力原単位が 0 . 8 7以下の S / Lは 0 . 2〜0 . 4 5の範囲である。 プラズマトー チ 2の支点 P i をこの範囲に配置すれば傾動角度を大きくすることなく 第 4図の状態を実現できスラグの安定出滓が可能となる。 加えて、 第 8図に示す本発明のプラズマ溶融炉 3 0 0は、 安定的なス ラグ流出と効率の良いスラグ化を確保しつつ、 特に焼却灰のように飛散 しゃすい廃棄物を確実にスラグ溜まりに吹き込むものである。
第 8図において、 炉本体 1は、 円筒状で外壁を水冷し、 内側は耐火物 構造である。 炉本体 1の上面から側壁にかけてのコーナ部にプラズマト ーチ 2が挿入されている。 炉本体 1の上面に設けられ供給孔 1 2に、 焼 却灰の供給ノズル 1 2 a及びガスノズル 3 1 2が揷入されている。 この 供給ノズル 1 2 aの外周にガスノズル 3 1 2が同轴に設けられ、 二重円 筒形状になっている。 娆却灰 4は炉本体 1の上部に設けられた焼却灰ホ ツバ 3 0 5、 スクリューフィーダ一 3 0 6、 供給ノズル 1 2 a、 供給孔 1 2を経て、 炉本体 1内に供給される。 炉本体 1の側壁にはスラグの排 出孔 7が設けられており、 オーバ一フローした溶融スラグ 6が排出孔 7 を経て炉外へ排出される。 冷却されたスラグは石状となり、 コンベア 9 で搬出される。
プラズマトーチ 2は、 炉本体 1の上部に設けられた駆動装置 3 1 1に よって、 矢印 a 3のようにトーチの蚰方向に移動可能であると共に、 P
1 3点を中心にして矢印 b 3のように排出孔 7側の点 P 2 3と供給孔 1
2側の点 P 3 3とを結ぶ曲線上を傾動可能となっている。 これは、 スラ グを連続的に排出させる場合に、 排出口 7でスラグが冷却固化し、 排出 口 7を閉塞させ、 スラグが流出しなくなり、 炉本体 1を停止させざるを 得なくなる問題を解決するためのものである。 すなわち、 プラズマァー クの照射できる領域を炉本体 1内のスラグ溜まり 1 5面から排出口 7の 先端までとなるようにプラズマトーチを支点 P 1 3を中心に傾動させて 、 排出孔 7のスラグをプラズマアークで直接加熱させ、 スラグの冷却を 防ぎ、 連続的に流出できるようにしたものである。 そのため、 プラズマ ト一チ 2は排出孔 7の上方に配置するのが望ましい。
本発明の特徴の一つは、 供,袷孔 1 2に設けられたガスノズル 3 1 2が 、 供給ノズル 1 2 aと同軸の円筒をしており、 ガス供給孔 3 1 2 aにガ ス供給ライン 3 1 4からの空気等のガスが供給され、 廃棄物供給孔 1 2 側から前記プラズマトーチの照射先に位置するスラグ溜まり 1 5にガス を吹きつけ、 供給孔 1 2から投入される焼却灰 4の投下方向をプラズマ トーチの照射方向に向ける。 そして、 このガスノズル 3 1 2からの吹き つけ角度を変化させる駆動装置 3 1 3力く炉本体 1上部に設けられており 、 ガスノズル 3 1 2を支点 P 4 3を中心に矢印 c 3方向に傾動させて、 ガスの吹きつけ角度を変化させる。 この駆動装置 3 1 3はプラズマトー チの駆動装置 3 1 1と連動しており、 常に、 プラズマトーチ 2の照射先 に位置するスラグ溜まり 1 5に向けてガスと共に焼却灰を吹き込むよう にするために、 ガスノズル 3 1 2の吹き込み角度を変化させる。
又、 ガスノズル 3 1 2の吹き込み角度が変化する際には、 供給ノズル 1 2 aも ί頃動する。 そのため、 供給ノズル 1 2 aの上部はフレキシブル なべローズ 3 1 5を介して、 スクリユーフィーダ一 3 0 6に接続されて いる。 尚、 ガスを吹きつける強さは後述する誘因ガスの流れよりも強く 、 加えて、 ガスの吹きつけにより炉本体 1の温度低下が焼却灰 4の溶融 に影響しない範囲にすることに留意する必要がある。 そのため、 ガスの 吹きつけによる炉本体 1の温度低下を防ぐのに、 後述するリサイクルガ スを使用することが望ましい。
制御装置 3 2 2は、 プラズマトーチ 2の躯動装置 3 1 1とガスノズル 3 1 2の駆動装置 3 1 3を連動制御させるものである。 プラズマトーチ 2が排出孔 7 (点 P 2 3 ) に向け傾動すると、 ガスノズル 3 1 2力、らの ガス吹きつけ方向を矢印 c 3の右方向に移動させ、 プラズマトーチ 2が 供給孔 1 2 (点 P 3 3 ) に向け傾動すると、 ガスノズル 3 1 2からのガ ス吹きつけ方向を矢印 c 3の左方向に移動させる。 すなわち、 常にガス ノズル 3 1 2からのガス吹きつけ方向が、 プラズマトーチ 2のプラズマ アーク照射位置にあるスラグ溜まり 1 5に向くように制御している。 誘因フアン 3 1 9は、 供給孔 1 2から排出孔 7への流れをつくり、 炉 本体 1内を負圧運転させるものである。 そして、 微粒子の焼却灰 4が炉 本体 1内に投入される時や溶融されるまでの間に、 炉本体 1外の大気へ 洩れないようにするためのものである。 そのため、 排出孔 7からは、 瑢 融スラグ 6と共に誘因ファン 3 1 9による誘因ガスが排出され、 排出孔 7に設けられた煙道 1 1を誘因ガスが上昇する。 煙道 1 1を上昇してき た誘因ガスは、 バグフィルター 3 2 0で、 誘因ガスに含まれている微粒 子が捕集され、 誘因ファン 3 1 9、 ダンバ 3 1 8を経由して大気に放散 される。
又、 後述するガス供袷ライン 3 1 4に排ガスがリサイクルガスとして 供給される場合は、 ガス循環ライン 3 1 7を通って、 ガス供給ライン 3 1 4に排ガスが導入される。 なお、 ダンバ 3 1 8は大気に放散されるガ スの量を調整するもので、 排ガスがリサイクルガスとして利用される場 合は、 ガス循環ライン 3 1 7へのガス供給量を調整する。
ガス供給ライン 3 1 4から供給される空気等のガスには、 ガスブロア 3 1 6から供給される新しいガスと、 前記記載のガス循環ライン 3 1 7 からの排ガスの 2種があり、 適宜必要に応じて使い分けることが望まし い。 排ガスをリサイクルガスとして用いる利点は、 炉本体 1から排出さ れたものであるので、 ガスブロア 3 1 6から供給される新しいガスより も比較的温度が高い点である。 温度が比較的髙ぃリサイクルガスは、 ガ スの吹きつけによる炉本体 1の温度低下が少なく、 焼却灰の溶融に影響 を及ばすことがない。 そこで、 ガスブロア 3 1 6から新しいガスを供給 するのは、 吹きつけ用のガスの量が少なくなつた時だけに限って行うと よい。
このようなプラズマ溶融炉の運転は以下のように行われる。 焼却灰 が炉本体 1の上部に設けられた焼却灰ホツバ 3 0 5、 スクリューフィ一 ダー 3 0 6、 供給ノズル 1 2 a、 供給孔 1 2を経て、 炉本体 1内に供給 される。 この時、 焼却灰 4はガスノズル 3 1 2からの吹きつけガスと共 に炉本体 1内に供給されるので、 吹き付けガスの流れに乗って焼却灰が スラグ溜まり 1 5に吹き付けられる。 そのため、 供給孔 1 2から排出孔 7への炉内の排ガスの流れに沿って、 焼却灰が炉外へ放散してしまうこ とがなくなり、 プラズマトーチ 2の照射先に位置するスラグ溜まり 1 5 に向けて確実に落下する。 更に、 ガスノズル 3 1 2の駆動装置 3 1 3は、 プラズマトーチ 2の駆 動装置 3 1 1と連動して、 常に、 プラズマトーチ 2の照射先に位置する スラグ溜まり 1 5に向け焼却灰を吹きつけるように、 プラズマトーチ 2 の矢印 b 3方向の傾動に合わせて、 ガスノズル 3 1 2を矢印 c 3方向に 移動させる。 そして、 焼却灰 4は、 プラズマトーチの照射先に位置する 高温領域のスラグ溜まり 1 5に吹き込まれ、 効率良く溶融しスラグ化さ れる。
スラグ溜まり 1 5で、 オーバーフローしたスラグ 6は炉本体 1の側壁 の排出孔 7から炉外へ排出され、 冷却されて石状となり、 コンベア 9で 搬出される。 この時、 誘因ファン 3 1 9により誘因された排ガスは、 煙 道 1 1を上昇し、 バグフィルター 3 2 0及び誘因ファン 3 1 9経て排出 される。 排ガスの一部は、 リサイクルガスとして、 ガス循環ライ ン 3 1 7を通り、 ガス供給ラインに供給される。 そして、 ガス供給孔 3 1 2 a からガスノズル 3 1 2に入り、 再び、 炉本体 1のプラズマトーチの照射 先に位置するスラグ溜まり 1 5に向けて吹き込まれる。
なお、 ガスノズル 3 1 2の先端内に旋回羽根を設け、 吹きつけガスを 旋回させてもよい。 この場合は、 吹きつけガスを旋回させることにより 、 周囲のガス流が卷き込まれ焼却灰 4の散逸を防止できると同時に、 焼 却灰 4の微粒子にモーメントを持たすことができ、 スラグ溜まり 1 5へ の混入を促進する。
このように本発明のプラズマ溶融炉 3 0 0及びその運転方法は、 空気 等のガスを炉床のスラグ溜まり 1 5に向 て吹き込むガスノズル 3 1 2 を溶融炉 1の供給孔 1 2に設け、 プラズマトーチ 2が駆動装置 3 1 1に より傾動する場合は、 ガスノズル 3 1 2の吹き込み角度を前記プラズマ トーチ 2の駆動装置 3 1 1と連動して変化させる駆動装置 3 2 2を溶融 炉 1に備えさせる構造となっている。 そして、 空気等のガスを供給孔 1 2から、 常に、 プラズマトーチ 2の照射先に位置するスラグ溜まり 1 5 に向けて吹き込んで運転するようにして、 供給孔 1 2からプラズマトー チ 2の照射先に位置するスラグ溜まり 1 5に向けて吹き込まれる空気等 のガスの流れにより焼却灰 4を誘導し、 誘因ファン 3 1 9による供給孔 1 2から排出孔 7への炉内の排ガスの流れに沿って、 スラグ溜まり 1 5 に混入する以前に排出孔 7から炉外へ放散してしまうことを防ぐ。 その 結果、 焼却灰 4が確実に炉床のスラグ溜まり 1 5に混入する。 加えて、 焼却灰 4は、 常に、 プラズマトーチ 2の照射先に位置する高温領域のス ラグ溜まり 1 5に混入するので、 効率良く溶融しスラグ化する。
又、 吹きつけ用のガスとして、 炉本体 1から排出されたガスをリサイ クルガスとして使用すると、 リサイクルガスは炉本体 1から排出さたも のであるので比較的温度が高く、 ガス吹きつけ時に炉本体 1の温度を低 下させることなく、 焼却灰 4の溶融に影響を及ばすことがない。 そして、 第 9図乃至第 1 1図に示す本発明のプラズマ溶融炉の運転方 法は、 N O Xの発生を低減するものである。
第 9図において、 炉本体 1からの排ガス 4 1 3は、 排気孔 4 1 6を経 て排ガス 4 1 4となり煙道 1 1の上側から図示されない集じん機を経て 大気放散される。 この排気孔 4 1 6の入口には、 N O xを低減するため に気体(都市ガス、 ブタンガス等) 又は液体 (灯油や A重油等) の如く 吹き込み可能な燃料 4 0 5の噴射孔 4 0 8を設ける。 この噴射孔 4 0 8 からの燃料 4 0 5が排ガス 4 1 3中に噴射され均一に混合されて燃焼す る。 すると、 排ガス 4 1 3が還元性ガス雰囲気になり、 N O Xを還元す る。 また排気孔 4 1 6からの排ガス 4 1 3に残る還元性ガスを、 煙道 1 1に設けられた燃焼用空気の吹き込みノズルまたはバ―ナ 4 1 0で完全 燃焼させ、 クリーンな排ガス 4 1 4となり煙道 1 1の上側から図示され ない集じん機を経て大気放散される。
プラズマトーチ 2には様々なタイプの物があり、 プラズマガスも A r 、 N2 、 空気など様々なガスが使われる。 コスト的にはプラズマガスと して空気を使用する場合が最も安いので広く使われている。 この場合に は、 空気中の N2 と 02 が高温のプラズマ炎 (アーク炎) の中で反応し て高濃度の NO Xを発生する。 この NO Xは、 光化学スモッグや酸性雨 などの公害の原因物質であり、 排出ガス 4 1 3に含まれたまま排出され る。 そこで噴射孔 40 8から気体又は液体の燃料好ましくは気体燃料 4 05を排ガス 4 1 3中に噴射させ均一に混合し、 還元性ガスの燃焼状態 とし、 NO Xを還元して低減する。 プラズマガスの空気量は、 出力 30 0 kwクラスで 1 0〜3 ONm3 /H, 1. 5MWで 8 0〜1 2 0Nm 3ノ H程度であり、 排ガス 4 1 3中の 02 は廃棄物中に可燃分が無い場 合は約 2 1%である。 従って燃料は NO X低诚効果を高めるために、 排 ガス量と 02 濃度を勘案して還元性ガスが発生するように気体燃料又は 液体燃料を吹込めば良い。 上記の条件例で気体燃料として 1 3 A都市ガ スを吹込む場合の吹込み量は、 300 kwクラスでわずか 1〜3 Nm3 ノ H, 1. 5MWで 8〜1 2 Nm3 /H程度となる。 勿論、 廃棄物中に 可燃分が含まれる場合には、 プラズマ空気中の 02 が消費されるので、 吹込み都市ガス量が少なくて済むことになる。 またこの都市ガスが炉内 に逆流しないので、 炉とトーチ 2の隙間から漏れる排ガスに CO等の有 害物質が紛れ込む恐れがない。
ここで、 燃料噴射孔 4 08の位置は、 第 9図のように排ガス 4 13と の良好な混合を保ち、 高温燃焼できるように排気孔 4 1 6の炉内側 (入 口部) に設けることが好ましいが、 煙道 1 1に設けても良い。 この場合 の気体または液体燃料の吹込み位置の排ガス温度は少なくとも各燃料の 着火温度以上ならば良く、 50 0て以上が良い。 また、 N 0 Xの低減効 果を高めるためには、 吹込み燃料を残存酸素量を消費するよりも多量に 吹込み、 C O, H 2 などの還元性ガスを発生させるので、 煙道 1 1では 空気ノズル 4 1 0から燃焼用空気を吹込み完全燃娩させる必要がある。 この燃焼用空気の吹込み位置温度は、 大気放散される C 0濃度を 1 0 0 P m以下に抑制するために排ガス温度を 8 0 0 ΐ以上とする必要があ る。
また、 超高温空気はプラズマトーチ 2の銅電極等を酸化させやすい。 そこでトーチ 2の寿命を長く保っために、 プラズマガス空気量を周期的 に変動させている。 即ち、 プラズマガス量を周期的に変動させると、 超 高温のプラズマの発生点が電極内で移動するので電極の消耗量が一様に なり電極寿命が長くなる。 従来の如くブラズマ炉内に不定型固体の炭素 源または炭水化物源を別途投入添加する場合には、 これら不定型固体が ガス化、 溶融して還元ガスを発生するまでに時間がかかり、 かつ固体の 種類または大きさによつて大幅に還元性ガス発生速度が異なるため Ν 0 X低减効果を高めるための多量の固体の炭素源または炭水化物源を加え る必要があり、 応答性が低くなる。 一方本発明では都市ガスなど還元性 ガスを有した気体のような燃料 4 0 5を使用し、 吹込みと同時に還元性 ガスとなり Ν 0 Xを還元できるので、 少量で Ν 0 X低減効果が非常に大 きく取扱いも容易である。 そこでプラズマガス量の周期的変動と連動さ せた燃料 4 0 5の吹き込みも簡単にでき、 還元性ガス量を適切に保つこ とによって N O Xをより低いレベルまで低減できる。
つぎに、 実験例について説明する。 第 9図に示すプラズマ溶融炉 1を 使用して都市ごみ焼却灰 2 5 0 k g /Hをノントランスファータイププ ラズマトーチ 3 0 0 k wの出力で溶融した。 プラズマガスとして空気を 使用し、 そのガス量は平均値 2 1 N m 3 ZHとし ± 2 0 %で空気量を周 期的に変動させている。 燃料の吹き込み量によつて、 C 0濃度及び N 0 X低減率がどのように 変化するか調べた結果を第 10図 ( a ) 及び第 10図 ( b ) に示す。 な お燃料 405として都市ガス 13A (メタン 88%, ェタン 6%, プロ パン 4%, ブタン 2%) を噴射孔 408から排ガス 413中に噴射した 都市ガス吹込み量が 1 Nm3 /Hの条件では C 0濃度は 1 ϋ ϋ p p m 以下で NO x低減率は 46%程度となる。 更に都市ガス吹込み量を 2 N m3 /Hから 4Nm3 /Hまで増加させると、 (A) 曲線の O印データ のように、 CO ¾度が上昇し、 N 0 X低减率が約 90 %程度まで大きく なる。 また煙道において大気を吸い込んで CO濃度を减少させているが 、 それでも相当高くなる。 そこで、 娌道に更に燃焼用空気を吹き込みノ ズル 410から空気を 2 ϋ〜30Nm, 1強制的に吹込み排ガスと混 合させ、 COの発生を抑制した結果が (B) 曲線の X印データであり、 NO X低诚率は 90〜92%と変わらないが、 COを 100 p p m以下 に低减できた。
第 11図は炉本休 1の構造が第 9図と異なるプラズマ溶融炉の断面図 である。 第 9図のものと異なる点は、 スラグの排出孔 7が排ガス 41 3 の排出孔兼用となっている点である。 この場合も排出孔 7の入口に燃料 405の噴射孔 408が設けられている。 第 9図のものと同様に排ガス 13を還元性雰面気にして NO Xを低減させると共に、 排出孔 7の加 熱も同時にでき、 スラグ 6の安定的な流出を確保できる。
通常プラズマ溶融炉は燃焼溶融炉に比較すると排ガス量が約 30分の 1以下と少量である。 そのためプラズマ溶融炉の排出孔 7の出口付近を 高温に保つことが難しく、排出孔 7の出口にスラグ 6力個まり出滓不能 になつたり、 炉内の炉圧制御ができず浮遊しているばい塵が大気に放出 されて環境を悪くする。 しかし噴射孔 408から吹き込まれた燃料は、 排出孔 7の中で排ガス 4 13と良く混合して抉い空間で燃焼し、 高熱を 発 する。 この結果排出孔 7の全域が高温に保たれ、 排出孔 7の出口付 近も高温になり、 排出孔 7の閉塞を防止するという効果を奏する。 した がって排出孔 7の全域を高温に保っために、 燃料噴射孔 4 0 8を排出孔 7の入口に設ける。
つぎに、 第 1 1図のタイプのプラズマ溶融炉置による実験例を以下に 説明する。 第 1 1図に示すプラズマ炉を使用して都市ごみ焼却灰 3 0 0 k g /Hをノントランスファータイププラズマトーチ 3 0 0 k wの出力 て'瑢融した。 ブラズマガス量は 1 5〜 2 5 N n ノ Hの範囲で 3分周期 で流量変動させた。 また煙道 1 1で未襟ガスを燃焼させるために、 吹き 込みノズル 4 1 0から燃焼用空気を 2 0 N m a II吹き込み C 0の排出 を抑制した。 上述した都市ガス 1 3 Aの 3 . O N m 3 ZHを噴射孔 8か ら吹き込んだところ、 N O X低減率は時間平均で 9 3. 7 %が得られた 。 この場合、 プラズマガス量が変動するのに対して、 吹き込む都市ガス の流量を一定にしていたため、 還元度がプラズマガス量が多い場合に低 く、 N 0 X低'减率が小さくなつた。 一方ブラズマガス置が少ない合に、 還元度が高く、 N O x低減率が大きくなり、 時間的変動が大きかった。 そこで、 プラズマガス量の変劻と同期させて時間平均 3 . O N m 3 / H の都市ガスを噴射孔 4 0 8から吹き込んだところ、 N O X低減率は時間 平均で 9 6。 4 %の高い値か得られた。 また、 排出孔 7に都市ガスを吹 き込まな 、場合には、 排出孔 7の出口にスラグ 6が固まり、 約 5時間に —回程度のメィンテナンスが必要であった。 しかし排出孔 7に都市ガス を吹き込むと、 スラグ 6が固まるトラブルは完全に解消されメィンテナ ンスが不要となった。 さらにスラグ 6力く高温で流出するので、 スラグ 6 の品質が非常に良く、 骨材等に広く利用できるようになつた。
このように、 本発明のプラズマ溶融炉の運転方法は、 排ガス中に燃料 を吹き込んで還元性ガス雰囲気にするので、 排ガスに含まれる N O Xは 還元され、 燃料は有効に還元に活用されるので、 少量の燃料吹込みで容 易に N O Xを低減できる。 すなわち、 吹き込み可能な気体又は液体の如 き燃料であるので、 固体燃料に比較して扱い易く、 プラズマガスの流動 変動周期に同調した吹き込みも可能であり、 還元性ガスの過不足を最適 に保持できる。 また炉内を還元性ガスの雰囲気にするものではないので 、 炉から漏れる排ガスに有害物質が舍まれる恐れは少なくなる。 また排 ガスの排気孔を兼ねたスラグの排出孔に燃料を吹き込んで燃焼させると 、 スラグの排出孔の加熱もでき、 スラグの安定的な流出に寄与する。 更には、 第 1 2図乃至第 1 4図は、 本発明のプラズマ溶融炉にける有 価物回収装置及び回収方法を示すものである。
第 1 2図において、 プラズマアーク 3に伴って高温のプラズマガスが 発生し、 排ガスとなって排出孔 7から矢印のように煙道 (二次燃焼室) 1 1に流れ出る。 この排ガスには蒸発した低融点物質が舍まれている。 また A点の温度は 1 3 0 0。 C前後と高温である。 排ガスは水冷管 5 1 2を通過し、 水冷サイクロン 5 1 3で排ガスから有価物ダストが分離さ れる構成となっている。 また煙道 1 1の下流 (図面の上方) に希釈空気 管 5 1 4が接続され、 水冷管 5 1 2の上流 (図面の下方) にダスト循環 路 5 1 5が接続されている。
水冷管 5 1 2は、 第 1 3図に示されるように、 内管 5 2 0をステ一 5 2 1を介して外管 5 2 2内に収めた二重管となっており、 排ガス通路 5 2 3と冷却水通路 5 2 4が形成されている。 第 1 2図において、 水冷管 5 1 2の垂直軸に対する立ち上げ角度 5はゼロであって、 垂直にするこ とが好ましい。 しかしレイァゥトの都合等で、 垂直に出来ない場合には 、 ダスト堆積防止の観点から が 3 0度以内になるように立ち上げる。 つまり 3 0度以内ならば、 水冷管 5 1 2の内面にダストが付着しても、 ダストの付着力が弱いので、 約 1〜2 mmまで堆積が成長した後、 自然 に剥離が発生し、 ダスト堆積トラブルまで至らないからである。 なお、 水冷管 5 1 2から水冷サイクロン 5 1 3に至る水平部の距離 Lはレイァ ゥト上許される限り、 最短にすることが望ましい。
水冷サイクロン 5 1 3は旋回流を発生させる容器 5 2 5の外周に水冷 ジャケッ ト 5 2 6力設けられたものであり、 容器 5 2 5の中心下方に溜 まるダストはロータリジョント 5 2 7を経てボックス 5 2 8に落下させ られる。 またダストが分離された排ガスは容器 5 2 5の上部から排出さ れる。 ボックス 5 2 8の有価物ダス卜の一部はダスト循環路 5 1 5を経 て水冷管 5 1 2の上流側に戻される。 有価物ダストは更に濃縮され、 粒 子中の例えば Z n濃度を 2〜3倍にまで髙めることが可能となる。 水冷管 5 1 2や水冷サイクロン 5 1 3による排ガスの冷却は有価物ダ ストの捕集に重要であり、 水冷サイクロン 5 1 3出口の排ガス温度を 6 5 0 ° C以下にする必要がある。 徘ガス冷却を効率良く行うために、 煙 道 1 1の下流に希釈空気管 5 1 4を接続することが有効であり、 水冷管 5 1 2の入口で排ガスが急速冷却され、 以下に述べる有価物凝集が効率 良く行われる。
つぎに、 上述した有価物回収装置による有価物の回収を説明する。 P bや Z nの如く融点、 沸点が低い有価物はプラズマ溶融炉で殆ど全部が 蒸発して排ガス中に揮散し、 プラズマ溶融炉内でサブミク口ンの粒子と なる。 この粒子は排ガスの冷却と共に冷却され、 凝縮しながら他の粒子 と凝集し、 水冷サイクロンで捕集可能なダストまで成長する。 特に核に なる粒子は、 スラグにならないままプラズマ溶融炉からキャリーオーバ —される粒子であり、 数^ m〜数十// mのサイズで分布している。 した がって水冷管 5 1 2を垂直又は垂直に近くすることによって、 排ガスと 粒子及び粒子同士の間に相対速度差が生じ、 サブミクロン粒子は冷却さ れながら、 キャリーオーバーされた粒子に衝突し付着し、 各粒子が衝突 する毎に粒子柽が大きくなり、 有価物力 <次第に濃縮される。 ダスト循環 路 5 1 5の水冷管 5 1 2への接続により、 有価物が再循環し更に濃縮さ れる。
一方、 Cuのように融点、 沸点が比較的高い有価物は、 約 3000 ' C以上のプラズマ炎で直接加熱される領域では蒸発するが、 他の領域で はスラグの中に封じ込められる。 3そのため蒸発し揮散した有価物が回収
2
される。 またチタンのように融点、 沸点が非常に高い金属は蒸発せず、 殆どがスラグの中に封じ込められ回収はできない。
さらに、 有価物回収の実験例を第 1 4図により説明する。 実験条件は 以下の通りである。
プラズマ出力: 30 O Kwh (トランスファータイプ) 、 被溶融物:都市ごみ焼却飛灰、
( Z n 0. 8%, P b 0. 4%. Cu 0. 6%) 被溶融物供給量: 3 00 K g/h、 プラズマガス:空気 第 1 4図の水冷サイクロン出口排ガス温度は希釈空気量でコントロー ルされ、 各温度での回収率を測定した。 融点、 沸点の低い Z ri, P bは 65 0 ° C以下で急速に回収率が上がっている。 すなわちプラズマ溶融 炉で殆どが蒸発し、 排ガス中に揮散しているので、 水冷サイクロン出口 温度を 6 50。 C以下に保つと、 凝集して水冷サイクロンで捕集される 。 融点、 沸点が比較的高い Cuも 65 0° C以下で急速に回収率力上が るが、 相当量がスラグの中に封じ込められてきるため、 面収率が 50% 前後で上げ止まる。
このように本発明のプラズマ溶融炉における有価物回収装置又は方法 は、 P b, Zn. Cu等の低融点物質の粒子を立ち上げ管内で堆積させ ることなく成長させ、 有価物ダストとして効率良く捕集するのて'、 排ガ ス処理装置の通路の閉塞トラブルを生じさせることなく、 有価物を資源 として回収してリサイクルすることができ、 サブミクロン程度の有価物 を大気に放出することによる公害も防止できる。 最後に、 第 1 5図乃至第 2 0図は、 本発明のプラズマ溶融炉における プラズマトーチの運転監視装置を示している。
本発明のブラズマ溶融炉におけるプラズマトーチの運転監視装置は、 溶融炉 1の炉壁に設けられる圧力センサ 6 0 4と、 プラズマトーチの電 源装置 6 0 3内に設けられる電圧センサ 6 0 5と、 溶融炉操作制御ボッ クス 6 1 1等に設けられる積分手段 6 0 6、 第 1比較手段 6 0 7、 第 2 比較手段 6 0 8及び判断手段 6 0 9とからなる。
圧力センサ 6 0 4は、 プラズマトーチ 2からの冷却水漏れによる炉本 体 1内の圧力変動を検出するためのもので、 圧力信号波形を積分手段 6 0 6に送る。 圧力センサ 6 0 4からの圧力信号波形は第 1 6図 ( a ) 、 第 1 6図 ( b ) に示すようなものである。 第 1 6図 (a ) は安定運転中 の信号波形で、 第 1 6図 (b ) はプラズマトーチからの冷却水漏れが起 こり、 信号波形が乱れている状態である。
積分手段 6 0 6は、 圧力センサ 6 0 4からの圧力の信号波形をバンド フィルタ 6 0 6 aを通して所定の周波数带域を抽出し、 その周波数帯域 でのバヮ一スぺク トル積分 (以下スぺク トル積分という, ) を行い、 そ の積分値を第 1比較手段 6 0 7へ送るものである。 ここで、 所定の周波 数带域を抽出してスぺク トル積分を行う理由は、 第 1 7図 (a ) 、 第 1 7図 (b ) に示すように、 プラズマトーチからの冷却水漏れによる信号 波形の乱れは、 安定運転中の信号波形の周波数領域とは別の領域に現れ るからである。 第 1 7図 (a ) は安定運 ¾£中の信号波形の) 11波数領域で 、 第 1 7図 (b ) はプラズマトーチからの冷却水漏れが起こり、 信号波 形が乱れている状態の周波数領域である。
第 1比較手段 7は、 第 1 8図に示すように、 積分手段 6 0 6で積分さ れた積分値と所定の第 1基準値と比較して大きい場合に判断手段 6 0 9 に異常信号を発するものである。 所定の第 1基準値とは、 プラズマトー チからの冷却水漏れによる信号波形の乱れが現れる周波数領域での安定 運転中のスぺクトル積分の値である。
又、 このスぺク トル積分値は、 第 1 9図に示すように、 プラズマトー チのプラズマガスの流量によって異なるので、 上記所定の第 1基準値は 、 プラズマガスの流量に合わせて、 第 1 9図中の鎖線の如く変化して設 定される。
電圧センサ 6 0 5は、 プラズマトーチの電源電圧の変動を検出するた めのもので、 第 2比較手段 6 0 8は、 前記電圧センサの電圧信号を所定 の第 2基準値と比較して電源の電圧降下を検出し、 判断手段 6 0 9に電 圧降下信号を送るものである。 これは、 プラズマトーチからの冷却水漏 れが発生するとプラズマトーチの電源電圧が降下することに着目して、 プラズマトーチの異常を前記第 1比較手段 7からの異常信号と併用する ことによって、 確実にプラズマトーチの異常を検出してプラズマトーチ の運転監視装置の誤作動を防止する。
判断手段 6 0 9は、 前記第 2比較手段 6 0 8と前記第 1比較手段 6 0 7からの信号により、 適切な判断をして、 非常停止信号をプラズマトー チ電源装置 6 0 3等に送ったり、 警報信号を警報ランブ 6 1 0等に送つ たりする。 判断手段 6 0 9の判断基準例をを第 2 1図に示す。 前記第 1 比較手段 6 0 7からの信号が異常信号で、 且つ、 前記第 2比較手段 6 0 8が電圧降下信号である場合には、 冷却水が多量に炉内に漏れ非常に危 険な状態にあるので、 非常停止信号を第 1 5図に示すプラズマトーチ電 源装置 6 0 3に送り、 プラズマトーチ 2の運転を直ちに停止させる。 前 記第 1比較手段 6 0 7からの信号が異常信号で、 前記第 2比較手段 6 0 8からの電圧降下信号でない場合には、 冷却水漏れが疑わしい状態で、 警報信号を簪報ランプ 6 1 0等に送り、 作業員の注意を促す。 前記第 1 比較手段 6 0 7からも異常信号が無く、 前記第 2比較手段 6 0 8からも 電圧降下信号がない場合には、 そのままプラズマトーチ 2の運転を統行 する。
このようなプラズマトーチの運転監視装置においては、 プラズマト一 チ 2から冷却水が炉内に漏れると、 炉内圧力の変動を圧力センサ 6 0 4 が検出し、 更にプラズマトーチ 2の電源電圧の変動を電圧センサ 6 0 5 が検出する。 そして、 積分手段 6 0 6が前記圧力センサ 6 0 4からの信 号波形を所定周波数帯域でスぺクトル積分し、 その積分値を第 1比較手 段 6 0 7が所定の第 1基準値と比較して大きい場合に異常信号を発する 。 また、 第 2比較手段 6 0 8が前記電圧センサ 6 0 5からの電圧信号を 所定の第 2基準値と比較して電源の電圧降下を検出する。 そして、 判断 手段 6 0 9が前記第 2比較手段 6 0 8からの電圧降下信号と前記第 1比 較手段 6 0 7からの異常信号を受けると、 プラズマトーチ 2の運転を停 止させる信号を発して、 運転中に起こるプラズマトーチの異常を即時に 検出する。
次に、 本発明のプラズマ溶融装置における他のプラズマトーチの運転 監視装置を第 2 0図により説明する。 プラズマトーチ 2は、 第 2 2図 ( a ) 、 第 2 2図 (b ) に示すように、 電極が中空円筒構造であるので、 この中空部分 6 5 6の圧力も炉内に冷却水が漏れると、 水蒸気により上 昇し変動する。 このプラズマトーチ 2内の圧力変動はプラズマガス供給 圧の変動により検出することができる。 そこで、 プラズマトーチ 2から の冷却水漏れによる異常を、 第 1 5図に示す実施例の如く炉内圧力の変 動により検出するのではなく、 ブラズマガス供給圧の変動により検出し ようとするの力 第 2 0図に示す本発明のプラズマ溶融装置における他 のプラズマトーチの運転監視装置である。
従って、 この本発明のプラズマ溶融炉における他のプラズマトーチの 運転監視装置において、 第 1 5図と異なるところは、 プラズマガスの供 給圧を測定する圧力計 6 1 7が、 プラズマガス供給装置 6 1 6とブラズ マトーチ 2との間に接続されている点である。 その圧力信号波形は、 炉 内に冷却水が漏れによる異常が積分を行う周波数带ゃ基準値が異なるだ けで、 第 1 5図に示すプラズマトーチの運転監視装置の場合と同様のパ ターンで現れるので、 圧力計 6 1 7からの信号波形の処理は、 積分を行 う周波数带ゃ基準値のみを変えて、 第 1 5図に示すプラズマトーチの運 転監視装置と同様に処理される。 そして、 判断手段 6 0 9が前記第 2比 較手段 6 0 8からの電圧降下信号と前記第 1比較手段 6 0 7からの異常 信号を受けると、 プラズマトーチ 2の運転を停止させる信号を発して、 運転中に起こるプラズマトーチの異常を即時に検出する。
このようにして、 本発明のプラズマ溶融炉におけるプラズマトーチの 運転監視装置は、 運転中に起こるプラズマトーチの異常を即時に発見で きるので、 プラズマトーチの劣化による冷却水漏れに気がつかずに運転 し続けることがなく、.多量の冷却水を炉内へ噴出して水蒸気爆発などの 災害を招くこともない。
産業上の利用可能性
以上詳細に説明した様に、 本発明のプラズマ溶融炉及びその運転方法 において、 スラグの排出孔から流出するスラグの流下方向に沿って排ガ スを誘導する耐火物製の誘導筒を配置し、 高温の排ガスの顕熱により流 下するスラグ及び排出孔の出口近傍を強制的に加熱し昇温するものは、 排出孔出口近傍でのスラグ固化による閉塞が生じにく くなり、 安定した 操業が可能なプラズマ溶融炉及びその運転方法として最適である。 更に、 プラズマトーチの傾動中心をスラグの排出孔入口と廃棄物の供 給孔出口との間の距離 Lとの間であつて廃棄物供給孔から 0. 2 L〜 0 . 4 5 Lの範囲にずらして設け、 プラズマ熱を廃棄物の供給孔近傍に与 えて廃棄物を高速溶融し、 スラグの排出孔がつまり始めたらプラズマト ーチを排出孔に向けて少し傾動させるものは、 プラズマトーチの運転を 最適化でき、 安定な出滓を確保しつつ、 電力原単位およびスラグ化率の 性能が良くなるブラズマ溶融炉及びその運転方法として最適である。 加えて、 空気等のガスをスラグ溜まりに向けて吹き込むガスノズルを 溶融炉の焼却灰の供給孔に同軸に設け、 プラズマトーチが駆動装置によ り傾動する場合は、 ガスノズルの吹き込み角度を前記プラズマトーチの 躯動装置と連動して変化させる駆動装置を镕融炉に備えさせ、 空気等の ガスを焼却灰の供給孔から、 常にプラズマトーチの照射先に位置するス ラグ溜まりに向けて吹き込んで運転するものは、 安定的なスラグの流出 及び効率の良い溶融スラグ化を確保しつつ、 焼却灰を確実にスラグ溜ま りに混入させるプラズマ瑢融炉及びその運転方法として最適である。 そして、 溶融炉の排ガス中に燃料を吹き込むことを基本として運転す るものは、 N O Xの発生を低減する運転方法として最適である。
更には、 有価物回収装置を備えたものは、 排ガス処理設備の通路を閉 塞することなく徘ガスに舍まれる有価物を効率良く回収するプラズマ溶 融伊及びその運転方法として最適である。
最後に、 プラズマトーチの運転監視装置が設けられたものは、 ブラズ マトーチの劣化による冷却水漏れに気がつかずに運転し続けて水蒸気爆 発などの災害を招くことのないプラズマ溶融炉として最適である。

Claims

請 求 の 範 囲
1 . 内部に溶融状態のスラグを溜める炉本体と、
該炉本体に設けられ、 前記スラグに対してプラズマアークを発生させ るためのプラズマトーチと、
前記炉本体に設けられ、 前記スラグに廃棄物を供給する供給孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する排ガスを上方に導くための煙 道と、
前記排出孔に設けられ、 前記煙道内で前記排ガスを前記スラグの流下 方向に ¾つて 導するための耐火物製の誘導筒と、
を備えたプラズマ溶融炉。
2 . プラズマアークで廃棄物を溶融して炉本体の内部にスラグの溜ま りを形成する工程と、
前記炉本体に設けられた排出孔から溢れた前記スラグを排ガスと共に 排出する工程と、
前記排出孔から流出する排ガスを前記スラグが流下する方向に強制的 に誘導する工程と、
高温の前記俳ガスにより、 流下する前記スラグおよび前記排出孔の出 口近傍を強制的に加熱し舁温させる工程と、
を含んでなるブラズマ溶融炉装置の運転方法。
3 - 内部に溶融状態のスラグを溜める炉本体と、
該炉本体に設けられ、 前記スラグに対してプラズマアークを発生させ るためのプラズマトーチと、
前記炉本休に設けられ、 前記スラグに廃棄物を供給する供給孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する排ガスを上方に導くための煙 道と、
前記プラズマトーチをトーチの軸方向に移動可能にすると共に、 トー チの照射方向を前記供給孔と前記排出孔を結ぶ線に沿って傾劻可能とす る躯動装置と、
を備えたプラズマ溶融炉であって、
前記プラズマトーチの傾動中心が、 前記供給孔の出口と前記排出孔の 入口との距離 Lの間であって、 前記供給孔の出口から 0 . 2 L〜0 . 4 5 Lの位置に設けられているプラズマ瑢融炉。
4 . 請求項 3記載のプラズマ溶融炉を用 、、
間欠的に前記排出孔の入口、 又は、 廃棄物供袷孔の出口に向かって傾 動させるブラズマ溶融炉装置の運転方法。
5 . 内部に溶融状態のスラグを溜める炉本体と、
該炉本休に設けられ、 前記スラグに対してプラズマアークを発生させ るためのプラズマトーチと、
前記炉本体に設けられ、 前記スラグに廃棄物を供給する供袷孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する排ガスを上方に導くための煙 道と、
該煙道から排ガスを抜き出す通路と、
該通路に接続され、 前記供給孔と同軸に設けられて、 前記排ガスを前 記炉本体内に吹き込むガスノズルと、
を備えたプラズマ溶融炉。
6 . 内部に溶融状態のスラグを溜める炉本体と、
該炉本体に設けられ、 前記スラグに対してプラズマアークを発生させ るためのプラズマトーチと、
前記炉本体に設けられ、 前記スラグに廃棄物を供給する供給孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する俳ガスを上方に導くための煙 道と、
該煙道から排ガスを抜き出す通路と、
該通路に接続され、 前記供給孔と同軸に設けられて、 前記排ガスを前 記炉本体内に吹き込むガスノズルと、
前記プラズマトーチをトーチの軸方向に移動可能にすると共に、 トー チの照射方向を前記供給孔と前記排出孔を結ぶ線にぬって傾動可能とす る第 1の駆動装置と、
前記ガスノズルの吹き込み角度を可変する第 2の躯動装置と、 を備えてなるプラズマ溶融炉。
7. 請求項 6記載のプラズマ榕融炉において、
前記第 2の駆動装置と前記第 1の駆動装置とを同じ向きに連動させる 制御装置と、
を備えてなるブラズマ' it融炉。
8. 炉本体内にプラズマトーチでプラズマアークを発生させ、 前記炉 本体の供給孔から供給される焼却灰を溶融してスラグの溜まりを形成す る工程と、
前記溜まりから溢れた前記スラグを前記炉本体に設けられた排出孔か ら連統的に排出し冷却固化する工程とを有するブラズマ溶融伊の運転方 法であって、
前記供給孔と同軸に設けられたガスノズルからガスを前記炉本体に吹 き込み、 吹き込まれた前記ガスの流れによって、 前記焼却灰を前記ブラ ズマトーチの照射先に位置する前記スラグに向けて着床させる工程を舍 ませたブラズマ溶融炉の運転方法。
9. プラズマアークで廃棄物を镕融して炉本体の内部にスラグの溜ま りを形成する工程と、
前記伊本体に設けられた排気孔から排ガスを排出する工程と、 前記排ガス中に燃料を吹き込んで N 0 Xの発生を低減する工程と、 を含んでなるブラズマ溶融炉装置の運転方法。
1 0 . 前記排気孔に前記燃料を吹き込む請求項 9記載のプラズマ溶融 炉の運転方法。
1 1 . 前記燃料の吹き込み位置の前記排ガスの温度を 5 0 0 ° C以上 とする請求項 9記載のブラズマ溶融炉の運転方法。
1 2 . 前記プラズマアークにおけるプラズマガス量の変動と前記燃料 の吹き込み量とを連動させる請求項 9記載のブラズマ溶融炉の運転方法
1 3 . プラズマアークで廃棄物を溶融して炉本体の内部にスラグの溜 まりを形成する工程と、
前記炉本体に設けられた排気孔から排ガスを排出する工程と、 前記排気孔内の排ガス中に燃料を吹き込んで N 0 Xの発生を低缄する 工程と、
前記排気孔から排出された排気ガスに更に燃料を吹き込んで N O Xの 発生を低減する工程と、
を舍んでなるプラズマ溶融炉の運転方法。
1 4 . 前記排気孔から排出された排気ガスであって、 前記燃料の吹き 込み位置の前記排気ガスの温度を 8 0 0 ° C以上とする請求項 1 3記載 のプラズマ溶融炉の運転方法。
1 5 . 内部に溶融状態のスラグを溜める炉本体と、
該炉本体に設けられ、 前記スラグに対してプラズマアークを発生させ るためのプラズマトーチと、
前記炉本体に設けられ、 前記スラグに廃棄物を供給する供袷孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する排ガスを上方に導くための煙 道と、
該煙道に接続され、 垂直方向に対して 3 0度以内に立ち上げられた水 冷管と、
を備えたプラズマ溶融炉。
1 6 . 前記水冷管の下流に設けられ、 前記水冷管内に溜まる有価物ダ ストを捕集する水冷サイクロンを
備えた請求項 1 5記載のブラズマ溶融炉。
1 7 . 前記水冷管の上流又は前記煙道の下流に希釈空気管を接続した 請求項 1 5記載のブラズマ瑢融炉。
1 8 . 前記水冷管の上流又は前記煙道の下流に前記水冷サイク口ンか らの有価物ダストの一部を戻すダスト循環路を接統した請求項 1 6記載 のプラズマ溶融炉。
1 9 . プラズマアークで廃棄物を溶融して炉本体の内部にスラグの溜 まりを形成する工程と、
前記炉本体に設けられた排出孔から溢れた前記スラグを排ガスと共に 排出する工程と、
前記排ガスを垂直軸に対して 3 0度以内に立ち上げた管を通して冷却 する工程と、
前記排ガスを更に冷却しながら有価物ダストを分離する工程と、 を含んでなるプラズマ溶融炉の運転方法。
2 0 . 有価物ダストの前記分離工程を経た排ガス温度を 6 5 0度以下 にする請求項 1 9記載のプラズマ瑢融炉の運転方法。
2 1 . 内部に溶融状態のスラグを溜める炉本体と、
該炉本体に設けられ、 プラズマガスを供給しつつ前記スラグに対して プラズマアークを発生させるためのプラズマトーチと、
前記炉本体に設けられ、 前記スラグに廃棄物を供給する供給孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する排ガスを上方に導くための煙 道と、
前記炉本体の内部の圧力の变動または前記プラズマガスの供袷圧の変 動を検出する圧力センサと、
該圧力センサからの信号波形を所定周波数帯域でスぺク トル積分する 積分手段と、
該積分手段からの積分値を所定の基準値と比較してこの δ準値より大 きいと異常信号を発する比較手段と、
を備えてなるブラズマ溶融炉。
2 2 . 前記基準値が、 前記プラズマトーチから供給される前記プラズ マガスの流量によつて変化する請求項 2 1記載のプラズマ溶融炉。
2 3 . 内部に溶融状態のスラグを溜める炉本体と、
該炉本体に設けられ、 プラズマガスを供給しつつ前記スラグに対して プラズマアークを発生させるためのプラズマトーチと、
前記炉本体に設けられ、 前記スラグに廃棄物を供袷する供給孔と、 前記炉本体に設けられ、 溢れた前記スラグを流下させる排出孔と、 該排出孔から前記スラグと共に流出する排ガスを上方に導くための煙 道と、
前記炉本体の内部の圧力の変動または前記プラズマガスの供給圧の変 動を検出する圧力センサと、
該圧力センサからの信号波形を所定周波数带域でスぺク トル積分する 積分手段と、
該積分手段からの積分値を所定の基準値と比較してこの基準値より大 きいと異常信号を発する第 1比較手段と、
前記プラズマトーチの電源電圧の変動を検出する電圧センサと、 該電圧センサの電圧信号を所定の基準値と比較して電源の電圧降下を 検出する第 2比較手段と、
該第 2比較手段からの電圧降下信号と前記第 1比較手段からの異常信 号を受けた時に、 プラズマトーチの運転を停止させる信号を発する判断 手段と、
を備えたプラズマ溶融炉。
PCT/JP1994/000362 1993-03-08 1994-03-08 Four a fusion de plasma et mode de fonctionnement de ce four Ceased WO1994020791A1 (fr)

Priority Applications (5)

Application Number Priority Date Filing Date Title
DK94908506T DK0645584T3 (da) 1993-03-08 1994-03-08 Fremgangsmåde ved drift af en plasmaovn
CA 2135204 CA2135204C (en) 1993-03-08 1994-03-08 Plasma furnace and a method of operating the same
EP19940908506 EP0645584B1 (en) 1993-03-08 1994-03-08 Method of operating a plasma furnace
DE69411835T DE69411835T2 (de) 1993-03-08 1994-03-08 Verfahren zum Betrieb eines Plasmaschmelzofens
US08/556,022 US5579705A (en) 1993-03-08 1995-11-13 Plasma furnace and a method of operating the same

Applications Claiming Priority (14)

Application Number Priority Date Filing Date Title
JP5/75199 1993-03-08
JP7519993 1993-03-08
JP5/75200 1993-03-08
JP7520093A JPH06257725A (ja) 1993-03-08 1993-03-08 プラズマ溶融炉及びその運転方法
JP5/78757 1993-03-11
JP7875793A JPH06265134A (ja) 1993-03-11 1993-03-11 プラズマ溶融炉における有価物回収装置及び有価物回収方法
JP5109919A JP3032400B2 (ja) 1993-03-08 1993-04-12 プラズマ炉におけるNOx低減方法
JP10992093A JPH06300234A (ja) 1993-04-12 1993-04-12 プラズマ溶融炉及びその出滓方法
JP5/109920 1993-04-12
JP5/109919 1993-04-12
JP5/120790 1993-04-23
JP5120790A JP3039590B2 (ja) 1993-04-23 1993-04-23 プラズマ溶融炉及びその運転方法
JP5/31300U 1993-05-18
JP1993031300U JP2591142Y2 (ja) 1993-05-18 1993-05-18 プラズマトーチの運転監視装置

Publications (1)

Publication Number Publication Date
WO1994020791A1 true WO1994020791A1 (fr) 1994-09-15

Family

ID=27564277

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP1994/000362 Ceased WO1994020791A1 (fr) 1993-03-08 1994-03-08 Four a fusion de plasma et mode de fonctionnement de ce four

Country Status (6)

Country Link
EP (2) EP0645584B1 (ja)
AT (2) ATE168762T1 (ja)
CA (2) CA2205529C (ja)
DE (2) DE69427412T2 (ja)
DK (1) DK0645584T3 (ja)
WO (1) WO1994020791A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110121750A (zh) * 2017-12-06 2019-08-13 原子能股份公司 放射性废物处理装置
CN111453973A (zh) * 2020-05-08 2020-07-28 武汉美尔汀环保科技有限公司 一种电阻式熔融炉及起炉方法

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6355904B1 (en) * 1996-06-07 2002-03-12 Science Applications International Corporation Method and system for high-temperature waste treatment
CA2188357C (en) * 1996-10-21 1999-09-07 Peter G. Tsantrizos plasma gasification and vitrification of ashes
JP3098733B2 (ja) * 1996-12-25 2000-10-16 株式会社神戸製鋼所 溶融処理装置
EP0959049A1 (de) * 1998-05-22 1999-11-24 DBI DEUTSCHES BRENNSTOFFINSTITUT ROHSTOFF &amp; ANLAGENTECHNIK GmbH Verfahren und Vorrichtung zur thermischen Umsetzung von Reststoffen
FR2807912B1 (fr) * 2000-04-17 2003-06-27 Lasers Et Tech Avancees Bureau Procede et torche a plasma pour traiter une surface dans une cavite, et installation de remplissage bouchage s'y rapportant
CN103184403B (zh) * 2011-12-27 2016-12-07 鸿富锦精密工业(深圳)有限公司 等离子成膜装置
CN103589867B (zh) * 2013-11-20 2015-03-25 北京环宇冠川等离子技术有限公司 等离子体炬加热技术处理炼铁灰、泥和选矿尾砂的方法及装置
RU2729301C1 (ru) * 2020-03-10 2020-08-05 Акционерное общество «Радиотехнические и Информационные Системы Воздушно-космической обороны (АО «РТИС ВКО») Утилизатор бытовых отходов
DE102022211214A1 (de) 2022-10-21 2024-05-02 Thermal Processing Solutions GmbH Verfahren zum Schmelzen und Warmbehandeln von Feststoffen
DE102022211216A1 (de) * 2022-10-21 2024-05-02 Technische Universität Bergakademie Freiberg, Körperschaft des öffentlichen Rechts Verfahren zum Schmelzen und Warmbehandeln von Feststoffen
CN116221735A (zh) * 2023-03-29 2023-06-06 常州大学 油基钻屑等离子体气化熔融炉以及油基钻屑处理方法
CN119334161B (zh) * 2024-12-19 2025-04-15 广东巨晨装备科技有限公司 一种废铝回收熔炉用废气处理系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5044105A (ja) * 1973-08-22 1975-04-21
JPS6287707A (ja) * 1985-10-14 1987-04-22 Hitachi Zosen Corp NOx抑制燃焼法
JPS63315819A (ja) * 1987-06-15 1988-12-23 Kubota Ltd 廃棄物溶融炉
JPH0355411A (ja) * 1989-07-25 1991-03-11 Ebara Infilco Co Ltd 焼却灰の溶融処理装置
JPH04309833A (ja) * 1991-04-08 1992-11-02 Nkk Corp タンディッシュ内溶鋼加熱用プラズマトーチの冷却水            漏水検出装置

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2286323A (en) * 1940-01-11 1942-06-16 Corning Glass Works Apparatus and method for feeding and fabricating glass
US3372224A (en) * 1964-09-15 1968-03-05 Allegheny Ludlum Steel Control system for consumable electrode arc melting furnace to raise the electrode upon a power failure
GB1185742A (en) * 1967-04-18 1970-03-25 Qualitats Und Edelstahl Kom Ve Plasma Arc Smelting Units
GB1390351A (en) * 1971-02-16 1975-04-09 Tetronics Research Dev Co Ltd High temperature treatment of materials
GB8321525D0 (en) * 1983-08-10 1983-09-14 Rockware Group Plc Glass articles
DE3841918C1 (ja) * 1988-12-13 1990-04-12 Sorg Gmbh & Co Kg, 8770 Lohr, De
DE4112162C1 (ja) * 1991-04-13 1992-07-30 Beteiligungen Sorg Gmbh & Co Kg, 8770 Lohr, De

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5044105A (ja) * 1973-08-22 1975-04-21
JPS6287707A (ja) * 1985-10-14 1987-04-22 Hitachi Zosen Corp NOx抑制燃焼法
JPS63315819A (ja) * 1987-06-15 1988-12-23 Kubota Ltd 廃棄物溶融炉
JPH0355411A (ja) * 1989-07-25 1991-03-11 Ebara Infilco Co Ltd 焼却灰の溶融処理装置
JPH04309833A (ja) * 1991-04-08 1992-11-02 Nkk Corp タンディッシュ内溶鋼加熱用プラズマトーチの冷却水            漏水検出装置

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110121750A (zh) * 2017-12-06 2019-08-13 原子能股份公司 放射性废物处理装置
CN111453973A (zh) * 2020-05-08 2020-07-28 武汉美尔汀环保科技有限公司 一种电阻式熔融炉及起炉方法

Also Published As

Publication number Publication date
CA2205529A1 (en) 1994-09-15
DE69411835T2 (de) 1999-01-14
ATE168762T1 (de) 1998-08-15
CA2135204C (en) 2000-04-18
ATE201863T1 (de) 2001-06-15
DE69427412D1 (de) 2001-07-12
CA2205529C (en) 2000-10-24
DE69427412T2 (de) 2001-10-25
EP0645584B1 (en) 1998-07-22
EP0645584A1 (en) 1995-03-29
DK0645584T3 (da) 1998-10-26
EP0757972A2 (en) 1997-02-12
EP0757972A3 (en) 1997-02-19
CA2135204A1 (en) 1994-09-15
EP0757972B1 (en) 2001-06-06
EP0645584A4 (en) 1995-07-19
DE69411835D1 (de) 1998-08-27

Similar Documents

Publication Publication Date Title
US5579705A (en) Plasma furnace and a method of operating the same
AU2003229428B8 (en) Hazardous waste treatment method and apparatus
US5616296A (en) Waste management facility
WO1994020791A1 (fr) Four a fusion de plasma et mode de fonctionnement de ce four
EP1367323A1 (en) Gasification melting furnace and gasification melting method for combustible refuse and/or burned ash
JP4179122B2 (ja) 溶融スラグ水砕水の処理方法及び装置
EA004993B1 (ru) Способ обработки шлама с частицами, содержащими металл, оксид металла или гидроокись металла, и аппарат для осуществления данного способа
JP3280265B2 (ja) 焼却残渣と飛灰の溶融処理装置及びその溶融処理方法
JP3904379B2 (ja) 二次燃焼室のダスト排出装置
JP4197289B2 (ja) 灰処理設備
JP4725960B2 (ja) 廃棄物溶融設備水砕水汚染防止方法及びその装置
JP3049170B2 (ja) 旋回流溶融炉
JP3575785B2 (ja) 二次燃焼室の落下灰処理方法及びその装置
JP2008285730A (ja) 鉄鋼材料分別回収装置及び方法
JP4102717B2 (ja) 内部循環流動層ガス化炉および廃棄物処理装置
JP2005195229A (ja) 灰溶融装置
JPH0842828A (ja) 竪型焼却炉の運転管理方法
JP4972458B2 (ja) 灰溶融炉の燃焼室
JPH06300234A (ja) プラズマ溶融炉及びその出滓方法
JPH0275814A (ja) サイクロン型溶融処理炉
JP2006010199A (ja) 廃棄物の溶融処理方法
JPH0721329B2 (ja) 都市ごみ焼却灰の処理方法および装置

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): CA US

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): AT BE CH DE DK ES FR GB GR IE IT LU MC NL PT SE

WWE Wipo information: entry into national phase

Ref document number: 2135204

Country of ref document: CA

WWE Wipo information: entry into national phase

Ref document number: 1994908506

Country of ref document: EP

ENP Entry into the national phase

Ref document number: 1994 325433

Country of ref document: US

Date of ref document: 19941123

Kind code of ref document: A

121 Ep: the epo has been informed by wipo that ep was designated in this application
WWP Wipo information: published in national office

Ref document number: 1994908506

Country of ref document: EP

ENP Entry into the national phase

Ref document number: 1995 556022

Country of ref document: US

Date of ref document: 19951113

Kind code of ref document: A

ENP Entry into the national phase

Ref document number: 1997 838011

Country of ref document: US

Date of ref document: 19970422

Kind code of ref document: A

WWG Wipo information: grant in national office

Ref document number: 1994908506