US20230080917A1 - Method for tuning choke operation in a managed pressure drilling system - Google Patents
Method for tuning choke operation in a managed pressure drilling system Download PDFInfo
- Publication number
- US20230080917A1 US20230080917A1 US17/963,827 US202217963827A US2023080917A1 US 20230080917 A1 US20230080917 A1 US 20230080917A1 US 202217963827 A US202217963827 A US 202217963827A US 2023080917 A1 US2023080917 A1 US 2023080917A1
- Authority
- US
- United States
- Prior art keywords
- choke
- pressure
- well
- fractional
- fluid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F3/00—Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
- G06F3/16—Sound input; Sound output
- G06F3/165—Management of the audio stream, e.g. setting of volume, audio stream path
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B21/00—Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
- E21B21/08—Controlling or monitoring pressure or flow of drilling fluid, e.g. automatic filling of boreholes, automatic control of bottom pressure
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F21—LIGHTING
- F21V—FUNCTIONAL FEATURES OR DETAILS OF LIGHTING DEVICES OR SYSTEMS THEREOF; STRUCTURAL COMBINATIONS OF LIGHTING DEVICES WITH OTHER ARTICLES, NOT OTHERWISE PROVIDED FOR
- F21V33/00—Structural combinations of lighting devices with other articles, not otherwise provided for
- F21V33/0004—Personal or domestic articles
- F21V33/0052—Audio or video equipment, e.g. televisions, telephones, cameras or computers; Remote control devices therefor
- F21V33/0056—Audio equipment, e.g. music instruments, radios or speakers
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F3/00—Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
- G06F3/01—Input arrangements or combined input and output arrangements for interaction between user and computer
- G06F3/048—Interaction techniques based on graphical user interfaces [GUI]
- G06F3/0484—Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range
- G06F3/04847—Interaction techniques to control parameter settings, e.g. interaction with sliders or dials
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10H—ELECTROPHONIC MUSICAL INSTRUMENTS; INSTRUMENTS IN WHICH THE TONES ARE GENERATED BY ELECTROMECHANICAL MEANS OR ELECTRONIC GENERATORS, OR IN WHICH THE TONES ARE SYNTHESISED FROM A DATA STORE
- G10H1/00—Details of electrophonic musical instruments
- G10H1/0008—Associated control or indicating means
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10L—SPEECH ANALYSIS TECHNIQUES OR SPEECH SYNTHESIS; SPEECH RECOGNITION; SPEECH OR VOICE PROCESSING TECHNIQUES; SPEECH OR AUDIO CODING OR DECODING
- G10L25/00—Speech or voice analysis techniques not restricted to a single one of groups G10L15/00 - G10L21/00
- G10L25/48—Speech or voice analysis techniques not restricted to a single one of groups G10L15/00 - G10L21/00 specially adapted for particular use
- G10L25/51—Speech or voice analysis techniques not restricted to a single one of groups G10L15/00 - G10L21/00 specially adapted for particular use for comparison or discrimination
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05B—ELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
- H05B47/00—Circuit arrangements for operating light sources in general, i.e. where the type of light source is not relevant
- H05B47/10—Controlling the light source
- H05B47/105—Controlling the light source in response to determined parameters
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B2200/00—Special features related to earth drilling for obtaining oil, gas or water
- E21B2200/02—Down-hole chokes or valves for variably regulating fluid flow
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10H—ELECTROPHONIC MUSICAL INSTRUMENTS; INSTRUMENTS IN WHICH THE TONES ARE GENERATED BY ELECTROMECHANICAL MEANS OR ELECTRONIC GENERATORS, OR IN WHICH THE TONES ARE SYNTHESISED FROM A DATA STORE
- G10H1/00—Details of electrophonic musical instruments
- G10H1/0033—Recording/reproducing or transmission of music for electrophonic musical instruments
- G10H1/0041—Recording/reproducing or transmission of music for electrophonic musical instruments in coded form
- G10H1/0058—Transmission between separate instruments or between individual components of a musical system
- G10H1/0066—Transmission between separate instruments or between individual components of a musical system using a MIDI interface
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10H—ELECTROPHONIC MUSICAL INSTRUMENTS; INSTRUMENTS IN WHICH THE TONES ARE GENERATED BY ELECTROMECHANICAL MEANS OR ELECTRONIC GENERATORS, OR IN WHICH THE TONES ARE SYNTHESISED FROM A DATA STORE
- G10H2210/00—Aspects or methods of musical processing having intrinsic musical character, i.e. involving musical theory or musical parameters or relying on musical knowledge, as applied in electrophonic musical tools or instruments
- G10H2210/031—Musical analysis, i.e. isolation, extraction or identification of musical elements or musical parameters from a raw acoustic signal or from an encoded audio signal
- G10H2210/066—Musical analysis, i.e. isolation, extraction or identification of musical elements or musical parameters from a raw acoustic signal or from an encoded audio signal for pitch analysis as part of wider processing for musical purposes, e.g. transcription, musical performance evaluation; Pitch recognition, e.g. in polyphonic sounds; Estimation or use of missing fundamental
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10H—ELECTROPHONIC MUSICAL INSTRUMENTS; INSTRUMENTS IN WHICH THE TONES ARE GENERATED BY ELECTROMECHANICAL MEANS OR ELECTRONIC GENERATORS, OR IN WHICH THE TONES ARE SYNTHESISED FROM A DATA STORE
- G10H2210/00—Aspects or methods of musical processing having intrinsic musical character, i.e. involving musical theory or musical parameters or relying on musical knowledge, as applied in electrophonic musical tools or instruments
- G10H2210/031—Musical analysis, i.e. isolation, extraction or identification of musical elements or musical parameters from a raw acoustic signal or from an encoded audio signal
- G10H2210/076—Musical analysis, i.e. isolation, extraction or identification of musical elements or musical parameters from a raw acoustic signal or from an encoded audio signal for extraction of timing, tempo; Beat detection
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10H—ELECTROPHONIC MUSICAL INSTRUMENTS; INSTRUMENTS IN WHICH THE TONES ARE GENERATED BY ELECTROMECHANICAL MEANS OR ELECTRONIC GENERATORS, OR IN WHICH THE TONES ARE SYNTHESISED FROM A DATA STORE
- G10H2220/00—Input/output interfacing specifically adapted for electrophonic musical tools or instruments
- G10H2220/021—Indicator, i.e. non-screen output user interfacing, e.g. visual or tactile instrument status or guidance information using lights, LEDs or seven segments displays
- G10H2220/026—Indicator, i.e. non-screen output user interfacing, e.g. visual or tactile instrument status or guidance information using lights, LEDs or seven segments displays associated with a key or other user input device, e.g. key indicator lights
- G10H2220/061—LED, i.e. using a light-emitting diode as indicator
- G10H2220/066—Colour, i.e. indications with two or more different colours
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10H—ELECTROPHONIC MUSICAL INSTRUMENTS; INSTRUMENTS IN WHICH THE TONES ARE GENERATED BY ELECTROMECHANICAL MEANS OR ELECTRONIC GENERATORS, OR IN WHICH THE TONES ARE SYNTHESISED FROM A DATA STORE
- G10H2220/00—Input/output interfacing specifically adapted for electrophonic musical tools or instruments
- G10H2220/155—User input interfaces for electrophonic musical instruments
- G10H2220/405—Beam sensing or control, i.e. input interfaces involving substantially immaterial beams, radiation, or fields of any nature, used, e.g. as a switch as in a light barrier, or as a control device, e.g. using the theremin electric field sensing principle
- G10H2220/411—Light beams
Definitions
- This disclosure relates to the field of flow control devices (“chokes”) used in well drilling. More specifically, the disclosure relates to chokes used during drilling operations for managing pressure in a well annulus.
- Managed pressure drilling is used to maintain drilling fluid pressure in the well annulus (the space between open formations and a drilling tool “string”) of a drilling well within a range between exposed formation fluid (“pore”) pressure and exposed formation mechanical failure (“fracture”) pressure.
- the difference between the foregoing pressures is known as a pressure window, is sometimes referred to as the “drilling margin” and represents the pressure range within which little or no formation fluids are drawn into the well and little or no drilling fluids are lost to the exposed formations.
- drilling fluids are typically weighted (made more dense than plain water and/or oil to exert higher pressure), other factors including fluid friction, pipe rotation, and applied surface back pressure (“ASBP”) contribute to the effective fluid pressure acting on the exposed formations.
- ASBP applied surface back pressure
- MPD Managed pressure drilling
- rig drilling unit
- MPD systems seal the annulus surrounding the drill string for all operations, including rotating and stripping operations, and improve the ability of equipment on the drilling unit (“rig”) to manage well annulus pressure.
- MPD systems allow for the application of “surface back pressure” to the well, namely, fluid pressure applied from equipment at the surface to the well annulus.
- the drilling rig operator may cause the MPD system to apply additional surface back pressure to increase the pressure overbalance acting on the exposed formations, or he may drill ahead with back pressure and relatively less dense drilling fluid to allow for rapid downward bottom hole pressure adjustment to mitigate fluid losses.
- surface back pressure may be increased to offset the loss of pressure otherwise resulting from circulation-caused friction that occurs when the drilling fluid (mud) pumps are stopped.
- pressure is increased during connections when the mud pumps are stopped by an amount proportional to the difference between the equivalent circulating density (“ECD”) or equivalent well pressure including fluid friction pressure, and the equivalent static density (“ESD”) or equivalent well pressure with no fluid friction pressure.
- ECD equivalent circulating density
- ESD equivalent static density
- MPD systems may allow the drilling rig operator to more quickly detect warning signs of a potentially hazardous situation.
- all returning fluids from the well may be measured with greater accuracy, enabling faster fluid influx and loss detection than is available using conventional drilling techniques.
- Faster detection and response time may result in a smaller influx because the duration of the underbalanced condition is reduced.
- Smaller influxes are typically easier to circulate out of the well because there is typically less gas or light annular fluids that place less stress on weaker formations.
- MPD systems may be used to apply surface back pressure to the well to stop the influx before shutting the blowout preventer (“BOP”), which eliminates drawdown pressure acting on the formation following mud pump shutdown and closure of the BOP and further reduces the influx volume.
- BOP blowout preventer
- the annular sealing system may include a rotating control device (“RCD”), an active control device (“ACD”), or other type of annular sealing device that is configured to seal the annulus surrounding the drill pipe while it rotates and moves axially. The annulus is thus encapsulated such that it is not exposed to the atmosphere.
- the drill string isolation tool is usually disposed directly below the annular sealing system and includes an annular packer that encapsulates the well and maintains annular pressure when rotation has stopped and the annular sealing system, or components thereof, are being installed, serviced, removed, or otherwise disengaged.
- the flow spool is usually disposed directly below the drill string isolation tool and, as part of the pressurized fluid return system, diverts fluids from below the annular seal to the surface.
- the flow spool is in fluid communication with a choke manifold, typically disposed on a platform of the drilling rig that is in fluid communication with a mud-gas separator, shakers, or other fluids processing system.
- the pressure tight seal on the annulus allows for the precise control of wellbore pressure by manipulation of the choke settings of the choke manifold and the corresponding application of surface back pressure.
- One or more variable orifice chokes in the choke manifold may be operated automatically in response to measurements of one or more parameters having a relationship to the annulus pressure, for example and without limitation flow rate of fluid out of the well.
- Automating operation of the one or more variable orifice chokes requires tuning or calibrating of the choke orifice with respect to annulus fluid pressure for each set of well drilling equipment specifications, well depth, well diameter and drilling fluid rheological properties among other parameters.
- the characterizations in at least one of (a) and (b), and the characterization in (c) are used to calculate control parameters for a proportional integral differential controller having as output the choke opening and as input the fluid pressure in the well before the choke.
- the characterizing change in flow rate of fluid through the choke with respect to fractional choke opening at a substantially constant pressure drop across the choke comprises pumping fluid through a conduit extended into the well, measuring flow rate of fluid leaving the well through an annular space between the conduit and a wall of the well, measuring pressure of fluid in the well upstream of the choke, adjusting the fractional choke opening and changing a rate of the pumping fluid so that the measured pressure remains substantially constant.
- the characterizing a response time of pressure in the well to changes in the fractional choke opening, a delay time of pressure response after a change in fractional choke opening and a surface back pressure applied to the well with respect to fractional choke opening comprises measuring pressure in the well upstream of the choke, measuring pressure upstream of the choke, and change in the measured pressure with respect to change in the fractional choke opening while pumping fluid into the well at a substantially constant rate.
- the characterizing a response time of pressure in the well to changes in the fractional choke opening comprises measuring pressure in the well upstream of the choke with respect to time, and determining an elapsed time between change in the fractional choke opening and a change in the measured pressure while pumping fluid into the well at a substantially constant rate.
- FIG. 1 shows an example embodiment of a managed pressure drilling (MPD) system.
- MPD managed pressure drilling
- FIG. 2 shows an example embodiment of an automatic choke.
- FIG. 3 shows an example embodiment of a control system.
- FIG. 4 shows a graph of an example well system response to changes in pressure.
- FIG. 5 shows a graph of an example choke response with respect to position or opening.
- FIG. 6 shows an example sensitivity curve for a choke.
- FIG. 7 shows identifiable regions within a choke response as in FIG. 5 .
- FIG. 8 shows a graph of an example embodiment of choke “fingerprinting.”
- FIG. 9 shows a graph defining parameters used in choke characterization.
- MPD managed pressure drilling
- reference numeral 100 refers, in general, to an embodiment of a system (e.g., an MPD system) for controlling the fluid pressures within an oil or gas well 10 .
- the system 100 includes an automatic choke 102 for controllably releasing pressurized fluids from an annular space (“annulus”) 24 between a wellbore casing 16 (and open drilled well below the casing 16 , not shown) and drill pipe 18 .
- Fluid e.g., drilling mud
- the fluid leaves the bottom of the drill pipe 18 and moves into the annulus 24 .
- the annulus 24 is closed by a rotating control device 26 or similar annular seal.
- the fluid is released from the annulus 24 through an automatic choke 102 which controllably restricts the outflow thereby to create back pressure within the wellbore 12 .
- the outflow ultimately moves from the choke 102 to a mud tank 20 .
- a control system 104 controls the operation (i.e., the effective orifice size) of the automatic choke 102 to maintain a selected pressure in the wellbore 12 .
- the control system 104 may be in signal communication with a display and operator control panel 34 wherein control signals may be entered by a system operator, and system response may be observed.
- a pressure sensor 32 a may measure pressure in the wellbore casing 16 (CSP).
- Another pressure sensor 32 b may measure pressure in the drill pipe (DPP) or stand pipe (SPP).
- a flow meter such as a Coriolis flow meter 106 may measure fluid flow out of the casing 16 and into the choke 102 .
- Another flowmeter 108 may measure fluid flow rate into the drill pipe 18 .
- the other flow meter 108 may be substituted by or supplemented with a stroke counter on the drilling unit mud pump(s) 22 .
- the foregoing sensors may be in signal communication with the control system 104 .
- Some embodiments may include a sensor 32 c that can measure pressure proximate the bottom of the wellbore 12 , for example, a pressure while drilling (PWD) sensor.
- PWD pressure while drilling
- the automatic choke 102 may comprise a movable valve element 102 a that defines a continuously variable flow path resistance depending upon the position of the movable valve element 102 a .
- the position of the movable valve element 102 a may controlled by a first control pressure signal 102 b , and an opposite acting, second control pressure signal 102 c .
- the first control pressure signal 102 b may be representative of a set point pressure (SPP) that is generated by the control system 104
- the second control pressure signal 102 c is representative of the fluid pressure inside the casing 16 (CSP).
- the automatic choke 102 provides pressure regulation than can controllably bleed off pressurized fluids from the annulus 24 and thereby also controllably create and maintain back pressure in the wellbore 12 .
- the automatic choke 102 may be further provided substantially as described in U.S. Pat. No. 6,253,787 issued to Suter et al., which is incorporated herein by reference in its entirety
- the system 100 may enable the CSP to be automatically controlled by the human system operator 104 c selecting the desired SPP.
- the automatic choke 102 then regulates the CSP as a function of the selected SPP.
- the illustrated embodiment herein may be implemented in the form of pressure transducers for measuring SPP and CSP, and the control system 104 may be implemented in the form of a programmable logic controller, floating point gate array, application specific integrated circuit or any other microcomputer, computer, computer processor or controller known in the art. Accordingly, the embodiment explained above is not a limitation on the scope of the present disclosure.
- controlling pressure in the annulus is performed by controlling position of the automatic choke 102 in response to measurements of pressure and flow of drilling fluid (mud) into and/or out of the wellbore 12 .
- a method according to the present disclosure has as an objective the calibration or “tuning” of the pressure control response of the MPD system, and in particular operation of the control system 104 as to its control of the automatic choke 102 in order to more precisely maintain well pressure under foreseeable operating conditions during drilling.
- Open loop stable means that if a change in choke opening (position) is made, the pressure in the well will change correspondingly without going out of bounds or predetermined limits, if the choke opening is itself within reasonable limits. This characteristic may be used to predict an initial set of stable proportional integral differential (PID) control loop parameters.
- PID proportional integral differential
- the pressure as measured on the annulus side of the choke is indicated by curve 401 .
- a localized peak, at 403 in the actual well pressure response shown in FIG. 4 is due to characteristics of the MPD system surface equipment and is not due to well characteristics. This peak 403 is characteristic for marine (offshore) MPD operations and is commonly encountered. In determining the parameters of the well for choke tuning according to the present disclosure the peak 403 shown in FIG. 4 may be disregarded.
- the theoretical well pressure response is shown at curve 402 .
- the choke's flow characteristic is usually not linear but follows an approximate sigmoid function. This means that a nominal change, e.g., a nominal fractional step change in choke opening, does not result in a corresponding nominal flow variation over the entire range of choke opening. This is a well-known characteristic of chokes.
- FIG. 5 shows a graph of characteristic flow for a choke, called Cv, at curve 501 .
- Cv may be presented in units of flow rate of the choke at a specified pressure drop (in this case 1.0 pounds per square inch) for a particular fluid; in many cases for commercial characterization, pure water at 60 degrees Fahrenheit is used for characterization. Expressed as a formula:
- the choke characteristic flow Cv may be determined for the particular choke, that is, the choke 102 in FIG. 1 , with respect to the actual drilling fluid used to drill the well ( FIG. 1 ).
- the MPD control system ( 104 in FIG. 1 ) may comprise, e.g., in software operating on any form of computer or processor, a feed forward controller and a PID controller to ensure reliable pressure control while the MPD system is operating automatically.
- the feed forward controller is used to predict the optimal new choke opening in response to a change in determined or chosen (setpoint) well pressure, while the PID controller fine-tunes the choke opening to maintain a chosen target well pressure. This makes it possible to accommodate large pressure setpoint variations or determined pressure variations with only minimal overshoot in choke operation, and to substantially reduce the time needed for the MPD system to respond to a change in the setpoint pressure.
- the PID controller may have different options available, for example, “Manual” PID selection where a static set of PID parameters is used, and “Automatic” PID selection where the operator can define two (or more) sets of PID parameters, dependent on the choke characteristics in low and high operating (opening) range.
- “Manual” PID selection where a static set of PID parameters is used
- “Automatic” PID selection where the operator can define two (or more) sets of PID parameters, dependent on the choke characteristics in low and high operating (opening) range.
- the most sophisticated models may use continuous PID parameter variations across the operating range. This will avoid the need for any manual retuning for large setpoint or determined well pressure step changes that would correspondingly require large step changes in choke opening.
- FIG. 7 is a graph illustrating a choke having an ordinary, non-linear Cv characteristic that may be used in a choke tuning example.
- the choke Cv may be approximated over the entire choke opening range by three different slopes A—[opening in the range of about 10%-45%], B—[opening in the range of about 45%-80%] and C—[opening in the range of about 80%-100%].
- the system operator may choose which of the three choke opening ranges is of most interest during MPD system operation. If the MPD system is run with choke operating predominantly within the B,C opening range, then tuning can be best done in these ranges. Consequently, if the upper slope C is not considered important for pressure control, the system tuning may be performed with choke within opening ranges A, B.
- the following actions may be undertaken when first initializing the MPD system on any specific well. Because every well may be different, that is, have a unique pressure response with respect to changes in drilling rig mud pump operating rate and choke position, it is desirable to perform the following steps at the start of drilling operations on any well or well section.
- Cv curve that is, the flow/choke %/pressure characterization for the specific choke ( 102 in FIG. 1 ) as actually used in the MPD system on the well being drilled.
- Maximum drilling fluid pressure and flow rates may be determined for any particular well.
- An example method for characterizing the flow/choke %/pressure, that is, determining the Cv curve, may be implemented according to the following table.
- Step Activity 1 Activate choke in manual choke control mode and open 100%. 3. Run the mud pumps up to the maximum allowable flow according to the well construction plan 4. Close the active choke in 10% intervals from 100% to 70%. 5. At choke set points below 70%, decrease flow as per plan to the next 5% choke value before moving the choke to this value. 6. Optionally if the curve below 35% choke opening needs to be determined, decrease choke set points in 2% increments. 7. Ramp Down Mud Pumps and, open all chokes to 100% 8. Repeat the procedure for any other chokes in the system (if multiple chokes are present). 9. Use logged data points to create Cv table 10. If necessary re-adjust the Cv curve loaded in the system to match the measured curve
- FIG. 8 shows a graph of an example embodiment of choke “fingerprinting”, wherein actual surface back pressure (SPB) with respect to flow rate and choke opening combinations are used to determined Cv values at different choke openings.
- SPB surface back pressure
- Determining the well parameters to be used in the PID controller can be a fast and easy to implement procedure.
- the system characteristic response of the combination of choke and well is related to the particular flow characteristics of both; therefore characterization should be repeated for every new well section (e.g., when a casing or liner is set and/or drill bit diameter changes) or if large changes in drilling operating parameters are encountered.
- the characterization should be performed within the expected range of drilling operating parameters (mud flow rate, surface back pressure, mud weight, etc.).
- the well parameter determination has to be performed in expected operating region A, B or C of the Cv curve (see FIG. 7 ) in order for the right parameters to be entered into the PID controller.
- the well parameter determination may be performed in manual choke control mode (i.e., with automatic control of the choke 102 disabled) and may comprise using predetermined steps in the choke opening.
- the surface back pressure (SBP) response is measured and will provide key inputs for determining optimal PID controller parameters.
- SBP surface back pressure
- the steps in the table below may be performed in several different choke opening ranges to allow for the choke curve to be optimally covered.
- Step Activity 1 Ensure the “Choke Cv curve” is configured in the control system.
- 2 Line up flow lines to one choke only. Close the inactive choke completely.
- 3 Set the MPD-CS in manual control mode and open the choke to the max of the first slope plus a margin and request the driller to slowly increase the pump speed.
- 4 Freeze the pump speed when a desired surface back pressure is reached. Let the system stabilize until flow in/flow out are the same, or with a fixed offset. 5 Manually close the choke in fixed increments and log the SBP (psi) and choke opening (%) over time. The system needs to stabilize between each step. 6 While in manual mode open the choke to the max of the second slope plus a margin and request the driller to slowly increase the pump speed.
- t choke (or each choke in a multiple choke MPD system) fill in the determined values in the following table using the graph and definitions in FIG. 9 as guidance for determining t choke , t SBP and t S .
- the number of steps in any embodiment may be any chosen number.
- t SBP is the first indication of the real pressure rise. It is not the time slope of the pressure curve.
- Step Km (psi/%) Tm (sec) Sm (sec) K m SBP change Choke change ⁇ ( psi ) ( % ) t SBP ⁇ t choke t s ⁇ t SBP 1 2 3 Average Region
- This step will provide the starting parameters for the PID controller.
- the starting parameter calculations may provide in most cases stable operation of the PID controller. This can be used as a basis to fine tune performance for specific situations. It has been determined that effective PID controller operation may be effected using three parameters, Km, Tm and Sm.
- Sm represents the time constant of the well, in essence how fast the well reacts to changes in choke setting.
- Tm represents time delay, that is, when the well starts reacting after a change in choke setting is made and Km represents the gain factor of the well and MPD system, that is, how the SBP changes as function of the choke opening change. It has been found that by empirically determining the foregoing three parameters, the MPD system can be made to operate reliably by the system operator without the need for guessing values of system operating parameters.
- Determining the basic control parameters based on the step response of the system allows the definition of a stable set of PID parameters. These PID parameters can be used to further refine performance if needed. No knowledge of the well, mud properties or choke curves is required.
- the functionality of the choke(s) in an MPD system it is possible to accurately estimate a fluid volume necessary to add to or remove from the drilling circulation system (comprising the mud pump 22 , drill pipe, casing 16 , wellbore and annulus 24 in FIG. 1 ) in order to cause a predetermined change in the surface back pressure (SBP).
- SBP surface back pressure
- Such estimation makes possible much more rapid MPD system response to changes in setpoint pressure.
- increasing the setpoint pressure may be effected by substantial closure of the choke ( 102 in FIG. 1 ) for a determined time, after which the choke ( 102 in FIG. 1 ) is opened to a new fractional opening that will result in the SBP being substantially at the new setpoint.
- Corresponding opening of the choke may take place to effect a drop in the setpoint pressure. Accordingly, MPD system response using calibrated choke(s) according to the present disclosure may operate more quickly and therefore safely than using uncalibrated choke(s) controlled only by the PID controller or equivalent.
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Multimedia (AREA)
- Theoretical Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Human Computer Interaction (AREA)
- Acoustics & Sound (AREA)
- Health & Medical Sciences (AREA)
- Audiology, Speech & Language Pathology (AREA)
- General Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Mechanical Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- General Health & Medical Sciences (AREA)
- Computational Linguistics (AREA)
- Signal Processing (AREA)
- Earth Drilling (AREA)
- Fluid-Pressure Circuits (AREA)
- Electrical Discharge Machining, Electrochemical Machining, And Combined Machining (AREA)
Abstract
Description
- Continuation of International Application No. PCT/US2021/026402 filed on Apr. 8, 2021. Priority is claimed from U.S. Provisional Application No. 63/009,097 filed on Apr. 13, 2020. Both the foregoing applications are incorporated herein by reference in their entirety.
- Not Applicable
- Not Applicable.
- This disclosure relates to the field of flow control devices (“chokes”) used in well drilling. More specifically, the disclosure relates to chokes used during drilling operations for managing pressure in a well annulus.
- Managed pressure drilling is used to maintain drilling fluid pressure in the well annulus (the space between open formations and a drilling tool “string”) of a drilling well within a range between exposed formation fluid (“pore”) pressure and exposed formation mechanical failure (“fracture”) pressure. The difference between the foregoing pressures is known as a pressure window, is sometimes referred to as the “drilling margin” and represents the pressure range within which little or no formation fluids are drawn into the well and little or no drilling fluids are lost to the exposed formations. While drilling fluids are typically weighted (made more dense than plain water and/or oil to exert higher pressure), other factors including fluid friction, pipe rotation, and applied surface back pressure (“ASBP”) contribute to the effective fluid pressure acting on the exposed formations. Failure to precisely control the foregoing variables can result in a well control event, including the unintentional influx of formation fluids into the wellbore or the loss of expensive drilling fluids to the formation. Consequently, allowing fluid pressure to fall outside the drilling margin can substantially increase drilling costs and expose the drilling rig and personnel to dangerous conditions including, potentially, a blowout (uncontrolled influx of fluid into the well).
- Managed pressure drilling (“MPD”) systems seal the annulus surrounding the drill string for all operations, including rotating and stripping operations, and improve the ability of equipment on the drilling unit (“rig”) to manage well annulus pressure. With the wellbore sealed, MPD systems allow for the application of “surface back pressure” to the well, namely, fluid pressure applied from equipment at the surface to the well annulus. The drilling rig operator may cause the MPD system to apply additional surface back pressure to increase the pressure overbalance acting on the exposed formations, or he may drill ahead with back pressure and relatively less dense drilling fluid to allow for rapid downward bottom hole pressure adjustment to mitigate fluid losses. During connections (assembly and disassembly of segments of drilling pipe and/or tools to change the length of the tool string), surface back pressure may be increased to offset the loss of pressure otherwise resulting from circulation-caused friction that occurs when the drilling fluid (mud) pumps are stopped. Typically, pressure is increased during connections when the mud pumps are stopped by an amount proportional to the difference between the equivalent circulating density (“ECD”) or equivalent well pressure including fluid friction pressure, and the equivalent static density (“ESD”) or equivalent well pressure with no fluid friction pressure.
- MPD systems may allow the drilling rig operator to more quickly detect warning signs of a potentially hazardous situation. With the well annulus closed as explained above, all returning fluids from the well may be measured with greater accuracy, enabling faster fluid influx and loss detection than is available using conventional drilling techniques. Faster detection and response time may result in a smaller influx because the duration of the underbalanced condition is reduced. Smaller influxes are typically easier to circulate out of the well because there is typically less gas or light annular fluids that place less stress on weaker formations. In the event an unintentional influx is taken into the wellbore, MPD systems may be used to apply surface back pressure to the well to stop the influx before shutting the blowout preventer (“BOP”), which eliminates drawdown pressure acting on the formation following mud pump shutdown and closure of the BOP and further reduces the influx volume.
- Conventional MPD systems include an annular sealing system, a drill string isolation tool, and a flow spool, or equivalents thereof that actively manage wellbore pressure during drilling and other operations. The annular sealing system may include a rotating control device (“RCD”), an active control device (“ACD”), or other type of annular sealing device that is configured to seal the annulus surrounding the drill pipe while it rotates and moves axially. The annulus is thus encapsulated such that it is not exposed to the atmosphere. The drill string isolation tool is usually disposed directly below the annular sealing system and includes an annular packer that encapsulates the well and maintains annular pressure when rotation has stopped and the annular sealing system, or components thereof, are being installed, serviced, removed, or otherwise disengaged. The flow spool is usually disposed directly below the drill string isolation tool and, as part of the pressurized fluid return system, diverts fluids from below the annular seal to the surface. The flow spool is in fluid communication with a choke manifold, typically disposed on a platform of the drilling rig that is in fluid communication with a mud-gas separator, shakers, or other fluids processing system. The pressure tight seal on the annulus allows for the precise control of wellbore pressure by manipulation of the choke settings of the choke manifold and the corresponding application of surface back pressure.
- One or more variable orifice chokes in the choke manifold may be operated automatically in response to measurements of one or more parameters having a relationship to the annulus pressure, for example and without limitation flow rate of fluid out of the well. Automating operation of the one or more variable orifice chokes requires tuning or calibrating of the choke orifice with respect to annulus fluid pressure for each set of well drilling equipment specifications, well depth, well diameter and drilling fluid rheological properties among other parameters.
- One aspect of the present disclosure is a method for tuning a managed pressure drilling system comprising a variable orifice choke to control fluid flow from a drilling well includes (a) characterizing change in flow rate through the choke with respect to choke opening at a substantially constant pressure drop; (b) characterizing change in fluid pressure in the well with respect to change in choke opening at a substantially constant flow rate into the well; (c) characterizing a response time of pressure in the well to changes in the choke opening, a delay time of pressure response after a change in choke opening and a back pressure applied to the well with respect to choke opening. The characterizations in at least one of (a) and (b), and the characterization in (c) are used to calculate control parameters for a proportional integral differential controller having as output the choke opening and as input the fluid pressure in the well before the choke.
- In some embodiments, the characterizing change in flow rate of fluid through the choke with respect to fractional choke opening at a substantially constant pressure drop across the choke comprises pumping fluid through a conduit extended into the well, measuring flow rate of fluid leaving the well through an annular space between the conduit and a wall of the well, measuring pressure of fluid in the well upstream of the choke, adjusting the fractional choke opening and changing a rate of the pumping fluid so that the measured pressure remains substantially constant.
- In some embodiments, the characterizing a response time of pressure in the well to changes in the fractional choke opening, a delay time of pressure response after a change in fractional choke opening and a surface back pressure applied to the well with respect to fractional choke opening comprises measuring pressure in the well upstream of the choke, measuring pressure upstream of the choke, and change in the measured pressure with respect to change in the fractional choke opening while pumping fluid into the well at a substantially constant rate.
- In some embodiments, the characterizing a response time of pressure in the well to changes in the fractional choke opening comprises measuring pressure in the well upstream of the choke with respect to time, and determining an elapsed time between change in the fractional choke opening and a change in the measured pressure while pumping fluid into the well at a substantially constant rate.
- Other aspects and possible advantages will be apparent from the description and claims that follow.
-
FIG. 1 shows an example embodiment of a managed pressure drilling (MPD) system. -
FIG. 2 shows an example embodiment of an automatic choke. -
FIG. 3 shows an example embodiment of a control system. -
FIG. 4 shows a graph of an example well system response to changes in pressure. -
FIG. 5 shows a graph of an example choke response with respect to position or opening. -
FIG. 6 shows an example sensitivity curve for a choke. -
FIG. 7 shows identifiable regions within a choke response as inFIG. 5 . -
FIG. 8 shows a graph of an example embodiment of choke “fingerprinting.” -
FIG. 9 shows a graph defining parameters used in choke characterization. - An example embodiment of a managed pressure drilling (MPD) system that may be used in accordance with a method of the present disclosure will be explained with reference to
FIGS. 1 through 3 . It is to be clearly understood that the example embodiment of MPD system shown herein is only for purposes of illustration. Other embodiments of MPD system may be used in accordance with the present disclosure with equal effect. - Referring to
FIGS. 1-3 ,reference numeral 100 refers, in general, to an embodiment of a system (e.g., an MPD system) for controlling the fluid pressures within an oil or gas well 10. Thesystem 100 includes anautomatic choke 102 for controllably releasing pressurized fluids from an annular space (“annulus”) 24 between a wellbore casing 16 (and open drilled well below thecasing 16, not shown) anddrill pipe 18. Fluid (e.g., drilling mud) is pumped from amud tank 20 by mud pump(s) 22 into thedrill pipe 18. The fluid leaves the bottom of thedrill pipe 18 and moves into theannulus 24. Theannulus 24 is closed by a rotatingcontrol device 26 or similar annular seal. - The fluid is released from the
annulus 24 through anautomatic choke 102 which controllably restricts the outflow thereby to create back pressure within thewellbore 12. The outflow ultimately moves from thechoke 102 to amud tank 20. Acontrol system 104 controls the operation (i.e., the effective orifice size) of theautomatic choke 102 to maintain a selected pressure in thewellbore 12. Thecontrol system 104 may be in signal communication with a display andoperator control panel 34 wherein control signals may be entered by a system operator, and system response may be observed. - A
pressure sensor 32 a may measure pressure in the wellbore casing 16 (CSP). Anotherpressure sensor 32 b may measure pressure in the drill pipe (DPP) or stand pipe (SPP). A flow meter such as aCoriolis flow meter 106 may measure fluid flow out of thecasing 16 and into thechoke 102. Anotherflowmeter 108 may measure fluid flow rate into thedrill pipe 18. Theother flow meter 108 may be substituted by or supplemented with a stroke counter on the drilling unit mud pump(s) 22. The foregoing sensors may be in signal communication with thecontrol system 104. Some embodiments may include a sensor 32 c that can measure pressure proximate the bottom of thewellbore 12, for example, a pressure while drilling (PWD) sensor. Such sensor 32 c may provide the advantage of certainty in determining in-wellbore pressure under dynamic conditions, however such sensor 32 c is not a requirement in order to operate the MPD system according to the present disclosure. - As illustrated in
FIG. 2 , theautomatic choke 102 may comprise amovable valve element 102 a that defines a continuously variable flow path resistance depending upon the position of themovable valve element 102 a. The position of themovable valve element 102 a may controlled by a first control pressure signal 102 b, and an opposite acting, second control pressure signal 102 c. In the illustrated example embodiment, the first control pressure signal 102 b may be representative of a set point pressure (SPP) that is generated by thecontrol system 104, and the second control pressure signal 102 c is representative of the fluid pressure inside the casing 16 (CSP). In this manner, if the CSP is greater than the SPP, pressurized fluid within theannulus 24 of the well 10 is bled off at a greater rate into themud tank 20 by increasing thechoke 102 orifice. Conversely, if the CSP is equal to or less than the SPP, then the pressurized fluidic materials within theannulus 24 of the well 10 are bled off more slowly, by decreasing thechoke 102 orifice, into themud tank 20. In this manner, theautomatic choke 102 provides pressure regulation than can controllably bleed off pressurized fluids from theannulus 24 and thereby also controllably create and maintain back pressure in thewellbore 12. In an example embodiment, theautomatic choke 102 may be further provided substantially as described in U.S. Pat. No. 6,253,787 issued to Suter et al., which is incorporated herein by reference in its entirety - Thus, the
system 100 may enable the CSP to be automatically controlled by the human system operator 104 c selecting the desired SPP. Theautomatic choke 102 then regulates the CSP as a function of the selected SPP. - The illustrated embodiment herein may be implemented in the form of pressure transducers for measuring SPP and CSP, and the
control system 104 may be implemented in the form of a programmable logic controller, floating point gate array, application specific integrated circuit or any other microcomputer, computer, computer processor or controller known in the art. Accordingly, the embodiment explained above is not a limitation on the scope of the present disclosure. - In the most general terms, controlling pressure in the annulus is performed by controlling position of the
automatic choke 102 in response to measurements of pressure and flow of drilling fluid (mud) into and/or out of thewellbore 12. A method according to the present disclosure has as an objective the calibration or “tuning” of the pressure control response of the MPD system, and in particular operation of thecontrol system 104 as to its control of theautomatic choke 102 in order to more precisely maintain well pressure under foreseeable operating conditions during drilling. - MPD System and Well Characteristics on a Drilling Well
- The pressure response of most drilling wells to changes in fluid flow and/or choke opening can be approximated by a first order system having a time delay. Such wells are known as “open loop stable” (refer to the graph of
FIG. 4 for an example). Open loop stable means that if a change in choke opening (position) is made, the pressure in the well will change correspondingly without going out of bounds or predetermined limits, if the choke opening is itself within reasonable limits. This characteristic may be used to predict an initial set of stable proportional integral differential (PID) control loop parameters. - The graph in
FIG. 4 shows the pressure in the annulus (the “upstream” side of thechoke 102 inFIG. 1 ) with reference to time, beginning at an arbitrary baseline pressure (ordinate axis=0). A choke position change is entered by the operator into the control system (104 inFIG. 1 ) at time t=0. The pressure as measured on the annulus side of the choke is indicated bycurve 401. Note that a localized peak, at 403, in the actual well pressure response shown inFIG. 4 is due to characteristics of the MPD system surface equipment and is not due to well characteristics. Thispeak 403 is characteristic for marine (offshore) MPD operations and is commonly encountered. In determining the parameters of the well for choke tuning according to the present disclosure thepeak 403 shown inFIG. 4 may be disregarded. The theoretical well pressure response is shown atcurve 402. - The choke's flow characteristic is usually not linear but follows an approximate sigmoid function. This means that a nominal change, e.g., a nominal fractional step change in choke opening, does not result in a corresponding nominal flow variation over the entire range of choke opening. This is a well-known characteristic of chokes.
-
FIG. 5 shows a graph of characteristic flow for a choke, called Cv, atcurve 501. Cv may be presented in units of flow rate of the choke at a specified pressure drop (in this case 1.0 pounds per square inch) for a particular fluid; in many cases for commercial characterization, pure water at 60 degrees Fahrenheit is used for characterization. Expressed as a formula: -
Cv=Q√{square root over (SG/ΔP)} - wherein Q represents flow rate, ΔP represents pressure drop across the choke and SG represents the fluid's specific gravity. The coordinate axis, in fractional opening of the choke, from fully closed to fully open, is expressed in units of percent choke opening. The change in Cv for a 10 percentage point change in choke opening is shown at different points along the full range of choke opening, in the
present case 30 to 40% opening, and 60 to 70% opening, compared to a linear curve, at 502, superimposed on the graph ofFIG. 5 . Note that although the absolute change in Cv is more for the 60% to 70% opening change, the relative change for a step from 30% to 40% is much larger. Therefore the reaction of the pressure with respect to choke position changes will be more pronounced at smaller choke openings. Some commercially available PID loop models recognize the foregoing and allow two PID loop parameter sets to be defined so that optimal choke performance is achieved over the majority of the opening range of the choke. Sensitivity of the choke (expressed in Δ%/%) is shown graphically inFIG. 6 . In one aspect of a method according to the present disclosure, the choke characteristic flow Cv may be determined for the particular choke, that is, thechoke 102 inFIG. 1 , with respect to the actual drilling fluid used to drill the well (FIG. 1 ). - The MPD control system (104 in
FIG. 1 ) may comprise, e.g., in software operating on any form of computer or processor, a feed forward controller and a PID controller to ensure reliable pressure control while the MPD system is operating automatically. The feed forward controller is used to predict the optimal new choke opening in response to a change in determined or chosen (setpoint) well pressure, while the PID controller fine-tunes the choke opening to maintain a chosen target well pressure. This makes it possible to accommodate large pressure setpoint variations or determined pressure variations with only minimal overshoot in choke operation, and to substantially reduce the time needed for the MPD system to respond to a change in the setpoint pressure. - The PID controller may have different options available, for example, “Manual” PID selection where a static set of PID parameters is used, and “Automatic” PID selection where the operator can define two (or more) sets of PID parameters, dependent on the choke characteristics in low and high operating (opening) range. The most sophisticated models may use continuous PID parameter variations across the operating range. This will avoid the need for any manual retuning for large setpoint or determined well pressure step changes that would correspondingly require large step changes in choke opening.
- For tuning the MPD control system (104 in
FIG. 1 ), it is desirable to divide the tuning of the PID controller separately from the feed forward controller. However for both the PID and feed forward controllers, an accurate Cv curve is required and a good approximation of the well reaction should be known. -
FIG. 7 is a graph illustrating a choke having an ordinary, non-linear Cv characteristic that may be used in a choke tuning example. As shown inFIG. 7 , the choke Cv may be approximated over the entire choke opening range by three different slopes A—[opening in the range of about 10%-45%], B—[opening in the range of about 45%-80%] and C—[opening in the range of about 80%-100%]. The system operator may choose which of the three choke opening ranges is of most interest during MPD system operation. If the MPD system is run with choke operating predominantly within the B,C opening range, then tuning can be best done in these ranges. Consequently, if the upper slope C is not considered important for pressure control, the system tuning may be performed with choke within opening ranges A, B. - Methods according to the present disclosure may be described by the following generalized procedures.
- Fingerprinting procedure:
-
- a. Determine actual choke parameters (fingerprinting Cv curve)
- b. Determine the well characteristic (or process model as it is described in MPD literature)
- Feed forward controller procedure:
-
- a. Calculate the required added (or removed) drilling circulation system volume required to effect a specific well pressure change
- b. Operate the choke(s) (or increase/decrease pump rate) closed/open to ensure a flow rate change.
- c. Measure the corresponding drilling circulation system volume changes
- d. Move the choke(s) to the predetermined position based on fingerprinted Cv (characterized choke) when the volume change required has been reached.
- PID Controller procedure:
-
- a. Use the PID controller to stabilize the well pressure and keep the well pressure at the chosen (desired) value using the values found in the fingerprinting procedure
- Actions needed to carry out the above procedures will be explained in more detail below.
- Initial Characterization of Choke Response
- The following actions may be undertaken when first initializing the MPD system on any specific well. Because every well may be different, that is, have a unique pressure response with respect to changes in drilling rig mud pump operating rate and choke position, it is desirable to perform the following steps at the start of drilling operations on any well or well section.
- Using the choke manufacturer's initially provided Cv curve (e.g., see
FIG. 5 ), by using the procedure in the following table it is possible to create a Cv curve, that is, the flow/choke %/pressure characterization for the specific choke (102 inFIG. 1 ) as actually used in the MPD system on the well being drilled. Maximum drilling fluid pressure and flow rates may be determined for any particular well. An example method for characterizing the flow/choke %/pressure, that is, determining the Cv curve, may be implemented according to the following table. -
Step Activity 1. Activate choke in manual choke control mode and open 100%. 3. Run the mud pumps up to the maximum allowable flow according to the well construction plan 4. Close the active choke in 10% intervals from 100% to 70%. 5. At choke set points below 70%, decrease flow as per plan to the next 5% choke value before moving the choke to this value. 6. Optionally if the curve below 35% choke opening needs to be determined, decrease choke set points in 2% increments. 7. Ramp Down Mud Pumps and, open all chokes to 100% 8. Repeat the procedure for any other chokes in the system (if multiple chokes are present). 9. Use logged data points to create Cv table 10. If necessary re-adjust the Cv curve loaded in the system to match the measured curve -
FIG. 8 shows a graph of an example embodiment of choke “fingerprinting”, wherein actual surface back pressure (SPB) with respect to flow rate and choke opening combinations are used to determined Cv values at different choke openings. - Determining Well Parameters
- Determining the well parameters to be used in the PID controller can be a fast and easy to implement procedure. However, the system characteristic response of the combination of choke and well is related to the particular flow characteristics of both; therefore characterization should be repeated for every new well section (e.g., when a casing or liner is set and/or drill bit diameter changes) or if large changes in drilling operating parameters are encountered. For best results the characterization should be performed within the expected range of drilling operating parameters (mud flow rate, surface back pressure, mud weight, etc.). Also the well parameter determination has to be performed in expected operating region A, B or C of the Cv curve (see
FIG. 7 ) in order for the right parameters to be entered into the PID controller. - The well parameter determination may be performed in manual choke control mode (i.e., with automatic control of the
choke 102 disabled) and may comprise using predetermined steps in the choke opening. The surface back pressure (SBP) response is measured and will provide key inputs for determining optimal PID controller parameters. The steps in the table below may be performed in several different choke opening ranges to allow for the choke curve to be optimally covered. -
Step Activity 1 Ensure the “Choke Cv curve” is configured in the control system. 2 Line up flow lines to one choke only. Close the inactive choke completely. 3 Set the MPD-CS in manual control mode and open the choke to the max of the first slope plus a margin and request the driller to slowly increase the pump speed. 4 Freeze the pump speed when a desired surface back pressure is reached. Let the system stabilize until flow in/flow out are the same, or with a fixed offset. 5 Manually close the choke in fixed increments and log the SBP (psi) and choke opening (%) over time. The system needs to stabilize between each step. 6 While in manual mode open the choke to the max of the second slope plus a margin and request the driller to slowly increase the pump speed. 7 Freeze the pump speed when a desired surface back pressure is reached. Let the system stabilize. 8 Manually close the choke in fixed increments and log the SBP (psi) and choke opening (%) over time. The system needs to stabilize between each step. 9 Repeat the above for any other chokes in the system and or any other regions of interest. - For the choke 102 (or each choke in a multiple choke MPD system) fill in the determined values in the following table using the graph and definitions in
FIG. 9 as guidance for determining tchoke, tSBP and tS. The number of steps in any embodiment may be any chosen number. Note tSBP is the first indication of the real pressure rise. It is not the time slope of the pressure curve. -
Step Km (psi/%) Tm (sec) Sm (sec) tSBP − tchoke ts − tSBP 1 2 3 Average Region - Determining PID Controller Parameters
- This step will provide the starting parameters for the PID controller. The starting parameter calculations may provide in most cases stable operation of the PID controller. This can be used as a basis to fine tune performance for specific situations. It has been determined that effective PID controller operation may be effected using three parameters, Km, Tm and Sm. Sm represents the time constant of the well, in essence how fast the well reacts to changes in choke setting. Tm represents time delay, that is, when the well starts reacting after a change in choke setting is made and Km represents the gain factor of the well and MPD system, that is, how the SBP changes as function of the choke opening change. It has been found that by empirically determining the foregoing three parameters, the MPD system can be made to operate reliably by the system operator without the need for guessing values of system operating parameters.
- There are several different methods to calculate the PID parameters—each with its different characteristics. A spreadsheet as shown in the table below may be used to display the parameters when the Km, Tm and Sm values are filled in to populate the table. A good reference for determining proper parameters is “Handbook of PI and PID Controller Tuning Rules”, 3rd edition, Aidan O'Dwyer.
-
Kp (controller proportional gain) Ti (controller integral time) Td Method (-) (s) (s) 1 2 T_m 0.5 · S_m 3 2.38 · S_m 0.42 · S_m - The following PID parameters combinations can be used as a starting point in case of the following example:
-
Km (psi/%) Tm (sec) Sm (sec) 0.47 5 5 -
Method Kp Ti(s) Td(s) 1 1.9 2.9 2.6 2 1.3 5 2.5 3 2 11.9 2.1 - Determining the basic control parameters based on the step response of the system allows the definition of a stable set of PID parameters. These PID parameters can be used to further refine performance if needed. No knowledge of the well, mud properties or choke curves is required.
- By tuning the functionality of the choke(s) in an MPD system according to the present disclosure, it is possible to accurately estimate a fluid volume necessary to add to or remove from the drilling circulation system (comprising the
mud pump 22, drill pipe, casing 16, wellbore andannulus 24 inFIG. 1 ) in order to cause a predetermined change in the surface back pressure (SBP). Such estimation makes possible much more rapid MPD system response to changes in setpoint pressure. By way of example, increasing the setpoint pressure may be effected by substantial closure of the choke (102 inFIG. 1 ) for a determined time, after which the choke (102 inFIG. 1 ) is opened to a new fractional opening that will result in the SBP being substantially at the new setpoint. Corresponding opening of the choke may take place to effect a drop in the setpoint pressure. Accordingly, MPD system response using calibrated choke(s) according to the present disclosure may operate more quickly and therefore safely than using uncalibrated choke(s) controlled only by the PID controller or equivalent. - In light of the principles and example embodiments described and illustrated herein, it will be recognized that the example embodiments can be modified in arrangement and detail without departing from such principles. The foregoing discussion has focused on specific embodiments, but other configurations are also contemplated. In particular, even though expressions such as in “an embodiment,” or the like are used herein, these phrases are meant to generally reference embodiment possibilities, and are not intended to limit the disclosure to particular embodiment configurations. As used herein, these terms may reference the same or different embodiments that are combinable into other embodiments. As a rule, any embodiment referenced herein is freely combinable with any one or more of the other embodiments referenced herein, and any number of features of different embodiments are combinable with one another, unless indicated otherwise. Although only a few examples have been described in detail above, those skilled in the art will readily appreciate that many modifications are possible within the scope of the described examples. Accordingly, all such modifications are intended to be included within the scope of this disclosure as defined in the following claims.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US17/963,827 US20230080917A1 (en) | 2020-04-13 | 2022-10-11 | Method for tuning choke operation in a managed pressure drilling system |
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US202063009097P | 2020-04-13 | 2020-04-13 | |
| PCT/US2021/026402 WO2021211355A1 (en) | 2020-04-13 | 2021-04-08 | Method for tuning choke operation in a managed pressure drilling system |
| US17/963,827 US20230080917A1 (en) | 2020-04-13 | 2022-10-11 | Method for tuning choke operation in a managed pressure drilling system |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/US2021/026402 Continuation WO2021211355A1 (en) | 2020-04-13 | 2021-04-08 | Method for tuning choke operation in a managed pressure drilling system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20230080917A1 true US20230080917A1 (en) | 2023-03-16 |
Family
ID=78006564
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US17/963,827 Pending US20230080917A1 (en) | 2020-04-13 | 2022-10-11 | Method for tuning choke operation in a managed pressure drilling system |
Country Status (5)
| Country | Link |
|---|---|
| US (1) | US20230080917A1 (en) |
| EP (1) | EP4136315A4 (en) |
| AU (1) | AU2021256403B2 (en) |
| BR (1) | BR112022020633A2 (en) |
| WO (1) | WO2021211355A1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US12345108B1 (en) * | 2015-03-18 | 2025-07-01 | Pruitt Tool & Supply Co. | Method and system for maintaining constant back pressure during managed pressure drilling |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20150240579A1 (en) * | 2012-07-02 | 2015-08-27 | Halliburton Energy Services, Inc. | Pressure Control in Drilling Operations with Choke Position Determined by Cv Curve |
| US20160102511A1 (en) * | 2014-10-08 | 2016-04-14 | Weatherford Technology Holdings, Llc | Choke Control Tuned by Flow Coefficient for Controlled Pressure Drilling |
| US20170037690A1 (en) * | 2015-08-06 | 2017-02-09 | Schlumberger Technology Corporation | Automatic and integrated control of bottom-hole pressure |
| US20170328151A1 (en) * | 2016-05-10 | 2017-11-16 | Weatherford Technology Holdings, Llc | Drilling System and Method Having Flow Measurement Choke |
| US20190120003A1 (en) * | 2012-05-03 | 2019-04-25 | Managed Pressure Operations Pte. Ltd. | Method of drilling a subterranean borehole |
| US20210230966A1 (en) * | 2020-01-23 | 2021-07-29 | NTDrill Holdings, LLC | Drilling choke with matched actuator |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6253787B1 (en) | 1999-05-21 | 2001-07-03 | M-I L.L.C. | Fluid flow and pressure control system and method |
| US9988866B2 (en) * | 2014-12-12 | 2018-06-05 | Halliburton Energy Services, Inc. | Automatic choke optimization and selection for managed pressure drilling |
-
2021
- 2021-04-08 AU AU2021256403A patent/AU2021256403B2/en active Active
- 2021-04-08 WO PCT/US2021/026402 patent/WO2021211355A1/en not_active Ceased
- 2021-04-08 EP EP21788147.3A patent/EP4136315A4/en active Pending
- 2021-04-08 BR BR112022020633A patent/BR112022020633A2/en unknown
-
2022
- 2022-10-11 US US17/963,827 patent/US20230080917A1/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20190120003A1 (en) * | 2012-05-03 | 2019-04-25 | Managed Pressure Operations Pte. Ltd. | Method of drilling a subterranean borehole |
| US20150240579A1 (en) * | 2012-07-02 | 2015-08-27 | Halliburton Energy Services, Inc. | Pressure Control in Drilling Operations with Choke Position Determined by Cv Curve |
| US20160102511A1 (en) * | 2014-10-08 | 2016-04-14 | Weatherford Technology Holdings, Llc | Choke Control Tuned by Flow Coefficient for Controlled Pressure Drilling |
| US20170037690A1 (en) * | 2015-08-06 | 2017-02-09 | Schlumberger Technology Corporation | Automatic and integrated control of bottom-hole pressure |
| US20170328151A1 (en) * | 2016-05-10 | 2017-11-16 | Weatherford Technology Holdings, Llc | Drilling System and Method Having Flow Measurement Choke |
| US20210230966A1 (en) * | 2020-01-23 | 2021-07-29 | NTDrill Holdings, LLC | Drilling choke with matched actuator |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US12345108B1 (en) * | 2015-03-18 | 2025-07-01 | Pruitt Tool & Supply Co. | Method and system for maintaining constant back pressure during managed pressure drilling |
Also Published As
| Publication number | Publication date |
|---|---|
| EP4136315A1 (en) | 2023-02-22 |
| WO2021211355A1 (en) | 2021-10-21 |
| AU2021256403B2 (en) | 2024-10-03 |
| BR112022020633A2 (en) | 2022-12-20 |
| AU2021256403A1 (en) | 2022-10-20 |
| EP4136315A4 (en) | 2024-05-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DK2542753T3 (en) | System and method for safe well control operation | |
| RU2592583C2 (en) | Using results of measuring pressure in wellbore during drilling for detection inflows and for reduction thereof | |
| EP2467571B1 (en) | Method for determining formation fluid control events in a borehole using a dynamic annular pressure control system | |
| US9995098B2 (en) | Choke control tuned by flow coefficient for controlled pressure drilling | |
| US7562723B2 (en) | Method for determining formation fluid entry into or drilling fluid loss from a borehole using a dynamic annular pressure control system | |
| US6575244B2 (en) | System for controlling the operating pressures within a subterranean borehole | |
| AU769274B2 (en) | Controlling pressure and detecting control problems in gas-lift riser during offshore well drilling | |
| EP1664478B1 (en) | Drilling system and method | |
| CA2477683C (en) | Method and system for controlling well circulation rate | |
| EP2414619B1 (en) | Apparatus for and method of drilling a subterranean borehole | |
| US20100288507A1 (en) | Method and apparatus for controlling bottom hole pressure in a subterranean formation during rig pump operation | |
| MXPA04008063A (en) | Dynamic annular pressure control apparatus and method. | |
| US20180135365A1 (en) | Automatic managed pressure drilling utilizing stationary downhole pressure sensors | |
| US20230080917A1 (en) | Method for tuning choke operation in a managed pressure drilling system | |
| RU2807455C1 (en) | Method for setting operation of throttle in drilling system with adjustable pressure | |
| Stave | Faculty of Science and Technology | |
| BRPI0307810B1 (en) | System and method for controlling formation pressure while drilling an underground formation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AS | Assignment |
Owner name: NOBLE RIG HOLDINGS LIMITED, TEXAS Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:VAN KUILENBURG, ROBERT;REEL/FRAME:061382/0668 Effective date: 20210317 |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: NON FINAL ACTION MAILED |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: FINAL REJECTION MAILED |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: NON FINAL ACTION COUNTED, NOT YET MAILED |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: NON FINAL ACTION MAILED |