US20160145815A1 - Method for pre-stressing a steel structure, and steel structure pre-stressed using said method - Google Patents
Method for pre-stressing a steel structure, and steel structure pre-stressed using said method Download PDFInfo
- Publication number
- US20160145815A1 US20160145815A1 US14/898,452 US201414898452A US2016145815A1 US 20160145815 A1 US20160145815 A1 US 20160145815A1 US 201414898452 A US201414898452 A US 201414898452A US 2016145815 A1 US2016145815 A1 US 2016145815A1
- Authority
- US
- United States
- Prior art keywords
- steel
- reinforced
- carbon fibre
- steel structure
- band
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 108
- 239000010959 steel Substances 0.000 title claims abstract description 108
- 238000000034 method Methods 0.000 title claims abstract description 17
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 claims abstract description 29
- 229920002430 Fibre-reinforced plastic Polymers 0.000 claims abstract description 29
- 229910052799 carbon Inorganic materials 0.000 claims abstract description 29
- 239000011151 fibre-reinforced plastic Substances 0.000 claims abstract description 29
- 239000004918 carbon fiber reinforced polymer Substances 0.000 claims description 22
- 238000013519 translation Methods 0.000 claims description 5
- 229920000642 polymer Polymers 0.000 claims 3
- 238000004026 adhesive bonding Methods 0.000 claims 1
- 238000004873 anchoring Methods 0.000 abstract description 4
- 239000000853 adhesive Substances 0.000 description 7
- 230000001070 adhesive effect Effects 0.000 description 7
- 238000010276 construction Methods 0.000 description 7
- 238000005260 corrosion Methods 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 229910052751 metal Inorganic materials 0.000 description 2
- 229910001018 Cast iron Inorganic materials 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000004453 electron probe microanalysis Methods 0.000 description 1
- 239000003822 epoxy resin Substances 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- KJPHTXTWFHVJIG-UHFFFAOYSA-N n-ethyl-2-[(6-methoxypyridin-3-yl)-(2-methylphenyl)sulfonylamino]-n-(pyridin-3-ylmethyl)acetamide Chemical compound C=1C=C(OC)N=CC=1N(S(=O)(=O)C=1C(=CC=CC=1)C)CC(=O)N(CC)CC1=CC=CN=C1 KJPHTXTWFHVJIG-UHFFFAOYSA-N 0.000 description 1
- 229920000647 polyepoxide Polymers 0.000 description 1
- 230000002250 progressing effect Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D6/00—Truss-type bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/04—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
- E04C3/10—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal prestressed
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/08—Members specially adapted to be used in prestressed constructions
- E04C5/085—Tensile members made of fiber reinforced plastics
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
- E01D2101/32—Metal prestressed
Definitions
- the bridge according to FIG. 1 has a lower strut 2 , that means the lower-most horizontal strut 3 is subjected to tensile stress, and it can be reinforced by means of CFPR bands 4 , for which the following applies.
- a CFPR band 4 is joined - over a section or over the entire length of a part of the structure subjected to tension - at both end regions thereof, capable of transferring tensile forces.
- FIG. 4 shows a steel structure in the form of a steel bridge with upper struts 6 with a CFRP band 4 loosely joined therewith.
- the fitted CFRP band 4 extends along the lower-most horizontal steel girder, wherein obviously there are several such steel girders in practice, which extend along the bridge, and each is equipped with at least one CFRP band 4 , each with two end anchorages 5 , which join these to the structure or the said steel girder at the ends of the band 4 , capable of transferring the tensile forces.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Bridges Or Land Bridges (AREA)
- Rod-Shaped Construction Members (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
Description
- This invention relates to a method for pre-stressing a steel structure, and the steel structure existing both on a new construction and preferably on an existing one, especially on bridge constructions. According to a study by Bien J. Elfgren L. and Olofsson J. entitled Sustainable Bridges, Assessment for Future Traffic Demands and Longer Lives, Wroclaw, Dolnoslaskie Wydawnictwo Edukacyjne, 2007, the European Railway Authorities confirm that there are about 220,000 railway bridges in Europe alone, and these are located in different climatic regions. Approximately 22% of which are metal or steel constructions, which are also often referred to as steel bridges. 3% are cast iron bridges, 25% are welded steel constructions, and 53% are made of steel, and about 20% are made of a material, not clearly identified. 28% of these metal constructions are more than 100 years old and almost 70% of the bridges are more than 50 years old. Since today trains are becoming longer, heavier and faster, the loading of these bridges is increasing very much. Each axle load generates vibrations, and thus, small cracks and gaps develop with time in the structures, and the fatigue of the carrier is progressing ever more quickly.
- Tests at EMPA in CH-Dübendorf demonstrated that the steel girders can be strengthened in principle by the application of carbon fibre-reinforced polymers (CFRP=Carbon Fiber Reinforced Polymers). These CFRP are attached to the steel girders by means of adhesives and are capable to absorb a tensile stress, which slows down or even stops the crack formation. Nevertheless, adhesives are only partially suitable in many places, because steel is heated to high temperatures by the sunlight and this can bring the adhesive to the glass transformation limit thereof. The publications Engineering Structures 45 (2012) 270-283 and the international Journal of Fatigue 44 (2012) 303-315 in Elsevier Journal (www.elsevier.com) should be followed in this respect.
- Another issue is the galvanic corrosion. Although, CFRP are not corrosive, they form galvanic cells in combination with steel. Then, there are many riveted steel bridges. In these, the problem is how best to attach the flat CFRP bands to the steel girders. And finally, the protection of monuments should often be taken into account, in which for instance it is required that historically important structures must again be restored into their original state where appropriate, which could hardly be achieved with glued on CFRP bands. And finally, it would be desirable, not only to strengthen the structures, but also to pre-stress, thus in order to completely close the already existing cracks and gaps and to continuously prevent further growth of these cracks and gaps. Therefore, one of the most important objects of a reinforcement system is the appropriate selection of the mechanical anchoring system, so that this develops sufficient clamping force, is subjected to minimal corrosion, if possible, requires no direct contact of the CFRP bands with the steel, and the stress-initiation in the anchoring system takes place gradually.
- It is the object of the present invention to specify a method for pre-stressing a steel structure, and also a steel structure prestressed thereby. Therefore, the crack formation on a new or existing steel structure should be prevented by means of this pre-stressing, or already existing cracks should be closed or their further growth should be stopped or at least slowed down.
- The object is accomplished by a method for pre-stressing a steel structure, in which at least one carbon fibre-reinforced polymer band each is joined to a steel girder to be reinforced at the end regions thereof, capable of transferring tensile forces, and subsequently at least one lifting element disposed between the respective carbon fibre-reinforced polymer band and the steel girder to be reinforced, is extended in a region between these end anchorages, substantially perpendicular to the carbon fibre-reinforced polymer band, for causing a tensile stress between the end regions of the respective carbon fibre-reinforced polymer band.
- The object is further accomplished by a steel structure, which is characterized by that at least one carbon fibre-reinforced polymer band each is joined to a steel girder of the steel structure to be reinforced at end regions thereof, capable of transferring tensile forces, wherein at least one lifting element disposed between the respective carbon fibre-reinforced polymer band and the steel girder to be reinforced, is disposed in the region between these end regions, by means of which, the respective carbon fibre-reinforced polymer band is subjected to tensile stress from the steel girder by substantially perpendicular lifting of the carbon fibre-reinforced polymer band.
- The invention is schematically represented in the figures and described in the following with the help of these exemplary figures and the function of the method as well as the steel structure reinforced thereby is described.
- It shows:
-
FIG. 1 : shows a steel structure in the form of a steel bridge with lower struts having a slack with CFRP band joined to the underside thereof subjected to tension; -
FIG. 2 : shows the steel structure according toFIG. 1 after inserting a lifting element; -
FIG. 3 : shows the steel structure according toFIG. 1 after inserting two lifting elements; -
FIG. 4 : shows a steel structure in the form of a steel bridge with upper struts having a slack with CFRP band joined to the underside thereof subjected to tension; -
FIG. 5 : shows the steel structure according toFIG. 4 after inserting three lifting elements; -
FIG. 6 : shows a steel structure in the form of a steel bridge with arched lower struts with an applied CFRP band and several lifting elements for pre-stressing thereof. - In
FIG. 1 , a steel structure is represented in the form of asteel bridge 1 withlower struts 2, wherein the lower-mosthorizontal steel girder 3 is subjected to tensile stresses. In such steel bridges, there are always steel girders, which are under compression and those which are subjected to tension. In addition, bending moments are caused, especially if the bridge is temporarily loaded, for example when a train rolls over it. Each axle load causes vibrations and these contribute towards material fatigue, so that over the years, cracks may appear in the steel girders, which increasingly weaken the steel girders. It is important to stop this process or at least to slow it down. Since carbon fibre-reinforced polymer bands (CFRP-bands) are exceptionally strong under tensile stresses and also not subjected to any corrosion, they offer to strengthen the steel girders subjected to tensile stresses. The most efficient approach would be to pre-stress the steel girders subjected to tensile stresses by means of such bands. There have been suggestions to subsequently reinforce the concrete structure by pre-stressed bands in order to improve the tensile strength thereof. In this case, the bands are highly pre-stressed by means of special device and positioned next to the concrete structure in this pre-stressed state and laminated on the concrete by means of epoxy resin adhesives. After hardening of the adhesive, the device, which generated and maintained the stress, is removed, whereupon the pre-stressed CFRP band continuously transfers the stresses thereof to the structure. However, such a method cannot be used on steel constructions. First, these generally have no smooth surfaces, and second, the use of adhesives in steel girders proves to be less suitable, because steel constructions are heated to high temperatures under intense sunlight and thus advect/drive-up the adhesive to the borders thereof. Furthermore, the advection of a heavy device for pre-stressing the bands is not feasible in many cases due to ambient conditions or due to lack of space. Especially, this method cannot be used when a bridge stretches at a great height over a vast expanse. - The bridge according to
FIG. 1 has alower strut 2, that means the lower-mosthorizontal strut 3 is subjected to tensile stress, and it can be reinforced by means ofCFPR bands 4, for which the following applies. ACFPR band 4 is joined - over a section or over the entire length of a part of the structure subjected to tension - at both end regions thereof, capable of transferring tensile forces. To achieve this, there aresuitable end anchorages 5 from the state of the art, for example in the form of clamping shoes, by means of which thebands 4 are mechanically joined to thesteel girder 3 permanently and highly capable of transferring tensile forces. In the example shown, aCFPR band 4 stretches over the entire length of the underside of the lowerhorizontal steel girder 3, wherein theend anchorages 5 are attached on both sides in the vicinity of the ends of thesteel girder 3. Therefore, theband 4 is loosely tensioned. Further, in the example shown, in the middle of theCFPR band 4 that means midway, alifting element 7 is installed betweensteel girder 3 andCFPR band 4. Thislifting element 7 can be a hydraulically, pneumatically, electrically or mechanically operatedlifting element 7, which provides such translation that high lifting forces are generated, for example a few 10 k Newton. Thus, short reaction paths are created with comparatively longer action paths. When such lifting force acts substantially perpendicular to theCFPR band 4 constrained at end regions thereof and it is lifted off from thesteel girder 3, then high tensile stresses are generated, widely translated on theCFPR band 4 itself, and these are then transferred to thestructure 1 via theend anchorages 5. Thus, thesteel girder 3 pre-stressed in such a manner experiences a very substantial reinforcement. If it already has microscopic cracks or even serious cracks, then these can be closed in many cases by means of such pre-stressing or at least it can be achieved that these cracks do not grow further. It should be understood that not just asingle CFPR band 4 should be attached, but a multitude ofCFPR bands 4 can be installed over the width of the bridge, or even in sections over the length of the bridge, severalsuccessive CFPR bands 4 orCFPR bands 4 mutually overlapping in the length can also be attached, which are positioned adjacently and extend parallel to each other, or even overlap in height, thus can be superimposed or intersected. In this case, thebands 4 are not laid exactly in the orientation of the steel girder itself, but laid slightly oblique-angled to it, so that intersections of thebands 4 are formed. - In
FIG. 2 , the steel structure according toFIG. 1 is shown after inserting alifting element 7. It was mounted under the attachedCFRP band 4 loosely tensioned, for example by means of a mechanical joint with thesteel girder 3, by welding or bolting. Thislifting element 7 can be constructed similar to a lifting jack, so that it can be hydraulically lifted by means of an external hydraulic pump, in which a hydraulic pipe is temporarily coupled to thelifting element 7. By a corresponding translation, sufficiently large forces can be generated. The elevation is then secured by means of a mechanical latch or by means of mechanical supports. Such mechanical supports are installed after completion of the working stroke of thelifting element 7, which in this case is raised a little above the tensile stress to be finally achieved, besides thelifting element 7, between theband 4 and thesteel girder 3 to be reinforced. Then, thelifting element 7 is again relieved a bit, so that the targeted stress is achieved and then the supporting force is absorbed by the supports. As an alternative, thelifting element 7 can also be pneumatically operated. Then, a compressed air pipe can be attached, and the retraction of thelifting element 7 is done by a sufficient translation based on pneumatic pressure. Finally, an electric variant of thelifting element 7 is also possible, in which an enclosed EL-Motor generates a sufficiently large lifting force via a short translation, for example by means of spindles and levers. In this case, just an electric wire is needed to be directed to thelifting element 7, and it can be easily adjusted, when required. Finally, a purely mechanical embodiment is also possible, similarly equipped with spindle and/or levers, wherein the required lifting force is then generated manually or by motor with a crank arm to be attached. In any case, the loosely tensionedCFRP band 4 is tensioned by means of thelifting element 7 and then a high tensile stress is generated on theband 4 due to the lifting action, which is many times greater than the lifting force. While theanchorages 5 practically remain stationary or only marginally yield along with the structure, the travel of thelifting element 7 can be several centimetres. Because of the geometry, in this manner, it follows that very high tensile stresses of x times 10 k N are transferred to the structure. -
FIG. 3 shows the steel structure according toFIG. 1 after inserting two liftingelements 7. In case of inserting two liftingelements 7, these are advantageously extended at the same time; so that the stress is build up uniformly distributed over the band length. As an alternative, this can extend one lifting element 7 a little bit, then the second one by a similar amount, then again the first one, then again the second one and so on, so that the tensile force is generated alternately by and by to a certain extent by both thelifting elements 7. -
FIG. 4 shows a steel structure in the form of a steel bridge withupper struts 6 with aCFRP band 4 loosely joined therewith. In this case, the fittedCFRP band 4 extends along the lower-most horizontal steel girder, wherein obviously there are several such steel girders in practice, which extend along the bridge, and each is equipped with at least oneCFRP band 4, each with twoend anchorages 5, which join these to the structure or the said steel girder at the ends of theband 4, capable of transferring the tensile forces. -
FIG. 5 shows this steel structure according toFIG. 4 after inserting three liftingelements 7, which are disposed distributed over the length of eachCFRP band 4 and in turn extended at the same time or else first of all, both the outer ones are extended a little bit and subsequently the middle one is extended a little further, so that a uniform tensile stress is generated over the entire length of theCFRP band 4. -
FIG. 6 finally shows another steel structure in the form of a steel bridge with archedlower strut 2. Here, by the own weight of thebridge 1 and by the loading thereof, a tensile force acts on the archedlong girder 8 at the end of the bridge. In this case,CFRP bands 4 are laid and assembled along thiscurved steel girder 8. In the example shown, asingle CFRP band 4 extends over the entire bridge length along thelower girder 8 and is firmly joined to thesteel girder 8 of thesteel bridge 1 at both the end regions by theanchorage elements 5 attached there. Here, fivelifting elements 7 are inserted uniformly distributed over the band length. These are all simultaneously lifted up in order to generate a most uniform or homogenous stress build-up in theCFRP band 4. This tensile force is then transferred to thestructure 1 via theanchoring elements 5. - By means of such reinforcements, cracks or gaps in steel structures, i.e. in the elements which are tensioned, are closed in some cases. In other cases, a further growth of these cracks and gaps can be prevented, or at least the weakening process can be substantially slowed down, and overall the structures can be definitely reinforced and stabilized, so that the service life thereof is extended, or optionally, the load bearing capacity is enhanced.
Claims (10)
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CH00950/13A CH706630B1 (en) | 2013-05-14 | 2013-05-14 | Method for pretensioning steel structure e.g. iron bridge, involves vertically driving lifting element to polymer tapes in region between end anchorages for causing traction force tensioning between end regions of polymer tapes |
| CH950/2013 | 2013-05-14 | ||
| PCT/CH2014/000049 WO2014183224A1 (en) | 2013-05-14 | 2014-04-16 | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CH2014/000049 A-371-Of-International WO2014183224A1 (en) | 2013-05-14 | 2014-04-16 | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US16/874,643 Continuation US11326313B2 (en) | 2013-05-14 | 2020-05-14 | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20160145815A1 true US20160145815A1 (en) | 2016-05-26 |
Family
ID=49773102
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US14/898,452 Abandoned US20160145815A1 (en) | 2013-05-14 | 2014-04-16 | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method |
| US16/874,643 Active US11326313B2 (en) | 2013-05-14 | 2020-05-14 | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method |
Family Applications After (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US16/874,643 Active US11326313B2 (en) | 2013-05-14 | 2020-05-14 | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method |
Country Status (14)
| Country | Link |
|---|---|
| US (2) | US20160145815A1 (en) |
| EP (1) | EP2997197B1 (en) |
| KR (1) | KR102267298B1 (en) |
| CN (1) | CN105518218A (en) |
| AU (1) | AU2014268098B2 (en) |
| BR (1) | BR112015028588B1 (en) |
| CA (1) | CA2918395C (en) |
| CH (1) | CH706630B1 (en) |
| EA (1) | EA031304B1 (en) |
| ES (1) | ES2802887T3 (en) |
| NZ (1) | NZ713701A (en) |
| PT (1) | PT2997197T (en) |
| WO (1) | WO2014183224A1 (en) |
| ZA (1) | ZA201509090B (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2017214699A (en) * | 2016-05-30 | 2017-12-07 | 東日本旅客鉄道株式会社 | Girder reinforcement structure |
| CN108867393A (en) * | 2018-08-02 | 2018-11-23 | 中铁二院工程集团有限责任公司 | A kind of long-span continuous rigid-framed bridge external prestressing load system |
| US10190936B2 (en) | 2015-01-05 | 2019-01-29 | Bae Systems Plc | Mobile bridge apparatus |
| US10202729B2 (en) * | 2015-01-05 | 2019-02-12 | Bae Systems Plc | Mobile bridge module |
| CN109537475A (en) * | 2018-11-26 | 2019-03-29 | 山东交通学院 | The method and ruggedized construction of bent cap reinforcing are carried out using carbon fiber |
| WO2019175065A1 (en) * | 2018-03-15 | 2019-09-19 | Re-Fer Ag | Method for creating a prestress on a component made of steel, metal or an alloy by means of an sma plate, and component prestressed in such a manner |
| JP2020111416A (en) * | 2019-01-09 | 2020-07-27 | 日本製鉄株式会社 | Steel member reinforcement structure and reinforcement method |
| CN112942144A (en) * | 2021-01-27 | 2021-06-11 | 招商局重庆交通科研设计院有限公司 | Reinforced concrete arch bridge reinforcing method based on thermal expansion principle |
| US11225803B2 (en) * | 2018-01-12 | 2022-01-18 | Changsha University Of Science & Technology | Prestressed bailey beam for reinforcement and construction method therefor |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CH706630B1 (en) | 2013-05-14 | 2013-12-31 | S & P Clever Reinforcement Company Ag | Method for pretensioning steel structure e.g. iron bridge, involves vertically driving lifting element to polymer tapes in region between end anchorages for causing traction force tensioning between end regions of polymer tapes |
| PT108710A (en) * | 2015-07-21 | 2017-01-23 | António Saraiva Pires Da Fonseca João | SYSTEM FOR ARC BRIDGE STRUCTURE, WITH MOBILIZATION OF EXTERIOR REACTIONS THROUGH DEFINITIVE STRETCHERS. |
| CN107060349A (en) * | 2017-06-20 | 2017-08-18 | 中国华西企业有限公司 | A kind of large-span steel girder upper air installing system in place and its construction |
| CN107152078B (en) * | 2017-06-29 | 2023-04-07 | 中国建筑第二工程局有限公司 | Hinge device and construction method for releasing welding internal stress of steel gallery by using hinge device |
| CN111395210B (en) * | 2020-04-07 | 2021-10-22 | 浙江大学 | A method of improving the bearing capacity of a truss girder bridge with external prestressing tendons |
| CN112412097B (en) * | 2020-11-29 | 2022-03-25 | 恒上建设有限公司 | Jacking reinforcing apparatus with adjustable gaseous film building top bearing is prevented caving in |
| CN112942890A (en) * | 2021-04-07 | 2021-06-11 | 上海悍马建筑科技有限公司 | Method for simultaneously reinforcing positive and negative bending moments of concrete flexural member |
| CN114457706A (en) * | 2022-02-28 | 2022-05-10 | 广西交科集团有限公司 | Method for reinforcing assembled abdominal arch ring of double-arch bridge |
Citations (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US238130A (en) * | 1881-02-22 | Bridge | ||
| US762632A (en) * | 1904-02-18 | 1904-06-14 | Joseph W Headley | Truss-bridge. |
| US3427811A (en) * | 1967-03-22 | 1969-02-18 | Claude C White | Mine roof support system |
| US3909863A (en) * | 1972-09-11 | 1975-10-07 | Krupp Gmbh | Bridge crane girder |
| US4021875A (en) * | 1975-04-10 | 1977-05-10 | The United States Of America As Represented By The Secretary Of The Army | Pivotable and extensible tension post for a cable bridge structure |
| US4129915A (en) * | 1978-04-14 | 1978-12-19 | The United States Of America As Represented By The Secretary Of The Army | Cable tensioning means for king post structuring |
| US4223506A (en) * | 1976-05-19 | 1980-09-23 | Blair John T | Frameworks and like structures |
| US4589157A (en) * | 1982-01-29 | 1986-05-20 | Bouygues | Apparatus for the construction of a bridge floor and similar structures, and constructions which are obtained |
| US4631772A (en) * | 1983-12-28 | 1986-12-30 | Bonasso S G | Tension arch structure |
| US4987629A (en) * | 1988-03-25 | 1991-01-29 | Muller Jean M | Deck for wide-span bridge |
| US5313749A (en) * | 1992-04-28 | 1994-05-24 | Conner Mitchel A | Reinforced steel beam and girder |
| US6065257A (en) * | 1999-05-24 | 2000-05-23 | Hubbell, Roth & Clark, Inc. | Tendon alignment assembly and method for externally reinforcing a load bearing beam |
| US6170209B1 (en) * | 1996-11-05 | 2001-01-09 | University Of Maine | Prestressing system for wood structures and elements |
| US20020194808A1 (en) * | 2001-06-22 | 2002-12-26 | Ratliff Frank W. | Lightweight high load capacity reinforced beam and method of making same |
| US6571518B1 (en) * | 1998-08-06 | 2003-06-03 | Anthony Donald Barley | Ground anchorage |
| US6892410B2 (en) * | 2002-09-04 | 2005-05-17 | Asahi Engineering Co., Ltd. | Reinforcement structure of truss bridge or arch bridge |
| US20050247016A1 (en) * | 2002-08-20 | 2005-11-10 | Leonhardt, Andra Und Partner Beratende Ingenieure Vbi Gmbh | Method of installing tension members on supporting structures, and apparatus for performing the method |
| US7047704B1 (en) * | 1999-10-08 | 2006-05-23 | Interconstec Co., Ltd. | Method for designing and fabricating multi-step tension prestressed girder |
| US7748180B1 (en) * | 2005-06-23 | 2010-07-06 | Plavidal Richard W | Joist stiffening system |
| US20110072745A1 (en) * | 2008-06-12 | 2011-03-31 | Pantelides Chris P | Anchoring, splicing and tensioning elongated reinforcement members |
| US20110203195A1 (en) * | 2006-01-13 | 2011-08-25 | Hillman John R | Hybrid composite beams and beam systems |
| US8925279B2 (en) * | 2008-06-12 | 2015-01-06 | The University Of Utah Research Foundation | Anchoring, splicing and tensioning elongated reinforcement members |
Family Cites Families (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| BE810043A (en) * | 1974-01-22 | 1974-05-16 | PROCEDURE FOR PRE-STRESSING AND COUNTER-REFLECTION OF MIXED STEEL AND CONCRETE BEAMS. | |
| DE19849605A1 (en) * | 1998-10-28 | 2000-05-04 | Goehler Andrae Und Partner Ber | Tensioning device for a band-shaped tension member |
| KR100301431B1 (en) * | 1998-11-07 | 2001-10-29 | 박상일 | Prestressed concrete girder with regulable tensile force |
| KR20000063499A (en) * | 2000-07-18 | 2000-11-06 | 박창열 | Tension method of PS steel to improve bridge performance. |
| KR100438113B1 (en) * | 2002-03-30 | 2004-07-02 | 조병완 | non-metallic anchorage apparatus for prestressed concrete structure and pre-stressing method using the same |
| DE10249266B3 (en) * | 2002-10-23 | 2004-04-08 | Leonhardt, Andrä und Partner Beratende Ingenieure VBI GmbH | Tension device for belt-like traction members on concrete support structures has guide member locally fixed between tension bar and tension anchor and supporting traction member for sliding movement upwards |
| KR101115160B1 (en) * | 2009-02-27 | 2012-02-24 | 서울시립대학교 산학협력단 | Prestessed steel beam using 3D cross type bilateral anchorage |
| US20120180407A1 (en) * | 2011-01-13 | 2012-07-19 | Rees Kyle J | Roof truss kit to enable support of solar panels on roof structures |
| CN102140780A (en) * | 2011-04-08 | 2011-08-03 | 浙江省电力设计院 | Method and device for reinforcing bridge by external pre-stressed strands under bridge |
| CN102322025B (en) * | 2011-08-22 | 2014-07-30 | 陈东军 | Pre-stressing reinforced and widened bridge structure |
| CH706630B1 (en) | 2013-05-14 | 2013-12-31 | S & P Clever Reinforcement Company Ag | Method for pretensioning steel structure e.g. iron bridge, involves vertically driving lifting element to polymer tapes in region between end anchorages for causing traction force tensioning between end regions of polymer tapes |
-
2013
- 2013-05-14 CH CH00950/13A patent/CH706630B1/en not_active IP Right Cessation
-
2014
- 2014-04-16 ES ES14722518T patent/ES2802887T3/en active Active
- 2014-04-16 WO PCT/CH2014/000049 patent/WO2014183224A1/en not_active Ceased
- 2014-04-16 EP EP14722518.9A patent/EP2997197B1/en active Active
- 2014-04-16 KR KR1020157035406A patent/KR102267298B1/en not_active Expired - Fee Related
- 2014-04-16 US US14/898,452 patent/US20160145815A1/en not_active Abandoned
- 2014-04-16 CA CA2918395A patent/CA2918395C/en active Active
- 2014-04-16 AU AU2014268098A patent/AU2014268098B2/en not_active Ceased
- 2014-04-16 NZ NZ713701A patent/NZ713701A/en not_active IP Right Cessation
- 2014-04-16 PT PT147225189T patent/PT2997197T/en unknown
- 2014-04-16 CN CN201480026747.2A patent/CN105518218A/en active Pending
- 2014-04-16 EA EA201501078A patent/EA031304B1/en active IP Right Grant
- 2014-04-16 BR BR112015028588-0A patent/BR112015028588B1/en not_active IP Right Cessation
-
2015
- 2015-12-14 ZA ZA2015/09090A patent/ZA201509090B/en unknown
-
2020
- 2020-05-14 US US16/874,643 patent/US11326313B2/en active Active
Patent Citations (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US238130A (en) * | 1881-02-22 | Bridge | ||
| US762632A (en) * | 1904-02-18 | 1904-06-14 | Joseph W Headley | Truss-bridge. |
| US3427811A (en) * | 1967-03-22 | 1969-02-18 | Claude C White | Mine roof support system |
| US3909863A (en) * | 1972-09-11 | 1975-10-07 | Krupp Gmbh | Bridge crane girder |
| US4021875A (en) * | 1975-04-10 | 1977-05-10 | The United States Of America As Represented By The Secretary Of The Army | Pivotable and extensible tension post for a cable bridge structure |
| US4223506A (en) * | 1976-05-19 | 1980-09-23 | Blair John T | Frameworks and like structures |
| US4129915A (en) * | 1978-04-14 | 1978-12-19 | The United States Of America As Represented By The Secretary Of The Army | Cable tensioning means for king post structuring |
| US4589157A (en) * | 1982-01-29 | 1986-05-20 | Bouygues | Apparatus for the construction of a bridge floor and similar structures, and constructions which are obtained |
| US4631772A (en) * | 1983-12-28 | 1986-12-30 | Bonasso S G | Tension arch structure |
| US4987629A (en) * | 1988-03-25 | 1991-01-29 | Muller Jean M | Deck for wide-span bridge |
| US5313749A (en) * | 1992-04-28 | 1994-05-24 | Conner Mitchel A | Reinforced steel beam and girder |
| US6170209B1 (en) * | 1996-11-05 | 2001-01-09 | University Of Maine | Prestressing system for wood structures and elements |
| US6571518B1 (en) * | 1998-08-06 | 2003-06-03 | Anthony Donald Barley | Ground anchorage |
| US6065257A (en) * | 1999-05-24 | 2000-05-23 | Hubbell, Roth & Clark, Inc. | Tendon alignment assembly and method for externally reinforcing a load bearing beam |
| US7047704B1 (en) * | 1999-10-08 | 2006-05-23 | Interconstec Co., Ltd. | Method for designing and fabricating multi-step tension prestressed girder |
| US20020194808A1 (en) * | 2001-06-22 | 2002-12-26 | Ratliff Frank W. | Lightweight high load capacity reinforced beam and method of making same |
| US20050247016A1 (en) * | 2002-08-20 | 2005-11-10 | Leonhardt, Andra Und Partner Beratende Ingenieure Vbi Gmbh | Method of installing tension members on supporting structures, and apparatus for performing the method |
| US6892410B2 (en) * | 2002-09-04 | 2005-05-17 | Asahi Engineering Co., Ltd. | Reinforcement structure of truss bridge or arch bridge |
| US7748180B1 (en) * | 2005-06-23 | 2010-07-06 | Plavidal Richard W | Joist stiffening system |
| US20110203195A1 (en) * | 2006-01-13 | 2011-08-25 | Hillman John R | Hybrid composite beams and beam systems |
| US20110072745A1 (en) * | 2008-06-12 | 2011-03-31 | Pantelides Chris P | Anchoring, splicing and tensioning elongated reinforcement members |
| US8925279B2 (en) * | 2008-06-12 | 2015-01-06 | The University Of Utah Research Foundation | Anchoring, splicing and tensioning elongated reinforcement members |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US10190936B2 (en) | 2015-01-05 | 2019-01-29 | Bae Systems Plc | Mobile bridge apparatus |
| US10202729B2 (en) * | 2015-01-05 | 2019-02-12 | Bae Systems Plc | Mobile bridge module |
| JP2017214699A (en) * | 2016-05-30 | 2017-12-07 | 東日本旅客鉄道株式会社 | Girder reinforcement structure |
| US11225803B2 (en) * | 2018-01-12 | 2022-01-18 | Changsha University Of Science & Technology | Prestressed bailey beam for reinforcement and construction method therefor |
| WO2019175065A1 (en) * | 2018-03-15 | 2019-09-19 | Re-Fer Ag | Method for creating a prestress on a component made of steel, metal or an alloy by means of an sma plate, and component prestressed in such a manner |
| CN108867393A (en) * | 2018-08-02 | 2018-11-23 | 中铁二院工程集团有限责任公司 | A kind of long-span continuous rigid-framed bridge external prestressing load system |
| CN109537475A (en) * | 2018-11-26 | 2019-03-29 | 山东交通学院 | The method and ruggedized construction of bent cap reinforcing are carried out using carbon fiber |
| JP2020111416A (en) * | 2019-01-09 | 2020-07-27 | 日本製鉄株式会社 | Steel member reinforcement structure and reinforcement method |
| JP7115324B2 (en) | 2019-01-09 | 2022-08-09 | 日本製鉄株式会社 | Steel member reinforcement structure and reinforcement method |
| CN112942144A (en) * | 2021-01-27 | 2021-06-11 | 招商局重庆交通科研设计院有限公司 | Reinforced concrete arch bridge reinforcing method based on thermal expansion principle |
Also Published As
| Publication number | Publication date |
|---|---|
| US20200299911A1 (en) | 2020-09-24 |
| KR20160015255A (en) | 2016-02-12 |
| EP2997197A1 (en) | 2016-03-23 |
| KR102267298B1 (en) | 2021-06-21 |
| US11326313B2 (en) | 2022-05-10 |
| CN105518218A (en) | 2016-04-20 |
| CA2918395C (en) | 2021-10-26 |
| CH706630B1 (en) | 2013-12-31 |
| EA031304B1 (en) | 2018-12-28 |
| CA2918395A1 (en) | 2014-11-20 |
| NZ713701A (en) | 2019-01-25 |
| PT2997197T (en) | 2020-07-03 |
| AU2014268098B2 (en) | 2018-04-26 |
| EA201501078A1 (en) | 2016-06-30 |
| EP2997197B1 (en) | 2020-04-22 |
| WO2014183224A1 (en) | 2014-11-20 |
| BR112015028588B1 (en) | 2021-11-23 |
| AU2014268098A1 (en) | 2015-11-26 |
| ES2802887T3 (en) | 2021-01-21 |
| BR112015028588A2 (en) | 2018-07-24 |
| ZA201509090B (en) | 2017-01-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US11326313B2 (en) | Method for pre-stressing a steel structure, and steel structure pre-stressed using said method | |
| Quantrill et al. | The flexural rehabilitation of reinforced concrete beams by the use of prestressed advanced composite plates | |
| Mohee et al. | Anchors for CFRP plates: State-of-the-art review and future potential | |
| Al-Saidy et al. | Strengthening of steel–concrete composite girders using carbon fiber reinforced polymer plates | |
| CN105113405B (en) | A kind of combined bridge deck based on steel and UHPC | |
| Rizkalla et al. | Effectiveness of FRP for strengthening concrete bridges | |
| CN108824221B (en) | Web replacement and strengthening method of concrete continuous girder bridge based on corrugated steel plate | |
| CN105544415A (en) | Concrete bridge reinforcing method and structure | |
| JP7118880B2 (en) | Shear reinforcement method for PC box girder bridge | |
| Wight et al. | Prestressed CFRP sheets for strengthening concrete slabs in fatigue | |
| Siwowski et al. | Strengthening bridges with prestressed CFRP strips | |
| CN109898883A (en) | A kind of anchorage technology measure of armored concrete beam bottom sticking carbon fiber plate | |
| KR101198960B1 (en) | Bridge girde with the function of adjusting pre-stress | |
| US20120255251A1 (en) | Construction structure with strengthening device and method | |
| Nordin | Strengthening structures with externally prestressed tendons: literature review | |
| Pipinato | Assessment and rehabilitation of steel railway bridges using fibre-reinforced polymer (FRP) composites | |
| CN106245539B (en) | A kind of freely-supported plate girder bridge is used for the reinforcement means of Over-size transport | |
| CN109610349B (en) | PC box girder web plate reinforcing structure with built-in obliquely-woven mesh and method | |
| COMPANYAG et al. | 12, Patent Application Publication o Pub. No.: US 2016/0145815A1 | |
| Yang et al. | A new concept for sustainable refurbishment of existing bridges using FRP materials | |
| JP4885327B1 (en) | Steel material repair structure and steel material repair method | |
| CN222558184U (en) | Prefabricated steel reinforced concrete beam reinforced by UHPC | |
| Askar et al. | Flexural retrofitting of reinforced concrete bridges; applications | |
| KR101029994B1 (en) | Structure reinforcement method using all synthetic gerber beam | |
| Wight et al. | CFRP Sheet Strengthening Damaged Continuous Reinforced Concrete Beams |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: NON FINAL ACTION MAILED |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: RESPONSE TO NON-FINAL OFFICE ACTION ENTERED AND FORWARDED TO EXAMINER |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: FINAL REJECTION MAILED |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: RESPONSE AFTER FINAL ACTION FORWARDED TO EXAMINER |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |
|
| AS | Assignment |
Owner name: S&P CLEVER REINFORCEMENT COMPANY AG, SWAZILAND Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:MOTAVALLI, MASOUD;GHAFOORI, ELYAS;REEL/FRAME:059288/0261 Effective date: 20220315 |
|
| AS | Assignment |
Owner name: S&P CLEVER REINFORCEMENT COMPANY AG, SWITZERLAND Free format text: CORRECTIVE ASSIGNMENT TO CORRECT THE THE NAME OF THE ASSIGNEE'S COUNTRY PREVIOUSLY RECORDED AT REEL: 059288 FRAME: 0261. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT;ASSIGNORS:MOTAVALLI, MASOUD;GHAFOORI, ELYAS;REEL/FRAME:059568/0647 Effective date: 20220315 |