[go: up one dir, main page]

US20140112718A1 - Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism - Google Patents

Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism Download PDF

Info

Publication number
US20140112718A1
US20140112718A1 US13/694,011 US201213694011A US2014112718A1 US 20140112718 A1 US20140112718 A1 US 20140112718A1 US 201213694011 A US201213694011 A US 201213694011A US 2014112718 A1 US2014112718 A1 US 2014112718A1
Authority
US
United States
Prior art keywords
cofferdam
framing
columnar
embedded
rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/694,011
Inventor
Vitaly Boris Feygin
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US13/694,011 priority Critical patent/US20140112718A1/en
Publication of US20140112718A1 publication Critical patent/US20140112718A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Definitions

  • This application relates to cofferdams, specifically to non-traditional cellular cofferdam with embedded prefabricated framing and embedded rock anchor.
  • Original cellular cofferdam was designed as an open ended cellular can structure filled with granular material.
  • the first close cell cofferdam was designed by General Harley B. Ferguson and Charles S. Boardman in 1911.
  • the first fully successful modern day full circle cofferdam was constructed on Ohio River in 1928 by J. S. Miller and Dravo Corporation.
  • Construction of the cell cofferdam requires in situ installation of highly complicated template framing with consequent construction of the cofferdam skin consisting of flat sheet piling forming a circular can.
  • Traditional close cell cofferdam works as a gravitational structure, deriving sliding and overturning stability from the gravity and sliding resistance of the cofferdam cell granular fill, hoop forces developing in the skin of the cofferdam and shear forces developing in the granular material of the cofferdam fill.
  • Typical failure modes of the regular cellular cofferdam structure are shown in FIG. 1 .
  • Collapse of the close cell cofferdam is caused by the cofferdam can rotation and consequent escape of the granular fill material 22 from the bottom of the cellular can built of the interlocked flat sheet pile sections 15 .
  • Cell stability failure is marked by three distinguished slip circle lines A, B, C and sliding plan D. Therefore, stability of the original cofferdam cell depends on capacity restricted by 4 unrestrained failure modes described above.
  • the Invention was designed to permit the assembly of the cofferdam with co-acting interior bracing in any convenient location from which it could be lifted as a unit and set into position where sheet piles are released from separable reinforcing cage or bracing form and driven to final tip elevation.
  • the separable reinforcing cage is formed of series of annular circular wales spaced vertically and connected by vertical spacing members. Such arrangement allows central unobstructed opening that permits removing the material from the bottom of excavation.
  • this structural system does not address any failure mode challenges presented by the original cellular cofferdam system. The system suffers from a number of disadvantages:
  • Burkemper introduced a new method for conventional cofferdam construction. His system comprises a temporary template framing for cofferdam template construction.
  • System designed by Burkemper describes in situ built template for temporary support of shoring cell during the cofferdam cell construction.
  • Burkemper describes temporary structure consisting of plurality of circular rings serving as wales for construction of the open can sheet pile skin and supported by the number of spud piles installed on cell perimeter. Further, Burkemper explains in column 1, lines 54-58 (U.S. Pat. No. 4,419,030) that “After the shoring walls of the cofferdam cell are complete, the template is removed from the interior of the cell and, in some instances, the interior of the cell is filled with sand or other fill material so as to form a cofferdam.”
  • Burkemper describes the new method of the conventional cofferdam construction with no embedded framing and no permanently embedded rock anchors.
  • a Universal Cellular Cofferdam with Embedded Columnar Framing and Rock Anchor Mechanism comprises columnar framing 10 with columns 11 placed on the circumference of the cofferdam circular cell; rock or soil anchors 16 embedded and grouted into the columns of the cofferdam framing and into the reinforced concrete pile cap 25 ; rock anchors 16 anchored into the bed rock or another competent soil base strata; cofferdam perimeter skin 15 formed of interlocked flat sheet pile sections, and granular fill 22 of the cofferdam cell.
  • FIG. 1 shows failure modes of the conventional cellular cofferdam.
  • FIG. 2 shows failure modes of the Universal Cofferdam
  • FIG. 3 shows 3-D view of universal prefabricated cofferdam framing. (Sheet pile interlock connector 14 and horizontal truss moment connection plates 18 are not shown for clarity)
  • FIG. 4 shows Universal Cofferdam framing in plan.
  • FIG. 5 shows sectional view 5 - 5 indicated by section line 5 - 5 in FIG. 4
  • FIG. 6 shows truss diaphragm connection to the column of the cofferdam framing.
  • FIGS. 7 and 8 show cofferdam column bearing support.
  • FIGS. 9 and 10 show Cofferdam lifting hat detail
  • FIG. 11 show Universal Cofferdam with rock anchors in plan
  • FIG. 12 shows sectional view 12 - 12 indicated by section line 12 - 12 in FIG. 11
  • FIG. 13 shows Section 13 - 13 indicated by section line 13 - 13 in FIG. 11 .
  • FIG. 14 , 15 show resistance mechanism of the group of preloaded rock or soil anchors.
  • the Universal Cellular Cofferdam framing assembly 10 comprises 6 tubular columns 11 interconnected by two levels of star truss diaphragms 12 and two levels of perimeter wales 13 . Each end of the star truss diaphragm is connected to the column with gusset plates 18 .
  • Skin of the Universal Cellular Cofferdam consists of six segments of interconnected flat sheet pile sections 15 connected to cofferdam columns 11 separating each Universal Cellular Cofferdam skin segment. Extreme sheet pile elements of each sheet pile segment are connected to each column with sheet pile interlock connector 14 welded to column 11 .
  • the cofferdam framing assembly 10 shown in FIG. 3 is anchored to the soil sub base with rock or soil anchor inserts 16 grouted inside of each column 11 and within predrilled rock socket 23 . At the upper end rock anchor inserts 16 are anchored into the reinforced concrete pile cap 25 .
  • rock or soil anchors inserts have headed studs 17 welded to the body of the anchor insert 16 embedded and grouted inside the rock socket 23 ; and to the body of the insert 16 embedded into concrete pile cap 25 .
  • each column 11 of the cofferdam framing 10 is terminated with column bearing detail 19 .
  • Bearing detail 19 reduces the bearing pressure under the cofferdam column during the cofferdam framing positioning.
  • Lifting points of each cofferdam column are terminated with removable lifting hat detail 20 with two air lock holes 21 shown in FIGS. 9 and 10 .
  • Air lock holes 21 prevent formation of the air plug in the column, and prevent cofferdam framing floatation during cofferdam submergence.
  • Universal Cellular Cofferdam framing 10 can be installed without rock or soil anchors. In that case it will function as a prefabricated columnar template framing for a conventional cofferdam.
  • FIG. 3 shows Universal Cellular Cofferdam framing 10 without cofferdam skin 15 and rock anchor inserts 16 .
  • Present art overcomes handicaps of the original TVA design widely used since cofferdam invention. It is based on a different concept of full cellular cofferdam construction utilizing embedded pipe columnar framing as a false work for sheet piling installation; and for anchoring cofferdam to the bedrock.
  • Present art utilizes pipe rock anchors 16 installed through the pipe columns 11 of the Universal Cellular Cofferdam framing 10 as the most rational rock anchor detail. Connection of the rock anchors 16 to the Universal Cellular Cofferdam pile cap 25 enhances Universal Cellular Cofferdam stability arresting Cofferdam skin 15 differential sliding and skin buckling depicted by numeral 15 A in FIG. 1 .
  • FIG. 14 shows Universal Cellular Cofferdam framing in plan with a footprint of the engaged truncated rock anchor cones 24 resisting Universal Cellular Cofferdam overturning.
  • the configuration of the Universal Cellular Cofferdam star truss diaphragm 12 makes force directionality irrelevant.
  • FIG. 15 shows the mechanism of the rock anchor in sectional view.
  • Each pair of the truncated rock rupture cones 24 is effectively preloaded by cofferdam granular fill 22 .
  • Such arrangement increases pull out capacity of the rock or soil anchors and prevents Universal Cellular Cofferdam rotation.
  • Two rock anchors 16 shown along the horizontal fulcrum axis X′-X′ serve as compression elements of the resisting couple composed of the two tension rock anchor elements and two compression rock anchor elements.
  • Directionality of the fulcrum axis X′-X′ and position of the two engaged tension anchors depends on the directionality of the overturning force H shown in FIGS. 1 and 2 .
  • Universal Cellular Cofferdam system Another advantage of the Universal Cellular Cofferdam system is evident from the enhanced sliding capacity of the cofferdam along the plan D shown in FIG. 2 .
  • Sliding resistance of the Universal Cellular Cofferdam becomes the combination of the sliding resistance between the granular fill 22 and cofferdam sub base; and shear resistance capacity of the rock anchor sockets 23 with embedded rock anchors 16 .
  • Universal Cellular Cofferdam rock anchor system prevents convex slip circle failure through the granular fill (Line A), and concave slip circle failure through the sub base of the cofferdam (Line B). Similarly, Universal Cellular Cofferdam system prevents deep slip circle failure (Line C).
  • the deep slip circle failure of the Universal Cofferdam can happen only in case of buckling or yielding of the two rock anchors 16 located along the floating fulcrum axis X′-X′.
  • Such mechanism makes Universal Cofferdam more than 10 times stiffer than conventional cofferdam of the similar geometry.
  • the present art allows great flexibility for usage of Universal Cellular Cofferdam. It can be used for construction of deep water quay walls and dolphins subjected to unusually high lateral loads. However, it becomes the most efficient solution for bridge protection devices, protecting bridge piers from high load of ship and ice collision impact.
  • the Universal Cellular Cofferdam of the various embodiments can be used for construction of the conventional cellular cofferdam systems and for anchored cofferdam systems with greatly enhanced resisting capacity to sliding and overturning.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

One embodiment of Universal Cellular Cofferdam with embedded prefabricated columnar framing (10), embedded rock anchors (16), pile cap (25), cofferdam perimeter skin (15) and granular fill (22) constitutes a hybrid cofferdam structure comprising columnar framing and cofferdam gravity cell. The described structure utilizes resisting mechanisms of structural framing, cofferdam gravity forces and mechanism of rock anchor devices for creation of unique resisting mechanism where all three resisting mechanisms compliment each other, preventing modes of structural failures typical for gravitational or columnar structures alone.

Description

  • A portion of the disclosure of this patent document contains material which is subject to copyright protection. The copyright owner has no objection to the facsimile reproduction by anyone of the patent document or the patent disclosure, as it appears in the Patent and Trademark Office patent file or records, but otherwise reserves all copyright rights whatsoever.
  • CROSS REFERENCES TO RELATED APPLICATIONS
  • Not applicable
  • FEDERALLY SPONSORED RESEARCH
  • Not applicable
  • SEQUENCE LISTING OR PROGRAM
  • Not applicable
  • BACKGROUND
  • 1. Field
  • This application relates to cofferdams, specifically to non-traditional cellular cofferdam with embedded prefabricated framing and embedded rock anchor.
  • 2. Prior Art
  • Traditionally cellular cofferdams are utilized for such waterfront devices as mooring and breasting dolphins, quay walls at deep water port berthing facilities, and for bridge protection devices designed for protection of the bridge piers from the extremely high lateral load of the ship collision impact.
  • Original cellular cofferdam was designed as an open ended cellular can structure filled with granular material.
  • The first close cell cofferdam was designed by General Harley B. Ferguson and Charles S. Boardman in 1911. The first fully successful modern day full circle cofferdam was constructed on Ohio River in 1928 by J. S. Miller and Dravo Corporation.
  • Construction of the cell cofferdam requires in situ installation of highly complicated template framing with consequent construction of the cofferdam skin consisting of flat sheet piling forming a circular can. Traditional close cell cofferdam works as a gravitational structure, deriving sliding and overturning stability from the gravity and sliding resistance of the cofferdam cell granular fill, hoop forces developing in the skin of the cofferdam and shear forces developing in the granular material of the cofferdam fill.
  • Typical failure modes of the regular cellular cofferdam structure are shown in FIG. 1. Collapse of the close cell cofferdam is caused by the cofferdam can rotation and consequent escape of the granular fill material 22 from the bottom of the cellular can built of the interlocked flat sheet pile sections 15. Cell stability failure is marked by three distinguished slip circle lines A, B, C and sliding plan D. Therefore, stability of the original cofferdam cell depends on capacity restricted by 4 unrestrained failure modes described above.
  • Thus if at least one of the potential slip surfaces fails, this structure becomes unstable: it slides along the plan D or rotates along one of the slip circles: A, B or C losing stability and structural integrity as granular fill 22 escapes the tilted bottom of the open cell cofferdam structure. Another mode of failure that usually accompanies cofferdam tilting or rotation along the slip circles A, B or C is buckling failure of the cofferdam skin shown in FIG. 1 and depicted by reference numeral 15A.
  • Several types of the cellular cofferdam modifications have been proposed in the past—for example, in 1921 C. S. Boardman modified his original design, creating means of cofferdam construction in the dry using interior bracing for transporting fully built structure into position.
  • U.S. Pat. No. 1,398,221
  • Inventor: Charles S. Boardman
  • Issued: Nov. 29, 1921
  • Invention was designed to permit the assembly of the cofferdam with co-acting interior bracing in any convenient location from which it could be lifted as a unit and set into position where sheet piles are released from separable reinforcing cage or bracing form and driven to final tip elevation. The separable reinforcing cage is formed of series of annular circular wales spaced vertically and connected by vertical spacing members. Such arrangement allows central unobstructed opening that permits removing the material from the bottom of excavation. Although, relatively inexpensive to fabricate, this structural system does not address any failure mode challenges presented by the original cellular cofferdam system. The system suffers from a number of disadvantages:
      • (a) The weight of the lifted system becomes prohibitively high, restricting diameter and height of the cofferdam.
      • (b) The system does not resolve stability issues attributed to the conventional cellular cofferdam systems presently in use.
  • The U.S. Pat. No. 1,398,221 presents a new method for construction of the conventional cofferdam system.
  • Another attempt to modify construction method for conventional cofferdam system was presented by Werener W. Burkemper, U.S. Pat. No. 4,419,030.
  • U.S. Pat. No. 4,419,030
  • Inventor: Werner W. Burkemper
  • Issued: Sep. 14, 1981
  • Burkemper introduced a new method for conventional cofferdam construction. His system comprises a temporary template framing for cofferdam template construction. System designed by Burkemper describes in situ built template for temporary support of shoring cell during the cofferdam cell construction. Burkemper describes temporary structure consisting of plurality of circular rings serving as wales for construction of the open can sheet pile skin and supported by the number of spud piles installed on cell perimeter. Further, Burkemper explains in column 1, lines 54-58 (U.S. Pat. No. 4,419,030) that “After the shoring walls of the cofferdam cell are complete, the template is removed from the interior of the cell and, in some instances, the interior of the cell is filled with sand or other fill material so as to form a cofferdam.”
  • Burkemper describes the new method of the conventional cofferdam construction with no embedded framing and no permanently embedded rock anchors.
  • SUMMARY
  • In accordance with one embodiment, a Universal Cellular Cofferdam with Embedded Columnar Framing and Rock Anchor Mechanism, further called Universal Cellular Cofferdam for simplicity, comprises columnar framing 10 with columns 11 placed on the circumference of the cofferdam circular cell; rock or soil anchors 16 embedded and grouted into the columns of the cofferdam framing and into the reinforced concrete pile cap 25; rock anchors 16 anchored into the bed rock or another competent soil base strata; cofferdam perimeter skin 15 formed of interlocked flat sheet pile sections, and granular fill 22 of the cofferdam cell.
  • DRAWINGS—FIGURES
  • In the drawings, closely related figures have the same number.
  • FIG. 1 shows failure modes of the conventional cellular cofferdam.
  • FIG. 2 shows failure modes of the Universal Cofferdam
  • FIG. 3 shows 3-D view of universal prefabricated cofferdam framing. (Sheet pile interlock connector 14 and horizontal truss moment connection plates 18 are not shown for clarity)
  • FIG. 4 shows Universal Cofferdam framing in plan.
  • FIG. 5 shows sectional view 5-5 indicated by section line 5-5 in FIG. 4
  • FIG. 6 shows truss diaphragm connection to the column of the cofferdam framing.
  • FIGS. 7 and 8 show cofferdam column bearing support.
  • FIGS. 9 and 10 show Cofferdam lifting hat detail
  • FIG. 11 show Universal Cofferdam with rock anchors in plan
  • FIG. 12 shows sectional view 12-12 indicated by section line 12-12 in FIG. 11
  • FIG. 13 shows Section 13-13 indicated by section line 13-13 in FIG. 11.
  • FIG. 14, 15 show resistance mechanism of the group of preloaded rock or soil anchors.
  • DRAWINGS—REFERENCE NUMERALS
  • 10 cofferdam framing assembly
  • 11 Universal Cofferdam column
  • 12 star truss diaphragm
  • 13 Universal Cofferdam wale
  • 14 sheet pile interlock connector
  • 15 flat sheet piling of the cofferdam skin
  • 15A deformed or buckled section of the cofferdam skin
  • 16 rock anchor insert
  • 17 headed studs
  • 18 star truss diaphragm flange to column gusset plate connector
  • 19 column bearing detail
  • 20 lifting hat detail
  • 21 air lock hole
  • 22 granular fill
  • 23 rock socket
  • 24 rock rupture cone
  • 25 concrete pile cap
  • 26 rock anchor grouting outlet/spacer
  • Abbreviations shown on the figures:
  • MHV—Mean High Water
  • MLV—Mean Low Water
  • BDR—Bed Rock elevation
  • R.S.—bottom of rock socket hole.
  • T.B.—base of cofferdam
  • A—convex surface failure through the granular fill
  • B—concave shallow surface failure through the base
  • C—concave deep surface sliding failure
  • D—plain failure sliding surface
  • H—lateral destabilizing force
  • Detailed Description—FIGS. 3, 11, 12, 13, 14 and 15—First Embodiment
  • One embodiment of the Universal Cellular Cofferdam is illustrated in FIG. 11 (top view of the Universal Cellular Cofferdam framing) and FIGS. 12 and 13 ( sections 12 and 13 taken from FIG. 10). The Universal Cellular Cofferdam framing assembly 10 comprises 6 tubular columns 11 interconnected by two levels of star truss diaphragms 12 and two levels of perimeter wales 13. Each end of the star truss diaphragm is connected to the column with gusset plates 18. Skin of the Universal Cellular Cofferdam consists of six segments of interconnected flat sheet pile sections 15 connected to cofferdam columns 11 separating each Universal Cellular Cofferdam skin segment. Extreme sheet pile elements of each sheet pile segment are connected to each column with sheet pile interlock connector 14 welded to column 11.
  • In the preferred embodiment, the cofferdam framing assembly 10 shown in FIG. 3 is anchored to the soil sub base with rock or soil anchor inserts 16 grouted inside of each column 11 and within predrilled rock socket 23. At the upper end rock anchor inserts 16 are anchored into the reinforced concrete pile cap 25.
  • In the preferred embodiment, rock or soil anchors inserts have headed studs 17 welded to the body of the anchor insert 16 embedded and grouted inside the rock socket 23; and to the body of the insert 16 embedded into concrete pile cap 25.
  • Headed studs 17 increase the grip between the concrete of the rock socket 23 and rock anchor insert 16; and between the concrete of the pile cap 25 and rock anchor insert 16 correspondingly. At the bottom end each column 11 of the cofferdam framing 10 is terminated with column bearing detail 19. Bearing detail 19 reduces the bearing pressure under the cofferdam column during the cofferdam framing positioning. Lifting points of each cofferdam column are terminated with removable lifting hat detail 20 with two air lock holes 21 shown in FIGS. 9 and 10. Air lock holes 21 prevent formation of the air plug in the column, and prevent cofferdam framing floatation during cofferdam submergence. In other embodiments Universal Cellular Cofferdam framing 10 can be installed without rock or soil anchors. In that case it will function as a prefabricated columnar template framing for a conventional cofferdam. FIG. 3 shows Universal Cellular Cofferdam framing 10 without cofferdam skin 15 and rock anchor inserts 16.
  • Advantages
  • Present art overcomes handicaps of the original TVA design widely used since cofferdam invention. It is based on a different concept of full cellular cofferdam construction utilizing embedded pipe columnar framing as a false work for sheet piling installation; and for anchoring cofferdam to the bedrock. Present art utilizes pipe rock anchors 16 installed through the pipe columns 11 of the Universal Cellular Cofferdam framing 10 as the most rational rock anchor detail. Connection of the rock anchors 16 to the Universal Cellular Cofferdam pile cap 25 enhances Universal Cellular Cofferdam stability arresting Cofferdam skin 15 differential sliding and skin buckling depicted by numeral 15A in FIG. 1.
  • While regular cellular cofferdams are well suited for the purposes for which they were originally designed, they have more limited load capacity than Universal Cellular Cofferdam of the present art. The lateral load resisted by Universal Cellular Cofferdam by far exceeds the load magnitude resisted by the conventional cellular cofferdam of similar height and diameter.
  • Features and advantages of the present invention will become more fully appreciated and understood when reviewed in conjunction with accompanying FIGS. 14 and 15.
  • FIG. 14 shows Universal Cellular Cofferdam framing in plan with a footprint of the engaged truncated rock anchor cones 24 resisting Universal Cellular Cofferdam overturning.
  • The configuration of the Universal Cellular Cofferdam star truss diaphragm 12 makes force directionality irrelevant.
  • At least 2 rock anchors 16 are engaged in the Universal Cellular Cofferdam resistance to overturning at any time. FIG. 15 shows the mechanism of the rock anchor in sectional view. Each pair of the truncated rock rupture cones 24 is effectively preloaded by cofferdam granular fill 22. Such arrangement increases pull out capacity of the rock or soil anchors and prevents Universal Cellular Cofferdam rotation. Two rock anchors 16 shown along the horizontal fulcrum axis X′-X′ serve as compression elements of the resisting couple composed of the two tension rock anchor elements and two compression rock anchor elements. Directionality of the fulcrum axis X′-X′ and position of the two engaged tension anchors depends on the directionality of the overturning force H shown in FIGS. 1 and 2. Another advantage of the Universal Cellular Cofferdam system is evident from the enhanced sliding capacity of the cofferdam along the plan D shown in FIG. 2. Sliding resistance of the Universal Cellular Cofferdam becomes the combination of the sliding resistance between the granular fill 22 and cofferdam sub base; and shear resistance capacity of the rock anchor sockets 23 with embedded rock anchors 16. Universal Cellular Cofferdam rock anchor system prevents convex slip circle failure through the granular fill (Line A), and concave slip circle failure through the sub base of the cofferdam (Line B). Similarly, Universal Cellular Cofferdam system prevents deep slip circle failure (Line C). The deep slip circle failure of the Universal Cofferdam can happen only in case of buckling or yielding of the two rock anchors 16 located along the floating fulcrum axis X′-X′. Such mechanism makes Universal Cofferdam more than 10 times stiffer than conventional cofferdam of the similar geometry.
  • The present art allows great flexibility for usage of Universal Cellular Cofferdam. It can be used for construction of deep water quay walls and dolphins subjected to unusually high lateral loads. However, it becomes the most efficient solution for bridge protection devices, protecting bridge piers from high load of ship and ice collision impact.
  • While, concept of U.S. Pat. No. 1,398,221 was a step forward from the original art, allowing cofferdam assembly in the dry, it failed to realize benefits of columnar framing and rock anchoring devices for stability of the cellular cofferdam structure. The system described by U.S. Pat. No. 1,398,221 has not eliminated cofferdam skin buckling mode caused by escaping granular fill.
  • Similarly, concept of U.S. Pat. No. 4,419,030 was just another modification of the currently practiced cellular cofferdam construction method. However, solution suggested by U.S. Pat. No. 4,419,030 was not addressing stability issues of the final cofferdam structure, nor it was claiming a new cofferdam system.
  • Conclusions, Ramifications, and Scope.
  • Accordingly, the reader will see that the Universal Cellular Cofferdam of the various embodiments can be used for construction of the conventional cellular cofferdam systems and for anchored cofferdam systems with greatly enhanced resisting capacity to sliding and overturning.
  • Furthermore, the system has additional advantages in that:
      • it allows fabrication of the cofferdam template in the convenience of the fabrication shop, thus shortening and eliminating many efforts associated with a field work.
      • it can be easily leveled on site using leveling pads under each framing column.
      • it permits installation of the rock anchors, significantly increasing cofferdam resistance to sliding and overturning.
      • columnar framing of the Universal Cellular Cofferdam prevents cofferdam skin buckling failure typical for conventional cofferdams with escaping granular fill.
  • Although the description above contains specificities, these should not be construed as limiting the scope of the embodiments but as merely providing illustrations of some of the presently preferred embodiments.
  • Thus the scope of the embodiments should be determined by the appended claims and their legal equivalents, rather than by the examples given.

Claims (2)

The present invention claims the following:
1. Hybrid gravity-columnar system comprising circular prefabricated columnar space framing; perimeter sheet pile infill between the columns of the framing and granular infill confined by a formed barrel herein; rock anchors installed and grouted into bedrock and each column annular space, and anchored into the concrete pile cap of the composite framing, forming composite anchored columnar—gravitational system called Universal Cellular Cofferdam herein.
2. Prefabricated rigid space framing comprising six pipe columns and two horizontal six end star truss diaphragms consisting of two equally sided triangles having all truss elements of the diaphragm intersected and connected in one plan, serving as an integral structural support and lateral bracing for hybrid gravity-columnar system.
US13/694,011 2012-10-22 2012-10-22 Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism Abandoned US20140112718A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US13/694,011 US20140112718A1 (en) 2012-10-22 2012-10-22 Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US13/694,011 US20140112718A1 (en) 2012-10-22 2012-10-22 Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism

Publications (1)

Publication Number Publication Date
US20140112718A1 true US20140112718A1 (en) 2014-04-24

Family

ID=50485469

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/694,011 Abandoned US20140112718A1 (en) 2012-10-22 2012-10-22 Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism

Country Status (1)

Country Link
US (1) US20140112718A1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436689A (en) * 2016-10-05 2017-02-22 黄坤坤 Bearing platform steel plate pile support and steel plate pile serving bearing platform template construction method
CN109469085A (en) * 2018-08-13 2019-03-15 中建三局第三建设工程有限责任公司 A kind of embedding rock cushion cap foundation construction method of deep water
CN109469080A (en) * 2018-12-11 2019-03-15 中铁五局集团贵州工程有限公司 A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water
CN109653227A (en) * 2019-01-08 2019-04-19 中铁大桥局集团有限公司 A kind of sliding launch device of heavy steel cofferdam
CN114411781A (en) * 2022-01-06 2022-04-29 中交第二航务工程局有限公司 Construction method of rock geological sheet pile cofferdam
CN115324087A (en) * 2022-07-29 2022-11-11 中交路桥建设有限公司 Deepwater rock-socketed combined light cofferdam
CN120119665A (en) * 2025-05-14 2025-06-10 山西省水利建筑工程局集团有限公司 A water conservancy construction cofferdam device and use method thereof

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1014626A (en) * 1906-12-13 1912-01-09 Oliver Cromwell Edwards Jr Caisson.
US1485381A (en) * 1922-01-03 1924-03-04 William E Pease Cribbing for shore-protecting systems
US1500120A (en) * 1922-01-03 1924-07-08 William E Pease Wave-resisting structure
US1827146A (en) * 1929-07-06 1931-10-13 Thomas L Durocher Crib, caisson, and the like
US2189804A (en) * 1938-05-14 1940-02-13 Herbert M Knight Sheet piling
US3710579A (en) * 1971-05-13 1973-01-16 D Killmer Portable coffer dam and method of making
US6893191B2 (en) * 2002-07-19 2005-05-17 Creative Pultrusions, Inc. Wale and retaining wall system
US7390144B2 (en) * 2006-02-02 2008-06-24 Nova Group Inc. Pre-cast/pre-stressed concrete and steel pile and method for installation
US20120301227A1 (en) * 2011-05-24 2012-11-29 Dehan Intellectual Technology Co., Ltd Foundation pile and installing method thereof
US8453416B2 (en) * 2008-05-29 2013-06-04 David R. Brindle Apparatus and method for an adjustable column
US8474212B2 (en) * 2009-04-22 2013-07-02 Rautaruukki Oyj Tower for a wind power plant

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1014626A (en) * 1906-12-13 1912-01-09 Oliver Cromwell Edwards Jr Caisson.
US1485381A (en) * 1922-01-03 1924-03-04 William E Pease Cribbing for shore-protecting systems
US1500120A (en) * 1922-01-03 1924-07-08 William E Pease Wave-resisting structure
US1827146A (en) * 1929-07-06 1931-10-13 Thomas L Durocher Crib, caisson, and the like
US2189804A (en) * 1938-05-14 1940-02-13 Herbert M Knight Sheet piling
US3710579A (en) * 1971-05-13 1973-01-16 D Killmer Portable coffer dam and method of making
US6893191B2 (en) * 2002-07-19 2005-05-17 Creative Pultrusions, Inc. Wale and retaining wall system
US7390144B2 (en) * 2006-02-02 2008-06-24 Nova Group Inc. Pre-cast/pre-stressed concrete and steel pile and method for installation
US8453416B2 (en) * 2008-05-29 2013-06-04 David R. Brindle Apparatus and method for an adjustable column
US8474212B2 (en) * 2009-04-22 2013-07-02 Rautaruukki Oyj Tower for a wind power plant
US20120301227A1 (en) * 2011-05-24 2012-11-29 Dehan Intellectual Technology Co., Ltd Foundation pile and installing method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Foundation Piling LTD website; wayback machine capture; Oct 29, 2011 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436689A (en) * 2016-10-05 2017-02-22 黄坤坤 Bearing platform steel plate pile support and steel plate pile serving bearing platform template construction method
CN109469085A (en) * 2018-08-13 2019-03-15 中建三局第三建设工程有限责任公司 A kind of embedding rock cushion cap foundation construction method of deep water
CN109469080A (en) * 2018-12-11 2019-03-15 中铁五局集团贵州工程有限公司 A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water
CN109653227A (en) * 2019-01-08 2019-04-19 中铁大桥局集团有限公司 A kind of sliding launch device of heavy steel cofferdam
CN114411781A (en) * 2022-01-06 2022-04-29 中交第二航务工程局有限公司 Construction method of rock geological sheet pile cofferdam
CN115324087A (en) * 2022-07-29 2022-11-11 中交路桥建设有限公司 Deepwater rock-socketed combined light cofferdam
CN120119665A (en) * 2025-05-14 2025-06-10 山西省水利建筑工程局集团有限公司 A water conservancy construction cofferdam device and use method thereof

Similar Documents

Publication Publication Date Title
US20140112718A1 (en) Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism
US20100232878A1 (en) Universal Framed Cofferdam
CN103741706B (en) A kind of deep water open type combination foundation harbour and construction method thereof
CN114319143A (en) A temporary pier structure for bridge jacking in deep soft soil layers
WO2013153387A1 (en) Foundation structures
US3913337A (en) Piling
CN110777806A (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
US4132082A (en) Piling
US4674919A (en) Off-shore platform structure
JP4743412B2 (en) Pile head seismic isolation structure
CN112627208B (en) Assembled cofferdam suitable for rock foundation and construction method thereof
EP4377522A1 (en) Gravity based foundation
JP5685493B2 (en) Foundation structure
NO136375B (en)
EP2597206B1 (en) Foundation and method of manufacture
CN110735394A (en) Cable tower structure and construction method thereof
CN110761192B (en) Caisson pile foundation and construction method thereof
Haydl et al. Design and construction errors—Case studies
WO2011154799A2 (en) Pre-stressed concrete foundation for a marine building structure
RU2321704C2 (en) Vertical steel tank base
CN207987917U (en) A kind of frost-cracking-preventing steel-pipe pile suitable for frost zone bridge subaqueous work
CN206173998U (en) Pile adds muscle retaining wall
CN117071576B (en) Soft soil foundation pit support structures and their support methods and lattice steel pipe piles
JPH03103535A (en) Countermeasure structure for liquefaction of building
CN118756714B (en) A three-row pile structure and construction method thereof

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION