slab
ballast
fixed road
stopper
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/736,729
Inventor
Tristan Moelter
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DB Netz AG
Original Assignee
DB Netz AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DB Netz AG filed Critical DB Netz AG
Assigned to DB NETZ AG reassignment DB NETZ AG ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: MOELTER, TRISTAN
Publication of US20110197379A1 publication Critical patent/US20110197379A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • E01B1/007Ballastless track, e.g. concrete slab trackway, or with asphalt layers with interlocking means to withstand horizontal forces
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/003Arrangement of tracks on bridges or in tunnels

Definitions

  • the invention relates to a fixed road for rail-bound vehicles on a bridge, wherein the fixed road is composed of a bridge superstructure slab, a support slab comprising a longitudinal hump and stopper covering said slab and a ballast slab comprising clearances, on which the rails are arranged with fasteners.
  • a support slab is applied to the bridge superstructure slab for protection of the surface seal, which in the region of the tracks comprises reinforcement strips of greater thickness, in which depressions longitudinally spaced from one another are arranged. Ballast slabs, which with spurs at their bottom engage in the depressions in the reinforcement strips of the support slab are located on these reinforcement strips and are thus positively connected to said support slab.
  • a fixed road for rail-bound vehicles on bridges which is composed of a bridge superstructure slab, a support slab and a ballast slab.
  • the ballast slab comprises clearances for individual humps, each of which is arranged at the longitudinal ends of the support slab. The clearances of the ballast slab with this construction engage about the humps of the support slab.
  • each slab has to comprise two stoppers.
  • the invention is based on the object of developing a structure which makes possible simpler longitudinal reinforcement and reduced shuttering and manufacturing expenditure and the production of longer slabs.
  • the support slab ( 1 ) comprising the longitudinal depression ( 4 ) comprises the stopper ( 5 ) at the height of the middle of the ballast slab ( 8 ) to be arranged above and the longitudinal depression ( 7 ) of the support slab ( 1 ) in this region is interrupted by the stopper ( 5 ) over a length of 60 to 100 cm and the ballast slab ( 8 ) comprises a longitudinal rib ( 4 ), which in its middle region is interrupted by means of a clearance ( 6 ) over a length of 65 cm to 105 cm, in which the stopper ( 5 ) of the support slab ( 1 ) positively engages.
  • the margins of the longitudinal rib ( 4 ) comprise strip bearings, wherein an elastomer strip as strip bearing is glued on to the margins of the longitudinal rib ( 4 ). This has a thickness of 1.0 to 1.5 cm.
  • a protective concrete layer ( 3 ) is arranged under the support slab ( 1 ). It preferentially has a minimum concrete grade of C25/35 and a thickness of 5 to 11 cm.
  • a seal ( 11 ) can be arranged between bridge superstructure slab ( 2 ) and the support slab ( 1 ) or the protective concrete layer ( 3 ) . This is embodied with bitumen webs and serves to protect the bridge superstructure slab ( 2 ).
  • the support slab ( 1 ) at its side facing the protective concrete layer ( 3 ) comprises transverse channels ( 9 ; 10 ) at a mutual spacing of 300 to 800 cm, which have a width of 8 to 12 cm and are embodied over the entire width of the support slab ( 1 ).
  • the longitudinal rib ( 4 ) with clearance ( 6 ) can also be arranged on the support slab ( 1 ) and the longitudinal depression ( 7 ) with stopper ( 5 ) on the ballast slab ( 8 ). Because of this, the structure can be better adapted to the respective conditions of the bridge and the respective load introduced.
  • the length of the slabs on bridges can be increased and then amount . . . up to approximately 30 m.
  • the arrangement of the stoppers in the middle of the support slab merely requires one stopper per support slab and one clearance in the ballast slab
  • ballast slabs and the stoppers are substantially reduced for a bridge superstructure length (e.g. 18 m of slab length with one stopper instead of 6 m slab length with two stoppers).
  • FIG. 1 the bridge structure of the fixed road in longitudinal section
  • FIG. 2 a cross section through the bridge in the end region of the slab
  • FIG. 3 a cross section through the bridge in the slab middle
  • the support slab 1 is mounted on the bridge superstructure slab 2 by way of a protective concrete layer 3 .
  • the support slab 1 has the longitudinal depression 7 and in the middle region the stopper 5 , which engages in the clearance 6 of the longitudinal rib 4 of the ballast slab 8 arranged in the middle.
  • the support slab 1 comprises transverse channels 9 ; 10 which are embodied in a width of approximately 10 cm. These serve for the transverse drainage of the bridge superstructure slab 2 .
  • a seal 11 is arranged between the support slab 1 and the bridge superstructrue slab 2 or the protective concrete layer 3 .
  • the support slab 1 is separated from the ballast slab 8 through a separating plane 12 . Because of this it is achieved that both slabs can move differently from each other under the influence of temperature, so that cracks in the structure can be avoided.
  • Strip bearings in form of elastomer tape (t ⁇ 10 mm) are glued on to the margins of the longitudinal rib 4 .

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Railway Tracks (AREA)

Abstract

The invention relates to a fixed road for rail-bound vehicles on a bridge, wherein the fixed road consists of a bridge superstructure slab, a support slab covering said bridge superstructure slab and comprising longitudinal humps and stoppers and a ballast slab comprising clearances, on which the rails are arranged with fasteners.
The invention is based on the object of developing a structure which requires simpler longitudinal reinforcement and reduced shuttering and manufacturing expenditure and makes possible the manufacture of longer ballast slabs.
According to the invention, this is achieved in that the support slab (1) comprising the longitudinal depression (7) comprises only one stopper (5) at the height of the middle of the ballast slab (8) to be arranged above and the longitudinal depression (7) of the support slab (1) in this region is interrupted by the stopper (5) over a length of 60 to 100 cm and the ballast slab (8) comprises a longitudinal rib (4), which in its middle region is interrupted by means of a clearance (6) over a length of 65 cm to 105 cm in which the stopper (5) of the support slab (1) positively engages.

Description

  • The invention relates to a fixed road for rail-bound vehicles on a bridge, wherein the fixed road is composed of a bridge superstructure slab, a support slab comprising a longitudinal hump and stopper covering said slab and a ballast slab comprising clearances, on which the rails are arranged with fasteners.
  • On the rapid transport routes of the railway so-called fixed roads have increasingly become dominant in recent years. With these structures, the rails are not fastened to sleepers arranged on a gravel bed, but mounted on a reinforced concrete support slab. The reason for using the fixed road for high-speed routes is the better position constancy and the greater availability resulting from longer maintenance intervals.
  • Placing a fixed road on bridges has been a problem to date. With a fixed road with continuously welded rails every cross section practically remains almost locationally fixed undisplaceably in any temperature, while temperature changes merely cause changes in stress in the rails. Since with bridge structures changes in length materialise due to temperature changes, the combination of a fixed road with a bridge constitutes a problem that is difficult to solve.
  • To solve the problem, it was proposed in DE 24 43 770 to arrange the support slab longitudinally displaceable on the bridge structure so that the bridge structure can move below the fixed road. The potentially very large forces during the braking of a train are absorbed into and passed on to the support slab which has to transfer said forces to the bridge superstructure. Dimensioning of the brake force distribution over the bridge and the continuous rails is highly problematic.
  • In order to avoid this problem, fixed roads for rail-bound vehicles and bridges have been developed which are know as “Rheda” system. With this system, a support slab is applied to the bridge superstructure slab for protection of the surface seal, which in the region of the tracks comprises reinforcement strips of greater thickness, in which depressions longitudinally spaced from one another are arranged. Ballast slabs, which with spurs at their bottom engage in the depressions in the reinforcement strips of the support slab are located on these reinforcement strips and are thus positively connected to said support slab.
  • Producing this known fixed road is time-consuming and costly and requires substantial material expenditure so that the weight and the construction height with unilateral track elevation become too great.
  • DE 196 20 731 A1 is known, wherein a fixed road for rail-bound vehicles on bridges is described, which is composed of a bridge superstructure slab, a support slab and a ballast slab. The ballast slab comprises clearances for individual humps, each of which is arranged at the longitudinal ends of the support slab. The clearances of the ballast slab with this construction engage about the humps of the support slab.
  • This construction requires elaborate longitudinal reinforcement and high-precision working. This requires a lot of work and time. In addition, the reinforcement strips of the support slabs and the ballast slab each are embodied only with a short maximum length of 6 m. This requires a multiplicity of slabs on a bridge and elaborate shuttering and reinforcement work for the concrete slab and the stoppers. Through the arrangement of the stoppers each at the end of the slabs of the structure, each slab has to comprise two stoppers.
  • The invention is based on the object of developing a structure which makes possible simpler longitudinal reinforcement and reduced shuttering and manufacturing expenditure and the production of longer slabs.
  • According to the invention, this is achieved in that the support slab (1) comprising the longitudinal depression (4) comprises the stopper (5) at the height of the middle of the ballast slab (8) to be arranged above and the longitudinal depression (7) of the support slab (1) in this region is interrupted by the stopper (5) over a length of 60 to 100 cm and the ballast slab (8) comprises a longitudinal rib (4), which in its middle region is interrupted by means of a clearance (6) over a length of 65 cm to 105 cm, in which the stopper (5) of the support slab (1) positively engages.
  • The margins of the longitudinal rib (4) comprise strip bearings, wherein an elastomer strip as strip bearing is glued on to the margins of the longitudinal rib (4). This has a thickness of 1.0 to 1.5 cm.
  • Under the support slab (1) a protective concrete layer (3) is arranged. It preferentially has a minimum concrete grade of C25/35 and a thickness of 5 to 11 cm.
  • Between bridge superstructure slab (2) and the support slab (1) or the protective concrete layer (3) a seal (11) can be arranged. This is embodied with bitumen webs and serves to protect the bridge superstructure slab (2).
  • The support slab (1) at its side facing the protective concrete layer (3) comprises transverse channels (9; 10) at a mutual spacing of 300 to 800 cm, which have a width of 8 to 12 cm and are embodied over the entire width of the support slab (1).
  • The longitudinal rib (4) with clearance (6) can also be arranged on the support slab (1) and the longitudinal depression (7) with stopper (5) on the ballast slab (8). Because of this, the structure can be better adapted to the respective conditions of the bridge and the respective load introduced.
  • ADVANTAGES OF THE INVENTION
  • The length of the slabs on bridges can be increased and then amount . . . up to approximately 30 m.
  • Only simple and cost-effective longitudinal reinforcement is required (less cutting and bending)
  • The slabs altogether require less reinforcement (less reinforcement for stoppers)
  • The expenditure for shuttering, reinforcing and other expenditure drops by approximately 50%
  • The arrangement of the stoppers in the middle of the support slab merely requires one stopper per support slab and one clearance in the ballast slab
  • If only one stopper instead of two stoppers is arranged, of which with the conventional design, one each is arranged on each slab end, no constraints develop between ballast slab and bridge superstructure slab in the event of changes in length
  • “Migrating” of the ballast slab in longitudinal direction is avoided
  • The ballast slab can expand freely under the effect of temperature because of the middle arrangement of the stopper
  • The number of ballast slabs and the stoppers is substantially reduced for a bridge superstructure length (e.g. 18 m of slab length with one stopper instead of 6 m slab length with two stoppers).
  • EXEMPLARY EMBODIMENT
  • In the following, the invention is explained in more detail by means of an exemplary embodiment.
  • Here it shows:
  • FIG. 1—the bridge structure of the fixed road in longitudinal section
  • FIG. 2—a cross section through the bridge in the end region of the slab
  • FIG. 3—a cross section through the bridge in the slab middle
  • The support slab 1 is mounted on the bridge superstructure slab 2 by way of a protective concrete layer 3. The support slab 1 has the longitudinal depression 7 and in the middle region the stopper 5, which engages in the clearance 6 of the longitudinal rib 4 of the ballast slab 8 arranged in the middle. At a spacing of 300 to 800 cm, the support slab 1 comprises transverse channels 9; 10 which are embodied in a width of approximately 10 cm. These serve for the transverse drainage of the bridge superstructure slab 2.
  • Between the support slab 1 and the bridge superstructrue slab 2 or the protective concrete layer 3 a seal 11 is arranged. The support slab 1 is separated from the ballast slab 8 through a separating plane 12. Because of this it is achieved that both slabs can move differently from each other under the influence of temperature, so that cracks in the structure can be avoided.
  • Strip bearings in form of elastomer tape (t≈10 mm) are glued on to the margins of the longitudinal rib 4.

Claims (10)

1. A fixed road for rail-bound vehicles on a bridge, wherein the fixed road consists of a bridge superstructure slab (2) a support slab (1) comprising a longitudinal depression and a stopper covering said bridge superstructure slab and a ballast slab (8) comprising longitudinal ribs, on which the rails are arranged with fasteners,
wherein the support slab (1) comprising the longitudinal depression (4) comprises the stopper (5) at the height of the middle of the ballast slab (8) to be arranged above and the longitudinal depression (7) of the support slab (1) in this region is interrupted by the stopper (5) over a length of approximately 60 to 100 cm and the ballast slab (8) comprises a longitudinal rib (4), which in its middle region is interrupted over a length of approximately 65 cm to 105 cm by means of a clearance (6), in which the stopper (5) of the support slab (1) positively engages.
2. The fixed road according to claim 1, wherein the margins of the longitudinal rib (4) comprise strip bearings.
3. The fixed road according to claim 1, wherein an elastomer tape is glued on to the margins of the longitudinal rib (7) as strip bearing.
4. The fixed road according to claim 1, wherein under the support slab (1) a protective concrete layer (3) is arranged.
5. The fixed road according to claim 1, wherein between bridge superstructure slab (2) and the support slab (1) or the protective concrete layer (3) a seal (11) is arranged.
6. The fixed road according to claim 1, wherein the support slab (1) at a mutual spacing of approximately 600 to 800 cm to the stopper (5) comprises transverse channels (9; 10) each, which have a width of 8 to 12 cm, are embodied over the entire length of the support slab (1) and run through the longitudinal rib (4).
7. The fixed road according to claim 1, wherein the longitudinal depression (7) with stopper (5) is arranged on the bottom of the ballast slab (8) and the longitudinal rib (4) with clearance (6) on the support slab (1).
8. The fixed road according to claim 1, wherein the stopper (5) is arranged in the middle of the length of the ballast slab (8).
9. The fixed road according to claim 1, wherein between the ballast slab (8) and the support slab (1) a separating layer as webbing and/or matting and/or coating is/are installed.
10. The fixed road according to claim 1, wherein the ballast slab (8) is embodied up to approximately 30 m long.
US12/736,729 2008-05-05 2009-03-05 Fixed road for rail-bound vehicles on a bridge Abandoned US20110197379A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DE202008006153.9 2008-05-05
DE202008006153U DE202008006153U1 (en) 2008-05-05 2008-05-05 Slab track for rail vehicles on a bridge
PCT/EP2009/001547 WO2009135554A1 (en) 2008-05-05 2009-03-05 Fixed track for rail-bound vehicles on a bridge

Publications (1)

Publication Number Publication Date
US20110197379A1 true US20110197379A1 (en) 2011-08-18

Family

ID=39598176

Family Applications (1)

Application Number Title Priority Date Filing Date
US12/736,729 Abandoned US20110197379A1 (en) 2008-05-05 2009-03-05 Fixed road for rail-bound vehicles on a bridge

Country Status (9)

Country Link
US (1) US20110197379A1 (en)
EP (1) EP2274486B1 (en)
JP (1) JP5220184B2 (en)
KR (1) KR101225807B1 (en)
CN (1) CN102016177B (en)
CA (1) CA2723757C (en)
DE (1) DE202008006153U1 (en)
RU (1) RU2460837C2 (en)
WO (1) WO2009135554A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022185101A1 (en) * 2021-03-05 2022-09-09 Overail S.R.L. Process and system for laying tracks for underground, railway and tramway lines

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947547A (en) * 2014-03-26 2015-09-30 苏州安邦轨道科技有限公司 Composite vibration reduction slab track system single body and composite type vibration isolation floating ballast bed
DE102016001953B4 (en) * 2016-02-19 2023-04-13 Karl Gerhards Railway bridges with slab track and continuously welded rails
RU173710U1 (en) * 2017-04-25 2017-09-07 Федеральное государственное бюджетное образовательное учреждение высшего образования "Петербургский государственный университет путей сообщения Императора Александра I" CONTINUOUS SPAN STRUCTURE OF A METAL BRIDGE WITH A SANDLESS WAY ON REINFORCED CONCRETE PLATES
RU2751167C1 (en) * 2020-09-22 2021-07-09 Федеральное государственное бюджетное образовательное учреждение высшего образования "Уральский государственный университет путей сообщения" Fixing block for securing diagram of sleepers of railway track for high-speed networks, long-distance and heavy train traffic

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4728032A (en) * 1985-10-02 1988-03-01 Getzner-Chemie Gesellschaft M.B.H. Loading members for railroad track
US4905896A (en) * 1987-10-31 1990-03-06 Dyckerhoff & Widmann Aktiengesellschaft Railroad roadway for high speed rail-mounted vehicles
US5163614A (en) * 1988-06-03 1992-11-17 Beton-Es Vasbetonipari Muvek Railway roadbeds with rail slabs, and method for preparing

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2443770C2 (en) 1974-09-13 1985-08-08 Ed. Züblin AG, 7000 Stuttgart Railway bridge with continuously welded tracks
JPS6018101U (en) * 1983-07-13 1985-02-07 東海ゴム工業株式会社 Rubber mats for slabs or ballast used in track structures
SU1617074A1 (en) * 1988-05-27 1990-12-30 Научно-Исследовательский И Проектный Институт Городского Пассажирского Транспорта Г.Москвы Tram crossing
DE19620731A1 (en) 1996-05-23 1997-11-27 Strabag Hoch Und Ingenieurbau Rigid track for rail vehicles across bridges
JP3622375B2 (en) * 1996-10-28 2005-02-23 清水建設株式会社 Floating slab structure and construction method
DE10004194C2 (en) * 2000-02-01 2002-04-18 Walter Heilit Verkehrswegebau Process for the production of a fixed railroad track on a bridge
DE102004061165A1 (en) * 2004-12-16 2006-07-06 Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg Concrete carriageway for rail vehicles
DE102005013947A1 (en) * 2005-03-26 2006-10-05 Pfleiderer Infrastrukturtechnik Gmbh & Co Kg Method for height correction of a fixed rail track and fixed rail track
DE102005032912A1 (en) * 2005-07-12 2007-01-18 Max Bögl Bauunternehmung GmbH & Co. KG Solid roadway on a bridge structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4728032A (en) * 1985-10-02 1988-03-01 Getzner-Chemie Gesellschaft M.B.H. Loading members for railroad track
US4905896A (en) * 1987-10-31 1990-03-06 Dyckerhoff & Widmann Aktiengesellschaft Railroad roadway for high speed rail-mounted vehicles
US5163614A (en) * 1988-06-03 1992-11-17 Beton-Es Vasbetonipari Muvek Railway roadbeds with rail slabs, and method for preparing

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022185101A1 (en) * 2021-03-05 2022-09-09 Overail S.R.L. Process and system for laying tracks for underground, railway and tramway lines

Also Published As

Publication number Publication date
DE202008006153U1 (en) 2008-07-10
CA2723757C (en) 2013-08-13
KR20100137509A (en) 2010-12-30
RU2460837C2 (en) 2012-09-10
RU2010142940A (en) 2012-04-27
KR101225807B1 (en) 2013-01-23
EP2274486B1 (en) 2013-05-08
JP2011518971A (en) 2011-06-30
WO2009135554A1 (en) 2009-11-12
CA2723757A1 (en) 2009-11-12
JP5220184B2 (en) 2013-06-26
EP2274486A1 (en) 2011-01-19
CN102016177A (en) 2011-04-13
CN102016177B (en) 2013-03-13

Similar Documents

Publication Publication Date Title
US8281722B2 (en) Solid track comprising a concrete strip
US9222225B2 (en) Pre-stressed concrete track slab of slab-type ballast-less track
US4905896A (en) Railroad roadway for high speed rail-mounted vehicles
US20110197379A1 (en) Fixed road for rail-bound vehicles on a bridge
CN106400613A (en) Ballastless track
KR101293285B1 (en) Fixed running track on a bridge structure
CN101194071A (en) Fixed rails for rail vehicles
KR20130079542A (en) Non-ballasted track for rail vehicles having an escape route
KR101673957B1 (en) Steel-Concrete Composite Sleeper and Railway Ballasted Track using such Composite Sleeper
Ižvolt et al. Historical development and applications of unconventional structure of railway superstructure of the railway infrastructure of the Slovak Republic
RU2328569C1 (en) Railway track for tunnels
RU2352705C1 (en) Method for installation of permanent way
RU2636289C1 (en) Device of upper track structure on bridges with driving on ballast and method of its erection
JP2014163150A (en) Through girder
JP7414658B2 (en) How to repair existing rails
KR102138365B1 (en) Non-ballast track structure for allowing longitudinal direction slip of steel railway bridge
US20160265176A1 (en) Continuous travel track on a viaduct structure
TR2024001009U5 (en) PLATE TRAVELER FOR BALLASTLESS RAILWAYS
CN105874125B (en) Without quarrel railway
US1121421A (en) Railway-track construction in paved streets.
RU107170U1 (en) ROAD OF THE ROAD BRIDGE
RU2588352C2 (en) Pre-stressed concrete track slab of slab-type ballast-less track
Morison et al. Discussion on Thin Floors for Bridges
CZ30758U1 (en) A safety rail assembly with concrete sleepers
HK1235438B (en) Overhead guided-transport track span and guided-transport viaduct

Legal Events

Date Code Title Description
AS Assignment

Owner name: DB NETZ AG, GERMANY

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:MOELTER, TRISTAN;REEL/FRAME:025331/0244

Effective date: 20101116

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION