US20100071570A1 - Baler tie feed apparatus - Google Patents
Baler tie feed apparatus Download PDFInfo
- Publication number
- US20100071570A1 US20100071570A1 US12/284,257 US28425708A US2010071570A1 US 20100071570 A1 US20100071570 A1 US 20100071570A1 US 28425708 A US28425708 A US 28425708A US 2010071570 A1 US2010071570 A1 US 2010071570A1
- Authority
- US
- United States
- Prior art keywords
- tie
- compaction chamber
- channels
- platen
- bale
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000005056 compaction Methods 0.000 claims abstract description 75
- 239000000463 material Substances 0.000 claims abstract description 34
- 230000007246 mechanism Effects 0.000 claims description 29
- 239000010813 municipal solid waste Substances 0.000 description 5
- 238000010276 construction Methods 0.000 description 3
- 229920000742 Cotton Polymers 0.000 description 2
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 238000004064 recycling Methods 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 241000251468 Actinopterygii Species 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000010902 straw Substances 0.000 description 1
- 230000001960 triggered effect Effects 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65B—MACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
- B65B27/00—Bundling particular articles presenting special problems using string, wire, or narrow tape or band; Baling fibrous material, e.g. peat, not otherwise provided for
- B65B27/12—Baling or bundling compressible fibrous material, e.g. peat
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B30—PRESSES
- B30B—PRESSES IN GENERAL
- B30B9/00—Presses specially adapted for particular purposes
- B30B9/30—Presses specially adapted for particular purposes for baling; Compression boxes therefor
- B30B9/3003—Details
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B30—PRESSES
- B30B—PRESSES IN GENERAL
- B30B9/00—Presses specially adapted for particular purposes
- B30B9/30—Presses specially adapted for particular purposes for baling; Compression boxes therefor
- B30B9/3096—Presses specially adapted for particular purposes for baling; Compression boxes therefor the means against which, or wherein, the material is compacted being retractable
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65B—MACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
- B65B13/00—Bundling articles
- B65B13/18—Details of, or auxiliary devices used in, bundling machines or bundling tools
- B65B13/20—Means for compressing or compacting bundles prior to bundling
Definitions
- the present invention generally relates to a baler tie feed apparatus useful in conjunction with a baler used to compact loose material, such as trash, refuse and recyclables, into dense, compact bales.
- the invention has specific utility in tying a bale of compacted material to maintain its compacted size and shape once the bale is discharged from the baler.
- Such balers typically consist of a hopper into which the material to be compacted is deposited, a compaction chamber in which the bale of compacted material is formed and a ram or platen which is activated to move the material from the hopper into the compaction chamber in which the material is compacted into a compact, dense bale. Once a bale is so formed, the platen is withdrawn and the bale discharged from the compaction chamber. Upon discharge from the compaction chamber, however, the compacted material in the bale will not maintain its shape, but tends to expand and increase in size. It is well known to tie the compacted bale with various media (such as twine, string, wire and metal banding) to minimize the size of the bale for handling, transfer, storage and/or disposal.
- various media such as twine, string, wire and metal banding
- the most basic tying arrangement includes manually wrapping the tying media around the bale after the bale is released from the baler and securing the opposed ends of the tying media once the bale is so wrapped. Since the material in the bale expands fairly quickly once the bale is removed from the baler, it is important to complete such manual wrapping as soon as possible to keep the expansion of the bale to a minimum. It is inevitable that some expansion will occur, however, no matter how quickly the bale is wrapped.
- bale wrapping devices are disclosed in U.S. Pat. No. 3,528,364 to Freund.
- a wire carrier is disclosed which moves partially around the bale to wrap a number of baling wires around the bale once formed. Once the baling wires have encircled the bale, a wire twisting mechanism is activated to twist the opposed ends of the baling wires to tighten and secure them.
- baler is provided in which channels or grooves are provided in the bottom of the ram (platen), rear and floor of the baler.
- the channels or grooves are aligned to define continuous channels or grooves around three sides of the bale.
- U.S. Pat. No. 5,852,969 to Anthony Another example of the prior art bale wrapping devices is shown in U.S. Pat. No. 5,852,969 to Anthony.
- a number of wedge-shaped, bale compression members are provided on the inner faces of opposed platens which cause compressed areas in a cotton bale as the same is being formed. Wires are threaded through the recesses in the compression members to encircle the bale. Once the opposed ends of the wires are secured, the platens are withdrawn and the wires remain in place around the bale by passing out of the recesses through an opening.
- bale wrapping devices of the prior art is described in U.S. Pat. No. 6,971,307 to Daniel et al.
- a bale encircling, movable guide track is provided having opposed sections defining a wire receiving groove. Once the guide track is in place, a wire is passed through the groove to encircle the bale. The opposed ends of the wire are secured by twisting, and the wire is tensioned to pull the wire from between the opposed sections of the guide track. At that point, the movable portions of the guide track are removed to leave the wire tied around the bale.
- a baler tie feed apparatus having a compaction chamber, a platen and a door, wherein aligned channels are defined within the top and bottom of the compaction chamber, the platen and the door so as to define a plurality of continuous open channels surrounding a bale of compacted material having horizontal top and bottom portions and vertical front and rear portions.
- the tying media i.e., wire
- the tying media is manually threaded though the top and rear portions of each channel until the end of the tying media is positioned adjacent the rear of the bottom portion of the channel.
- a tie feed apparatus which comprises a plurality of elongate tie engaging members, each of which operates within the bottom portion of one of the channels between a rear position wherein the forward ends of each tie engaging member is located beneath the rear portion of one of the channels and a forward position wherein the forward ends of each tie engaging member is located beneath the front portion of one of the channels.
- the front ends of the tie engaging members are adapted to engage the tying media.
- a rack and pinion drive is provided to operate the tie feed apparatus between the rear and forward positions. In operation, once the tying media has been manually inserted through the top and rear portions of the desired channels, the tie feed apparatus is advanced from its rear position toward its forward position.
- the front ends of the tie guiding members engage the corresponding tying media and thread it through the bottom portion of the corresponding channel until it reaches the front portion of the channel.
- the tying media can be manually grasped and extended upward through the front portion of the channel and secured to bind the bale.
- FIG. 1 is a side plan view of a refuse baler according to the present invention with the door in the closed position.
- FIG. 2 is a top plan view of a refuse baler according to the present invention with the door in the closed position.
- FIG. 3 is a side sectional view of a refuse baler according to the present invention with the door in an opened position, showing the platen in rear position A.
- FIG. 4 is a side sectional view of a refuse baler according to the present invention with the door in an opened position, showing the platen in intermediate position B.
- FIG. 5 is a side sectional view of a refuse baler according to the present invention with the door in an opened position, showing the platen in forward position C.
- FIG. 6 is a top sectional view of a portion of a refuse baler according to the present invention with the door in an opened position.
- FIG. 7 is a front plan view of the compaction chamber of a refuse baler according to the present invention with the door latched in the closed position.
- FIG. 8 is a top sectional view of the compaction chamber of a refuse baler according to the present invention taken along line 8 - 8 of FIG. 1 .
- FIG. 9 is a front sectional view of the compaction chamber of a refuse baler according to the present invention taken along the line 9 - 9 of FIG. 5 .
- FIG. 10 is a top sectional view of the door of a refuse baler according to the present invention taken along the line 10 - 10 of FIG. 7 .
- FIG. 11 is a bottom elevational view of a baler tie feed apparatus according to the present invention.
- FIG. 12 is a fragmented bottom perspective view of a tie feed apparatus and rack and pinion drive of a baler tie feed apparatus according to the present invention.
- FIGS. 13 a , 13 b and 13 c are side sectional views of a baler tie feed apparatus according to the present invention showing a bale tie wire in various stages of wrapping a bale.
- Baler 10 comprises a housing 11 supported by a frame 12 having vertical frame members 13 , and defines a compaction chamber 15 at the front of housing 11 and a hopper portion 14 positioned rearwardly of and adjacent to compaction chamber 15 ; and a platen 16 operable within housing 11 between a rear position A wherein the leading edge of platen 16 is positioned substantially along the same vertical plane as the rear of hopper portion 14 , an intermediate position B wherein the leading edge of platen 16 is positioned substantially along the same vertical plane as the front of hopper portion 14 , and a forward position C wherein the leading edge of platen 16 extends into compaction chamber 15 adjacent to the front of compaction chamber 15 .
- Frame 12 comprises spaced, vertical members 13 and spaced, upper and lower horizontal members (not shown) extending transversely of housing 11 and between the corresponding vertical members 13 .
- Vertical members 13 have feet 20 at their lower ends to permit attachment of baler 10 to the floor once in the desired location.
- the front end of compaction chamber 15 comprises a door 21 hinged at one side to swing outwardly to facilitate removal of a bale of compacted material from compaction chamber 15 once fully formed.
- Door 21 may be locked in a closed position by a hydraulically activated latch mechanism 22 .
- Baler 10 is provided with conventional controls.
- Platen 16 is operable between rear position A and forward position C by a power unit, generally shown as 23 , having a motor, hydraulic pumps and valves, acting on hydraulic cylinders to extend and withdraw platen 16 from one position to another.
- baler 10 The general operation of baler 10 is as follows. With platen 16 in position A and door 21 closed and latched shut, material to be compacted is deposited into hopper portion 14 through an upwardly facing opening in housing 11 by means of chute 24 . Once the material to be compacted is loaded into hopper portion 14 , power unit 23 is activated (either manually or automatically) to advance platen 16 toward position C, thereby moving the material into compaction chamber 15 and compacting it. Platen 16 will advance until the point at which the resistance of the material being compacted prevents further advancement. The power unit 23 is activated to advance platen 16 for a predetermined amount of time, at the end of which a switch is triggered to reverse the direction of platen 16 to retract it toward position A.
- platen 16 While being retracted, platen 16 moves at a constant speed. By measuring the amount of time it takes platen 16 to return to position B, the distance traveled by platen 16 while being retracted (and thus the depth of the compacted material in compaction chamber 15 ) can be determined. When such return time indicates that the bale is fully formed (i.e., compaction chamber 15 is full), platen 16 is stopped at position B while the bale is tied as is more fully described below. Once the bale is tied, door 21 is opened by unlatching latch mechanism 22 and platen 16 is advanced again toward position C to push the bale from compaction chamber 15 . All of the foregoing operations are accomplished with conventional equipment and controls.
- Compaction chamber 15 comprises a top portion 31 , a bottom portion 32 and side portions 33 extending between front frame member 12 and compaction chamber frame 34 .
- Compaction chamber frame 34 has spaced, vertical side members 35 and spaced, upper and lower horizontal members 36 , 37 .
- Top portion 31 of compaction chamber 15 is formed by a number of parallel “U” shaped ceiling beams 38 attached at one end to the underside of upper horizontal member of front frame member 12 and at the other end to upper horizontal member 36 of compaction chamber frame 34 .
- Ceiling beams 38 are oriented in such a manner that the webs of ceiling beams 38 face downwardly and form the ceiling of compaction chamber 15 .
- Ceiling beams 38 are spaced to define a number of parallel channels 39 between them.
- bottom portion 32 of compaction chamber 15 is formed by a number of parallel “U” shaped floor beams 40 attached at one-end to the top of lower horizontal member of front frame member 12 and at the other end to the top of lower horizontal member 37 of compaction chamber frame 34 .
- Floor beams 40 are oriented in such a manner that the webs of floor beams 40 face upwardly and form the floor of compaction chamber 15 .
- Floor beams 40 are spaced to define a number of parallel channels 41 between them. Each floor beam 40 is positioned directly below a ceiling beam 38 such that the channels 41 are located directly below a corresponding channel 39 .
- Door 21 comprises a door frame 50 having spaced, vertical side members, spaced, upper and lower horizontal members and a plurality of parallel, vertical “U” shaped door beams 54 attached at one end to the inside of upper horizontal member and at the other end to the insider of lower horizontal member.
- Door beams 54 are oriented in such a manner that the webs of door beams 54 face inwardly (or rearwardly) toward compaction chamber 15 when door 21 is closed and form the forward wall of compaction chamber 15 when door 21 is closed.
- Door beams 54 are spaced to define a number of parallel channels 55 between them.
- Each door beam 54 is aligned with a corresponding ceiling beam 38 and floor beam 40 such that channels 55 are aligned with corresponding channels 39 and 41 .
- Platen 16 comprises a platen frame 60 and a platen face 61 located on the forward end of platen frame 60 .
- Platen frame 60 has the same general cross-sectional configuration as housing 11 and is sized to slide within housing 11 . Wear pads are provided to maintain contact and even spacing between platen frame 60 and the inside of housing 11 .
- Platen face 61 is comprised of a plurality of parallel, vertical “U” shaped platen beams 63 attached to one end to the front of the top of platen frame 60 and at the other end to the front of the bottom of platen frame 60 .
- Platen beams 63 are oriented in such a manner that the webs of platen beams 63 face forwardly toward compaction chamber 15 to form platen face 61 .
- Platen beams 63 are spaced to define a number of parallel channels 64 between them.
- Each platen beam 63 is aligned with a corresponding ceiling beam 38 and floor beam 40 such that channels 64 align with corresponding channels 39 , 41 and 55 .
- each set of aligned channels 39 , 41 , 55 and 64 form a continuous channel around compaction chamber 15 when platen 16 is located between positions B and C.
- a platen shear bar 65 is attached to the top of platen face 61 .
- Platen shear bar 65 has a forward facing cutting edge 66 and a plurality of slots 67 which are aligned and communicate with channels 64 . Slots 67 permit the introduction of tying members into channels 64 when the tying process is commenced as described below.
- Shear bar 65 will act to cut through and shear off any material deposited in chute 24 that does not fit within hopper portion 14 as platen 16 passes from hopper portion 14 toward compaction chamber 15 .
- a stop plate 70 is attached across vertical members of compaction chamber frame 34 below the front of hopper portion 14 . Stop plate 70 is positioned such that it will lie beneath channels 64 in platen face 61 when platen 16 is in position B. A horizontal rod 71 is attached across the bottom of floor beams 40 slightly forward of stop plate 70 as shown.
- a tie guide mechanism 80 is attached to and operable on the underside of housing 11 .
- Tie guide mechanism 80 comprises a transverse bar 81 and a plurality of tie push rods 82 attached to tie transverse bar 81 at one end and extending forwardly therefrom.
- Tie guide mechanism 80 is suspended beneath housing 11 by means of suspension brackets 83 extending downwardly from the bottom of housing 11 and bearing pads attached to suspension brackets 83 , with two or more of tie push rods 82 riding on bearing pads as shown.
- the number of tie push rods 82 is equal to the number of channels 41 in the bottom portion 32 of compaction chamber 15 .
- Tie push rods 82 are aligned with channels 41 such that one tie push rod 82 is operable within and along length of each channel 41 .
- the length of tie push rods 82 is greater than the length of compaction chamber 15 .
- Tie guide mechanism 80 is operable between a position D wherein the forward ends of tie push rods 82 are located slightly rearwardly of platen face 61 when platen 16 is in position B and a position E wherein the forward ends of tie push rods 82 extend forwardly of the front of door 21 .
- Tie guide mechanism 80 is moved between position D and position E by means of a rack and pinion mechanisms 85 wherein a rack is located on the underside of each of the outer tie push rods 82 and engage a corresponding pinion rotatable on a shaft 86 attached to a motor 87 .
- rack and pinion mechanisms 85 By operating motor 87 in a forward or backward manner, the rack and pinion mechanisms 85 will cause tie guide mechanism 80 to move forward or backward.
- Rack and pinion mechanisms 85 is operable by conventional control means (either manual or automatic).
- each tie push rod 82 is notched as at notches to engage a tie when a tie is inserted down through the channels 55 in platen face 61 as described below.
- tie guide mechanism 80 Operation of tie guide mechanism 80 is best understood with reference to FIGS. 13 a to 13 c .
- platen 16 is returned to position B, whereby the bale is contained entirely within compaction chamber 15 .
- a bale tie wire 90 is inserted beneath frame 12 adjacent the front of baler 10 into each of the ceiling channels 39 and each of the corresponding platen channels 64 until tie wire 90 is stopped by coming into contact with stop plate 70 .
- rack and pinion mechanisms 85 are activated to move tie guide mechanism 80 forward from position D toward position E.
- tie guide mechanism 80 As tie guide mechanism 80 is moved forwardly, notches in the forward end of each tie push rod 82 engage the corresponding tie wire 90 at a point slightly above its end and push it forwardly. As the ends of tie wires 90 move forward, the end of tie wires 90 come into contact with rod 71 which causes the ends of tie wires 90 to be bent back against themselves thereby securing tie wires 90 in corresponding notches while tie wires 90 are threaded through the corresponding channels 41 in the bottom portion 32 of compaction chamber 15 .
- tie guide mechanism 80 is advanced to position E, the ends of tie wires 90 are manually advanced through the corresponding channels 55 in door 21 until tie wires 90 completely encircle the bale. Tie wires 90 are then cut and the opposed ends wrapped or otherwise secured. When all tie wires 90 have been so secured, door 21 is opened by releasing latch mechanism 22 and platen 16 is activated to advance it from position B toward position C, thereby expelling the bale from compaction chamber 15 .
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Basic Packing Technique (AREA)
Abstract
A baler tie feed apparatus is provided having a compaction chamber, a platen and a door, wherein aligned channels are defined within the top and bottom of the compaction chamber, the platen and the door so as to define a plurality of continuous open channels surrounding a bale of compacted material having horizontal top and bottom portions and vertical front and rear portions. A tie feed apparatus is provided which comprises a plurality of elongate tie engaging members, each of which engages tying media inserted through the top and rear portions of the channels and is advanced to thread the tying media through the bottom portion of the channels.
Description
- The present invention generally relates to a baler tie feed apparatus useful in conjunction with a baler used to compact loose material, such as trash, refuse and recyclables, into dense, compact bales. The invention has specific utility in tying a bale of compacted material to maintain its compacted size and shape once the bale is discharged from the baler.
- It is well known to compact loose material by means of a refuse or recycling baler into dense, tightly packed bales to facilitate the transfer, storage, disposal and/or recycling of such material. The types of material which may be so compacted range from agricultural products, such as straw, hay, cotton and the like, to trash, refuse and recyclables. For the purpose of this discussion, the material will be referred to as trash, refuse or recyclables, although it will be apparent that the present invention has utility with respect to the compaction of such other materials as well.
- Such balers typically consist of a hopper into which the material to be compacted is deposited, a compaction chamber in which the bale of compacted material is formed and a ram or platen which is activated to move the material from the hopper into the compaction chamber in which the material is compacted into a compact, dense bale. Once a bale is so formed, the platen is withdrawn and the bale discharged from the compaction chamber. Upon discharge from the compaction chamber, however, the compacted material in the bale will not maintain its shape, but tends to expand and increase in size. It is well known to tie the compacted bale with various media (such as twine, string, wire and metal banding) to minimize the size of the bale for handling, transfer, storage and/or disposal.
- A number of different tying arrangements have been utilized for this purpose. The most basic tying arrangement includes manually wrapping the tying media around the bale after the bale is released from the baler and securing the opposed ends of the tying media once the bale is so wrapped. Since the material in the bale expands fairly quickly once the bale is removed from the baler, it is important to complete such manual wrapping as soon as possible to keep the expansion of the bale to a minimum. It is inevitable that some expansion will occur, however, no matter how quickly the bale is wrapped.
- To solve the problems inherent with wrapping the bale manually after it is removed from the baler, it has been known to provide various means to wrap the bale while it is still in the baler and before it has an opportunity to expand. The primary challenge to be overcome in so doing is to wrap the bale with tying media while the bale is still located within the structure of the compaction chamber and the platen is in place. The prior art devices typically involve providing channels or openings within the compaction chamber and platen through which the tying media may be threaded to encircle the bale while the bale is in its most compacted form and prior to discharging the bale from the baler. These prior art solutions present their own set of problems, however.
- One example of such prior art bale wrapping devices is disclosed in U.S. Pat. No. 3,528,364 to Freund. In that instance, a wire carrier is disclosed which moves partially around the bale to wrap a number of baling wires around the bale once formed. Once the baling wires have encircled the bale, a wire twisting mechanism is activated to twist the opposed ends of the baling wires to tighten and secure them.
- Another example of such prior art bale wrapping devices is disclosed in U.S. Pat. No. 4,232,599 to Ulrich. In that instance, a baler is provided in which channels or grooves are provided in the bottom of the ram (platen), rear and floor of the baler. The channels or grooves are aligned to define continuous channels or grooves around three sides of the bale. Once the bale is formed, the door is opened and a “fish tool” is inserted into each channel to draw a number of wires or cords around three sides of the bale. Once so drawn around the bale, the opposed ends of the wires or cords are tied to secure the bale.
- Another example of the prior art bale wrapping devices is shown in U.S. Pat. No. 5,852,969 to Anthony. In this instance, a number of wedge-shaped, bale compression members are provided on the inner faces of opposed platens which cause compressed areas in a cotton bale as the same is being formed. Wires are threaded through the recesses in the compression members to encircle the bale. Once the opposed ends of the wires are secured, the platens are withdrawn and the wires remain in place around the bale by passing out of the recesses through an opening.
- Still yet another example of the bale wrapping devices of the prior art is described in U.S. Pat. No. 6,971,307 to Daniel et al. In this instance, a bale encircling, movable guide track is provided having opposed sections defining a wire receiving groove. Once the guide track is in place, a wire is passed through the groove to encircle the bale. The opposed ends of the wire are secured by twisting, and the wire is tensioned to pull the wire from between the opposed sections of the guide track. At that point, the movable portions of the guide track are removed to leave the wire tied around the bale.
- All of the prior art devices utilize complicated, detailed mechanisms which are expensive to construct and maintain.
- It is one object of the present invention to provide an apparatus for wrapping a bale of compacted material such as trash and refuse while the bale is still under pressure.
- It is another object of the present invention to provide an apparatus for wrapping a bale of compacted material which is inexpensive and reliable in construction and operation.
- To those ends, a baler tie feed apparatus is provided having a compaction chamber, a platen and a door, wherein aligned channels are defined within the top and bottom of the compaction chamber, the platen and the door so as to define a plurality of continuous open channels surrounding a bale of compacted material having horizontal top and bottom portions and vertical front and rear portions. The tying media (i.e., wire) is manually threaded though the top and rear portions of each channel until the end of the tying media is positioned adjacent the rear of the bottom portion of the channel. A tie feed apparatus is provided which comprises a plurality of elongate tie engaging members, each of which operates within the bottom portion of one of the channels between a rear position wherein the forward ends of each tie engaging member is located beneath the rear portion of one of the channels and a forward position wherein the forward ends of each tie engaging member is located beneath the front portion of one of the channels. The front ends of the tie engaging members are adapted to engage the tying media. A rack and pinion drive is provided to operate the tie feed apparatus between the rear and forward positions. In operation, once the tying media has been manually inserted through the top and rear portions of the desired channels, the tie feed apparatus is advanced from its rear position toward its forward position. In so doing, the front ends of the tie guiding members engage the corresponding tying media and thread it through the bottom portion of the corresponding channel until it reaches the front portion of the channel. At that point, the tying media can be manually grasped and extended upward through the front portion of the channel and secured to bind the bale.
-
FIG. 1 is a side plan view of a refuse baler according to the present invention with the door in the closed position. -
FIG. 2 is a top plan view of a refuse baler according to the present invention with the door in the closed position. -
FIG. 3 is a side sectional view of a refuse baler according to the present invention with the door in an opened position, showing the platen in rear position A. -
FIG. 4 is a side sectional view of a refuse baler according to the present invention with the door in an opened position, showing the platen in intermediate position B. -
FIG. 5 is a side sectional view of a refuse baler according to the present invention with the door in an opened position, showing the platen in forward position C. -
FIG. 6 is a top sectional view of a portion of a refuse baler according to the present invention with the door in an opened position. -
FIG. 7 is a front plan view of the compaction chamber of a refuse baler according to the present invention with the door latched in the closed position. -
FIG. 8 is a top sectional view of the compaction chamber of a refuse baler according to the present invention taken along line 8-8 ofFIG. 1 . -
FIG. 9 is a front sectional view of the compaction chamber of a refuse baler according to the present invention taken along the line 9-9 ofFIG. 5 . -
FIG. 10 is a top sectional view of the door of a refuse baler according to the present invention taken along the line 10-10 ofFIG. 7 . -
FIG. 11 is a bottom elevational view of a baler tie feed apparatus according to the present invention. -
FIG. 12 is a fragmented bottom perspective view of a tie feed apparatus and rack and pinion drive of a baler tie feed apparatus according to the present invention. -
FIGS. 13 a, 13 b and 13 c are side sectional views of a baler tie feed apparatus according to the present invention showing a bale tie wire in various stages of wrapping a bale. - Referring to the drawing, wherein like numerals represent like elements throughout the several views, there is shown a trash or refuse baler generally designated by the numeral 10.
Baler 10 comprises ahousing 11 supported by aframe 12 havingvertical frame members 13, and defines acompaction chamber 15 at the front ofhousing 11 and ahopper portion 14 positioned rearwardly of and adjacent tocompaction chamber 15; and aplaten 16 operable withinhousing 11 between a rear position A wherein the leading edge ofplaten 16 is positioned substantially along the same vertical plane as the rear ofhopper portion 14, an intermediate position B wherein the leading edge ofplaten 16 is positioned substantially along the same vertical plane as the front ofhopper portion 14, and a forward position C wherein the leading edge ofplaten 16 extends intocompaction chamber 15 adjacent to the front ofcompaction chamber 15. -
Frame 12 comprises spaced,vertical members 13 and spaced, upper and lower horizontal members (not shown) extending transversely ofhousing 11 and between the correspondingvertical members 13.Vertical members 13 havefeet 20 at their lower ends to permit attachment ofbaler 10 to the floor once in the desired location. - The front end of
compaction chamber 15 comprises adoor 21 hinged at one side to swing outwardly to facilitate removal of a bale of compacted material fromcompaction chamber 15 once fully formed.Door 21 may be locked in a closed position by a hydraulically activatedlatch mechanism 22. -
Baler 10 is provided with conventional controls.Platen 16 is operable between rear position A and forward position C by a power unit, generally shown as 23, having a motor, hydraulic pumps and valves, acting on hydraulic cylinders to extend and withdrawplaten 16 from one position to another. - The general operation of
baler 10 is as follows. Withplaten 16 in position A anddoor 21 closed and latched shut, material to be compacted is deposited intohopper portion 14 through an upwardly facing opening inhousing 11 by means ofchute 24. Once the material to be compacted is loaded intohopper portion 14,power unit 23 is activated (either manually or automatically) to advanceplaten 16 toward position C, thereby moving the material intocompaction chamber 15 and compacting it.Platen 16 will advance until the point at which the resistance of the material being compacted prevents further advancement. Thepower unit 23 is activated to advanceplaten 16 for a predetermined amount of time, at the end of which a switch is triggered to reverse the direction ofplaten 16 to retract it toward position A. While being retracted,platen 16 moves at a constant speed. By measuring the amount of time it takesplaten 16 to return to position B, the distance traveled by platen 16 while being retracted (and thus the depth of the compacted material in compaction chamber 15) can be determined. When such return time indicates that the bale is fully formed (i.e.,compaction chamber 15 is full),platen 16 is stopped at position B while the bale is tied as is more fully described below. Once the bale is tied,door 21 is opened by unlatchinglatch mechanism 22 andplaten 16 is advanced again toward position C to push the bale fromcompaction chamber 15. All of the foregoing operations are accomplished with conventional equipment and controls. -
Compaction chamber 15 comprises atop portion 31, abottom portion 32 andside portions 33 extending betweenfront frame member 12 andcompaction chamber frame 34.Compaction chamber frame 34 has spaced,vertical side members 35 and spaced, upper and lower 36, 37.horizontal members Top portion 31 ofcompaction chamber 15 is formed by a number of parallel “U” shaped ceiling beams 38 attached at one end to the underside of upper horizontal member offront frame member 12 and at the other end to upperhorizontal member 36 ofcompaction chamber frame 34. Ceiling beams 38 are oriented in such a manner that the webs of ceiling beams 38 face downwardly and form the ceiling ofcompaction chamber 15. Ceiling beams 38 are spaced to define a number ofparallel channels 39 between them. - Similarly,
bottom portion 32 ofcompaction chamber 15 is formed by a number of parallel “U” shaped floor beams 40 attached at one-end to the top of lower horizontal member offront frame member 12 and at the other end to the top of lowerhorizontal member 37 ofcompaction chamber frame 34. Floor beams 40 are oriented in such a manner that the webs of floor beams 40 face upwardly and form the floor ofcompaction chamber 15. Floor beams 40 are spaced to define a number ofparallel channels 41 between them. Eachfloor beam 40 is positioned directly below aceiling beam 38 such that thechannels 41 are located directly below a correspondingchannel 39. - Construction of
door 21 is best understood with reference toFIGS. 5 , 7 and 10.Door 21 comprises adoor frame 50 having spaced, vertical side members, spaced, upper and lower horizontal members and a plurality of parallel, vertical “U” shaped door beams 54 attached at one end to the inside of upper horizontal member and at the other end to the insider of lower horizontal member. Door beams 54 are oriented in such a manner that the webs of door beams 54 face inwardly (or rearwardly) towardcompaction chamber 15 whendoor 21 is closed and form the forward wall ofcompaction chamber 15 whendoor 21 is closed. Door beams 54 are spaced to define a number ofparallel channels 55 between them. Eachdoor beam 54 is aligned with acorresponding ceiling beam 38 andfloor beam 40 such thatchannels 55 are aligned with 39 and 41.corresponding channels - Construction of
platen 16 is best understood with reference toFIGS. 6 and 9 .Platen 16 comprises aplaten frame 60 and aplaten face 61 located on the forward end ofplaten frame 60.Platen frame 60 has the same general cross-sectional configuration ashousing 11 and is sized to slide withinhousing 11. Wear pads are provided to maintain contact and even spacing betweenplaten frame 60 and the inside ofhousing 11. Platen face 61 is comprised of a plurality of parallel, vertical “U” shaped platen beams 63 attached to one end to the front of the top ofplaten frame 60 and at the other end to the front of the bottom ofplaten frame 60. Platen beams 63 are oriented in such a manner that the webs of platen beams 63 face forwardly towardcompaction chamber 15 to formplaten face 61. Platen beams 63 are spaced to define a number of parallel channels 64 between them. Eachplaten beam 63 is aligned with acorresponding ceiling beam 38 andfloor beam 40 such that channels 64 align with 39, 41 and 55. Thus, it will be seen that each set of alignedcorresponding channels 39, 41, 55 and 64 form a continuous channel aroundchannels compaction chamber 15 whenplaten 16 is located between positions B and C. - A
platen shear bar 65 is attached to the top ofplaten face 61.Platen shear bar 65 has a forward facing cuttingedge 66 and a plurality ofslots 67 which are aligned and communicate with channels 64.Slots 67 permit the introduction of tying members into channels 64 when the tying process is commenced as described below.Shear bar 65 will act to cut through and shear off any material deposited inchute 24 that does not fit withinhopper portion 14 asplaten 16 passes fromhopper portion 14 towardcompaction chamber 15. - A
stop plate 70 is attached across vertical members ofcompaction chamber frame 34 below the front ofhopper portion 14. Stopplate 70 is positioned such that it will lie beneath channels 64 inplaten face 61 whenplaten 16 is in position B. Ahorizontal rod 71 is attached across the bottom of floor beams 40 slightly forward ofstop plate 70 as shown. - As best seen in
FIG. 11 , atie guide mechanism 80 is attached to and operable on the underside ofhousing 11.Tie guide mechanism 80 comprises atransverse bar 81 and a plurality oftie push rods 82 attached to tietransverse bar 81 at one end and extending forwardly therefrom.Tie guide mechanism 80 is suspended beneathhousing 11 by means ofsuspension brackets 83 extending downwardly from the bottom ofhousing 11 and bearing pads attached tosuspension brackets 83, with two or more oftie push rods 82 riding on bearing pads as shown. The number oftie push rods 82 is equal to the number ofchannels 41 in thebottom portion 32 ofcompaction chamber 15.Tie push rods 82 are aligned withchannels 41 such that onetie push rod 82 is operable within and along length of eachchannel 41. The length oftie push rods 82 is greater than the length ofcompaction chamber 15.Tie guide mechanism 80 is operable between a position D wherein the forward ends oftie push rods 82 are located slightly rearwardly of platen face 61 whenplaten 16 is in position B and a position E wherein the forward ends oftie push rods 82 extend forwardly of the front ofdoor 21.Tie guide mechanism 80 is moved between position D and position E by means of a rack andpinion mechanisms 85 wherein a rack is located on the underside of each of the outertie push rods 82 and engage a corresponding pinion rotatable on ashaft 86 attached to amotor 87. By operatingmotor 87 in a forward or backward manner, the rack andpinion mechanisms 85 will causetie guide mechanism 80 to move forward or backward. Rack andpinion mechanisms 85 is operable by conventional control means (either manual or automatic). - The forward end of each tie push
rod 82 is notched as at notches to engage a tie when a tie is inserted down through thechannels 55 inplaten face 61 as described below. - Operation of
tie guide mechanism 80 is best understood with reference toFIGS. 13 a to 13 c. Once a bale of compacted material is fully formed,platen 16 is returned to position B, whereby the bale is contained entirely withincompaction chamber 15. Abale tie wire 90 is inserted beneathframe 12 adjacent the front ofbaler 10 into each of theceiling channels 39 and each of the corresponding platen channels 64 untiltie wire 90 is stopped by coming into contact withstop plate 70. Once atie wire 90 is so inserted through all channels 64, rack andpinion mechanisms 85 are activated to movetie guide mechanism 80 forward from position D toward position E. Astie guide mechanism 80 is moved forwardly, notches in the forward end of each tie pushrod 82 engage thecorresponding tie wire 90 at a point slightly above its end and push it forwardly. As the ends oftie wires 90 move forward, the end oftie wires 90 come into contact withrod 71 which causes the ends oftie wires 90 to be bent back against themselves thereby securingtie wires 90 in corresponding notches whiletie wires 90 are threaded through the correspondingchannels 41 in thebottom portion 32 ofcompaction chamber 15. - Once
tie guide mechanism 80 is advanced to position E, the ends oftie wires 90 are manually advanced through the correspondingchannels 55 indoor 21 untiltie wires 90 completely encircle the bale.Tie wires 90 are then cut and the opposed ends wrapped or otherwise secured. When all tiewires 90 have been so secured,door 21 is opened by releasinglatch mechanism 22 andplaten 16 is activated to advance it from position B toward position C, thereby expelling the bale fromcompaction chamber 15. - While we have described the preferred embodiment of our invention, it will be evident to those skilled in the art that other embodiments may be possible within the scope of our invention.
Claims (9)
1. A baler tie feed apparatus for securing a bale of compacted material formed in a baler having a compaction chamber for receiving material to be compacted and having a top, bottom and sides, a platen movable from a rear position to a forward position for compacting material within the compaction chamber into a bale and a door operable between a closed position when the bale is being formed and an open position when the bale is being discharged from the baler, comprising:
(a) plurality of spaced channels defined in said top and bottom of said compaction chamber;
(b) a plurality of spaced channels defined in said platen, each of said platen channels being aligned with one of said spaced open channels in said top and bottom of said compaction chamber;
(c) a plurality of spaced channels defined in said door, each of said door channels being aligned with one of said channels in said top and bottom of said compaction chamber, whereby the aligned channels for a plurality of spaced channels surrounding a bale formed within said baler through which a plurality of bale ties may be inserted;
(d) a tie guide mechanism positioned beneath said compaction chamber having a plurality of tie engaging members, each of said tie engaging members being operable within said channels defined in said bottom of said compaction chamber and having a forward end defining means for engaging a tie, said tie guide mechanism being operable between a first position wherein said forward end of each of said tie guide members is positioned beneath one of said channels defined in said platen and a second position wherein said forward end of each of said tie guide members extends through one of said channels defined in said door; and
(e) means for moving said tie guide mechanism between said first position and said second position.
2. A baler tie feed apparatus according to claim 1 , wherein said means for moving said tie guide mechanism comprises a rack attached to one of said tie engaging members, a pinion engaging said rack and mounted on a shaft, and a motor operable to rotate said shaft.
3. A baler tie feed apparatus according to claim 1 , wherein said platen further comprises a shear member attached to the top of said platen, said shear member defining slots aligned with said channels.
4. A baler tie feed apparatus according to claim 1 , wherein said tie engaging means comprises a notch formed in said forward end of each of said tie engaging members.
5. A baler tie feed apparatus for securing a bale of compacted material formed in a baler comprising:
(a) a compaction chamber for receiving material to be compacted and having a top, bottom and sides, and a plurality of spaced channels defined in said top and bottom of said compaction chamber;
(b) a platen movable within said compaction chamber from a rear position to a forward position for compacting material within the compaction chamber into a bale, said platen defining a plurality of spaced channels, each of said channels of said platen being aligned with a channel in said top of said compaction chamber and with a channel in said bottom of said compaction chamber;
(c) a door attached to one end of said compaction chamber and being operable between a closed position and an open position, said door defining a plurality of spaced channels, each of said channels of said door being aligned with a channel in said top of said compaction chamber and with a channel in said bottom of said compaction chamber so as to define a plurality of continuous channels surrounding a bale formed within said compaction chamber;
(d) a tie guide mechanism positioned beneath said compaction chamber having a plurality of tie engaging members, each of said tie engaging members being operable within said channels defined in said bottom of said compaction chamber and having a forward end defining means for engaging a tie, said tie guide mechanism being operable between a first position wherein said forward end of each of said tie guide members is positioned beneath one of said channels defined in said platen and a second position wherein said forward end of each of said tie guide members extends through one of said channels defined in said door; and
(e) means for moving said tie guide mechanism between said first position and said second position.
6. A baler tie feed apparatus according to claim 5 , wherein said means for moving said tie guide mechanism comprises a rack attached to one of said tie engaging members, a pinion engaging said rack and mounted on a shaft, and a motor operable to rotate said shaft.
7. A baler tie feed apparatus according to claim 5 , wherein said platen further comprises a shear member attached to the top of said platen, said shear member defining slots aligned with said channels.
8. A baler tie feed apparatus according to claim 5 , wherein said tie engaging means comprises a notch formed in said forward end of each of said tie engaging members.
9. A baler tie feed apparatus for securing a bale of compacted material formed in a baler comprising:
(a) a compaction chamber for receiving material to be compacted and having a top, bottom and sides, and a plurality of spaced channels defined in said top and bottom of said compaction chamber;
(b) a platen movable within said compaction chamber from a rear position to a forward position for compacting material within the compaction chamber into a bale, said platen defining a plurality of spaced channels, each of said channels of said platen being aligned with a channel in said top of said compaction chamber and with a channel in said bottom of said compaction chamber, said platen having a shear member attached to the top of said platen, said shear member defining slots aligned with said channels;
(c) a door attached to one end of said compaction chamber and being operable between a closed position and an open position, said door defining a plurality of spaced channels, each of said channels of said door being aligned with a channel in said top of said compaction chamber and with a channel in said bottom of said compaction chamber so as to define a plurality of continuous channels surrounding a bale formed within said compaction chamber;
(d) a tie guide mechanism positioned beneath said compaction chamber having a plurality of tie engaging members, each of said tie engaging members being operable within said channels defined in said bottom of said compaction chamber and having a forward end defining a notch for engaging a tie, said tie guide mechanism being operable between a first position wherein said forward end of each of said tie guide members is positioned beneath one of said channels defined in said platen and a second position wherein said forward end of each of said tie guide members is positioned beneath one of said channels defined in said door; and
(e) a rack attached to one of said tie engaging members, a pinion engaging said rack and mounted on a shaft, and a motor operable to rotate said shaft.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US12/284,257 US7690297B1 (en) | 2008-09-22 | 2008-09-22 | Baler tie feed apparatus |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US12/284,257 US7690297B1 (en) | 2008-09-22 | 2008-09-22 | Baler tie feed apparatus |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| US20100071570A1 true US20100071570A1 (en) | 2010-03-25 |
| US7690297B1 US7690297B1 (en) | 2010-04-06 |
Family
ID=42036296
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US12/284,257 Expired - Fee Related US7690297B1 (en) | 2008-09-22 | 2008-09-22 | Baler tie feed apparatus |
Country Status (1)
| Country | Link |
|---|---|
| US (1) | US7690297B1 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2628591A3 (en) * | 2012-02-17 | 2017-11-22 | SIB Strautmann Ingenieurbüro GmbH | Press for manufacturing pressed bales, binding device and re-pressing device |
| EP3695960A1 (en) * | 2019-02-12 | 2020-08-19 | Bollegraaf Patents and Brands B.V. | Baling press and method of operating a baling press |
| US11141946B2 (en) * | 2018-08-02 | 2021-10-12 | Sebright Products, Inc. | Baling apparatus |
Families Citing this family (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US8490367B2 (en) * | 2008-03-03 | 2013-07-23 | H.W.J. Designs For Agribusiness, Inc. | Bagging assembly |
| WO2014144566A1 (en) | 2013-03-15 | 2014-09-18 | Cnh Industrial America Llc | Strapping system for agricultural implement |
| US11066201B2 (en) * | 2014-03-29 | 2021-07-20 | C & M Baling Systems, Inc. | Baling press for cotton gin trash and other biomass feedstock and methods of using the same |
| US10306839B2 (en) * | 2014-03-29 | 2019-06-04 | C & M Baling Systems, Inc. | Baling press for cotton gin trash and other biomass feedstock and methods of using the same |
| WO2015153300A1 (en) * | 2014-03-31 | 2015-10-08 | Cnh Industrial America Llc | Strapping system for agricultural implement |
| US10493714B2 (en) * | 2014-11-19 | 2019-12-03 | Hermann Schwelling | Lifting/ tipping device for emptying a collection container in a baling press, as well as baling press and method for filling the baling press |
| US10077125B2 (en) * | 2015-05-19 | 2018-09-18 | Charles Sidney Wildes | Bale tie-off accelerator chambers and methods |
| AU2017269405A1 (en) | 2016-05-27 | 2020-09-24 | Oneplus Systems Inc. | Techniques for optimally sensing full containers |
| US11304372B2 (en) | 2020-02-07 | 2022-04-19 | C & M Baling Systems, Inc. | Automatic bale strapping mechanism |
| US11623775B1 (en) | 2022-02-15 | 2023-04-11 | Accent Wire Holdings Llc | Multiple strapping device |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US228515A (en) * | 1880-06-08 | peters | ||
| US3528364A (en) * | 1968-07-25 | 1970-09-15 | Munro Systems Corp | Bale tying method and apparatus |
| US3827349A (en) * | 1972-04-28 | 1974-08-06 | W Gilman | Machine for conditioning waste material for recycling |
| US4232599A (en) * | 1978-10-19 | 1980-11-11 | J. V. Manufacturing & Welding, Inc. | Waste paper compacter with front access features |
| US4718336A (en) * | 1986-10-22 | 1988-01-12 | Cives Corp. | Modular automatic bale tier |
| US5699727A (en) * | 1994-12-24 | 1997-12-23 | Schwelling; Hermann | Method of manually tying bales in waste material presses |
| US5852969A (en) * | 1997-07-10 | 1998-12-29 | The United States Of America As Represented By The Secretary Of Agriculture | Device for reducing bale packaging forces |
| US7237477B1 (en) * | 2006-07-27 | 2007-07-03 | Anthony Fox | Compactor/baler with built-in supply storage |
-
2008
- 2008-09-22 US US12/284,257 patent/US7690297B1/en not_active Expired - Fee Related
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US228515A (en) * | 1880-06-08 | peters | ||
| US3528364A (en) * | 1968-07-25 | 1970-09-15 | Munro Systems Corp | Bale tying method and apparatus |
| US3827349A (en) * | 1972-04-28 | 1974-08-06 | W Gilman | Machine for conditioning waste material for recycling |
| US4232599A (en) * | 1978-10-19 | 1980-11-11 | J. V. Manufacturing & Welding, Inc. | Waste paper compacter with front access features |
| US4718336A (en) * | 1986-10-22 | 1988-01-12 | Cives Corp. | Modular automatic bale tier |
| US5699727A (en) * | 1994-12-24 | 1997-12-23 | Schwelling; Hermann | Method of manually tying bales in waste material presses |
| US5852969A (en) * | 1997-07-10 | 1998-12-29 | The United States Of America As Represented By The Secretary Of Agriculture | Device for reducing bale packaging forces |
| US7237477B1 (en) * | 2006-07-27 | 2007-07-03 | Anthony Fox | Compactor/baler with built-in supply storage |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2628591A3 (en) * | 2012-02-17 | 2017-11-22 | SIB Strautmann Ingenieurbüro GmbH | Press for manufacturing pressed bales, binding device and re-pressing device |
| US11141946B2 (en) * | 2018-08-02 | 2021-10-12 | Sebright Products, Inc. | Baling apparatus |
| EP3695960A1 (en) * | 2019-02-12 | 2020-08-19 | Bollegraaf Patents and Brands B.V. | Baling press and method of operating a baling press |
| NL2022562B1 (en) * | 2019-02-12 | 2020-08-27 | Bollegraaf Patents And Brands B V | Baling press and method of operating a baling press |
Also Published As
| Publication number | Publication date |
|---|---|
| US7690297B1 (en) | 2010-04-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7690297B1 (en) | Baler tie feed apparatus | |
| US4788901A (en) | Dead ended square baler | |
| US5247880A (en) | Horizontal baler with movable bottom support ejector | |
| CN105228440B (en) | System and method for packing crops material | |
| US7849790B2 (en) | Single ram baler | |
| CN105407705B (en) | System and method for removing crop material from a baler | |
| US3999476A (en) | Closed chamber baler | |
| US12311630B2 (en) | Bale press | |
| EP0178767B1 (en) | Charging door assembly for a baler | |
| CA1087028A (en) | Baler for unshredded material | |
| US4150613A (en) | Apparatus for baling hay or straw | |
| US3916781A (en) | Bale ejection system | |
| US4711078A (en) | Baler and process for making bales or for operating the baler | |
| US3929062A (en) | Closed chamber baler | |
| DE3448516C2 (en) | Bale press for compressing materials such as paper waste or the like into bales | |
| CA2986343A1 (en) | Baling press and method of pressing and tying bales in a baling press | |
| EP3573820A1 (en) | Bale press | |
| US4148253A (en) | Vertical closed chamber baler | |
| EP1418044A2 (en) | Press for miscellaneous scrap, such as paper | |
| CN119054519B (en) | Pasture hay bundling machine | |
| RU36794U1 (en) | HYDRAULIC PACKING PRESS | |
| DE2647473A1 (en) | BALER | |
| US4785730A (en) | Needle-protecting system for baler | |
| HK40032895A (en) | Bale press machine | |
| CN114902879A (en) | Ensiling bundling and film-coating integrated machine |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AS | Assignment |
Owner name: HARMONY ENTERPRISES, INC.,MINNESOTA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:SAGEN, STEPHEN W.;SCRABECK, STEVEN W.;REEL/FRAME:021609/0742 Effective date: 20080829 |
|
| REMI | Maintenance fee reminder mailed | ||
| LAPS | Lapse for failure to pay maintenance fees | ||
| STCH | Information on status: patent discontinuation |
Free format text: PATENT EXPIRED DUE TO NONPAYMENT OF MAINTENANCE FEES UNDER 37 CFR 1.362 |
|
| FP | Lapsed due to failure to pay maintenance fee |
Effective date: 20140406 |