Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Самарин Александр АлексеевичfiledCriticalСамарин Александр Алексеевич
Priority to UAU200800326UpriorityCriticalpatent/UA34251U/en
Publication of UA34251UpublicationCriticalpatent/UA34251U/en
Water boiler has body, furnace chamber and convection chamber connected to it with gas duct, water jacket and reservoir, with installed there branch pipes for supply of cold and discharge of hot water, respectively, flue pipe placed in the lower part of convection chamber and gas duct connected through convection chamber, at that furnace chamber has burner unit. Gas duct is placed in center of water boiler and is formed with vertical walls of water jacket in its upper part.