SU1535914A1 - Method of constructing hydraulic station with concrete dam - Google Patents
Method of constructing hydraulic station with concrete dam Download PDFInfo
- Publication number
- SU1535914A1 SU1535914A1 SU884400514A SU4400514A SU1535914A1 SU 1535914 A1 SU1535914 A1 SU 1535914A1 SU 884400514 A SU884400514 A SU 884400514A SU 4400514 A SU4400514 A SU 4400514A SU 1535914 A1 SU1535914 A1 SU 1535914A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- stage
- dam
- concrete
- construction
- spillway
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims description 7
- 238000010276 construction Methods 0.000 claims abstract description 15
- 238000004519 manufacturing process Methods 0.000 claims abstract description 5
- 238000006424 Flood reaction Methods 0.000 claims description 2
- 238000009434 installation Methods 0.000 abstract 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 5
- 230000004888 barrier function Effects 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 2
- 238000011144 upstream manufacturing Methods 0.000 description 2
- 241000190687 Gobius Species 0.000 description 1
- 238000003491 array Methods 0.000 description 1
- 244000309464 bull Species 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000013022 venting Methods 0.000 description 1
Landscapes
- Revetment (AREA)
Abstract
Изобретение относитс к гидротехническому строительству. Цель изобретени - упрощение производства работ, ускорение строительства и снижение его стоимости. При возведении гидроузла с бетонной плотиной водослив с широким порогом устраивают на участке плотины, возводимом в котловане второй очереди. После пропуска паводка надстраивают водослив бетонным массивом, содержащим донные и глубинные отверсти . Это обеспечивает возможность вести в котловане первой очереди после его осушени строительно-монтажные работы непрерывно, независимо от гидрологического режима реки. 7 ил.FIELD OF THE INVENTION The invention relates to hydraulic engineering. The purpose of the invention is to simplify the production of works, accelerate construction and reduce its cost. When erecting a hydropower station with a concrete dam, a weir with a wide threshold is arranged on the dam site erected in the second-trench pit. After skipping the flood, build up the spillway with a concrete massif containing bottom and deep holes. This provides the opportunity to carry out construction and installation work in the first-trench of the foundation pit continuously, regardless of the hydrological regime of the river. 7 il.
Description
Изобретение относитс к гидротехническому строительству, в частности к возведению сооружений энергетических гидроузлов с высокой бетонной плотиной, сооружаемых на многоводных реках с большой внутри годовой неравномерностью стока.The invention relates to hydraulic construction, in particular to the construction of structures for power plants with a high concrete dam, built on high-flow rivers with large annual flow irregularities.
Цель изобретени - дальнейшее упрощение производства работ, ускорение строительства и снижение его стоимости.The purpose of the invention is to further simplify the production of works, speed up construction and reduce its cost.
На фиг. 1 показан вид русловой части плотины энергетического гидроузла со стороны верхнего бьефа; на фиг. 2 - водослив с широким порогом на втором этапе возведени плотины, поперечный разрез; на фиг. 3 водослив , надстроенный массивом с донными и глубинными отверсти ми на третьем этапе оозведени плотины, поперечный разрез;,на фиг. А и 5 плотины по глубинному и лонному отверстием на четвертом этапе возведени сооружени , поперечные разрезы, соответственно; на фиг. 6 - разрез А-А на фиг. 3; на фиг.7 разрез Б-Б на фиг. 3.FIG. 1 shows a view of the channel part of the dam of an energy hydroelectric complex from the upstream side; in fig. 2 - weir with a wide threshold at the second stage of the dam construction, cross section; in fig. 3 a weir, built up with an array with bottom and deep holes in the third stage of the dam construction, a transverse section;, FIG. A and 5 of the dam along the deep and the orifice in the fourth stage of the erection of the structure, transverse sections, respectively; in fig. 6 shows section A-A in FIG. 3; FIG. 7 is a section on BB in FIG. 3
Способ осуществл ют следующим образом .The method is carried out as follows.
С помощью известных приемов ограждают перемычками часть русла реки, пропуска ее расход через оставшуюс часть живого сечени , и организует котлован первой очереди. В нем возвод т станционную асть плотины 1 с опережающим ростом ее верховой зоны, а также раздельный устой 2, в котором выполн ют донные водоспуски 3 оборудованные затворами известных типов.Using known techniques, bridging a part of the river bed, passing its flow through the remaining part of the living section, and organizing the first-stage excavation. In it, the station side of the dam 1 is erected with the advance growth of its upper zone, as well as a separate section 2, in which bottom outlets 3 are equipped with valves of known types.
СП СОJV CO
елate
СО ЈCO Ј
Далее в меженный период производ т перекрытие низководными перемычками суженной части русла, пропуска расходы реки через водоспуски 3, в котловане второй очереди возвод т водослив 4 с широким порогом до незатоп- л емой в межень отметки, фундаментную плиту 5, низовые бычки 6 с пазами 7 дл шандорных заграждений и плиту креплени 8 скалы в нижнем бьефе. I Под водосливом 4 устраивают галереи 9Then, in the low-flow period, low-water bridges of the narrowed part of the riverbed are overlapped, the river flow passes through the waterways 3, the weir 4 is erected in a trench of the second stage with a wide threshold to the bottom-free bottom, the base plate 5, downstream gobies 6 with grooves 7 for traverse obstacles and a fastening plate for 8 rocks in the downstream. I Under the weir 4 galleries arrange 9
Перечисленные работы производ т в течение двух межпаводковых сезонов с затоплением котлована при пропуске паводка.The above works were carried out during two interflood seasons with the flooding of the excavation at the skipping of the flood.
После пропуска через водослив паводка и понижени уровн воды в верхнем бьефе с помощью водоспусков 3 над водосливом и плитой 5 под защитой шандорного заграждени 10, опускаемого в пазы 7, бетонируют массив 11 с верховыми бычками 12, в которых устроены пазы 13- Внутри массива 11 устраивают донные отверсти 1 и вер- ховые части глубинных отверстий 15, имеющие одинаковые поперечные сечени . После возведени массива 11 из галереи 9 устраивают цементационную завесу 16 и дренаж основани 17. В котловане первой очереди в течение круглого года ведут работы по возведению станционной плотины до отметок, незатопл емых при пропуске следующего паводка, и приступают к строительно- монтажным работам на здании ГЭС (не показано). Очередной паводок пропускают через отверсти и 15, водоспуски 3, а также поверх массива 11 через проран 18. После пропуска павод ка перекрывают отверсти и 15 с верховой стороны затворами 19, ас низовой стороны шандорным заграждением 10. Выполн ют низовую часть глубинных отверстий 15, бетониру массивы трамплинов 20 и носок 21 эксплуатационного водослива 22. Внутри носка 21 устраивают затворную камеру 23 и помещение дл приводов , монтируют рабочие сегментные затворы 25 и ремонтные затворы 26. Возвод т следующий рус плотины 27 с доведением его верховой части до пусковых отметок с оставлением прорана 28. Производ т заделку донных отверстий , В котловане первой очереди подготав5After passing through the flood spillway and lowering the water level in the upstream by using the ventings 3 above the spillway and stove 5 under the protection of the barbed barrier 10, lowered into the grooves 7, concrete array 11 is mounted with riding bulls 12, in which grooves 13 are arranged. the bottom openings 1 and the top portions of the deep openings 15 having the same cross section. After the erection of the massif 11 from the gallery 9, they arrange the cementing curtain 16 and the drainage of the base 17. In the first-trench of the first stage, the station dam is erected to the marks not filled by the next flood, and the construction work on the hydroelectric power station is started (not shown). The next flood is passed through the openings and 15, the outlets 3, and also over the array 11 through the aperture 18. After passing the flood, the openings and 15 on the upper side are closed by the gates 19, and the lower side is covered with a barrier 10. The bottom part of the deep openings 15 are completed, concrete the arrays of springboards 20 and the toe 21 of the operational weir 22. Inside the sock 21 arrange the breech chamber 23 and the room for the drives, assemble the working segment closures 25 and the repair breeches 26. The next Russian dam 27 is erected with its top the second part to launch marks leaving a closure channel 28. Manufact.:WEEKE m terminations bottom opening, in the first phase pit podgotav5
оabout
5five
ливают к вводу в эксплуатацию первоочередные агрегаты с водоприемниками 29 в станционной плотине 1.First-priority units with water intakes 29 in the station dam 1 are commissioned for commissioning.
Возвод т плотину по всей длине напорного фронта до незатопл емых отметок при пропуске наводка. Пропуск очередного паводка производ т через глубинные отверсти 15, водоспуски 3, первоочередные агрегаты с водоприемниками 29 и при необходимости через проран 28.Raise the dam along the entire length of the pressure front to the unsinkable marks when passing the tip. The passage of the next flood is made through the deep holes 15, the outlets 3, the primary aggregates with the water intakes 29 and, if necessary, through the blockhole 28.
Далее, примен те же приемы, достраивают плотину до проектных отметок , выполн ют работы по устройству эксплуатационного водослива 22, после этого закрывают водоспуски 3 и глубинные отверсти 15 и по мере готовности ввод т в эксплуатацию агрегаты с водоприемниками 30.Further, using the same methods, they complete the dam to the design marks, carry out works on the device of the production weir 22, then the outlets 3 and the deep holes 15 are closed and, as soon as they are ready, commissioned units with water intakes 30.
Применение данного способа позволит по сравнению с проектом не менее , чем на 1 год ускорить ввод в эксплуатацию первоочередных агрегатов ГЭС на промежуточном напоре и получить значительный экономический эффект за счет стоимости дополнительно выработанной электроэнергии.The use of this method will allow, in comparison with the project for at least 1 year, speed up the commissioning of high-priority hydroelectric units at an intermediate head and obtain a significant economic effect due to the cost of the additionally generated electricity.
30thirty
ФормулаFormula
зобретени acquisitions
5five
00
5five
00
5five
Способ возведени гидроузла с бетонной плотиной, включающий поэтапное возведение сооружений с поочередным ограждением котлованов в русле перемычками и поэтапный пропуск строительных расходов, при этом строительные расходы на первом этапе пропускают через стесненное русло, на втором этапе - через донные водоспуски в раздельлом устое и водослив с широким порогом после перекрыти русла , на последующих этапах - через упом нутые водоспуски, донные и глубинные отверсти , а во врем паводков - также через прораны в недостроенной плотине, отличающий- с тем, что, с целью упрощени производства работ, ускорени строительства и снижени его стоимости, водослив устраивают на участке плотины, возводимой в котловане второй очереди , а после пропуска паводка надстраивают водослив бетонным массивом, содер чащим донные и глубинные отверсти .The method of erecting a hydropower plant with a concrete dam, including the phased construction of structures with alternate fencing of trenches in the bed of bridges and phased skipping of construction costs, while construction costs are passed through the constrained bed at the first stage, at the second stage through the bottom outlets in the section and the spillway with a wide after the channel is cut off, at subsequent stages through the above-mentioned outlets, bottom and deep holes, and during floods, also through holes in the unfinished dam , with the fact that, in order to simplify production, speed up construction and reduce its cost, spillway is arranged on the dam site erected in the second stage of the foundation pit, and after skipping the flood, overflow the spillway with a concrete mass containing bottom and deep holes.
--
А 5A 5
Фие.1Phie.1
I-Iujr-l (Второй этап)I-Iujr-l (Second Stage)
зшwow
хх мл хх лTA 0 5бxx ml xx lTA 0 5b
fe xLJI/fe xLJI /
л w .l w.
V Ч|д- /V./5V h | d- /V./5
Г7G7
8 I8 I
IfIf
А Л Л /f ЛГ A L L / f LG
I-I иЛ-П (третий этап)I-I IL-P (third stage)
rvrv
Й/«.3Y / ". 3
Ј#. &/л;...у.Ј #. & / l; ... y.
л ...,l ...
tftf
2121
f. . . . .. f .f. . . . .. f.
..-. I : -:/V..-. I: -: / V
У Г ..f. G ... f.
. . Л . I . . L I
g i .,-fg i., - f
.Il : .- - У .. Г .Il: .- - Do .. T
x АТл у Y А л л Х/Л/TL x ATL y Y A L H / L / TL
/J / J
7575
f5 2(7f5 2 (7
J-JJ j
A«.vA ".v
(Четвертый этап)(Fourth stage)
..у...- -сХ ..y ...- -cX
( - .У.: .y.-.v. V-; i-.V. ;. (- .U .: .y .-. V. V-; i-.V.;.
4v V -|ff;ft-: ::Q:S r-- 4 4v V - | ff; ft-: :: Q: S r-- 4
J А и J a and
WW
/J / J
7575
A«.vA ".v
Фие.5FI.5
В-БVb
14 714 7
шшшшшshhhh
ьx4iiilx4iii
. :-.Учу .у1 5. : -. I teach .u1 5
:. .;-:-..:. .; -: - ..
.-.-..-.-.
Л(L (
k/v k / v
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU884400514A SU1535914A1 (en) | 1988-03-31 | 1988-03-31 | Method of constructing hydraulic station with concrete dam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU884400514A SU1535914A1 (en) | 1988-03-31 | 1988-03-31 | Method of constructing hydraulic station with concrete dam |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| SU1535914A1 true SU1535914A1 (en) | 1990-01-15 |
Family
ID=21364686
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SU884400514A SU1535914A1 (en) | 1988-03-31 | 1988-03-31 | Method of constructing hydraulic station with concrete dam |
Country Status (1)
| Country | Link |
|---|---|
| SU (1) | SU1535914A1 (en) |
-
1988
- 1988-03-31 SU SU884400514A patent/SU1535914A1/en active
Non-Patent Citations (1)
| Title |
|---|
| Гогоберидзе Т.П. строительных расходов ческос строительство, с. 50-5. Авторское свидетельство СССР fr 116162 4, кл. Е 02 В 1/00, 1983. ( СПОСОБ ВОЗВЕДЕНИЯ ГИДРОУЗЛА С БЕТОННОЙ ПЛОТИНОЙ и др. Пропуск - Энергети- 1975, Н1 12, * |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105603943A (en) | Tunnel type nature fishway imitated fish-barring lifting device and method | |
| CN105735210B (en) | Layout structure of tunnel type imitation natural fishway combined with fish gate and its use method | |
| CN105464058B (en) | Tunnel formula imitates nature fish pass | |
| SU1535914A1 (en) | Method of constructing hydraulic station with concrete dam | |
| CN105484213B (en) | Tunnel formula multiple exit imitates nature fish pass | |
| CN105568943B (en) | A kind of river truss-like draws anchor means for preventing driftage and its construction method | |
| CN205348128U (en) | Nature fishway is imitated to tunnel formula multiple exit | |
| SU937600A1 (en) | Method of constructing a hydro-electric installation with concrete dam and dam-adjoining power station | |
| SU1055799A1 (en) | Method of erecting a hydraulic structure with concrete dam | |
| SU1161624A1 (en) | Method of constructing hydraulic complex with concrete dam | |
| CN205475148U (en) | River course truss -like draws anchor to prevent floating device | |
| SU1583511A1 (en) | Method of constructing a hydraulic power station | |
| SU1162893A1 (en) | Dam construction method | |
| RU2805419C1 (en) | Device for blocking bed of small river | |
| SU1330237A1 (en) | Method of constructing hydraulic complex with concrete dam | |
| CN213538823U (en) | Novel ecological water storage system | |
| Van den Bosch | Structures for water control and distribution | |
| SU1752859A1 (en) | Spillway dam | |
| SU1291653A1 (en) | Method of passing construction flaws under a dam | |
| SU1124087A1 (en) | Spillway tunnel of high-head earth-filled dam | |
| SU1308676A1 (en) | Method of constructing integrated water power development on a river | |
| US400804A (en) | Sub-river tunnel | |
| SU1397591A1 (en) | Method of constructing a dam | |
| SU1036834A1 (en) | Method for erecting dam | |
| RU2016966C1 (en) | Method for drain siphon laying |