SU1573079A1 - Method of washing tailing pond - Google Patents
Method of washing tailing pond Download PDFInfo
- Publication number
- SU1573079A1 SU1573079A1 SU884462708A SU4462708A SU1573079A1 SU 1573079 A1 SU1573079 A1 SU 1573079A1 SU 884462708 A SU884462708 A SU 884462708A SU 4462708 A SU4462708 A SU 4462708A SU 1573079 A1 SU1573079 A1 SU 1573079A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- cards
- section
- dams
- tier
- filling
- Prior art date
Links
- 238000005406 washing Methods 0.000 title claims abstract 5
- 238000000034 method Methods 0.000 title claims 2
- 239000002002 slurry Substances 0.000 claims abstract 3
- 238000005516 engineering process Methods 0.000 claims abstract 2
- 230000015572 biosynthetic process Effects 0.000 claims 3
- 238000010276 construction Methods 0.000 claims 1
- 238000007599 discharging Methods 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 1
- 238000000926 separation method Methods 0.000 abstract 2
Landscapes
- Separation Of Solids By Using Liquids Or Pneumatic Power (AREA)
Abstract
Изобретение относитс к гидротехническому строительству. Цель изобретени - упрощение технологии работ. Хвостохранилище 1 заполн ют посекционно. Создание секций начинают с самой дальней от водосбросного колодца 3, причем каждую последующую секцию создают после заполнени (замыва) предыдущей. Секцию выполн ют в виде смежных карт 5 и 6 путем намыва из хвостов двух дамб - отсечной 7 и разделительной 8. Перва дамба отсекает секцию от остальной емкости хвостохранилища, втора раздел ет ее на карты. Заполнение осуществл ют на полную высоту из выпусков распределительного пульповода, расположенного вдоль разделительной дамбы 8, путем поочередного замыва каждого руса карт с последующим возведением отсечной и разделительной дамб следующего руса из намытых хвостов. 5 ил.FIELD OF THE INVENTION The invention relates to hydraulic engineering. The purpose of the invention is to simplify the work technology. Tailing 1 is filled section by section. The creation of sections starts from the farthest from the spillway well 3, and each subsequent section is created after filling (closing) of the previous one. The section is made in the form of contiguous cards 5 and 6 by washing out the tailings of two dams - cut-off 7 and dividing 8. The first dam cuts off the section from the rest of the tailing tank, the second splits it into cards. Filling is carried out to the full height from the outlets of the distribution slurry line located along separation dam 8 by alternately closing each tier of cards with the subsequent erection of the cut-off and separation dams of the next tier from the washed tailings. 5 il.
Description
7 6 777 6 77
Фиг. 2FIG. 2
7 9 щ к7 9 u to
4four
//
1one
11eleven
Фиг.33
Фиг ЛFIG L
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU884462708A SU1573079A1 (en) | 1988-07-18 | 1988-07-18 | Method of washing tailing pond |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU884462708A SU1573079A1 (en) | 1988-07-18 | 1988-07-18 | Method of washing tailing pond |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| SU1573079A1 true SU1573079A1 (en) | 1990-06-23 |
Family
ID=21390691
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SU884462708A SU1573079A1 (en) | 1988-07-18 | 1988-07-18 | Method of washing tailing pond |
Country Status (1)
| Country | Link |
|---|---|
| SU (1) | SU1573079A1 (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2157869C2 (en) * | 1997-01-14 | 2000-10-20 | АО Красноярский проектно-изыскательский институт "Гидропроект" | Sludge pond |
| RU2160339C2 (en) * | 1997-01-14 | 2000-12-10 | АО Красноярский проектно-изыскательский институт "Гидропроект" | Method for disposal of enterprise grain wastes within area occupied by long time waste-storage pond |
| RU2275458C1 (en) * | 2004-08-10 | 2006-04-27 | Открытое Акционерное общество "Красноярский проектно-изыскательский институт "Гидропроект" | Gully two-stage slurry dump for granular industrial waste |
| RU2338029C2 (en) * | 2006-11-15 | 2008-11-10 | Общество с ограниченной ответственностью "Русская инжиниринговая компания" | Two-stage joist-ravine disposal area of industrial enterprises grainy waste |
| CN101838992A (en) * | 2010-06-23 | 2010-09-22 | 贵阳铝镁设计研究院 | Method for dry-method compatibilization of valley-type wet-method red dump site |
| CN101851926A (en) * | 2010-06-23 | 2010-10-06 | 贵阳铝镁设计研究院 | Method for carrying out dry-method capacity expansion in mountainside wet-process red mud disposal site |
| CN104831678A (en) * | 2015-01-30 | 2015-08-12 | 王健 | Ecological restoration method for tailing depot reclamation after tailing depot closure |
| CN108643132A (en) * | 2018-06-29 | 2018-10-12 | 长江勘测规划设计研究有限责任公司 | The grinding concrete structure and its construction method of composite pulp material are injected in rock ballast material |
| RU2808151C1 (en) * | 2023-05-04 | 2023-11-24 | федеральное государственное бюджетное образовательное учреждение высшего образования "Иркутский национальный исследовательский технический университет" (ФГБОУ ВО "ИРНИТУ") | Method for stacking concentration tailings |
-
1988
- 1988-07-18 SU SU884462708A patent/SU1573079A1/en active
Non-Patent Citations (1)
| Title |
|---|
| Авторское свидетельство СССР № 685752, кл. Е 02 В 7/06, 1977. Авторское свидетельство СССР № 1052614, кл. Е 02 В 7/06, 1981. * |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2157869C2 (en) * | 1997-01-14 | 2000-10-20 | АО Красноярский проектно-изыскательский институт "Гидропроект" | Sludge pond |
| RU2160339C2 (en) * | 1997-01-14 | 2000-12-10 | АО Красноярский проектно-изыскательский институт "Гидропроект" | Method for disposal of enterprise grain wastes within area occupied by long time waste-storage pond |
| RU2275458C1 (en) * | 2004-08-10 | 2006-04-27 | Открытое Акционерное общество "Красноярский проектно-изыскательский институт "Гидропроект" | Gully two-stage slurry dump for granular industrial waste |
| RU2338029C2 (en) * | 2006-11-15 | 2008-11-10 | Общество с ограниченной ответственностью "Русская инжиниринговая компания" | Two-stage joist-ravine disposal area of industrial enterprises grainy waste |
| CN101838992A (en) * | 2010-06-23 | 2010-09-22 | 贵阳铝镁设计研究院 | Method for dry-method compatibilization of valley-type wet-method red dump site |
| CN101851926A (en) * | 2010-06-23 | 2010-10-06 | 贵阳铝镁设计研究院 | Method for carrying out dry-method capacity expansion in mountainside wet-process red mud disposal site |
| CN101851926B (en) * | 2010-06-23 | 2014-03-12 | 贵阳铝镁设计研究院有限公司 | Method for carrying out dry-method capacity expansion in mountainside wet-process red mud disposal site |
| CN101838992B (en) * | 2010-06-23 | 2014-03-12 | 贵阳铝镁设计研究院有限公司 | Method for dry-method compatibilization of valley-type wet-method red dump site |
| CN104831678A (en) * | 2015-01-30 | 2015-08-12 | 王健 | Ecological restoration method for tailing depot reclamation after tailing depot closure |
| CN108643132A (en) * | 2018-06-29 | 2018-10-12 | 长江勘测规划设计研究有限责任公司 | The grinding concrete structure and its construction method of composite pulp material are injected in rock ballast material |
| CN108643132B (en) * | 2018-06-29 | 2021-01-26 | 长江勘测规划设计研究有限责任公司 | Rolled concrete structure with composite slurry injected into stone slag material and construction method thereof |
| RU2808151C1 (en) * | 2023-05-04 | 2023-11-24 | федеральное государственное бюджетное образовательное учреждение высшего образования "Иркутский национальный исследовательский технический университет" (ФГБОУ ВО "ИРНИТУ") | Method for stacking concentration tailings |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| SU1573079A1 (en) | Method of washing tailing pond | |
| SU1778218A1 (en) | Method for erection of hydraulic mine dump | |
| Sissons | Sub‐glacial stream erosion in Southern Northumberland | |
| SU1730346A1 (en) | Method for storing dressing waste in tailing dump | |
| RU2016163C1 (en) | Method of underwater formation of silting structure layer | |
| SU1030491A1 (en) | Twin water lock | |
| SU1663098A1 (en) | Method for soil washing up | |
| SU866033A1 (en) | Method of constructing hydraulic-fill structures | |
| SU1740672A1 (en) | Ore storage for hydraulic production | |
| RU135329U1 (en) | INTEGRATED STRUCTURE | |
| SU1682442A1 (en) | Method for washing up soil | |
| SU1507903A1 (en) | Method of constructing hydraulically-deposited structure | |
| SU1698354A1 (en) | Method of erecting weirs | |
| SU1629375A1 (en) | Method for hydraulic filling of structures | |
| SU1134664A1 (en) | Method of hydraulic filling of hydraulic structure | |
| SU1458483A1 (en) | Method of erecting earth structure | |
| SU1442598A1 (en) | Method of hydraulic filling of earth structure | |
| SU889784A1 (en) | Method of erecting hydraulically filled structures in water ducts | |
| SU1155663A1 (en) | Method of constructing a tail pond | |
| SU1488385A1 (en) | Chart of hydraulic deposition of a dam and method of its deposition | |
| SU1714020A1 (en) | Hydraulic filling method | |
| SU1209752A1 (en) | Method of erecting structures of rocky soil | |
| SU1271928A1 (en) | Method of constructing tails storage | |
| SU1498882A1 (en) | Method of hydraulic deposition of narrow-profile structure | |
| SU1528845A1 (en) | Method of storing hydraulically deposited rock |