SU1467181A1 - Method of working benches - Google Patents
Method of working benches Download PDFInfo
- Publication number
- SU1467181A1 SU1467181A1 SU874276570A SU4276570A SU1467181A1 SU 1467181 A1 SU1467181 A1 SU 1467181A1 SU 874276570 A SU874276570 A SU 874276570A SU 4276570 A SU4276570 A SU 4276570A SU 1467181 A1 SU1467181 A1 SU 1467181A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- rocks
- collapse
- block
- rock
- height
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims description 3
- 239000011435 rock Substances 0.000 claims abstract description 23
- 238000009412 basement excavation Methods 0.000 claims abstract description 6
- 238000005065 mining Methods 0.000 claims abstract description 4
- 239000002689 soil Substances 0.000 claims abstract description 4
- 238000012958 reprocessing Methods 0.000 claims 1
- 238000005422 blasting Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000004880 explosion Methods 0.000 description 1
Landscapes
- Earth Drilling (AREA)
Abstract
Изобретение относитс к горной промьшшенности. Цель изобретени - обеспечение безопасных условий работы при отработке развалов пород, превышающих по высоте предельно допустимые дл экскавационного оборудовани . Производ т взрьшную отработку уступа с разделением развала породы на под- уступы. Развал пород, превьшающий предельно допустимую высоту по условию безопасности, отрабатьшают с нижнего подуступа. После отработки верхнего подуступа перемещают породу-очередного блока на нижний подуступ взрьюом. Отрабатьшают объединенный развал породы с почвы уступа до высо- .ты, не превьшающей предельно допусти- мую по условию отработки объединенного развала пород в указанном блоке, а затем отрабатьшают оставшуюс часть g развала высотой, превышающей предельно допустимую, с разделением на под- уступы.This invention relates to the mining industry. The purpose of the invention is to provide safe working conditions when working out rock breaks that exceed the maximum permissible for excavation equipment. The recessing of the ledge is carried out with the division of the collapse of the rock into the steps. The collapse of rocks, exceeding the maximum permissible height according to the condition of safety, is removed from the lower sub-approach. After working out the upper sub-step, the rock is transferred from the next block to the lower sub-stem. Combine the collapse of the rock from the scarp soil to a height that does not exceed the maximum allowable condition for working out the combined collapse of rocks in the specified block, and then work out the remaining part of the c collapse with a height exceeding the maximum allowable, divided into sub-steps.
Description
Изобретение относитс к горной промышленности и может быть использова- но при открытой разработке полезных ископаемых.The invention relates to the mining industry and can be used in open pit mining.
Цель изобретени - обеспечение безопасных условий работы при разработке развалов пород, превышающих по высоте предельно допустимые дл экскавационного оборудовани . The purpose of the invention is to provide safe working conditions in the development of rock breaks that exceed the maximum permissible for excavation equipment.
Способ осуществл ют следующим образом .The method is carried out as follows.
Разработку уступа осуществл ют блоками. Производ т буровзрьтные работы с формированием развала породы, затем взорванную породу блока в зонах с допустимой высотой развала по условию безопасной работы экскавационного оборудовани разрабатьшают забоем на всю высоту развала.The development of the ledge is carried out in blocks. Drilling and blasting operations are carried out with the formation of rock camber, then the rock that has been blasted in the block with permissible camber height, according to the condition of safe operation of the excavation equipment, is slaughtered to the full camber height.
При перемещении забо в зоны с высотой развала, превышающей предельно допустимую по условию безопасности. Производ т разделение развала на верхний и нижний подуступы. Отработ- ку развала породы производ т с нижнего подуступа. После отработки верхнего подуступа производ т буровзрывные работы на следующем, за отрабо- танным, блоке. Перемещают взрывом породу блока на нижний псдуступ и формируют объединенньш развал породы. Объединенную таким образом породу развала отрабатывают забо ми с почвы уступа до высоты развала, не превы4When moving the bottom in zones with a camber height exceeding the maximum permissible according to the condition of safety. The camber is divided into upper and lower access points. The development of rock collapse was carried out from the lower sub-step. After the upper sub-stage has been worked out, the drilling and blasting operations are carried out on the next, after the finished block. The rock of the block is moved by the explosion to the lower level and forms the combined camber of the rock. The collapse rock combined in such a way is worked off from the ledge soil to the collapse height, not exceeding 3
сь is smiling
; шающей предельно допустимую по усло- в ю безопасности рабоЛт экскавацион- ного оборудовани , а породу развала отрабатьшаемого блока в зонах с высо- той, превьшающей предельно допустимую , отрабатывают с разделением ра з- вала на пОдуступы в аналогичном по- :р дке.; The maximum permissible safety of working excavation equipment, and the rock of the collapse of the working block in areas with a height exceeding the maximum permissible, is worked out by dividing the memory into equal parts in a similar order.
::
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU874276570A SU1467181A1 (en) | 1987-07-06 | 1987-07-06 | Method of working benches |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU874276570A SU1467181A1 (en) | 1987-07-06 | 1987-07-06 | Method of working benches |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| SU1467181A1 true SU1467181A1 (en) | 1989-03-23 |
Family
ID=21316470
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SU874276570A SU1467181A1 (en) | 1987-07-06 | 1987-07-06 | Method of working benches |
Country Status (1)
| Country | Link |
|---|---|
| SU (1) | SU1467181A1 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2208221C2 (en) * | 2001-07-18 | 2003-07-10 | ОАО "Восточный научно-исследовательский горнорудный институт" | Method for selective mining extraction of qualitative mineral resource in open pit |
| RU2511330C2 (en) * | 2012-07-16 | 2014-04-10 | Федеральное государственное бюджетное учреждение науки ИНСТИТУТ ПРОБЛЕМ КОМПЛЕКСНОГО ОСВОЕНИЯ НЕДР РОССИЙСКОЙ АКАДЕМИИ НАУК (ИПКОН РАН) | Method for large-scale explosive destruction of mine rock masses of complex structure for selective extraction of mineral deposit at open-pit mining |
-
1987
- 1987-07-06 SU SU874276570A patent/SU1467181A1/en active
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2208221C2 (en) * | 2001-07-18 | 2003-07-10 | ОАО "Восточный научно-исследовательский горнорудный институт" | Method for selective mining extraction of qualitative mineral resource in open pit |
| RU2511330C2 (en) * | 2012-07-16 | 2014-04-10 | Федеральное государственное бюджетное учреждение науки ИНСТИТУТ ПРОБЛЕМ КОМПЛЕКСНОГО ОСВОЕНИЯ НЕДР РОССИЙСКОЙ АКАДЕМИИ НАУК (ИПКОН РАН) | Method for large-scale explosive destruction of mine rock masses of complex structure for selective extraction of mineral deposit at open-pit mining |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| SU1467181A1 (en) | Method of working benches | |
| ES8503401A1 (en) | In situ leaching process. | |
| RU95119561A (en) | METHOD FOR DEVELOPING MINERAL DEPOSITS | |
| RU94028322A (en) | Well completion method | |
| SU1337517A1 (en) | Method of combined underground/open mining of coal beds | |
| SU1257221A1 (en) | Method of mining ore bodies | |
| RU2060390C1 (en) | Method for stage excavation of deep open pits | |
| SU492662A1 (en) | Method for developing steeply dipping ore bodies | |
| SU1620629A1 (en) | Method of safeguarding a mine working | |
| SU934052A1 (en) | Method of starting a sloping coal bed by entry-driving set | |
| SU815298A2 (en) | Method of conducting stripping work | |
| ATE72480T1 (en) | PROCESS FOR BUILDING A TUNNEL OR ADIBE AND TUNNEL BORING MACHINE FOR CARRYING OUT THE PROCESS. | |
| SU1460260A1 (en) | Method of mining an open pit | |
| SU595475A1 (en) | Method of breaking chutes in well | |
| SU783472A1 (en) | Method of solid rood control | |
| SU909176A1 (en) | Method of working thin and medium-thick coal beds | |
| SU1295005A1 (en) | Method of converting shock-hazardous rock body into shock-safe state | |
| SU848557A1 (en) | Wedgeless method of drilling multibore wells | |
| SU636391A1 (en) | Mineral winning method | |
| SU896957A1 (en) | Method of making cutting-off slot | |
| SU983273A1 (en) | Method of protecting a preparatory working | |
| SU1313999A1 (en) | Working member for sinking holes | |
| SU1686183A1 (en) | Method of development and mining of seams with entry pillars recovered | |
| SU1578335A1 (en) | Method of mining seams of useful mineral with poorly caving roof | |
| SU1564351A1 (en) | Method of controlling mining pressure |