SU1273562A1 - Method of safeguarding mine workings - Google Patents

Method of safeguarding mine workings Download PDF

Info

Publication number
SU1273562A1
SU1273562A1 SU853929959A SU3929959A SU1273562A1 SU 1273562 A1 SU1273562 A1 SU 1273562A1 SU 853929959 A SU853929959 A SU 853929959A SU 3929959 A SU3929959 A SU 3929959A SU 1273562 A1 SU1273562 A1 SU 1273562A1
Authority
SU
USSR - Soviet Union
Prior art keywords
wells
production
slab
auxiliary
reinforcing
Prior art date
Application number
SU853929959A
Other languages
Russian (ru)
Inventor
Анатолий Архипович Пятаченко
Николай Кузьмич Клишин
Геннадий Алексеевич Аверин
Юрий Филиппович Савенко
Original Assignee
Коммунарский горно-металлургический институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Коммунарский горно-металлургический институт filed Critical Коммунарский горно-металлургический институт
Priority to SU853929959A priority Critical patent/SU1273562A1/en
Application granted granted Critical
Publication of SU1273562A1 publication Critical patent/SU1273562A1/en

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

Изобретение относитс  к горной промьшленности и позвол ет повысить надежность охраны горных выработок (Б) и уменьшить объемы проходки вспомогательных Б. Дл  этого по пласту параллельно охран емой В 1 провод т вспомогательную Б 2. Над Б 1 ниже разгрузочных скважин (С) 4 создают плиту перекрыти  путем бурени  из Б 2 дополнительного р да параллельных С 3, установки в них армирующих элементов и нагнетани  под давлением укрепл ющего раствора 7. При создании плиты перекрыти  между ней и Б 1 формируют породную подушку, преп тствующую самообрушению пород кровли. До набора проектной прочности укрепл ющего раствора плиты перекрыти  выше нее в границах площади разгрузки бус $ р т параллельные разгрузочные С 3 с последуюш им разбуриванием их через (Л одну С 5 армирующих элементов большеThe invention relates to the mining industry and allows to increase the reliability of protection of mine workings (B) and reduce the penetration volumes of auxiliary B. To do this, an auxiliary B 2 is conducted along the formation guarded in parallel B 1. A slab is created below B 1 below relief wells (C) 4 overlap by drilling from B 2 an additional row of parallel C 3, installing reinforcing elements in them and forcing a reinforcing solution 7 under pressure. When creating a slab between it and B 1, they form a rock pad that prevents self-penetration usheniyu roof rocks. Before the design strength of the reinforcement mortar is obtained, the slabs of the slab above it, within the unloading area of the beads, are parallel C 3 unloading, followed by drilling them through (L one C 5 reinforcing elements are more

Description

го диаметра. Созданна  монолитна  армированна  плита своими концами опираетс  на угольные целики и выполн ет роль перекрыти . Бурение разгрузочных С снижает нагрузку от пород основной кровли и смещает максимум опорного давлени  вглубь массива. 1 ил.th diameter. The created monolithic reinforced plate with its ends rests on coal pillars and performs the role of overlapping. Drilling offloading C reduces the load on the rocks of the main roof and shifts the maximum of the reference pressure into the bulk. 1 il.

Claims (1)

Изобретение относитс  к горной промьшшенности и может быть использо вано дл  охраны горных выработок при разработке угольных пластов. Цель изобретени  - повышение надежности охраны горных выработок и уменьшение объемов проходки вспомога тельных выработок. На фиг.1 изображена схема располо жени  охран емой и вспомогательной горных выработок, разгрузочных скважин , монолитна  армированна  плита (заштрихованна  зона); на фиг.2 схема расположени  разгрузочных сква жин и штанг с раствором, укрепл ющих породы непосредственной кровли. На фиг.1 и 2 обозначены охран ема  выработка 1, вспомогательна  выработка 2,скважины 3-5,армирующие элементы 6, укрепл ющий раствор 7. Способ осуществл ют следующим образом . Параллельно охран емой выработке 1 провод т вспомогательную выработку 2,из которой бур т в кровле над выработкой дополнительный р д скважин 3.Нри этом между скважинами 3 и выработкой 1 формируют породную подушку , мощность которой должна быть достаточной , чтобы преп тствовать самообрушению пород непосредственной кровли. В скважинах 3 размещают арми рующие элементы 6 (из труб, арматуры катанов и т.д.) на всю длину скважин и нагнетают в скважины под давлением укрепл юищй раствор 7 (цементный раствор), в результате чего создают над выработкой 1 плиту перекрыти . До набора проектной прочности укрепл ющего раствора плиты перекрыти  вьш1е нее бур т разгрузочные скважины 4 с последующим разбуриванием их через одну скважинами 5 большего диаметра . Длина скважин зависит от угла их наклона и ширины планируемой зоны разгрузки, котора  равна ширине охран емой выработки и ширине двух целиков по бокам выработки. Созданна  монолитна  армированна  плита выполн ет роль перекрыти , своими концами опира сь на угольные целики. Формула изобретени  Способ охраны горных выработок, включающий проведение по пласту вспомогательной выработки, бурение из нее над охран емой выработкой разгрузочных параллельных скважин в границах площади разгрузки и разбуривание разгрузочных скважин через одну скважинами большего диаметра, отличающий с   тем,что, с целью повышени  надежности охраны горных выработок и уменьшени  объемов проходки вспомогательных выработок, над охран емой выработкой ниже разгрузочных скважин создают плиту перекрыти  бурением из вспомогательной выработки дополнительного р да параллельных скважин, в которые устанавливают армирующие элементы и производ т нагнетание под давлением укрепл ющих растворов, причем при создании плиты перекрыти  между ней и охран емой выработкой формируют породную подушку, а разгрузочные скважины бур т до набора проектной прочности укрепл ющего раствора плиты перекрыти  .The invention relates to the mining industry and can be used to protect mine workings in the development of coal seams. The purpose of the invention is to increase the reliability of protection of mine workings and reduce the amount of penetration of auxiliary workings. Fig. 1 shows a diagram of the location of the protected and auxiliary mine workings, relief wells, a monolithic reinforced slab (shaded area); Fig. 2 shows the layout of the discharge wells and rods with mortar, reinforcing the rocks of the immediate roof. Figures 1 and 2 denote protected production 1, secondary production 2, wells 3-5, reinforcing elements 6, reinforcing solution 7. The method is carried out as follows. In parallel with the protected development 1, an auxiliary production 2 is conducted, from which an additional row of wells 3 is drilled in the roof above. At the same time between the wells 3 and production 1 they form a rock cushion, the power of which must be sufficient to prevent self-destruction of the rocks of the immediate roof . In wells 3, reinforcing elements 6 (from pipes, fittings, katanas, etc.) are placed over the entire length of the wells and pressurized fortification solution 7 (cement mortar) into the wells under pressure, resulting in a floor slab above production. Before the design strength of the reinforcing mortar of the slab is reached, the relief wells 4 will be drilled above, followed by drilling them through one well 5 of larger diameter. The length of the wells depends on the angle of inclination and the width of the planned discharge zone, which is equal to the width of the protected development and the width of the two pillars on the sides of the production. The created monolithic reinforced plate performs the role of overlapping, with its ends resting on coal pillars. Formula of the Invention A method of guarding mine workings, including conducting auxiliary mine along a formation, drilling out of it over guarded production of parallel wells within the discharge area and drilling relief wells through one well of a larger diameter, so as to increase the reliability of mining workings and reduce the amount of penetration of auxiliary workings, above the protected production below the discharge wells, create a slab block by drilling from producing additional rows of parallel wells, into which reinforcing elements are installed and injection solutions are used to strengthen reinforcing solutions, and when creating the slab between it and the protected outlet, a rock cushion is formed, and the relief wells are drilled to obtain the design strength of the reinforcement plate shut off.
SU853929959A 1985-06-17 1985-06-17 Method of safeguarding mine workings SU1273562A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU853929959A SU1273562A1 (en) 1985-06-17 1985-06-17 Method of safeguarding mine workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU853929959A SU1273562A1 (en) 1985-06-17 1985-06-17 Method of safeguarding mine workings

Publications (1)

Publication Number Publication Date
SU1273562A1 true SU1273562A1 (en) 1986-11-30

Family

ID=21189381

Family Applications (1)

Application Number Title Priority Date Filing Date
SU853929959A SU1273562A1 (en) 1985-06-17 1985-06-17 Method of safeguarding mine workings

Country Status (1)

Country Link
SU (1) SU1273562A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2167301C1 (en) * 1999-11-29 2001-05-20 Кузбасский государственный технический университет Method of supporting mine workings in adjacent coal seams

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 1102953, кл. Е 21 С 41/04, 1982. Авторское свидетельство СССР № 825982, кл. Е 21 D 9/00, 1981. *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2167301C1 (en) * 1999-11-29 2001-05-20 Кузбасский государственный технический университет Method of supporting mine workings in adjacent coal seams

Similar Documents

Publication Publication Date Title
US4997317A (en) System and method for supporting a mining gallery
US3427811A (en) Mine roof support system
US11976557B2 (en) Coal bump control method for sectional hydraulic fracturing regions of near vertical ultra thick coal seam
US5462391A (en) Mine roof support cribbing system
CN102268998A (en) Dual-micro-arch span-reducing support method of large-span open-off cut
CN113073978B (en) Thick coal seam confined concrete pillar roof-cutting roadway coal-pillar-free mining method
AU2019456662B2 (en) Design method for mine without leaving coal pillar and without roadway tunneling
CN110985123A (en) High-pressure hydraulic pre-cracking dangerous impact ore pressure crossheading roadway drilling arrangement method
CN102900449A (en) Support method for underground goaf roof of coal mine
SU1273562A1 (en) Method of safeguarding mine workings
CN110552731A (en) top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof
RU2007577C1 (en) Method of guarding of workings in heaving soils
CN109184752A (en) A kind of coal mine supporting construction and its method for protecting support for passing through old kiln goaf
CN116696371B (en) Supporting method for large-section tunnel tunneling of shield tunneling machine in water-guiding fracture zone
CN112459782A (en) Coal mine rock burst treatment method based on F-shaped fully mechanized mining face and with small coal pillars
RU2013546C1 (en) Method for protection of reused workings
CN109751062A (en) A method for preventing and controlling the floor heave in the roadway with small coal pillars in the air
RU2471990C1 (en) Method to mine sloping and inclined coal beds of average capacity
SU1761953A1 (en) Method of working steep coal bed
CN114151116A (en) Advanced support method for reinforcing anchor cable beam and roof cutting pressure relief
SU1550157A1 (en) Tunnel construction method
RU2219341C1 (en) Process of development of thick gently dipping coal formations with roof rocks difficult to fall
Singh et al. Review of fill mining technology in Canada
SU1739043A1 (en) Method for working stabilization with anchor-frame support
RU2403387C1 (en) Method for development of contiguous beds series