[go: up one dir, main page]

SU1002361A1 - Cone suspension of blast furnace charging apparatus (modifications) - Google Patents

Cone suspension of blast furnace charging apparatus (modifications) Download PDF

Info

Publication number
SU1002361A1
SU1002361A1 SU802979307A SU2979307A SU1002361A1 SU 1002361 A1 SU1002361 A1 SU 1002361A1 SU 802979307 A SU802979307 A SU 802979307A SU 2979307 A SU2979307 A SU 2979307A SU 1002361 A1 SU1002361 A1 SU 1002361A1
Authority
SU
USSR - Soviet Union
Prior art keywords
cone
traverse
blast furnace
suspension
insert
Prior art date
Application number
SU802979307A
Other languages
Russian (ru)
Inventor
Борис Цезаревич Соколовский
Владимир Яковлевич Черкасский
Виктор Павлович Докучиц
Яков Моисеевич Черкасский
Original Assignee
Всесоюзный научно-исследовательский проектно-конструкторский технологический институт механизации труда в черной металлургии и ремонтно-механических работ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный научно-исследовательский проектно-конструкторский технологический институт механизации труда в черной металлургии и ремонтно-механических работ filed Critical Всесоюзный научно-исследовательский проектно-конструкторский технологический институт механизации труда в черной металлургии и ремонтно-механических работ
Priority to SU802979307A priority Critical patent/SU1002361A1/en
Application granted granted Critical
Publication of SU1002361A1 publication Critical patent/SU1002361A1/en

Links

Landscapes

  • Blast Furnaces (AREA)

Description

Изобретение относитс  к черной металлургии, а именно к оборудованию загруэки доменных печей.FIELD OF THE INVENTION The invention relates to ferrous metallurgy, in particular, to equipment for loading of blast furnaces.

Известна в доменном производстве подвеска большого конуса, состо ща  из траверсы и двух т г С 1Наиболее близким к изобретению по технической сущности и достигаемому результату  вл етс  подвеска большого конуса загрузочного устройства доменной печи, состо ща  из траверсы с внутренним отверстием дл  штанги конуса, закрепл емой на ней гайками, и двух т г, которые нижними концают посредством гаек соединены с траверсой, а верхними с помощью ст жных гаек балансиров с т гами балансира конуса C JНедостатком известной конструкции  вл етс  больша  трудоемкость и длительность монтажа загрузочного устройства, св занна  со сложностью заведени  верхнего конца штанги большого конуса в отверстие траверсы подвески. Кроме того, при осуществлении указанной операции траверса, опуска сь па верхнему концу штанги большого конуса, часто нарушает имеющуюс  там резьбу, предназначенную дл  гаек, фиксирующихKnown in the blast furnace production is a large cone suspension consisting of a traverse and two tons of C 1. Closest to the invention to the technical essence and the achieved result is a suspension of a large cone of a blast furnace charging device consisting of a traverse with an internal opening for a cone rod fixed there are nuts on it, and two tg, which the lower end is connected to the crossbeam by means of nuts, and the upper, by means of clamping nuts, balancers with the balancer of the cone C. The disadvantage of the known construction is lsha complexity and duration of loading device assembly, associated with the complexity house advantage upper end of rod of a large hole in the cone suspension traverse. In addition, when performing the above traverse operation, lowering to the upper end of the large cone rod often breaks the thread there, intended for nuts that fix

штангу относительно траверсы. Это снижает на;дежность (в частности, долговечность и ремонтопригодность)rod relative to the traverse. This reduces reliability, (in particular, durability and maintainability)

с узла соединени  штанги большого нуса с подвеской и, в конечном , счете, снижает нгщежность загрузочного устройства в целом.from the node connecting the rods of a large housus to the suspension and, ultimately, reduces the level of the entire boot device.

Целью изобретени   вл етс  сок-The aim of the invention is to

IQ ращение трудоемкости и длительности монтажа загрузочного устройства и повышение его надежности.IQ increases labor intensity and installation time of the boot device and increases its reliability.

Дл  этого в подвеске большого конуса загрузочного устройства до15 менной печи, содержащей траверсу с внутренним отверстием дл  штанги и конуса т ги и соединительные гайки , траверса выполнена разъемной в поперечной плоскости симметрии, а For this, in the suspension of the large cone of the charging device of the submerged furnace, containing a traverse with an internal hole for the rod and the cone and connecting nuts, the traverse is made detachable in the transverse plane of symmetry, and

20 на поверхности разъема выполнены фиксирующие выступы и соответствующие им пазы.20, locking protrusions and corresponding grooves are made on the surface of the connector.

Согласно другому варианту траверса выполнена с пазом по боковой According to another embodiment, the traverse is made with a groove along the side

25 поверхности, достигающим продольной плоскости симметрии, и снабжена. вставкой, причем поверхность разъема траверсы и вставки проходит через диаметральную плоскость отверсти  25 surface reaching a longitudinal plane of symmetry, and is equipped with. insert, and the surface of the connector traverse and insert passes through the diametral plane of the hole

30 дл  штанги конуса, а на поверхност х разъема выполнены фиксирующие выступы и соответствующие им пазы. На фиг.1 изображена предлагаема  подвеска большого конуса; на фиг.2 разрез А-А на фиг.1; на фиг.3-4 вариант подвески. Подвеска большого конуса (см. фиг. 1 и 2) содержит траверсу, сойто щую ий двух частей 1 и 2, две т ги 3 и гайки 4 . Болты 5 (.их количество показано условно) соедин ют части 1 и. 2 траверсы между собой-. На поверхно :т х разъема частей 1 и 2 траверсы выполнены фиксирующие вы тупы б и соответствующие им пазы 7. Внутри центрального отверсти , ось которого совмещена с осью симметрии траверсы, находитс  верхний конец штанги 8 большого конуса, зафиксиро ванной относительно траверсой верхней и нижней гайками 9. Подвеска по варианту (см.фиг.3 и 4) отличаетс  тем, что на боковой поверхности траверсы выполнен паз достигающий продольной плоскости симметрии, и снабжена вставкой 10, причем поверхность разъема траверсы и вставки проходит через диаметраль ную плоскость отверсти  дл  штанги 8. На вставке 10 выполнены дополнительные фиксирующие выступы 11. Устройство работает следующим образом. При монтаже загрузочного устройства доменной печи части 1 и 2 траверсы устанавливаютс  на снабженном резьбой верхнем конце штанги 8 выше нижней гайки 9, охватыва  штангу 8. При этом выступы 6 вход т в соответствующие им пазы 7 и предотвращают смещение частей 1 и 2 траверсы одна относительно другой в плоскост разъема при монтаже и эксплуатации загрузочного устройстваi Части 1 и 2траверсы соединены друг с другом с домощью болтов 5, а с помощью гае 4- с т гами 3. Верхн   часть, т г 3соединена с т гами балансира боль шого конуса (не показаны). Подвеска большого конуса используетс  в паре с подвеской малого конуса; В семи из восьми примен емы типоразмеров подвесок конусов т ги подвески малого конуса (не показаны расположены в плоскости, перпендику л рной плоскости т г 3 подвески бол шого конуса. В одной из модификаций т ги подвесок конусов расположены в одной плоскости, при этом т ги подвески малого конуса проход т через отверсти  в траверсе подвески большого конуса. Приливы в част х 1 и 2 траверсы подвески большого ко нуса, предназначенныедл  болтов 5(см. фиг.2), по ширине меньше рас сто ни  между т гами подвески малого конуса. Работа устройства по варианту отличаетс  тем, что после установки траверсы 1 на верхнем конце штанги 8 большого конуса вставка 10 вводитс  в предназначенный дл  нее паз на боковой поверхности траверсы 1, при этом фиксирующие выступы 6 и 11 преп тствуют смещению вставки относительно траверсы: выступы б - в. горизонтальном направлении и выступы 11 - в вертикальном. Толщина фиксирующих выступов 11 не превышает 15% поперечного размера траверсы 1 дл  возможности заведени  вставки 10 в паз траверсы 1 в габаритах загрузочного устройства (упом нутое выше наличие т г .подвески малого конуса в поперечной плоскости симметрии траверсы 1) . При эксплуатации доменной печи подвеска передает на т ги балансира нагрузку от веса большого конуса со штангой, веса наход щихс  на большом конусе шахтоматериалов и возможные динамические усили  при ударном закрыт.ии большого конуса. Изобретение позволит уменьшить трудоемкость и длительность монтажа загрузочного устройства доменной печи за счет облегчени  соединени  подвески со штангой большого конуса, а также повысить надежность загрузочного устройства засчет гарантированного сохранени  целости резьбы на верхнем конце штанги большого конуса , что часто невыполнимо при применении подвески большого конуса существующей конструкции. Произведенные расчеты показали, что при выполнении болтов, соедин ющих части предлагаемой траверсы подвески из сталей, имеющих повышенный предел прочности при раст жении . например,дл  стали кг/см , предлагаема  траверса  вл етс  равнопрочной существующим конструкци м, содержащим, дельную траверсу. При выполнении подвески большого конуса по варианту наиболее опасное центральное поперечное сечение траверсы , не ослаблено (траверса 1 и вставка 2 работают на изгиб совместно ) , поэтому предлагаема  конструкци  также равнопрочна с существующими . Суммарна  прочность на разрыв болтов 5, соедин ющих вставку 10 и траверсу, обеспечивает воспри тие возможных боковых усилий, иногда возникающих при принудительном открывании большого конуса, при переполнении печи шихтоматериалами. Экономи  от внедрени  изобретени  достигаетс  за счет сокращени  прост тоев доменных печей на замене загрузочных устройств, обусловленного уменьшением трудоемкости и длительности монтажа засыпного аппарата, и составл ет650 руб. на одну доменную печь, в год по сравнению с базовым объектом подвеской большого конуса с цельной траверсой.30 for a cone rod, and fixing protrusions and corresponding grooves are made on the surfaces of the connector. Figure 1 shows the proposed suspension of a large cone; in Fig.2 a section aa in Fig.1; figure 3-4 option suspension. The suspension of a large cone (see Figs. 1 and 2) contains a traverse, which consists of two parts 1 and 2, two bars 3 and nuts 4. Bolts 5 (.the quantity shown conventionally) connect parts 1 and. 2 traverses between themselves-. On the surface: the t x connectors of parts 1 and 2 of the cross bar are made locking b and the corresponding grooves 7. Inside the central hole, the axis of which is aligned with the axis of symmetry of the cross bar, is the upper end of the large cone rod 8, fixed relative to the cross bar by the upper and lower nuts 9. The suspension according to the variant (see Figures 3 and 4) is characterized by the fact that a groove reaching the longitudinal plane of symmetry is made on the lateral surface of the crosshead, and is provided with an insert 10, the crosshead and the insert surface passing through the diametral th aperture plane for the rod 8. The insert 10 are additional locking projections 11. The apparatus operates as follows. When installing the charging device of the blast furnace, parts 1 and 2 of the crossbeam are mounted on the threaded upper end of the rod 8 above the lower nut 9, covering the rod 8. In this case, the projections 6 fit into the corresponding grooves 7 and prevent the crossheads 1 and 2 from moving in the plane of the connector during installation and operation of the boot device i Parts 1 and 2 of the cross-arm are connected to each other with the house of the bolts 5, and with the help of a heel 4 - with the cords 3. The upper part, the c 3 is connected to the cams of the large cone balance bar (not shown) . A large cone suspension is paired with a small cone suspension; In seven out of eight, the standard sizes of cones for cones and small cones are not shown (not shown in the plane perpendicular to the plane of cones for the large cone. In one of the modifications, cones for propellers are in the same plane, with The small cone hangers pass through the holes in the traverse of the large cone hanger. The tides in parts 1 and 2 of the large cone hanger, designed for the bolts 5 (see Fig. 2), are less than the width between the small cone hangers. Device operation by The riant is characterized in that after installing the crosspiece 1 on the upper end of the large cone rod 8, the insert 10 is inserted into the groove intended for it on the side surface of the crosshead 1, while the fixing protrusions 6 and 11 prevent the insert from being displaced relative to the crosshead: the projections are horizontal. the direction and the protrusions 11 are vertical. The thickness of the locking protrusions 11 does not exceed 15% of the transverse dimension of the yoke 1 in order to insert the insert 10 into the groove of the yoke 1 in the dimensions of the loading device (the above presence of the suspension t small cone in the transverse plane of symmetry of the traverse 1). During the operation of a blast furnace, the suspension transfers the weight of a large cone with a rod, the weights of a large cone of the chess materiel and possible dynamic forces during a shock closure of a large cone to a load balancer. The invention will reduce the laboriousness and duration of installation of the blast furnace boot device by facilitating the connection of the suspension with the large cone rod, as well as increasing the reliability of the loading device by ensuring that the thread cones is kept at the upper end of the large cone rod, which is often not feasible when using a large cone suspension of the existing structure. The calculations made showed that when the bolts are connected, the parts of the proposed suspension bar are made of steels with increased tensile strength. For example, for steel kg / cm, the proposed cross bar is a uniformly existing structure containing a cross bar. When performing a suspension of a large cone, the most dangerous central cross section of the crosshead is not weakened (crosshead 1 and insert 2 work on bending together), therefore, the proposed design also has equal strength with the existing ones. The total tensile strength of the bolts 5 connecting the insert 10 and the traverse ensures the perception of possible lateral forces, sometimes arising from the forced opening of a large cone, when the furnace material overflows. Saving from the implementation of the invention is achieved by reducing the simpleness of blast furnaces to replace the loading devices, due to the reduction of labor intensity and the installation time of the charging apparatus, and is 650 rubles. per blast furnace per year compared to the base object of a large cone suspension with a solid crosshead.

Применение подвески большого конуса с разъемной траверсой возможно .на всех доменных печах, оснащенных конусными загрузочными устройствами.The use of a large cone suspension with a detachable crosshead is possible on all blast furnaces equipped with cone loading devices.

Claims (2)

1. Подвеска большого конуса загрузочного устройства доменной печи, содержаща  траверсу с внутренним отверстием дл  штанги конуса, т ги и соединительные гайки, отличающа с  тем, что, с целью сокращени  трудоемкости длительност монтажа и повышени  надежности, траверса выполнена разъемной в поперечной плоскости симметрии, а на поверхност х разъема выполнены фиксирующие и соответствующие им пазы.1. Suspension of a large cone of a blast furnace charging device, containing a traverse with an internal opening for a cone rod, drawbars and connecting nuts, characterized in that, in order to reduce the labor intensity of the installation time and increase reliability, the traverse is made detachable in the transverse plane of symmetry, and fixing and corresponding grooves are made on the surfaces of the connector. 2; ПЬдвеска большого конуса загрузочного устройства доменной печи.2; Lift the large cone boot device blast furnace. содержаща  траверсу с внутренним ютвеЕЮтием дл  штанГи конуса, т ги и соединительные гайки о т л ич а ю щ а   с   тем, что, с целью сокращени  трудоемкости, длительности монтажа и повышени  надежности, траверса выполнена с пазом н боковой поверхности, достиггиощим продольной плоскости симметрии, и снабжена вставкой, причем поверхность разъема траверсы и вставки проходит через диаметргшьную плоскость отверсти  дл  штанги конуса, а на поверхност х разъема выполнены фиксирующие выступы и соответствующие им пазы.containing traverse with internal threading for cone rods, drawbars and connecting nuts, so that, in order to reduce labor intensity, assembly time and increase reliability, the traverse is made with a groove and side surface, achieving a longitudinal symmetry plane , and is provided with an insert, wherein the surface of the crosspiece and insert connector passes through the diametrical plane of the opening for the cone rod, and fixing protrusions and corresponding slots are made on the surfaces of the connector. Источники информации, прин тые во внимание при экспертизеSources of information taken into account in the examination 1.Чернов Н.Н. и др. Засыпные устройства домен.ных печей. М.., 1 етаплургиздат , 1962, с. 40-41,фиг.191. Chernov N.N. and others. Filling devices domain. furnaces. M .., 1 etaplurgizdat, 1962, p. 40-41, FIG. 19 2.Агломерационное, окомковательное и доменное оборудование. Каталог-справочник . Ч. 2. М., НИ АФОРМТЯЖМАШ , 1970, с. 52-54, фиг. 26 и 27.2. Agglomeration, pelletizing and domain equipment. Directory reference. Part 2. M., NO AFORMTYAMZHMASH, 1970, p. 52-54, FIG. 26 and 27. ААAA
SU802979307A 1980-09-01 1980-09-01 Cone suspension of blast furnace charging apparatus (modifications) SU1002361A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802979307A SU1002361A1 (en) 1980-09-01 1980-09-01 Cone suspension of blast furnace charging apparatus (modifications)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802979307A SU1002361A1 (en) 1980-09-01 1980-09-01 Cone suspension of blast furnace charging apparatus (modifications)

Publications (1)

Publication Number Publication Date
SU1002361A1 true SU1002361A1 (en) 1983-03-07

Family

ID=20916721

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802979307A SU1002361A1 (en) 1980-09-01 1980-09-01 Cone suspension of blast furnace charging apparatus (modifications)

Country Status (1)

Country Link
SU (1) SU1002361A1 (en)

Similar Documents

Publication Publication Date Title
CA1142498A (en) Suspension clamp
US5353893A (en) Elevator cab and/or counterweight compensation rope hitch assembly
US2946619A (en) Double socket and sling structure
KR20130113424A (en) Device for suspending a rail, in particular a rail of an overhead conveyor or lifting gear
SU1002361A1 (en) Cone suspension of blast furnace charging apparatus (modifications)
US3854256A (en) Fabrication of furnace linings with support frame
US3705445A (en) Vibration damped fitting
CN212294353U (en) Suspender tensioning device
US3045305A (en) Concrete prestressing cable grip
US5577065A (en) Device for mounting a self-baking electrode for an electric arc furnace
CN209025203U (en) Hub node structure and device with hub node structure
CN105926953B (en) Temperature pier structure for prefabricated part hanging
CN205313591U (en) Be used for to reinforced steel scrap fill of converter
KR102375567B1 (en) Fixing equipment and balance lever using the same
CN210939859U (en) Reinforcing bar locating component during reinforcement cage ligature
US4735450A (en) Lifting gear and testing it
US1953290A (en) Cable clamp
DE2804621C2 (en) Device for setting, monitoring and readjusting the tensioning forces in guide and friction ropes in shaft hoisting systems in the mining industry
DE2934373C2 (en) Device for attaching electrical cables to a multiple insulator chain
CN217676306U (en) Hoisting connecting device
KR102307606B1 (en) A earthquake-resistant access floor base reinforcement device
DD214419A1 (en) KERBWIRKUNGSARME CENTRIC RIVET FASTENING
CN110397095B (en) Pile foundation bearing capacity detection system and method
US1957724A (en) Intermediate connection for haulage cages
US2613964A (en) Clamp