[go: up one dir, main page]

RU2032019C1 - Method for erecting embankment from improvised materials - Google Patents

Method for erecting embankment from improvised materials Download PDF

Info

Publication number
RU2032019C1
RU2032019C1 SU4946909A RU2032019C1 RU 2032019 C1 RU2032019 C1 RU 2032019C1 SU 4946909 A SU4946909 A SU 4946909A RU 2032019 C1 RU2032019 C1 RU 2032019C1
Authority
RU
Russia
Prior art keywords
dam
excavator
drainage ditch
embankment
erecting
Prior art date
Application number
Other languages
Russian (ru)
Inventor
Вадим Николаевич Калишевский
Original Assignee
Вадим Николаевич Калишевский
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Вадим Николаевич Калишевский filed Critical Вадим Николаевич Калишевский
Priority to SU4946909 priority Critical patent/RU2032019C1/en
Application granted granted Critical
Publication of RU2032019C1 publication Critical patent/RU2032019C1/en

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

FIELD: hydraulic engineering. SUBSTANCE: method involves filling an embankment in conjunction with railway transport by an excavator moving through drain ditch dug in advance in embankment footing and filled with crushed rock to the excavator level. EFFECT: higher efficiency. 4 dwg

Description

Изобретение относится к гидротехническому строительству и может быть использовано при возведении дамб обвалования намывных хвостохранилищ и гидроотвалов. The invention relates to hydraulic engineering construction and can be used in the construction of dams of the landslide of alluvial tailings and hydraulic dumps.

Цель изобретения - снижение стоимости строительства дамбы при возведении ее на водонасыщенных нескальных грунтах. The purpose of the invention is to reduce the cost of building a dam when erecting it on water-saturated non-rocky soils.

На фиг. 1 изображена дамба, поперечный разрез; на фиг.2 - схема разработки дренажной канавы в основании дамбы; на фиг.3 - схема засыпки дренажной канавы скальными породами, отсыпки нижнего яруса противофильтрационного элемента дамбы, крепления верхового откоса и упорной призмы; на фиг. 4 - схема отсыпки верхнего яруса противофильтрационного элемента дамбы. In FIG. 1 shows a dam, a cross section; figure 2 is a diagram of the development of a drainage ditch at the base of the dam; figure 3 is a diagram of the filling of the drainage ditch with rock, dumping of the lower tier of the anti-filter element of the dam, fastening the upper slope and a persistent prism; in FIG. 4 is a diagram of the dumping of the upper tier of the dam filter element.

Дамба включает нижний ярус противофильтрационного элемента 1, упорную призму 2 и верхний ярус противофильтрационного элемента 3. В основание дамбы заглублена заполненная дробленными скальными породами дренажная канава 4. The dam includes the lower tier of the antifiltration element 1, a persistent prism 2, and the upper tier of the antifiltration element 3. A drainage ditch 4 filled with crushed rock is buried at the base of the dam.

Нижний ярус противофильтрационного элемента выполнен в виде верховой призмы, а его верхний ярус - в виде экрана. Основанием последнего может служить не только гребень нижнего яруса противофильтрационного элемента, но и намытый перед ним при заполнении хвостохранилища (гидроотвала) материала (хвосты) 5. The lower tier of the anti-filtration element is made in the form of an upper prism, and its upper tier is in the form of a screen. The basis of the latter can serve not only as the crest of the lower tier of the antifiltration element, but also washed in front of it when filling the tailings (hydraulic dump) of the material (tails) 5.

На верховом откосе противофильтрационного элемента дамбы может быть размещено крепление 6 в виде каменной наброски. On the upper slope of the anti-filtering element of the dam, a fastening 6 in the form of a stone outline can be placed.

Способ осуществляется следующим образом. The method is as follows.

Первоначально одноковшовым экскаватором, оборудованным драглайном или обратной лопатой, разрабатывают в основании дамбы по трассе движения отсыпающего ее тело карьерного экскаватора дренажную канаву. При этом разрабатываемый грунт перемещают в расположенный вдоль дренажной канавы 4 временный отвал или непосредственно в нижний ярус противофильтрационного элемента 1 дамбы. Initially, with a single-bucket excavator equipped with a dragline or backhoe, a drainage ditch is developed at the base of the dam along the path of movement of a quarry excavator that dumps her body. In this case, the developed soil is moved to a temporary dump located along the drainage ditch 4 or directly to the lower tier of the dam filter element 1.

По мере разработки дренажной канавы 4 ее засыпают дробленными скальными породами до уровня установки отсыпающего дамбу карьерного экскаватора. Последний используют и для засыпки дренажной канавы. As the drainage ditch 4 is developed, it is covered with crushed rock to the level of installation of a dump excavating quarry excavator. The latter is also used to fill the drainage ditch.

Засыпка канавы карьерным экскаватором производится до уровня его установки вперед по ходу движения, нижним подуступом. Первый участок канавы длиной 10-20 м может быть засыпан с помощью автосамосвалов и бульдозера. Устройство дренажной канавы позволяет ускорить консолидацию грунта в основании дамбы и расположить на 1,5-2,0 м ниже его поверхности используемый для отсыпки дамбы карьерный экскаватор. При этом глубина дренажной канавы должна быть такой, чтобы слой скальных пород, отсыпанный под гусеницы карьерного экскаватора, обеспечивал его устойчивое положение. Ширина дренажной канавы на уровне установки экскаватора должна превышать ширину его гусеничного хода. Filling the ditch with a career excavator is carried out to the level of its installation forward along the direction of travel, with the lower sub-stage. The first section of the ditch with a length of 10-20 m can be bombarded with dump trucks and a bulldozer. The device of the drainage ditch allows you to accelerate the consolidation of the soil at the base of the dam and to place a quarry excavator used to fill the dam 1.5-2.0 m below its surface. At the same time, the depth of the drainage ditch should be such that a layer of rock sprinkled under the tracks of a quarry excavator ensures its stable position. The width of the drainage ditch at the excavator installation level must exceed the width of its caterpillar track.

Вода, попадающая в дренажную канаву, может не отводиться, если она не мешает работе карьерного экскаватора. При необходимости эта вода отводится за пределы дренажной канавы (в дренажную систему ограждающих сооружений хвостохранилища и прилегающей к нему территории, в прудок оборотного водоснабжения и т.д.). Water entering the drainage ditch may not be discharged if it does not interfere with the operation of the mining excavator. If necessary, this water is discharged outside the drainage ditch (into the drainage system of the enclosing structures of the tailing dump and the adjacent territory, into the pond of recycled water supply, etc.).

Карьерным экскаватором по мере его движения по засыпанной скальными породами дренажной канаве 4 последнюю уширяют выше горизонта установки экскаватора в сторону нижнего бьефа до подошвы низового откоса возводимой дамбы. Разрабатываемая в основании дамбы траншея может быть уширена экскаватором и в сторону верхнего бьефа до противофильтрационного элемента 1. Разрабатываемый в основании дамбы грунт отсыпается в нижний ярус противофильтрационного элемента 1. Одновременно с этим карьерным экскаватором перемещают в нижний ярус противофильтрационного элемента дамбы и грунт из временного отвала, если последний отсыпается при разработке дренажной канавы. As a quarry excavator moves along the drainage ditch filled with rock, the latter is broadened above the excavator installation horizon towards the downstream to the bottom of the lower slope of the constructed dam. The trench developed at the base of the dam can be widened by the excavator and towards the upstream to the anti-filter element 1. The soil developed at the base of the dam is poured into the lower tier of the anti-filter element 1. At the same time as the excavator, the dam and soil from the temporary dump are moved to the lower tier of the dam, if the latter is covered during the development of the drainage ditch.

Упорная призма 2 дамбы отсыпается карьерным экскаватором назад по ходу движения по засыпанной скальными породами дренажной канаве (верхним подуступом). The persistent prism of the 2 dams is poured back by a quarry excavator along the course of movement along the drainage ditch filled with rocky rocks (upper sub-level).

При этом отсыпку экскаватором скальных пород в дренажную канаву и упорную призму дамбы целесообразно производить поочередно без значительного опережения по фронту работ. Параллельно с отсыпкой упорной призмы карьерным экскаватором можно отсыпать и крепления 6 нижнего яруса противофильтрационного элемента дамбы. At the same time, it is advisable to alternately fill the rocks with the excavator in the drainage ditch and the prismatic prism of the dam without significant advance on the front of the work. In parallel with the dumping of the persistent prism by a mining excavator, it is possible to pour off the fastenings 6 of the lower tier of the dam filter element.

Материал для засыпки дренажной канавы, а также устройства упорной призмы и крепления дамбы доставляется непосредственно к карьерному экскаватору (в экскаваторный приямок) железнодорожным транспортом - думпкарными поездами (вертушками). Для его доставки вдоль подошвы низового откоса возводимой дамбы укладывается железнодорожный путь. После отсыпки упорной призмы и нижнего яруса противофильтрационного элемента дамбы перед последним намывают складируемый в хвостохранилище (гидроотвале) материал 5, из которого затем экскаватором драглайном или бульдозером отсыпают верхний ярус противофильтрационного элемента 3 дамбы. На его верховой откос с помощью автосамосвалов и бульдозера может быть отсыпана каменная наброска. Material for filling the drainage ditch, as well as the device of the persistent prism and fixing the dam, is delivered directly to the quarry excavator (into the excavation pit) by rail - dump trains (turntables). For its delivery, a railway line is laid along the bottom of the lower slope of the constructed dam. After dumping the thrust prism and the lower tier of the anti-filtration element of the dam, the material 5 stored in the tailing dump (hydraulic dump) is washed before the last, from which the upper tier of the anti-filtration element 3 of the dam is then dumped with an excavator or a bulldozer. A stone sketch can be dumped on its horse slope using dump trucks and a bulldozer.

Предлагаемое изобретение позволяет возводить дамбы обвалования мощной горнотранспортной техникой в процессе отвалообразования на слабых водонасыщенных грунтах. The present invention allows the construction of embankment dams with powerful mining equipment in the process of dumping on weak water-saturated soils.

Claims (1)

СПОСОБ ВОЗВЕДЕНИЯ ДАМБЫ ИЗ МЕСТНЫХ МАТЕРИАЛОВ, включающий отсыпку нижнего яруса противофильтрационного элемента дамбы из разрабатываемых в ее основании грунтов, отсыпку упорной призмы и верхнего яруса противофильтрационного элемента дамбы, отличающийся тем, что, с целью снижения стоимости строительства дамбы при возведении ее на водонасыщенных нескальных грунтах, возведение дамбы начинают с разработки заглубленной в ее основание дренажной канавы, которую затем засыпают дроблеными скальными породами для движения по ним отсыпающего дамбу экскаватора. METHOD FOR BUILDING A DAM FROM LOCAL MATERIALS, including dumping the lower tier of the dam barrier element from the soils developed at its base, dumping the thrust prism and upper tier of the dam barrier element, characterized in that, in order to reduce the cost of building the dam when erecting it on water-saturated, not saturated the construction of the dam begins with the development of a drainage ditch buried in its base, which is then filled up with crushed rock formations to move ambu excavator.
SU4946909 1991-06-19 1991-06-19 Method for erecting embankment from improvised materials RU2032019C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU4946909 RU2032019C1 (en) 1991-06-19 1991-06-19 Method for erecting embankment from improvised materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU4946909 RU2032019C1 (en) 1991-06-19 1991-06-19 Method for erecting embankment from improvised materials

Publications (1)

Publication Number Publication Date
RU2032019C1 true RU2032019C1 (en) 1995-03-27

Family

ID=21580026

Family Applications (1)

Application Number Title Priority Date Filing Date
SU4946909 RU2032019C1 (en) 1991-06-19 1991-06-19 Method for erecting embankment from improvised materials

Country Status (1)

Country Link
RU (1) RU2032019C1 (en)

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР N 1300084, кл. E 02B 7/06, 1985. *
Авторское свидетельство СССР N 1710658, кл. E 02B 7/06, 1990. *

Similar Documents

Publication Publication Date Title
NO318657B1 (en) Procedure for the construction of an underground continuous wall
SU1765400A1 (en) Method at sail mass reclamation during preparation of quarry sanitary-protection zone
Heede Design, construction, and cost of rock check dams
RU2039151C1 (en) Washed-up hydraulic structure
RU2032019C1 (en) Method for erecting embankment from improvised materials
CN109113045A (en) A kind of soft-soil foundation treatment method
RU2011826C1 (en) Method for mining of inundated placers
RU2176700C1 (en) Method for protecting territory from flooding
US3182460A (en) Apparatus for making permeable conduits in subterranean lines of drainage
JP3138950B2 (en) Roadway construction method on slope
Prisk et al. Delivering Wadi Dayqah, Oman's tallest dam
CN115354680A (en) Large river channel inner framework clay core wall type cofferdam construction method
RU2791061C1 (en) Method for waterproofing a man-made container using loose overburden rocks in development of mineral deposits
RU2426832C1 (en) Method to build earth water-retaining construction in warm season (versions)
RU2106494C1 (en) Method for handling overburden earth
JP2001011849A (en) Soil liquefaction prevention structure, its construction method and ground improvement method
US3191387A (en) Method for making permeable conduits in subterranean lines of drainage
KR102225104B1 (en) Open shield method
RU2451179C1 (en) Method of pits conservation with flooding of selected area
SU1463857A1 (en) Method of constructing trenchless drainage system
Stamatopoulos et al. Embankment construction on yielding sea bottom
Hou et al. Practical Solutions for Mountainous Pipeline Construction: Mechanically Stabilized Earth Retaining Walls on a Western Canadian Transmission Pipeline Project
RU1788262C (en) Method for internal refuse disposal
Lane et al. Tuttle Creek Dam of rolled shale and dredged sand
SU1724814A1 (en) Embankment filling method