[go: up one dir, main page]

KR20250115166A - Construction method of narrow-pillar tunnel using reinforcing system - Google Patents

Construction method of narrow-pillar tunnel using reinforcing system

Info

Publication number
KR20250115166A
KR20250115166A KR1020240010261A KR20240010261A KR20250115166A KR 20250115166 A KR20250115166 A KR 20250115166A KR 1020240010261 A KR1020240010261 A KR 1020240010261A KR 20240010261 A KR20240010261 A KR 20240010261A KR 20250115166 A KR20250115166 A KR 20250115166A
Authority
KR
South Korea
Prior art keywords
tunnel
support
tie bolt
steel
close
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
KR1020240010261A
Other languages
Korean (ko)
Inventor
이재호
문경선
Original Assignee
주식회사 바우컨설탄트
(주)하경엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 바우컨설탄트, (주)하경엔지니어링 filed Critical 주식회사 바우컨설탄트
Priority to KR1020240010261A priority Critical patent/KR20250115166A/en
Publication of KR20250115166A publication Critical patent/KR20250115166A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/22Clamps or other yieldable means for interconnecting adjacent arch members either rigidly, or allowing arch member parts to slide when subjected to excessive pressure
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/183Supporting means for arch members, not provided for in E21D11/22
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 터널 내부면을 지지하도록 터널 길이 방향을 따라 설치된 강지보 사이에 필라부 측으로 관입된 타이볼트의 단부가 관통되도록 강지보 지압부재를 설치함으로써, 필라부의 원지반 강도 및 터널 지보재의 최대 부재력을 활용하여 터널 굴착 즉시 복합 지지력을 발휘할 수 있는 근접병설터널 시공 방법에 대한 것이다.
본 발명은 (a) 선행터널을 굴착하는 단계; (b) 상기 선행터널의 내부면을 지지하는 복수 열의 제1강지보를 상호 이격 설치하는 단계; (c) 상기 굴착된 선행터널의 필라부가 형성될 일측에 타이볼트를 관입 시공하는 단계; (d) 양단부가 이웃하는 양측의 제1강지보에 지지되도록 상기 타이볼트의 선행터널 측 단부에 강지보 지압부재를 설치하는 단계; (e) 상기 선행터널 내부면에 숏크리트를 타설하는 단계; (f) 후행터널을 굴착하여 상기 타이볼트의 후행터널 측 단부가 노출되도록 선행터널과의 사이에 상기 필라부를 형성하는 단계; (g) 상기 후행터널 내부면을 지지하는 복수 열의 제2강지보를 상호 이격 설치하는 단계; (h) 양단부가 이웃하는 양측의 제2강지보에 지지되도록 상기 타이볼트의 후행터널 측 단부에 강지보 지압부재를 설치하는 단계; 및 (i) 상기 후행터널 내부면에 숏크리트를 타설하는 단계; 를 포함한다.
The present invention relates to a method for constructing a close-contact tunnel, which can exert a composite bearing capacity immediately after tunnel excavation by utilizing the original ground strength of the pillar portion and the maximum member force of the tunnel support member by installing a support member so that the end of a tie bolt inserted toward the pillar portion penetrates between the support members installed along the length of the tunnel to support the inner surface of the tunnel.
The present invention comprises the steps of: (a) excavating a preceding tunnel; (b) mutually spaced-apart installing a plurality of rows of first steel supports to support the inner surface of the preceding tunnel; (c) penetrating and constructing tie bolts on one side of the excavated preceding tunnel where a pillar portion is to be formed; (d) installing a steel support bearing member on the end of the tie bolt on the preceding tunnel side so that both ends are supported by the first steel supports on both adjacent sides; (e) pouring shotcrete on the inner surface of the preceding tunnel; (f) excavating a subsequent tunnel so that the pillar portion is formed between the subsequent tunnel and the preceding tunnel so that the end of the tie bolt on the subsequent tunnel side is exposed; (g) mutually spaced-apart installing a plurality of rows of second steel supports to support the inner surface of the subsequent tunnel; (h) installing a steel support bearing member on the end of the tie bolt on the subsequent tunnel side so that both ends are supported by the second steel supports on both adjacent sides; and (i) a step of pouring shotcrete on the inner surface of the rear tunnel;

Description

강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법{Construction method of narrow-pillar tunnel using reinforcing system}Construction method of narrow-pillar tunnel using reinforcing system

본 발명은 터널 내부면을 지지하도록 터널 길이 방향을 따라 설치된 강지보 사이에 필라부 측으로 관입된 타이볼트의 단부가 관통되도록 강지보 지압부재를 설치함으로써, 터널 필라부의 원지반 강도 및 터널 지보재의 최대 부재력을 활용하여 터널 굴착 즉시 조기에 복합 지지력을 발휘할 수 있는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법에 대한 것이다.The present invention relates to a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a support beam, which can exert a composite bearing capacity immediately after tunnel excavation by utilizing the original ground strength of the tunnel pillar portion and the maximum member force of the tunnel support member by installing a support beam bearing member so that the end of a tie bolt inserted toward the pillar portion penetrates between the support beams installed along the length of the tunnel to support the inner surface of the tunnel.

터널 설계는 터널 단면에 따라 단선병설터널, 대단면 터널, 2-아치 터널, 근접병설터널 등으로 구분된다.Tunnel designs are classified into single-track parallel tunnels, large-section tunnels, two-arch tunnels, and close-track parallel tunnels depending on the tunnel cross-section.

도로 터널은 시공이 단순한 단선병설터널로 건설하는 것이 일반적이다. 이러한 일반적인 병설터널은 터널의 구조적 안정성 확보를 위해 두 개의 터널을 충분한 거리로 이격시켜야 하는데, 통상 터널 폭(D)의 1.5배 이상 이격되도록 설계한다. 이 경우 터널과 연결되는 도로 또한 동일한 간격으로 분리되어야 하기 때문에 도로 점유 면적이 넓어져야 한다.Road tunnels are typically constructed as simple, single-track parallel tunnels. These typical parallel tunnels require sufficient separation between the two tunnels to ensure structural stability. This separation is typically designed to be at least 1.5 times the tunnel width (D). In this case, the road connecting the tunnel must also be separated by the same distance, necessitating a larger road surface area.

그러나 도심지에서는 용지 매입이 쉽지 않고, 자연환경보존에 대한 사회적 요구가 강화되면서 터널 간 이격거리를 1.5D 이상 확보하기 어렵다.However, it is not easy to purchase land in urban areas, and as social demands for environmental conservation are strengthened, it is difficult to secure a distance of more than 1.5D between tunnels.

이에 용지 수용이 곤란하거나 신설 터널에 근접하여 기존 보안건물이 존재하여 일반 병설터널 계획이 곤란한 경우, 대단면 단선터널이나 2-Arch 터널 형식을 적용할 수 있다.In cases where paper acceptance is difficult or an existing security building exists close to a new tunnel, making it difficult to plan a general parallel tunnel, a large-section single-track tunnel or a 2-Arch tunnel format can be applied.

그러나 대단면 단선터널은 터널 높이가 높아 굴착량이 과도하게 많이 발생하고, 상하 분할하여 굴착을 진행해야 하므로 공사비와 공기가 많이 소요된다. 특히, 암질이 불량하고 용지 매입이 극히 제한되는 도심지 터널은 대단면 단선터널을 적용하기 어렵다.However, large-diameter single-track tunnels require excessive excavation due to their high tunnel height. Furthermore, the excavation must be performed in two sections, resulting in significant construction costs and time constraints. In particular, large-diameter single-track tunnels are difficult to apply to urban tunnels, where rock quality is poor and land acquisition is extremely limited.

따라서 터널 간 이격거리 확보가 용이하지 않은 경우에는 병설터널 사이 간격을 줄일 수 있는 2-Arch 터널을 적용할 수 있다. 2-Arch 터널은 두 개의 터널이 형성될 중앙부에 먼저 중앙터널을 시공하여 중앙에 벽체를 형성하고, 벽체 양옆으로 본선 터널을 차례로 굴착한다. 그러나 이 공법은 중앙터널을 굴착하여 중앙 벽체를 시공한 후 본선 터널을 차례로 확장 굴착하므로, 시공 과정이 복잡하고 공사 기간과 공사비가 많이 소요된다. 뿐만 아니라 중앙터널 상부 지하수 고임으로 인해 운용 중 유지관리비용이 증가한다.Therefore, in cases where securing a sufficient distance between tunnels is difficult, a two-arch tunnel can be applied to reduce the gap between parallel tunnels. A two-arch tunnel involves first constructing a central tunnel in the central area where two tunnels will be formed, forming a central wall. Then, the main tunnels are sequentially excavated on either side of the wall. However, this method complicates the construction process, requiring significant time and cost due to the central tunnel being excavated, the central wall being constructed, and then the main tunnels being expanded sequentially. Furthermore, groundwater accumulation above the central tunnel increases maintenance costs during operation.

최근에는 도심지 용지 매입이 상당히 어렵고, 자연환경훼손 등의 우려를 고려하여 병설터널 간 이격거리가 상당히 근접된 형태의 터널 계획이 증가하고 있다. 이에 근접병설터널 공법을 고려할 수 있다.Recently, due to the significant difficulty in acquiring land in urban areas and concerns about environmental damage, plans for tunnels with significantly closer spacing between adjacent tunnels are increasing. Therefore, the close-contact tunneling method may be considered.

근접병설터널은 기존 일반 병설터널과 2-Arch 터널의 단점을 보완하기 위해 개발된 것으로, 필라부에 보강재를 설치하고 가압 그라우팅과 프리텐션 등에 의해 지반의 전단강도를 증가시켜 변위를 최소화함으로써 터널의 시공성, 구조적 안정성 및 경제성을 확보할 수 있는 공법이다.The close-contact tunnel was developed to complement the shortcomings of existing general contact tunnels and 2-Arch tunnels. It is a construction method that can secure the constructability, structural stability, and economic feasibility of a tunnel by installing reinforcement materials in the pillar section and increasing the shear strength of the ground through pressurized grouting and pretensioning to minimize displacement.

일반적인 병설터널 굴착시, 터널 굴착 파괴 영역(①), 터널 외측 손상 영역(②) 및 터널 필라부 교란 영역(③)의 3가지 영역이 발생된다(도 1). 그런데 근접병설터널은 터널 필라부의 폭이 좁아 선행터널(1a)과 후행터널(1b)의 손상 영역(②)이 중첩되어 일반적인 병설터널에 비해 구조적 안정성이 떨어지는 특성이 있다.During the excavation of a typical parallel tunnel, three areas occur: the tunnel excavation destruction area (①), the tunnel outer damage area (②), and the tunnel pillar disturbance area (③) (Fig. 1). However, in a close parallel tunnel, the tunnel pillar width is narrow, so the damage areas (②) of the preceding tunnel (1a) and the succeeding tunnel (1b) overlap, resulting in lower structural stability compared to a typical parallel tunnel.

터널 외측의 손상 영역(②)은 터널 발파 진동에너지가 직접적으로 터널 굴착면에 작용하여 d=0.5∼1.0m 두께의 영구적인 지반 이완 영역이 형성된다. 터널 필라부(10) 교란 영역(③)은 선행터널(1a)과 후행터널(1b)의 변형에 의하여 터널 필라부 지반 이완 영역이 확대되어 형성되는 것으로, 터널 필라부 지반의 변형 및 강도 특성, 터널의 굴착 방법이나 지보 시스템의 적용 등에 따라 지반 교란 영역과 상태가 상이하게 발생한다. 특히, 터널 필라부 교란 영역은 선행터널(1a)보다는 후행터널(1b) 굴착 후 급속하게 진행되는 특징이 있다(도 2의 근접병설터널 굴착시 지반 응력 참조).The damaged area (②) on the outside of the tunnel is formed by the direct vibration energy of tunnel blasting on the tunnel excavation surface, thereby forming a permanent ground relaxation area with a thickness of d=0.5∼1.0m. The tunnel pillar (10) disturbance area (③) is formed by the expansion of the tunnel pillar ground relaxation area due to the deformation of the preceding tunnel (1a) and the succeeding tunnel (1b), and the ground disturbance area and condition are generated differently depending on the deformation and strength characteristics of the tunnel pillar ground, the tunnel excavation method, or the application of the support system. In particular, the tunnel pillar disturbance area is characterized by progressing more rapidly after the excavation of the succeeding tunnel (1b) than that of the preceding tunnel (1a) (see ground stress during excavation of a closely parallel tunnel in Fig. 2).

근접병설터널은 필라부 폭이 협소하므로, 터널 굴착에 의한 필라부 손상 영역과 교란 영역은 터널의 안정성 확보에 큰 영향 요소로 작용한다.Since the width of the pillars in a close-contact tunnel is narrow, the area of pillar damage and disturbance caused by tunnel excavation is a major factor influencing the stability of the tunnel.

도 3에 도시된 종래 근접병설터널 공법에서는 방진 제어 발파에 의한 굴착으로 터널 필라부(10)의 손상을 최소화하고, 타이볼트(3) 및 철근(50) 보강 숏크리트(5)와 같은 고강성의 보강 시스템으로 터널 필라부(10)의 안정성을 확보한다. 그러나 종방향 터널 분할 굴착(필라부 후행 굴착)과 필라부(10)의 타이볼트(3) 및 철근보강 숏크리트(5) 타설로 시공 공정이 복잡하고, 일반 병설터널에 비해 시공성이 떨어지는 문제가 있다(등록특허 제10-1028535호). In the conventional close-contact tunnel construction method illustrated in Fig. 3, damage to the tunnel pillar (10) is minimized by excavation using vibration-controlled blasting, and the stability of the tunnel pillar (10) is secured by a high-strength reinforcement system such as tie bolts (3) and reinforcing bar (50) reinforced shotcrete (5). However, the construction process is complicated due to longitudinal tunnel segmentation excavation (post-pillar excavation) and tie bolts (3) and reinforcing bar shotcrete (5) pouring of the pillar (10), and there is a problem that the constructability is lower than that of a general parallel tunnel (Patent Registration No. 10-1028535).

특히, 터널 필라부(10)의 타이볼트(3) 및 철근보강 숏크리트(5) 보강은 시공 품질 확보를 위해 터널 막장 후방에서 1.0∼3.0D 영역에 대하여 일체로 시공된다. 그러므로 터널 필라부의 지반 조건이 불량하면 굴착 즉시 필라부의 지보력을 기대하기 어렵고, 필라부 교란 영역 확대로 지반 침하가 추가로 발생하는 등 터널 안정성 저하 우려가 있다. 따라서 후행터널(1b)의 필라부 무지보 구간에 대해서는 일부 폭을 남겨두고 굴착한 다음, 후방에서 철근보강 및 숏크리트 시공을 진행하여 지보력을 확보한 후 잔여 폭을 굴착하여 제거한다. 이에 전후방 왕복 굴착으로 시공이 번거롭고, 공기가 많이 소요된다.In particular, the tie bolt (3) and reinforced shotcrete (5) reinforcement of the tunnel pillar (10) are constructed integrally for the 1.0 to 3.0D area behind the tunnel face to ensure construction quality. Therefore, if the ground conditions of the tunnel pillar are poor, it is difficult to expect the bearing capacity of the pillar immediately after excavation, and there is a concern that the tunnel stability may be reduced, such as additional ground subsidence occurring due to the expansion of the pillar disturbance area. Therefore, for the pillar unsupported section of the subsequent tunnel (1b), excavation is performed while leaving some width, and then reinforced steel and shotcrete construction are performed at the rear to secure the bearing capacity, and then the remaining width is excavated and removed. Therefore, the construction is cumbersome due to the back-and-forth excavation, and it takes a lot of time.

한편, 터널 필라부(10)를 주로 보강하는 기존 터널 필라부 보강 공법은 필라부(10)에 강연선이나 강봉과 같은 타이볼트(3)를 설치하여 긴장하고 그라우팅함으로써 필라부(10)를 보강한다(도 4, 등록특허 제10-1353882호). Meanwhile, the existing tunnel pillar reinforcement method that mainly reinforces the tunnel pillar (10) reinforces the pillar (10) by installing tie bolts (3) such as steel wires or steel bars on the pillar (10) and applying tension and grouting (Fig. 4, Patent No. 10-1353882).

이러한 종래 기술은 후행터널(1b) 막장과 선행터널(1a) 막장 사이에서는 타이볼트(3)에 긴장력을 도입할 수 없으므로, 선행터널(1a) 내에서 필라부 무지보 구간이 발생한다. 또한, 타이볼트 보강 구조가 복잡하여 시공 난이도가 높고, 실제 터널 필라부 보강은 터널 막장 후방 1.0∼3.0D 구간에서 진행되므로 필라부에 즉시 지보력 발휘 효과를 기대하기 어려우며, 필라부 지반 교란 영역 확대가 불가피하다. 더욱이 타이볼트(3) 양단 지지부에 터널 굴착 중 지속적으로 과도한 지반하중이 작용할 경우, 타이볼트(3)의 단부나 지압판 손상에 의한 지보력 저하 우려가 있다.Since this conventional technology cannot introduce tension force to the tie bolt (3) between the face of the subsequent tunnel (1b) and the face of the preceding tunnel (1a), an unsupported section of the pillar occurs within the preceding tunnel (1a). In addition, the tie bolt reinforcement structure is complex, making construction difficult, and since the actual tunnel pillar reinforcement is performed in the 1.0 to 3.0D section behind the tunnel face, it is difficult to expect the pillar to immediately exert its bearing capacity, and the expansion of the pillar ground disturbance area is inevitable. Furthermore, if excessive ground load is continuously applied to the support portions of the tie bolts (3) at both ends during tunnel excavation, there is a concern that the bearing capacity may be reduced due to damage to the ends of the tie bolts (3) or the bearing plates.

상기와 같은 문제점을 해결하기 위하여 본 발명은 터널 필라부의 원지반 강도 및 터널 지보재의 최대 부재력을 활용하여 터널 굴착 즉시 조기에 복합 지지력을 발휘할 수 있는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공하고자 한다.In order to solve the above problems, the present invention provides a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a support beam that can exert a composite bearing capacity immediately after tunnel excavation by utilizing the original ground strength of the tunnel pillar and the maximum member strength of the tunnel support material.

바람직한 실시예에 따른 본 발명은 선행터널과 후행터널이 병렬 시공되는 근접병설터널의 시공 방법에 관한 것으로, (a) 선행터널을 굴착하는 단계; (b) 상기 선행터널의 내부면을 지지하는 복수 열의 제1강지보를 상호 이격되게 설치하는 단계; (c) 상기 굴착된 선행터널의 필라부가 형성될 일측에 타이볼트를 관입 시공하는 단계; (d) 양단부가 이웃하는 양측의 제1강지보에 지지되도록 상기 타이볼트의 선행터널 측 단부에 강지보 지압부재를 설치하는 단계; (e) 상기 선행터널의 내부면에 숏크리트를 타설하는 단계; (f) 후행터널을 굴착하여 상기 타이볼트의 후행터널 측 단부가 노출되도록 선행터널과의 사이에 상기 필라부를 형성하는 단계; (g) 상기 후행터널의 내부면을 지지하는 복수 열의 제2강지보를 상호 이격되게 설치하는 단계; (h) 양단부가 이웃하는 양측의 제2강지보에 지지되도록 상기 타이볼트의 후행터널 측 단부에 강지보 지압부재를 설치하는 단계; 및 (i) 상기 후행터널의 내부면에 숏크리트를 타설하는 단계; 를 포함하여 구성되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공한다.The present invention, according to a preferred embodiment, relates to a method for constructing a close-contact tunnel in which a preceding tunnel and a succeeding tunnel are constructed in parallel, comprising the steps of: (a) excavating a preceding tunnel; (b) installing a plurality of rows of first steel supports, which support the inner surface of the preceding tunnel, with a distance therebetween; (c) constructing tie bolts on one side of the excavated preceding tunnel where a pillar portion is to be formed; (d) installing a steel support bearing member on the end of the tie bolt on the preceding tunnel side so that both ends are supported by the first steel supports on both adjacent sides; (e) pouring shotcrete on the inner surface of the preceding tunnel; (f) excavating a succeeding tunnel so that the pillar portion is formed between the preceding tunnel and the succeeding tunnel by exposing the ends of the tie bolts on the succeeding tunnel side; (g) installing a plurality of rows of second steel supports, which support the inner surface of the succeeding tunnel, with a distance therebetween; (h) a step of installing a steel support bearing member on the end of the tie bolt on the subsequent tunnel side so that both ends are supported by the second steel support beams on both adjacent sides; and (i) a step of pouring shotcrete on the inner surface of the subsequent tunnel; a method for constructing a close-contact tunnel using a steel support tie bolt reinforcement system is provided.

다른 바람직한 실시예에 따른 본 발명은 상기 제1, 2강지보는 H형강이고, 상기 강지보 지압부재는 제1, 2강지보의 외측플랜지 내측면에 지지되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공한다.According to another preferred embodiment, the present invention provides a method for constructing a close-contact tunnel using a steel beam fastening tie bolt reinforcement system, characterized in that the first and second steel beams are H-shaped steel beams, and the steel beam pressure member is supported on the inner surface of the outer flange of the first and second steel beams.

다른 바람직한 실시예에 따른 본 발명은 상기 강지보 지압부재는 한 쌍의 플랜지와 상기 한 쌍의 플랜지 일단을 연결하는 웨브로 구성되어, 상기 웨브가 제1, 2강지보의 외측플랜지 내측면에 지지되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공한다.According to another preferred embodiment, the present invention provides a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a steel beam, characterized in that the steel beam support member is composed of a pair of flanges and a web connecting one end of the pair of flanges, and the web is supported on the inner surface of the outer flanges of the first and second steel beams.

다른 바람직한 실시예에 따른 본 발명은 상기 제1, 2강지보에는 배면은 제1, 2강지보의 외측플랜지 내측면에 밀착되고, 전면은 수직 방향으로 형성되어 상기 강지보 지압부재가 지지되는 받침부재가 더 구비되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공한다.According to another preferred embodiment, the present invention provides a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a steel beam, characterized in that the first and second steel beams further include a support member formed in a vertical direction with a back surface that is in close contact with the inner surface of the outer flange of the first and second steel beams and a front surface that supports the steel beam support member.

다른 바람직한 실시예에 따른 본 발명은 상기 받침부재는 상기 제1, 2강지보의 외측플랜지 내측면에 밀착되는 고정판, 상기 고정판의 상단 또는 하단에 회전 가능하게 결합되어 상기 강지보 지압부재가 지지되는 가동판 및 상기 고정판과 가동판 사이에 구비되어 가동판의 각도를 고정하는 각도조절부재로 구성되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공한다.According to another preferred embodiment, the present invention provides a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a steel beam, characterized in that the support member comprises a fixed plate that is in close contact with the inner surface of the outer flange of the first and second steel beams, a movable plate that is rotatably connected to the upper or lower end of the fixed plate to support the steel beam support member, and an angle adjusting member that is provided between the fixed plate and the movable plate to fix the angle of the movable plate.

다른 바람직한 실시예에 따른 본 발명은 상기 가동판의 전면 하부에는 상기 강지보 지압부재의 단부가 거치되는 거치부가 돌출 형성되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공한다.According to another preferred embodiment, the present invention provides a method for constructing a close-contact tunnel using a reinforcing tie bolt system for fastening a reinforcing bar, characterized in that a mounting portion on which an end of the reinforcing bar pressure member is mounted is protruded from the lower front surface of the movable plate.

본 발명에 따르면 터널 내부면을 지지하도록 터널 길이 방향을 따라 설치된 강지보 사이에 필라부 측으로 관입된 타이볼트의 단부가 관통되도록 강지보 지압부재를 설치함으로써, 타이볼트와 강지보가 복합 지보력을 발휘하여 필라부를 보강할 수 있는 근접병설터널 시공 방법을 제공할 수 있다.According to the present invention, a method for constructing a close-contact tunnel can be provided in which a tie bolt and a steel support beam exert a composite support force to reinforce a pillar section by installing a steel support beam bearing member so that the end of a tie bolt inserted toward a pillar section penetrates between steel support beams installed along the length of the tunnel to support the inner surface of the tunnel.

이에 따라 첫째, 터널 막장의 아칭 효과에 의한 지보력이 발휘되는 상태에서 조기에 터널 필라부를 보강함으로써 필라부 변형을 최소화하고, 최대 지보력을 발휘하여 필라부 교란 영역을 최소화할 수 있다.Accordingly, first, by reinforcing the tunnel pillar early in a state where the supporting force due to the arching effect of the tunnel face is exerted, the pillar deformation can be minimized, and the pillar disturbance area can be minimized by exerting the maximum supporting force.

둘째, 터널 필라부의 원지반 강도 및 터널 지보재의 최대 부재력을 활용하여 터널 굴착 즉시 조기에 복합 지지력을 발휘할 수 있다.Second, by utilizing the original ground strength of the tunnel pillar and the maximum member strength of the tunnel support material, the composite bearing capacity can be exerted immediately after tunnel excavation.

셋째, 일반적인 병설터널과 동일한 시공 공정을 적용하여 단순하고 반복적인 공정에 의해 근접병설터널을 시공할 수 있다.Third, a close parallel tunnel can be constructed through a simple and repetitive process by applying the same construction process as a general parallel tunnel.

도 1은 근접병설터널에서 필라부의 지반 이완 개념을 나타내는 도면.
도 2는 근접병설터널 굴착시 지반 응력을 나타내는 도면.
도 3은 종래 철근보강 숏크리트를 이용한 필라부 보강 공법을 도시하는 도면.
도 4는 종래 타이볼트 긴장에 의한 필라부 보강 공법을 도시하는 도면.
도 5는 본 발명에 의해 시공되는 근접병설터널을 도시하는 횡단면도.
도 6 내지 도 14는 각각 본 발명 근접병설터널 시공 방법의 단계별 공정을 도시하는 평단면도.
도 15는 강지보 지압부재에 의한 강지보와 타이볼트의 결합 관계를 도시하는 사시도.
도 16은 막장 아칭 효과를 도시하는 평단면도.
도 17은 강지보 지압부재와 강지보의 결합 관계를 도시하는 사시도.
도 18은 강지보 지압부재의 설치 상태를 도시하는 사시도.
도 19는 받침부재를 도시하는 사시도.
도 20은 받침부재에 의해 강지보 지압부재가 설치된 상태를 도시하는 단면도.
도 21은 받침부재에 의해 강지보 지압부재가 설치된 상태를 도시하는 사시도.
Figure 1 is a drawing showing the concept of ground relaxation of a pillar in a close-contact tunnel.
Figure 2 is a drawing showing ground stress during excavation of a close-contact tunnel.
Figure 3 is a drawing showing a conventional pillar reinforcement method using reinforced shotcrete.
Figure 4 is a drawing showing a conventional pillar reinforcement method using tie bolt tension.
Figure 5 is a cross-sectional view showing a close-contact tunnel constructed according to the present invention.
Figures 6 to 14 are cross-sectional views each showing a step-by-step process of the method for constructing a close-contact tunnel of the present invention.
Figure 15 is a perspective view showing the connection relationship between a support beam and a tie bolt by a support beam pressure member.
Figure 16 is a cross-sectional view showing the effect of the blind arching.
Figure 17 is a perspective view showing the connection relationship between the support member and the support member.
Figure 18 is a perspective view showing the installation state of the steel support pressure member.
Fig. 19 is a perspective view showing a supporting member.
Figure 20 is a cross-sectional view showing a state in which a support member is installed by a support member.
Figure 21 is a perspective view showing a state in which a support member is installed by a support member.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the attached drawings and preferred embodiments.

도 5는 본 발명에 의해 시공되는 근접병설터널을 도시하는 횡단면도이고, 도 6 내지 도 14는 각각 본 발명 근접병설터널 시공 방법의 단계별 공정을 도시하는 평단면도이다. 그리고 도 15는 강지보 지압부재에 의한 강지보와 타이볼트의 결합 관계를 도시하는 사시도이고, 도 16은 막장 아칭 효과를 도시하는 평단면도이다. Fig. 5 is a cross-sectional view illustrating a close-contact tunnel constructed according to the present invention, and Figs. 6 to 14 are plan sectional views illustrating step-by-step processes of the close-contact tunnel construction method of the present invention, respectively. Fig. 15 is a perspective view illustrating the connection relationship between a support beam and a tie bolt by a support pressure member, and Fig. 16 is a plan sectional view illustrating the face arching effect.

도 5, 도 6 내지 도 14 등에 도시된 바와 같이, 본 발명 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법은 선행터널(1a)과 후행터널(1b)이 병렬 시공되는 근접병설터널의 시공 방법에 관한 것으로, (a) 선행터널(1a)을 굴착하는 단계; (b) 상기 선행터널(1a)의 내부면을 지지하는 복수 열의 제1강지보(2a)를 상호 이격되게 설치하는 단계; (c) 상기 굴착된 선행터널(1a)의 필라부(10)가 형성될 일측에 타이볼트(3)를 관입 시공하는 단계; (d) 양단부가 이웃하는 양측의 제1강지보(2a)에 지지되도록 상기 타이볼트(3)의 선행터널(1a) 측 단부에 강지보 지압부재(4)를 설치하는 단계; (e) 상기 선행터널(1a)의 내부면에 숏크리트(5)를 타설하는 단계; (f) 후행터널(1b)을 굴착하여 상기 타이볼트(3)의 후행터널(1b) 측 단부가 노출되도록 선행터널(1a)과의 사이에 상기 필라부(10)를 형성하는 단계; (g) 상기 후행터널(1b)의 내부면을 지지하는 복수 열의 제2강지보(2b)를 상호 이격되게 설치하는 단계; (h) 양단부가 이웃하는 양측의 제2강지보(2b)에 지지되도록 상기 타이볼트(3)의 후행터널(1b) 측 단부에 강지보 지압부재(4)를 설치하는 단계; 및 (i) 상기 후행터널(1b)의 내부면에 숏크리트(5)를 타설하는 단계; 를 포함하여 구성되는 것을 특징으로 한다.As illustrated in FIGS. 5, 6 to 14, etc., a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a steel beam of the present invention relates to a method for constructing a close-contact tunnel in which a preceding tunnel (1a) and a succeeding tunnel (1b) are constructed in parallel, comprising the steps of: (a) excavating a preceding tunnel (1a); (b) installing a plurality of rows of first steel beams (2a) spaced apart from each other to support the inner surface of the preceding tunnel (1a); (c) constructing a tie bolt (3) by penetrating into one side of the excavated preceding tunnel (1a) where a pillar portion (10) is to be formed; (d) installing a steel beam bearing member (4) on the end of the tie bolt (3) on the preceding tunnel (1a) side so that both ends are supported by the first steel beams (2a) on both adjacent sides; (e) pouring shotcrete (5) onto the inner surface of the preceding tunnel (1a); (f) forming the pillar portion (10) between the preceding tunnel (1a) and the preceding tunnel (1b) by excavating the succeeding tunnel (1b) so that the succeeding tunnel (1b) side end of the tie bolt (3) is exposed; (g) installing a plurality of rows of second steel supports (2b) to support the inner surface of the succeeding tunnel (1b) at a distance from each other; (h) installing a steel support pressure member (4) at the succeeding tunnel (1b) side end of the tie bolt (3) so that both ends are supported by the adjacent second steel supports (2b) on both sides; and (i) pouring shotcrete (5) onto the inner surface of the succeeding tunnel (1b).

본 발명은 터널 필라부(10)의 원지반 강도 및 터널 지보재의 최대 부재력을 활용하여 터널 굴착 즉시 조기에 복합 지지력을 발휘할 수 있는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법을 제공하기 위한 것이다.The present invention provides a method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a support beam that can exert a composite support force immediately after tunnel excavation by utilizing the original ground strength of a tunnel pillar (10) and the maximum member strength of a tunnel support material.

본 발명은 선행터널(1a)과 후행터널(1b)이 병렬 시공되어 선행터널(1a)과 후행터널(1b) 사이에 필라부(10)가 형성되는 근접병설터널을 시공하기 위한 것이다.The present invention is for constructing a close parallel tunnel in which a preceding tunnel (1a) and a succeeding tunnel (1b) are constructed in parallel and a pillar (10) is formed between the preceding tunnel (1a) and the succeeding tunnel (1b).

본 발명은 터널 전체 구간에 적용될 수도 있고, 지반 조건에 따라 터널 일부 구간에만 적용될 수도 있다.The present invention may be applied to the entire tunnel section, or may be applied to only a portion of the tunnel section depending on ground conditions.

본 발명에서는 먼저 (a) 지반을 일정 깊이로 굴착하여 선행터널(1a)을 형성한다(도 6).In the present invention, first, (a) the ground is excavated to a certain depth to form a preliminary tunnel (1a) (Fig. 6).

이때 터널 굴착에 의한 필라부 손상 영역의 지반 이완을 최소화하여 원지반 강도 특성을 유지할 수 있도록 선행터널(1a)의 필라부(10) 굴착선 외측에 선형 방진공을 설치하여 진동 제어 발파에 의해 지반을 굴착할 수 있다.At this time, in order to minimize ground relaxation in the area of damage to the pilaster due to tunnel excavation and maintain the original ground strength characteristics, a linear vacuum hole is installed outside the excavation line of the pilaster (10) of the preceding tunnel (1a) so that the ground can be excavated by vibration-controlled blasting.

터널 단면이 큰 경우 상반과 하반을 나누어 분할 굴착할 수 있다.If the tunnel cross-section is large, it can be divided into upper and lower halves and excavated separately.

다음으로 (b) 상기 선행터널(1a)의 내부면을 지지하는 복수 열의 제1강지보(2a)를 상호 이격되게 설치한다(도 7).Next, (b) multiple rows of first reinforcement beams (2a) supporting the inner surface of the preceding tunnel (1a) are installed spaced apart from each other (Fig. 7).

상기 선행터널(1a)의 굴착과 함께 바로 후속하여 제1강지보(2a)를 설치한다.Immediately following the excavation of the above-mentioned preceding tunnel (1a), the first reinforcement beam (2a) is installed.

상기 제1강지보(2a)는 굴착 직후 터널 주변 지반의 이완을 최소화하고 굴착면의 과다한 초기 변위를 억제한다.The above first support beam (2a) minimizes the relaxation of the ground around the tunnel immediately after excavation and suppresses excessive initial displacement of the excavation surface.

상기 제1강지보(2a)는 터널 폭 방향으로 설치되는 것으로, 터널 형상에 대응되는 형상으로 형성되어 선행터널(1a)의 내부면을 지지한다.The above first support member (2a) is installed in the direction of the tunnel width, and is formed in a shape corresponding to the tunnel shape to support the inner surface of the preceding tunnel (1a).

상기 제1강지보(2a)는 터널 길이 방향으로 이격되도록 복수 개가 순차적으로 설치된다.The first support beam (2a) is installed sequentially in multiple pieces so as to be spaced apart in the direction of the tunnel length.

상기 제1강지보(2a)를 설치한 후에는 (c) 상기 굴착된 선행터널(1a)의 필라부(10)가 형성될 일측에 타이볼트(3)를 관입 시공한다(도 8).After installing the first reinforcement member (2a) above, (c) a tie bolt (3) is driven into one side of the excavated preceding tunnel (1a) where the pillar portion (10) will be formed (Fig. 8).

상기 타이볼트(3)는 이웃하는 제1강지보(2a) 사이에 시공될 수 있다.The above tie bolt (3) can be constructed between adjacent first reinforcement beams (2a).

그리고 (d) 양단부가 이웃하는 양측의 제1강지보(2a)에 지지되도록 상기 타이볼트(3)의 선행터널(1a) 측 단부에 강지보 지압부재(4)를 설치한다(도 9).And (d) a support member (4) is installed on the end of the preceding tunnel (1a) side of the tie bolt (3) so that both ends are supported by the first support members (2a) on both sides (Fig. 9).

상기 제1강지보(2a)와 타이볼트(3)를 시공한 후에는 상기 타이볼트(3)의 선행터널(1a) 측 단부에 강지보 지압부재(4)를 설치한다.After constructing the first support beam (2a) and tie bolt (3), a support beam pressure member (4) is installed on the end of the preceding tunnel (1a) side of the tie bolt (3).

상기 타이볼트(3)는 단부가 강지보 지압부재(4)를 관통하여 강지보 지압부재(4) 전면으로 돌출된다. 상기 타이볼트(3)의 돌출된 단부에 너트(31)를 체결할 수 있다. 필요에 따라 상기 너트(31)의 체결 전 지압판(32)을 설치할 수 있다(도 17).The above tie bolt (3) has an end that penetrates the steel support pressure member (4) and protrudes toward the front of the steel support pressure member (4). A nut (31) can be fastened to the protruding end of the tie bolt (3). If necessary, a pressure plate (32) can be installed before fastening the nut (31) (Fig. 17).

상기 강지보 지압부재(4)는 중앙에 상기 타이볼트(3)가 결합되고, 양단부는 양측의 제1강지보(2a)에 지지된다.The above-mentioned steel support pressure member (4) is connected to the tie bolt (3) in the center, and both ends are supported by the first steel support members (2a) on both sides.

이에 따라 상기 타이볼트(3)에 작용하는 하중은 강지보 지압부재(4)를 통해 제1강지보(2a)로 전달되어 타이볼트(3)와 제1강지보(2a)가 복합 지보력을 발휘할 수 있다.Accordingly, the load acting on the tie bolt (3) is transmitted to the first steel support beam (2a) through the steel support pressure member (4), so that the tie bolt (3) and the first steel support beam (2a) can exert a combined support force.

상기 제1강지보(2a)와 타이볼트(3) 및 강지보 지압부재(4)가 시공된 후에는 (e) 선행터널(1a)의 내부면에 숏크리트(5)를 타설한다(도 10).After the first support beam (2a), tie bolt (3), and support beam pressure member (4) are constructed, (e) shotcrete (5) is poured on the inner surface of the preceding tunnel (1a) (Fig. 10).

상기 숏크리트(5)는 경화 후 제1강지보(2a)와 일체화되어 지보 능력을 향상시킨다.The above shotcrete (5) is integrated with the first reinforcement (2a) after hardening to improve the support capacity.

후행터널(1b)의 시공 전 선행터널(1a)의 필라부(10) 측을 충분한 길이로 보강하기 위해 상기 (a) 단계 내지 (e) 단계를 1회 또는 2회 이상 반복 수행한다.In order to reinforce the pillar (10) side of the preceding tunnel (1a) to a sufficient length before construction of the subsequent tunnel (1b), steps (a) to (e) are repeated once or twice or more.

이후 (f) 후행터널(1b)을 굴착하여 상기 타이볼트(3)의 후행터널(1b) 측 단부가 노출되도록 선행터널(1a)과의 사이에 상기 필라부(10)를 형성한다(도 11).Afterwards, (f) the follow-up tunnel (1b) is excavated to form the pillar portion (10) between the follow-up tunnel (1b) and the preceding tunnel (1a) so that the follow-up tunnel (1b) side end of the tie bolt (3) is exposed (Fig. 11).

상기 후행터널(1b)은 선행터널(1a)과 일정 간격을 두고 후행 시공되며, 선행터널(1a)과 동일한 방식으로 굴착될 수 있다.The above-mentioned subsequent tunnel (1b) is constructed at a certain interval from the preceding tunnel (1a) and can be excavated in the same manner as the preceding tunnel (1a).

상기 후행터널(1b)이 굴착됨에 따라 선행터널(1a)과 후행터널(1b) 사이에 소정 폭을 갖는 필라부(10)가 형성된다.As the preceding tunnel (1b) is excavated, a pillar (10) having a predetermined width is formed between the preceding tunnel (1a) and the succeeding tunnel (1b).

이때, 상기 선행터널(1a) 시공시 후행터널(1b) 측으로 관입 시공했던 타이볼트(3)의 타단이 노출된다.At this time, the other end of the tie bolt (3) that was constructed to penetrate the subsequent tunnel (1b) during the construction of the preceding tunnel (1a) is exposed.

그리고 (g) 상기 후행터널(1b)의 내부면을 지지하는 복수 열의 제2강지보(2b)를 상호 이격되게 설치한다(도 12).And (g) multiple rows of second reinforcement beams (2b) supporting the inner surface of the above-mentioned rear tunnel (1b) are installed spaced apart from each other (Fig. 12).

상기 선행터널(1a)에서와 마찬가지로 후행터널(1b) 역시 굴착과 함께 바로 후속하여 제2강지보(2b)를 설치한다.As with the preceding tunnel (1a), the subsequent tunnel (1b) is also excavated and the second support beam (2b) is installed immediately thereafter.

상기 제2강지보(2b)는 터널 형상에 대응되는 형상으로 형성되어 후행터널(1b)의 내부면을 지지할 수 있다.The above second reinforcement (2b) is formed in a shape corresponding to the tunnel shape and can support the inner surface of the subsequent tunnel (1b).

이웃하는 제2강지보(2b) 사이에는 상기 타이볼트(3)의 타단이 돌출된다.The other end of the tie bolt (3) protrudes between the adjacent second support beams (2b).

그리고 (h) 양단부가 이웃하는 양측의 제2강지보(2b)에 지지되도록 상기 타이볼트(3)의 후행터널(1b) 측 단부에 강지보 지압부재(4)를 설치하고(도 13, 도 15), (i) 상기 후행터널(1b)의 내부면에 숏크리트(5)를 타설한다(도 14).And (h) a support member (4) is installed on the end of the tie bolt (3) on the side of the subsequent tunnel (1b) so that both ends are supported by the second support members (2b) on both sides (Fig. 13, Fig. 15), and (i) shotcrete (5) is poured on the inner surface of the subsequent tunnel (1b) (Fig. 14).

상기 제2강지보(2b)의 설치 후에는 이웃하는 제2강지보(2b) 사이에 돌출된 타이볼트(3)에 강지보 지압부재(4)를 설치한다.After the installation of the second support beam (2b) above, a support beam pressure member (4) is installed on the tie bolt (3) protruding between the adjacent second support beams (2b).

상기 강지보 지압부재(4)는 양단이 제2강지보(2b)에 지지되고, 강지보 지압부재(4)를 관통한 타이볼트(3)의 단부에는 너트(31)가 체결된다.The above-mentioned steel support member (4) is supported on both ends by the second steel support member (2b), and a nut (31) is fastened to the end of the tie bolt (3) that penetrates the steel support member (4).

상기 강지보 지압부재(4)의 설치 직후 바로 타이볼트(3)와 제2강지보(2b)가 복합 지보력을 발휘하여 필라부(10)를 보강한다.Immediately after the installation of the above-mentioned steel support pressure member (4), the tie bolt (3) and the second steel support (2b) exert a combined support force to reinforce the pillar (10).

따라서 후행터널(1b) 굴착시 필라부(10)에 무지보 구간이 발생하지 않는다.Therefore, when excavating the subsequent tunnel (1b), no unsupported section is created in the pillar (10).

상기 제2강지보(2b)는 후행터널(1b)의 굴착과 동시에 설치되어 막장(100) 직후방까지 매우 근접하여 설치될 수 있다. 그러므로 터널 막장(100) 자체의 종방향 아칭 효과에 의한 지보력과 제2강지보(2b)와 타이볼트(3)에 의한 지보력이 복합적으로 작용하여 최대 지보력을 발휘할 수 있다(도 16). 아울러 필라부 교란 영역의 응력을 원지반 수준으로 이동하여 필라부 교란 영역을 최소화하고, 필라부(10)의 변형을 최소화할 수 있다.The above second support beam (2b) can be installed simultaneously with the excavation of the subsequent tunnel (1b) and can be installed very close to the face (100). Therefore, the support strength due to the longitudinal arching effect of the tunnel face (100) itself and the support strength due to the second support beam (2b) and tie bolts (3) can work in combination to exert maximum support strength (Fig. 16). In addition, the stress in the pillar disturbance area can be moved to the original ground level, thereby minimizing the pillar disturbance area and minimizing deformation of the pillar (10).

본 발명에서는 상기 타이볼트(3)를 강지보 지압부재(4)에 의해 강지보에 연결하여 즉시 지보력을 발휘할 수 있다. 그러므로 천공장비가 별도로 투입되고 공기가 많이 소요되는 록볼트의 시공이 필요 없다. 다만 필라부(10) 외 부분은 록볼트(11)를 시공할 수 있다(도 5). 그리고 필라부(10) 측면에 더미를 남기지 않고 일괄 굴착 가능하여 공기를 단축할 수 있다.In the present invention, the tie bolt (3) is connected to the support beam by the support pressure member (4), enabling immediate application of support force. Therefore, there is no need for separate drilling equipment and the construction of rock bolts, which consume a lot of air. However, rock bolts (11) can be installed in areas other than the pillar (10) (Fig. 5). In addition, since excavation can be performed in one go without leaving a pile on the side of the pillar (10), the construction period can be shortened.

이와 같이 선행터널(1a)과 후행터널(1b)이 근접하여 폭이 좁은 필라부(10)를 형성하는 경우에도 후행터널(1b) 굴착과 동시에 즉시 필라부(10)를 보강할 수 있다. 그러므로 선행터널(1a)과 후행터널(1b)이 충분히 이격된 일반적인 병설터널과 동일한 순서로 단순하고 반복적인 공정에 의해 시공 가능하고, 기존 근접병설터널에 비해 공기를 크게 단축할 수 있다.Even in this case where the preceding tunnel (1a) and the succeeding tunnel (1b) are close together to form a narrow pillar (10), the pillar (10) can be reinforced immediately at the same time as the excavation of the succeeding tunnel (1b). Therefore, the preceding tunnel (1a) and succeeding tunnel (1b) can be constructed through a simple and repetitive process in the same order as a typical parallel tunnel with sufficient separation between them, and the construction period can be significantly shortened compared to the existing close parallel tunnel.

도 17은 강지보 지압부재와 강지보의 결합 관계를 도시하는 사시도이고, 도 18은 강지보 지압부재의 설치 상태를 도시하는 사시도이다. Figure 17 is a perspective view showing the connection relationship between the support member and the support member, and Figure 18 is a perspective view showing the installation state of the support member.

도 17, 도 18에 도시된 바와 같이, 상기 제1, 2강지보(2a, 2b)는 H형강이고, 상기 강지보 지압부재(4)는 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 지지될 수 있다.As shown in FIGS. 17 and 18, the first and second support beams (2a, 2b) are H-shaped steel, and the support beam pressure member (4) can be supported on the inner surface of the outer flange (21) of the first and second support beams (2a, 2b).

상기 제1, 2강지보(2a, 2b)는 한 쌍의 플랜지(21, 22)와 상기 플랜지(21, 22)의 중앙을 연결하는 웨브(23)로 구성된 H형강일 수 있다.The above first and second support members (2a, 2b) may be H-shaped steel members composed of a pair of flanges (21, 22) and a web (23) connecting the centers of the flanges (21, 22).

상기 제1, 2강지보(2a, 2b)의 외측플랜지(21)는 터널 내면에 밀착될 수 있다.The outer flange (21) of the first and second reinforcements (2a, 2b) can be in close contact with the inner surface of the tunnel.

이를 위해 H형강인 상기 제1, 2강지보(2a, 2b)는 터널 형상에 따라 만곡되게 형성 가능하다.For this purpose, the first and second H-shaped steel beams (2a, 2b) can be formed to be curved according to the shape of the tunnel.

상기 제1, 2강지보(2a, 2b)와 강지보 지압부재(4)를 시공한 후에는 선후행터널(1a, 1b)의 내부면에 숏크리트(5)가 타설되어, 상기 제1, 2강지보(2a, 2b)와 강지보 지압부재(4)가 숏크리트(5) 내부에 매립된다.After the first and second support beams (2a, 2b) and the support pressure member (4) are constructed, shotcrete (5) is poured onto the inner surface of the preceding and succeeding tunnels (1a, 1b), so that the first and second support beams (2a, 2b) and the support pressure member (4) are embedded within the shotcrete (5).

이때 상기 숏크리트(5)의 두께를 최소화하여 숏크리트(5) 물량을 줄일 수 있도록 상기 강지보 지압부재(4)는 제1, 2강지보(2a, 2b)의 내부 즉, 외측플랜지(21)와 내측플랜지(22) 사이에 삽입하여 외측플랜지(21) 내측면에 지지되게 할 수 있다.At this time, in order to minimize the thickness of the shotcrete (5) and reduce the amount of shotcrete (5), the steel support bearing member (4) can be inserted into the inside of the first and second steel supports (2a, 2b), that is, between the outer flange (21) and the inner flange (22), so as to be supported on the inner surface of the outer flange (21).

여기서 외측은 필라부(10) 측, 내측은 터널 내부 측을 의미한다.Here, the outer side refers to the side of the pillar (10), and the inner side refers to the inside of the tunnel.

상기 강지보 지압부재(4)는 한 쌍의 플랜지(41)와 상기 한 쌍의 플랜지(41) 일단을 연결하는 웨브(42)로 구성되어, 상기 웨브(42)가 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 지지될 수 있다.The above-mentioned steel support member (4) is composed of a pair of flanges (41) and a web (42) connecting one end of the pair of flanges (41), so that the web (42) can be supported on the inner surface of the outer flange (21) of the first and second steel support members (2a, 2b).

상기 강지보 지압부재(4)는 H형강인 제1, 2강지보(2a, 2b)에 지지가 용이하면서도 적절한 강성을 발휘할 수 있고, 타이볼트(3)를 쉽게 체결할 수 있도록 ㄷ자 형강으로 구성할 수 있다.The above-mentioned steel support member (4) can be configured as a T-shaped steel so that it can easily support the first and second steel support members (2a, 2b) which are H-shaped steel while exhibiting appropriate rigidity, and so that the tie bolt (3) can be easily fastened.

즉, 상기 강지보 지압부재(4)는 상부와 하부의 플랜지(41)와 상기 한 쌍의 플랜지(41) 일단을 연결하는 웨브(42)로 구성될 수 있다. 상기 웨브(42)는 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 지지되고, 상기 플랜지(41)는 웨브(42) 전면으로 돌출되어 휨 강성을 발휘할 수 있다.That is, the above-mentioned steel support member (4) may be composed of upper and lower flanges (41) and a web (42) connecting one end of the pair of flanges (41). The web (42) is supported on the inner surface of the outer flange (21) of the first and second steel support members (2a, 2b), and the flange (41) protrudes to the front of the web (42) to exert bending rigidity.

상기 타이볼트(3)에 작용하는 하중은 강지보 지압부재(4)의 휨 및 전단 강성에 의해 이웃하는 제1, 2강지보(2a, 2b)로 전달된다.The load applied to the above tie bolt (3) is transmitted to the neighboring first and second steel supports (2a, 2b) by the bending and shear rigidity of the steel support pressure member (4).

상기 타이볼트(3)는 강지보 지압부재(4)의 웨브(42)를 관통하고, 상기 웨브(42)의 내측에서 너트(31)가 타이볼트(3)의 단부에 나사 결합될 수 있다.The above tie bolt (3) penetrates the web (42) of the steel support pressure member (4), and a nut (31) can be screwed to the end of the tie bolt (3) on the inside of the web (42).

도 19는 받침부재를 도시하는 사시도이고, 도 20은 받침부재에 의해 강지보 지압부재가 설치된 상태를 도시하는 단면도이며, 도 21은 받침부재에 의해 강지보 지압부재가 설치된 상태를 도시하는 사시도이다. Fig. 19 is a perspective view showing a supporting member, Fig. 20 is a cross-sectional view showing a state in which a support member is installed by a supporting member, and Fig. 21 is a perspective view showing a state in which a support member is installed by a supporting member.

도 19 내지 도 21에 도시된 바와 같이, 상기 제1, 2강지보(2a, 2b)에는 배면은 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 밀착되고, 전면은 수직 방향으로 형성되어 상기 강지보 지압부재(4)가 지지되는 받침부재(6)가 더 구비될 수 있다.As shown in FIGS. 19 to 21, the first and second support members (2a, 2b) may further be provided with a support member (6) whose back surface is in close contact with the inner surface of the outer flange (21) of the first and second support members (2a, 2b) and whose front surface is formed in a vertical direction to support the support member pressure member (4).

터널 굴착 단면은 보통 반원형, 마제형, 원형 등으로 형성된다.The tunnel excavation cross-section is usually formed in a semicircular, round, or oval shape.

이에 상기 타이볼트(3)는 필라부(10)를 좌우로 관통하여 수평 방향으로 설치되는 반면, 제1, 2강지보(2a, 2b)는 터널의 굴착 단면 형상을 따라 적절하게 만곡되어 형성된다. 그러므로 타이볼트(3)가 설치되는 위치에 따라 타이볼트(3) 방향과 타이볼트(3)가 결합되는 위치에서 제1, 2강지보(2a, 2b)의 접선 방향이 직각을 이루지 않아 상호 비스듬하게 결합될 수 있다.Accordingly, the tie bolt (3) is installed horizontally by penetrating the pillar (10) from left to right, while the first and second support beams (2a, 2b) are formed to be appropriately curved along the excavated cross-section shape of the tunnel. Therefore, depending on the position where the tie bolt (3) is installed, the direction of the tie bolt (3) and the tangent direction of the first and second support beams (2a, 2b) at the position where the tie bolt (3) is joined may not be perpendicular, and thus they may be joined at an angle to each other.

이때 상기 타이볼트(3)에 강지보 지압부재(4)가 결합되는 위치에서 너트(31) 또는 지압판(32)이 강지보 지압부재(4)의 웨브(42) 내측면에 밀착되지 못하여 하중을 제대로 전달하기 어려울 수 있다.At this time, at the position where the support member (4) is connected to the tie bolt (3), the nut (31) or the support plate (32) may not be in close contact with the inner surface of the web (42) of the support member (4), making it difficult to properly transmit the load.

따라서 상기 제1, 2강지보(2a, 2b)의 경사각과 상관없이 강지보 지압부재(4)가 타이볼트(3)와 직교하는 방향으로 배치될 수 있도록 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측에 받침부재(6)가 구비될 수 있다.Accordingly, regardless of the inclination angle of the first and second support beams (2a, 2b), a support member (6) may be provided on the inner side of the outer flange (21) of the first and second support beams (2a, 2b) so that the support pressure member (4) can be arranged in a direction perpendicular to the tie bolt (3).

상기 받침부재(6)는 전면은 수직 방향으로 형성되어 강지보 지압부재(4)의 웨브(42)가 밀착되어 지지되고, 배면은 타이볼트(3)가 결합되는 위치에서 제1, 2강지보(2a, 2b)의 기울기와 대응되는 경사면으로 형성되어 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 밀착된다.The front surface of the above-mentioned support member (6) is formed in a vertical direction so that the web (42) of the support member (4) is supported in close contact with it, and the back surface is formed as an inclined surface corresponding to the inclination of the first and second support members (2a, 2b) at the position where the tie bolt (3) is coupled, so that it is in close contact with the inner surface of the outer flange (21) of the first and second support members (2a, 2b).

상기 받침부재(6)는 제1, 2강지보(2a, 2b)에 용접 또는 볼팅 등에 의해 고정 가능하다.The above support member (6) can be fixed to the first and second support members (2a, 2b) by welding or bolting.

상기 받침부재(6)는 상기 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 밀착되는 고정판(61), 상기 고정판(61)의 상단 또는 하단에 회전 가능하게 결합되어 상기 강지보 지압부재(4)가 지지되는 가동판(62) 및 상기 고정판(61)과 가동판(62) 사이에 구비되어 가동판(62)의 각도를 고정하는 각도조절부재(63)로 구성될 수 있다.The above-mentioned support member (6) may be composed of a fixed plate (61) that is in close contact with the inner surface of the outer flange (21) of the first and second reinforcement members (2a, 2b), a movable plate (62) that is rotatably connected to the upper or lower end of the fixed plate (61) and supports the reinforcement support pressure member (4), and an angle adjusting member (63) that is provided between the fixed plate (61) and the movable plate (62) and fixes the angle of the movable plate (62).

상기 제1, 2강지보(2a, 2b)는 터널 형상에 대응되도록 만곡되게 형성되므로 높이에 따라 기울기가 변화된다. 이 경우 상기 제1, 2강지보(2a, 2b)의 기울기에 따라 기울기가 상이한 받침부재(6)를 사용해야 하므로 번거로울 수 있다.The above first and second supporting members (2a, 2b) are formed to be curved to correspond to the shape of the tunnel, so that their inclinations change according to the height. In this case, it may be cumbersome to use a support member (6) with a different inclination depending on the inclination of the first and second supporting members (2a, 2b).

따라서 상기 받침부재(6)를 가변형으로 구성하여 제1, 2강지보(2a, 2b)의 기울기에 따라 받침부재(6)의 각도를 조절 가능하도록 구성할 수 있다.Accordingly, the support member (6) can be configured to be variable so that the angle of the support member (6) can be adjusted according to the inclination of the first and second reinforcements (2a, 2b).

이를 위해 상기 받침부재(6)는 고정판(61)과 가동판(62)을 회전 가능하게 결합하되, 상기 고정판(61)과 가동판(62) 사이에 각도를 조절하여 고정할 수 있는 각도조절부재(63)가 구비될 수 있다.To this end, the support member (6) may be configured to rotatably connect a fixed plate (61) and a movable plate (62), and an angle adjustment member (63) may be provided between the fixed plate (61) and the movable plate (62) to adjust the angle and fix them.

상기 고정판(61)은 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 밀착되는 것으로, 외측플랜지(21)에 용접이나 볼팅 등으로 고정될 수 있다.The above fixed plate (61) is in close contact with the inner surface of the outer flange (21) of the first and second reinforcements (2a, 2b), and can be fixed to the outer flange (21) by welding or bolting.

상기 가동판(62)은 고정판(61)의 상단이나 하단 중 어느 하나에 상하로 회전 가능하게 결합되는 것으로, 전면에 강지보 지압부재(4)가 밀착 설치된다.The above movable plate (62) is rotatably connected to either the upper or lower end of the fixed plate (61), and a strong support pressure member (4) is installed in close contact on the front.

상기 고정판(61)이 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측에 고정되고, 가동판(62)이 수직 방향을 이룬 상태에서 각도조절부재(63)가 고정판(61)과 가동판(62)의 각도를 고정할 수 있다.The above fixed plate (61) is fixed to the inner side of the outer flange (21) of the first and second reinforcements (2a, 2b), and the movable plate (62) is in a vertical direction, and the angle adjustment member (63) can fix the angle of the fixed plate (61) and the movable plate (62).

이를 위해 상기 각도조절부재(63)는 길이 조절 가능하게 구성될 수 있다.For this purpose, the angle adjustment member (63) can be configured to be adjustable in length.

예를 들어 상기 각도조절부재(63)는 일단이 고정판(61)에 힌지 결합되는 제1지지바(631), 일단이 가동판(62)에 힌지 결합되는 제2지지바(632) 및 상기 제1지지바(631)와 제2지지바(632)를 연결하는 커플러(633)로 구성될 수 있다.For example, the angle adjustment member (63) may be composed of a first support bar (631) having one end hinged to a fixed plate (61), a second support bar (632) having one end hinged to a movable plate (62), and a coupler (633) connecting the first support bar (631) and the second support bar (632).

상기 커플러(633)를 회전시켜 가동판(62)의 각도를 조절할 수 있다.The angle of the movable plate (62) can be adjusted by rotating the above coupler (633).

도 19 등에 도시된 바와 같이, 상기 가동판(62)은 상단이 고정판(61)의 상단에 회전 가능하게 결합될 수 있다.As shown in Fig. 19, the movable plate (62) can be rotatably connected to the upper end of the fixed plate (61).

상기 가동판(62)의 전면 하부에는 상기 강지보 지압부재(4)의 단부가 거치되는 거치부(621)가 돌출 형성될 수 있다.A mounting portion (621) on which the end of the above-mentioned strong support pressure member (4) is mounted can be protruded and formed on the lower front side of the above-mentioned movable plate (62).

상기 제1, 2강지보(2a, 2b)와 강지보 지압부재(4)는 숏크리트(5) 내부에 매립되어 일체화된다. 그러므로 상기 강지보 지압부재(4)는 숏크리트(5) 경화 전까지 제1, 2강지보(2a, 2b)에 가고정되면 된다.The above first and second reinforcing members (2a, 2b) and the reinforcing member bearing member (4) are embedded in the shotcrete (5) and become one. Therefore, the reinforcing member bearing member (4) may be temporarily fixed to the first and second reinforcing members (2a, 2b) until the shotcrete (5) hardens.

그런데 상기 강지보 지압부재(4)가 받침부재(6)의 가동판(62) 전면에 단순 밀착될 경우, 타이볼트(3)에 너트(31)를 체결하여 강지보 지압부재(4)를 받침부재(6) 측으로 가압하기 전까지 강지보 지압부재(4)의 위치를 가고정하기 어렵다. 그리고 너트(31)를 체결하기 위해서는 강지보 지압부재(4)를 고정하는 1인과 너트(31)를 체결하는 1인, 총 2인의 작업자가 필요하다.However, if the above-mentioned steel support pressure member (4) is simply pressed against the front surface of the movable plate (62) of the support member (6), it is difficult to temporarily fix the position of the steel support pressure member (4) until the nut (31) is fastened to the tie bolt (3) to pressurize the steel support pressure member (4) toward the support member (6). In addition, in order to fasten the nut (31), a total of two workers are required, one to fix the steel support pressure member (4) and one to fasten the nut (31).

따라서 상기 강지보 지압부재(4)의 설치시 강지보 지압부재(4)의 위치를 가고정할 수 있도록 가동판(62)의 하단 전면에 거치부(621)를 돌출 형성할 수 있다.Therefore, when installing the above-mentioned steel support pressure member (4), a mounting portion (621) can be formed protrudingly on the lower front surface of the movable plate (62) so that the position of the steel support pressure member (4) can be temporarily fixed.

상기 가동판(62)은 수직 방향으로 구비되므로, 상기 거치부(621)는 가동판(62)의 하단에서 수평 방향으로 절곡되어 형성될 수 있다.Since the above movable plate (62) is provided in a vertical direction, the above-mentioned mounting portion (621) can be formed by bending in a horizontal direction at the lower end of the movable plate (62).

이에 따라 상기 가동판(62)의 거치부(621) 상면에 강지보 지압부재(4)를 거치한 상태에서 타이볼트(3)에 너트(31)를 체결할 수 있으므로, 작업자 1인이 강지보 지압부재(4)를 신속하게 설치할 수 있다.Accordingly, the nut (31) can be fastened to the tie bolt (3) while the steel support pressure member (4) is placed on the upper surface of the mounting portion (621) of the movable plate (62), so that one worker can quickly install the steel support pressure member (4).

1a: 선행터널 1b: 후행터널
10: 필라부 100: 막장
11: 록볼트 2a: 제1강지보
2b: 제2강지보 21: 외측플랜지
22: 내측플랜지 23: 웨브
3: 타이볼트 31: 너트
32: 지압판 4: 강지보 지압부재
41: 플랜지 42: 웨브
5: 숏크리트 6: 받침부재
61: 고정판 62: 가동판
621: 거치부 63: 각도조절부재
631: 제1지지바 632: 제2지지바
633: 커플러
1a: Preceding tunnel 1b: Following tunnel
10: Philaboo 100: The End
11: Rock Bolt 2a: 1st Reinforcement
2b: Second reinforcement 21: Outer flange
22: Inner flange 23: Web
3: Tie bolt 31: Nut
32: Acupressure plate 4: Gangjibo acupressure member
41: Flange 42: Web
5: Shotcrete 6: Supporting member
61: Fixed plate 62: Movable plate
621: Mounting part 63: Angle adjustment member
631: 1st support bar 632: 2nd support bar
633: Coupler

Claims (6)

선행터널(1a)과 후행터널(1b)이 병렬 시공되는 근접병설터널의 시공 방법에 관한 것으로,
(a) 선행터널(1a)을 굴착하는 단계;
(b) 상기 선행터널(1a)의 내부면을 지지하는 복수 열의 제1강지보(2a)를 상호 이격되게 설치하는 단계;
(c) 상기 굴착된 선행터널(1a)의 필라부(10)가 형성될 일측에 타이볼트(3)를 관입 시공하는 단계;
(d) 양단부가 이웃하는 양측의 제1강지보(2a)에 지지되도록 상기 타이볼트(3)의 선행터널(1a) 측 단부에 강지보 지압부재(4)를 설치하는 단계;
(e) 상기 선행터널(1a)의 내부면에 숏크리트(5)를 타설하는 단계;
(f) 후행터널(1b)을 굴착하여 상기 타이볼트(3)의 후행터널(1b) 측 단부가 노출되도록 선행터널(1a)과의 사이에 상기 필라부(10)를 형성하는 단계;
(g) 상기 후행터널(1b)의 내부면을 지지하는 복수 열의 제2강지보(2b)를 상호 이격되게 설치하는 단계;
(h) 양단부가 이웃하는 양측의 제2강지보(2b)에 지지되도록 상기 타이볼트(3)의 후행터널(1b) 측 단부에 강지보 지압부재(4)를 설치하는 단계; 및
(i) 상기 후행터널(1b)의 내부면에 숏크리트(5)를 타설하는 단계; 를 포함하여 구성되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법.
This relates to a construction method of a close parallel tunnel in which a preceding tunnel (1a) and a succeeding tunnel (1b) are constructed in parallel.
(a) A step of excavating a preceding tunnel (1a);
(b) A step of installing multiple rows of first reinforcement beams (2a) that support the inner surface of the preceding tunnel (1a) at a distance from each other;
(c) A step of constructing a tie bolt (3) by penetrating one side of the excavated preceding tunnel (1a) where the pillar portion (10) is to be formed;
(d) a step of installing a support bearing member (4) on the end of the preceding tunnel (1a) side of the tie bolt (3) so that both ends are supported by the first support beams (2a) on both sides;
(e) A step of pouring shotcrete (5) on the inner surface of the preceding tunnel (1a);
(f) A step of forming the pillar portion (10) between the preceding tunnel (1a) and the subsequent tunnel (1b) by excavating the subsequent tunnel (1b) so that the subsequent tunnel (1b) side end of the tie bolt (3) is exposed;
(g) A step of installing multiple rows of second reinforcement beams (2b) that support the inner surface of the above-mentioned rear tunnel (1b) at a distance from each other;
(h) a step of installing a support bearing member (4) on the end of the rear tunnel (1b) side of the tie bolt (3) so that both ends are supported by the second support beams (2b) on both sides; and
(i) A method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a steel beam, characterized in that it comprises a step of pouring shotcrete (5) on the inner surface of the above-mentioned subsequent tunnel (1b);
제1항에서,
상기 제1, 2강지보(2a, 2b)는 H형강이고, 상기 강지보 지압부재(4)는 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 지지되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법.
In paragraph 1,
A method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening steel beams, characterized in that the first and second steel beams (2a, 2b) are H-shaped steel beams, and the steel beam pressure member (4) is supported on the inner surface of the outer flange (21) of the first and second steel beams (2a, 2b).
제2항에서,
상기 강지보 지압부재(4)는 한 쌍의 플랜지(41)와 상기 한 쌍의 플랜지(41) 일단을 연결하는 웨브(42)로 구성되어, 상기 웨브(42)가 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 지지되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법.
In paragraph 2,
A method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening steel beams, characterized in that the above-mentioned steel beam pressure member (4) is composed of a pair of flanges (41) and a web (42) connecting one end of the pair of flanges (41), and the web (42) is supported on the inner surface of the outer flange (21) of the first and second steel beams (2a, 2b).
제2항에서,
상기 제1, 2강지보(2a, 2b)에는 배면은 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 밀착되고, 전면은 수직 방향으로 형성되어 상기 강지보 지압부재(4)가 지지되는 받침부재(6)가 더 구비되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법.
In paragraph 2,
A method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening steel beams, characterized in that the first and second steel beams (2a, 2b) further include a support member (6) formed in a vertical direction on the front surface so as to be in close contact with the inner surface of the outer flange (21) of the first and second steel beams (2a, 2b) and to support the steel beam support member (4).
제4항에서,
상기 받침부재(6)는 상기 제1, 2강지보(2a, 2b)의 외측플랜지(21) 내측면에 밀착되는 고정판(61), 상기 고정판(61)의 상단 또는 하단에 회전 가능하게 결합되어 상기 강지보 지압부재(4)가 지지되는 가동판(62) 및 상기 고정판(61)과 가동판(62) 사이에 구비되어 가동판(62)의 각도를 고정하는 각도조절부재(63)로 구성되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법.
In paragraph 4,
A method for constructing a close-contact tunnel using a tie bolt reinforcement system for fastening a steel beam, characterized in that the support member (6) is composed of a fixed plate (61) that is in close contact with the inner surface of the outer flange (21) of the first and second steel beams (2a, 2b), a movable plate (62) that is rotatably connected to the upper or lower end of the fixed plate (61) to support the steel beam pressure member (4), and an angle adjusting member (63) that is provided between the fixed plate (61) and the movable plate (62) to fix the angle of the movable plate (62).
제5항에서,
상기 가동판(62)의 전면 하부에는 상기 강지보 지압부재(4)의 단부가 거치되는 거치부(621)가 돌출 형성되는 것을 특징으로 하는 강지보 체결 타이볼트 보강 시스템을 이용한 근접병설터널 시공 방법.
In paragraph 5,
A method for constructing a close-contact tunnel using a steel beam fastening tie bolt reinforcement system, characterized in that a mounting portion (621) on which an end of the steel beam pressure member (4) is mounted is protruded on the front lower portion of the above movable plate (62).
KR1020240010261A 2024-01-23 2024-01-23 Construction method of narrow-pillar tunnel using reinforcing system Pending KR20250115166A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020240010261A KR20250115166A (en) 2024-01-23 2024-01-23 Construction method of narrow-pillar tunnel using reinforcing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020240010261A KR20250115166A (en) 2024-01-23 2024-01-23 Construction method of narrow-pillar tunnel using reinforcing system

Publications (1)

Publication Number Publication Date
KR20250115166A true KR20250115166A (en) 2025-07-30

Family

ID=96584609

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020240010261A Pending KR20250115166A (en) 2024-01-23 2024-01-23 Construction method of narrow-pillar tunnel using reinforcing system

Country Status (1)

Country Link
KR (1) KR20250115166A (en)

Similar Documents

Publication Publication Date Title
CN111395351B (en) Assembled supporting structure of foundation pit and supporting construction method
CN106968257B (en) Concrete-fabricated profile steel mixed supporting system for ultra-large deep foundation pit and construction method thereof
KR102129608B1 (en) Semi open cut type tunnel construction method at low overburden
CN102418345B (en) Apparatus for fixing steel wire of wale
JP2006517628A (en) Prestressed temporary structure
CN108868834B (en) Temporary support device for tunnel arch wall primary support intrusion limit arch changing construction
CN113944479B (en) Poor geological tunnel three-fork construction method
KR102484548B1 (en) Support Structure for Tunnel and Construction Method for the same
KR20250115166A (en) Construction method of narrow-pillar tunnel using reinforcing system
CN217976269U (en) Novel steel-concrete superimposed sleeve lining for tunnel
JP2006502324A (en) Prestressed temporary construction method
JP2019157550A (en) Construction method of underground structure
CN212316935U (en) Disassembly-free support rod piece and foundation pit supporting system
JP4332074B2 (en) Tunnel structure using synthetic segment and its design method
JP4465459B2 (en) PC plate for lining and mounting structure of PC plate for lining
JP4505105B2 (en) Shield tunnel lining method and lining structure thereof
CN116025008A (en) Large-span underground space combined pipe-jacking pipe segment structure connecting system and construction method
JPS62202121A (en) Jack-up method for shore strut
JP2725972B2 (en) Underground structure construction method and segment piece used therefor
CN111379572A (en) Formwork trolley for underground engineering construction and beam column construction method thereof
DE69218195T2 (en) LONG-SHAPED COVER OF LARGE DIAMETER AND MANUFACTURING PROCESS
JP3406370B2 (en) Horizontal shaft construction method
JP3192982B2 (en) Simple steel panel for tunnel liner and its mounting device
CN212772373U (en) Assembled bearing structure of foundation ditch
US2234782A (en) Fabricated metal structure

Legal Events

Date Code Title Description
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PG1501 Laying open of application

St.27 status event code: A-1-1-Q10-Q12-nap-PG1501

Q12 Application published

Free format text: ST27 STATUS EVENT CODE: A-1-1-Q10-Q12-NAP-PG1501 (AS PROVIDED BY THE NATIONAL OFFICE)