[go: up one dir, main page]

KR20170107117A - the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same - Google Patents

the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same Download PDF

Info

Publication number
KR20170107117A
KR20170107117A KR1020160030209A KR20160030209A KR20170107117A KR 20170107117 A KR20170107117 A KR 20170107117A KR 1020160030209 A KR1020160030209 A KR 1020160030209A KR 20160030209 A KR20160030209 A KR 20160030209A KR 20170107117 A KR20170107117 A KR 20170107117A
Authority
KR
South Korea
Prior art keywords
column
concrete
plate
bracket
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
KR1020160030209A
Other languages
Korean (ko)
Other versions
KR101844343B1 (en
Inventor
홍원기
김선국
Original Assignee
경희대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 경희대학교 산학협력단 filed Critical 경희대학교 산학협력단
Priority to KR1020160030209A priority Critical patent/KR101844343B1/en
Publication of KR20170107117A publication Critical patent/KR20170107117A/en
Application granted granted Critical
Publication of KR101844343B1 publication Critical patent/KR101844343B1/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • E04B1/40
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

본 발명은 기둥하부콘크리트(110)와 기둥하부철근(120) 그리고 상기 기둥하부철근(120)의 상단이 결합된 기둥하부플레이트(130)를 포함하여 구성되는 하부PC기둥(100);
기둥상부콘크리트(210)와 기둥상부철근(220) 그리고 상기 기둥상부철근(220)의 하단이 결합된 기둥상부플레이트(230)를 포함하여 구성되는 상부PC기둥(200);
상기 기둥하부플레이트(130)와 상기 기둥상부플레이트(230) 사이에 설치되는 필러플레이트(PP);
상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 상기 기둥상부플레이트(230)의 단부에 설치되는 보거치브래킷(300);
보콘크리트(410)와 상기 보콘크리트(410) 상부 단부로 돌출된 보상부철골(490)을 포함하여 구성되는 PC보(400);
를 포함하여 구성되되,
상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고,
상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결되며,
상기 보상부철골(490)과 상기 기둥브래킷(290)은 콘크리트(미도시) 타설시 함께 타설되어 강접합을 실현하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공한다.
더불어 상기 기둥상부콘크리트(210) 내부에는 상부에 플레이트가 접합되고 하부가 상기 기둥상부플레이트(230)의 상부에 접합된 기둥중심철골(250);이 포함되고, 상기 기둥중심철골(250)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공하며,
또한 상기 기둥상부콘크리트(210) 외면에는 보연결기둥철근(270);이 돌출되어, 상기 보연결기둥철근(270)에 보상부철근(450)이 철근이음되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공한다.
The present invention relates to a lower PC column 100 comprising a column lower concrete 110, a column lower reinforcement 120 and a column lower plate 130 coupled with the upper ends of the column lower reinforcement 120;
An upper PC column 200 including a column upper concrete 210, a column upper reinforcement 220 and a column upper plate 230 coupled with a lower end of the column upper reinforcement 220;
A filler plate (PP) installed between the column lower plate (130) and the column upper plate (230);
A bracket bracket 300 installed at an end of the column top plate 230 protruded outward from the outer surface of the column top concrete 210;
A PC beam 400 including beam concrete 410 and a compensating section steel frame 490 protruding to an upper end of the beam concrete 410;
, ≪ / RTI >
The lower end of the beam concrete 410 is mounted on the beam bracket 300,
The compensating part steel frame 490 is fastened to a column bracket 290 protruding outside the outer surface of the columnar concrete 210,
The reinforcing portion steel frame 490 and the column bracket 290 are disposed together when the concrete (not shown) is poured, thereby realizing a strong bonding. The reinforcing steel frame 490 and the column bracket 290 are formed of a steel- A joint structure, and a method of constructing a steel joint structure using the same.
And a column center frame 250 in which a plate is joined to an upper portion of the column top concrete 210 and a lower portion thereof is joined to an upper portion of the column top plate 230. In the column center frame 250, The present invention provides a rigid joint structure of a steel-concrete hybrid PC column and a PC beam, and a method of constructing a rigid joint structure using the same, wherein one end of the column bracket 290 is joined.
And a reinforcing steel reinforcing bar 450 is joined to the reinforcing reinforcing steel reinforcing bars 450 on the outer surface of the column upper concrete 210. [ - It provides strong jointing structure of concrete hybrid PC column and PC beam, and a method of constructing strong jointing structure using it.

Description

접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법{the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same}This paper describes a rigid connection structure between a steel column and concrete hybrid PC column and PC beam with joints placed thereon, and a rigid connection structure between the rigid connection structure and a rigid connection structure using the same}

본 발명은 기둥과 보의 접합부를 개선하여 건식공법으로 모멘트 접합방식을 구현하되 PC기둥에 설치된 시공성이 증대된 PC보거치플레이트를 선택적으로 활용한 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법에 관한 것이다.The present invention relates to a steel-concrete hybrid PC column and a PC beam with a joining portion selectively installed using a PC beam mounting plate installed on a PC column to implement a moment bonding method by improving a joining portion between a column and a beam And a method of constructing a steel joint structure using the same.

근래에는 시공성을 확보하고 공기를 절감하기 위하여 PC(precast concrete) 공법의 사용이 증대되고 있다.In recent years, the use of PC (precast concrete) method has been increasing in order to secure workability and to save air.

종래의 PC공법은 (1) PC보를 PC기둥에 단순 거치하는 공법, (2) PC기둥-PC보 부재를 일체식으로 타설하는 공법 등이 주로 사용된다.Conventional PC method is mainly used for (1) simple installation of PC beams on PC columns, and (2) construction of PC columns and PC beams in one body.

상기 (1) PC보를 PC기둥에 단순 거치하는 공법은,(1) The method of simply mounting the PC beam on the PC column,

현재 많이 사용되고 있는 공법 중의 하나로써 공기가 다소 절감되기는 하지만, 지진 등 횡력이 작용할 때에는 기둥-보 접합부가 단순접합이므로 모멘트를 전달할 수 없게 된다. 따라서 추가로 횡력보강 수단인 전단벽, 브레이스 등을 설치해야 함으로 공기절감을 위해 계획된 PC공법의 장점에 부응하지 못하고 공사비 및 공기의 증가가 불가피하다. Although the air is somewhat reduced as one of the currently used methods, when a lateral force such as an earthquake acts, the column-to-beam connection is simply connected, and the moment can not be transmitted. Therefore, it is necessary to install a shear wall, brace, etc., which is a lateral reinforcement means, so that it is inevitable to increase the construction cost and air without meeting the merit of the PC method planned for air saving.

또한 PC기둥에 단순 거치된 PC보는 기둥-보 접합부의 이탈로 안전사고의 원인이 될 수 있다. 따라서 기둥-보 접합부에 구조적 불안정이 야기될 가능성 때문에 고층 구조물에는 사용이 제한되고 있는 실정이다.In addition, a PC mounted on a PC column may cause a safety accident due to the deviation of the column-to-beam connection. Therefore, the use of high - rise structures is limited due to the possibility of structural instability in column - beam connections.

상기 (2) PC기둥-PC보 부재를 일체식으로 타설하는 공법은,The above-mentioned (2) method of integrally installing the PC column -PC beam member,

접합부를 콘크리트를 타설하게 되는 데, 콘크리트 양생에 따른 공기지연 및 양생기간 중 기둥-보 접합부에 구조적 불안정이 야기될 가능성 때문에 고층 구조물에는 사용이 제한되고 있는 실정이다.The use of concrete in the high-rise structure is limited due to the possibility of structural instability in the column-beam connection during the air delay and curing period due to concrete curing.

이와 같은 종래의 PC공법의 단점을 해결하고자,In order to solve the drawbacks of the conventional PC method,

최근 모멘트 접합방식의 PC공법의 연구자 활발히 이루어지고 있으나 시공상세가 복잡하며 경제성이 낮고 시공성이 떨어지는 등 여러 가지 단점때문에 넓게, 특히 고층 구조물에는 사용되기 어렵다.Recently, researchers of the PC method of the moment joint method have been actively carried out, but it is difficult to use it widely, especially in high-rise structures due to various disadvantages such as complicated construction details, low economic efficiency and poor workability.

이에 본 발명자는 건식 시공방식이면서 추가적인 전단벽(거푸집 및 습식공법)이나 브레이스 등 횡력보강 수단의 설치를 배제할 수 있는 모멘트 저항골조를 제안하여, 기둥-보 접합부가 볼트로 체결 된 후에는 접합부, 슬래브 등의 타설 없이 프리캐스트 골조의 프레임 시공이 진행 될 수 있기 때문에 철골공사의 유사한 공기와 시공성을 구현할 수 있게 된다. 특히 미숙련공도 매뉴얼만 숙지하면 안전하고 빠르게 시공할 수 있는 PC공법을 제안하기에 이르렀다.Therefore, the present inventor proposed a moment-resisting framework capable of eliminating the installation of the lateral shear reinforcement means such as an additional shear wall (formwork and wet construction method) or a brace while being dry type, and after the column- The frame construction of the precast framing can be carried out without piling, so that similar air and workability of the steel frame construction can be realized. Especially, unskilled workers have come to propose a PC construction method that can be done safely and quickly when only the manual is known.

[문헌 1] 대한민국 등록특허 제10-1289934호 프리캐스트 SRC기둥과 프리캐스트 SRC보의 포스트텐션 압착식 접합구조물 및 그 접합구조물의 시공방법, 2013.07.25.[Patent Document 1] Korean Registered Patent No. 10-1289934 Post-tensioned compression bonded joint structure of precast SRC column and precast SRC beam, and method of constructing the jointed structure, 2013.07.25. [문헌 2] 대한민국 등록특허 제10-1369998호 철골기둥 접합용 철골 일체형 합성PC기둥과 이를 이용한 복합기둥 시공방법, 2014.03.06[Patent Document 2] Korean Registered Patent No. 10-1369998 A steel frame integrated steel column for joining a steel column, and a method for constructing a composite column using the same, 2014.03.06

본 발명은 상기한 바와 같은 종래의 제반 문제점을 해소하기 위해서 제시되는 것으로써,Disclosure of Invention Technical Problem [8] The present invention has been made in order to solve the above-mentioned problems of the related art,

기둥과 보의 접합부를 개선하여 건식공법으로 모멘트 접합방식을 구현하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공하고자 한다.We propose a rigid joint structure of steel - concrete hybrid PC columns and PC beams, and a method of constructing a rigid joint structure using the joints, which improves the joints of columns and beams and implements the moment - joint method by dry method.

상기한 기술적 과제를 해결하기 위해 본 발명은 기둥하부콘크리트(110)와 기둥하부철근(120) 그리고 상기 기둥하부철근(120)의 상단이 결합된 기둥하부플레이트(130)를 포함하여 구성되는 하부PC기둥(100);The present invention is directed to a lower PC 130 including a column lower concrete 110, a lower column reinforcement 120, and a column lower plate 130 coupled to upper ends of the lower column reinforcement 120, A column 100;

기둥상부콘크리트(210)와 기둥상부철근(220) 그리고 상기 기둥상부철근(220)의 하단이 결합된 기둥상부플레이트(230)를 포함하여 구성되는 상부PC기둥(200);An upper PC column 200 including a column upper concrete 210, a column upper reinforcement 220 and a column upper plate 230 coupled with a lower end of the column upper reinforcement 220;

상기 기둥하부플레이트(130)와 상기 기둥상부플레이트(230) 사이에 설치되는 필러플레이트(PP);A filler plate (PP) installed between the column lower plate (130) and the column upper plate (230);

상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 상기 기둥상부플레이트(230)의 단부에 설치되는 보거치브래킷(300);A bracket bracket 300 installed at an end of the column top plate 230 protruded outward from the outer surface of the column top concrete 210;

보콘크리트(410)와 상기 보콘크리트(410) 상부 단부로 돌출된 보상부철골(490)을 포함하여 구성되는 PC보(400);A PC beam 400 including beam concrete 410 and a compensating section steel frame 490 protruding to an upper end of the beam concrete 410;

를 포함하여 구성되되,, ≪ / RTI >

상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고,The lower end of the beam concrete 410 is mounted on the beam bracket 300,

상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결되며,The compensating part steel frame 490 is fastened to a column bracket 290 protruding outside the outer surface of the columnar concrete 210,

상기 보상부철골(490)과 상기 기둥브래킷(290)은 콘크리트(미도시) 타설시 함께 타설되어 강접합을 실현하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공한다.The reinforcing portion steel frame 490 and the column bracket 290 are disposed together when the concrete (not shown) is poured, thereby realizing a strong bonding. The reinforcing steel frame 490 and the column bracket 290 are formed of a steel- A joint structure, and a method of constructing a steel joint structure using the same.

더불어 상기 기둥상부콘크리트(210) 내부에는 상부에 플레이트가 접합되고 하부가 상기 기둥상부플레이트(230)의 상부에 접합된 기둥중심철골(250);이 포함되고, 상기 기둥중심철골(250)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공하며,And a column center frame 250 in which a plate is joined to an upper portion of the column top concrete 210 and a lower portion thereof is joined to an upper portion of the column top plate 230. In the column center frame 250, The present invention provides a rigid joint structure of a steel-concrete hybrid PC column and a PC beam, and a method of constructing a rigid joint structure using the same, wherein one end of the column bracket 290 is joined.

또한 상기 기둥상부콘크리트(210) 외면에는 보연결기둥철근(270);이 돌출되어, 상기 보연결기둥철근(270)에 보상부철근(450)이 철근이음되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공한다.And a reinforcing steel reinforcing bar 450 is joined to the reinforcing reinforcing steel reinforcing bars 450 on the outer surface of the column upper concrete 210. [ - It provides strong jointing structure of concrete hybrid PC column and PC beam, and a method of constructing strong jointing structure using it.

본 발명에 따르면 기둥과 보의 접합부를 개선하여 건식공법으로 모멘트 접합방식을 구현하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법을 제공한다.According to the present invention, a rigid joint structure of a steel-concrete hybrid PC column and a PC beam, in which a joint for implementing a moment joining method is improved by improving a joining portion between a column and a beam, and a construction method of a rigid joint structure using the joining structure to provide.

도 1 내지 13은 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정을 순서대로 도시한 것이다.
도 14는 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법에서 PC기둥의 실시예를 도시한 것이다.
도 15 내지 16은 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정의 다른 실시예를 도시한 것이다.
도 17 내지 18은 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정의 다른 실시예를 도시한 것이다.
도 19는 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정의 다른 실시예를 도시한 것이다.
FIGS. 1 to 13 show a steel joint structure of a steel-concrete hybrid PC column and a PC beam with joints of the present invention installed, and a construction process of a steel joint joint structure using the same.
FIG. 14 is a view showing an embodiment of a PC column in a steel jointed structure of a steel-concrete hybrid PC column and a PC beam in which a joint part of the present invention is installed, and a method of constructing a steel jointed structure using the same.
FIGS. 15 to 16 show another embodiment of a steel joint assembly of a steel-concrete hybrid PC column and a PC beam with joints of the present invention, and a construction method of a steel joint assembly structure using the same.
FIGS. 17 to 18 show another embodiment of a construction method of a steel-concrete hybrid PC column and a PC beam having a joining portion of the present invention installed thereon, and a construction method of a steel-joint joining structure using the same.
19 is a view showing another embodiment of the construction process of the steel joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint part of the present invention is installed, and the construction method of the steel joint joint structure using the same.

이하 첨부한 도면과 함께 상기와 같은 본 발명의 개념이 바람직하게 구현된 실시예를 통하여 본 발명을 더욱 상세하게 설명한다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 13은 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정을 순서대로 도시한 것이다.FIGS. 1 to 13 show a steel joint structure of a steel-concrete hybrid PC column and a PC beam with joints of the present invention installed, and a construction process of a steel joint joint structure using the same.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는, The rigid joint structure of steel-concrete hybrid PC columns and PC beams with joints of the present invention,

기둥하부콘크리트(110)와 기둥하부철근(120) 그리고 상기 기둥하부철근(120)의 상단이 결합된 기둥하부플레이트(130)를 포함하여 구성되는 하부PC기둥(100);A lower PC column 100 including a column lower concrete 110, a column lower bar 120, and a column lower plate 130 coupled with the upper ends of the column lower bar 120;

기둥상부콘크리트(210)와 기둥상부철근(220) 그리고 상기 기둥상부철근(220)의 하단이 결합된 기둥상부플레이트(230)를 포함하여 구성되는 상부PC기둥(200);An upper PC column 200 including a column upper concrete 210, a column upper reinforcement 220 and a column upper plate 230 coupled with a lower end of the column upper reinforcement 220;

상기 기둥하부플레이트(130)와 상기 기둥상부플레이트(230) 사이에 설치되는 필러플레이트(PP);A filler plate (PP) installed between the column lower plate (130) and the column upper plate (230);

상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 상기 기둥상부플레이트(230)의 단부에 설치되는 보거치브래킷(300);A bracket bracket 300 installed at an end of the column top plate 230 protruded outward from the outer surface of the column top concrete 210;

보콘크리트(410)와 상기 보콘크리트(410) 상부 단부로 돌출된 보상부철골(490)을 포함하여 구성되는 PC보(400);A PC beam 400 including beam concrete 410 and a compensating section steel frame 490 protruding to an upper end of the beam concrete 410;

를 포함하여 구성되되,, ≪ / RTI >

상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고,The lower end of the beam concrete 410 is mounted on the beam bracket 300,

상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결되며,The compensating part steel frame 490 is fastened to a column bracket 290 protruding outside the outer surface of the columnar concrete 210,

상기 보상부철골(490)과 상기 기둥브래킷(290)은 콘크리트(미도시) 타설시 함께 타설되어 강접합을 실현하는 것을 특징으로 한다.The compensating section steel frame 490 and the column bracket 290 are poured together when concrete (not shown) is poured to realize a strong joint.

그리고 도시되지는 않았으나,And although not shown,

상기 PC보(400)는 단부에 보하부철근(420)이 돌출되고,The PC beam 400 has a beam lower reinforcing bar 420 protruding from its end,

상기 보하부철근(420)이 상기 기둥상부콘크리트(210) 측면에 돌출된 연결철근(미도시)에 커플러로 결합될 수 있다.The beam lower reinforcing bars 420 may be coupled to coupling reinforcing bars (not shown) protruding from the side of the column upper concrete 210 as couplers.

구체적으로 도 2에 도시된 바와 같이,Specifically, as shown in FIG. 2,

상기 기둥상부콘크리트(210) 내부에는 상부에 플레이트가 접합되고 하부가 상기 기둥상부플레이트(230)의 상부에 접합된 기둥중심철골(250);이 포함되고,A column center frame 250 having a plate joined to an upper portion of the column top concrete 210 and a lower portion joined to an upper portion of the column top plate 230,

상기 기둥중심철골(250)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 한다.And one end of the column bracket 290 is connected to the column center frame 250.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은,A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;

(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;

(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the bracket to the column bracket 290;

(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;

(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);

(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(6) Concrete pouring step for pouring concrete (not shown);

(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

상기 보단부플레이트(500)는 도 13과 같이 실링(S) 처리하여 고정한다.The lower end plate 500 is fixed by sealing (S) treatment as shown in FIG.

그리고 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joining portion of the present invention installed,

상기 기둥상부콘크리트(210) 외면에는 보연결기둥철근(270);이 돌출되어, 상기 보연결기둥철근(270)에 보상부철근(450)이 철근이음되는 것을 특징으로 한다.A beam connecting column reinforcing bar 270 protrudes on an outer surface of the column upper concrete 210 so that the compensating reinforcing bar 450 is reinforced to the beam connecting column reinforcing bar 270.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은,A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;

(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;

(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;

(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;

(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);

(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(6) Concrete pouring step for pouring concrete (not shown);

(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

그리고 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 도 2에 도시된 바와 같이,As shown in FIG. 2, the steel-concrete hybrid PC column and the PC beam with the joining portion of the present invention installed thereon,

상기 기둥상부철근(220)의 하부는 직선으로 상기 기둥상부플레이트(230) 하부로 돌출되어 너트로 결합되고,The lower portion of the columnar reinforcing bar 220 is linearly protruded to the lower portion of the column upper plate 230 and coupled with a nut,

상기 기둥하부철근(120)의 상부는 굽혀져 상단이 상기 기둥하부플레이트(130) 상부로 돌출되어 너트로 결합되므로,Since the upper portion of the columnar lower reinforcing bar 120 is bent and the upper end thereof is protruded to the upper portion of the column lower plate 130,

상부로 돌출된 너트 결합부위가 서로 간섭되지 않고 상기 필러플레이트(PP)의 구멍에 삽입되는 것을 특징으로 한다.And the nut coupling portions projected upward are inserted into the holes of the filler plate PP without interfering with each other.

또한 상기 기둥하부플레이트(130) 상부에는 내부볼트(IR);가 돌출되어,An inner bolt (IR) protrudes above the column lower plate 130,

상기 내부볼트(IR)가 상기 필러플레이트(PP)를 관통하여 상기 기둥상부플레이트(230)에 체결되므로,Since the inner bolt (IR) passes through the filler plate (PP) and is fastened to the column top plate (230)

상기 내부볼트(IR)가 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130) 상호간의 접촉면이 이격되는 것을 방지하여 수직 및 수평 하중을 전달함과 동시에 기둥 하중에 의해 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130)에 발생하는 변위를 감소시키는 것을 특징으로 한다. The inner bolt IR prevents the contact surface between the column top plate 230, the filler plate PP and the column bottom plate 130 from being separated from each other, thereby transmitting the vertical and horizontal loads, The displacement generated in the column top plate 230, the filler plate PP, and the column bottom plate 130 is reduced.

그리고 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 도시되지는 않았으나, 상기 기둥상부콘크리트(210) 하부 측면에 개구부(미도시);를 형성하고, Although not shown, the steel joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint part of the present invention is installed is formed by forming an opening (not shown) on the lower side of the columnar concrete 210,

상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후,After a nut is fastened to the upper end of the inner bolt (IR) through the opening (not shown)

상기 개구부(미도시)를 그라우팅(G);할 수 있다.And grouting (G) the opening (not shown).

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은,A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;

(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;

(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;

(4) 상기 개구부(O)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후 상기 개구부(O)를 그라우팅(G)하는 그라우팅단계;(4) a grouting step of grouting (G) the opening (O) after fastening a nut to the upper end of the inner bolt (IR) through the opening (O);

(5) 상기 (2) 내지 (4)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(5) repeating the steps (2) to (4) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;

(6) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (6) installing a lower end plate (500) in the bracket bracket (300) so as to close between the end of the beam concrete (410) and the outer surface of the column top concrete (210);

(7) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(7) Concrete pouring step for pouring concrete (not shown);

(8) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(8) disassembly of the lower end plate 500 during curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

본 발명은 도 6에 도시된 바와 같이,The present invention, as shown in FIG. 6,

상기 PC보(400)는,The PC beam 400,

상기 보콘크리트(410) 하부 단부에 보강플레이트(430);가 결합되고,A reinforcing plate 430 is coupled to the lower end of the beam concrete 410,

상기 보강플레이트(430)에 보하부철근(420)이 접합되어,The beam lower reinforcing bars 420 are joined to the reinforcing plate 430,

상기 보강플레이트(430)가 상기 보거치브래킷(300)과의 접촉에서 상기 보콘트리트(410)의 파손을 방지하는 것을 특징으로 할 수 있다.And the reinforcing plate 430 prevents breakage of the beam 410 by contact with the beam bracket 300.

도 14는 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법에서 PC기둥의 실시예를 도시한 것이다.FIG. 14 is a view showing an embodiment of a PC column in a steel jointed structure of a steel-concrete hybrid PC column and a PC beam in which a joint part of the present invention is installed, and a method of constructing a steel jointed structure using the same.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 상기 하부PC기둥(100) 상단부터 하단까지 기둥하부철골(152);이 설치되고,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joining portion of the present invention installed is provided with a column lower steel frame 152 from the upper end to the lower end of the lower PC column 100,

상기 기둥중심철골(250); 대신에 상기 상부PC기둥(200) 상단부터 하단까지 기둥상부철골(252);이 설치되며,The column center frame 250; Instead, an upper column steel frame 252 is installed from the upper end to the lower end of the upper PC column 200,

상기 기둥상부철골(252)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 한다.And one end of the column bracket 290 is joined to the column top steel frame 252.

도 15 내지 16은 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정의 다른 실시예를 도시한 것이다.FIGS. 15 to 16 show another embodiment of a steel joint assembly of a steel-concrete hybrid PC column and a PC beam with joints of the present invention, and a construction method of a steel joint assembly structure using the same.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 기둥콘크리트(110`)와 기둥철근(120`)을 포함하여 구성되는 PC기둥(100`);The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint part of the present invention is installed is composed of a PC column 100 'comprising a column concrete 110' and a columnar bar 120 ';

상기 기둥콘크리트(110`) 외면 밖으로 돌출되게 설치되는 보거치브래킷(300`);A bracket bracket 300 'installed so as to protrude from the outer surface of the column concrete 110';

보콘크리트(410)와 상기 보콘크리트(410) 상부 단부로 돌출된 보상부철골(490)을 포함하여 구성되는 PC보(400); A PC beam 400 including beam concrete 410 and a compensating section steel frame 490 protruding to an upper end of the beam concrete 410;

를 포함하여 구성되되,, ≪ / RTI >

상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고,The lower end of the beam concrete 410 is mounted on the beam bracket 300 '

상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결되며,The compensating part steel frame 490 is fastened to a column bracket 290 protruding from the outer surface of the column concrete 110 '

상기 보상부철골(490)과 상기 기둥브래킷(290)은 콘크리트(미도시) 타설시 함께 타설되어 강접합을 실현하는 것을 특징으로 한다. The compensating section steel frame 490 and the column bracket 290 are poured together when concrete (not shown) is poured to realize a strong joint.

그리고 상기 기둥콘크리트(110`) 내부에는 상부에 플레이트가 접합된 기둥중심철골(250);이 포함되고,And a column center frame 250 having an upper plate joined to the inside of the column concrete 110 '

상기 기둥중심철골(250)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 한다.And one end of the column bracket 290 is connected to the column center frame 250.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은, A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';

(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 ', and the compensating section steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step for joining the projected column bracket 290;

(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;

(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');

(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(5) Concrete pouring step for pouring concrete (not shown);

(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

또한 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 상기 기둥콘크리트(110`) 외면에는 보연결기둥철근(270);이 돌출되어, 상기 보연결기둥철근(270)에 보상부철근(450)이 철근이음되는 것을 특징으로 한다.In addition, the steel joint structure of the steel-concrete hybrid PC column and the PC beam with the joining portion of the present invention installed therein is formed such that a beam connecting column reinforcing bar 270 protrudes from the outer surface of the column concrete 110 ' And the compensating reinforcing bars 450 are joined to the reinforcing bars.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은, A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';

(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 ', and the compensating section steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening them to the protruded column brackets 290;

(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;

(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');

(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(5) Concrete pouring step for pouring concrete (not shown);

(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

도 17 내지 18은 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정의 다른 실시예를 도시한 것이다.FIGS. 17 to 18 show another embodiment of a construction method of a steel-concrete hybrid PC column and a PC beam having a joining portion of the present invention installed thereon, and a construction method of a steel-joint joining structure using the same.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 상기 기둥중심철골(250); 대신에 상기 PC기둥(100`) 상단부터 하단까지 기둥철골(252`);이 설치되며,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joining portion of the present invention installed is the same as the column center steel frame 250; Instead, a column steel frame 252 'is installed from the top to the bottom of the PC column 100'

상기 기둥철골(252`)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 한다.And one end of the column bracket 290 is joined to the column steel frame 252 '.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은, A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';

(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 ', and the compensating section steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step for joining the projected column bracket 290;

(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;

(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');

(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(5) Concrete pouring step for pouring concrete (not shown);

(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

그리고 도시되지는 않았으나, 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는 상기 보거치브래킷(300)은 생략되고, 상기 보콘크리트(410)의 하부 단부는 상기 기둥상부플레이트(230) 단부에 거치되는 것을 특징으로 한다.Although not shown, in the steel joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint of the present invention is installed, the beam bracket 300 is omitted, and the lower end of the beam concrete 410 And is mounted on the end of the column top plate 230.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은, A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;

(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;

(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 기둥상부플레이트(230) 단부에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is mounted on the end of the column upper plate 230, and the compensating part steel frame 490 is moved outside the column top concrete 210 A PC beam joining step for joining the projected column bracket 290;

(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;

(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);

(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(6) Concrete pouring step for pouring concrete (not shown);

(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

도 19는 본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조, 이를 이용한 강접합 결합구조의 시공방법의 시공과정의 다른 실시예를 도시한 것이다.19 is a view showing another embodiment of the construction process of the steel joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint part of the present invention is installed, and the construction method of the steel joint joint structure using the same.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조는상기 보거치브래킷(300`) 대신에 상기 기둥콘크리트(110`) 외면에 돌출된 코벨(300``)이 형성되고,The steel joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint part of the present invention is installed has a structure in which a cobble 300 '' protruding from the outer surface of the column concrete 110 'is used instead of the beam bracket 300' Formed,

상기 보콘크리트(410)의 하부 단부는 상기 코벨(300``) 상부에 거치되는 것을 특징으로 한다.The lower end of the beam concrete 410 is mounted on the upper portion of the coble 300 '.

본 발명의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법은, A method of constructing a steel joint-bonded structure using a steel-joint hybrid structure of a steel-concrete hybrid PC column and a PC beam in which a joint of the present invention is installed,

상기 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint is installed is used,

(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';

(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 코벨(300``) 상부에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is mounted on the upper part of the coble 300 ', and the compensating part steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step for joining the projected column bracket 290;

(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;

(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계; (4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');

(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;(5) Concrete pouring step for pouring concrete (not shown);

(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);

를 포함하여 구성되는 것을 특징으로 한다.And a control unit.

본 발명은 상기에서 언급한 바와 같이 바람직한 실시예와 관련하여 설명되었으나, 본 발명의 요지를 벗어남이 없는 범위 내에서 다양한 수정 및 변형이 가능하며, 다양한 분야에서 사용 가능하다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the invention.

따라서 본 발명의 청구범위는 이건 발명의 진정한 범위 내에 속하는 수정 및 변형을 포함한다.It is therefore intended that the appended claims cover such modifications and variations as fall within the true scope of the invention.

PP: 필러플레이트
IR: 내부볼트
G: 그라우팅
100: 하부PC기둥
100`: PC기둥
110: 기둥하부콘크리트
110`: 기둥콘크리트
120: 기둥하부철근
120`: 기둥철근
130: 기둥하부플레이트
152: 기둥하부철골
200: 상부PC기둥
210: 기둥상부콘크리트
220: 기둥상부철근
230: 기둥상부플레이트
250: 기둥중심철골
252: 기둥상부철골
252`: 기둥철골
270: 보연결기둥철근
290: 기둥브래킷
300, 300`: 보거치브래킷
300``: 코벨
400: PC보
410: 보콘크리트
420: 보하부철근
430: 보강플레이트
450: 보상부철근
490: 보상부철골
PP: filler plate
IR: internal bolt
G: Grouting
100: Lower PC column
100`: PC column
110: Column lower concrete
110`: column concrete
120: Column lower bar
120 `: pillar rebar
130: column bottom plate
152: column lower steel frame
200: Top PC column
210: Columnar concrete
220: Upper column bracing
230: column top plate
250: column center steel frame
252: Upper column steel frame
252 `: column steel frame
270: beam connection pillar
290: Column bracket
300, 300`: Bracket bracket
300``: Korb
400: PC Bo
410: beam concrete
420: Beam bottom reinforcement
430: reinforcing plate
450: Reinforcing section reinforcing bar
490: Compensation department steel

Claims (38)

기둥하부콘크리트(110)와 기둥하부철근(120) 그리고 상기 기둥하부철근(120)의 상단이 결합된 기둥하부플레이트(130)를 포함하여 구성되는 하부PC기둥(100);
기둥상부콘크리트(210)와 기둥상부철근(220) 그리고 상기 기둥상부철근(220)의 하단이 결합된 기둥상부플레이트(230)를 포함하여 구성되는 상부PC기둥(200);
상기 기둥하부플레이트(130)와 상기 기둥상부플레이트(230) 사이에 설치되는 필러플레이트(PP);
상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 상기 기둥상부플레이트(230)의 단부에 설치되는 보거치브래킷(300);
보콘크리트(410)와 상기 보콘크리트(410) 상부 단부로 돌출된 보상부철골(490)을 포함하여 구성되는 PC보(400);
를 포함하여 구성되되,
상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고,
상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결되며,
상기 보상부철골(490)과 상기 기둥브래킷(290)은 콘크리트(미도시) 타설시 함께 타설되어 강접합을 실현하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
A lower PC column 100 including a column lower concrete 110, a column lower bar 120, and a column lower plate 130 coupled with the upper ends of the column lower bar 120;
An upper PC column 200 including a column upper concrete 210, a column upper reinforcement 220 and a column upper plate 230 coupled with a lower end of the column upper reinforcement 220;
A filler plate (PP) installed between the column lower plate (130) and the column upper plate (230);
A bracket bracket 300 installed at an end of the column top plate 230 protruded outward from the outer surface of the column top concrete 210;
A PC beam 400 including beam concrete 410 and a compensating section steel frame 490 protruding to an upper end of the beam concrete 410;
, ≪ / RTI >
The lower end of the beam concrete 410 is mounted on the beam bracket 300,
The compensating part steel frame 490 is fastened to a column bracket 290 protruding outside the outer surface of the columnar concrete 210,
The reinforcing portion steel frame 490 and the column bracket 290 are disposed together when the concrete (not shown) is poured, thereby realizing a strong bonding. The reinforcing steel frame 490 and the column bracket 290 are formed of a steel- Bond structure.
제1항에서,
상기 기둥상부콘크리트(210) 내부에는 상부에 플레이트가 접합되고 하부가 상기 기둥상부플레이트(230)의 상부에 접합된 기둥중심철골(250);이 포함되고,
상기 기둥중심철골(250)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
The method of claim 1,
A column center frame 250 having a plate joined to an upper portion of the column top concrete 210 and a lower portion joined to an upper portion of the column top plate 230,
Wherein a column bracket (290) is coupled to the column center frame (250), and one end of the column bracket (290) is joined to the column center frame frame (250).
제1항 또는 제2항에서,
상기 기둥상부콘크리트(210) 외면에는 보연결기둥철근(270);이 돌출되어,
상기 보연결기둥철근(270)에 보상부철근(450)이 철근이음되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method according to claim 1 or 2,
A beam connecting column reinforcing bar 270 protrudes on the outer surface of the column top concrete 210,
And the compensating reinforcing bars 450 are joined to the reinforcing reinforcing reinforcing bars 450 by the reinforcing reinforcing bars 450. The reinforced reinforcing bars 450 are joined to the reinforcing reinforcing bars 450 by reinforcing bars.
제1항 또는 제2항에서,
상기 기둥상부철근(220)의 하부는 직선으로 상기 기둥상부플레이트(230) 하부로 돌출되어 너트로 결합되고,
상기 기둥하부철근(120)의 상부는 굽혀져 상단이 상기 기둥하부플레이트(130) 상부로 돌출되어 너트로 결합되므로,
상부로 돌출된 너트 결합부위가 서로 간섭되지 않고 상기 필러플레이트(PP)의 구멍에 삽입되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method according to claim 1 or 2,
The lower portion of the columnar reinforcing bar 220 is linearly protruded to the lower portion of the column upper plate 230 and coupled with a nut,
Since the upper portion of the columnar lower reinforcing bar 120 is bent and the upper end thereof is protruded to the upper portion of the column lower plate 130,
Wherein the nut joint portions protruded upward are inserted into the holes of the filler plate (PP) without interfering with each other. The rigid joint structure of the steel frame-concrete hybrid column and the PC beam with the joint attached.
제3항에서,
상기 기둥상부철근(220)의 하부는 직선으로 상기 기둥상부플레이트(230) 하부로 돌출되어 너트로 결합되고,
상기 기둥하부철근(120)의 상부는 굽혀져 상단이 상기 기둥하부플레이트(130) 상부로 돌출되어 너트로 결합되므로,
상부로 돌출된 너트 결합부위가 서로 간섭되지 않고 상기 필러플레이트(PP)의 구멍에 삽입되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
4. The method of claim 3,
The lower portion of the columnar reinforcing bar 220 is linearly protruded to the lower portion of the column upper plate 230 and coupled with a nut,
Since the upper portion of the columnar lower reinforcing bar 120 is bent and the upper end thereof is protruded to the upper portion of the column lower plate 130,
Wherein the nut joint portions protruded upward are inserted into the holes of the filler plate (PP) without interfering with each other. The rigid joint structure of the steel frame-concrete hybrid column and the PC beam with the joint attached.
제1항 또는 제2항에서,
상기 기둥하부플레이트(130) 상부에는 내부볼트(IR);가 돌출되어,
상기 내부볼트(IR)가 상기 필러플레이트(PP)를 관통하여 상기 기둥상부플레이트(230)에 체결되므로,
상기 내부볼트(IR)가 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130) 상호간의 접촉면이 이격되는 것을 방지하여 수직 및 수평 하중을 전달함과 동시에 기둥 하중에 의해 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130)에 발생하는 변위를 감소시키는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method according to claim 1 or 2,
An inner bolt (IR) protrudes above the column lower plate 130,
Since the inner bolt (IR) passes through the filler plate (PP) and is fastened to the column top plate (230)
The inner bolt IR prevents the contact surface between the column top plate 230, the filler plate PP and the column bottom plate 130 from being separated from each other, thereby transmitting the vertical and horizontal loads, And the column bottom plate (130) is reduced by the elastic force of the columnar plate (230), the column top plate (230), the filler plate (PP) Bond structure.
제3항에서,
상기 기둥하부플레이트(130) 상부에는 내부볼트(IR);가 돌출되어,
상기 내부볼트(IR)가 상기 필러플레이트(PP)를 관통하여 상기 기둥상부플레이트(230)에 체결되므로,
상기 내부볼트(IR)가 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130) 상호간의 접촉면이 이격되는 것을 방지하여 수직 및 수평 하중을 전달함과 동시에 기둥 하중에 의해 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130)에 발생하는 변위를 감소시키는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
4. The method of claim 3,
An inner bolt (IR) protrudes above the column lower plate 130,
Since the inner bolt (IR) passes through the filler plate (PP) and is fastened to the column top plate (230)
The inner bolt IR prevents the contact surface between the column top plate 230, the filler plate PP and the column bottom plate 130 from being separated from each other, thereby transmitting the vertical and horizontal loads, And the column bottom plate (130) is reduced by the elastic force of the columnar plate (230), the column top plate (230), the filler plate (PP) Bond structure.
제4항에서,
상기 기둥하부플레이트(130) 상부에는 내부볼트(IR);가 돌출되어,
상기 내부볼트(IR)가 상기 필러플레이트(PP)를 관통하여 상기 기둥상부플레이트(230)에 체결되므로,
상기 내부볼트(IR)가 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130) 상호간의 접촉면이 이격되는 것을 방지하여 수직 및 수평 하중을 전달함과 동시에 기둥 하중에 의해 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130)에 발생하는 변위를 감소시키는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
5. The method of claim 4,
An inner bolt (IR) protrudes above the column lower plate 130,
Since the inner bolt (IR) passes through the filler plate (PP) and is fastened to the column top plate (230)
The inner bolt IR prevents the contact surface between the column top plate 230, the filler plate PP and the column bottom plate 130 from being separated from each other, thereby transmitting the vertical and horizontal loads, And the column bottom plate (130) is reduced by the elastic force of the columnar plate (230), the column top plate (230), the filler plate (PP) Bond structure.
제5항에서,
상기 기둥하부플레이트(130) 상부에는 내부볼트(IR);가 돌출되어,
상기 내부볼트(IR)가 상기 필러플레이트(PP)를 관통하여 상기 기둥상부플레이트(230)에 체결되므로,
상기 내부볼트(IR)가 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130) 상호간의 접촉면이 이격되는 것을 방지하여 수직 및 수평 하중을 전달함과 동시에 기둥 하중에 의해 상기 기둥상부플레이트(230)와 상기 필러플레이트(PP) 그리고 상기 기둥하부플레이트(130)에 발생하는 변위를 감소시키는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
The method of claim 5,
An inner bolt (IR) protrudes above the column lower plate 130,
Since the inner bolt (IR) passes through the filler plate (PP) and is fastened to the column top plate (230)
The inner bolt IR prevents the contact surface between the column top plate 230, the filler plate PP and the column bottom plate 130 from being separated from each other, thereby transmitting the vertical and horizontal loads, And the column bottom plate (130) is reduced by the elastic force of the columnar plate (230), the column top plate (230), the filler plate (PP) Bond structure.
제6항에서,
상기 기둥상부콘크리트(210) 하부 측면에 개구부(미도시);를 형성하고,
상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후,
상기 개구부(미도시)를 그라우팅(G);하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
The method of claim 6,
An opening (not shown) is formed on a lower side surface of the columnar concrete 210,
After a nut is fastened to the upper end of the inner bolt (IR) through the opening (not shown)
And the opening (not shown) is grouted (G). The steel joining structure of the steel-concrete hybrid PC column and the PC beam with the joining portion placed thereon.
제7항에서,
상기 기둥상부콘크리트(210) 하부 측면에 개구부(미도시);를 형성하고,
상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후,
상기 개구부(미도시)를 그라우팅(G);하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
8. The method of claim 7,
An opening (not shown) is formed on a lower side surface of the columnar concrete 210,
After a nut is fastened to the upper end of the inner bolt (IR) through the opening (not shown)
And the opening (not shown) is grouted (G). The steel joining structure of the steel-concrete hybrid PC column and the PC beam with the joining portion placed thereon.
제8항에서,
상기 기둥상부콘크리트(210) 하부 측면에 개구부(미도시);를 형성하고,
상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후,
상기 개구부(미도시)를 그라우팅(G);하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
9. The method of claim 8,
An opening (not shown) is formed on a lower side surface of the columnar concrete 210,
After a nut is fastened to the upper end of the inner bolt (IR) through the opening (not shown)
And the opening (not shown) is grouted (G). The steel joining structure of the steel-concrete hybrid PC column and the PC beam with the joining portion placed thereon.
제9항에서,
상기 기둥상부콘크리트(210) 하부 측면에 개구부(미도시);를 형성하고,
상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후,
상기 개구부(미도시)를 그라우팅(G);하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
The method of claim 9,
An opening (not shown) is formed on a lower side surface of the columnar concrete 210,
After a nut is fastened to the upper end of the inner bolt (IR) through the opening (not shown)
And the opening (not shown) is grouted (G). The steel joining structure of the steel-concrete hybrid PC column and the PC beam with the joining portion placed thereon.
제1항 또는 제2항에서,
상기 PC보(400)는,
상기 보콘크리트(410) 하부 단부에 보강플레이트(430);가 결합되고,
상기 보강플레이트(430)에 보하부철근(420)이 접합되어,
상기 보강플레이트(430)가 상기 보거치브래킷(300)과의 접촉에서 상기 보콘트리트(410)의 파손을 방지하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method according to claim 1 or 2,
The PC beam 400,
A reinforcing plate 430 is coupled to the lower end of the beam concrete 410,
The beam lower reinforcing bars 420 are joined to the reinforcing plate 430,
And the reinforcing plate (430) prevents breakage of the beam concrete (410) due to contact with the beam bracket (300). The rigid joining combination of the steel column and concrete hybrid PC column and the PC beam rescue.
제3항에서,
상기 PC보(400)는,
상기 보콘크리트(410) 하부 단부에 보강플레이트(430);가 결합되고,
상기 보강플레이트(430)에 보하부철근(420)이 접합되어,
상기 보강플레이트(430)가 상기 보거치브래킷(300)과의 접촉에서 상기 보콘트리트(410)의 파손을 방지하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
4. The method of claim 3,
The PC beam 400,
A reinforcing plate 430 is coupled to the lower end of the beam concrete 410,
The beam lower reinforcing bars 420 are joined to the reinforcing plate 430,
And the reinforcing plate (430) prevents breakage of the beam concrete (410) due to contact with the beam bracket (300). The rigid joining combination of the steel column and concrete hybrid PC column and the PC beam rescue.
제4항에서,
상기 PC보(400)는,
상기 보콘크리트(410) 하부 단부에 보강플레이트(430);가 결합되고,
상기 보강플레이트(430)에 보하부철근(420)이 접합되어,
상기 보강플레이트(430)가 상기 보거치브래킷(300)과의 접촉에서 상기 보콘트리트(410)의 파손을 방지하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
5. The method of claim 4,
The PC beam 400,
A reinforcing plate 430 is coupled to the lower end of the beam concrete 410,
The beam lower reinforcing bars 420 are joined to the reinforcing plate 430,
And the reinforcing plate (430) prevents breakage of the beam concrete (410) due to contact with the beam bracket (300). The rigid joining combination of the steel column and concrete hybrid PC column and the PC beam rescue.
제5항에서,
상기 PC보(400)는,
상기 보콘크리트(410) 하부 단부에 보강플레이트(430);가 결합되고,
상기 보강플레이트(430)에 보하부철근(420)이 접합되어,
상기 보강플레이트(430)가 상기 보거치브래킷(300)과의 접촉에서 상기 보콘트리트(410)의 파손을 방지하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
The method of claim 5,
The PC beam 400,
A reinforcing plate 430 is coupled to the lower end of the beam concrete 410,
The beam lower reinforcing bars 420 are joined to the reinforcing plate 430,
And the reinforcing plate (430) prevents breakage of the beam concrete (410) due to contact with the beam bracket (300). The rigid joining combination of the steel column and concrete hybrid PC column and the PC beam rescue.
제1항 또는 제2항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;
(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
A rigid joint structure of a steel-concrete hybrid PC column and a PC beam in which the joint of claim 1 or 2 is installed is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the bracket to the column bracket 290;
(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);
(6) Concrete pouring step for pouring concrete (not shown);
(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제3항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;
(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
The rigid joint structure of the steel-concrete hybrid PC column and the PC beam in which the joint of claim 3 is installed is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;
(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);
(6) Concrete pouring step for pouring concrete (not shown);
(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제10항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;
(4) 상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후 상기 개구부(미도시)를 그라우팅(G)하는 그라우팅단계;
(5) 상기 (2) 내지 (4)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(6) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(7) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(8) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
A rigid joint structure of a steel-concrete hybrid PC column and a PC beam in which the joint of claim 10 is installed is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;
(4) a grouting step of grouting (G) the opening (not shown) after fastening a nut to the upper end of the inner bolt (IR) through the opening (not shown);
(5) repeating the steps (2) to (4) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(6) installing a lower end plate (500) in the bracket bracket (300) so as to close between the end of the beam concrete (410) and the outer surface of the column top concrete (210);
(7) Concrete pouring step for pouring concrete (not shown);
(8) disassembly of the lower end plate 500 during curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제11항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;
(4) 상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후 상기 개구부(미도시)를 그라우팅(G)하는 그라우팅단계;
(5) 상기 (2) 내지 (4)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(6) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(7) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(8) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joint of the eleventh claim is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;
(4) a grouting step of grouting (G) the opening (not shown) after fastening a nut to the upper end of the inner bolt (IR) through the opening (not shown);
(5) repeating the steps (2) to (4) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(6) installing a lower end plate (500) in the bracket bracket (300) so as to close between the end of the beam concrete (410) and the outer surface of the column top concrete (210);
(7) Concrete pouring step for pouring concrete (not shown);
(8) disassembly of the lower end plate 500 during curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제12항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;
(4) 상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후 상기 개구부(미도시)를 그라우팅(G)하는 그라우팅단계;
(5) 상기 (2) 내지 (4)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(6) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(7) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(8) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joint of the claim 12 is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;
(4) a grouting step of grouting (G) the opening (not shown) after fastening a nut to the upper end of the inner bolt (IR) through the opening (not shown);
(5) repeating the steps (2) to (4) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(6) installing a lower end plate (500) in the bracket bracket (300) so as to close between the end of the beam concrete (410) and the outer surface of the column top concrete (210);
(7) Concrete pouring step for pouring concrete (not shown);
(8) disassembly of the lower end plate 500 during curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제13항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300)에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;
(4) 상기 개구부(미도시)를 통하여 상기 내부볼트(IR) 상단에 너트를 체결한 후 상기 개구부(미도시)를 그라우팅(G)하는 그라우팅단계;
(5) 상기 (2) 내지 (4)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(6) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(7) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(8) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
A rigid joint structure of a steel-concrete hybrid PC column and a PC beam in which the joint of claim 13 is installed is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 and the compensating section steel frame 490 is projected outward from the outer surface of the columnar concrete 210 A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening the reinforcing reinforcing bars 450 to the column brackets 290;
(4) a grouting step of grouting (G) the opening (not shown) after fastening a nut to the upper end of the inner bolt (IR) through the opening (not shown);
(5) repeating the steps (2) to (4) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(6) installing a lower end plate (500) in the bracket bracket (300) so as to close between the end of the beam concrete (410) and the outer surface of the column top concrete (210);
(7) Concrete pouring step for pouring concrete (not shown);
(8) disassembly of the lower end plate 500 during curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제2항에서,
상기 하부PC기둥(100) 상단부터 하단까지 기둥하부철골(152);이 설치되고,
상기 기둥중심철골(250); 대신에 상기 상부PC기둥(200) 상단부터 하단까지 기둥상부철골(252);이 설치되며,
상기 기둥상부철골(252)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method of claim 2,
A column lower steel frame 152 is installed from the upper end to the lower end of the lower PC column 100,
The column center frame 250; Instead, an upper column steel frame 252 is installed from the upper end to the lower end of the upper PC column 200,
And the one end of the column bracket (290) is joined to the columnar steel frame (252). The rigid joint structure of the steel frame-concrete hybrid column and the PC beam with the joining portion inserted.
기둥콘크리트(110`)와 기둥철근(120`)을 포함하여 구성되는 PC기둥(100`);
상기 기둥콘크리트(110`) 외면 밖으로 돌출되게 설치되는 보거치브래킷(300`);
보콘크리트(410)와 상기 보콘크리트(410) 상부 단부로 돌출된 보상부철골(490)을 포함하여 구성되는 PC보(400);
를 포함하여 구성되되,
상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고,
상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결되며,
상기 보상부철골(490)과 상기 기둥브래킷(290)은 콘크리트(미도시) 타설시 함께 타설되어 강접합을 실현하는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
A PC column 100 'including a column concrete 110' and a columnar bar 120 ';
A bracket bracket 300 'installed so as to protrude from the outer surface of the column concrete 110';
A PC beam 400 including beam concrete 410 and a compensating section steel frame 490 protruding to an upper end of the beam concrete 410;
, ≪ / RTI >
The lower end of the beam concrete 410 is mounted on the beam bracket 300 '
The compensating part steel frame 490 is fastened to a column bracket 290 protruding from the outer surface of the column concrete 110 '
The reinforcing portion steel frame 490 and the column bracket 290 are disposed together when the concrete (not shown) is poured, thereby realizing a strong bonding. The reinforcing steel frame 490 and the column bracket 290 are formed of a steel- Bond structure.
제25항에서,
상기 기둥콘크리트(110`) 내부에는 상부에 플레이트가 접합된 기둥중심철골(250);이 포함되고,
상기 기둥중심철골(250)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
26. The method of claim 25,
A column center steel frame 250 having a plate joined to the upper portion of the column concrete 110 '
Wherein a column bracket (290) is coupled to the column center frame (250), and one end of the column bracket (290) is joined to the column center frame frame (250).
제25항 또는 제26항에서,
상기 기둥콘크리트(110`) 외면에는 보연결기둥철근(270);이 돌출되어,
상기 보연결기둥철근(270)에 보상부철근(450)이 철근이음되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
26. The method of claim 25 or 26,
On the outer surface of the column concrete 110 ', a beam connecting column reinforcing bar 270 is projected,
And the compensating reinforcing bars 450 are joined to the reinforcing reinforcing reinforcing bars 450 by the reinforcing reinforcing bars 450. The reinforced reinforcing bars 450 are joined to the reinforcing reinforcing bars 450 by reinforcing bars.
제25항 또는 제26항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;
(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
26. A steel-concrete hybrid PC column and a PC beam having joints according to claim 25 or 26,
(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';
(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 ', and the compensating section steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step for joining the projected column bracket 290;
(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;
(4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');
(5) Concrete pouring step for pouring concrete (not shown);
(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제27항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키며 상기 보연결기둥철근(270)에 보상부철근(450)을 철근이음시키는 PC보결합단계;
(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
A steel-concrete hybrid PC column and a PC beam having a joining portion according to Claim 27 are used.
(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';
(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 ', and the compensating section steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step of fastening the reinforcing reinforcing bars 450 to the beam reinforcing bars 270 by fastening them to the protruded column brackets 290;
(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;
(4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');
(5) Concrete pouring step for pouring concrete (not shown);
(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제26항에서,
상기 기둥중심철골(250); 대신에 상기 PC기둥(100`) 상단부터 하단까지 기둥철골(252`);이 설치되며,
상기 기둥철골(252`)에는 상기 기둥브래킷(290)의 일단이 접합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
26. The method of claim 26,
The column center frame 250; Instead, a column steel frame 252 'is installed from the top to the bottom of the PC column 100'
And the one end of the column bracket (290) is joined to the column steel frame (252 '). The rigid joint structure of the steel frame-concrete hybrid column and the PC beam is provided with the joining portion.
제30항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 보거치브래킷(300`)에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;
(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
The hybrid joint structure of a steel-concrete hybrid PC column and a PC beam in which the joint of claim 30 is installed is used,
(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';
(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is placed on the beam bracket 300 ', and the compensating section steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step for joining the projected column bracket 290;
(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;
(4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');
(5) Concrete pouring step for pouring concrete (not shown);
(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제1항 또는 제2항에서,
상기 보거치브래킷(300)은 생략되고,
상기 보콘크리트(410)의 하부 단부는 상기 기둥상부플레이트(230) 단부에 거치되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method according to claim 1 or 2,
The fixing bracket 300 is omitted,
And a lower end of the beam concrete (410) is mounted on an end of the column top plate (230). The steel joint structure of a steel-concrete hybrid PC column and a PC beam is provided with a joint.
제32항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 기둥상부플레이트(230) 단부에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;
(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
A steel-concrete hybrid PC column and a PC beam having the joining portion according to claim 32 are used.
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is mounted on the end of the column upper plate 230, and the compensating part steel frame 490 is moved outside the column top concrete 210 A PC beam joining step for joining the projected column bracket 290;
(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);
(6) Concrete pouring step for pouring concrete (not shown);
(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제24항에서,
상기 보거치브래킷(300)은 생략되고,
상기 보콘크리트(410)의 하부 단부는 상기 기둥상부플레이트(230) 단부에 거치되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
25. The method of claim 24,
The fixing bracket 300 is omitted,
And a lower end of the beam concrete (410) is mounted on an end of the column top plate (230). The steel joint structure of a steel-concrete hybrid PC column and a PC beam is provided with a joint.
제34항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 상부PC기둥(200)을 양중하여 상기 하부PC기둥(100)의 상부에 결합하는 PC기둥결합단계;
(2) 상기 상부PC기둥(200)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(3) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 기둥상부플레이트(230) 단부에 거치되고 상기 보상부철골(490)은 상기 기둥상부콘크리트(210) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;
(4) 상기 (2) 내지 (3)단계를 상기 상부PC기둥(200)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(5) 상기 보콘크리트(410) 단부와 상기 기둥상부콘크리트(210) 외면 사이를 막도록 상기 보거치브래킷(300)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(6) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(7) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joining part of the claim 34 is used,
(1) a PC column coupling step of coupling the upper PC column 200 to the upper part of the lower PC column 100;
(2) a step of recovering the PC beam 400 on one surface of the upper PC column 200;
(3) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is mounted on the end of the column upper plate 230, and the compensating part steel frame 490 is moved outside the column top concrete 210 A PC beam joining step for joining the projected column bracket 290;
(4) repeating the steps (2) to (3) on the other surface of the upper PC column 200 to install a plurality of PC beams 400;
(5) installing a lower end plate (500) in the bracket bracket (300) so as to close the space between the end of the beam concrete (410) and the outer surface of the column upper concrete (210);
(6) Concrete pouring step for pouring concrete (not shown);
(7) disassembling the secondary plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제25항 또는 제26항에서,
상기 보거치브래킷(300`) 대신에 상기 기둥콘크리트(110`) 외면에 돌출된 코벨(300``)이 형성되고,
상기 보콘크리트(410)의 하부 단부는 상기 코벨(300``) 상부에 거치되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
26. The method of claim 25 or 26,
A coble 300 '' protruding from the outer surface of the column concrete 110 'is formed instead of the bracket 300'
And a lower end of the beam concrete (410) is mounted on the upper part of the cobble (300 ''). The rigid joint structure of the steel-concrete hybrid PC column and the PC beam with the joint attached.
제36항의 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 것으로써,
(1) 상기 PC기둥(100`)의 일면에 상기 PC보(400)를 양중하는 PC보양중단계;
(2) 상기 PC보(400)를 하강시켜 상기 보콘크리트(410)의 하부 단부는 상기 코벨(300``) 상부에 거치되고 상기 보상부철골(490)은 상기 기둥콘크리트(110`) 외면 밖으로 돌출된 기둥브래킷(290)에 체결시키는 PC보결합단계;
(3) 상기 (1) 내지 (2)단계를 상기 PC기둥(100`)의 다른 면에 반복하여 다수개의 PC보(400)를 설치하는 PC보설치단계;
(4) 상기 보콘크리트(410) 단부와 상기 기둥콘크리트(110`) 외면 사이를 막도록 상기 보거치브래킷(300`)에 보단부플레이트(500)를 설치하는 보단부플레이트설치단계;
(5) 콘크리트(미도시)를 타설하는 콘크리트타설단계;
(6) 상기 콘크리트(미도시) 양생중 또는 양생후 상기 보단부플레이트(500)를 해체하는 보단부플레이트해체단계;
를 포함하여 구성되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조를 이용한 강접합 결합구조의 시공방법.
A steel-concrete hybrid PC column and a PC beam having the joint of claim 36 are used.
(1) a step of recovering the PC beam 400 on one side of the PC column 100 ';
(2) The PC beam 400 is lowered so that the lower end of the beam concrete 410 is mounted on the upper part of the coble 300 ', and the compensating part steel frame 490 is moved out of the outer surface of the column concrete 110' A PC beam joining step for joining the projected column bracket 290;
(3) a PC beam installation step of repeating the steps (1) and (2) on the other surface of the PC column 100 'to install a plurality of PC beams 400;
(4) installing a second end plate (500) on the beam bracket (300 ') to close the space between the end of the beam concrete (410) and the outer surface of the column concrete (110');
(5) Concrete pouring step for pouring concrete (not shown);
(6) a step of dismounting the lower end plate 500 during the curing or curing of the concrete (not shown);
The method of claim 1, wherein the reinforced concrete pillar and the reinforced concrete pavement of the steel frame are made of steel.
제1항 또는 제2항에서,
상기 PC보(400)는 단부에 보하부철근(420)이 돌출되고,
상기 보하부철근(420)이 상기 기둥상부콘크리트(210) 측면에 돌출된 연결철근(미도시)에 커플러로 결합되는 것을 특징으로 하는 접합부가 타설된 철골-콘크리트 하이브리드 PC기둥 및 PC보의 강접합 결합구조.
3. The method according to claim 1 or 2,
The PC beam 400 has a beam lower reinforcing bar 420 protruding from its end,
The reinforcing bars 420 are coupled to coupling reinforcing bars (not shown) protruding from the side of the column top concrete 210. The steel reinforced concrete pillars and the PC beams are welded Bond structure.
KR1020160030209A 2016-03-14 2016-03-14 the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same Expired - Fee Related KR101844343B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160030209A KR101844343B1 (en) 2016-03-14 2016-03-14 the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160030209A KR101844343B1 (en) 2016-03-14 2016-03-14 the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same

Publications (2)

Publication Number Publication Date
KR20170107117A true KR20170107117A (en) 2017-09-25
KR101844343B1 KR101844343B1 (en) 2018-05-21

Family

ID=60035065

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160030209A Expired - Fee Related KR101844343B1 (en) 2016-03-14 2016-03-14 the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same

Country Status (1)

Country Link
KR (1) KR101844343B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755963A (en) * 2018-06-12 2018-11-06 西安建筑科技大学 A kind of partial precast assembled steel reinforced concrete giant frame structure and construction method
KR20190136509A (en) * 2018-05-31 2019-12-10 염경수 Connecting structure and connecting method for CFT column
CN112814149A (en) * 2021-01-07 2021-05-18 郑晓峰 Precast concrete member
CN113089825A (en) * 2021-04-19 2021-07-09 重庆恒昇大业建筑科技集团有限公司 Beam-column mixed frame node, and preparation method and construction method of precast concrete beam
CN115434236A (en) * 2022-10-19 2022-12-06 甘肃交设智远实业有限公司 Exempt from horizontal diaphragm structure of template assembled
CN115726463A (en) * 2022-10-27 2023-03-03 中南大学 A prefabricated concrete frame structure
CN116378228A (en) * 2023-05-30 2023-07-04 上海城建市政工程(集团)有限公司 Construction method for connection node of box-type stiff column and concrete beam

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101033693B1 (en) * 2008-06-24 2011-05-12 코비코리아 주식회사 Pipe racks assembled from precast concrete
KR100937745B1 (en) * 2009-04-24 2010-01-20 에스에이치공사 Constructing method using precast concrete column
KR101030419B1 (en) * 2010-07-28 2011-04-20 경희대학교 산학협력단 Combined structure of vertical member and horizontal member

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190136509A (en) * 2018-05-31 2019-12-10 염경수 Connecting structure and connecting method for CFT column
CN108755963A (en) * 2018-06-12 2018-11-06 西安建筑科技大学 A kind of partial precast assembled steel reinforced concrete giant frame structure and construction method
CN112814149A (en) * 2021-01-07 2021-05-18 郑晓峰 Precast concrete member
CN112814149B (en) * 2021-01-07 2022-11-08 东莞市鸿安预制构件有限公司 Precast concrete member
CN113089825A (en) * 2021-04-19 2021-07-09 重庆恒昇大业建筑科技集团有限公司 Beam-column mixed frame node, and preparation method and construction method of precast concrete beam
CN115434236A (en) * 2022-10-19 2022-12-06 甘肃交设智远实业有限公司 Exempt from horizontal diaphragm structure of template assembled
CN115726463A (en) * 2022-10-27 2023-03-03 中南大学 A prefabricated concrete frame structure
CN116378228A (en) * 2023-05-30 2023-07-04 上海城建市政工程(集团)有限公司 Construction method for connection node of box-type stiff column and concrete beam

Also Published As

Publication number Publication date
KR101844343B1 (en) 2018-05-21

Similar Documents

Publication Publication Date Title
KR101844343B1 (en) the rigid connection structure between hybrid precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same
KR101295740B1 (en) Joint of Steel Column
KR101995496B1 (en) the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure of the precast concrete girder using the same
KR101490808B1 (en) Prefabricated steel frame equipped with removable concrete form for composite member of steel and concrete
KR101766806B1 (en) the rigid connection structure between precast concrete column and precast concrete beam using the temporary bracket installing precast concrete column, the modular system using the same
KR101995497B1 (en) the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure of the precast concrete girder using the same
KR101844344B1 (en) the rigid connection structure between precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same
KR101766809B1 (en) the rigid connection structure between precast concrete column and precast concrete beam using the permanent bracket installing precast concrete column
KR101766810B1 (en) the rigid connection structure between precast concrete column and precast concrete beam using the permanent bracket installing precast concrete column
KR100770023B1 (en) Joint Structure of Concrete-filled Steel Pipe Column and Reinforced Concrete Flat Plate Using Shear Head
KR101872274B1 (en) the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure between precast concrete column and precast concrete beam
JP4980782B2 (en) Seismic isolation mechanism for intermediate floors of buildings
KR102585526B1 (en) Composite frame with end-buried girder joint
KR101766808B1 (en) the rigid connection structure between precast concrete column and precast concrete beam using the permanent bracket installing precast concrete column
KR101836896B1 (en) the rigid connection structure between precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same
KR101858972B1 (en) the rigid connection structure without concrete between the upper precast concrete column and the lower precast concrete column and the rigid connection structure between precast concrete column and precast concrete beam
KR101872298B1 (en) the rigid connection structure between precast concrete column and precast concrete beam
KR101864198B1 (en) the SRC connection structure between precast concrete column and precast concrete beam, the plate connection structure between precast concrete upper column and precast concrete lower column
KR101766811B1 (en) the rigid connection structure between precast concrete column and precast concrete beam using the permanent bracket installing precast concrete column
KR100710583B1 (en) Composite structure of PC pillar and cheolgolbo
KR101083062B1 (en) Compound beam
KR200323668Y1 (en) Prefabrication struture by composing steel frame and concrete composite
JPH10292488A (en) Connecting structure for steel frame column and concrete foundation
KR20050081060A (en) Steel beam joint attachment
KR101891963B1 (en) the improved hybrid precast concrete beam for saving the rebar and the rigid connection structure between precast concrete column and precast concrete beam using the same

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

PG1501 Laying open of application

St.27 status event code: A-1-1-Q10-Q12-nap-PG1501

E13-X000 Pre-grant limitation requested

St.27 status event code: A-2-3-E10-E13-lim-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 4

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 5

PC1903 Unpaid annual fee

St.27 status event code: A-4-4-U10-U13-oth-PC1903

Not in force date: 20230328

Payment event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

PC1903 Unpaid annual fee

St.27 status event code: N-4-6-H10-H13-oth-PC1903

Ip right cessation event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

Not in force date: 20230328

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000