KR20130030340A - Structure of retaining wall and construction method for installing underground structures - Google Patents

Structure of retaining wall and construction method for installing underground structures Download PDF

Info

Publication number
KR20130030340A
KR20130030340A KR1020110093059A KR20110093059A KR20130030340A KR 20130030340 A KR20130030340 A KR 20130030340A KR 1020110093059 A KR1020110093059 A KR 1020110093059A KR 20110093059 A KR20110093059 A KR 20110093059A KR 20130030340 A KR20130030340 A KR 20130030340A
Authority
KR
South Korea
Prior art keywords
panel
underground
coupled
excavation
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
KR1020110093059A
Other languages
Korean (ko)
Inventor
정진덕
Original Assignee
주식회사 동림건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 동림건설 filed Critical 주식회사 동림건설
Priority to KR1020110093059A priority Critical patent/KR20130030340A/en
Publication of KR20130030340A publication Critical patent/KR20130030340A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C19/00Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/086Travelling trench shores
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 지중 관 및 하수박스 등의 지하구조물 설치를 위한 지반 굴착작업 시, 토압에 대응하고 굴착 토사의 붕괴를 방지하기 위해 굴착부 측면으로 설치되는 흙막이 구조 및 그를 이용한 지하구조물 시공방법에 관한 것으로, 더욱 상세하게는 지하구조물 설치를 위해 착탈식의 견인 수단이 설치되는 흙막이 구조를 구현함으로써 지중 구조물 견인 및 설치를 위한 별도의 크레인 장비 동원이 불필요하게 되어 공간활용성 및 작업성을 높이며, 또한 지하구조물의 설치 폭에 따라 너비의 가변이 가능하도록 하여 현장여건에 맞는 능동적인 시공 대처가 즉각적으로 이루어지도록 한 너비 조절이 가능한 착탈식 견인 수단이 구비된 흙막이 구조와 이를 이용한 지하구조물 시공방법에 관한 것이다.
상기 본 발명은 크게 세 부분으로 구성되는 바, 굴착부 내측으로 입설되는 흙막이부(100)와, 흙막이부(100) 상부에 설치되어 수평방향으로 왕복 운동하도록 설치되는 이송부(200)와, 지중 구조물을 인양하여 굴착부에 배치시키는 견인부(300)로 구성되게 된다.
상기 본 발명 흙막이부(100)는 굴착부 내측에 일정 간격 입설되는 다수 개의 지주(110)와, 지주(110)의 일측 체결홀(112a)에 끼워지는 상부 지지 패널(121a) 및 하부 지지 패널(121b)과 타측 체결홀(112b)에 끼워지는 상부 슬라이드 패널(123a) 및 하부 슬라이드 패널(123b)로 구성되는 패널(120)과, 지주(110)에 활강편(131)이 끼워져 결합되되 일정거리 수직 하강하여 고정되는 지지재(130) 및 마주하는 지지재(130) 사이에 결합, 설치되어 굴착폭에 따라 조립 갯수를 달리하게 되는 간격재(140)로 구성되게 된다.
본 발명 이송부(200)는 지주(110) 및 패널(120) 상부에 결합되는 레일(210)과 레일(210) 상에서 활주하는 롤러(220) 및 그의 상부에 결합, 배치되는 유압잭(240)이 설치된 프레임체(230)와 최상부 수평 프레임(232) 하부에 결합되는 가이드 레일(250)로 구성되게 되며, 견인부(300)는 구동모터(310)와, 구동모터(310)의 회전력을 롤러(330)에 전달하는 감속기(320)와, 가이드 레일(250) 상에 설치되되 구동모터(310)의 회전력을 전달받아 회전하며 수평방향으로 운동하는 회전 롤러(330)와, 지하구조물을 인양하는 권취 체인(350) 및 견인 체인(370)으로 구성된다.
상기 구성을 갖는 본 발명 흙막이 구조는 지중구조물 설치를 위한 흙막이 공사의 시행에 있어, 공사 현장의 공간 활용성을 높일 수 있을 뿐만 아니라, 지중구조물 설치를 위한 별도의 인발 장치 및 크레인 사용에 따른 제반 비용 손실을 줄일 수 있으며, 또한 공사 기간을 단축할 수 있어 효율적으로 흙막이 공사를 수행할 수 있는 장점이 있다.
또한, 견인장치의 진입이 힘든 협소한 작업 현장에도 적용할 수 있으며, 굴착폭에 따라 견인부의 너비 조절이 가능하도록 하여 지중구조물이 설치되는 현장여건에 맞는 능동적이며 즉각적인 시공 대처가 이루어져 효율성을 높인 특징이 있다.
The present invention relates to an earthquake structure that is installed on the side of the excavation to cope with earth pressure and to prevent the collapse of the excavated soil during the ground excavation work for the installation of underground structures such as underground pipes and sewage boxes, and the underground structure construction method using the same. More specifically, by implementing the earth block structure in which the detachable towing means is installed to install the underground structure, it is unnecessary to mobilize separate crane equipment for the towing and installation of the underground structure, thereby improving space utilization and workability, and also the underground structure The present invention relates to an earthquake structure equipped with a detachable traction means capable of controlling the width according to the installation width of the installation and to enable an active construction response to the site conditions immediately, and a construction method of the underground structure using the same.
The present invention is composed of three parts large bar, the earthquake portion 100 which is placed inside the excavation portion, and the transport portion 200 is installed on the earthquake portion 100 to reciprocate in the horizontal direction, underground structure It is to be configured by the towing unit 300 to lift and place the excavation.
The earth retaining part 100 of the present invention includes a plurality of struts 110 which are placed at a predetermined interval inside the excavation portion, and an upper support panel 121a and a lower support panel fitted to one side fastening hole 112a of the strut 110. The slide 120 131 is fitted to the panel 120 including the upper slide panel 123a and the lower slide panel 123b fitted into the 121b) and the other fastening hole 112b, and is coupled to a predetermined distance. It is composed of a spacer 140 that is coupled and installed between the support member 130 and the support member 130 facing and fixed vertically to vary the number of assembly according to the excavation width.
The conveying part 200 of the present invention is provided with a rail 210 coupled to an upper portion of the support 110 and a panel 120, a roller 220 sliding on the rail 210, and a hydraulic jack 240 coupled to and disposed on an upper portion thereof. It is composed of a guide rail 250 coupled to the frame body 230 and the lower portion of the uppermost horizontal frame 232, the towing unit 300 is a drive motor 310, the rotational force of the drive motor 310 roller 330 Reduction gear 320 to be transmitted to), the rotary roller 330 which is installed on the guide rail 250, rotates by receiving the rotational force of the drive motor 310 and moves in the horizontal direction, and the winding chain to lift the underground structure 350 and tow chain 370.
The present invention structure having the above structure is not only to increase the space utilization of the construction site in the implementation of the earthquake construction for the installation of underground structures, but also the overall cost of using a separate drawing device and crane for installing the underground structures The loss can be reduced, and also the construction period can be shortened, so that there is an advantage that can efficiently perform the earthquake construction.
In addition, it can be applied to a narrow work site where it is difficult to enter the towing device, and it is possible to adjust the width of the towing part according to the excavation width, so that active and immediate construction measures are made according to the site conditions where the underground structure is installed. There is this.

Description

착탈식 견인 수단이 구비된 흙막이 구조 및 이를 이용한 지하구조물 시공방법 { Structure of Retaining Wall and Construction method for installing underground structures } Structure of Retaining Wall and Construction method for installing underground structures equipped with detachable traction means

본 발명은 지중 관 및 하수박스 등의 지하구조물 설치를 위한 지반 굴착작업 시, 토압에 대응하고 굴착 토사의 붕괴를 방지하기 위해 굴착부 측면으로 설치되는 흙막이 구조 및 그를 이용한 지하구조물 시공방법에 관한 것으로, 더욱 상세하게는 지하구조물 설치를 위해 착탈식의 견인 수단이 설치되는 흙막이 구조를 구현함으로써 지중 구조물 견인 및 설치를 위한 별도의 크레인 장비 동원이 불필요하게 되어 공간활용성 및 작업성을 높이며, 또한 지하구조물의 설치 폭에 따라 너비의 가변이 가능하도록 하여 현장여건에 맞는 능동적인 시공 대처가 즉각적으로 이루어지도록 한 너비 조절이 가능한 착탈식 견인 수단이 구비된 흙막이 구조와 이를 이용한 지하구조물 시공방법에 관한 것이다.
The present invention relates to an earthquake structure that is installed on the side of the excavation to cope with earth pressure and to prevent the collapse of the excavated soil during the ground excavation work for the installation of underground structures such as underground pipes and sewage boxes, and the underground structure construction method using the same. More specifically, by implementing the earth block structure in which the detachable towing means is installed to install the underground structure, it is unnecessary to mobilize separate crane equipment for the towing and installation of the underground structure, thereby improving space utilization and workability, and also the underground structure The present invention relates to an earthquake structure equipped with a detachable traction means capable of controlling the width according to the installation width of the installation and to enable an active construction response to the site conditions immediately, and a construction method of the underground structure using the same.

일반적으로 건축물의 지하층이나 지하철 등 지하구조물을 구축하거나 지중 관을 매설하기 위해 관로 터파기를 하는 등의 지반 굴착작업 시 건축물 배치 주변에 공지의 면적이 넓어 충분한 안식각을 구할 수 있을 때는 경사면 오픈 컷(open cut)을 실시할 수 있으나, 현장 여건상 여유있는 안식각이 확보되지 않은 현장의 경우 흙벽의 붕괴를 방지하기 위해 굴착부의 측면으로 흙막이 벽체가 설치되게 된다.
Generally, when the ground excavation work such as building underground structures such as underground floors of buildings, subways, or dig pipes to bury underground pipes, when the well-known area is wide around the layout of the building, a sufficient angle of relief can be obtained. In the case of a site where a sufficient angle of repose is not secured due to the site conditions, the earth wall is installed on the side of the excavation to prevent the earth wall from collapsing.

상기 흙막이 벽체는 터파기 공사 중 생성되는 토압 및 수압 등의 측압을 일시적으로 부담하는 가설물로 그의 종류도 다양한 바, The cobble wall is a temporary construction that bears the side pressure such as earth pressure and water pressure generated during the excavation work, its variety is also various bars,

먼저 엄지 말뚝식 흙막이 벽은 지중을 천공하고 H-파일(H-PILE)을 삽입한 후 굴착하면서 두 개의 H-파일(H-PILE) 사이에 토류판을 설치하는 것으로, 강재 엄지 말뚝을 천공 또는 진동 압입하거나 보링하여 지중에 삽입한 후에 굴착을 진행하면서, 토류판을 끼워서 굴착벽을 지지하는 방법이다.First, the thumb pile earth wall is to install the earth plate between two H-piles while drilling the ground, inserting the H-pile, and then excavating. It is a method of supporting an excavation wall by inserting a earth plate while inserting or boring and inserting it into the ground and proceeding excavation.

또한, 흙막이 벽은 강널 말뚝의 또 다른 공법으로도 설치될 수 있는 바, 강널 말뚝을 설치하여 차수벽과 토류벽의 역활이 동시에 가능하도록 하는 공법으로 주로 차수성이 필요한 곳에 사용되고 있다.
In addition, the retaining wall is a bar that can be installed as another method of steel sheet piles, the method of installing the steel sheet piles to enable the role of the water wall and earth wall at the same time is mainly used where water-repellency is required.

상기 제시된 흙막이 구조는 궁극적으로 하수박스 등의 지하구조물을 설치하기 위한 것으로, 지하구조물 설치를 요하는 현장에 굴착을 진행하기 위한 굴착기와, 지중 굴착부에 지하 구조물을 설치하기 위한 크레인이 현장에 함께 동원되어 굴착기로 토사를 굴착하면서 측면의 토사를 방지하기 위한 흙막이를 설치한 후, 크레인으로 지하구조물을 인양하여 굴착부에 설치하는 공정으로 지하구조물이 설치되게 된다.
The structure of the above-mentioned mudguard is ultimately intended to install underground structures such as sewage boxes, an excavator for proceeding with excavation at a site requiring installation of underground structures, and a crane for installing underground structures at underground excavations. After mobilizing and excavating the earth and sand with an excavator, the earth block is installed to prevent the earth and sand on the side, and the underground structure is installed by lifting the underground structure with a crane and installing the excavation unit.

상기 시행되는 지하구조물 설치에 따른 장비들을 동원하여 시공시, 작업 공간을 크게 차지하여 인근 지대까지 불편을 안겨주게 되며, 또한, 소규모 공사가 시행되는 작업 현장이거나 지하구조물을 견인하기 위한 크레인의 진입이 힘든 협소한 작업현장일 경우, 지하구조물 설치에 큰 어려움이 있었으며 이는 작업성을 떨어뜨릴 뿐 아니라 공사기간을 연장시키며 공사비를 증대시키는 요인이 되었다.
When mobilizing the equipment according to the installation of the underground structure to be implemented, it occupies a large working space and causes inconvenience to the neighboring zone, and also the entry of a crane for towing a underground structure or a work site where a small construction is carried out In the case of a difficult and narrow work site, there was a great difficulty in installing the underground structure, which not only reduced workability but also extended the construction period and increased the construction cost.

이에, 본원 발명은 지중구조물 설치를 위한 흙막이 공사의 시행에 있어, 공사 현장의 작업 공간 활용성을 높이며, 동시에 공사 기간 또한 단축시킬 수 있는 효율적인 흙막이 구조 및 그를 이용한 지하구조물 시공방법을 제시하고자 한다.
Accordingly, the present invention is to propose an efficient earth block structure and an underground structure construction method using the same in the implementation of the earth block construction for the installation of underground structures, to increase the usability of the work space at the construction site, and at the same time also shorten the construction period.

상기 목적을 달성하기 위해 본 발명은 크게 세 부분으로 구성되는 바, 굴착부 내측으로 입설되는 흙막이부(100)와, 흙막이부(100) 상부에 설치되어 수평방향으로 왕복 운동하도록 설치되는 이송부(200)와, 지중 구조물을 인양하여 굴착부에 배치시키는 견인부(300)로 구성되게 된다.
In order to achieve the above object, the present invention is composed of three parts. The bar part 100 installed in the excavation part and the transfer part 200 installed on the earth part 100 and reciprocating in the horizontal direction are installed. ) And a towing unit 300 which lifts the underground structure and places the excavation unit.

상기 본 발명 흙막이부(100)는 굴착부 내측에 일정 간격 입설되는 다수 개의 지주(110)와, 지주(110)의 일측 체결홀(112a)에 끼워지는 상부 지지 패널(121a) 및 하부 지지 패널(121b)과 타측 체결홀(112b)에 끼워지는 상부 슬라이드 패널(123a) 및 하부 슬라이드 패널(123b)로 구성되는 패널(120)과, 지주(110)에 활강편(131)이 끼워져 결합되되 일정거리 수직 하강하여 고정되는 지지재(130) 및 마주하는 지지재(130) 사이에 결합, 설치되어 굴착폭에 따라 조립 갯수를 달리하게 되는 간격재(140)로 구성되게 된다.The earth retaining part 100 of the present invention includes a plurality of struts 110 which are placed at a predetermined interval inside the excavation portion, and an upper support panel 121a and a lower support panel fitted to one side fastening hole 112a of the strut 110. The slide 120 131 is fitted to the panel 120 including the upper slide panel 123a and the lower slide panel 123b fitted into the 121b) and the other fastening hole 112b, and is coupled to a predetermined distance. It is composed of a spacer 140 that is coupled and installed between the support member 130 and the support member 130 facing and fixed vertically to vary the number of assembly according to the excavation width.

본 발명 이송부(200)는 지주(110) 및 패널(120) 상부에 결합되는 레일(210)과 레일(210) 상에서 활주하는 롤러(220) 및 그의 상부에 결합, 배치되는 유압잭(240)이 설치된 프레임체(230)와 최상부 수평 프레임(232) 하부에 결합되는 가이드 레일(250)로 구성되게 되며, 견인부(300)는 구동모터(310)와, 구동모터(310)의 회전력을 롤러(330)에 전달하는 감속기(320)와, 가이드 레일(250) 상에 설치되되 구동모터(310)의 회전력을 전달받아 회전하며 수평방향으로 운동하는 회전 롤러(330)와, 지하구조물을 인양하는 권취 체인(350) 및 견인 체인(370)으로 구성된다.
The conveying part 200 of the present invention is provided with a rail 210 coupled to an upper portion of the support 110 and a panel 120, a roller 220 sliding on the rail 210, and a hydraulic jack 240 coupled to and disposed on an upper portion thereof. It is composed of a guide rail 250 coupled to the frame body 230 and the lower portion of the uppermost horizontal frame 232, the towing unit 300 is a drive motor 310, the rotational force of the drive motor 310 roller 330 Reduction gear 320 to be transmitted to), the rotary roller 330 which is installed on the guide rail 250, rotates by receiving the rotational force of the drive motor 310 and moves in the horizontal direction, and the winding chain to lift the underground structure 350 and tow chain 370.

상기 구성을 갖는 본 발명 흙막이 구조는 지중구조물 설치를 위한 흙막이 공사의 시행에 있어, 공사 현장의 공간 활용성을 높일 수 있을 뿐만 아니라, 지중구조물 설치를 위한 별도의 인발 장치 및 크레인 사용에 따른 제반 비용 손실을 줄일 수 있으며, 또한 공사 기간을 단축할 수 있어 효율적으로 흙막이 공사를 수행할 수 있는 장점이 있다.
The present invention structure having the above structure is not only to increase the space utilization of the construction site in the implementation of the earthquake construction for the installation of underground structures, but also the overall cost of using a separate drawing device and crane for installing the underground structures The loss can be reduced, and also the construction period can be shortened, so that there is an advantage that can efficiently perform the earthquake construction.

또한, 견인장치의 진입이 힘든 협소한 작업 현장에도 적용할 수 있으며, 굴착폭에 따라 견인부의 너비 조절이 가능하도록 하여 지중구조물이 설치되는 현장여건에 맞는 능동적이며 즉각적인 시공 대처가 이루어져 효율성을 높인 특징이 있다.
In addition, it can be applied to a narrow work site where it is difficult to enter the towing device, and it is possible to adjust the width of the towing part according to the excavation width, so that active and immediate construction measures are made according to the site conditions where the underground structure is installed. There is this.

도 1은 본 발명 흙막이 구조의 결합 상태를 나타낸 정면도
도 2는 본 발명 흙막이 구조의 결합 상태를 나타낸 평면도
도 3은 본 발명 흙막이 구조의 사용 상태를 나타낸 측면도
도 4는 본 발명 흙막이 구조의 사용 상태를 나타낸 정면도
도 5는 본 발명 흙막이 구조의 일부 분해 사시도
1 is a front view showing a coupling state of the earth structure of the present invention
Figure 2 is a plan view showing a bonding state of the earth structure of the present invention
Figure 3 is a side view showing a state of use of the present invention structure structure
Figure 4 is a front view showing a state of use of the present invention structure
5 is a partially exploded perspective view of the present structure of the earth block

본 발명은 지중 관 및 하수박스 등의 지하구조물 설치를 위한 지반 굴착작업 시, 토압에 대응하고 굴착 토사의 붕괴를 방지하기 위해 굴착부 측면으로 설치되는 흙막이 구조 및 그를 이용한 지하구조물 시공방법에 관한 것으로, 더욱 상세하게는 지하구조물 설치를 위해 착탈식의 견인 수단이 설치되는 흙막이 구조를 구현함으로써 지중 구조물 견인 및 설치를 위한 별도의 크레인 장비 동원이 불필요하게 되어 공간활용성 및 작업성을 높이며, 또한 지하구조물의 설치 폭에 따라 너비의 가변이 가능하도록 하여 현장여건에 맞는 능동적인 시공 대처가 즉각적으로 이루어지도록 한 너비 조절이 가능한 착탈식 견인 수단이 구비된 흙막이 구조와 이를 이용한 지하구조물 시공방법에 관한 것이다.
The present invention relates to an earthquake structure that is installed on the side of the excavation to cope with earth pressure and to prevent the collapse of the excavated soil during the ground excavation work for the installation of underground structures such as underground pipes and sewage boxes, and the underground structure construction method using the same. More specifically, by implementing the earth block structure in which the detachable towing means is installed to install the underground structure, it is unnecessary to mobilize separate crane equipment for the towing and installation of the underground structure, thereby improving space utilization and workability, and also the underground structure The present invention relates to an earthquake structure equipped with a detachable traction means capable of controlling the width according to the installation width of the installation and to enable an active construction response to the site conditions immediately, and a construction method of the underground structure using the same.

이하 본 발명의 실시 예를 첨부도면을 통해 살펴보면 다음과 같다.
Looking at the embodiment of the present invention through the accompanying drawings as follows.

우선, 도 1은 본 발명 흙막이 구조의 결합된 정면도를 나타낸 것이고, 도 2는 본 발명 흙막이 구조의 결합된 평면도를 나타낸 것이고, 도 3는 본 발명 흙막이 구조의 실시 예에 따른 결합된 측면도를 나타낸 것이며, 도 4는 본 발명 흙막이 구조의 실시 예에 따른 결합된 정면도를 도시한 것이고, 도 5는 본 발명 흙막이 구조의 일부 분해 사시도를 도시한 것으로, First, Figure 1 shows a combined front view of the present invention structure, Figure 2 shows a combined plan view of the present invention structure, Figure 3 shows a combined side view according to an embodiment of the present invention structure. 4 illustrates a combined front view according to an embodiment of the present invention structure, and FIG. 5 illustrates a partially exploded perspective view of the present invention structure.

도시된 바와 같이, 지하구조물 설치를 위한 본 발명 흙막이 구조는 크게 세 부분으로 구성되는 바, 굴착부 내측으로 입설되는 흙막이부(100)와 흙막이부(100) 상부에 설치되어 수평방향으로 왕복 운동하도록 설치되는 이송부(200)와 지중 구조물을 인양하여 굴착부 내측에 배치시키는 견인부(300)로 이루어지는 대략적인 구성을 갖는다.
As shown, the present invention for the construction of the underground structure of the earth structure is largely composed of three parts, it is installed on the earthen portion 100 and the earthen portion 100 which is placed inside the excavation portion to reciprocate in the horizontal direction It has an approximate configuration consisting of a transport unit 200 to be installed and a traction unit 300 to lift the underground structure to be disposed inside the excavation.

우선, 본 발명 흙막이부(100)를 살펴보면, 굴착부 내측에 일정 간격 입설되는 다수 개의 지주(110)와, 지주(110)의 일측 체결홀(112a)에 끼워지는 상부 지지 패널(121a) 및 하부 지지 패널(121b)과 타측 체결홀(112b)에 끼워지는 상부 슬라이드 패널(123a) 및 하부 슬라이드 패널(123b)로 구성되는 패널(120)로 구성되며, 지주(110)에 활강편(131)이 결합되되, 일정거리 수직 하강하여 고정되는 지지재(130) 및 마주하는 지지재(130) 사이에 결합, 설치되어 굴착폭에 따라 조립 갯수를 달리하게 되는 간격재(140)로 구성되게 된다.First, looking at the present invention the earth portion 100, a plurality of struts 110 which are placed at a predetermined interval inside the excavation portion, and the upper support panel 121a and the lower portion fitted to one side fastening hole 112a of the strut 110 It consists of a panel 120 composed of an upper slide panel 123a and a lower slide panel 123b fitted into the support panel 121b and the other fastening hole 112b, and the sliding piece 131 is formed on the support 110. It is coupled, but is composed of the spacer 140 is coupled, installed between the support member 130 and the support member 130 facing the fixed down vertically fixed distance to vary the number of assembly according to the excavation width.

상기 지주(110)는 다수 개의 길쭉한 프레임(111)의 결합으로 형성되되, 양측면으로 패널과의 체결을 위한 길쭉한 체결홀(112a, 112b)이 형성되도록 다수 개의 프레임(111)이 결합되며, 상기 지주(110)의 전방으로는 길쭉한 플레이트 형상의 가이드 프레임(113)이 형성되는 바, 상기 가이드 프레임(113)은 지주(110)의 전방에 형성되되, 지주(110)와 일정간격 이격된 거리로 결합되어 가이드 프레임(113)과 지주(110) 사이 양측으로 끼움홀(114)이 형성되게 된다.The support 110 is formed by the combination of a plurality of elongated frames 111, a plurality of frames 111 are coupled to form an elongated fastening holes (112a, 112b) for fastening with the panel on both sides, the support A guide plate 113 having an elongated plate shape is formed in front of the 110, and the guide frame 113 is formed in front of the support 110, and is coupled to the support 110 at a predetermined distance from the support frame. As a result, the fitting holes 114 are formed at both sides between the guide frame 113 and the support 110.

또한, 상기 지주(110)의 전방으로는 다수 개의 체결공(115)이 형성되는 바, 후술하는 지지재(130)를 끼움홀(114)의 상부로 끼워넣어 하부로 일정거리 활강시킨 후, 지지재(130)의 하부에 위치되는 체결공(115)에 체결핀(116)을 끼워넣어 지지재(130)가 더 이상 하강하지 않고 고정되도록 지지시킨다. In addition, a plurality of fastening holes 115 are formed in front of the support 110, and the support member 130, which will be described later, is inserted into the upper portion of the fitting hole 114, and then slides downward for a predetermined distance. The fastening pin 116 is inserted into the fastening hole 115 positioned at the lower portion of the ash 130 to support the support member 130 so as not to be lowered anymore.

한편, 상기 지주(110)의 양측으로는 패널(120)이 끼워져 고정되는 바, 상기 패널(120)은 상부 지지 패널(121a) 및 하부 지지 패널(121b)과 그에 각각 슬라이딩 입출되는 상부 슬라이드 패널(123a) 및 하부 슬라이드 패널(123b)로 구성되며, 상기 각 패널은 지주(110)의 양측에 형성되는 체결홀(112a, 112b)에 끼워질 수 있도록 체결편(122a, 122b, 124a, 124b)이 형성되어 상기 체결편(122a, 124a)을 체결홀(112)의 상부로부터 하부로 활강시켜 지주(110)에 결합시킨다.On the other hand, the panel 120 is inserted and fixed to both sides of the support 110, the panel 120 is the upper support panel 121a and the lower support panel 121b and the upper slide panel (sliding and sliding) respectively 123a) and a lower slide panel 123b, wherein each panel includes fastening pieces 122a, 122b, 124a, and 124b to be fitted into fastening holes 112a and 112b formed at both sides of the support 110. Is formed to slide the fastening pieces (122a, 124a) from the top of the fastening hole 112 to the bottom to couple to the support (110).

상기 하부 슬라이드 패널(123b)은 하부 지지 패널(121b)에 그 일단이 외부로 입출되지 않도록 구속되되, 하부 지지 패널(121b)의 체결편(122b)이 하나의 지주(110)에 결합되게 되면, 그에 구속된 하부 슬라이드 패널(123b)의 체결편(124b)은 상기 하부 지지 패널(121b)과 결합된 상기 지주(110)와 이웃하는 지주(110)와 결합시키게 되며, 상기 지주(110)와 패널(120)의 반복적 결합으로 하나의 흙막이 벽체가 재현되게 된다.The lower slide panel 123b is constrained so that one end of the lower slide panel 123b does not enter or exit the outside, and the fastening piece 122b of the lower support panel 121b is coupled to one support 110. The fastening piece 124b of the lower slide panel 123b constrained thereto is coupled to the strut 110 adjacent to the strut 110 coupled with the lower support panel 121b, and the strut 110 and the panel. By repetitive combination of 120, one retaining wall is reproduced.

한편, 상기 상부 지지 패널(121a) 및 하부 지지 패널(121b)과 그에 각각 슬라이딩 입출되는 상부 슬라이드 패널(123a) 및 하부 슬라이드 패널(123b)의 상부로는 패널(120)을 인양하고 이동, 설치하기 위한 인발공(125a, 125b)이 형성되며, 상부 지지 패널(121a) 및 상부 슬라이드 패널(123a)의 하부로는 하부 지지 패널(121b) 및 하부 슬라이드 패널(123b)과의 결합을 위한 체결공(126a)이 형성되어 인발공(125a, 125b)과 체결공(126a)을 체결핀(127)으로 결합시킴으로써 상부 및 하부로 구분된 패널을 하나의 패널체로 결합되게 한다.Meanwhile, the upper support panel 121a and the lower support panel 121b and the upper slide panel 123a and the lower slide panel 123b that slide in and out respectively are lifted, moved, and installed on the upper part of the upper support panel 121a and the lower support panel 121b. Draw holes 125a and 125b are formed, and fastening holes for coupling with the lower support panel 121b and the lower slide panel 123b to the lower portions of the upper support panel 121a and the upper slide panel 123a ( 126a is formed to couple the upper and lower panels into one panel by coupling the drawing holes 125a and 125b and the fastening holes 126a with the fastening pins 127.

상기 하부 지지 패널(121b)의 하부로는 유압잭(128)에 결합되어 왕복운동하는 렉기어(129)가 형성되는 바, 유압펌프(미도시)로부터 유압이 공급되면, 피스톤이 신장되어 렉기어(129)를 일방향으로 밀어주게 되며, 유압을 차단하면 렉기어(129)가 대기상태의 위치로 회귀하게 되며, 상기와 같이 렉기어(129)의 수평방향으로의 왕복운동으로 패널(120)의 지중 입설을 용이하게 하여준다.The lower support panel 121b has a lower gear panel 129 coupled to the hydraulic jack 128 to reciprocate to form a lower bar. When hydraulic pressure is supplied from a hydraulic pump (not shown), the piston is extended to provide a lex gear ( 129 is pushed in one direction, and when the hydraulic pressure is interrupted, the lex gear 129 returns to the standby position, and the ground of the panel 120 is reciprocated in the horizontal direction of the lex gear 129 as described above. It facilitates the entry.

한편, 상기 지주(110)의 전방에 결합되는 지지재(130)는 직사각 박스형태로 형성되되, 일측은 길쭉한 플레이트 형태의 활강편(131)이 형성되어 상기 끼움홀(114)에 끼워지어 지주(110)에 결합되되, 타측은 다수의 통공(132)이 형성된 플레이트가 결합 형성되게 되며, 굴착부에 흙막이를 설치시 마주하게 되는 두 개의 지지재(130) 사이로는 간격재(140)가 결합되되, 다수의 통공(141)이 형성된 플레이트가 양측으로 결합 형성된 직사각 박스형태로 형성되며 지지재(130) 및 간격재(140)의 마주하는 결합공을 체결핀(150)으로 체결하여 지지재(130)와 간격재(140)를 결합시키며, 굴착부 폭에 따라 간격재(140)의 결합 갯수를 달리하여 결합시켜 현장 굴착폭에 따른 유동적인 변형이 용이한 흙막이부(100)의 결합이 이루어진다.
On the other hand, the support member 130 coupled to the front of the support 110 is formed in a rectangular box shape, one side is formed of a sliding plate 131 of the elongated plate shape is inserted into the fitting hole 114 to support ( 110 is coupled to the other side, the plate formed with a plurality of through holes 132 is formed to be coupled, the spacer 140 is coupled between the two support member 130 which is faced when installing the earthenware excavation portion , The plate formed with a plurality of through holes 141 is formed in a rectangular box shape formed to be coupled to both sides and the support member 130 by fastening the coupling hole facing the support member 130 and the spacer 140 with a fastening pin 150. ) And the spacer 140 are coupled, and the coupling unit 100 is easily coupled by varying the number of couplings of the spacer 140 according to the width of the excavation part, thereby allowing the fluid deformation 100 to be easily changed according to the site excavation width.

다음으로, 이송부(200)를 살펴보면, 흙막이부(100) 지주(110)와 상부 지지 패널(121b) 및 상부 슬라이드 패널(123b)의 상부에 설치되는 레일(210)과 레일(210)상에서 활주하는 롤러(220) 및 이송부(200)의 지지체가 되는 다수 개의 수직 프레임(231)과 수평 프레임(232) 및 지지 프레임(233)으로 형성되게 된다.Next, referring to the conveying part 200, the sliding part 100 installed on the rails 210 and the rails 210 installed on the support 110, the upper support panel 121b, and the upper slide panel 123b. The plurality of vertical frames 231, horizontal frames 232, and support frames 233, which are the supports of the roller 220 and the transfer unit 200, are formed.

상기 지지체는 다수 개의 수직 프레임(231)과 다수 개의 수평 프레임(232)으로 형성되는 직사각 형태의 프레임과 직사각 프레임을 지지하기 위한 지지 프레임(233)으로 결합되는 프레임체(230)가 마련되는 바, 상기 프레임체(230)는 그 하부에 다수의 롤러(220)를 형성하여 레일(210)상에 배치시킴으로써 프레임체(230)가 수평 이동할 수 있도록 구성된다.The support is provided with a frame body 230 coupled to a frame having a rectangular shape formed of a plurality of vertical frames 231 and a plurality of horizontal frames 232 and a support frame 233 for supporting a rectangular frame. The frame body 230 is configured such that the frame body 230 can move horizontally by forming a plurality of rollers 220 on the rail 210 and disposed on the rail 210.

또한, 상기 다수 개의 수평 프레임(232)의 일정 위치로는 유압잭(240)이 설치되어 유압 펌프(미도시)로부터 유압이 공급되고 차단됨으로 유압잭(240)의 피스톤이 신장, 수축되고, 수평 프레임(232)의 일단을 밀어주고 회귀시켜주게 되며, 이로 인해 수평 프레임(232)의 길이 신장과 수축이 가능하도록 하며, 상기 다수의 최상부 수평 프레임(232)의 하부로는 가이드 레일(250)이 형성되어, 후술하는 견인부(300)가 결합될 수 있게 한다.
In addition, the hydraulic jack 240 is installed at a predetermined position of the plurality of horizontal frames 232 so that the hydraulic pressure is supplied and shut off from the hydraulic pump (not shown), so that the piston of the hydraulic jack 240 is extended and contracted, and the horizontal frame ( One end of the 232 is pushed and returned, thereby allowing the extension and contraction of the length of the horizontal frame 232, the guide rail 250 is formed in the lower portion of the plurality of top horizontal frames 232 , Towing unit 300 to be described later.

마지막으로, 견인부(300)는 구동 모터(310)와 모터의 회전력을 롤러(330)에 전달하는 감속기(320)와, 상기 가이드 레일(250) 상에 설치되되, 구동모터(310)의 회전력을 전달받아 회전하며 수평방향으로 전진 및 후진하는 회전 롤러(330)와, 지하구조물을 인양하기 위한 권취 체인(350) 및 견인 체인(370)으로 구성된다.Finally, the traction unit 300 is installed on the guide rail 250 and the reducer 320 for transmitting the rotational force of the drive motor 310 and the motor to the roller 330, the rotational force of the drive motor 310 It is composed of a rotating roller 330 that receives and rotates forward and backward in a horizontal direction, and a winding chain 350 and a traction chain 370 for lifting an underground structure.

상기 구동 모터(310)는 회전 롤러(330)의 회전과 권취 체인(350)의 권취를 위한 구동력을 제공해주며, 상기 감속기(320)가 롤러(330)와 권취 박스(340) 내의 권취 롤러(미도시)에 구동력을 전달하여 롤러 회전이 이루어지게 된다.The drive motor 310 provides a driving force for the rotation of the rotary roller 330 and the winding of the winding chain 350, the reduction gear 320 is a winding roller (not shown) in the roller 330 and the winding box 340 When the driving force is transmitted to the roller rotation is made.

상기 권취 박스(340) 내부로는 권취 체인(350)이 권취되는 바, 상기 권취 체인(350)은 수평방향으로 길쭉하게 형성되는 플레이트 형태의 지지바(360)에 걸림고리 등으로 결합 되어지며, 상기 지지바(360)의 하부 양측으로 견인 체인(370)이 마련되어 상기 견인 체인(370)으로 지하구조물을 인양하여 굴착부에 설치하도록 구성된다.
The winding chain 350 is wound into the winding box 340, and the winding chain 350 is coupled to the support bar 360, which is formed in an elongated shape in the horizontal direction, by a hook or the like. Traction chains 370 are provided on both lower sides of the support bar 360 to lift underground structures with the traction chains 370 to be installed in the excavation part.

한편, 상기 본 발명 흙막이 구조를 통한 지하구조물 시공방법을 살펴보면,On the other hand, look at the construction method of the underground structure through the earth block structure of the present invention,

지하구조물 시공 현장에 본 발명 흙막이 구조를 이루는 각 구성 부재와 설치할 지하구조물을 반입하여 두고, 두 개의 지주(110)에 각각 하나씩 지지재(130)를 결합시키되, 지주(110) 끼움홀(114)의 상부로부터 지지재(130)의 활강편(131)을 끼워넣어 일정거리 하강시킨 후, 지주(110)에 형성된 다수의 체결공(115) 중 지지재(130)의 하부에 위치되는 체결공(115)에 체결핀(116)을 끼워넣어 볼트 등으로 체결하여 지지재(130)가 더이상 하강하지 못하도록 위치를 고정함으로써 지주(110)와 지지재(130)를 결합시키고, 상기 마주하는 두 지지재(130) 사이로 간격재(140)를 결합시키는 바, 시공 현장에서 요하는 굴착폭에 상응하도록 간격재(140)의 갯수를 산정하여 결합시키되, 지지재(130)의 일측에 마련된 다수 개의 통공(132)과 간격재(140)의 양측에 형성된 다수 개의 통공(141)이 서로 맞접되도록 위치시켜 상기 통공(132, 141)을 관통하도록 다수 개의 체결핀(150)을 체결하여 결합시키면 된다.While carrying out each structural member and basement structure to be installed in the construction site of the earth structure to the construction site of the underground structure, to combine the support member 130 to each one of the two support (110), the support (110) fitting hole 114 After inserting the sliding piece 131 of the support member 130 from the upper portion of the support member 130 and lowering it by a predetermined distance, the fastening hole located at the lower portion of the support member 130 among the plurality of fastening holes 115 formed in the support 110 ( Insert the fastening pin 116 into the 115 and fasten with a bolt or the like to fix the position so that the support member 130 does not lower anymore, thereby combining the support 110 and the support member 130, and the two support members facing each other. Couple the spacer 140 between the bars 130, the number of the spacer 140 is calculated to be coupled to correspond to the excavation width required in the construction site, a plurality of through holes provided on one side of the support member 130 ( 132 and a plurality of through-holes 141 formed on both sides of the spacer 140 is standing It was placed such that when coupled to matjeop is entered into a number of coupling pins 150 to pass through the through holes (132, 141).

그런 다음, 최초 시공할 위치에 굴착기로 일정깊이 터파기를 실시한 후, 상기 조립한 지주(110)와 지지재(130) 및 간격재(140) 결합체를 와이어로 들어 굴착위치에 입설시킨다. Then, after carrying out the trench at a predetermined depth to the position to be constructed initially, the assembled strut 110, the support member 130 and the spacer 140 is combined with a wire and placed in the excavation position.

그런 후, 하부 지지 패널(121b) 및 하부 슬라이드 패널(122b)을 설치하게 되는데, 하부 슬라이드 패널(122b)은 하부 지지 패널(121b)에 그 일단이 외부로 입출되지 않도록 구속되되, 패널의 외부 노출 면적을 자유로이 조절할 수 있도록 수평방향으로 직선운동 가능하도록 결합시킨 상태에서, 인발공(125b)에 와이어 및 걸림 부재를 걸어 패널을 인양시킨 후, 지주(110)의 체결홀(112a) 상부로부터 체결편(123b)을 끼워넣어 하강시켜 결합시키고, 마주하는 지주(110)도 동일하게 패널을 결합시킨다. Thereafter, the lower support panel 121b and the lower slide panel 122b are installed, and the lower slide panel 122b is constrained so that one end of the lower slide panel 122b does not enter the outside, but is exposed to the outside of the panel. In a state in which the linear motion in the horizontal direction is combined to freely adjust the area, the wire and the engaging member are hooked to the drawing hole 125b to lift the panel, and then the fastening piece from the upper part of the fastening hole 112a of the support 110. 123b is inserted and lowered to be coupled, and the struts 110 facing each other are similarly coupled to the panel.

상기 지주(110)와 패널(120)의 결합이 완료되면, 굴착과 압입을 반복하여 목표 굴착깊이까지 굴착하여 흙막이부(100)를 설치하게 되는데, 이때 유압펌프(미도시)로부터 유압잭(128)으로 유압의 공급과 차단을 반복하여 렉 기어(129)가 수평방향으로 왕복 운동하도록 하여 패널(120)의 압입이 용이하도록 한다.When the coupling of the support 110 and the panel 120 is completed, the excavation and indentation are repeated to excavate to a target excavation depth to install the earth block portion 100, wherein the hydraulic jack 128 from the hydraulic pump (not shown) As a result, the rack gear 129 reciprocates in the horizontal direction by repeatedly supplying and shutting off the hydraulic pressure to facilitate the press-fit of the panel 120.

상기의 공정을 두 개조 내지 세 개조 시공 후, 상기 지주(110)와 패널(120)의 상부에 레일(210)을 설치하면 되는데, 상기 레일(210)은 다수 개의 레일(210)이 일렬로 정렬되어 하나의 긴 레일체가 형성되도록 하되, 하나의 레일(210)의 중앙부가 지주(110)의 상부에 위치되도록 하여 배치시킨 후, 상부에 프레임체(230)가 결합된 롤러(220)를 레일(210)상에 배치시킨다.After two or three modifications to the above process, the rails 210 may be installed on the pillar 110 and the panel 120, and the rails 210 may be arranged in a row in a plurality of rails 210. One long rail body to be formed, and the central part of the one rail 210 is positioned to be positioned above the strut 110, and then the roller 220 having the frame body 230 coupled to the upper rail ( On 210).

그런 후, 구동 모터(310)를 구동시켜 회전 롤러(330)를 회전이 이루어지게 하여 견인부(330)를 전진 및 후진시키게 되는데, 현장에 반입되어 있는 지중구조물을 견인 체인(370)으로 걸어 지중구조물을 견인부(300)에 고정시킨 후, 권취 체인(350)을 권취 박스(340) 내에 권취시킴으로써 지중 구조물을 인양하여 굴착부에 안착시키고, 굴착부에 설치된 지중 구조물에 이웃하게 다른 하나의 지중 구조물을 설치하며 상기 작업의 반복적인 전진 시공 후, 이송부(200) 및 견인부(300)를 철거하고, 굴착부에 되메우기 한 후, 흙막이부(100)를 인발하면 본 발명에 따른 지하구조물의 설치가 완료되게 된다.
Thereafter, the driving roller 310 is driven to rotate the rotating roller 330 to move the traction unit 330 forward and backward. The underground structure carried in the site is hung on the traction chain 370. After fixing the structure to the towing unit 300, the winding chain 350 is wound in the winding box 340 to lift the underground structure to be seated in the excavation, the other underground adjacent to the underground structure installed in the excavation After installing the structure and repeating the forward construction of the operation, after dismantling the transfer unit 200 and the traction unit 300, and backfilled in the excavation, when pulling up the retaining unit 100, the installation of the underground structure according to the present invention Will be completed.

100 : 흙막이부 110 : 지주
111 : 프레임 112a, 112b : 체결홀
113 : 가이드 프레임 114 : 끼움홀
115 : 체결공 116 : 체결핀
120 : 패널 121a : 상부 지지 패널
121b : 하부 지지 패널 122a, 122b : 체결편
123a : 상부 슬라이드 패널 123b: 하부 슬라이드 패널
124a, 124b : 체결편 125a, 125b : 인발공
126a : 체결공 127 : 체결핀
128 : 유압잭 129 : 렉 기어
130 : 지지재 131 : 활강편
132 : 통공 140 : 간격재
141 : 통공 150 : 체결핀
200 : 이송부 210 : 레일
220 : 롤러 230 : 프레임체
231 : 수직 프레임 232 : 수평 프레임
233 : 지지 프레임 240 : 유압잭
250 : 가이드 레일 300 : 견인부
310 : 구동 모터 320 : 감속기
330 : 회전 롤러 340 : 권취 박스
350 : 권취 체인 360 : 지지바
370 : 견인 체인
100: soil portion 110: prop
111: frame 112a, 112b: fastening hole
113: guide frame 114: fitting hole
115: fastening hole 116: fastening pin
120 panel 121a upper support panel
121b: Lower support panel 122a, 122b: Fastening piece
123a: upper slide panel 123b: lower slide panel
124a, 124b: Fastener 125a, 125b: Drawing hole
126a: fastening hole 127: fastening pin
128: hydraulic jack 129: rack gear
130: support material 131: downhill
132: through hole 140: spacer
141: through hole 150: fastening pin
200: transfer unit 210: rail
220: roller 230: frame
231: vertical frame 232: horizontal frame
233: support frame 240: hydraulic jack
250: guide rail 300: towing unit
310: drive motor 320: reducer
330: rotary roller 340: winding box
350: winding chain 360: support bar
370: tow chain

Claims (4)

지중 관 및 하수박스 등의 지하구조물 설치를 위한 지반 굴착작업 시, 토압에 대응하고 굴착 토사의 붕괴를 방지하기 위해 굴착부 측면으로 설치되는 흙막이 구조에 있어서,
다수 개의 길쭉한 프레임(111)의 결합으로 형성되어 굴착부 내측에 일정 간격 입설되되 양측면으로 길쭉한 체결홀(112a, 112b)이 형성된 다수 개의 지주(110)와, 일단이 지주(110)의 일측 체결홀(112a)에 끼워지는 상부 지지 패널(121a) 및 하부 지지 패널(121b)과, 상부 지지 패널(121a) 및 하부 지지 패널(121b)에 일단이 결속되어 수평방향으로 슬라이딩 입출되되 타단은 또 다른 지주(110)의 타측 체결홀(112b)에 끼워지는 상부 슬라이드 패널(123a) 및 하부 슬라이드 패널(123b)로 구성되는 패널(120)과, 지주(110)에 활강편(131)이 결합되되 일정거리 수직 하강하여 고정되는 지지재(130) 및 마주하는 지지재(130) 사이에 결합, 설치되어 굴착폭에 따라 조립개수를 달라히는 간격재(140)로 구성되는 흙막이부(100)와;
지주(110)와 상부 지지 패널(121a) 및 상부 슬라이드 패널(123a)의 상부에 설치되는 레일(210)과, 레일(210) 상에서 활주하는 다수 개의 롤러(220)와, 롤러(220)의 상부에 형성되되 다수 개의 수직 프레임(231)과 수평 프레임(232)의 결합으로 직사각 프레임을 형성하는 프레임체(230)와, 최상부 수평 프레임(232)의 하부에 형성되는 가이드 레일(250)로 구성되는 이송부(200)와;
구동 모터(310)와, 구동 모터(310)의 회전력을 전달하는 감속기(320)와, 가이드 레일(250) 상에서 활주하되 구동 모터(310)의 회전력을 전달받아 회전하며 수평방향으로 전진 및 후진하는 회전 롤러(330)와, 지하 구조물을 인양하는 견인 체인(370)으로 구성되는 견인부(300)로 구성되어 착탈식의 견인 수단이 구비되어 지하 구조물을 설치하도록 함을 특징으로 하는 흙막이 구조.
In the earth excavation work for the installation of underground structures such as underground pipes and sewage boxes, in the earth block structure that is installed on the side of the excavation part to cope with earth pressure and prevent the collapse of the excavated soil,
Formed by the combination of a plurality of elongated frame 111 is placed in a predetermined interval inside the excavation portion, but a plurality of struts 110 formed with elongated fastening holes (112a, 112b) on both sides, one end of one side of the strut 110 One end is coupled to the upper support panel 121a and the lower support panel 121b and the upper support panel 121a and the lower support panel 121b to be fitted to the 112a, and slides in and out in the horizontal direction, but the other end is another post. The sliding piece 131 is coupled to the panel 120 including the upper slide panel 123a and the lower slide panel 123b inserted into the other fastening hole 112b of the 110 and the support 110, but a predetermined distance is provided. An earth retaining portion 100 configured to be coupled and installed between the support member 130 and the support member 130 facing each other by being vertically lowered and configured with a spacer 140 varying in the number of assembly according to the excavation width;
Rails 210 installed on the support 110, the upper support panel 121a, and the upper slide panel 123a, a plurality of rollers 220 sliding on the rails 210, and upper portions of the rollers 220. Is formed in the frame body 230 to form a rectangular frame by combining a plurality of vertical frame 231 and a horizontal frame 232, and a guide rail 250 formed on the lower portion of the uppermost horizontal frame 232 A transfer unit 200;
The drive motor 310, the reducer 320 for transmitting the rotational force of the drive motor 310, and slides on the guide rail 250, rotates by receiving the rotational force of the drive motor 310 to move forward and backward in the horizontal direction Retaining structure consisting of a rotating roller 330, the traction unit 300 consisting of a traction chain 370 to lift the underground structure is provided with a removable traction means to install the underground structure.
제 1항에 있어서,
하부 지지 패널(121b) 하부로는 유압의 공급과 차단에 따라 신장 및 수축되는 유압잭(128)이 마련되되, 유압잭(128)과 연계되어 수평방향으로 왕복운동하는 렉 기어(129)가 형성되어 패널의 지중 입설을 용이하게 함을 특징으로 하는 착탈식 견인 수단이 구비된 흙막이 구조.
The method of claim 1,
The lower support panel 121b is provided with a hydraulic jack 128 that extends and contracts according to supply and interruption of the hydraulic pressure, and a rack gear 129 is formed to reciprocate in a horizontal direction in connection with the hydraulic jack 128. A retaining structure provided with a detachable towing means, characterized in that it facilitates the installation of underground.
제 1항에 있어서,
다수 개의 수평 프레임(232)의 일정 위치로 유압잭(240)이 설치되어 유압잭(240)의 신장과 수축을 통해 굴착폭에 따라 수평 프레임(232) 길이를 조절할 수 있도록 함을 특징으로 하는 착탈식 견인 수단이 구비된 흙막이 구조.
The method of claim 1,
Removable towing means characterized in that the hydraulic jack 240 is installed to a predetermined position of the plurality of horizontal frame 232 to adjust the length of the horizontal frame 232 according to the excavation width through the expansion and contraction of the hydraulic jack 240. It is equipped with a retaining structure.
지중 관 및 하수박스 등의 지하구조물 시공방법에 있어서,
최초 시공할 위치에 굴착기로 일정 깊이 터파기를 실시한 후, 두 개의 지주(110)에 각각 하나씩 지지재(130)를 결합시키고 굴착폭에 상응하도록 갯수를 산정하여 두 지지재(130) 사이에 간격재(140)를 결합시켜 굴착 위치에 입설시킨 후, 내측 하부에 유압잭(128)과 유압잭(128)의 신장 및 수축에 따라 수평 운동하는 렉 기어(129)가 결합된 하부 지지 패널(121b)과 하부 지지 패널(121b)에 일단이 결속되는 하부 슬라이드 패널(123b)을 결합시키고, 결합된 하부 지지 패널(121b)과 하부 슬라이드 패널(123b)을 인양하여 각각의 두 개 지주(110)의 상부로부터 일단을 끼워 하강시키되 유압을 공급하여 하부 지지 패널(121b) 하부에 형성된 유압잭(128)의 신장과 수축을 반복하여 렉 기어(129)의 수평운동이 이루어지게 하면서 하부 지지 패널(121b)과 하부 슬라이드 패널(123b)을 지중에 압입시키고, 마주하는 두 개의 하부 지지 패널(121b) 사이의 토사를 굴착하면서 하부 지지 패널(121b)과 하부 슬라이드 패널(123b)의 상부에 상부 지지 패널(121a)과 상부 지지 패널(121a)에 일단이 결속되는 상부 슬라이드 패널(123a)을 결합시키고, 지주(110) 입설과 패널(120) 설치를 두 개조 내지 세 개조 시공 후, 지주(110)와 상부 지지 패널(121a) 및 상부 슬라이드 패널(123a) 상부에 다수 개의 레일(210)을 설치하고, 하부에 롤러(220)가 결합되고 구동 모터(310)와 그에 의해 구동하는 견인 체인(370)이 결합된 프레임체(230)를 레일(210) 상부에 배치한 후, 구동 모터(310)를 구동시켜 견인 체인(370)이 구조물을 인양하여 굴착부에 안착시켜 지하 구조물을 설치하도록 함을 특징으로 하는 지하구조물 시공방법.
In the construction method of underground structures such as underground pipes and sewage boxes,
After the trench was drilled at a position to be constructed for the first time, the support member 130 was coupled to each of the two struts 110, and the number of the gaps was calculated to correspond to the excavation width. The lower support panel 121b and the lower portion of the lower support panel 121b coupled with the rack gear 129 which horizontally moves in accordance with the elongation and contraction of the hydraulic jack 128 and the hydraulic jack 128 are coupled to the excavated position after entering the excavation position 140. Coupling the lower slide panel 123b, one end of which is bound to the support panel 121b, and lifting the combined lower support panel 121b and the lower slide panel 123b to one end from the top of each two struts 110. The lower support panel 121b and the lower slide panel while supplying hydraulic pressure to supply the hydraulic pressure to repeat the expansion and contraction of the hydraulic jack 128 formed under the lower support panel 121b to allow horizontal movement of the rack gear 129. Underground (123b) One end of the upper support panel 121a and the upper support panel 121a on the upper part of the lower support panel 121b and the lower slide panel 123b while being press-fitted and excavating soil between two opposing lower support panels 121b. The binding upper slide panel 123a is coupled to each other, and the post 110 and the installation of the panel 120 are retrofitted after two or three renovations, and then the support 110 and the upper support panel 121a and the upper slide panel 123a. ) A plurality of rails 210 are installed on the upper part of the rail, and the rails 210 are coupled to the lower part of the frame body 230 to which the roller 220 is coupled, and the driving motor 310 and the towing chain 370 driven thereto are coupled. After placing the upper portion, the underground structure construction method characterized in that by driving the drive motor 310 tow the traction chain (370) to lift the structure to be seated in the excavation to install the underground structure.
KR1020110093059A 2011-09-15 2011-09-15 Structure of retaining wall and construction method for installing underground structures Withdrawn KR20130030340A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110093059A KR20130030340A (en) 2011-09-15 2011-09-15 Structure of retaining wall and construction method for installing underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110093059A KR20130030340A (en) 2011-09-15 2011-09-15 Structure of retaining wall and construction method for installing underground structures

Publications (1)

Publication Number Publication Date
KR20130030340A true KR20130030340A (en) 2013-03-27

Family

ID=48179897

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110093059A Withdrawn KR20130030340A (en) 2011-09-15 2011-09-15 Structure of retaining wall and construction method for installing underground structures

Country Status (1)

Country Link
KR (1) KR20130030340A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173001A (en) * 2020-02-22 2020-05-19 王笑然 Multi-row pile foundation pit supporting structure
CN114482065A (en) * 2021-12-09 2022-05-13 中建八局第二建设有限公司 Deep foundation pit construction device for newly-built building, close to subway and connected with subway
KR200496251Y1 (en) * 2021-12-08 2022-12-09 박현희 Maintenance structure apparatus setting on upper side of polar crane in nuclear power plant containment building
CN116177387A (en) * 2022-12-01 2023-05-30 中铁十六局集团有限公司 Auxiliary crane for manual hole-digging pile construction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173001A (en) * 2020-02-22 2020-05-19 王笑然 Multi-row pile foundation pit supporting structure
CN111173001B (en) * 2020-02-22 2021-08-06 广东新业建设股份有限公司 Multi-row pile foundation pit supporting structure
KR200496251Y1 (en) * 2021-12-08 2022-12-09 박현희 Maintenance structure apparatus setting on upper side of polar crane in nuclear power plant containment building
CN114482065A (en) * 2021-12-09 2022-05-13 中建八局第二建设有限公司 Deep foundation pit construction device for newly-built building, close to subway and connected with subway
CN114482065B (en) * 2021-12-09 2023-09-12 中建八局第二建设有限公司 Deep foundation pit construction device for newly-built building adjacent to subway and connected with subway
CN116177387A (en) * 2022-12-01 2023-05-30 中铁十六局集团有限公司 Auxiliary crane for manual hole-digging pile construction

Similar Documents

Publication Publication Date Title
KR101034398B1 (en) Underground structure construction method that combines underground clogging method
KR101094827B1 (en) Variable Simple Earth Block Structure
US20150021530A1 (en) Modular Guide Sleeve Apparatus and Method
KR20130030340A (en) Structure of retaining wall and construction method for installing underground structures
KR20130061377A (en) Structure of retaining wall and construction method for installing underground structures
KR20130085772A (en) Structure of retaining wall for underground connection structure construction method in low depth
KR20120119570A (en) Structure of variable temporary retaning wall
KR20120109418A (en) Inclined earth retaining structure method
KR20130061372A (en) Structure of retaining wall and construction method for installing underground structures
KR101185599B1 (en) Apparatus for constructing retaining wall
KR101517169B1 (en) The the underground structure to equip the pressing dievice
KR20130061368A (en) Structure of retaining wall and construction method for installing underground structures
KR20130085776A (en) Structure of retaining wall for underground connection structure construction method in low depth
JP6387778B2 (en) Suspension jig used when building the core material of the underground continuous wall, the method of building the core material of the underground continuous wall, and the system for building the core material of the underground continuous wall
KR20120088627A (en) Temporary pile using bending restoring force and temporary structure construction method therewith
KR20060122047A (en) Pile driver for underground continuous wall with guide rail and clamping device
KR20120088929A (en) Structure of Temporary Retaning wall
KR100568988B1 (en) Structure of retaining wall using slide panel and installation method
KR200392277Y1 (en) Pile driver for structural walls having inducement rail-unit & catch-unit
KR20130061370A (en) Structure of retaining wall and construction method for installing underground structures
KR100669527B1 (en) Earthwork
KR101239899B1 (en) Structures and production methods column mesh of slurry wall and construction method using a column mesh of slurry wall
JP3043502B2 (en) Drilling hole formation method for thin film wall construction
EP1348812A1 (en) Building methods and apparatus
JP7301203B1 (en) Earth retaining device for shallow excavated trenches

Legal Events

Date Code Title Description
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20110915

PG1501 Laying open of application
PC1203 Withdrawal of no request for examination
WITN Application deemed withdrawn, e.g. because no request for examination was filed or no examination fee was paid