[go: up one dir, main page]

JPH1136788A - Tunnel excavation method with continuous supply support - Google Patents

Tunnel excavation method with continuous supply support

Info

Publication number
JPH1136788A
JPH1136788A JP9212643A JP21264397A JPH1136788A JP H1136788 A JPH1136788 A JP H1136788A JP 9212643 A JP9212643 A JP 9212643A JP 21264397 A JP21264397 A JP 21264397A JP H1136788 A JPH1136788 A JP H1136788A
Authority
JP
Japan
Prior art keywords
tunnel
support
support material
continuous supply
excavation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9212643A
Other languages
Japanese (ja)
Inventor
Tomoyuki Aoki
智幸 青木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP9212643A priority Critical patent/JPH1136788A/en
Publication of JPH1136788A publication Critical patent/JPH1136788A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

(57)【要約】 【課題】 簡単な方法により、作業性のよい、安価
な連続供給支保によるトンネル掘削工法を提供する。 【解決手段】 トンネルを掘進し、掘進した後方に支保
工を設置するための方法であって、トンネル掘削機内部
に支保材を収納し、トンネル掘削機の掘進に伴い、支保
材が連続的に掘進した後方に供給されていくことを特徴
とする、連続供給支保によるトンネル掘削工法であり、
また、支保材は、ロール状又は折り畳み状にして支保材
収納箱に収納し、トンネル掘削機の上半断面部分に設け
た供給口から連続的に供給されていくことを特徴とす
る、連続供給支保によるトンネル掘削工法であり、さら
にまた、連続的に供給される支保材は、トンネル頂部
と、トンネル両側壁部とに分割して供給されていくこと
を特徴とする、連続供給支保によるトンネル掘削工法で
ある。
(57) [Summary] [PROBLEMS] To provide a tunnel excavation method with good workability and inexpensive continuous supply by a simple method. SOLUTION: This is a method for digging a tunnel and installing a shoring behind the digging, in which a shoring material is stored inside the tunnel digging machine, and the shoring material is continuously formed as the tunnel digging machine excavates. It is a tunnel excavation method with continuous supply support characterized by being supplied behind the excavation,
Further, the support material is stored in a support material storage box in a roll shape or a folded shape, and is continuously supplied from a supply port provided in an upper half cross section of the tunnel excavator. A tunnel excavation method using continuous support, wherein the continuously supplied support material is divided and supplied to the top of the tunnel and both side walls of the tunnel. It is a construction method.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、トンネル支保工の
設置方法に関する。
The present invention relates to a method for installing a tunnel support.

【0002】[0002]

【従来の技術】トンネル掘削機には、トンネルボーリン
グマシーン(以下、TBMという。)やシールド掘削機
等がある。以下、図4、図5を参照して説明する。図4
はTBM1とシールド掘削機2を合体させた、シールド
型TBM3で掘進中の状況を示す縦断面図である。TB
M1先端のカッターヘッド4を回転させ、切羽Gを掘削
しジャッキ5を伸長してトンネル断面を形成していく。
これら従来のトンネル掘削機では、トンネルの天端や側
壁の岩塊6が崩落してトンネル掘削機の上に載った場
合、作業員の安全を確保しながら支保工を設置しなけれ
ばならず、そのためには先ず崩落した岩塊6を取り除
き、支保工を設置する必要があった。崩落した岩塊6を
取り除く作業は、それ自体非常に危険な作業でありその
間掘進作業は中断しなければならず、且つ、かなりの部
分が人力作業となるため、作業効率は大幅に低下するこ
とになる。
2. Description of the Related Art Tunnel excavators include a tunnel boring machine (hereinafter referred to as TBM), a shield excavator, and the like. Hereinafter, description will be made with reference to FIGS. FIG.
FIG. 3 is a vertical cross-sectional view showing a situation in which the shield type TBM 3 is excavating in which the TBM 1 and the shield excavator 2 are combined. TB
The cutter head 4 at the tip of M1 is rotated to excavate the face G and extend the jack 5 to form a tunnel cross section.
In these conventional tunnel excavators, when the rock mass 6 on the top or the side wall of the tunnel collapses and is mounted on the tunnel excavator, it is necessary to install a support while ensuring the safety of workers. For that purpose, it was necessary to first remove the collapsed rock mass 6 and install a shoring. The work of removing the collapsed rock mass 6 is a very dangerous work in itself, and the excavation work has to be interrupted during that time, and the work efficiency is greatly reduced because a considerable part of the work is manual work. become.

【0003】このような危険をさけるため、崩落した岩
塊6を取り除かずに支保工を設置する方法として、ライ
ナー(又はセグメント)を設置する方法がある。図5は
前記シールド型TBM3を使用し、掘進した後部にライ
ナー(又はセグメント)7を構築している状況を示す縦
断面図である。前記により切羽Gを掘削した後、シール
ド2後部の内側でライナー(又はセグメント)7を組み
立て、シールドジャッキ5を伸長させると同時に推力ジ
ャッキ9を縮めてTBM本体1を前進させる。ライナー
(又はセグメント)7とトンネル壁との間は、後で豆砂
利やモルタルなどの裏込め材8で充填する。この方法に
よれば、岩塊6はトンネル断面内に崩落する危険はな
く、安全に作業を行うことができる。しかし、トンネル
の天端や側壁部の岩塊6が大規模に崩落する場合はライ
ナー(又はセグメント)7の構築が必要となるが、中小
規模の崩落に対しては、上載岩塊の荷重に比べて支保耐
力が過剰に大きくなり、非経済的であるばかりでなく、
作業が大掛かりとなり、工期、工費の点で問題がある。
In order to avoid such a danger, there is a method of installing a liner (or a segment) as a method of installing a support without removing the collapsed rock mass 6. FIG. 5 is a longitudinal sectional view showing a situation in which a liner (or a segment) 7 is being constructed at the rear of the excavated area using the shield type TBM 3. After excavating the face G as described above, the liner (or segment) 7 is assembled inside the rear part of the shield 2, the shield jack 5 is extended, and at the same time, the thrust jack 9 is contracted and the TBM body 1 is advanced. The space between the liner (or segment) 7 and the tunnel wall is later filled with a backfill material 8 such as pea gravel or mortar. According to this method, there is no danger of the rock mass 6 falling into the tunnel cross section, and the work can be performed safely. However, if the rock mass 6 at the top or side wall of the tunnel collapses on a large scale, it is necessary to construct a liner (or segment) 7. Not only is the support capacity excessively large and uneconomical,
The work becomes large and there is a problem in terms of construction period and construction cost.

【0004】[0004]

【発明が解決しようとする課題】本発明は、上記従来の
問題点を解決するためになされたもので、簡単な方法に
より、作業性のよい、安価な連続供給支保によるトンネ
ル掘削工法を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned conventional problems, and provides a tunnel excavation method with good workability and inexpensive continuous supply by a simple method. The purpose is to:

【0005】[0005]

【課題を解決するための手段】本発明は、トンネルを掘
進し、掘進した後方に支保工を設置するための方法であ
って、トンネル掘削機内部に支保材を収納し、トンネル
掘削機の掘進に伴い、支保材が連続的に掘進した後方に
供給されていくことを特徴とする、連続供給支保による
トンネル掘削工法であり、また、支保材は、ロール状又
は折り畳み状にして支保材収納箱に収納し、トンネル掘
削機の上半断面部分に設けた供給口から連続的に供給さ
れていくことを特徴とする、連続供給支保によるトンネ
ル掘削工法であり、さらにまた、連続的に供給される支
保材は、トンネル頂部と、トンネル両側壁部とに分割し
て供給されていくことを特徴とする、連続供給支保によ
るトンネル掘削工法である。
SUMMARY OF THE INVENTION The present invention relates to a method for excavating a tunnel and installing a shoring behind the excavation. With this, the support material is supplied continuously to the rear of the excavation, and is a tunnel excavation method by continuous supply support. In addition, the support material is formed in a roll shape or a folded shape, and the support material storage box is provided. The tunnel excavation method by continuous supply support, characterized in that it is continuously supplied from a supply port provided in the upper half section of the tunnel excavator, and is further supplied continuously. The support material is a tunnel excavation method using continuous supply support, characterized in that the support material is divided and supplied to the top of the tunnel and both side walls of the tunnel.

【0006】[0006]

【発明の実施の形態】以下図面を参照しながら本発明の
実施形態について説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0007】[0007]

【全体構成】図1は本発明による連続供給支保によるト
ンネル掘削工法の縦側断面図を示し、図2は支保材を設
置した部分の平面図を示す。本発明で使用するトンネル
掘削機は、オープンタイプのTBM、シールド掘削機等
いずれでもよいが、前述のシールド型TBMを使用した
場合について説明する。 掘削機 掘進方向の先端にカッターヘッド4を備えたTBM1
と、TBM1全体をスキンプレート9で覆ったシールド
2を合体させた掘削機である。 支保材 TBM1内部には、支保材収納箱10内にロール状に丸
めて、又は、折り畳み状にして収納された支保材11が
設置されている。スキンプレート9の頂部及び両側壁部
には、供給口12が設けられ支保材11を送り出す構造
となっている。支保材11の素材は金網製、布製等現場
の地質条件および工事規模の大小によって選択すればよ
い。 削孔機 TBM1の後端部に削孔機13を設置し、ロックボルト
打設のための削孔装置としている。
FIG. 1 is a longitudinal sectional view of a tunnel excavation method using continuous supply support according to the present invention, and FIG. 2 is a plan view of a portion where a support material is installed. The tunnel excavator used in the present invention may be an open type TBM, a shield excavator, or the like, but the case where the above-mentioned shield type TBM is used will be described. Excavator TBM1 equipped with cutter head 4 at the tip in the excavation direction
And a shield 2 in which the entire TBM 1 is covered with a skin plate 9. Supporting material Inside the TBM 1, a supporting material 11 that is rolled or folded and stored in a supporting material storage box 10 is installed. Supply ports 12 are provided at the top and both side walls of the skin plate 9, and the support material 11 is sent out. The material of the support material 11 may be selected according to the geological conditions of the site, such as wire mesh or cloth, and the size of the construction. Drilling machine A drilling machine 13 is installed at the rear end of the TBM 1 to serve as a drilling device for driving rock bolts.

【0008】[0008]

【作用】図1〜図3を参照して連続供給支保によるトン
ネル掘削工法を説明する。
The tunnel excavation method using continuous supply support will be described with reference to FIGS.

【0009】<イ>支保材の引き出し 図1において、フロントグリッパ16を張って、推力ジ
ャッキ7を縮めることによりシールド型TBM3後部が
切羽Gに向かって引き付けられはじめた時、支保材収納
箱10から支保材11が供給口12から引き出され、シ
ールド型TBM3の後端部の岩盤に当てがわれる。この
時、大型のシールド型TBM3では、1枚の支保材11
だけではトンネル上半断面の大部分を覆うことができな
いため、支保材11を頂部の部分と、両側壁の部分とに
分割して引き出さなければならない。 そのため供給口
12は、図2に示すように3分割したものとする必要が
ある。 使用する支保材11が金網製の場合はロール巻
き式とし、布製の場合は折り畳み式とするなど、適宜選
択すればよい。
<A> Pulling out the support material In FIG. 1, when the rear part of the shield type TBM 3 starts to be attracted toward the face G by stretching the front gripper 16 and contracting the thrust jack 7, the support material storage box 10 The support material 11 is pulled out from the supply port 12 and applied to the rock at the rear end of the shield type TBM 3. At this time, in the case of the large shield type TBM3, one support material 11 is used.
It is not possible to cover most of the upper half section of the tunnel by itself, so the support material 11 must be divided into a top portion and side wall portions and pulled out. Therefore, the supply port 12 needs to be divided into three as shown in FIG. When the support material 11 to be used is made of a wire mesh, the support material may be a roll-wound type, and when it is made of a cloth, it may be a folding type.

【0010】<ロ>支保材の固定 シールド型TBM3の後端部に引き出された支保材11
は、その後端部に設置された削孔機13により岩盤を削
孔し、ロックボルト14を打設して岩盤に固定される。
(図1、図2) トンネル頂部に設置された支保材11と、トンネルの両
側壁部に設置された支保材11とを一体化させる。図3
は、支保材11を敷設した状態を示す横断面図である。
上記の方法の他に、鋼製支保材(H鋼)を建て込むこと
により、支保材11を岩盤に押し付ける固定方法もあ
る。
<B> Fixing of the support material The support material 11 pulled out to the rear end of the shield type TBM 3
Is rocked by a drilling machine 13 installed at the rear end thereof, and a rock bolt 14 is driven to fix the rock to the rock.
(FIGS. 1 and 2) The support members 11 installed on the top of the tunnel and the support members 11 installed on both side walls of the tunnel are integrated. FIG.
Is a cross-sectional view showing a state in which the support material 11 is laid.
In addition to the above method, there is also a fixing method in which the support material 11 is pressed against the rock by embedding a steel support material (H steel).

【0011】<ハ>支保材の敷設、固定 シールド型TBM3の掘進に伴い、端部が固定されてい
る支保材11は支保材収納箱10から自動的に引き出さ
れ、岩盤面に沿って敷設されていく。敷設された支保材
11は順次ロックボルト14の打設により岩盤面に固定
されていく。支保材11の敷設、固定により、トンネル
上半断面の岩塊6は崩落することなく、且つ、トンネル
の設計断面を確保しながら連続して掘進することができ
る。尚、この支保材11により岩塊6の崩落は防止した
ものの、ロックボルトや鋼製支保材のみではトンネル断
面の変形を押さえることができない場合には、吹き付け
コンクリートを施工することにより対処できる。
<C> Laying and fixing the support material With the excavation of the shield type TBM 3, the support material 11 whose end is fixed is automatically pulled out from the support material storage box 10 and laid along the rock surface. To go. The laid support materials 11 are sequentially fixed to the rock surface by driving the lock bolts 14. By laying and fixing the support material 11, the rock mass 6 in the upper half section of the tunnel can be continuously excavated without collapsing and securing the designed section of the tunnel. Although the rock material 6 is prevented from collapsing by the support material 11, when the deformation of the tunnel cross section cannot be suppressed only by the lock bolt or the steel support material, it can be dealt with by constructing the sprayed concrete.

【0012】[0012]

【発明の効果】本発明は以上説明したようになるから、
次のような効果を得ることができる。 <イ>支保材は地質条件、工事規模の大小により選択す
ればよいので、合理的な施工とすることができる。 <ロ>支保材の設置が掘進作業と並行して行えるので、
効率的な施工とすることができる。 <ハ>支保材の設置を掘進作業と並行して行うので、岩
塊が崩落することなく、安全に作業が行える。
Since the present invention has been described above,
The following effects can be obtained. <A> Since the supporting material may be selected according to the geological conditions and the size of the construction scale, a reasonable construction can be performed. <B> Since the support materials can be installed in parallel with the excavation work,
Efficient construction can be achieved. <C> Since the installation of the support material is performed in parallel with the excavation work, the work can be performed safely without the rock mass falling down.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明による連続供給支保によるトンネル掘削
工法の縦側断面図。
FIG. 1 is a vertical sectional view of a tunnel excavation method using continuous supply support according to the present invention.

【図2】同上平面図。FIG. 2 is a plan view of the same.

【図3】同上横断面図。FIG. 3 is a transverse sectional view of the same.

【図4】従来の掘進状況を示す縦断面図。FIG. 4 is a longitudinal sectional view showing a conventional excavation situation.

【図5】従来のその他の掘進状況を示す縦断面図。FIG. 5 is a longitudinal sectional view showing another conventional excavation situation.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】トンネルを掘進し、掘進した後方に支保工
を設置するための方法であって、 トンネル掘削機内部に支保材を収納し、 トンネル掘削機の掘進に伴い、支保材が連続的に掘進し
た後方に供給されていくことを特徴とする、 連続供給支保によるトンネル掘削工法。
A method for digging a tunnel and installing a shoring behind the digging, wherein a shoring material is stored inside the tunnel digging machine, and the shoring material is continuously provided as the tunnel digging machine excavates. A tunnel excavation method with continuous supply support, characterized by being supplied to the back of the tunnel.
【請求項2】請求項1に記載の構造物の連続供給支保に
よるトンネル掘削工法において、 支保材は、ロール状又は折り畳み状にして支保材収納箱
に収納し、 トンネル掘削機の上半断面部分に設けた供給口から連続
的に供給されていくことを特徴とする、 連続供給支保によるトンネル掘削工法。
2. The tunnel excavation method according to claim 1, wherein the support material is stored in a support material storage box in a roll shape or a folded shape, and an upper half section of the tunnel excavator. A tunnel excavation method with continuous supply support, characterized by continuous supply from a supply port provided in the facility.
【請求項3】請求項1又は請求項2のいずれかに記載の
連続供給支保によるトンネル掘削工法において、 連続的に供給される支保材は、トンネル頂部と、トンネ
ル両側壁部とに分割して供給されていくことを特徴とす
る、 連続供給支保によるトンネル掘削工法。
3. A tunnel excavation method according to claim 1 or 2, wherein the continuously supplied support material is divided into a tunnel top portion and a tunnel side wall portion. Tunnel excavation method with continuous supply support characterized by being supplied.
JP9212643A 1997-07-23 1997-07-23 Tunnel excavation method with continuous supply support Pending JPH1136788A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9212643A JPH1136788A (en) 1997-07-23 1997-07-23 Tunnel excavation method with continuous supply support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9212643A JPH1136788A (en) 1997-07-23 1997-07-23 Tunnel excavation method with continuous supply support

Publications (1)

Publication Number Publication Date
JPH1136788A true JPH1136788A (en) 1999-02-09

Family

ID=16626042

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9212643A Pending JPH1136788A (en) 1997-07-23 1997-07-23 Tunnel excavation method with continuous supply support

Country Status (1)

Country Link
JP (1) JPH1136788A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003106096A (en) * 2001-09-28 2003-04-09 Japan Highway Public Corp TBM integrated ground support for TBM
WO2005095760A1 (en) * 2004-03-26 2005-10-13 Rag Aktiengesellschaft Method and device for introducing heading supports
CN106703824A (en) * 2015-11-13 2017-05-24 马振凯 Suspension folding anchor rod drilling system
CN108386202A (en) * 2018-03-30 2018-08-10 重庆大学 City underground running tunnel list shield TBM constructions
CN111594239A (en) * 2020-06-05 2020-08-28 中国铁建重工集团股份有限公司 Automatic anchor rod construction control method of hard rock heading machine

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003106096A (en) * 2001-09-28 2003-04-09 Japan Highway Public Corp TBM integrated ground support for TBM
WO2005095760A1 (en) * 2004-03-26 2005-10-13 Rag Aktiengesellschaft Method and device for introducing heading supports
AU2004318024B2 (en) * 2004-03-26 2008-04-03 Rag Aktiengesellschaft Method and device for introducing heading supports
CN106703824A (en) * 2015-11-13 2017-05-24 马振凯 Suspension folding anchor rod drilling system
CN108386202A (en) * 2018-03-30 2018-08-10 重庆大学 City underground running tunnel list shield TBM constructions
CN111594239A (en) * 2020-06-05 2020-08-28 中国铁建重工集团股份有限公司 Automatic anchor rod construction control method of hard rock heading machine
CN111594239B (en) * 2020-06-05 2021-08-27 中国铁建重工集团股份有限公司 Automatic anchor rod construction control method of hard rock heading machine

Similar Documents

Publication Publication Date Title
KR100656194B1 (en) Open type method using tunnel method
JPH035600A (en) Construction method for shield tunnel branches and joints and temporary bulkhead construction equipment for branches and joints
JP4543130B2 (en) Tunnel widening device
JPH1136788A (en) Tunnel excavation method with continuous supply support
JP2000337080A (en) Construction method of underground joint structure
JPH06306853A (en) Construction of underground structure
JP4464248B2 (en) Shield widening method and shield machine capable of widening lining
JP2981632B2 (en) Construction method of joint of underground wall
JP3581332B2 (en) Earth retaining equipment and open-cutting method using it
JPH0442498B2 (en)
JP2540440B2 (en) Open shield method
JP2657731B2 (en) Open shield method and open shield machine
JP3302661B2 (en) Open shield machine and construction method of underground structure using it
JP2000337077A (en) Method for constructing tunnel
JPH05118189A (en) Large sectional tunnel excavating method
JP3926818B2 (en) Installation method of concrete box
JP3896003B2 (en) Connection method and structure of shaft
JPH07119866A (en) Underground pipe laying method
JP2897666B2 (en) Reaction receiving structure for starting a shield machine
JP2668109B2 (en) Construction method for underground structures
JPS6016535B2 (en) How to form retaining walls and underground walls
JPH054491B2 (en)
JP2987265B2 (en) Tunnel excavation method using belt-like reinforcement
JPH11141272A (en) Excavation method and excavator for bedrock shaft and inclined shaft in steel pipe laying construction
JPH084009A (en) Method of supporting earth retaining sheet pile, and device therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040510

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060822

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20061219