[go: up one dir, main page]

EP4004289B1 - Method and apparatus for replacing bridge constructions in track systems - Google Patents

Method and apparatus for replacing bridge constructions in track systems Download PDF

Info

Publication number
EP4004289B1
EP4004289B1 EP20736566.9A EP20736566A EP4004289B1 EP 4004289 B1 EP4004289 B1 EP 4004289B1 EP 20736566 A EP20736566 A EP 20736566A EP 4004289 B1 EP4004289 B1 EP 4004289B1
Authority
EP
European Patent Office
Prior art keywords
bridge
track
replacing
constructions
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP20736566.9A
Other languages
German (de)
French (fr)
Other versions
EP4004289A1 (en
EP4004289C0 (en
Inventor
Uwe Langer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Riga Mainz GmbH and Co KG
Original Assignee
Riga Mainz GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Riga Mainz GmbH and Co KG filed Critical Riga Mainz GmbH and Co KG
Publication of EP4004289A1 publication Critical patent/EP4004289A1/en
Application granted granted Critical
Publication of EP4004289B1 publication Critical patent/EP4004289B1/en
Publication of EP4004289C0 publication Critical patent/EP4004289C0/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Definitions

  • An exemplary task is to carry out the work in sections of 2 bridges per closure break with the shortest possible construction time, whereby there are old bridge structures that need to be replaced, each with a steel superstructure of approx. 70 t, which are to be replaced by new bridges, each with approx. 320 t Reinforced concrete are made.
  • the conventional procedure with a large crane involves dismantling the overhead lines on all 8 tracks step by step and then reassembling them again in order to be able to work with the crane technology from above. This already causes considerable preparation costs in order to even be able to start the work.
  • a possible crane that could be used here, for example, has a dead weight of approx. 800 t, plus the dead weight of the new bridge structure that has to be lifted.
  • the total weight of the crane including the bridge would then be approx. 1100t, which poses further problems with regard to the subsoil in the area of the crane parking space.
  • a target construction time for execution is, for example, around 34 hours per structure, during which time the crane would have to be brought into position and the lifting carried out.
  • the publication KR 101 234 090 B1 finally shows a girder replacement method for a railway bridge, wherein lifting and placing a new girder by a lifting device, transporting the new girder to the railway bridge by the operation of a motor vehicle and installing the new girder on piers from which the previous girder is removed is disclosed .
  • a rail-bound vehicle is disclosed as a means of transport for the new bridge element.
  • the aim is to be able to carry out the replacement without affecting the arrangement of overhead lines.
  • inventive method is carried out with a device according to claim 6, the following claims 7 to 10 having as their subject advantageous developments of this device.
  • the structural measure is carried out by a boiler bridge or elevated bridge, which is used in combination with an SPMT (Self-Propelled Modular Trailer).
  • SPMT Self-Propelled Modular Trailer
  • the SPMT is able to carry out the maneuvers longitudinal travel, transverse travel, diagonal travel or circular travel, which can be accessed fully electronically via the remote control.
  • a special lifting system comprising a steel structure to accommodate the lifting system in the boiler or high bridge.
  • the innovative development includes a parallel rope combination with suspension heads on both sides with an integrated rope pulley for lifting the load, in an advantageous version with 5 grooves for a load holding of 150 t plus the resulting force from the lifting bolts.
  • Another element relevant to the installation of the bridge structure is a hydraulic side displacement option for positioning the bridge in its final installation position, whereby the required longitudinal displacement can be carried out via the hydrostatic drive of the SPMT.
  • the suspension on the bridge has suspension heads on the bridge structure itself, which are each coordinated in conjunction with the static requirements and possibilities of the structure.
  • the high girder bridge and the lifting system can be positioned in such a way that they can be adjusted longitudinally and transversely so that the bridge structure can be lifted directly above the abutments on the structure. This has the advantage that no different bending moment occurs in the structure compared to the state in the end position.
  • the number of SPMT axle lines can be selected in such a way that a comparison calculation can be made compared to the loading scheme of, for example, the Irish Bahn for locomotives or freight trains can.
  • auxiliary bridge (HB) will be temporarily used to drive over the open gap after the old bridge has been expanded. On single-track routes, this can be done by driving in the HB with SPMT or lifting it in with a mobile crane. If this happens with an SPMT, it can remain as support under the HB. This means that the railway car can drive over the auxiliary bridge and the new bridge structure Lower it in exactly the right position, as already described in more detail.
  • FIG. 1 The device 1 according to the invention for removing an old bridge structure and installing a new bridge structure 3 is shown in plan view. This is the device 1 according to the invention, which is moved parallel to the bridge structure 3 before it is picked up.
  • the arrows 19 show that, due to the SPMTs 8 serving as chassis, a transverse journey 6 to the track system 7 is also possible in order to be able to pick up the bridge structure parked parallel to the tracks.
  • the device for height adjustment 10 of the high bridge 11 is raised exactly so that a safe distance from the overhead line 9 is guaranteed.
  • the old bridge structure has already been removed from the track system 7, the device 1 with the new bridge structure 3 suspended on the high bridge 11 has been moved into position, so that the new bridge structure 3 can be lowered to any height using the lifting technology according to the invention, like this can be seen through the lower position of the bridge structure 3.
  • This means that the new bridge can be placed precisely on bridge supports that may have been created for the new bridge structure after the old bridge was removed.
  • the Figure 3 now shows the lifting device 2 according to the invention only in the retracted state.
  • This is to be understood as meaning that the suspension head 15 is brought up to the strand jack 14, whereby the suspension head 15 is fixed
  • Parallel cables 17 are brought to the high bridge 11 via a cable pulley 13. This is therefore the position in which, for example, the new bridge structure 3 is lifted directly onto the high bridge.
  • an alternative hydraulic component could also be used, which, running parallel to the high bridge 11, causes the deflected parallel cable to be shortened by moving the suspension head 15.
  • FIG 5 the section AA through the high bridge 11 according to the invention with lifting devices 2 arranged thereon can be seen.
  • the high bridge 11 has lateral supports 21, between which a further support element 22 runs, on which the lifting devices 2 are arranged.
  • the plane of the overhead lines 9 is also shown, which runs above the pulleys 13 of the parallel cables 17. In this respect, there is no obstruction caused by the overhead line 9.
  • the bridge structure 3, which is suspended at two points on the suspension heads 15, can be seen, as well as that SPMT chassis 8, which moves the device on an excavated track 7.
  • a double piston cylinder 12 can be seen, via which a hydraulic lateral displacement of the bridge structure 3 is made possible when it fits into the remaining gap in the track system 7.
  • the longitudinal displacement is caused by the SPMT itself, the transverse displacement via the mentioned double-piston cylinder 12. In this way, perfect placement on the abutments is ensured.
  • FIGS. 6 and 7 now again show side views of the device 1, which is not part of the present invention, the difference being that the running gear is not designed as SPMTs, but the high bridge 11 is arranged on two railway cars, for example on beak-type carriages.
  • the background to this alternative representation is that in the case of a single track system 7 or a bridge structure 3 that has to be transported to the installation site over a large distance, or even a track system 7 that cannot be prepared for use with SPMTs, the Recourse to track-bound running gear is required, which is not part of the present invention, but should still be considered.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Description

Der Austausch von parallel zueinander angeordneten Brückenbauwerken in Gleisanlagen, die alle elektrifiziert sind, verursacht einen großen logistischen und technischen Aufwand sowie lange Ausfallzeiten an den betroffenen Gleisanlagen, insbesondere wenn hierbei nur max. 2 der parallel verlaufenden Gleise gleichzeitig gesperrt werden sollen. Dies wird aber angestrebt, um die Ausfallzeiten an der Gleisanlage insgesamt zu reduzieren und daher nur schrittweise vorzugehen. Daher entstand die Überlegung einer Entwicklung alternativer Lösungen zum Ein- und Ausbringen von Brückenbauwerken in elektrifizierten Gleisanlagen.The replacement of parallel bridge structures in track systems, which are all electrified, causes a great deal of logistical and technical effort as well as long downtimes on the affected track systems, especially if only a maximum of 2 of the parallel tracks are to be closed at the same time. However, this is aimed at reducing downtime on the track system overall and therefore only proceeding gradually. This led to the idea of developing alternative solutions for inserting and removing bridge structures in electrified track systems.

Bei mehreren parallel verlaufenden Brückenbauwerken in Gleisanlagen ist die herkömmliche Vorgehensweise, die Brückenbauwerke mit einem Großkran auszutauschen räumlich nicht möglich, wenn hierbei nur max. 2 Gleise gesperrt werden können. Eine beispielhafte Aufgabenstellung ist hierbei die Ausführung der Arbeiten in Abschnitten von je 2 Brücken je Sperrpause mit möglichst kurzer Bauzeit, wobei alte auszutauschende Brückenbauwerke vorliegen mit je ca. 70 t Stahlüberbau, die durch neue Brücken ersetzt werden sollen, die mit je ca. 320 t Stahlbeton gefertigt sind.If there are several parallel bridge structures in railway tracks, the conventional approach of replacing the bridge structures with a large crane is not spatially possible if only a maximum of 2 tracks can be closed. An exemplary task is to carry out the work in sections of 2 bridges per closure break with the shortest possible construction time, whereby there are old bridge structures that need to be replaced, each with a steel superstructure of approx. 70 t, which are to be replaced by new bridges, each with approx. 320 t Reinforced concrete are made.

Die herkömmliche Vorgehensweise mit einem Großkran sieht hierbei vor, die Oberleitungen aller 8 Gleise Zug um Zug zu demontieren und dann wieder zu remontieren, um mit der Krantechnik von oben arbeiten zu können. Dies verursacht bereits erhebliche Vorbereitungskosten, um überhaupt mit den Arbeiten beginnen zu können.The conventional procedure with a large crane involves dismantling the overhead lines on all 8 tracks step by step and then reassembling them again in order to be able to work with the crane technology from above. This already causes considerable preparation costs in order to even be able to start the work.

Ein möglicher Kran der hier zum Einsatz kommen könnte bringt beispielsweise ein Eigengewicht von ca. 800 t mit sich, zzgl. dem Eigengewicht des neuen Brückenbauwerks welches gehoben werden muss. Das Gesamtgewicht des Kranes inkl. der Brücke wäre so dann ca. 1100t, was weitere Probleme in Bezug auf den Untergrund im Bereich des Kranstellplatzes aufwirft.A possible crane that could be used here, for example, has a dead weight of approx. 800 t, plus the dead weight of the new bridge structure that has to be lifted. The total weight of the crane including the bridge would then be approx. 1100t, which poses further problems with regard to the subsoil in the area of the crane parking space.

Eine angestrebte Bauzeit bei der Ausführung liegt beispielsweise bei etwa 34 Stunden je Bauwerk, wobei in dieser Zeit der Kran in Stellung gebracht und der Hub ausgeführt werden müsste.A target construction time for execution is, for example, around 34 hours per structure, during which time the crane would have to be brought into position and the lifting carried out.

Massive Eingriffe in die Infrastruktur der Gleisanlagen, ggf. auch Setzungen im Kranstellplatzbereich, Sicherungsmaßnahmen und Kampfmittelsondierungen im Untergrund sind weitere, schwer einschätzbare Aufwendungen, die nur sehr schwierig im Vorfeld zu bewerten sind, was das Einhalten der angestrebten Bauzeit bei der Ausführung in Frage stellt. Die Entwicklung alternativer Lösungen zum Ein- und Ausbringen von Brückenbauwerken in elektrifizierten Gleisanlagen würde somit ggfs. erhebliche Einsparpotenziale mit sich bringen und idealerweise eine verlässliche Kalkulation einer verkürzten Bauzeit erlauben.Massive interventions in the infrastructure of the track systems, possibly also subsidence in the crane parking area, security measures and explosive ordnance soundings in the subsoil are further expenses that are difficult to estimate and are very difficult to evaluate in advance, which calls into question whether the desired construction time will be adhered to during execution. The development of alternative solutions for inserting and removing bridge structures in electrified track systems would potentially bring with it considerable savings potential and ideally allow a reliable calculation of a shortened construction time.

Der Stand der Technik bietet keinen Ansatz zur Lösung dieser Problematik. Aus der Veröffentlichung DE 10 2006 049 408 B4 ist ein Verfahren und eine Vorrichtung zum Austausch eines defekten oder verschlissenen Schienenstückes bekannt, bei dem ein schienengebundenes Fahrzeug über die auszutauschende Schienenstelle verfahren wird, in einem weiteren Schritt das abgetrennte defekte Schienenstück mittels des Wagens und einer unterseitig angeordneten Hebevorrichtung aus dem Schienenstrang herausgehoben wird, dann ein passgerecht abgelenktes Schienenstück als Ersatz in die entstandene Lücke eingesetzt und abschließend mit seinen Enden im Schienenstrang befestigt wird, wobei die verbliebenen Schienenenden, zwischen denen das neue Schienenstück eingesetzt wird mit Fixiermitteln relativ zu einander befestigt werden.The state of the art does not offer any approach to solving this problem. From the publication DE 10 2006 049 408 B4 a method and a device for replacing a defective or worn rail piece is known, in which a rail-bound vehicle is moved over the rail location to be replaced, in a further step the separated defective rail piece is lifted out of the rail track by means of the carriage and a lifting device arranged on the underside, then a correctly deflected rail piece is inserted as a replacement into the resulting gap and finally fastened with its ends in the rail track, the remaining rail ends, between which the new rail piece is inserted, being fastened relative to one another with fixing means.

Es handelt sich hierbei um ein Verfahren, dass ausschließlich auf einzelne Schienenelemente beschränkt anwendbar ist und hierbei keine Möglichkeit eröffnet, ein größeres bauliches Element wie einen Brückenkörper aus den Gleisanlagen zu entfernen und zu ersetzen.This is a process that is only applicable to individual rail elements and does not offer the possibility of removing and replacing a larger structural element such as a bridge body from the track system.

Ein ähnlicher Lösungsansatz befindet sich ebenfalls in der Druckschrift AT 501 272 A4 , die ebenfalls dem Entfernen schadhafter Schienenstücke in Gleisanlagen dient.A similar solution approach is also in the publication AT 501 272 A4 , which is also used to remove damaged pieces of rail in track systems.

Aus der Offenlegungsschrift DE 100 04 194 A1 ist ein Verfahren zur Fertigung einer festen Schienenfahrbahn auf einer Brücke offenbart. Hier werden Schritte offenbart, wie das Betonieren einer derartigen Brücke speziell für die Nutzung als Schienenfahrbahn vorteilhaft gestaltet werden kann. Anregungen zum Austausch einer Brücke in Gleisanlagen bietet diese Veröffentlichung allerdings nicht.From the Publication DE 100 04 194 A1 a method for producing a solid rail track on a bridge is disclosed. Steps are disclosed here as to how the concreting of such a bridge can be advantageously designed specifically for use as a rail track. However, this publication does not offer any suggestions for replacing a bridge in railway tracks.

Die Veröffentlichung KR 101 234 090 B1 schließlich zeigt ein Trägeraustauschverfahren für eine Eisenbahnbrücke, wobei ein Anheben und Platzieren eines neuen Trägers durch eine Hebevorrichtung, das Transportieren des neuen Trägers zur Eisenbahnbrücke durch den Betrieb eines Kraftfahrwagens und das Installieren des neuen Trägers auf Pfeilern offenbart ist, von denen der bisherige Träger entfernt wird. Hierfür wird allerdings ein schienengebundenes Fahrzeug als Transportmittel für das neue Brückenelement offenbart.The publication KR 101 234 090 B1 finally shows a girder replacement method for a railway bridge, wherein lifting and placing a new girder by a lifting device, transporting the new girder to the railway bridge by the operation of a motor vehicle and installing the new girder on piers from which the previous girder is removed is disclosed . For this purpose, however, a rail-bound vehicle is disclosed as a means of transport for the new bridge element.

Bei den Arbeiten an mehreren Brückenbauwerken in parallel verlaufenden Gleisanlagen ergeben sich sehr spezifische Problemstellungen, die durch die zuvor beschriebenen technischen Lösungen zum Austausch einzelner Schienenelemente nicht gelöst werden können. So wird angestrebt, lediglich zwei der parallelen Gleise gleichzeitig von der Baumaßnahme zu erfassen. Geht man beispielsweise von Gleisanlagen aus, bei denen acht parallele Gleise ein auszutauschendes Brückenbauwerk aufweisen, so ist es nach dem bisherigen Stand der Technik nur mit einem vergleichsweise großen technischen und logistischen Aufwand möglich, diese Brückenbauwerke nacheinander bei paarweiser Außerbetriebnahme der Gleise auszutauschen.When working on several bridge structures in parallel track systems, very specific problems arise that cannot be solved by the previously described technical solutions for replacing individual rail elements. The aim is to only include two of the parallel tracks in the construction work at the same time. For example, if one assumes track systems in which eight parallel tracks have a bridge structure that needs to be replaced, the current state of the art only requires a comparatively large technical and logistical one Effort possible to replace these bridge structures one after the other when the tracks are taken out of service in pairs.

Zudem wäre auch die Frage der Oberleitungen problematisch, da ein Betrieb der benachbarten Gleise mit elektrifizierten Oberleitungen risikobehaftet ist bei parallelen Arbeiten an Gleisen, deren Oberleitungen für den Bauabschnitt entfernt worden sind.In addition, the question of overhead lines would also be problematic, as operating the neighboring tracks with electrified overhead lines is risky in the case of parallel work on tracks whose overhead lines have been removed for the construction phase.

Es ist daher die Aufgabe der vorliegenden Erfindung, ein neuartiges Verfahren sowie eine hierfür erforderliche Vorrichtung zu schaffen, um deutlich effizienter Brückenbauwerke in Gleisanlagen austauschen zu können. Hierbei wird angestrebt, den Austausch ohne Beeinträchtigung der Anordnung von Oberleitungen durchführen zu können.It is therefore the object of the present invention to create a novel method and a device required for this in order to be able to replace bridge structures in track systems much more efficiently. The aim is to be able to carry out the replacement without affecting the arrangement of overhead lines.

Erreicht wird dies nach einem Verfahren nach Anspruch 1, die Unteransprüche 2 bis 5 haben vorteilhafte Weiterbildungen des Verfahrens zum Gegenstand.This is achieved using a method according to claim 1, subclaims 2 to 5 relate to advantageous developments of the method.

Des Weiteren wird das erfinderische Verfahren durchgeführt mit einer Vorrichtung nach Anspruch 6, wobei die folgenden Ansprüche 7 bis 10 vorteilhafte Ausbildungen dieser Vorrichtung zum Gegenstand haben.Furthermore, the inventive method is carried out with a device according to claim 6, the following claims 7 to 10 having as their subject advantageous developments of this device.

Konstruktiv wird die bauliche Maßnahme durch eine Kessel- oder Hochbrücke geleistet, die in Kombination mit einem SPMT (Self-Propelled-Modular-Trailer) zum Einsatz kommt. Der SPMT ist in der Lage die Manöver Längsfahrt, Querfahrt, Diagonalfahrt oder Kreisfahrt durchzuführen, die vollelektronisch über die Fernsteuerung abgerufen werden können.Structurally, the structural measure is carried out by a boiler bridge or elevated bridge, which is used in combination with an SPMT (Self-Propelled Modular Trailer). The SPMT is able to carry out the maneuvers longitudinal travel, transverse travel, diagonal travel or circular travel, which can be accessed fully electronically via the remote control.

Zu dieser Kombination kommt die Entwicklung einer speziellen Hebeanlage umfassend eine Stahlkonstruktion zur Aufnahme der Hebeanlage in der Kessel- bzw. Hochbrücke. Die neuartige Entwicklung umfasst eine Parallelseilkombination mit beidseitigen Aufhängeköpfen mit einer integrierten Seilrolle für die Lastaufnahme, in einer vorteilhaften Ausführung 5-rillig für eine Lastaufnahme von 150 t zzgl. der resultierenden Kraft aus den Hublitzen.In addition to this combination, there is the development of a special lifting system comprising a steel structure to accommodate the lifting system in the boiler or high bridge. The innovative development includes a parallel rope combination with suspension heads on both sides with an integrated rope pulley for lifting the load, in an advantageous version with 5 grooves for a load holding of 150 t plus the resulting force from the lifting bolts.

Ein weiteres beim Einbau des Brückenbauwerkes relevantes Element ist eine hydraulische Seitenverschubmöglichkeit zur Positionierung der Brücke in deren Einbau-Endlage, wobei der erforderliche Längsverschub über den hydrostatischen Antrieb der SPMT erfolgen kann.Another element relevant to the installation of the bridge structure is a hydraulic side displacement option for positioning the bridge in its final installation position, whereby the required longitudinal displacement can be carried out via the hydrostatic drive of the SPMT.

Die Aufhängung an der Brücke weist Aufhängeköpfe am Brückenbauwerk selbst auf, die jeweils in Verbindung mit den statischen Erfordernissen und Möglichkeiten des Bauwerks abgestimmt werden. Grundsätzlich sind die Hochträgerbrücke und die Hebeanlage so längs- und quer verstellbar platzierbar, dass das Brückenbauwerk direkt über den Widerlagern am Bauwerk gehoben werden kann. Dies hat den Vorteil, dass kein anderes Biegemoment im Bauwerk gegenüber dem Zustand in der Endlage entsteht.The suspension on the bridge has suspension heads on the bridge structure itself, which are each coordinated in conjunction with the static requirements and possibilities of the structure. In principle, the high girder bridge and the lifting system can be positioned in such a way that they can be adjusted longitudinally and transversely so that the bridge structure can be lifted directly above the abutments on the structure. This has the advantage that no different bending moment occurs in the structure compared to the state in the end position.

Mit Hilfe dieser neuen Transport- und Hebetechnik ist es möglich, eine alte Brücke herauszunehmen und diese gegen eine neue Brücke zu ersetzen ohne dass eine weitere Technik wie z. B. Verschub- oder Hebemittel erforderlich werden.With the help of this new transport and lifting technology, it is possible to remove an old bridge and replace it with a new bridge without the need for additional technology such as. B. shifting or lifting equipment may be required.

Im Folgenden wird die Vorgehensweise und deren Voraussetzungen näher betrachtet, wobei die nachfolgende Beschreibung sich auf ein beispielhaftes Projekt von 8 parallelen Gleisanlagen mit Brückenbauwerken bezieht.The procedure and its requirements will be examined in more detail below, with the following description referring to an exemplary project of 8 parallel track systems with bridge structures.

Aufgabenstellung ist, im Zuge eines 60-tägigen Zeitplans insgesamt 8 Brücken auszutauschen.

  1. (1) Alle neuen Brückenbauwerke werden vor Ort in Einbaunähe gefertigt.
  2. (2) Das Transport- und Hebegerät wird in Einzelteilen auf Standard-LKW's an der Baustelle angeliefert und einsatzbereit vormontiert.
  3. (3) Eine Baufirma stellt eine befahrbare Fläche zwischen den Gleisen und den einzelnen Gleissträngen her.
  4. (4) Die Oberleitungen müssen nicht entfernt oder verzogen werden, aber die Fahrdrähte werden zum Zeitpunkt der Durchführung spannungsfrei geschaltet und geerdet.
  5. (5) Das Transport- und Hebegerät fährt über die auszutauschende Brücke, nimmt diese mit der beschriebenen Hebetechnik auf, setzt durch Querfahrt auf das Nachbargleis um und kann somit die alte Brücke herausfahren.
  6. (6) Die alte Brücke wird abgelegt.
  7. (7) Das Transport- und Hebegerät fährt seitlich über das neue Bauwerk, nimmt dieses ebenfalls mit der beschriebenen Hebetechnik auf und fährt über das Nachbargleis in Linie der Einbauposition (Querachse der neuen Brücke).
  8. (8) Durch die Quer- und Längsfahrt wird Lage der neuen Brücke erreicht.
  9. (9) Die Brücke wird über die neu entwickelte Hebetechnik auf eine beliebige Höhe abgesenkt und auf den Widerlagern platziert. Hierbei kann auf Bedarf der Seitenschub erfolgen, der über einen Doppelkolbenzylinder vorgesehen ist.
  10. (10) Nach dem Aushängen der Brücke ist diese fertig für den weiteren Gleisbau.
The task is to replace a total of 8 bridges over a 60-day schedule.
  1. (1) All new bridge structures are manufactured on site close to installation.
  2. (2) The transport and lifting device is delivered to the construction site in individual parts on standard trucks and pre-assembled ready for use.
  3. (3) A construction company creates a passable area between the tracks and the individual track strands.
  4. (4) The overhead lines do not need to be removed or distorted, but the contact wires are de-energized and grounded at the time of implementation.
  5. (5) The transport and lifting device moves over the bridge to be replaced, picks it up using the lifting technology described, moves across to the neighboring track and can thus drive out the old bridge.
  6. (6) The old bridge is discarded.
  7. (7) The transport and lifting device moves laterally over the new structure, picks it up using the lifting technology described and moves over the neighboring track in line with the installation position (transverse axis of the new bridge).
  8. (8) The position of the new bridge is reached through the transverse and longitudinal travel.
  9. (9) The bridge is lowered to any height using the newly developed lifting technology and placed on the abutments. If necessary, the side shift can be carried out, which is provided via a double-piston cylinder.
  10. (10) After the bridge has been unhooked, it is ready for further track construction.

Was die Belastungen der Gleise und alten Brücken anbetrifft ist es beim erfindungsgemäßen Verfahren sowie der hierfür verwendeten Vorrichtung vorteilhaft, dass die Anzahl der SPMT-Achslinien so gewählt werden kann, dass eine Vergleichsrechnung gegenüber dem Belastungsschema beispielsweise der Deutschen Bahn für Loks bzw. Güterzüge erstellt werden kann. Grundsätzlich ist es hierbei möglich, die SPMT-Achslinien je nach Bedarf in einem Baukastensystem (4-Achser und 6-Achser Fahrwerke) zu erweitern bzw. zu verkürzen. Auf diese Weise ist die Anpassung an die jeweiligen Gegebenheiten und die Belastbarkeit einer Gleisanlage sichergestellt.As far as the loads on the tracks and old bridges are concerned, it is advantageous in the method according to the invention and the device used for this purpose that the number of SPMT axle lines can be selected in such a way that a comparison calculation can be made compared to the loading scheme of, for example, the Deutsche Bahn for locomotives or freight trains can. In principle, it is possible to expand or shorten the SPMT axle lines as required in a modular system (4-axle and 6-axle chassis). On This ensures adaptation to the respective circumstances and the resilience of a track system.

Eine Alternative, die ein Lösung darstellt, die nicht Teil der vorliegenden Erfindung ist, ist der Einsatz eines Bahnwagens, beispielsweise eines Tragschnabelwagens TSW-348, anstelle des SPMT für die technischen Bedingungen, dass

  • nur ein Gleis zur Verfügung steht,
  • oder die einzubauenden Brückenbauwerke ggf. über eine größere Distanz herangefahren werden müssen,
  • oder die Gleise aus baulichen Bedingungen nicht ausgebohlt bzw. nicht befahrbar hergerichtet werden und so ein Befahren mit einem gummibereiften Fahrzeug nicht möglich ist.
An alternative, which represents a solution that is not part of the present invention, is the use of a rail car, for example a TSW-348 beak car, instead of the SPMT for the technical conditions that
  • only one track is available,
  • or the bridge structures to be installed may have to be approached over a greater distance,
  • or the tracks are not dug out or prepared to be passable due to structural conditions and so driving on them with a rubber-tired vehicle is not possible.

Die Abweichungen zur zuvor beschriebenen Vorgehensweise besteht dann darin, dass die neuen Brückenbauwerke seitlich über eine Verschubtechnik unter die Hochbrücke geschoben werden, um diese aufnehmen zu können, da der Gleiswagen das Gleis ja nicht verlassen kann und somit keine Querfahrt möglich ist.The deviation from the previously described procedure is that the new bridge structures are pushed laterally under the high bridge using a sliding technology in order to be able to accommodate them, since the track carriage cannot leave the track and therefore no crossing is possible.

Analog hierzu erfolgt das Absetzen der aus der Gleisanlage gelösten zu ersetzenden alten Brücke in umgekehrter Reihenfolge.Similarly, the old bridge that has been removed from the track system and is to be replaced is removed in the reverse order.

Die Problematik besteht dann darin, dass nach dem Entfernen der aus der Gleisanlage gelösten zu ersetzenden alten Brücke eine Lücke in der Gleisanlage verbleibt, die die Positionierung des Bahnwagens mit aufgenommenem neuen Brückenbauwerk verhindert. Zum Überfahren der offenen Lücke nach dem Ausbau der alten Brücke wird temporär eine Hilfsbrücke (HB) eingesetzt. Dies kann bei eingleisigen Strecken durch Einfahren der HB mit SPMT oder dem Einheben durch einen Mobilkran durchgeführt werden. Geschieht das mit einem SPMT, so kann dieser als Unterstützung unter der HB verbleiben. So kann der Bahnwagen über die Hilfsbrücke fahren und das neue Brückenbauwerk genau positioniert absenken, wie dies bereits näher beschrieben ist.The problem then lies in the fact that after removing the old bridge that is to be replaced from the track system, a gap remains in the track system, which prevents the positioning of the railway car with the new bridge structure added. An auxiliary bridge (HB) will be temporarily used to drive over the open gap after the old bridge has been expanded. On single-track routes, this can be done by driving in the HB with SPMT or lifting it in with a mobile crane. If this happens with an SPMT, it can remain as support under the HB. This means that the railway car can drive over the auxiliary bridge and the new bridge structure Lower it in exactly the right position, as already described in more detail.

Im Folgenden wird das erfindungsgemäße Verfahren wie auch die Vorrichtung zu dessen Durchführung anhand von Zeichnungen näher beschrieben. Es zeigen

Fig. 1
eine Draufsicht auf die verwendete Hochbrücke (11) auf einer Gleisanlage (7) mit anzuhebendem Brückenbauwerk (3);
Fig. 2
eine seitliche Ansicht der erfindungsgemäßen Hochbrücke (11) gelagert auf SPMTs (8) mit aufgehängtem Brückenbauwerk (3);
Fig. 3
eine Kombination von Ansichten auf die erfindungsgemäße Hubvorrichtung in eingefahrenem Zustand zum Anheben einer Last;
Fig. 4
die erfindungsgemäße Hubvorrichtung ausgefahren zum Absenken einer Last;
Fig. 5
den Schnitt AA durch die Hochbrücke (11) mit aufgehängtem Brückenbauwerk (3) und darin angeordneter Hubvorrichtung;
Fig. 6
eine seitliche Ansicht einer alternativen Vorrichtung, die nicht auf SPMTs sondern auf gleisgebundenen Bahnwagen (18) gelagert ist und verfahren wird und somit ein Ausführungsbeispiel darstellt, das nicht Teil der vorliegenden Erfindung ist, sowie
Fig. 7
ebenfalls die nicht einen Teil der vorliegenden Erfindung bildende Vorrichtung nach Figur 6 beim Einbauvorgang eines neuen Brückenbauwerks (3).
The method according to the invention as well as the device for carrying it out are described in more detail below with reference to drawings. Show it
Fig. 1
a top view of the high bridge (11) used on a track system (7) with a bridge structure (3) to be lifted;
Fig. 2
a side view of the high bridge (11) according to the invention mounted on SPMTs (8) with a suspended bridge structure (3);
Fig. 3
a combination of views of the lifting device according to the invention in the retracted state for lifting a load;
Fig. 4
the lifting device according to the invention extended to lower a load;
Fig. 5
the section AA through the high bridge (11) with the suspended bridge structure (3) and the lifting device arranged therein;
Fig. 6
a side view of an alternative device, which is not mounted and moved on SPMTs but on track-bound railway carriages (18) and thus represents an exemplary embodiment that is not part of the present invention, and
Fig. 7
also reproduces the device which does not form part of the present invention Figure 6 during the installation process of a new bridge structure (3).

In Figur 1 ist in der Draufsicht die erfindungsgemä-ße Vorrichtung 1 zur Entnahme eines alten Brückenbauwerks sowie zum Einbau eines neuen Brückenbauwerks 3 dargestellt. Hierbei handelt es sich um die erfindungsgemäße Vorrichtung 1, die hierbei vor der Aufnahme des Brückenbauwerks 3 parallel zu diesem verfahren wird. Die Pfeile 19 zeigen hierbei, dass aufgrund der als Fahrwerk dienenden SPMTs 8 auch eine Querfahrt 6 zur Gleisanlage 7 möglich ist, um das parallel zu den Gleisen abgestellte Brückenbauwerk aufnehmen zu können.In Figure 1 The device 1 according to the invention for removing an old bridge structure and installing a new bridge structure 3 is shown in plan view. This is the device 1 according to the invention, which is moved parallel to the bridge structure 3 before it is picked up. The arrows 19 show that, due to the SPMTs 8 serving as chassis, a transverse journey 6 to the track system 7 is also possible in order to be able to pick up the bridge structure parked parallel to the tracks.

Es sind hierfür entsprechende Vorarbeiten durch eine Baufirma zu leisten, um eine befahrbare Fläche zwischen den Gleisen und den einzelnen Gleissträngen herzustellen, beispielsweise durch eine Asphaltierung, die die Nutzbarkeit der Gleise für den Schienenverkehr allerdings nicht beeinträchtigt. Auf diese Weise kann das SPMT 8 als Fahrwerk sowohl in einer Normalfahrt 4 entlang der Gleisführung wie auch einer Diagonalfahrt 5 oder einer Querfahrt 6 verfahren werden. Dies hat die vorgenannten deutlichen Vorteile, was das Aufnehmen des alten Brückenbauwerks, das Absetzen des alten Brückenbauwerks wie auch das Aufnehmen und Einbauen des neuen Brückenbauwerks 3 anbetrifft.Appropriate preparatory work must be carried out by a construction company in order to create a passable area between the tracks and the individual track strands, for example by asphalting, which does not affect the usability of the tracks for rail traffic. In this way, the SPMT 8 can be moved as a chassis in a normal journey 4 along the track as well as a diagonal journey 5 or a transverse journey 6. This has the aforementioned clear advantages in terms of picking up the old bridge structure, setting down the old bridge structure as well as picking up and installing the new bridge structure 3.

Ebenfalls ist in Figur 1 bereits erkennbar, dass spezielle Hubvorrichtungen 2 an der Hochbrücke 11 vorgesehen sind, die in Längsrichtung der Hochbrücke 11 verlaufend angeordnet sind. In den Figuren 1 und 2 ist hierbei die hydraulische Komponente, wie sie in den Figuren 3 und 4 erkennbar und näher erläutert wird, in ausgefahrenem Zustand dargestellt. Dies ist der Fall, wenn die Hubvorrichtung eine Last ablädt oder aufnimmt, bevor die Last angehoben wird.Also is in Figure 1 It can already be seen that special lifting devices 2 are provided on the high bridge 11, which are arranged running in the longitudinal direction of the high bridge 11. In the Figures 1 and 2 is the hydraulic component as shown in the Figures 3 and 4 recognizable and explained in more detail, shown in the extended state. This occurs when the lifting device unloads or picks up a load before the load is lifted.

In Figur 2 ist die Vorrichtung zur Höhenverstellbarkeit 10 der Hochbrücke 11 dargestellt. Es ist hierbei erkennbar, dass ebenfalls hydraulisch ein Verschwenken dieser Vorrichtung derart vorgesehen ist, dass die gesamte Hochbrücke 11 zu den SPMTs hin absenkbar oder zur Oberleitung 9 hin anhebbar ist. In Figur 2 wird ebenfalls deutlich, dass die Oberleitung 9 auch beim Unterfahren durch die Vorrichtung 1 mit der Hochbrücke 11 nicht tangiert wird. D.h., diese Vorrichtung ermöglicht es erstmalig, die Entnahme wie auch Einführung eines Brückenbauwerks ohne Beeinträchtigung der Oberleitungen vorzunehmen. Dies bewirkt bereits für sich genommen ein großen Einsparpotential sowohl, was die Bauzeit anbelangt, als auch was die hierfür erforderlichen Kosten anbetrifft.In Figure 2 the device for height adjustment 10 of the high bridge 11 is shown. It can be seen here that this device is also hydraulically pivoted in such a way that the entire high bridge 11 can be lowered towards the SPMTs or raised towards the overhead line 9. In Figure 2 It is also clear that the overhead line 9 also passes under the device 1 with the high bridge 11 is not affected. This means that, for the first time, this device makes it possible to remove and insert a bridge structure without affecting the overhead lines. This in itself creates a great potential for savings, both in terms of construction time and the costs required for this.

Die Vorrichtung zur Höhenverstellbarkeit 10 der Hochbrücke 11 ist hierbei exakt so angehoben, dass ein Sicherheitsabstand zur Oberleitung 9 gewährleistet bleibt. In Figur 2 ist bereits das alte Brückenbauwerk aus der Gleisanlage 7 entfernt worden, die Vorrichtung 1 mit an der Hochbrücke 11 aufgehängtem neuen Brückenbauwerk 3 ist in Position verfahren worden, so dass das neue Brückenbauwerk 3 über die erfindungsgemäße Hebetechnik auf eine beliebige Höhe abgesenkt werden kann, wie dies durch die untere Position des Brückenbauwerks 3 erkennbar ist. So kann die neue Brücke auf Brückenwiederlagern exakt platziert werden, die nach Entfernen der alten Brücke auch eventuell für das neue Brückenbauwerk erstellt worden sind.The device for height adjustment 10 of the high bridge 11 is raised exactly so that a safe distance from the overhead line 9 is guaranteed. In Figure 2 the old bridge structure has already been removed from the track system 7, the device 1 with the new bridge structure 3 suspended on the high bridge 11 has been moved into position, so that the new bridge structure 3 can be lowered to any height using the lifting technology according to the invention, like this can be seen through the lower position of the bridge structure 3. This means that the new bridge can be placed precisely on bridge supports that may have been created for the new bridge structure after the old bridge was removed.

Es wird in Figur 2 ebenfalls deutlich, dass durch die innovative Anordnung der hydraulischen Hubvorrichtung in Längsrichtung der Hochbrücke 11 eine Anordnung erreicht wird, bei der beispielsweise der Litzenheber 14 beim Ein- und Ausfahren Parallelseile 17 parallel zur Oberleitung 9 bewegt und insofern die Vorrichtung auch bei ausgefahrener Hubvorrichtung 2 und somit angehobenem Brückenbauwerk weiterhin problemlos unter den Oberleitungen mit den SPMTs 8 auch quer zur Erstreckung der Gleisanlage 7 verfahren werden kann. Dies ist beispielsweise dann erforderlich, wenn das Brückenelement 3 aufgenommen wurde und dann die Vorrichtung 1 erst einmal quer zur Gleisanlage 7 auf das Gleis verfahren werden muss, auf dem das Brückenbauwerk 3 nun eingesetzt werden soll.It will be in Figure 2 also clear that the innovative arrangement of the hydraulic lifting device in the longitudinal direction of the high bridge 11 achieves an arrangement in which, for example, the strand jack 14 moves parallel cables 17 parallel to the overhead line 9 when moving in and out and in this respect the device also moves when the lifting device 2 is extended and thus With the bridge structure raised, it can still be easily moved under the overhead lines with the SPMTs 8, even transversely to the extent of the track system 7. This is necessary, for example, when the bridge element 3 has been picked up and then the device 1 must first be moved across the track system 7 onto the track on which the bridge structure 3 is now to be used.

Die Figur 3 zeigt nun die erfindungsgemäße Hubvorrichtung 2 erst in eingefahrenem Zustand. Hierunter ist zu verstehen, dass der Aufhängekopf 15 an den Litzenheber 14 herangeführt wird, wodurch die am Aufhängekopf 15 festgelegten Paralellseile 17 über eine Seilrolle 13 an die Hochbrücke 11 herangeführt werden. Es handelt sich somit um die Position, in der beispielsweise das aufgenommene neue Brückenbauwerk 3 unmittelbar an die Hochbrücke angehoben wird.The Figure 3 now shows the lifting device 2 according to the invention only in the retracted state. This is to be understood as meaning that the suspension head 15 is brought up to the strand jack 14, whereby the suspension head 15 is fixed Parallel cables 17 are brought to the high bridge 11 via a cable pulley 13. This is therefore the position in which, for example, the new bridge structure 3 is lifted directly onto the high bridge.

Umgekehrt zeigt Figur 4 die Hubvorrichtung in ausgefahrenem Zustand, weshalb sich hier nun der Aufhängekopf 15 hin zur Seilrolle 13 verschoben hat und somit die Parallelseile 17 über die Seilrolle 13 geführt nach unten abgelassen worden sind. Sowohl an dem dem aufnehmenden Brückenbauwerk 3 zugeführten freien Ende wie auch an dem mit der Hydraulik verbundenen Ende der Parallelseile 17 sind entsprechende Aufhängeköpfe 15 angeordnet. Durch diese vorteilhafte und innovative Konstruktion ist es somit möglich über die Umlenkung der Parallelseile 17 über die Seilrolle 13 die Hubbewegung zu bewirken, ohne dass hier eine Erhöhung der Vorrichtung über einen Hydraulikzylinder in Richtung der Hubbewegung, nämlich vertikal, erfolgt. Die hydraulische Bewegung erfolgt lediglich horizontal und bewirkt somit keine negative Höhenveränderung der Vorrichtung 1, die eine Problematik mit der Oberleitung 9 bewirken würde.Shows the other way around Figure 4 the lifting device is in the extended state, which is why the suspension head 15 has now moved towards the rope pulley 13 and thus the parallel ropes 17 have been lowered downwards, guided over the rope pulley 13. Corresponding suspension heads 15 are arranged both on the free end supplied to the receiving bridge structure 3 and on the end of the parallel cables 17 connected to the hydraulics. This advantageous and innovative design makes it possible to effect the lifting movement by deflecting the parallel cables 17 via the cable pulley 13, without the device being raised via a hydraulic cylinder in the direction of the lifting movement, namely vertically. The hydraulic movement only takes place horizontally and therefore does not cause a negative change in the height of the device 1, which would cause problems with the overhead line 9.

Alternativ wäre anstelle des Litzenhebers 14 auch eine alternative hydraulische Komponente einsetzbar, die parallel zur Hochbrücke 11 verlaufend die Verkürzung des umgelenkten Parallelseiles durch die Verschiebung des Aufhängekopfes 15 bewirkt.Alternatively, instead of the strand jack 14, an alternative hydraulic component could also be used, which, running parallel to the high bridge 11, causes the deflected parallel cable to be shortened by moving the suspension head 15.

In Figur 5 ist der Schnitt A-A durch die erfindungsgemäße Hochbrücke 11 mit daran angeordneten Hubvorrichtungen 2 erkennbar. Die Hochbrücke 11 weist hierbei seitliche Träger 21 auf, zwischen denen ein weiteres Trägerelement 22 verläuft, auf dem die Hubvorrichtungen 2 angeordnet sind. In Figur 5 ist die Ebene der Oberleitungen 9 ebenfalls dargestellt, die über den Seilrollen 13 der Parallelseile 17 verläuft. Insofern besteht hier keine Behinderung durch die Oberleitung 9. Des Weiteren ist in diesem Schnitt die an den Aufhängeköpfen 15 an zwei Punkten aufgehängte Brückenbauwerk 3 erkennbar sowie das SPMT Fahrwerk 8, das auf einem ausgebohlten Gleis 7 die Vorrichtung verfährt.In Figure 5 the section AA through the high bridge 11 according to the invention with lifting devices 2 arranged thereon can be seen. The high bridge 11 has lateral supports 21, between which a further support element 22 runs, on which the lifting devices 2 are arranged. In Figure 5 the plane of the overhead lines 9 is also shown, which runs above the pulleys 13 of the parallel cables 17. In this respect, there is no obstruction caused by the overhead line 9. Furthermore, in this section, the bridge structure 3, which is suspended at two points on the suspension heads 15, can be seen, as well as that SPMT chassis 8, which moves the device on an excavated track 7.

Schließlich ist ein Doppelkolbenzylinder 12 erkennbar über den eine hydraulische seitliche Verschiebung des Brückenbauwerks 3 beim Einpassen in die verbliebene Lücke in der Gleisanlage 7 ermöglicht wird. Die Längsverschiebung wird hierbei durch die SPMT selbst bewirkt, die Querverschiebung über den angesprochenen Doppelkolbenzylinder 12. Auf diese Weise ist die perfekte Platzierung auf den Wiederlagern sichergestellt.Finally, a double piston cylinder 12 can be seen, via which a hydraulic lateral displacement of the bridge structure 3 is made possible when it fits into the remaining gap in the track system 7. The longitudinal displacement is caused by the SPMT itself, the transverse displacement via the mentioned double-piston cylinder 12. In this way, perfect placement on the abutments is ensured.

Die Figuren 6 und 7 nun zeigen wiederum seitliche Ansichten der Vorrichtung 1, die nicht Teil der vorliegenden Erfindung ist, wobei hierbei der Unterschied darin besteht, dass die Fahrwerke nicht als SPMTs ausgebildet sind, sondern die Hochbrücke 11 auf zwei Bahnwagen angeordnet ist, beispielsweise auf Tragschnabelwagen. Hintergrund dieser alternativen Darstellung ist es, dass bei einer einzelnen Gleisanlage 7 oder auch bei einem Brückenbauwerk 3, das über größere Distanz an die Einbaustelle zu befördern ist, oder auch durch eine Gleisanlage 7, die nicht für die Befahrung mit SPMTs hergerichtet werden kann, der Rückgriff auf gleisgebundene Fahrwerke erforderlich ist, was nicht Teil der vorliegenden Erfindung ist, aber dennoch betrachtet werden soll.The Figures 6 and 7 now again show side views of the device 1, which is not part of the present invention, the difference being that the running gear is not designed as SPMTs, but the high bridge 11 is arranged on two railway cars, for example on beak-type carriages. The background to this alternative representation is that in the case of a single track system 7 or a bridge structure 3 that has to be transported to the installation site over a large distance, or even a track system 7 that cannot be prepared for use with SPMTs, the Recourse to track-bound running gear is required, which is not part of the present invention, but should still be considered.

Da nun kein Verfahren der Vorrichtung quer zu den Gleisen möglich ist, ist es erforderlich, nach dem Entfernen des alten Brückenbauwerks 3 eine Hilfsbrücke 23 in die entstandene Lücke einzusetzen, um die Vorrichtung über diese Hilfsbrücke in die Ablassposition des Brückenbauwerks 3 verfahren zu können. In der Darstellung nach Figur 6 ist diese Hilfsbrücke auf SPMTs gelagert, die auch beim Überfahren der Hilfsbrücke durch die Vorrichtung selbst ein Abstützen der Hilfsbrücke bewirken.Since it is now not possible to move the device across the tracks, it is necessary to insert an auxiliary bridge 23 into the resulting gap after removing the old bridge structure 3 in order to be able to move the device over this auxiliary bridge into the lowering position of the bridge structure 3. In the representation Figure 6 This auxiliary bridge is mounted on SPMTs, which also support the auxiliary bridge when the device itself drives over the auxiliary bridge.

Auch hier ist erkennbar, dass diese alternative Lösung, die nicht Teil der vorliegenden Erfindung ist, Möglichkeit eröffnet, die Oberleitungen 9 in Position zu belassen und lediglich vom Strom zu nehmen. Es ist ebenfalls erkennbar, dass die erfindungsgemäße Hubvorrichtung diesbezüglich baugleich zur vorherigen Alternative ausgebildet ist. Zudem ist erkennbar, dass auch hier eine Vorrichtung zur Höhenverstellbarkeit 10 der Hochbrücke 11 auf den Bahnwagen 18 angeordnet ist, die eine andere Neigungsposition aufweist, als dies in Figur 2 erkennbar ist.Here too it can be seen that this alternative solution, which is not part of the present invention, opens up the possibility of leaving the overhead lines 9 in position and just unplug it. It can also be seen that the lifting device according to the invention is designed to be identical to the previous alternative in this respect. It can also be seen that here too a device for height adjustment 10 of the high bridge 11 is arranged on the railway carriage 18, which has a different inclination position than that in Figure 2 is recognizable.

In Figur 7 ist nun die Hilfsbrücke 23 auf den Gleisanlagen 7 herausgefahren worden, so dass nun das neue Brückenbauwerk 3 in die entstandene Lücke auf die nicht dargestellten Wiederlager absenkbar ist. Hierfür wird die Hubvorrichtung 2 ausgefahren und somit die Parallelseile 17 über die Seilrolle 13 abgesenkt.In Figure 7 The auxiliary bridge 23 has now been moved out on the tracks 7, so that the new bridge structure 3 can now be lowered into the resulting gap onto the abutment, not shown. For this purpose, the lifting device 2 is extended and the parallel cables 17 are lowered over the cable pulley 13.

Claims (10)

  1. Method for replacing bridge constructions (3) in track systems (7) having parallel tracks, said method comprising the steps of picking up and lifting a new bridge construction (3) by a displaceable device (1) for replacing bridge constructions (3) in track systems (7), wherein the displacing of this device (1) on or across the track system (7) below the existing catenaries (9) of the track system (7) to an installed position of the new bridge construction (3) takes place across a gap of the track system (7) created by removing the old bridge construction and lowering the new bridge construction (3) into the gap of the track system (7) so as to be positioned precisely on abutments for supporting the new bridge construction (3), characterized in that the picking up of a new bridge construction (3) and/or the depositing of a removed old bridge construction from the track system (7) takes place on a parallel second track, wherein the device (1) for changing between the parallel tracks of the track system (7) is displaced transversely and/or diagonally to the course of the tracks.
  2. Method for replacing bridge constructions (3) in track systems (7) according to Claim 1,
    characterized in that
    in a first method step an area accessible by vehicles is generated in the track system (7).
  3. Method for replacing bridge constructions (3) in track systems (7) according to Claim 2,
    characterized in that
    the area accessible by vehicles is produced by asphalting or covering the tracks to be driven across, wherein further parallel tracks of the track system that are not required for the method continue to be usable for rail traffic.
  4. Method for replacing bridge constructions (3) in track systems (7) according to one of the preceding claims,
    characterized in that
    the old bridge constructions to be removed as well as the new bridge constructions (3) are lifted from the track systems (7) by the device (1) and by the latter re-inserted into the track systems.
  5. Method for replacing bridge constructions (3) in track systems (7) according to one of Claims 1 to 4,
    characterized in that
    the removal of the old bridge construction takes place transversely to the course of the railway track by a platform which is displaceable below the old bridge construction.
  6. Device for replacing bridge constructions (3) in track systems (7) comprising catenaries (9) according to a method according to one of Claims 1 to 5,
    characterized by
    - a height-adjustable high bridge (11) which is disposed on two undercarriages (8) disposed so as to be spaced apart from one another;
    - on which high bridge (11) are disposed at least two lifting devices (2) for lifting a bridge construction up to the high bridge (11) and for lowering the bridge construction from this high bridge (11);
    - wherein the lifting devices (2) comprise hydraulic pulling devices which cause a pulling movement of the lifting devices (2) that is approximately parallel to the catenary (9), wherein a deflection device of the lifting device (2) causes a deflection of the vertical lifting movement of the load to the horizontal hydraulic pulling movement;
    - wherein the construction height of undercarriage and high bridge (11) constructed thereon and of lifting devices (2) disposed on the high bridge is less than the spacing between the catenaries (9) specified for rail traffic and the track system (7).
  7. Device for replacing bridge constructions (3) in track systems (7) according to Claim 6, characterized in that
    - a strandjack (14) as the hydraulic pulling device is part of the lifting device (2);
    - wherein parallel cables (17) engage on the load to be lifted by means of suspension heads (15)
    - and the parallel cables (17) are deflected from the vertical to the horizontal by way of a cable pulley (13).
  8. Device for replacing bridge constructions (3) in track systems (7) according to one of Claims 6 or 7,
    characterized in that
    lateral shifting of the load takes place by means of double piston cylinders (12) which engage on the lifting devices (2).
  9. Device for replacing bridge constructions (3) in track systems (7) according to one of Claims 6 to 8,
    characterized in that
    self-propelled modular trailers [SPMTs] (8) are used as undercarriages for the device.
  10. Device for replacing bridge constructions (3) in track systems (7) according to Claim 9,
    characterized in that
    the SPMTs (8) in relation to the track course (7) can be displaced in the longitudinal direction (4), the diagonal direction (5) and the transverse direction (6).
EP20736566.9A 2019-07-26 2020-06-15 Method and apparatus for replacing bridge constructions in track systems Active EP4004289B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102019120231.0A DE102019120231A1 (en) 2019-07-26 2019-07-26 Method and device for replacing bridge structures in track systems
PCT/DE2020/100498 WO2021018336A1 (en) 2019-07-26 2020-06-15 Method and apparatus for replacing bridge constructions in track systems

Publications (3)

Publication Number Publication Date
EP4004289A1 EP4004289A1 (en) 2022-06-01
EP4004289B1 true EP4004289B1 (en) 2023-09-13
EP4004289C0 EP4004289C0 (en) 2023-09-13

Family

ID=71465042

Family Applications (1)

Application Number Title Priority Date Filing Date
EP20736566.9A Active EP4004289B1 (en) 2019-07-26 2020-06-15 Method and apparatus for replacing bridge constructions in track systems

Country Status (3)

Country Link
EP (1) EP4004289B1 (en)
DE (2) DE102019120231A1 (en)
WO (1) WO2021018336A1 (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR388416A (en) * 1908-03-21 1908-08-12 Moisant Laurent Savey Des Atel Device for the rapid replacement of under-rail decks, small and medium spans of railways in operation
DE10066016B4 (en) 2000-02-01 2005-09-08 Walter-Heilit Verkehrswegebau Gmbh Formwork arrangement, in particular for the production of a concrete slab for a fixed railroad track
AT501272B8 (en) 2005-03-30 2007-02-15 Plasser Bahnbaumasch Franz METHOD FOR REMOVING DAMAGED RAILWAYS OF A TRAIL AND MACHINE
DE102006049408B4 (en) 2006-10-16 2013-03-14 Stahlberg Roensch GmbH Method and device for replacing a defective or worn rail piece
KR20100021874A (en) * 2008-08-18 2010-02-26 조영철 Method for removing, installing and replacing an upper structure of bridge, and lifting apparatus and transportation vehicle of the upper structure of bridge for the method
KR101234090B1 (en) * 2012-05-16 2013-02-19 (주) 철도안전연구소 Method for changing girder of railway plate girder bridge
US10214395B2 (en) * 2017-07-12 2019-02-26 Da Pan Gantry assembly and a system for replacing single or double railway bridges

Also Published As

Publication number Publication date
WO2021018336A1 (en) 2021-02-04
DE102019120231A1 (en) 2021-01-28
DE112020003586A5 (en) 2022-06-02
EP4004289A1 (en) 2022-06-01
EP4004289C0 (en) 2023-09-13

Similar Documents

Publication Publication Date Title
EP2763928B1 (en) Railroad crane
DE3313187C2 (en)
CH639717A5 (en) DEVICE FOR CONTINUOUSLY DISMANTLING OR REPLACING THE RAILS AND SILLS OF A TRACK.
DE69204189T2 (en) Device for moving and replacing railway elements and method for using this device.
CH630680A5 (en) MOBILE DEVICE FOR RECEIVING AND / OR LAYING TRACK YACHTS, SWITCH YOCS OR WHOLE SWITCHES consisting of RAILS AND SLEEPERS.
DE2313055A1 (en) METHOD AND DEVICE FOR REMOVING AND INSTALLING GLEISJOCHEN
EP1840072A2 (en) Crane with boom and raceway for cable roller assemblies
DE102006030432B3 (en) Changing method e.g. for changing lower floor panel construction units at rail-mounted vehicles, involves driving entire vehicle on track driven into workshop and which lower floor panel construction unit is loosened
DE2410718A1 (en) Switch point layer and dismantler - has two undercarriages on train connected by bridge and lifting equipment on chain drive
EP4004289B1 (en) Method and apparatus for replacing bridge constructions in track systems
DE102010016016B4 (en) Method for renewing longitudinal members of a bridge
DE3511520A1 (en) RAIL CARRIAGE FOR REPLACEMENT OR LAYING OR DISMANTLING AND TRANSPORTING TRACK YOCKS
DE202006010225U1 (en) Low floor components e.g. bogie, changing device for e.g. clock train, has changing mechanism designed as assembly tray attached to sink hole, where tray is connected with track standing at angle to rail sections in lowered condition
DE102007028778A1 (en) Lattice tower crane for dam, has rotating assembly arranged on chassis, and rotating platform mounted on rotating assembly via distance pipe, where main extension arm and derrick extension arm are arranged on rotating platform
DE2228196A1 (en) PROCEDURE AND ARRANGEMENT FOR RENEWAL OF RAILWAY SECTIONS
EP4001046B1 (en) Maintenance device for railway vehicles, running gear of a railway vehicle and maintenance method
DE2817635C2 (en)
EP3535455B1 (en) Rail vehicle having crane rails for a gantry crane
EP1881110B1 (en) Device and method for extending a track composed of track fields or track sections
DE102005020454A1 (en) Method and device for replacing wheelsets on rail vehicles by means of a movable device
EP3554912B9 (en) Transport system comprising a cable-drawn vehicle
DE19733633C1 (en) Manufacturing method for ballast=free railway track superstructure
DE202015008680U1 (en) Rail vehicle for use primarily in automated container sorting plants with intermediate intermediate storage areas
DE3122892A1 (en) Track-movable installation for erecting an auxiliary bridge
DE2140053A1 (en) METHOD AND DEVICE FOR CREATING ROAD UNDERWEAR UNDER RAILWAYS

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: UNKNOWN

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20220131

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

INTG Intention to grant announced

Effective date: 20230525

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502020005249

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20230913

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231214

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231213

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231214

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240113

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240113

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

U01 Request for unitary effect filed

Effective date: 20231012

U07 Unitary effect registered

Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT SE SI

Effective date: 20240402

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 502020005249

Country of ref document: DE

U20 Renewal fee for the european patent with unitary effect paid

Year of fee payment: 5

Effective date: 20240604

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20240614

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230913

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20240615

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240615

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240630

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240615

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20200615