EP4004289B1 - Method and apparatus for replacing bridge constructions in track systems - Google Patents
Method and apparatus for replacing bridge constructions in track systems Download PDFInfo
- Publication number
- EP4004289B1 EP4004289B1 EP20736566.9A EP20736566A EP4004289B1 EP 4004289 B1 EP4004289 B1 EP 4004289B1 EP 20736566 A EP20736566 A EP 20736566A EP 4004289 B1 EP4004289 B1 EP 4004289B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- bridge
- track
- replacing
- constructions
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
Definitions
- An exemplary task is to carry out the work in sections of 2 bridges per closure break with the shortest possible construction time, whereby there are old bridge structures that need to be replaced, each with a steel superstructure of approx. 70 t, which are to be replaced by new bridges, each with approx. 320 t Reinforced concrete are made.
- the conventional procedure with a large crane involves dismantling the overhead lines on all 8 tracks step by step and then reassembling them again in order to be able to work with the crane technology from above. This already causes considerable preparation costs in order to even be able to start the work.
- a possible crane that could be used here, for example, has a dead weight of approx. 800 t, plus the dead weight of the new bridge structure that has to be lifted.
- the total weight of the crane including the bridge would then be approx. 1100t, which poses further problems with regard to the subsoil in the area of the crane parking space.
- a target construction time for execution is, for example, around 34 hours per structure, during which time the crane would have to be brought into position and the lifting carried out.
- the publication KR 101 234 090 B1 finally shows a girder replacement method for a railway bridge, wherein lifting and placing a new girder by a lifting device, transporting the new girder to the railway bridge by the operation of a motor vehicle and installing the new girder on piers from which the previous girder is removed is disclosed .
- a rail-bound vehicle is disclosed as a means of transport for the new bridge element.
- the aim is to be able to carry out the replacement without affecting the arrangement of overhead lines.
- inventive method is carried out with a device according to claim 6, the following claims 7 to 10 having as their subject advantageous developments of this device.
- the structural measure is carried out by a boiler bridge or elevated bridge, which is used in combination with an SPMT (Self-Propelled Modular Trailer).
- SPMT Self-Propelled Modular Trailer
- the SPMT is able to carry out the maneuvers longitudinal travel, transverse travel, diagonal travel or circular travel, which can be accessed fully electronically via the remote control.
- a special lifting system comprising a steel structure to accommodate the lifting system in the boiler or high bridge.
- the innovative development includes a parallel rope combination with suspension heads on both sides with an integrated rope pulley for lifting the load, in an advantageous version with 5 grooves for a load holding of 150 t plus the resulting force from the lifting bolts.
- Another element relevant to the installation of the bridge structure is a hydraulic side displacement option for positioning the bridge in its final installation position, whereby the required longitudinal displacement can be carried out via the hydrostatic drive of the SPMT.
- the suspension on the bridge has suspension heads on the bridge structure itself, which are each coordinated in conjunction with the static requirements and possibilities of the structure.
- the high girder bridge and the lifting system can be positioned in such a way that they can be adjusted longitudinally and transversely so that the bridge structure can be lifted directly above the abutments on the structure. This has the advantage that no different bending moment occurs in the structure compared to the state in the end position.
- the number of SPMT axle lines can be selected in such a way that a comparison calculation can be made compared to the loading scheme of, for example, the Irish Bahn for locomotives or freight trains can.
- auxiliary bridge (HB) will be temporarily used to drive over the open gap after the old bridge has been expanded. On single-track routes, this can be done by driving in the HB with SPMT or lifting it in with a mobile crane. If this happens with an SPMT, it can remain as support under the HB. This means that the railway car can drive over the auxiliary bridge and the new bridge structure Lower it in exactly the right position, as already described in more detail.
- FIG. 1 The device 1 according to the invention for removing an old bridge structure and installing a new bridge structure 3 is shown in plan view. This is the device 1 according to the invention, which is moved parallel to the bridge structure 3 before it is picked up.
- the arrows 19 show that, due to the SPMTs 8 serving as chassis, a transverse journey 6 to the track system 7 is also possible in order to be able to pick up the bridge structure parked parallel to the tracks.
- the device for height adjustment 10 of the high bridge 11 is raised exactly so that a safe distance from the overhead line 9 is guaranteed.
- the old bridge structure has already been removed from the track system 7, the device 1 with the new bridge structure 3 suspended on the high bridge 11 has been moved into position, so that the new bridge structure 3 can be lowered to any height using the lifting technology according to the invention, like this can be seen through the lower position of the bridge structure 3.
- This means that the new bridge can be placed precisely on bridge supports that may have been created for the new bridge structure after the old bridge was removed.
- the Figure 3 now shows the lifting device 2 according to the invention only in the retracted state.
- This is to be understood as meaning that the suspension head 15 is brought up to the strand jack 14, whereby the suspension head 15 is fixed
- Parallel cables 17 are brought to the high bridge 11 via a cable pulley 13. This is therefore the position in which, for example, the new bridge structure 3 is lifted directly onto the high bridge.
- an alternative hydraulic component could also be used, which, running parallel to the high bridge 11, causes the deflected parallel cable to be shortened by moving the suspension head 15.
- FIG 5 the section AA through the high bridge 11 according to the invention with lifting devices 2 arranged thereon can be seen.
- the high bridge 11 has lateral supports 21, between which a further support element 22 runs, on which the lifting devices 2 are arranged.
- the plane of the overhead lines 9 is also shown, which runs above the pulleys 13 of the parallel cables 17. In this respect, there is no obstruction caused by the overhead line 9.
- the bridge structure 3, which is suspended at two points on the suspension heads 15, can be seen, as well as that SPMT chassis 8, which moves the device on an excavated track 7.
- a double piston cylinder 12 can be seen, via which a hydraulic lateral displacement of the bridge structure 3 is made possible when it fits into the remaining gap in the track system 7.
- the longitudinal displacement is caused by the SPMT itself, the transverse displacement via the mentioned double-piston cylinder 12. In this way, perfect placement on the abutments is ensured.
- FIGS. 6 and 7 now again show side views of the device 1, which is not part of the present invention, the difference being that the running gear is not designed as SPMTs, but the high bridge 11 is arranged on two railway cars, for example on beak-type carriages.
- the background to this alternative representation is that in the case of a single track system 7 or a bridge structure 3 that has to be transported to the installation site over a large distance, or even a track system 7 that cannot be prepared for use with SPMTs, the Recourse to track-bound running gear is required, which is not part of the present invention, but should still be considered.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Description
Der Austausch von parallel zueinander angeordneten Brückenbauwerken in Gleisanlagen, die alle elektrifiziert sind, verursacht einen großen logistischen und technischen Aufwand sowie lange Ausfallzeiten an den betroffenen Gleisanlagen, insbesondere wenn hierbei nur max. 2 der parallel verlaufenden Gleise gleichzeitig gesperrt werden sollen. Dies wird aber angestrebt, um die Ausfallzeiten an der Gleisanlage insgesamt zu reduzieren und daher nur schrittweise vorzugehen. Daher entstand die Überlegung einer Entwicklung alternativer Lösungen zum Ein- und Ausbringen von Brückenbauwerken in elektrifizierten Gleisanlagen.The replacement of parallel bridge structures in track systems, which are all electrified, causes a great deal of logistical and technical effort as well as long downtimes on the affected track systems, especially if only a maximum of 2 of the parallel tracks are to be closed at the same time. However, this is aimed at reducing downtime on the track system overall and therefore only proceeding gradually. This led to the idea of developing alternative solutions for inserting and removing bridge structures in electrified track systems.
Bei mehreren parallel verlaufenden Brückenbauwerken in Gleisanlagen ist die herkömmliche Vorgehensweise, die Brückenbauwerke mit einem Großkran auszutauschen räumlich nicht möglich, wenn hierbei nur max. 2 Gleise gesperrt werden können. Eine beispielhafte Aufgabenstellung ist hierbei die Ausführung der Arbeiten in Abschnitten von je 2 Brücken je Sperrpause mit möglichst kurzer Bauzeit, wobei alte auszutauschende Brückenbauwerke vorliegen mit je ca. 70 t Stahlüberbau, die durch neue Brücken ersetzt werden sollen, die mit je ca. 320 t Stahlbeton gefertigt sind.If there are several parallel bridge structures in railway tracks, the conventional approach of replacing the bridge structures with a large crane is not spatially possible if only a maximum of 2 tracks can be closed. An exemplary task is to carry out the work in sections of 2 bridges per closure break with the shortest possible construction time, whereby there are old bridge structures that need to be replaced, each with a steel superstructure of approx. 70 t, which are to be replaced by new bridges, each with approx. 320 t Reinforced concrete are made.
Die herkömmliche Vorgehensweise mit einem Großkran sieht hierbei vor, die Oberleitungen aller 8 Gleise Zug um Zug zu demontieren und dann wieder zu remontieren, um mit der Krantechnik von oben arbeiten zu können. Dies verursacht bereits erhebliche Vorbereitungskosten, um überhaupt mit den Arbeiten beginnen zu können.The conventional procedure with a large crane involves dismantling the overhead lines on all 8 tracks step by step and then reassembling them again in order to be able to work with the crane technology from above. This already causes considerable preparation costs in order to even be able to start the work.
Ein möglicher Kran der hier zum Einsatz kommen könnte bringt beispielsweise ein Eigengewicht von ca. 800 t mit sich, zzgl. dem Eigengewicht des neuen Brückenbauwerks welches gehoben werden muss. Das Gesamtgewicht des Kranes inkl. der Brücke wäre so dann ca. 1100t, was weitere Probleme in Bezug auf den Untergrund im Bereich des Kranstellplatzes aufwirft.A possible crane that could be used here, for example, has a dead weight of approx. 800 t, plus the dead weight of the new bridge structure that has to be lifted. The total weight of the crane including the bridge would then be approx. 1100t, which poses further problems with regard to the subsoil in the area of the crane parking space.
Eine angestrebte Bauzeit bei der Ausführung liegt beispielsweise bei etwa 34 Stunden je Bauwerk, wobei in dieser Zeit der Kran in Stellung gebracht und der Hub ausgeführt werden müsste.A target construction time for execution is, for example, around 34 hours per structure, during which time the crane would have to be brought into position and the lifting carried out.
Massive Eingriffe in die Infrastruktur der Gleisanlagen, ggf. auch Setzungen im Kranstellplatzbereich, Sicherungsmaßnahmen und Kampfmittelsondierungen im Untergrund sind weitere, schwer einschätzbare Aufwendungen, die nur sehr schwierig im Vorfeld zu bewerten sind, was das Einhalten der angestrebten Bauzeit bei der Ausführung in Frage stellt. Die Entwicklung alternativer Lösungen zum Ein- und Ausbringen von Brückenbauwerken in elektrifizierten Gleisanlagen würde somit ggfs. erhebliche Einsparpotenziale mit sich bringen und idealerweise eine verlässliche Kalkulation einer verkürzten Bauzeit erlauben.Massive interventions in the infrastructure of the track systems, possibly also subsidence in the crane parking area, security measures and explosive ordnance soundings in the subsoil are further expenses that are difficult to estimate and are very difficult to evaluate in advance, which calls into question whether the desired construction time will be adhered to during execution. The development of alternative solutions for inserting and removing bridge structures in electrified track systems would potentially bring with it considerable savings potential and ideally allow a reliable calculation of a shortened construction time.
Der Stand der Technik bietet keinen Ansatz zur Lösung dieser Problematik. Aus der Veröffentlichung
Es handelt sich hierbei um ein Verfahren, dass ausschließlich auf einzelne Schienenelemente beschränkt anwendbar ist und hierbei keine Möglichkeit eröffnet, ein größeres bauliches Element wie einen Brückenkörper aus den Gleisanlagen zu entfernen und zu ersetzen.This is a process that is only applicable to individual rail elements and does not offer the possibility of removing and replacing a larger structural element such as a bridge body from the track system.
Ein ähnlicher Lösungsansatz befindet sich ebenfalls in der Druckschrift
Aus der
Die Veröffentlichung
Bei den Arbeiten an mehreren Brückenbauwerken in parallel verlaufenden Gleisanlagen ergeben sich sehr spezifische Problemstellungen, die durch die zuvor beschriebenen technischen Lösungen zum Austausch einzelner Schienenelemente nicht gelöst werden können. So wird angestrebt, lediglich zwei der parallelen Gleise gleichzeitig von der Baumaßnahme zu erfassen. Geht man beispielsweise von Gleisanlagen aus, bei denen acht parallele Gleise ein auszutauschendes Brückenbauwerk aufweisen, so ist es nach dem bisherigen Stand der Technik nur mit einem vergleichsweise großen technischen und logistischen Aufwand möglich, diese Brückenbauwerke nacheinander bei paarweiser Außerbetriebnahme der Gleise auszutauschen.When working on several bridge structures in parallel track systems, very specific problems arise that cannot be solved by the previously described technical solutions for replacing individual rail elements. The aim is to only include two of the parallel tracks in the construction work at the same time. For example, if one assumes track systems in which eight parallel tracks have a bridge structure that needs to be replaced, the current state of the art only requires a comparatively large technical and logistical one Effort possible to replace these bridge structures one after the other when the tracks are taken out of service in pairs.
Zudem wäre auch die Frage der Oberleitungen problematisch, da ein Betrieb der benachbarten Gleise mit elektrifizierten Oberleitungen risikobehaftet ist bei parallelen Arbeiten an Gleisen, deren Oberleitungen für den Bauabschnitt entfernt worden sind.In addition, the question of overhead lines would also be problematic, as operating the neighboring tracks with electrified overhead lines is risky in the case of parallel work on tracks whose overhead lines have been removed for the construction phase.
Es ist daher die Aufgabe der vorliegenden Erfindung, ein neuartiges Verfahren sowie eine hierfür erforderliche Vorrichtung zu schaffen, um deutlich effizienter Brückenbauwerke in Gleisanlagen austauschen zu können. Hierbei wird angestrebt, den Austausch ohne Beeinträchtigung der Anordnung von Oberleitungen durchführen zu können.It is therefore the object of the present invention to create a novel method and a device required for this in order to be able to replace bridge structures in track systems much more efficiently. The aim is to be able to carry out the replacement without affecting the arrangement of overhead lines.
Erreicht wird dies nach einem Verfahren nach Anspruch 1, die Unteransprüche 2 bis 5 haben vorteilhafte Weiterbildungen des Verfahrens zum Gegenstand.This is achieved using a method according to
Des Weiteren wird das erfinderische Verfahren durchgeführt mit einer Vorrichtung nach Anspruch 6, wobei die folgenden Ansprüche 7 bis 10 vorteilhafte Ausbildungen dieser Vorrichtung zum Gegenstand haben.Furthermore, the inventive method is carried out with a device according to claim 6, the following
Konstruktiv wird die bauliche Maßnahme durch eine Kessel- oder Hochbrücke geleistet, die in Kombination mit einem SPMT (Self-Propelled-Modular-Trailer) zum Einsatz kommt. Der SPMT ist in der Lage die Manöver Längsfahrt, Querfahrt, Diagonalfahrt oder Kreisfahrt durchzuführen, die vollelektronisch über die Fernsteuerung abgerufen werden können.Structurally, the structural measure is carried out by a boiler bridge or elevated bridge, which is used in combination with an SPMT (Self-Propelled Modular Trailer). The SPMT is able to carry out the maneuvers longitudinal travel, transverse travel, diagonal travel or circular travel, which can be accessed fully electronically via the remote control.
Zu dieser Kombination kommt die Entwicklung einer speziellen Hebeanlage umfassend eine Stahlkonstruktion zur Aufnahme der Hebeanlage in der Kessel- bzw. Hochbrücke. Die neuartige Entwicklung umfasst eine Parallelseilkombination mit beidseitigen Aufhängeköpfen mit einer integrierten Seilrolle für die Lastaufnahme, in einer vorteilhaften Ausführung 5-rillig für eine Lastaufnahme von 150 t zzgl. der resultierenden Kraft aus den Hublitzen.In addition to this combination, there is the development of a special lifting system comprising a steel structure to accommodate the lifting system in the boiler or high bridge. The innovative development includes a parallel rope combination with suspension heads on both sides with an integrated rope pulley for lifting the load, in an advantageous version with 5 grooves for a load holding of 150 t plus the resulting force from the lifting bolts.
Ein weiteres beim Einbau des Brückenbauwerkes relevantes Element ist eine hydraulische Seitenverschubmöglichkeit zur Positionierung der Brücke in deren Einbau-Endlage, wobei der erforderliche Längsverschub über den hydrostatischen Antrieb der SPMT erfolgen kann.Another element relevant to the installation of the bridge structure is a hydraulic side displacement option for positioning the bridge in its final installation position, whereby the required longitudinal displacement can be carried out via the hydrostatic drive of the SPMT.
Die Aufhängung an der Brücke weist Aufhängeköpfe am Brückenbauwerk selbst auf, die jeweils in Verbindung mit den statischen Erfordernissen und Möglichkeiten des Bauwerks abgestimmt werden. Grundsätzlich sind die Hochträgerbrücke und die Hebeanlage so längs- und quer verstellbar platzierbar, dass das Brückenbauwerk direkt über den Widerlagern am Bauwerk gehoben werden kann. Dies hat den Vorteil, dass kein anderes Biegemoment im Bauwerk gegenüber dem Zustand in der Endlage entsteht.The suspension on the bridge has suspension heads on the bridge structure itself, which are each coordinated in conjunction with the static requirements and possibilities of the structure. In principle, the high girder bridge and the lifting system can be positioned in such a way that they can be adjusted longitudinally and transversely so that the bridge structure can be lifted directly above the abutments on the structure. This has the advantage that no different bending moment occurs in the structure compared to the state in the end position.
Mit Hilfe dieser neuen Transport- und Hebetechnik ist es möglich, eine alte Brücke herauszunehmen und diese gegen eine neue Brücke zu ersetzen ohne dass eine weitere Technik wie z. B. Verschub- oder Hebemittel erforderlich werden.With the help of this new transport and lifting technology, it is possible to remove an old bridge and replace it with a new bridge without the need for additional technology such as. B. shifting or lifting equipment may be required.
Im Folgenden wird die Vorgehensweise und deren Voraussetzungen näher betrachtet, wobei die nachfolgende Beschreibung sich auf ein beispielhaftes Projekt von 8 parallelen Gleisanlagen mit Brückenbauwerken bezieht.The procedure and its requirements will be examined in more detail below, with the following description referring to an exemplary project of 8 parallel track systems with bridge structures.
Aufgabenstellung ist, im Zuge eines 60-tägigen Zeitplans insgesamt 8 Brücken auszutauschen.
- (1) Alle neuen Brückenbauwerke werden vor Ort in Einbaunähe gefertigt.
- (2) Das Transport- und Hebegerät wird in Einzelteilen auf Standard-LKW's an der Baustelle angeliefert und einsatzbereit vormontiert.
- (3) Eine Baufirma stellt eine befahrbare Fläche zwischen den Gleisen und den einzelnen Gleissträngen her.
- (4) Die Oberleitungen müssen nicht entfernt oder verzogen werden, aber die Fahrdrähte werden zum Zeitpunkt der Durchführung spannungsfrei geschaltet und geerdet.
- (5) Das Transport- und Hebegerät fährt über die auszutauschende Brücke, nimmt diese mit der beschriebenen Hebetechnik auf, setzt durch Querfahrt auf das Nachbargleis um und kann somit die alte Brücke herausfahren.
- (6) Die alte Brücke wird abgelegt.
- (7) Das Transport- und Hebegerät fährt seitlich über das neue Bauwerk, nimmt dieses ebenfalls mit der beschriebenen Hebetechnik auf und fährt über das Nachbargleis in Linie der Einbauposition (Querachse der neuen Brücke).
- (8) Durch die Quer- und Längsfahrt wird Lage der neuen Brücke erreicht.
- (9) Die Brücke wird über die neu entwickelte Hebetechnik auf eine beliebige Höhe abgesenkt und auf den Widerlagern platziert. Hierbei kann auf Bedarf der Seitenschub erfolgen, der über einen Doppelkolbenzylinder vorgesehen ist.
- (10) Nach dem Aushängen der Brücke ist diese fertig für den weiteren Gleisbau.
- (1) All new bridge structures are manufactured on site close to installation.
- (2) The transport and lifting device is delivered to the construction site in individual parts on standard trucks and pre-assembled ready for use.
- (3) A construction company creates a passable area between the tracks and the individual track strands.
- (4) The overhead lines do not need to be removed or distorted, but the contact wires are de-energized and grounded at the time of implementation.
- (5) The transport and lifting device moves over the bridge to be replaced, picks it up using the lifting technology described, moves across to the neighboring track and can thus drive out the old bridge.
- (6) The old bridge is discarded.
- (7) The transport and lifting device moves laterally over the new structure, picks it up using the lifting technology described and moves over the neighboring track in line with the installation position (transverse axis of the new bridge).
- (8) The position of the new bridge is reached through the transverse and longitudinal travel.
- (9) The bridge is lowered to any height using the newly developed lifting technology and placed on the abutments. If necessary, the side shift can be carried out, which is provided via a double-piston cylinder.
- (10) After the bridge has been unhooked, it is ready for further track construction.
Was die Belastungen der Gleise und alten Brücken anbetrifft ist es beim erfindungsgemäßen Verfahren sowie der hierfür verwendeten Vorrichtung vorteilhaft, dass die Anzahl der SPMT-Achslinien so gewählt werden kann, dass eine Vergleichsrechnung gegenüber dem Belastungsschema beispielsweise der Deutschen Bahn für Loks bzw. Güterzüge erstellt werden kann. Grundsätzlich ist es hierbei möglich, die SPMT-Achslinien je nach Bedarf in einem Baukastensystem (4-Achser und 6-Achser Fahrwerke) zu erweitern bzw. zu verkürzen. Auf diese Weise ist die Anpassung an die jeweiligen Gegebenheiten und die Belastbarkeit einer Gleisanlage sichergestellt.As far as the loads on the tracks and old bridges are concerned, it is advantageous in the method according to the invention and the device used for this purpose that the number of SPMT axle lines can be selected in such a way that a comparison calculation can be made compared to the loading scheme of, for example, the Deutsche Bahn for locomotives or freight trains can. In principle, it is possible to expand or shorten the SPMT axle lines as required in a modular system (4-axle and 6-axle chassis). On This ensures adaptation to the respective circumstances and the resilience of a track system.
Eine Alternative, die ein Lösung darstellt, die nicht Teil der vorliegenden Erfindung ist, ist der Einsatz eines Bahnwagens, beispielsweise eines Tragschnabelwagens TSW-348, anstelle des SPMT für die technischen Bedingungen, dass
- nur ein Gleis zur Verfügung steht,
- oder die einzubauenden Brückenbauwerke ggf. über eine größere Distanz herangefahren werden müssen,
- oder die Gleise aus baulichen Bedingungen nicht ausgebohlt bzw. nicht befahrbar hergerichtet werden und so ein Befahren mit einem gummibereiften Fahrzeug nicht möglich ist.
- only one track is available,
- or the bridge structures to be installed may have to be approached over a greater distance,
- or the tracks are not dug out or prepared to be passable due to structural conditions and so driving on them with a rubber-tired vehicle is not possible.
Die Abweichungen zur zuvor beschriebenen Vorgehensweise besteht dann darin, dass die neuen Brückenbauwerke seitlich über eine Verschubtechnik unter die Hochbrücke geschoben werden, um diese aufnehmen zu können, da der Gleiswagen das Gleis ja nicht verlassen kann und somit keine Querfahrt möglich ist.The deviation from the previously described procedure is that the new bridge structures are pushed laterally under the high bridge using a sliding technology in order to be able to accommodate them, since the track carriage cannot leave the track and therefore no crossing is possible.
Analog hierzu erfolgt das Absetzen der aus der Gleisanlage gelösten zu ersetzenden alten Brücke in umgekehrter Reihenfolge.Similarly, the old bridge that has been removed from the track system and is to be replaced is removed in the reverse order.
Die Problematik besteht dann darin, dass nach dem Entfernen der aus der Gleisanlage gelösten zu ersetzenden alten Brücke eine Lücke in der Gleisanlage verbleibt, die die Positionierung des Bahnwagens mit aufgenommenem neuen Brückenbauwerk verhindert. Zum Überfahren der offenen Lücke nach dem Ausbau der alten Brücke wird temporär eine Hilfsbrücke (HB) eingesetzt. Dies kann bei eingleisigen Strecken durch Einfahren der HB mit SPMT oder dem Einheben durch einen Mobilkran durchgeführt werden. Geschieht das mit einem SPMT, so kann dieser als Unterstützung unter der HB verbleiben. So kann der Bahnwagen über die Hilfsbrücke fahren und das neue Brückenbauwerk genau positioniert absenken, wie dies bereits näher beschrieben ist.The problem then lies in the fact that after removing the old bridge that is to be replaced from the track system, a gap remains in the track system, which prevents the positioning of the railway car with the new bridge structure added. An auxiliary bridge (HB) will be temporarily used to drive over the open gap after the old bridge has been expanded. On single-track routes, this can be done by driving in the HB with SPMT or lifting it in with a mobile crane. If this happens with an SPMT, it can remain as support under the HB. This means that the railway car can drive over the auxiliary bridge and the new bridge structure Lower it in exactly the right position, as already described in more detail.
Im Folgenden wird das erfindungsgemäße Verfahren wie auch die Vorrichtung zu dessen Durchführung anhand von Zeichnungen näher beschrieben. Es zeigen
- Fig. 1
- eine Draufsicht auf die verwendete Hochbrücke (11) auf einer Gleisanlage (7) mit anzuhebendem Brückenbauwerk (3);
- Fig. 2
- eine seitliche Ansicht der erfindungsgemäßen Hochbrücke (11) gelagert auf SPMTs (8) mit aufgehängtem Brückenbauwerk (3);
- Fig. 3
- eine Kombination von Ansichten auf die erfindungsgemäße Hubvorrichtung in eingefahrenem Zustand zum Anheben einer Last;
- Fig. 4
- die erfindungsgemäße Hubvorrichtung ausgefahren zum Absenken einer Last;
- Fig. 5
- den Schnitt AA durch die Hochbrücke (11) mit aufgehängtem Brückenbauwerk (3) und darin angeordneter Hubvorrichtung;
- Fig. 6
- eine seitliche Ansicht einer alternativen Vorrichtung, die nicht auf SPMTs sondern auf gleisgebundenen Bahnwagen (18) gelagert ist und verfahren wird und somit ein Ausführungsbeispiel darstellt, das nicht Teil der vorliegenden Erfindung ist, sowie
- Fig. 7
- ebenfalls die nicht einen Teil der vorliegenden Erfindung bildende Vorrichtung nach
Figur 6 beim Einbauvorgang eines neuen Brückenbauwerks (3).
- Fig. 1
- a top view of the high bridge (11) used on a track system (7) with a bridge structure (3) to be lifted;
- Fig. 2
- a side view of the high bridge (11) according to the invention mounted on SPMTs (8) with a suspended bridge structure (3);
- Fig. 3
- a combination of views of the lifting device according to the invention in the retracted state for lifting a load;
- Fig. 4
- the lifting device according to the invention extended to lower a load;
- Fig. 5
- the section AA through the high bridge (11) with the suspended bridge structure (3) and the lifting device arranged therein;
- Fig. 6
- a side view of an alternative device, which is not mounted and moved on SPMTs but on track-bound railway carriages (18) and thus represents an exemplary embodiment that is not part of the present invention, and
- Fig. 7
- also reproduces the device which does not form part of the present invention
Figure 6 during the installation process of a new bridge structure (3).
In
Es sind hierfür entsprechende Vorarbeiten durch eine Baufirma zu leisten, um eine befahrbare Fläche zwischen den Gleisen und den einzelnen Gleissträngen herzustellen, beispielsweise durch eine Asphaltierung, die die Nutzbarkeit der Gleise für den Schienenverkehr allerdings nicht beeinträchtigt. Auf diese Weise kann das SPMT 8 als Fahrwerk sowohl in einer Normalfahrt 4 entlang der Gleisführung wie auch einer Diagonalfahrt 5 oder einer Querfahrt 6 verfahren werden. Dies hat die vorgenannten deutlichen Vorteile, was das Aufnehmen des alten Brückenbauwerks, das Absetzen des alten Brückenbauwerks wie auch das Aufnehmen und Einbauen des neuen Brückenbauwerks 3 anbetrifft.Appropriate preparatory work must be carried out by a construction company in order to create a passable area between the tracks and the individual track strands, for example by asphalting, which does not affect the usability of the tracks for rail traffic. In this way, the
Ebenfalls ist in
In
Die Vorrichtung zur Höhenverstellbarkeit 10 der Hochbrücke 11 ist hierbei exakt so angehoben, dass ein Sicherheitsabstand zur Oberleitung 9 gewährleistet bleibt. In
Es wird in
Die
Umgekehrt zeigt
Alternativ wäre anstelle des Litzenhebers 14 auch eine alternative hydraulische Komponente einsetzbar, die parallel zur Hochbrücke 11 verlaufend die Verkürzung des umgelenkten Parallelseiles durch die Verschiebung des Aufhängekopfes 15 bewirkt.Alternatively, instead of the
In
Schließlich ist ein Doppelkolbenzylinder 12 erkennbar über den eine hydraulische seitliche Verschiebung des Brückenbauwerks 3 beim Einpassen in die verbliebene Lücke in der Gleisanlage 7 ermöglicht wird. Die Längsverschiebung wird hierbei durch die SPMT selbst bewirkt, die Querverschiebung über den angesprochenen Doppelkolbenzylinder 12. Auf diese Weise ist die perfekte Platzierung auf den Wiederlagern sichergestellt.Finally, a
Die
Da nun kein Verfahren der Vorrichtung quer zu den Gleisen möglich ist, ist es erforderlich, nach dem Entfernen des alten Brückenbauwerks 3 eine Hilfsbrücke 23 in die entstandene Lücke einzusetzen, um die Vorrichtung über diese Hilfsbrücke in die Ablassposition des Brückenbauwerks 3 verfahren zu können. In der Darstellung nach
Auch hier ist erkennbar, dass diese alternative Lösung, die nicht Teil der vorliegenden Erfindung ist, Möglichkeit eröffnet, die Oberleitungen 9 in Position zu belassen und lediglich vom Strom zu nehmen. Es ist ebenfalls erkennbar, dass die erfindungsgemäße Hubvorrichtung diesbezüglich baugleich zur vorherigen Alternative ausgebildet ist. Zudem ist erkennbar, dass auch hier eine Vorrichtung zur Höhenverstellbarkeit 10 der Hochbrücke 11 auf den Bahnwagen 18 angeordnet ist, die eine andere Neigungsposition aufweist, als dies in
In
Claims (10)
- Method for replacing bridge constructions (3) in track systems (7) having parallel tracks, said method comprising the steps of picking up and lifting a new bridge construction (3) by a displaceable device (1) for replacing bridge constructions (3) in track systems (7), wherein the displacing of this device (1) on or across the track system (7) below the existing catenaries (9) of the track system (7) to an installed position of the new bridge construction (3) takes place across a gap of the track system (7) created by removing the old bridge construction and lowering the new bridge construction (3) into the gap of the track system (7) so as to be positioned precisely on abutments for supporting the new bridge construction (3), characterized in that the picking up of a new bridge construction (3) and/or the depositing of a removed old bridge construction from the track system (7) takes place on a parallel second track, wherein the device (1) for changing between the parallel tracks of the track system (7) is displaced transversely and/or diagonally to the course of the tracks.
- Method for replacing bridge constructions (3) in track systems (7) according to Claim 1,
characterized in that
in a first method step an area accessible by vehicles is generated in the track system (7). - Method for replacing bridge constructions (3) in track systems (7) according to Claim 2,
characterized in that
the area accessible by vehicles is produced by asphalting or covering the tracks to be driven across, wherein further parallel tracks of the track system that are not required for the method continue to be usable for rail traffic. - Method for replacing bridge constructions (3) in track systems (7) according to one of the preceding claims,
characterized in that
the old bridge constructions to be removed as well as the new bridge constructions (3) are lifted from the track systems (7) by the device (1) and by the latter re-inserted into the track systems. - Method for replacing bridge constructions (3) in track systems (7) according to one of Claims 1 to 4,
characterized in that
the removal of the old bridge construction takes place transversely to the course of the railway track by a platform which is displaceable below the old bridge construction. - Device for replacing bridge constructions (3) in track systems (7) comprising catenaries (9) according to a method according to one of Claims 1 to 5,
characterized by- a height-adjustable high bridge (11) which is disposed on two undercarriages (8) disposed so as to be spaced apart from one another;- on which high bridge (11) are disposed at least two lifting devices (2) for lifting a bridge construction up to the high bridge (11) and for lowering the bridge construction from this high bridge (11);- wherein the lifting devices (2) comprise hydraulic pulling devices which cause a pulling movement of the lifting devices (2) that is approximately parallel to the catenary (9), wherein a deflection device of the lifting device (2) causes a deflection of the vertical lifting movement of the load to the horizontal hydraulic pulling movement;- wherein the construction height of undercarriage and high bridge (11) constructed thereon and of lifting devices (2) disposed on the high bridge is less than the spacing between the catenaries (9) specified for rail traffic and the track system (7). - Device for replacing bridge constructions (3) in track systems (7) according to Claim 6, characterized in that- a strandjack (14) as the hydraulic pulling device is part of the lifting device (2);- wherein parallel cables (17) engage on the load to be lifted by means of suspension heads (15)- and the parallel cables (17) are deflected from the vertical to the horizontal by way of a cable pulley (13).
- Device for replacing bridge constructions (3) in track systems (7) according to one of Claims 6 or 7,
characterized in that
lateral shifting of the load takes place by means of double piston cylinders (12) which engage on the lifting devices (2). - Device for replacing bridge constructions (3) in track systems (7) according to one of Claims 6 to 8,
characterized in that
self-propelled modular trailers [SPMTs] (8) are used as undercarriages for the device. - Device for replacing bridge constructions (3) in track systems (7) according to Claim 9,
characterized in that
the SPMTs (8) in relation to the track course (7) can be displaced in the longitudinal direction (4), the diagonal direction (5) and the transverse direction (6).
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE102019120231.0A DE102019120231A1 (en) | 2019-07-26 | 2019-07-26 | Method and device for replacing bridge structures in track systems |
| PCT/DE2020/100498 WO2021018336A1 (en) | 2019-07-26 | 2020-06-15 | Method and apparatus for replacing bridge constructions in track systems |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| EP4004289A1 EP4004289A1 (en) | 2022-06-01 |
| EP4004289B1 true EP4004289B1 (en) | 2023-09-13 |
| EP4004289C0 EP4004289C0 (en) | 2023-09-13 |
Family
ID=71465042
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP20736566.9A Active EP4004289B1 (en) | 2019-07-26 | 2020-06-15 | Method and apparatus for replacing bridge constructions in track systems |
Country Status (3)
| Country | Link |
|---|---|
| EP (1) | EP4004289B1 (en) |
| DE (2) | DE102019120231A1 (en) |
| WO (1) | WO2021018336A1 (en) |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR388416A (en) * | 1908-03-21 | 1908-08-12 | Moisant Laurent Savey Des Atel | Device for the rapid replacement of under-rail decks, small and medium spans of railways in operation |
| DE10066016B4 (en) | 2000-02-01 | 2005-09-08 | Walter-Heilit Verkehrswegebau Gmbh | Formwork arrangement, in particular for the production of a concrete slab for a fixed railroad track |
| AT501272B8 (en) | 2005-03-30 | 2007-02-15 | Plasser Bahnbaumasch Franz | METHOD FOR REMOVING DAMAGED RAILWAYS OF A TRAIL AND MACHINE |
| DE102006049408B4 (en) | 2006-10-16 | 2013-03-14 | Stahlberg Roensch GmbH | Method and device for replacing a defective or worn rail piece |
| KR20100021874A (en) * | 2008-08-18 | 2010-02-26 | 조영철 | Method for removing, installing and replacing an upper structure of bridge, and lifting apparatus and transportation vehicle of the upper structure of bridge for the method |
| KR101234090B1 (en) * | 2012-05-16 | 2013-02-19 | (주) 철도안전연구소 | Method for changing girder of railway plate girder bridge |
| US10214395B2 (en) * | 2017-07-12 | 2019-02-26 | Da Pan | Gantry assembly and a system for replacing single or double railway bridges |
-
2019
- 2019-07-26 DE DE102019120231.0A patent/DE102019120231A1/en not_active Withdrawn
-
2020
- 2020-06-15 WO PCT/DE2020/100498 patent/WO2021018336A1/en not_active Ceased
- 2020-06-15 DE DE112020003586.7T patent/DE112020003586A5/en active Pending
- 2020-06-15 EP EP20736566.9A patent/EP4004289B1/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| WO2021018336A1 (en) | 2021-02-04 |
| DE102019120231A1 (en) | 2021-01-28 |
| DE112020003586A5 (en) | 2022-06-02 |
| EP4004289A1 (en) | 2022-06-01 |
| EP4004289C0 (en) | 2023-09-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2763928B1 (en) | Railroad crane | |
| DE3313187C2 (en) | ||
| CH639717A5 (en) | DEVICE FOR CONTINUOUSLY DISMANTLING OR REPLACING THE RAILS AND SILLS OF A TRACK. | |
| DE69204189T2 (en) | Device for moving and replacing railway elements and method for using this device. | |
| CH630680A5 (en) | MOBILE DEVICE FOR RECEIVING AND / OR LAYING TRACK YACHTS, SWITCH YOCS OR WHOLE SWITCHES consisting of RAILS AND SLEEPERS. | |
| DE2313055A1 (en) | METHOD AND DEVICE FOR REMOVING AND INSTALLING GLEISJOCHEN | |
| EP1840072A2 (en) | Crane with boom and raceway for cable roller assemblies | |
| DE102006030432B3 (en) | Changing method e.g. for changing lower floor panel construction units at rail-mounted vehicles, involves driving entire vehicle on track driven into workshop and which lower floor panel construction unit is loosened | |
| DE2410718A1 (en) | Switch point layer and dismantler - has two undercarriages on train connected by bridge and lifting equipment on chain drive | |
| EP4004289B1 (en) | Method and apparatus for replacing bridge constructions in track systems | |
| DE102010016016B4 (en) | Method for renewing longitudinal members of a bridge | |
| DE3511520A1 (en) | RAIL CARRIAGE FOR REPLACEMENT OR LAYING OR DISMANTLING AND TRANSPORTING TRACK YOCKS | |
| DE202006010225U1 (en) | Low floor components e.g. bogie, changing device for e.g. clock train, has changing mechanism designed as assembly tray attached to sink hole, where tray is connected with track standing at angle to rail sections in lowered condition | |
| DE102007028778A1 (en) | Lattice tower crane for dam, has rotating assembly arranged on chassis, and rotating platform mounted on rotating assembly via distance pipe, where main extension arm and derrick extension arm are arranged on rotating platform | |
| DE2228196A1 (en) | PROCEDURE AND ARRANGEMENT FOR RENEWAL OF RAILWAY SECTIONS | |
| EP4001046B1 (en) | Maintenance device for railway vehicles, running gear of a railway vehicle and maintenance method | |
| DE2817635C2 (en) | ||
| EP3535455B1 (en) | Rail vehicle having crane rails for a gantry crane | |
| EP1881110B1 (en) | Device and method for extending a track composed of track fields or track sections | |
| DE102005020454A1 (en) | Method and device for replacing wheelsets on rail vehicles by means of a movable device | |
| EP3554912B9 (en) | Transport system comprising a cable-drawn vehicle | |
| DE19733633C1 (en) | Manufacturing method for ballast=free railway track superstructure | |
| DE202015008680U1 (en) | Rail vehicle for use primarily in automated container sorting plants with intermediate intermediate storage areas | |
| DE3122892A1 (en) | Track-movable installation for erecting an auxiliary bridge | |
| DE2140053A1 (en) | METHOD AND DEVICE FOR CREATING ROAD UNDERWEAR UNDER RAILWAYS |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: UNKNOWN |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
| 17P | Request for examination filed |
Effective date: 20220131 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| DAV | Request for validation of the european patent (deleted) | ||
| DAX | Request for extension of the european patent (deleted) | ||
| GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
| GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
| INTG | Intention to grant announced |
Effective date: 20230525 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502020005249 Country of ref document: DE |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
| REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
| REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20230913 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231214 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231213 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231214 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240113 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240113 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 |
|
| U01 | Request for unitary effect filed |
Effective date: 20231012 |
|
| U07 | Unitary effect registered |
Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT SE SI Effective date: 20240402 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502020005249 Country of ref document: DE |
|
| U20 | Renewal fee for the european patent with unitary effect paid |
Year of fee payment: 5 Effective date: 20240604 |
|
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| 26N | No opposition filed |
Effective date: 20240614 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230913 |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20240615 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20240615 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20240630 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20240615 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20200615 |