EP2679724A1 - Asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement - Google Patents
Asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement Download PDFInfo
- Publication number
- EP2679724A1 EP2679724A1 EP12174361.1A EP12174361A EP2679724A1 EP 2679724 A1 EP2679724 A1 EP 2679724A1 EP 12174361 A EP12174361 A EP 12174361A EP 2679724 A1 EP2679724 A1 EP 2679724A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- pellets
- predefined fraction
- asphalt production
- pulverized
- production arrangement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C19/00—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
- E01C19/02—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for preparing the materials
- E01C19/05—Crushing, pulverising or disintegrating apparatus; Aggregate screening, cleaning, drying or heating apparatus; Dust-collecting arrangements specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C19/00—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
- E01C19/02—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for preparing the materials
- E01C19/10—Apparatus or plants for premixing or precoating aggregate or fillers with non-hydraulic binders, e.g. with bitumen, with resins, i.e. producing mixtures or coating aggregates otherwise than by penetrating or surface dressing; Apparatus for premixing non-hydraulic mixtures prior to placing or for reconditioning salvaged non-hydraulic compositions
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F26—DRYING
- F26B—DRYING SOLID MATERIALS OR OBJECTS BY REMOVING LIQUID THEREFROM
- F26B11/00—Machines or apparatus for drying solid materials or objects with movement which is non-progressive
- F26B11/02—Machines or apparatus for drying solid materials or objects with movement which is non-progressive in moving drums or other mainly-closed receptacles
- F26B11/028—Arrangements for the supply or exhaust of gaseous drying medium for direct heat transfer, e.g. perforated tubes, annular passages, burner arrangements, dust separation, combined direct and indirect heating
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F26—DRYING
- F26B—DRYING SOLID MATERIALS OR OBJECTS BY REMOVING LIQUID THEREFROM
- F26B23/00—Heating arrangements
- F26B23/02—Heating arrangements using combustion heating
- F26B23/028—Heating arrangements using combustion heating using solid fuel; burning the dried product
Definitions
- the present invention generally relates to an asphalt production arrangement and a method for preparing an asphalt mixture, for subsequent intermediate storage and future spreading on a road or the like.
- the present invention specifically relates to an asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement for preparation of an asphalt mixture, according to the preambles of the independent claims.
- Asphalt is basically a mixture of aggregate and a binder, and is used as a surface course, binder course and/or base course on for example roads, airports, parking sites, etc.
- a predetermined amount of aggregate e.g. from a raw material silo
- the drier preferably rotates during operation, and the aggregate is fed into a first upper end of the drier and is discharged from a second lower end.
- the aggregate is exposed to heat and is heated to a temperature between 120 and 300 °C, such that the aggregate is dried.
- the heat is generated by a heat source in the drier.
- the aggregate is placed in a mixer where a heated binder, which usually is bitumen based, is provided in liquid form. Subsequently, the asphalt mixture is kneaded, at a process temperature of approximately 160 °C, to its final consistency, for subsequent intermediate storage and future spreading.
- a heated binder which usually is bitumen based
- the heat source in the drier oftentimes is a burner, which usually is run on heavy oil, diesel, coal or propane gas. It is important that the temperature in the drier remains equal over the time.
- FR 2358966 A an example of a method for producing asphalt is disclosed. According to the method, an aggregate is heated without bitumen in a drying drum. Furthermore, the aggregate is mixed in a mixer.
- the inventors of the present invention has identified a need for an improved method and arrangement for producing asphalt, and in particular an improved asphalt production arrangement and a method for heating a drier applicable in preparation of an asphalt mixture, which method and arrangement are less harmless to the environment and which makes use of an alternative energy source.
- An object of the present invention to provide an asphalt production arrangement and a method for heating a drier in an asphalt production arrangement, which method and arrangement are more environmental friendly and provides improved working conditions.
- Another object of the present invention is to provide an asphalt production arrangement and a method for heating a drier in an asphalt production arrangement wherein an alternative energy source is used, such that undesirable consequences of the burning of fossil fuels, such as high carbon dioxide emissions, is avoided.
- a further object of the present invention is to provide an asphalt production arrangement and a method for heating a drier in an asphalt production arrangement, which provides equal temperature in the drier over the time in the short term perspective, and an equal temperature of the aggregate in a long term perspective.
- the asphalt production arrangement for preparation of an asphalt mixture comprises a hollow drier drum, adapted to hold an aggregate for an asphalt mixture, and a heat source arranged in connection with said drier drum.
- the heat source is adapted to heat said drier drum, such that said aggregate is heated to a desired temperature.
- the heat source comprises a pellets combustion device adapted to burn wood or biomass, or pellets, or pulverized pellets, of wood or biomass in order to generate said heat.
- the present invention relates to a method for heating a drier drum in an asphalt production arrangement.
- the method comprises the steps of:
- FIG. 1 shows an asphalt production arrangement 1 for preparation of an asphalt mixture, according to one embodiment of the present invention.
- the arrangement 1 comprises a hollow drier drum 2, adapted to hold an aggregate for an asphalt mixture and a heat source 3 arranged in connection with the drier drum 2.
- the heat source 3 is adapted to heat the drier drum 2, such that the aggregate is heated to a desired temperature.
- the desired temperature is between 120-300°C, and preferably between 180-280°C.
- the heat source 3 comprises a pellets combustion device 4 adapted to burn wood or biomass, or pellets, or pulverized pellets, of wood or biomass in order to generate the heat.
- the drier drum 2 may be provided with an inlet 5 for receiving an aggregate and an outlet 6 for discharging the aggregate from the drier drum 2.
- the pellets, or pulverized pellets are fed to the pellets combustion device 4 via a supply line 7.
- the desired temperature is dependent on, e.g. the moisture content of the aggregate.
- the desired temperature of the aggregate is obtained by regulating the amount of wood or biomass, or pellets, or pulverized pellets, being fed to the pellets combustion device 4.
- the pellets have a predefined fraction.
- the predefined fraction is preferably between 0-3 mm.
- the arrangement 1 comprises a pulverizing device 8 adapted to pulverize the pellets into a first predefined fraction 10.
- the first predefined fraction is less than 2 mm.
- the pulverizing device 8 comprises a plurality of cutting discs adapted to pulverize the pellets into the first predefined fraction 10.
- the first predefined fraction 10 comprises a second predefined fraction 11 which is less than 1 mm.
- the pulverizing device 8 may comprise an impact crusher or a grinding device.
- the arrangement 1 further comprises a sifting device 9 adapted to sift the first predefined fraction 10, wherein the second predefined fraction 11 is separated from the first predefined fraction 10.
- the second predefined fraction is less than 1 mm.
- Burning pellets, or pulverized pellets with a predefined fraction less than 1 mm is advantageous in that the pellets, or pulverized pellets may be fed to the pellets combustion device 4 in a more precise amount than when feeding the pellets combustion device 4 with pellets, or pulverized pellets having a larger fraction, which ensures that the temperature is kept at an equal level in the drier drum 2 over a time period.
- the sifting device 9 comprises a wind sifter provided with a first blowing device 12, adapted to generate a first air flow 13 which is adapted to flow through the pulverized pellets of the first predefined fraction 10 in the sifting device 9, such that the first air flow 13 forces the second predefined fraction 11 to be separated from the first predefined fraction 10.
- the second predefined fraction 11 is less than 1 mm.
- the wind sifter comprises cyclone separator 14 adapted to separate the second predefined fraction 11.
- the cyclone separator 14 is adapted to exhaust pulverized pellets of the second predefined fraction 11 from the sifting device 9 by suction.
- the fraction of the pulverized pellets which are exhausted from the sifting device 9 depends on the flow rate of the air flow. The greater the flow rate is, the larger the fraction of the pulverized pellets obtained is.
- the sifting device 9 comprises a rotary feeder 16 adapted to feed the second predefined fraction 11 to the buffer silo 20.
- the rotary feeder preferably comprises a rotating disc.
- the arrangement 1 comprises a dosing device 17 adapted to deliver a predetermined amount of pellets, or pulverized pellets of predefined fraction 10, 11 to the pellets combustion device 4.
- the arrangement 1 may further comprise a compressor 18 adapted to aid in transporting pellets, or pulverized pellets of the second predefined fraction 11, via said supply line 7, to said pellets combustion means 4, and a feeding means 19 adapted to feed pellets, or pulverized pellets of the second predefined fraction 11 from said dosing device 17 to said supply line 7.
- the arrangement 1 comprises a buffer silo 20 adapted to store a minimum amount of pellets, or pulverized pellets of said second predefined fraction 11, wherein the minimum amount of pellets, or pulverized pellets of said second predefined fraction 11 being stored is approximately between 5-20 m 3 , and preferably 12 m 3 . Storing a minimum amount of pellets, or pulverized pellets of said second predefined fraction 11 in a buffer silo 20 ensures that an equal amount of pellets, or pulverized pellets of said second predefined fraction 11 is fed to the pellets combustions device 4 over a time period.
- the buffer silo 20 may further comprise a level regulation device 21 which, depending on the amount of pellets, or pulverized pellets of said second predefined fraction 11 present in the buffer silo 20, regulates the amount of pellets being fed to the pulverizing device 8. This also helps to ensure that the feeding of pellets, or pulverized pellets of said second predefined fraction 11 to the pellets combustion device 4 remains equal over a time period.
- a level regulation device 21 which, depending on the amount of pellets, or pulverized pellets of said second predefined fraction 11 present in the buffer silo 20, regulates the amount of pellets being fed to the pulverizing device 8. This also helps to ensure that the feeding of pellets, or pulverized pellets of said second predefined fraction 11 to the pellets combustion device 4 remains equal over a time period.
- the arrangement 1 further comprises a storage silo 22 adapted to store pellets.
- the pellets is provided to the pulverizing device 8 via a feeder screw 23 or by any other suitable feeding means.
- the present invention further relates to a method for heating a drier drum 2 in an asphalt production arrangement 1.
- the method comprises the steps of:
- the pellets provided to the heat source 3 has a predefined fraction.
- the method further comprises the steps of:
- the method further comprises the step of:
- the method further comprises the step of:
- the method further comprises the step:
- the heat source 3 comprising the pellets combustion device 4 preferably bums pellets of said second predefined fraction 11.
- the pellets combustion device 4 may burn pellets of any other fraction.
- the advantage of burning pellets of the second predefined fraction 11 is that it facilitates keeping the temperature in the drier drum 2 at an equal level over a time period.
- the reason for keeping an equal temperature over the time in the drier drum 2 is to provide an exact temperature of the final product, i.e. the asphalt mixture, which is advantageous in that the asphalt provides for improved durability.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Road Paving Machines (AREA)
Abstract
Description
- The present invention generally relates to an asphalt production arrangement and a method for preparing an asphalt mixture, for subsequent intermediate storage and future spreading on a road or the like. The present invention specifically relates to an asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement for preparation of an asphalt mixture, according to the preambles of the independent claims.
- Asphalt is basically a mixture of aggregate and a binder, and is used as a surface course, binder course and/or base course on for example roads, airports, parking sites, etc. Generally, when preparing an asphalt mixture a predetermined amount of aggregate, e.g. from a raw material silo, is loaded onto a conveyer belt or the like, whereupon the aggregate is directed towards a drier. The drier preferably rotates during operation, and the aggregate is fed into a first upper end of the drier and is discharged from a second lower end. In the drier, the aggregate is exposed to heat and is heated to a temperature between 120 and 300 °C, such that the aggregate is dried. The heat is generated by a heat source in the drier. Thereafter, the aggregate is placed in a mixer where a heated binder, which usually is bitumen based, is provided in liquid form. Subsequently, the asphalt mixture is kneaded, at a process temperature of approximately 160 °C, to its final consistency, for subsequent intermediate storage and future spreading.
- Today the heat source in the drier oftentimes is a burner, which usually is run on heavy oil, diesel, coal or propane gas. It is important that the temperature in the drier remains equal over the time.
- In
an example of a method for producing asphalt is disclosed. According to the method, an aggregate is heated without bitumen in a drying drum. Furthermore, the aggregate is mixed in a mixer.FR 2358966 A - The inventors of the present invention has identified a need for an improved method and arrangement for producing asphalt, and in particular an improved asphalt production arrangement and a method for heating a drier applicable in preparation of an asphalt mixture, which method and arrangement are less harmless to the environment and which makes use of an alternative energy source.
- An object of the present invention to provide an asphalt production arrangement and a method for heating a drier in an asphalt production arrangement, which method and arrangement are more environmental friendly and provides improved working conditions.
- Another object of the present invention is to provide an asphalt production arrangement and a method for heating a drier in an asphalt production arrangement wherein an alternative energy source is used, such that undesirable consequences of the burning of fossil fuels, such as high carbon dioxide emissions, is avoided.
- A further object of the present invention is to provide an asphalt production arrangement and a method for heating a drier in an asphalt production arrangement, which provides equal temperature in the drier over the time in the short term perspective, and an equal temperature of the aggregate in a long term perspective.
- The above-mentioned objects are achieved by the present invention according to the independent claim.
- Preferred embodiments are set forth in the dependent claims.
- In accordance with the present invention the asphalt production arrangement for preparation of an asphalt mixture comprises a hollow drier drum, adapted to hold an aggregate for an asphalt mixture, and a heat source arranged in connection with said drier drum. The heat source is adapted to heat said drier drum, such that said aggregate is heated to a desired temperature. The heat source comprises a pellets combustion device adapted to burn wood or biomass, or pellets, or pulverized pellets, of wood or biomass in order to generate said heat.
- According to another aspect, the present invention relates to a method for heating a drier drum in an asphalt production arrangement. The method comprises the steps of:
- providing wood or biomass, or pellets, or pulverized pellets, of wood or biomass to said heat source;
- generating heat by combustion of said wood or biomass, or pellets, or pulverized pellets, in said heat source;
- applying heat to drier drum to heat an aggregate within said drier drum.
-
-
Figure 1 shows an asphalt production arrangement comprising a drier drum and a heat source according to one embodiment of the present invention. -
Figure 2 shows an asphalt production arrangement comprising a drier drum and a heat source according to another embodiment of the present invention. -
Figure 3 shows a method for heating a drier drum in an asphalt production arrangement according to another embodiment of the present invention. -
Figure 1 shows an asphalt production arrangement 1 for preparation of an asphalt mixture, according to one embodiment of the present invention. The arrangement 1 comprises ahollow drier drum 2, adapted to hold an aggregate for an asphalt mixture and aheat source 3 arranged in connection with thedrier drum 2. Theheat source 3 is adapted to heat thedrier drum 2, such that the aggregate is heated to a desired temperature. The desired temperature is between 120-300°C, and preferably between 180-280°C. Theheat source 3 comprises a pellets combustion device 4 adapted to burn wood or biomass, or pellets, or pulverized pellets, of wood or biomass in order to generate the heat. Thedrier drum 2 may be provided with an inlet 5 for receiving an aggregate and anoutlet 6 for discharging the aggregate from thedrier drum 2. The pellets, or pulverized pellets, are fed to the pellets combustion device 4 via asupply line 7. The desired temperature is dependent on, e.g. the moisture content of the aggregate. The desired temperature of the aggregate is obtained by regulating the amount of wood or biomass, or pellets, or pulverized pellets, being fed to the pellets combustion device 4. - According to one embodiment, the pellets have a predefined fraction. The predefined fraction is preferably between 0-3 mm.
- According to one embodiment, as illustrated in
Figure 2 , the arrangement 1 comprises a pulverizing device 8 adapted to pulverize the pellets into a firstpredefined fraction 10. The first predefined fraction is less than 2 mm. The pulverizing device 8 comprises a plurality of cutting discs adapted to pulverize the pellets into the firstpredefined fraction 10. The firstpredefined fraction 10 comprises a secondpredefined fraction 11 which is less than 1 mm. In another embodiment, the pulverizing device 8 may comprise an impact crusher or a grinding device. - In the embodiment shown in
Figure 2 , the arrangement 1 further comprises asifting device 9 adapted to sift the firstpredefined fraction 10, wherein the secondpredefined fraction 11 is separated from the firstpredefined fraction 10. The second predefined fraction is less than 1 mm. Thus, pulverized pellets of said firstpredefined fraction 10 having a greater fraction than 1 mm will remain in the pulverizing device 8 until a fraction of less than 1 mm is obtained. Burning pellets, or pulverized pellets with a predefined fraction less than 1 mm is advantageous in that the pellets, or pulverized pellets may be fed to the pellets combustion device 4 in a more precise amount than when feeding the pellets combustion device 4 with pellets, or pulverized pellets having a larger fraction, which ensures that the temperature is kept at an equal level in thedrier drum 2 over a time period. - In
Figure 2 , thesifting device 9 comprises a wind sifter provided with afirst blowing device 12, adapted to generate afirst air flow 13 which is adapted to flow through the pulverized pellets of the firstpredefined fraction 10 in thesifting device 9, such that thefirst air flow 13 forces the secondpredefined fraction 11 to be separated from the firstpredefined fraction 10. Preferably, the secondpredefined fraction 11 is less than 1 mm. - According to the embodiment shown in
Figure 2 , the wind sifter comprisescyclone separator 14 adapted to separate the secondpredefined fraction 11. Thecyclone separator 14 is adapted to exhaust pulverized pellets of the secondpredefined fraction 11 from thesifting device 9 by suction. The fraction of the pulverized pellets which are exhausted from thesifting device 9 depends on the flow rate of the air flow. The greater the flow rate is, the larger the fraction of the pulverized pellets obtained is. - In another embodiment, the
sifting device 9 comprises arotary feeder 16 adapted to feed the secondpredefined fraction 11 to thebuffer silo 20. The rotary feeder preferably comprises a rotating disc. - According to the embodiment shown in
Figure 2 , the arrangement 1 comprises adosing device 17 adapted to deliver a predetermined amount of pellets, or pulverized pellets of 10, 11 to the pellets combustion device 4. The arrangement 1 may further comprise a compressor 18 adapted to aid in transporting pellets, or pulverized pellets of the secondpredefined fraction predefined fraction 11, via saidsupply line 7, to said pellets combustion means 4, and afeeding means 19 adapted to feed pellets, or pulverized pellets of the secondpredefined fraction 11 from saiddosing device 17 to saidsupply line 7. - Furthermore, according the embodiment shown in
Figure 2 , the arrangement 1 comprises abuffer silo 20 adapted to store a minimum amount of pellets, or pulverized pellets of said secondpredefined fraction 11, wherein the minimum amount of pellets, or pulverized pellets of said secondpredefined fraction 11 being stored is approximately between 5-20 m3, and preferably 12 m3. Storing a minimum amount of pellets, or pulverized pellets of said secondpredefined fraction 11 in abuffer silo 20 ensures that an equal amount of pellets, or pulverized pellets of said secondpredefined fraction 11 is fed to the pellets combustions device 4 over a time period. Thebuffer silo 20 may further comprise alevel regulation device 21 which, depending on the amount of pellets, or pulverized pellets of said secondpredefined fraction 11 present in thebuffer silo 20, regulates the amount of pellets being fed to the pulverizing device 8. This also helps to ensure that the feeding of pellets, or pulverized pellets of said secondpredefined fraction 11 to the pellets combustion device 4 remains equal over a time period. - In the embodiment shown in
Figure 2 , the arrangement 1 further comprises astorage silo 22 adapted to store pellets. Preferably the pellets is provided to the pulverizing device 8 via afeeder screw 23 or by any other suitable feeding means. - According to another aspect, the present invention further relates to a method for heating a
drier drum 2 in an asphalt production arrangement 1. According to the embodiment shown inFigure 3 , the method comprises the steps of: - providing wood or biomass, or pellets, or pulverized pellets, of wood or biomass to the
heat source 3; - generating heat by combustion of the wood or biomass, or pellets, or pulverized pellets, in the
heat source 3; - applying heat to
drier drum 2 to heat an aggregate within thedrier drum 2. - In one embodiment, the pellets provided to the
heat source 3 has a predefined fraction. - According to another embodiment, the method further comprises the steps of:
- pulverizing the pellets into a first
predefined fraction 10; - burning pulverized pellets of the first
predefined fraction 10. - In another embodiment, the method further comprises the step of:
- sifting the pulverized pellets of the first
predefined fraction 10, wherein pulverized pellets of a secondpredefined fraction 11 is separated. - In another embodiment, the method further comprises the step of:
- burning pulverized pellets of the second
predefined fraction 11. - In yet another embodiment, the method further comprises the step:
- dosing the pellets, or pulverized pellets, of the predefined fraction, such that a predetermined amount of pellets, or pulverized pellets, of the predefined fraction is fed to the pellets combustion device 4.
- Thus, the
heat source 3 comprising the pellets combustion device 4 preferably bums pellets of said secondpredefined fraction 11. However, the pellets combustion device 4 may burn pellets of any other fraction. The advantage of burning pellets of the secondpredefined fraction 11 is that it facilitates keeping the temperature in thedrier drum 2 at an equal level over a time period. The reason for keeping an equal temperature over the time in thedrier drum 2 is to provide an exact temperature of the final product, i.e. the asphalt mixture, which is advantageous in that the asphalt provides for improved durability. - The present invention is not limited to the above-described preferred embodiments. Various alternatives, modifications and equivalents may be used. Therefore, the above embodiments should not be taken as limiting the scope of the invention, which is defined by the appending claims.
Claims (15)
- Asphalt production arrangement (1) for preparation of an asphalt mixture, said arrangement comprising:- a hollow drier drum (2), adapted to hold an aggregate for an asphalt mixture;- a heat source (3) arranged in connection with said drier drum (2), and adapted to heat said drier drum (2), such that said aggregate is heated to a desired temperature,
characterized in that said heat source (3) comprises a pellets combustion device (4) adapted to burn wood or biomass, or pellets, or pulverized pellets, of wood or biomass in order to generate said heat. - Asphalt production arrangement according to claim 1, wherein said pellets have a predefined fraction.
- Asphalt production arrangement according to claim 2, wherein said predefined fraction is between 0-3 mm.
- Asphalt production arrangement according to any of claims 1-3, wherein said arrangement comprises a pulverizing device (8) adapted to pulverize said pellets into a first predefined fraction (10).
- Asphalt production arrangement according to claims 4, wherein said pulverizing device (8) comprises a plurality of cutting discs adapted to pulverize said pellets into said first predefined fraction (10).
- Asphalt production arrangement according to any of claims 4-5, wherein said arrangement (1) comprises a sifting device (9) adapted to sift said first predefined fraction (10), wherein a second predefined fraction (11) is separated from said first predefined fraction (10).
- Asphalt production arrangement according to claim 4, wherein said second predefined fraction (11) is less than 1 mm.
- Asphalt production arrangement according to any of claims 6-7, wherein said sifting device (9) comprises a wind sifter provided with a blowing device (12), adapted to generate a first air flow (13) which is adapted to flow through said pulverized pellets of said first predefined fraction (10) in said sifting device (9) such that said first air flow (13) forces said second predefined fraction (11) to be separated from the first predefined fraction (10).
- Asphalt production arrangement according to claim 8, wherein said wind sifter comprises cyclone separator (14) adapted to separate said second predefined fraction (11).
- Asphalt production arrangement according to any of claims 1-9, wherein said arrangement (1) comprises a dosing device (17) adapted to deliver a predetermined amount of pellets, or pulverized pellets, of a predefined fraction to said pellets combustion device (4).
- Method for heating a drier drum (2) in an asphalt production arrangement (1) according to claims 1-10, said method comprising the steps of:- providing wood or biomass, or pellets, or pulverized pellets, of wood or biomass to said heat source (3);- generating heat by combustion of said wood or biomass, or pellets, or pulverized pellets, in said heat source (3);- applying heat to drier drum (2) to heat an aggregate within said drier drum (2).
- Method according to claim 11, wherein said method further comprises the steps of:- pulverizing said pellets into a first predefined fraction (10);- burning pulverized pellets of said first predefined fraction (10).
- Method according to claim 12, wherein said method further comprises the step of:- sifting said pulverized pellets of said first predefined fraction (10), wherein pulverized pellets of a second predefined fraction (11) is separated.
- Method according to claim 13, wherein said method further comprises the step of:- burning pulverized pellets of said second predefined fraction (11);
- Method according to any of claims 11-14, wherein said method further comprises the step of:- dosing said pellets, or pulverized pellets, of said predefined fraction (10, 11), such that a predetermined amount of pellets, or pulverized pellets, of said predefined fraction (10, 11) is fed to said pellets combustion device (4).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP12174361.1A EP2679724B1 (en) | 2012-06-29 | 2012-06-29 | Asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EP12174361.1A EP2679724B1 (en) | 2012-06-29 | 2012-06-29 | Asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| EP2679724A1 true EP2679724A1 (en) | 2014-01-01 |
| EP2679724B1 EP2679724B1 (en) | 2016-03-02 |
Family
ID=46419980
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP12174361.1A Active EP2679724B1 (en) | 2012-06-29 | 2012-06-29 | Asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement |
Country Status (1)
| Country | Link |
|---|---|
| EP (1) | EP2679724B1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021075907A (en) * | 2019-11-08 | 2021-05-20 | 前田道路株式会社 | Asphalt mixture manufacturing method and asphalt plant |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2358966A1 (en) | 1976-07-19 | 1978-02-17 | Schuster Rudolf | Gravel prepn. for bituminous concrete mfr. - by dry grinding in a depression, while removing dust particles |
| US4351251A (en) * | 1981-06-29 | 1982-09-28 | Mechtron International Corp. | Combustion apparatus |
| DE4425281A1 (en) * | 1994-07-16 | 1996-01-18 | Hermann Riede Strasen Und Tief | Asphalt mfr. and processing plant |
| JP2005016200A (en) * | 2003-06-27 | 2005-01-20 | Nikko Co Ltd | Dryer of asphalt plant |
-
2012
- 2012-06-29 EP EP12174361.1A patent/EP2679724B1/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2358966A1 (en) | 1976-07-19 | 1978-02-17 | Schuster Rudolf | Gravel prepn. for bituminous concrete mfr. - by dry grinding in a depression, while removing dust particles |
| US4351251A (en) * | 1981-06-29 | 1982-09-28 | Mechtron International Corp. | Combustion apparatus |
| DE4425281A1 (en) * | 1994-07-16 | 1996-01-18 | Hermann Riede Strasen Und Tief | Asphalt mfr. and processing plant |
| JP2005016200A (en) * | 2003-06-27 | 2005-01-20 | Nikko Co Ltd | Dryer of asphalt plant |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021075907A (en) * | 2019-11-08 | 2021-05-20 | 前田道路株式会社 | Asphalt mixture manufacturing method and asphalt plant |
Also Published As
| Publication number | Publication date |
|---|---|
| EP2679724B1 (en) | 2016-03-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5645468B2 (en) | Biomass crusher and biomass / coal co-firing system | |
| US20100154296A1 (en) | Coal particles briquette where the binder is lignin and methods and systems of preparing the same | |
| US20160304800A1 (en) | Torrefaction Process | |
| JP6180218B2 (en) | Solid fuel combustion equipment | |
| JP2009102468A (en) | Fuel pellets | |
| US20130055935A1 (en) | Biomass pulverizing apparatus and biomass/coal mixed-combustion system | |
| JP5566867B2 (en) | Biomass / coal mixed combustion system and biomass / coal mixed combustion method | |
| JP5482657B2 (en) | Coal processing method and processing system | |
| JP2009291692A (en) | Biomass grinder and method of controlling this grinder | |
| JP6161242B2 (en) | Manufacturing method of mixed fuel | |
| JP5959256B2 (en) | Biomass circulation processing system for livestock manure | |
| EP2679724B1 (en) | Asphalt production arrangement and a method for heating a drier drum in an asphalt production arrangement | |
| US20120204482A1 (en) | Moisture resistant biomass fuel compact and method of manufacturing | |
| JP6243982B2 (en) | Method for producing molded product for mixed fuel | |
| JP5323024B2 (en) | Method for producing biomass mixed fuel | |
| JP5758083B2 (en) | How to use waste oil solid fuel | |
| JP6283727B2 (en) | Manufacturing method of mixed fuel | |
| JP6283724B2 (en) | Manufacturing method of mixed fuel | |
| JP6283726B2 (en) | Manufacturing method of mixed fuel | |
| JP6283723B2 (en) | Manufacturing method of mixed fuel | |
| JP6283721B2 (en) | Manufacturing method of mixed fuel | |
| JP6283722B2 (en) | Manufacturing method of mixed fuel | |
| EP4560073A1 (en) | Dryer for an industrial plant for the production of bituminous macadams | |
| SE1850718A1 (en) | Asphalt plant and method for producing asphalt pulp | |
| JP6283725B2 (en) | Method for producing molded product for mixed fuel |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| AX | Request for extension of the european patent |
Extension state: BA ME |
|
| 17P | Request for examination filed |
Effective date: 20140630 |
|
| RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| RIC1 | Information provided on ipc code assigned before grant |
Ipc: E01C 19/05 20060101AFI20150911BHEP Ipc: F26B 23/02 20060101ALI20150911BHEP Ipc: E01C 19/10 20060101ALI20150911BHEP |
|
| GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
| INTG | Intention to grant announced |
Effective date: 20151028 |
|
| GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
| REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 778160 Country of ref document: AT Kind code of ref document: T Effective date: 20160315 Ref country code: CH Ref legal event code: EP |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602012015114 Country of ref document: DE |
|
| REG | Reference to a national code |
Ref country code: SE Ref legal event code: TRGR |
|
| REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20160302 |
|
| REG | Reference to a national code |
Ref country code: NO Ref legal event code: T2 Effective date: 20160302 Ref country code: LT Ref legal event code: MG4D |
|
| REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 778160 Country of ref document: AT Kind code of ref document: T Effective date: 20160302 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160603 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160702 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160704 Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602012015114 Country of ref document: DE |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602012015114 Country of ref document: DE |
|
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
| 26N | No opposition filed |
Effective date: 20161205 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160602 |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20160629 |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20170228 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20170103 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160629 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160629 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20120629 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160629 Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 Ref country code: MT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160302 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 20250307 Year of fee payment: 14 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FI Payment date: 20250616 Year of fee payment: 14 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NO Payment date: 20250618 Year of fee payment: 14 |