EP1799919B1 - Loader comprising arm sections that have a space that runs along the arm in which tubes or cables are arranged - Google Patents
Loader comprising arm sections that have a space that runs along the arm in which tubes or cables are arranged Download PDFInfo
- Publication number
- EP1799919B1 EP1799919B1 EP05784904A EP05784904A EP1799919B1 EP 1799919 B1 EP1799919 B1 EP 1799919B1 EP 05784904 A EP05784904 A EP 05784904A EP 05784904 A EP05784904 A EP 05784904A EP 1799919 B1 EP1799919 B1 EP 1799919B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- arm
- loader
- tubes
- space
- arm section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F3/00—Dredgers; Soil-shifting machines
- E02F3/04—Dredgers; Soil-shifting machines mechanically-driven
- E02F3/28—Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
- E02F3/34—Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets with bucket-arms, i.e. a pair of arms, e.g. manufacturing processes, form, geometry, material of bucket-arms directly pivoted on the frames of tractors or self-propelled machines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F3/00—Dredgers; Soil-shifting machines
- E02F3/04—Dredgers; Soil-shifting machines mechanically-driven
- E02F3/28—Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
- E02F3/36—Component parts
- E02F3/38—Cantilever beams, i.e. booms;, e.g. manufacturing processes, forms, geometry or materials used for booms; Dipper-arms, e.g. manufacturing processes, forms, geometry or materials used for dipper-arms; Bucket-arms
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F9/00—Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
- E02F9/14—Booms only for booms with cable suspension arrangements; Cable suspensions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F9/00—Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
- E02F9/20—Drives; Control devices
- E02F9/22—Hydraulic or pneumatic drives
- E02F9/2264—Arrangements or adaptations of elements for hydraulic drives
- E02F9/2275—Hoses and supports therefor and protection therefor
Definitions
- the loader is an extended construction, an arm construction, that connects a vehicle with a tool, and that makes possible movement of the tool relative to the vehicle.
- the loader comprises two arms arranged parallel to each other, which in turn comprise extended arm sections, parallel struts, linkage systems and joints.
- the loader has at one of its ends, the end that is facing towards the vehicle, two parts, arranged parallel to each other and terminating the arms, to which cylinders and other arm parts are attached. These are known as "bearing boxes". Each bearing box is mounted onto, connects with, the vehicle.
- the document JP 11 247 216 is showing an excavator. Cables running along the excavator arm are placed in a space surrounded by covering parts and the arm. Covering parts, being C- or U-formed, are used only on the side walls of the arm and this construction makes the arm broader which will disturb the field of vision for the driver.
- One aim of the present invention is to offer a loader with a design that is such that the problems described above are solved. Tubes and cables running along the arm of the loader are to be placed fully protected and in a place where they do not interrupt the field of vision.
- FIG. 1 shows a loader 1 according to the present invention.
- the loader 1 is constituted by an extended construction, an arm construction, comprising two arms 2a and 2b arranged parallel to each other.
- Each arm 2a and 2b comprises an extended arm section 3.
- the extended arm section 3 comprises a first and a second extended arm section 3.1 and 3.2, which are connected to each other or that constitute one single unit.
- the first arm section 3.1 is directed towards or is turned towards a vehicle, not shown in the drawing, and the second arm section 3.2 is directed towards the free end of the loader.
- the two arm sections 3.1 and 3.2, their longitudinal axes L1 and L2, are placed at an angle ⁇ , which is less than 180°, relative to each other, the angle being measured in a vertical plane in the longitudinal direction of the loader.
- the loader 1, the arms 2a and 2b comprise control and regulatory units 4, for example cylinder arrangements, and connectors, for example joints.
- control and regulatory units 4 for example cylinder arrangements, and connectors, for example joints.
- the loader has on one of its sides A, the rear end that faces the vehicle, two parallel parts 6, arranged parallel and next to each other and terminating the relevant arm 2a and 2b, to which the control units 4 and the first arm section 3.1 are attached. These parts 6 are known as “bearing boxes”. Each bearing box 6 is mounted on, connects with, the vehicle.
- the loader 1 comprises also tubes and cables 9 that make possible the transport of at least one of electricity, hydraulic driving agent, pneumatic driving agent and other control and driving agents from and to the vehicle 1 to and from the various parts of the loaders and the arms and to and from the equipment at the outer end B of the loader.
- the tubes 9 are arranged within a space X along one or both of the two arms 2a and 2b.
- the tubes 9 are arranged within the arm section 3 that, for an observer standing at the tool 7 and facing the loader 1 or the vehicle, is located on the left.
- the tubes 9 can, as an alternative, be located in the arm section on the right, or in both arm sections.
- the tubes are present solely in the left arm section 3 for remainder of this description.
- the second arm section 3.2 is also designed such that it offers an open space X2, a second part of the total space, within it, in which the tubes 9 are arranged such that they are located fully protected within the arm construction also at the second arm section 3.2, inside the space X2 that is surrounded by and protected by the outer parts of the arm construction. It is appropriate that the second arm section 3.2 is constituted by a beam element with a closed cross-section. See Figure 2 .
- an extended constructional part 10 which is located transverse relative to the longitudinal axes L2 of the second arm sections, a cross-strut or a cross-tube, arranged principally between the two arms 2a and 2b of the loader 1, as shown in Figure 1 .
- the constructional part 10 connects the two arms 2a and 2b with each other and provides stability to the loader 1.
- the constructional part 10 is attached at its ends 10a and 10b to the relevant arm 2a and 2b, between the second arm parts 3.2, through welding or through another suitable attachment method.
- the constructional part 10 offers an attachment region for a valve housing 11 to which the tubes 9 are connected.
- the valve housing 11 makes it possible to connect control and regulator units 4, for the operation of the tool 7 attached to the tool attachment 8 or other parts of the loader 1.
- the tubes 9 pass through the inner spaces X1 and X2 of the arm section and out from the arm section 3, the second arm section 3.2, through an opening D in the inner wall 3a of the arm section, see Fig. 3 .
- the opening D in the arm is arranged above the constructional part 10 in a direction towards the vehicle, towards the end A of the loader, while being located at a limited distance from the constructional part 10.
- the opening D in the arm is directed towards the space behind the constructional part 10.
- the tubes 9 follow subsequently the rear side 10B of the constructional part, that side of the constructional part 10 that faces the vehicle, up to the valve housing 11.
- the opening D in the arm is provided with a lining 12, suitably of a material that is softer that the material of the arm, that covers the hard edges of the hole such that the tubes 9 are not worn when lying in contact with the edges of the opening D in the arm.
- the arm section 3 is normally manufactured from a metal material, a steel material, and it is appropriate that the linings 3.1c and 12 are manufactured from, for example, a plastic material.
- the tubes 9 are bent with a large radius of curvature and gently follow the constructional part 10 up to the valve housing 11. The number of free break-points on the tubes 9 is reduced to a minimum, and also wear of the tubes 9 is reduced.
- Figures 3 and 4 show the region around the constructional part 10.
- the constructional part 10 is bent to form a "C" or a "U” along the direction of its longitudinal extent, and it has two ends 10a and 10b and a central part 10c.
- the constructional part 10 is mounted such that the two ends 10a and 10b are connected each to an arm 2a and 2b.
- the central part 10c of the constructional part, the front of the constructional part, the convexly bent side or surface 10A, is directed towards the tool attachment 8.
- the constructional part 10 is a beam element with a closed cross-section, with open ends and with an open inner space X3, see Figure 4 .
- the valve housing 11 is principally placed behind the constructional part 10, behind the central part 10c of the constructional part, in the direction towards the vehicle, at the rear side of the constructional part, the concave side 10B. This location is safer, less exposed.
- Contacts 12 are arranged at the valve housing 11 and they make it possible to connect the tubes 9 to the valve housing 11. These contacts 12 make possible also the connection of tubes 13 that pass between the valve housing 11 and the tool 7, control and regulatory units 4, and one or several accumulators located within the inner space X3 of the constructional part.
- the contacts 12 are principally arranged on the upper surface 10C of the constructional part such that it is easy to gain access to them when making connections, such that they in this way facilitate simple, easy and rapid connection of, mainly, the tool 7 to the loader 1.
- the valve housing 11 with its spread design and construction, is principally located in line with the arms 2a and 2b and behind the constructional part 10.
- the tubes 9, which come from the vehicle, are drawn and are led through at least one of the arms 2a and 2b to the valve housing 11.
- the tubes 9 are drawn and are led in through the opening C in the first arm section 3.1, through the space X1 in one of, or in both of, the arm sections or sections 3.1, onwards through the space X2 in the second arm section 3.2 and finally out of the arm 2a, or the arms 2a and 2b, through the opening D in the arm in one of the arm sections 3, or in both of the arm sections 3, in the inner wall 3a of the arm section.
- the opening D in the arm is arranged in the direction towards the rear side 10B of the constructional part, above the constructional part 10 in the direction towards the vehicle, at the end A of the loader.
- the tubes 9 follow subsequently the concave side 10B of the constructional part, the side that faces towards the vehicle, to the valve housing 11.
- the tubes 9 are bent with a large radius of curvature and follow gently the bent shape of the constructional part to the valve housing 11.
- the number of free break-points on the tubes 9 will in this way be reduced and also wear of the tubes will be reduced.
- Coverings 14a-14c are arranged over the tubes 9 and the valve housing 11 and they cover these and parts of the constructional part 10, such that they are protected and are not freely accessible for the elements, see Figure 4 .
- the covering that is shown is divided into several parts, where each part covers a particular region.
- Two coverings 14a and 14b are arranged at each end 10a and 10b of the constructional part, over the region at which the tubes 9 come out from and go into the arm sections 3.
- a third covering 14c covers the valve housing 11 and the cables 9 and 13 that pass to and from the valve housing 11.
- the coverings 14a-14c also hold the cables 9 and 13 in place such that they do not enter the field of view of the driver or obstruct the view.
- the coverings 14a-14c protect the cables 9 and 13 and they determine their positions. It is appropriate that the coverings 14a-14c have a principally plane shape and are of a plastic material or a sheet metal material that at least can withstand the load placed on it by a person who stands on the constructional part 10, together with one or more of the coverings.
- the coverings or any one covering may also form a single cover through several coverings being connected to each other in a suitable manner.
- the covering may also be designed as a single piece or it may comprise further parts, further coverings.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Component Parts Of Construction Machinery (AREA)
- Forklifts And Lifting Vehicles (AREA)
- Harvester Elements (AREA)
- Battery Mounting, Suspending (AREA)
- Measurement Of The Respiration, Hearing Ability, Form, And Blood Characteristics Of Living Organisms (AREA)
Abstract
Description
- The present invention concerns a loader according to the introduction to claim 1.
- Vehicles, usually tractors used for various types of work, for example lifting work, are previously known. The vehicles are normally provided with a construction, for example, a base, fastening irons, brackets, or similar, on which an arm construction, usually known as a "loader" is mounted.
- The loader is an extended construction, an arm construction, that connects a vehicle with a tool, and that makes possible movement of the tool relative to the vehicle. The loader comprises two arms arranged parallel to each other, which in turn comprise extended arm sections, parallel struts, linkage systems and joints. The loader has at one of its ends, the end that is facing towards the vehicle, two parts, arranged parallel to each other and terminating the arms, to which cylinders and other arm parts are attached. These are known as "bearing boxes". Each bearing box is mounted onto, connects with, the vehicle.
- The loader has at its second end, the foremost end, the end that faces away from the vehicle, towards the working area, an attachment arrangement that makes it possible to attach equipment at the outermost end of the loader. A short distance up on or into the loader, above the tool, there is a transverse constructional part, a transverse strut or a transverse tube, arranged between the two arms of the loader. The transverse strut provides stability for the arm construction and it also offers an attachment region for a valve housing that makes it possible to connect control and regulatory units for the operation of the equipment.
- Tubes and cables that attach to equipment, a tool, that is arranged at the attachment arrangement at the outer end of the loader, for control and regulatory units on the tractor lie on the outer surface of the arms of the loader and follow these surfaces. Also connections between valve housings and tubes or cables are located outside of the loader, in the working region of the loader. The tubes, cables and connections risk becoming trapped within parts of the loader and the vehicle, and becoming trapped in objects within the working space of the loader. The tubes, cables and connections tend to become covered with snow and dirt, which creates unsatisfactory hygienic conditions, increases wear and places limitations on the movements of the loader. The tubes, cables and connections also obstruct the view of the driver.
- There is known a loader from the
US having the tubes and cables placed inside the usual arm. This is taking the tubes and cables away from the driver's field of vision but is not giving a full protection for the tubes or cables regarding snow and dirt.patent 5 232 330 - The document
is showing an excavator. Cables running along the excavator arm are placed in a space surrounded by covering parts and the arm. Covering parts, being C- or U-formed, are used only on the side walls of the arm and this construction makes the arm broader which will disturb the field of vision for the driver.JP 11 247 216 - One aim of the present invention is to offer a loader with a design that is such that the problems described above are solved. Tubes and cables running along the arm of the loader are to be placed fully protected and in a place where they do not interrupt the field of vision.
- This aim is achieved with a loader comprising the technical properties that are specified in the characterising part of claim 1.
- The invention will be described in more detail below, with reference to the drawings.
-
Figure 1 shows a loader according to the present invention. -
Figure 2 shows a first arm section and, partially, a second arm section on a loader according to the invention. -
Figure 3 shows a second arm section and a transversely placed constructional part on a loader according to the invention. -
Figure 4 shows a transversely placed constructional part on a loader according to the invention. -
Figure 1 shows a loader 1 according to the present invention. The loader 1 is constituted by an extended construction, an arm construction, comprising two 2a and 2b arranged parallel to each other. Eacharms 2a and 2b comprises anarm extended arm section 3. Theextended arm section 3 comprises a first and a second extended arm section 3.1 and 3.2, which are connected to each other or that constitute one single unit. The first arm section 3.1 is directed towards or is turned towards a vehicle, not shown in the drawing, and the second arm section 3.2 is directed towards the free end of the loader. The two arm sections 3.1 and 3.2, their longitudinal axes L1 and L2, are placed at an angle α, which is less than 180°, relative to each other, the angle being measured in a vertical plane in the longitudinal direction of the loader. - The loader 1, the
2a and 2b, comprise control andarms regulatory units 4, for example cylinder arrangements, and connectors, for example joints. The parts that are present at several locations of the loader, on both arms, and that have the same design have been given the same reference numerals. - The loader has on one of its sides A, the rear end that faces the vehicle, two
parallel parts 6, arranged parallel and next to each other and terminating the 2a and 2b, to which therelevant arm control units 4 and the first arm section 3.1 are attached. Theseparts 6 are known as "bearing boxes". Eachbearing box 6 is mounted on, connects with, the vehicle. - Each first arm section 3.1 extends essentially between the
bearing box 6 and aconnector 5 at each 2a and 2b.arm - Each second arm section 3.2 extends between the
connector 5 and a second end B, the free end, the forwards end, of the loader that faces away from the loader with equipment or a tool 7 attached to the loader 1. Anattachment arrangement 8 that makes it possible to attach the equipment 7 to the loader 1 is arranged at the forwards end B of the loader 1. - The loader 1 comprises also tubes and
cables 9 that make possible the transport of at least one of electricity, hydraulic driving agent, pneumatic driving agent and other control and driving agents from and to the vehicle 1 to and from the various parts of the loaders and the arms and to and from the equipment at the outer end B of the loader. Thetubes 9 are arranged within a space X along one or both of the two 2a and 2b.arms - The
tubes 9 are located within one of thearm sections 3, inside both the first arm section 3.1 and the second arm section 3.2, as shown inFigure 2 . Thetubes 9 in this way lie completely protected and there is no risk that they become trapped in any type of object that is in the vicinity of the loader 1 during its work. Furthermore, there is now no longer space, or any surfaces, on which dirt or snow can become attached, nor can it fall between thetubes 9 and the 2a and 2b, thearms arm section 3. - The
tubes 9 are arranged within thearm section 3 that, for an observer standing at the tool 7 and facing the loader 1 or the vehicle, is located on the left. Thetubes 9 can, as an alternative, be located in the arm section on the right, or in both arm sections. The tubes are present solely in theleft arm section 3 for remainder of this description. - The first arm section 3.1 is so constructed that it offers a space X1 that constitutes a first part of the complete space, inside the arm section, in which the
tubes 9 are located and where they are completely protected. The space X1 is created in that a beam element 3.1a, appropriately a "U" beam in order not to provide the loader 1 with unnecessary weight, is welded attached to the normal arm section 3.1, at its lower side 3.1 b. An opening C is located at the end A of the arm section that faces the vehicle, through whichtubes 9 enter the space X1, when seen in the direction facing out from the vehicle. The opening C in the arm section is provided with a lining 3.1c of a material that is softer than the material of the arm section in order to protect thetubes 9 when making contact with the edge of the opening. SeeFigure 2 . - The second arm section 3.2 is also designed such that it offers an open space X2, a second part of the total space, within it, in which the
tubes 9 are arranged such that they are located fully protected within the arm construction also at the second arm section 3.2, inside the space X2 that is surrounded by and protected by the outer parts of the arm construction. It is appropriate that the second arm section 3.2 is constituted by a beam element with a closed cross-section. SeeFigure 2 . - Above the
tool attachment 8 there is located an extended constructional part 10, which is located transverse relative to the longitudinal axes L2 of the second arm sections, a cross-strut or a cross-tube, arranged principally between the two 2a and 2b of the loader 1, as shown inarms Figure 1 . The constructional part 10 connects the two 2a and 2b with each other and provides stability to the loader 1. The constructional part 10 is attached at itsarms 10a and 10b to theends 2a and 2b, between the second arm parts 3.2, through welding or through another suitable attachment method.relevant arm - The constructional part 10 offers an attachment region for a
valve housing 11 to which thetubes 9 are connected. Thevalve housing 11 makes it possible to connect control andregulator units 4, for the operation of the tool 7 attached to thetool attachment 8 or other parts of the loader 1. - The
tubes 9 pass through the inner spaces X1 and X2 of the arm section and out from thearm section 3, the second arm section 3.2, through an opening D in theinner wall 3a of the arm section, seeFig. 3 . The opening D in the arm is arranged above the constructional part 10 in a direction towards the vehicle, towards the end A of the loader, while being located at a limited distance from the constructional part 10. The opening D in the arm is directed towards the space behind the constructional part 10. Thetubes 9 follow subsequently therear side 10B of the constructional part, that side of the constructional part 10 that faces the vehicle, up to thevalve housing 11. The opening D in the arm is provided with alining 12, suitably of a material that is softer that the material of the arm, that covers the hard edges of the hole such that thetubes 9 are not worn when lying in contact with the edges of the opening D in the arm. - The
arm section 3 is normally manufactured from a metal material, a steel material, and it is appropriate that the linings 3.1c and 12 are manufactured from, for example, a plastic material. - The
tubes 9 are bent with a large radius of curvature and gently follow the constructional part 10 up to thevalve housing 11. The number of free break-points on thetubes 9 is reduced to a minimum, and also wear of thetubes 9 is reduced. -
Figures 3 and4 show the region around the constructional part 10. The constructional part 10 is bent to form a "C" or a "U" along the direction of its longitudinal extent, and it has two 10a and 10b and a central part 10c.The constructional part 10 is mounted such that the twoends 10a and 10b are connected each to anends 2a and 2b. Thearm central part 10c of the constructional part, the front of the constructional part, the convexly bent side orsurface 10A, is directed towards thetool attachment 8. The constructional part 10 is a beam element with a closed cross-section, with open ends and with an open inner space X3, seeFigure 4 . - The
valve housing 11 is principally placed behind the constructional part 10, behind thecentral part 10c of the constructional part, in the direction towards the vehicle, at the rear side of the constructional part, theconcave side 10B. This location is safer, less exposed.Contacts 12 are arranged at thevalve housing 11 and they make it possible to connect thetubes 9 to thevalve housing 11. Thesecontacts 12 make possible also the connection oftubes 13 that pass between thevalve housing 11 and the tool 7, control andregulatory units 4, and one or several accumulators located within the inner space X3 of the constructional part. (The accumulators are not shown in the drawings since these are not a part of the invention.) Thecontacts 12 are principally arranged on theupper surface 10C of the constructional part such that it is easy to gain access to them when making connections, such that they in this way facilitate simple, easy and rapid connection of, mainly, the tool 7 to the loader 1. - The
valve housing 11, with its spread design and construction, is principally located in line with the 2a and 2b and behind the constructional part 10.arms - The
tubes 9, which come from the vehicle, are drawn and are led through at least one of the 2a and 2b to thearms valve housing 11. Thetubes 9 are drawn and are led in through the opening C in the first arm section 3.1, through the space X1 in one of, or in both of, the arm sections or sections 3.1, onwards through the space X2 in the second arm section 3.2 and finally out of thearm 2a, or the 2a and 2b, through the opening D in the arm in one of thearms arm sections 3, or in both of thearm sections 3, in theinner wall 3a of the arm section. The opening D in the arm is arranged in the direction towards therear side 10B of the constructional part, above the constructional part 10 in the direction towards the vehicle, at the end A of the loader. - The
tubes 9 follow subsequently theconcave side 10B of the constructional part, the side that faces towards the vehicle, to thevalve housing 11. Thetubes 9 are bent with a large radius of curvature and follow gently the bent shape of the constructional part to thevalve housing 11. The number of free break-points on thetubes 9 will in this way be reduced and also wear of the tubes will be reduced. Also thetubes 13 that lead onwards away from or towards thevalve housing 11 either to or from the tool 7, or to or from the control andregulatory units 4, follow the concaverear surface 10B of the constructional part as much as is possible. -
Coverings 14a-14c are arranged over thetubes 9 and thevalve housing 11 and they cover these and parts of the constructional part 10, such that they are protected and are not freely accessible for the elements, seeFigure 4 . The covering that is shown is divided into several parts, where each part covers a particular region. Two 14a and 14b are arranged at eachcoverings 10a and 10b of the constructional part, over the region at which theend tubes 9 come out from and go into thearm sections 3. Athird covering 14c covers thevalve housing 11 and the 9 and 13 that pass to and from thecables valve housing 11. Thecoverings 14a-14c also hold the 9 and 13 in place such that they do not enter the field of view of the driver or obstruct the view.cables - The
coverings 14a-14c protect the 9 and 13 and they determine their positions. It is appropriate that thecables coverings 14a-14c have a principally plane shape and are of a plastic material or a sheet metal material that at least can withstand the load placed on it by a person who stands on the constructional part 10, together with one or more of the coverings. The coverings or any one covering may also form a single cover through several coverings being connected to each other in a suitable manner. The covering may also be designed as a single piece or it may comprise further parts, further coverings. - This description is not to be seen as a limitation of the invention. It is to be seen as a guide to full understanding of the invention in all of its parts. It should be realised that other designs are also possible than those that have been described above and shown in the drawings, and parts are possible within the framework of the innovative concept specified in the attached claims.
Claims (9)
- A loader (1) comprising two extended arms (2a, 2b) arranged parallel to each other, one end (A) of which can be connected to a vehicle and the other end (B) of which can be connected to a tool (7), where at least one arm (2a) comprises a space (X1, X2) that runs along the arm in which tubes or cables (9) are arranged that make it possible to transport at least one of electricity, hydraulic agent and pneumatic agent, from the vehicle to the various parts (4, 11) of the loader or the tool (7) and from the various parts (4, 11) of the loader or the tool (7) to the vehicle and where the arm (2a) comprises a first arm section (3.1) offering a first part (X1) of the space in which the tubes or cables (9) are arranged and that the first space part (X1) is formed by the first arm section (3.1) and a beam element (3.1 a) attached to each other, characterised in that the beam element (3.1a) is in contact with the lower surface (3. 1 b) of the first arm section (3.1) and that the beam element (3.1 a) has an open cross-section, essentially the shape of a "C" or a "U", such that the space (X1) is surrounded by, and is limited by, the beam element (3.1 a) and the first arm section (3.1).
- The loader according to claim 1 in which the space (X1, X2) is arranged inside of the arm (2a, 2b).
- The loader according to claim 1 or 2 in which a second arm section (3.2) offers a second part (X2) of the space in which the tubes (9) are arranged.
- The loader according to claim 3 in which the second arm section (3.2) comprises a beam element that forms the second part (X2) of the space.
- The loader according to claim 4 in which the second arm section (3.2) comprises a beam element with a closed cross-section.
- The loader according to any one of claims 1-5 in which an extended constructional part (10) is arranged between the two arms (2a, 2b) and connects the two arms (2a, 2b) to each other and provides stability to the loader (1) and where a valve housing (11) is arranged at the constructional part (10) to which the tubes (9), after coming out from the arm (2a, 2b), are connected.
- The loader according to claim 6 in which the tubes (9) pass out from the arms (2a, 2b) through an opening (D) directed towards the space (10B) behind the constructional part.
- The loader according to claim 7 in which the tubes (9) follow the rear surface (10B) of the constructional part to the valve housing (11).
- The loader according to any one of claims 6-8 in which at least one covering (14a-14c) is arranged over the tubes (9), parts of the constructional part (10) and the valve housing (11).
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SE0402365A SE531215C2 (en) | 2004-09-29 | 2004-09-29 | Loader comprising two arm parts provided with a space in which hoses / lines are drawn |
| PCT/SE2005/001371 WO2006036104A1 (en) | 2004-09-29 | 2005-09-20 | Loader comprising arm sections that have a space that runs along the arm in which tubes or cables are arranged |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| EP1799919A1 EP1799919A1 (en) | 2007-06-27 |
| EP1799919B1 true EP1799919B1 (en) | 2010-08-11 |
Family
ID=33414866
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP05784904A Expired - Lifetime EP1799919B1 (en) | 2004-09-29 | 2005-09-20 | Loader comprising arm sections that have a space that runs along the arm in which tubes or cables are arranged |
Country Status (8)
| Country | Link |
|---|---|
| US (1) | US20080063502A1 (en) |
| EP (1) | EP1799919B1 (en) |
| AT (1) | ATE477377T1 (en) |
| AU (1) | AU2005287952B2 (en) |
| CA (1) | CA2581972C (en) |
| DE (1) | DE602005022898D1 (en) |
| SE (1) | SE531215C2 (en) |
| WO (1) | WO2006036104A1 (en) |
Families Citing this family (24)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2448312B (en) * | 2007-04-10 | 2010-11-10 | Agco Gmbh | Loader attachment having at least two parallel arms |
| EP2152975A4 (en) * | 2007-05-08 | 2012-01-18 | Challenge Implements Holdings Pty Ltd | Hose entry system |
| AU321299S (en) * | 2007-09-28 | 2008-10-01 | Challenge Implements Holdings Pty Ltd | Front end loader |
| USD595746S1 (en) * | 2008-09-19 | 2009-07-07 | Yanmar Co., Ltd. | Front loader |
| US8047760B2 (en) | 2008-10-15 | 2011-11-01 | Clark Equipment Company | Integral power or electrical conduit coupler |
| USD610172S1 (en) | 2009-06-22 | 2010-02-16 | Yanmar Co., Ltd. | Front loader |
| USD629019S1 (en) * | 2009-09-17 | 2010-12-14 | J.C. Bamford Excavators Limited | Excavator arm |
| USD628604S1 (en) * | 2009-09-17 | 2010-12-07 | J.C. Bamford Excavators Limited | Loader arms |
| USD672373S1 (en) | 2011-01-10 | 2012-12-11 | Alo Aktiebolag | Front loader for a tractor |
| USD649171S1 (en) * | 2011-01-24 | 2011-11-22 | Alcar S.R.L. | Tractor arm |
| USD649170S1 (en) * | 2011-01-24 | 2011-11-22 | Alcar S.R.L. | Tractor arm |
| US8666609B2 (en) * | 2011-01-31 | 2014-03-04 | Yanmar Co., Ltd. | Work vehicle |
| USD656523S1 (en) * | 2011-07-07 | 2012-03-27 | Alo Aktiebolag | Front loader assembly |
| USD739446S1 (en) | 2011-07-08 | 2015-09-22 | Alo Aktiebolag | Front loader for a tractor |
| USD769335S1 (en) * | 2014-04-16 | 2016-10-18 | Deere & Company | Frontloader |
| USD768731S1 (en) * | 2014-04-16 | 2016-10-11 | Deere & Company | Frontloader |
| CA160237S (en) * | 2014-06-23 | 2016-01-27 | Deere & Co | Frontloader |
| USD777801S1 (en) * | 2014-09-26 | 2017-01-31 | Kubota Corporation | Air conditioning duct for construction equipment |
| USD766343S1 (en) * | 2015-05-20 | 2016-09-13 | Deere & Company | Front end final loader |
| JP1547702S (en) * | 2015-10-19 | 2016-04-11 | ||
| USD807407S1 (en) * | 2016-10-28 | 2018-01-09 | Kubota Corporation | Bucket work machine for a loader |
| USD943641S1 (en) * | 2020-01-23 | 2022-02-15 | Deere & Company | Loader arms |
| USD923062S1 (en) * | 2020-02-20 | 2021-06-22 | Hankuk Chain Industrial Co., Ltd. | Front end loader of tractor |
| USD983842S1 (en) * | 2021-05-17 | 2023-04-18 | George Hunter | Protective cover accessory for excavator arm |
Family Cites Families (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2782946A (en) * | 1954-07-22 | 1957-02-26 | Hough Co Frank | Power loaders |
| US2961106A (en) * | 1956-02-01 | 1960-11-22 | Davis Engineering Inc | Hydraulically operated mobile digging machine |
| US4050596A (en) * | 1975-07-24 | 1977-09-27 | Control Concepts, Inc. | Electrohydraulic valve assembly for front end loader attachment to farm tractor |
| JPH0726415B2 (en) * | 1989-12-13 | 1995-03-22 | 株式会社クボタ | Work implement boom assembly |
| US5232330A (en) * | 1992-06-29 | 1993-08-03 | Deere & Company | Structure for mounting hydraulic hoses for a power loader |
| US5533856A (en) * | 1995-05-22 | 1996-07-09 | Deere & Company | Combined loaded self-leveling and implement tilt linkages for effecting true level and enhanced roll back and dump characteristics throughout lift range of loader |
| JP2938373B2 (en) * | 1995-09-06 | 1999-08-23 | 住友建機株式会社 | Hydraulic piping in excavator |
| US6171050B1 (en) * | 1997-08-29 | 2001-01-09 | Gehl Company | Load arm assembly for a skid steer loader |
| JP3794004B2 (en) | 1998-03-04 | 2006-07-05 | 株式会社小松製作所 | Construction machine working machine |
| US6758024B1 (en) * | 1999-11-24 | 2004-07-06 | Liebherr-Hydraulikbagger Gmbh | Industrial shaft, particularly for packaging equipment |
| JP3822133B2 (en) * | 2002-05-09 | 2006-09-13 | 株式会社クボタ | Hydraulic piping structure of swing work machine |
| US6994511B2 (en) * | 2003-11-21 | 2006-02-07 | Westendorf Manufacturing Co., Inc. | Loader assembly, combination motor vehicle and loader assembly, hydraulic cylinders and methods for operating a loader assembly |
-
2004
- 2004-09-29 SE SE0402365A patent/SE531215C2/en not_active IP Right Cessation
-
2005
- 2005-09-20 CA CA2581972A patent/CA2581972C/en not_active Expired - Lifetime
- 2005-09-20 AU AU2005287952A patent/AU2005287952B2/en not_active Ceased
- 2005-09-20 EP EP05784904A patent/EP1799919B1/en not_active Expired - Lifetime
- 2005-09-20 DE DE602005022898T patent/DE602005022898D1/en not_active Expired - Lifetime
- 2005-09-20 AT AT05784904T patent/ATE477377T1/en not_active IP Right Cessation
- 2005-09-20 US US11/664,169 patent/US20080063502A1/en not_active Abandoned
- 2005-09-20 WO PCT/SE2005/001371 patent/WO2006036104A1/en not_active Ceased
Also Published As
| Publication number | Publication date |
|---|---|
| WO2006036104A1 (en) | 2006-04-06 |
| US20080063502A1 (en) | 2008-03-13 |
| CA2581972C (en) | 2011-08-30 |
| AU2005287952B2 (en) | 2011-01-06 |
| SE0402365L (en) | 2006-03-30 |
| SE0402365D0 (en) | 2004-09-29 |
| AU2005287952A1 (en) | 2006-04-06 |
| EP1799919A1 (en) | 2007-06-27 |
| SE531215C2 (en) | 2009-01-20 |
| DE602005022898D1 (en) | 2010-09-23 |
| ATE477377T1 (en) | 2010-08-15 |
| CA2581972A1 (en) | 2006-04-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP1799919B1 (en) | Loader comprising arm sections that have a space that runs along the arm in which tubes or cables are arranged | |
| SE0402365A1 (en) | Loader comprising two arm parts provided with a space in which hoses / wires are drawn | |
| US6854951B2 (en) | Vertical lift type arm device | |
| US4991659A (en) | Ripper assembly with pitch control and integral frame and push block | |
| AU2008247328C1 (en) | Hose entry system | |
| EP2631372B1 (en) | Construction machine cab having a rollover protection structure | |
| CA2581974C (en) | Loader comprising arm section and parallel struts with an open cross section | |
| KR20050004032A (en) | Construction machine | |
| US4087009A (en) | Backhoe frame | |
| US7419186B2 (en) | Working machine | |
| US7442001B2 (en) | Boom assembly | |
| JPWO2005003468A1 (en) | Construction machinery and its protrusions | |
| EP1775393A1 (en) | Protective structure for a cabin of a workmachine | |
| JP6581160B2 (en) | Construction machinery cab structure | |
| US20160060841A1 (en) | Bucket for work vehicle, and work vehicle equipped with bucket | |
| CN114250813B (en) | Working device of skid-steer loader and skid-steer loader | |
| EP2868813B1 (en) | Construction machine with pilot hoses | |
| CN114382117B (en) | Working device of skid-steer loader and skid-steer loader | |
| US11718971B2 (en) | Excavator arm | |
| JP4596982B2 (en) | Construction machinery cab | |
| JP4278581B2 (en) | Tractor front guard | |
| JP3443282B2 (en) | Hydraulic excavator upper frame | |
| JPH0514250U (en) | Construction machinery tube guard | |
| KR20180110079A (en) | Box-like structure for working machine | |
| JP3296655B2 (en) | Mounting structure of hydraulic piping to bucket cylinder in telescopic arm |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| 17P | Request for examination filed |
Effective date: 20070420 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR |
|
| DAX | Request for extension of the european patent (deleted) | ||
| RIC1 | Information provided on ipc code assigned before grant |
Ipc: E02F 9/14 20060101ALI20090404BHEP Ipc: E02F 3/38 20060101ALI20090404BHEP Ipc: E02F 3/34 20060101AFI20090404BHEP |
|
| 17Q | First examination report despatched |
Effective date: 20090916 |
|
| GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
| GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
| REF | Corresponds to: |
Ref document number: 602005022898 Country of ref document: DE Date of ref document: 20100923 Kind code of ref document: P |
|
| REG | Reference to a national code |
Ref country code: NL Ref legal event code: VDEP Effective date: 20100811 |
|
| LTIE | Lt: invalidation of european patent or patent extension |
Effective date: 20100811 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101211 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101111 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101213 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101112 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20100930 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 |
|
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101122 |
|
| 26N | No opposition filed |
Effective date: 20110512 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20100920 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602005022898 Country of ref document: DE Effective date: 20110512 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20110212 Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20100920 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20100811 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 11 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 12 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 13 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 14 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20220804 Year of fee payment: 18 Ref country code: DE Payment date: 20220805 Year of fee payment: 18 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20220817 Year of fee payment: 18 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20221001 Year of fee payment: 18 |
|
| P01 | Opt-out of the competence of the unified patent court (upc) registered |
Effective date: 20230525 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602005022898 Country of ref document: DE |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20230920 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230920 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230930 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230920 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230930 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20240403 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230930 |