[go: up one dir, main page]

EP1022386A2 - Procédé de fixation d'une voie de chemin de fer sur des dalles porteuses ainsi qu'un appareil et coffrage pour la mise en oeuvre de ce procédé - Google Patents

Procédé de fixation d'une voie de chemin de fer sur des dalles porteuses ainsi qu'un appareil et coffrage pour la mise en oeuvre de ce procédé Download PDF

Info

Publication number
EP1022386A2
EP1022386A2 EP19990122720 EP99122720A EP1022386A2 EP 1022386 A2 EP1022386 A2 EP 1022386A2 EP 19990122720 EP19990122720 EP 19990122720 EP 99122720 A EP99122720 A EP 99122720A EP 1022386 A2 EP1022386 A2 EP 1022386A2
Authority
EP
European Patent Office
Prior art keywords
sleepers
track
under
mass
threshold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP19990122720
Other languages
German (de)
English (en)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bahnbau Wels GmbH
Original Assignee
Bahnbau Wels GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bahnbau Wels GmbH filed Critical Bahnbau Wels GmbH
Publication of EP1022386A2 publication Critical patent/EP1022386A2/fr
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B37/00Making, maintaining, renewing, or taking-up the ballastway or the track, not provided for in a single one of groups E01B27/00 - E01B35/00
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • E01B1/004Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/003Arrangement of tracks on bridges or in tunnels
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/005Making of concrete parts of the track in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails

Definitions

  • the invention relates to a method for installing a Rails and sleepers of existing track on support plates one fixed carriageway, the track initially with vertical and horizontal Adjustment means aligned vertically and horizontally and is supported on support means.
  • the invention further relates to a formwork and a conveying and installation device for feeding and installing one flowable, hardening stabilizing compound under the sleepers of a track on a solid track.
  • the track In the case of railroad tracks for railroad trains running at very high speed run, the track is on as a solid carriageway Base plates laid out of concrete or asphalt, with the sleepers of the track embedded in a filling concrete almost up to its upper edge and be firmly connected to the support plates. To one To achieve rapid construction progress, it is advisable to stop Prefabricate rails and sleepers and existing track grate the track with relatively large rail lengths on the Lay support plates and align them horizontally and vertically. Then the filling concrete between the sleepers and inserted the support plates, which is the final and permanent Connects between the track and the underground.
  • the object of the invention is to avoid these disadvantages and to design a method of the type explained in more detail above, that large rail lengths can be installed and a quicker Construction progress is achieved without position corrections during installation of the aligned track are required.
  • Thresholds after alignment by at least partially underfilling be stabilized with a hardening stabilizing compound, that then after the stabilizing compound has hardened sufficiently the rails on the sleepers loosened and only after the final and permanent attachment of the sleepers to the Carrier plates of the solid carriageway are fixed again with the sleepers get connected.
  • This configuration has the advantage that changes in length of the Rails due to changing temperature influences during installation the correct position of the aligned sleepers no longer can influence, since the rails after loosening the Rail fasteners on the sleepers in the longitudinal direction of the rail can move. Because to underfill the thresholds only small amounts of stabilizing compound are required the underfilling and stabilization of the sleepers is very quick. A very quickly hardening stabilizing compound is also useful used, which is sustainable after a short time and driving on the track just laid with transport and Installation equipment or a track laying and leveling machine allowed.
  • the adjusting means can also be used and / or the support means removed and at another Body can be reused.
  • pourable asphalt or Cement concrete used, which contains early high-strength binders.
  • the stabilizing compound can be applied to the whole of the sleepers Length can be arranged. As a rule, however, it is sufficient if the stabilizing mass under the sleepers is only of limited length is placed under the bearing points of the rails.
  • the thresholds are not subjected to bending when the track driven by a heavy track laying and leveling machine as is the case with single-track tunnel sections, for example the case is.
  • the stabilizing compound not only supports the thresholds from below, but also on their faces, so that the sleepers also against lateral displacement are secured.
  • the filling concrete that is introduced later must also fill the gap between the underside of the sleeper and the bottom of the support plates Fill in so that the thresholds are fully supported. Because this filling concrete may be introduced much later as the stabilizing compound, it is already hardened, before the filling concrete hardens and reaches its final shrinkage. It can then happen that individual thresholds in the finished condition only at their ends over the stabilizing compound Support on the support plates, but in their middle area lying hollow. To avoid this, a special suggestion goes the invention, under the ends of the sleepers in the area limited length in which the stabilizing mass is introduced will arrange a setting strip of compressible material its thickness is the shrinkage of the later under the threshold attached filling concrete corresponds.
  • This setting strip can from a glued or concreted on the underside of the threshold
  • Non-woven strips of plastic or textile material exist, which compresses under load, so that then the threshold along its entire length on the hardened and under certain circumstances, filler concrete that has become a little thinner.
  • the stabilizing mass is useful with a transport and Installation device supplied and installed on the laid Track moves along its alignment.
  • This promotion and Installation device consists of a train with light wagons, which storage containers for the stabilizing mass or its raw materials, an agitator or a mixer and the built-in devices for the masses and those of a small tractor, for example, a trolley moved in the longitudinal direction of the track become.
  • the tractor can also have an energy generator be equipped to drive the agitator or of the mixer and a pump or an injection unit for the To supply stabilizing mass with energy.
  • a lost formwork is provided, which in a Embodiment of a sack made of one for hardening Mass partially permeable material is formed.
  • the sack can from a coarse-mesh fabric, a fleece or a perforated Foil exist.
  • This sack is with an injection hose or an injection lance with which this can be connected Sack filled with the hardening mass from the mixer or agitator after being in the space between the Underside of the threshold to be stabilized and the Support plate was arranged.
  • the one filled in the sack with overpressure Stabilizing compound not only fills the sack, but also also partially emerges between the stitches of the fabric or the perforation of the film and also forms on the outside of the sack a layer consisting of the stabilizing mass, the combines well with the filling concrete to be introduced later, the is expediently produced on the same basis as the stabilizing compound, i.e. if the stabilizing mass is made of a cement concrete consists, the filling concrete is also a cement concrete. Will be against Asphalt concrete used as filling concrete is used as a stabilizing compound a bitumen-bound stabilizing compound is also useful.
  • the formwork is lost for installing a flowable, hardening mass under the Sleeper of a track on the supporting plates of a solid carriageway according to the invention from a formwork frame with side walls Made of expanded metal, which fits between the support plate and the threshold and over at least one side surface or a top surface of the Threshold protrudes.
  • Expanded metal walls can partially fill the stabilizing compound penetrate through the walls and get on well with the Interlock and connect the filling compound to be filled in later, so that Stabilizing compound and filling concrete in the final, hardened state form a monolithic body in which the thresholds of the track are firmly anchored.
  • the formwork frame can have two side walls and at least one Have front wall.
  • One end wall fills the distance at least approximately between the threshold and the support plate.
  • this first end wall expediently has a curved one Tab that lies under the threshold and thereby the Formwork frame stabilized at the head end of the threshold.
  • the sidewalls and, if necessary, a second end wall, which the formwork frame closes at the rear and also expediently made of expanded metal are higher than those below the threshold End wall of the formwork frame.
  • the to the top of the side walls filled stabilizing compound not only underfills the threshold at their ends, but also trims them at theirs End faces, so that these sleepers against side shift are secured.
  • 10 is a fixed track for a track 11, which consists essentially of prefabricated support plates 12 consists of reinforced concrete, which is on a hydraulically bound Base layer 13 are laid, which is the substructure of the railway line forms.
  • support plates 12 have a U-shaped cross section with laterally towering sidewalls 14.
  • the support plates could also formed by flat plates without sidewalls made of asphalt or concrete become.
  • the track 11 is made of concrete sleepers 15 and formed by rails 16 with fasteners 17, e.g. with sleeper screws on the sleepers 15 are releasably attached.
  • the track 11 is preassembled and in great lengths with a track installation machine in the laid from the support plates 12 formed trough.
  • the track is horizontal and vertical aligned and supported on the bottom 19 of the support plates 12.
  • FIG. 1 The alignment and support is shown in FIG. 1 in the area PH2. It is done either with the help of a track 11 moving track straightener, or as shown in Fig. 3, manually with individual straightening and supporting devices, such as Vertical spindles 19, the vertical holes 20 in the sleepers 15 penetrate and rest on the bottom 18 of the support plates 15 and with horizontal adjusting means 21 with which the Thresholds can be set in the horizontal direction.
  • This horizontal adjustment means 21 are also screw spindles, which engage in threaded sleeves 22, which in the head surfaces 23rd the thresholds are arranged. Support with the other end the horizontal screw spindles 21 on the side cheeks 14 the support plates 12 from.
  • This proppant 27 can be the vertical spindles 19 with which the Thresholds 15 have already been aligned in their altitude.
  • the support means however, special support spindles between the sleepers can be arranged directly under the rails. Instead of the support spindles can also support frames made of concrete, hydraulic rams or other height-adjustable supports are used become.
  • This construction phase is shown in FIG. 1 in the area PH3.
  • the lost formwork is the one shown in FIGS. 1 and 2 Embodiment bags 24 from a coarse-mesh Fabric, a fleece or a perforated film. you will be from a transport and installation device 25 with a hardening stabilizing mass 26 filled, as in the area PH4 is shown in Fig. 1.
  • this stabilizing compound 26 is a mastic asphalt or a flowable cement concrete, which is preferably a early high strength cement is added as a binder, so that the Stabilizing compound 26 soon after it is filled into the sacks 24 hardened.
  • the stabilizing mass 26 is using an injection lance or an injection hose 28 with excess pressure in the bag formwork 24 filled. This allows the air from the Bags 24 escape and after the bags are completely filled 14 can some stabilizing mass through the mesh or perforation of the sack to the outside and harden there. At the Subsequent pouring of the filling concrete connects it then with the outward stabilizing material and it gives a good interlock between the two materials.
  • Fig. 1 shown in phase PH4.
  • the stabilizing compound 26 has hardened to the extent that it Load of the track and the transport and installation equipment traveling over it can be transferred to the support plates 12 the fasteners 17 of the rails 16 solved so far that the rails 16 in their longitudinal direction on the concrete sleepers 15 can move and no longer transmit longitudinal forces, if they lengthen due to the effects of temperature or shorten it.
  • the vertical spindles can also be used 19, the horizontal adjustment means 21 or other support means be removed. This process section is in the area in FIG. 1 PH5 shown.
  • Fig.1 Installation device 25 consists of a train light wagons 29 and 30 by a small tractor 31, for example a draisine in the installation direction 32 over the just laid track 11 are pulled.
  • the carriage 29 carries a reservoir 33 for the stabilizing mass or its Starting materials, for example a mixture of dry additives and cement fed into a conveyor via a conveyor 34 Mixer 35 are given, together with a water tank 36 is arranged on the second carriage 30 and with the addition of Water creates the flowable stabilizing mass, which then filled into the formwork 24 through the injection hose 28 becomes.
  • Fig. 4 is the Formwork frame 38 slightly larger than the base of the threshold 15 so that it over the side surfaces 43 and the top surfaces 23rd the threshold 15 protrudes.
  • the formwork frame 38 can thereby can be easily filled from above, using the stabilizing compound 26 also somewhat over the side surfaces 43 and the top surfaces 23 climb the threshold 15 and this at the bottom also sideways may include (Fig. 4).
  • two formwork frames 38 are arranged under the sleepers 15, each of which has only a limited length l 1 and which are arranged under the sleepers 15 in the region of the rails 16.
  • the end walls 41 and 42 and a side wall 40 of these formwork frames are not higher than the distance a between the underside of a threshold 15 and the bottom 18 of the support plates 12 after the thresholds have been aligned.
  • these formwork frames fit between the support plate 12 and the threshold 15 and can be pushed from the side under the vertically aligned thresholds.
  • the second side wall 39 protrudes beyond the side surface of the threshold 15 and can also protrude somewhat beyond the lower edge thereof in order to facilitate filling with the stabilizing compound 26.
  • formwork frames 38 are arranged only at the threshold ends 44 and only reach under them in a narrow area of limited length l 2 .
  • the filled stabilizing mass 26 therefore fills the distance a between the bottom 18 of the trough and the underside 52 of the threshold only in the region of limited length l 2 .
  • a set strip 51 made of a nonwoven fabric is arranged under the ends 44 of the sleepers 15 in the areas of limited length l 2 , the thickness d of which corresponds at least to the shrinkage of the filler concrete 37 which is later installed under the threshold 15.
  • This setting strip 51 can be placed in the formwork in the formwork and concreted onto the threshold during the manufacture of the concrete sleeper, but it is also possible to glue these setting strips 51 under the finished sleepers 15.
  • the formwork frames 38 have two side walls 39 and 40 and an end wall 45 made of expanded metal.
  • the end wall 45 fills the distance a between the threshold 15 and the support plate 12 and has at its upper edge 46 a bent tab 47, which is made in one piece with the end wall 45 and lies under the threshold when the formwork frame is installed.
  • the side walls 39 and 40 of the formwork frames 38 extend to the inner surfaces 48 of the side cheeks 14 of the support plates 12 and are connected to one another at their lower corners 49 by a spar 50. If the support plates 12 have no side walls 14, the formwork frame 38 is also provided on its rear side with a second end wall made of expanded metal.
  • the formwork frames can easily be made of expanded metal and, at their relatively low height, are also sufficiently stable to absorb the liquid pressure of the stabilizing composition filled. With a suitable consistency, this can partially pass through between the ribs of the expanded metal walls and also harden on the outer sides of the formwork frames and form a rough surface there, which interlocks with the filling concrete that will later be filled in between the sleepers.
  • the invention is not based on the described method and the illustrated and described embodiments of the used Formwork, facilities and equipment limited, but several additions and changes are possible without the Leave the scope of the invention.
  • other hardening stabilizing materials for example plastic-modified concretes or bitumen-bound masses use that are installed hot and harden when they cool down.
  • the thresholds are pushed.
  • the thresholds for the final state are also fixed in another way to connect the subsurface, for example screwing it into dowels, which are arranged in the support plates of the slab track become.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
EP19990122720 1998-12-01 1999-11-16 Procédé de fixation d'une voie de chemin de fer sur des dalles porteuses ainsi qu'un appareil et coffrage pour la mise en oeuvre de ce procédé Withdrawn EP1022386A2 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE1998155350 DE19855350A1 (de) 1998-12-01 1998-12-01 Verfahren zum Einbauen eines Gleises auf Tragplatten einer festen Fahrbahn sowie Schalung und Förderungs- und Einbaueinrichtung hierfür
DE19855350 1998-12-01

Publications (1)

Publication Number Publication Date
EP1022386A2 true EP1022386A2 (fr) 2000-07-26

Family

ID=7889592

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19990122720 Withdrawn EP1022386A2 (fr) 1998-12-01 1999-11-16 Procédé de fixation d'une voie de chemin de fer sur des dalles porteuses ainsi qu'un appareil et coffrage pour la mise en oeuvre de ce procédé

Country Status (2)

Country Link
EP (1) EP1022386A2 (fr)
DE (1) DE19855350A1 (fr)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT500982B1 (de) * 2003-04-23 2006-05-15 Rte Technologie Gmbh Verfahren zum verlegen eines gleisstranges einer festen fahrbahn
JP2016223239A (ja) * 2015-06-03 2016-12-28 神東塗料株式会社 てん充層形成用袋体
JP2016223240A (ja) * 2015-06-03 2016-12-28 神東塗料株式会社 てん充層形成用袋体

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1048783A1 (fr) 1999-04-29 2000-11-02 Bahnbau Wels GmbH Voie ferrée et sa méthode de réalisation
DE10039493C1 (de) * 2000-08-12 2002-01-31 Bahnbau Wels Gmbh Wels Verfahren zum Herstellen einer festen Fahrbahn für Schienenfahrzeuge
DE10046479B4 (de) * 2000-09-20 2004-05-27 Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg Zweiblockbetonschwelle für feste Schienenfahrbahn
WO2003002817A1 (fr) * 2001-05-16 2003-01-09 Peter Gunter Kusel Panneaux ou longrines pour voie ferree tubulaire
DE10343628B4 (de) * 2003-09-20 2007-08-09 Heitkamp Rail Gmbh Vorrichtung zum Anheben und Ausrichten von Gleisrosten
DE102005027758B3 (de) * 2005-06-15 2007-03-08 Rte Technologie Gmbh Verfahren für die Erneuerung eines mittels Schwellen in fester Fahrbahn verlegten Gleises sowie Heberichtschwelle zur Verwendung in dem Verfahren
DE102006044970B4 (de) * 2006-09-23 2012-06-21 FITR-Gesellschaft für Innovation im Tief- und Rohrleitungsbau Weimar mbH Verfahren zur Abdichtung gefährdeter Deichbereiche und Böschungen bei anstehendem Hochwasser
CN111218860A (zh) * 2020-03-02 2020-06-02 中铁二院工程集团有限责任公司 一种无砟轨道铁路变形调节路堤结构及构造方法

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4947756A (en) * 1988-08-18 1990-08-14 Peter G. Kusel Laying railway track
DE3901347A1 (de) * 1989-01-18 1990-07-26 Heilit & Woerner Bau Ag Verfahren und vorrichtung zur herstellung eines schotterlosen gleisoberbaus
DE4324301A1 (de) * 1993-07-20 1995-01-26 Heilit & Woerner Bau Ag Anordnung und Verfahren zur Herstellung eines schotterlosen Gleisoberbaus
DE4335877A1 (de) * 1993-10-18 1995-04-20 Betonwerk Rethwisch Gmbh Schotterloser Oberbau mit Betonschwellen
DE4340440A1 (de) * 1993-11-27 1995-06-01 Weiss Gmbh & Co Leonhard Verfahren zum Justieren und Fixieren eines lose auf einer festen Tragschicht aufliegenden Gleises
DE4430769C2 (de) * 1994-08-30 2001-05-03 Dyckerhoff & Widmann Ag Eisenbahnoberbau mit einem auf einer durchgehenden Tragplatte aus Stahlbeton aufgelagerten Gleisrost

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT500982B1 (de) * 2003-04-23 2006-05-15 Rte Technologie Gmbh Verfahren zum verlegen eines gleisstranges einer festen fahrbahn
JP2016223239A (ja) * 2015-06-03 2016-12-28 神東塗料株式会社 てん充層形成用袋体
JP2016223240A (ja) * 2015-06-03 2016-12-28 神東塗料株式会社 てん充層形成用袋体

Also Published As

Publication number Publication date
DE19855350A1 (de) 2000-06-15

Similar Documents

Publication Publication Date Title
DE2639812C3 (de) Vorgefertigtes Bauelement zur Herstellung von Decken und/oder Wänden sowie Verfahren und Einrichtung zu dessen Herstellung
DE69924777T2 (de) Verfahren zum Herstellen eines Gleisoberbaus
DE2306428A1 (de) Schienenfahrzeuggleis
EP0894898B1 (fr) Méthode de réalisation d'une voie ferrée et dispositif pour le réglage en hauteur et le support temporaire des rails
EP1022386A2 (fr) Procédé de fixation d'une voie de chemin de fer sur des dalles porteuses ainsi qu'un appareil et coffrage pour la mise en oeuvre de ce procédé
EP0635603A1 (fr) Procédé et dispositif pour la construction d'une superstructure de la voie sans ballast
DE10004194C2 (de) Verfahren zur Fertigung einer festen Schienenfahrbahn auf einer Brücke
DE4442498A1 (de) Fahrbare Betoniermaschine
DE2614036A1 (de) Einrichtung zum herstellen von fertigteilen aus spannbeton mit sofortigem verbund
EP1169516B1 (fr) Procede de renouvellement de voies ferrees
EP1576240B1 (fr) Procede de construction d'une voie sur dalle et voie de communication ainsi obtenue
DE19627468A1 (de) Rillenschiene
DE10312351A1 (de) Verfahren und Vorrichtung zur Herstellung einer insbesondere festen Fahrbahn für Schienenfahrzeuge
AT500982B1 (de) Verfahren zum verlegen eines gleisstranges einer festen fahrbahn
EP1191145B1 (fr) Procédé et dispositif pour relier une voie ferrée comprenant des rails et des plots d'appui unitaires à une structure fixe de soubassement de voie
AT500950A4 (de) Verfahren zur herstellung einer tunnelfahrbahn für schienenfahrzeuge
DE19522478C2 (de) Verfahren zur positionsgenauen und toleranzarmen Herstellung von Schienenstützpunkten mit hoher Oberflächengenauigkeit und Schalungselemente für die Durchführung des Verfahrens
DE3047650A1 (de) Verfahren und vorrichtung zum herstellen einer betonplatte
DE102012103001A1 (de) Feste Fahrbahn für Schienenfahrzeuge sowie Schienenbefestigungselement für eine feste Fahrbahn
EP1636424A1 (fr) Procede de production d'une voie ferree pour vehicules ferroviaires
AT512274B1 (de) Vorrichtungen und verfahren zur kontinuierlichen sanierung eines gleisbetts und seines unterbaus
DE202025105805U1 (de) Kompakter Körper zur Sanierung und Stabilisierung eines Gleisbetts
EP0751259B1 (fr) Procédé et dispositif pour la fabrication d'évidements dans des couches d'asphalte
DE102022100899A1 (de) Verfahren zur herstellung einer bahnsteigkante
EP1736599A1 (fr) Procédé de construction de voie pour un chemin de fer ou analogues

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

AX Request for extension of the european patent

Free format text: AL;LT;LV;MK;RO;SI

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20020601