EP0139100A1 - Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly - Google Patents

Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly Download PDF

Info

Publication number
EP0139100A1
EP0139100A1 EP84108125A EP84108125A EP0139100A1 EP 0139100 A1 EP0139100 A1 EP 0139100A1 EP 84108125 A EP84108125 A EP 84108125A EP 84108125 A EP84108125 A EP 84108125A EP 0139100 A1 EP0139100 A1 EP 0139100A1
Authority
EP
European Patent Office
Prior art keywords
sheet pile
sheet
piles
flange
web
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP84108125A
Other languages
German (de)
French (fr)
Inventor
Mitsuhiro Kunitoh
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ask Kenkyusho KK
Original Assignee
Ask Kenkyusho KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ask Kenkyusho KK filed Critical Ask Kenkyusho KK
Publication of EP0139100A1 publication Critical patent/EP0139100A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel

Definitions

  • the present invention is directed to a steel sheet pile for forming the wall of an excavation, the sheet piling assembly formed of a plurality of the steel sheet piles and the method of construction the assembly.
  • Figs. 1 and 2 there have been widely utilized for the construction of such sheetpiling wall channel steel piles 1 with joint elements 2 at their side edges or H steel piles 3 with joint elements 4 at the side edges of each of opposed flanges 5 of equal width.
  • These piles 1 and 3 are in use to be driven into the ground in side edge to side edge relationship with the joints elements interconnecting the adjacent piles.
  • the H steel piles 3 are found to be advantageous over the channel piles 1 from an economical standpoint since they have inherent rigidity higher than the channel piles with respect to unit weight and can be designed in less weight or thickness for the same rigidity required in constructing the sheetpiling wall.
  • H steel piles 3 are designed to be arranged in a straight line along the wall of an excavation such as a trench and a well and therefore find themselves impossible in some situations to be placed along a curved portion and a corner portion of the wall, because the remaining flanges 5 that do not act as the joint will certainly jam with each other when the piles 3 are required to be placed with little intervening space therebetween, as shown in Fig. 3, to prohibit an angled positioning of the H steel pile in relation to the adjacent piles. That is, the prior H piles 3 can be angularly disposed with each other only with considerable spaces therebetween which could weaken the sheet piling wall assembly to an unusable extent.
  • H steel pile 3 will sometimes incur a problem that the web 6 of each H steel pile 3 traverses the ground so as to divide the ground into separate portions, resulting in less binding forces between the individual portions of the ground on both sides of each web 6 and between the pile 3 and the ground.
  • the above drawbacks have been eliminated by the present invention which provides a steel sheet pile of unique and useful configuration for forming the wall of an excavation.
  • the sheet piles are driven into the ground in side edge to side edge relationship to form the wall in the ground.
  • Each of said sheet piles has a generally H-shaped cross section comprising a web with a wide flange on one side thereof and a narrow flange on the opposite side. Formed at the side edges of the wide flange are joint elements which interconnect the adjacent pairs of sheet piles and which allow a limited angular disposition of an individual sheet pile relative to the adjacent sheet pile.
  • the sheet piles With this configuration of the sheet pile having the wide and narrow flanges in addition to the joint construction of allowing the angular disposition of the sheet pile, the sheet piles can be successfully placed along a curved wall or at a corner portion thereof without requiring considerable intervening spaces between the adjacent sheet piles.
  • each sheet pile Formed in the web of each sheet pile are a series of longitudinally spaced perforations through which the soil of the ground or the like can pass for assuring strong binding of the soil or the like between the portions on both sides of the web and strong binding between the individual piles and the ground.
  • the sheet pile is formed at its wide flange with an integral rib of generally U-shaped configuration for increasing the mechanical strength of each sheet pile.
  • a method of forming such cutoff wall comprises the steps of forming a loose or unsolidified grout curtain in the ground with that grout material, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly by connecting the joint elements of the adjacent sheet piles and to permit the grout material to pass through the perforations in the web of each sheet pile, and allowing the loose grout curtain to dry for solidification.
  • the sheet piles can be sink in the ground under their own weight or aided by a slight push, enabling the sheet piles to be driven with a greatly reduced noise emission.
  • the sheet piles serve to be the core of the solidified grout curtain so as to form therewith the consolidated cutoff wall.
  • a sheet pile assembly 10 which is combined with a grout curtain 30 in the ground to form a cofferdam or a cutoff wall of an excavation such as a trench and a well.
  • the sheet pile assembly 10 consists of a series of sheet piles 11 arranged in side edge to side edge relationship with each other to extend along a straight or curved line.
  • Each of the sheet piles 11 is in the form of a generally H-shaped cross section along the entire length thereof comprising a web 12 with a wide flange 13 on one side thereof and a narrow flange 14 on the other side.
  • joint elements 15 and 16 are U -shaped return hooks, one up-turned and the other down-turned to have their openings facing in opposite directions.
  • Such construction of the joint elements 15 and 16 is conventional and permits the adjacent sheet piles 11 to be interconnected in mutually slidable edge-engagement for facilitating the placement of the sheet piles 11 in addition to that it permits a limited angular disposition of the individual sheet pile 11 relative to the adjacent one.
  • the members of the sheet pile 11 employed in the embodiment is dimensioned for example such that width A of web 12, width B of wide flange 13 and width C of narrow flange 14 are 400, 600 and 200 mm and that thickness T 1 of web 12, thickness T 2 of wide flange 13 and thickness T 3 of narrow flange 14 are 4.5, 6 and 18 mm.
  • the sheet pile of the present invention should not limited to the above dimensional feature except that the narrow flange 14 has a width preferably a half or less of the wide flange 13.
  • Formed in the web 12 are a series of longitudinally spaced perforations 18 which are trapezoid with one side thereof along the intersection between the web 12 and the wide flange 13. It is of course that the configuration and location of the perforations 18 should not limited to the above and may take the forms as illustrated in Figs. 8A and 8B.
  • Fig. 9 shows a modification of the above sheet pile which is similar to the above except that a sheet pile 21 is formed at its wide flange 23 with an integral rib 27 which is generally U -shaped in cross section and extends longitudinally along the intersection of a web 22 and the wide flange 23 for reinforcement of the sheet piles.
  • Such reinforcing rib 27 may be formed at a portion other than that intersection but within the width of the wide flange 23..
  • the sheet pile assembly 10 of the present embodiment is placed in a grout curtain 30 formed in the ground and cooperative therewith to form a cutoff wall around an excavation.
  • Said grout curtain 30 is made of a grout material such as soil-cement or soil-bentonite-cement mixture filled within a ditch 31 defined by a series of consecutive holes 32 dug in the ground.
  • a drilling derrick 40 having three parallel auger shafts 41, as shown in Figs. 10 and 11, is employed for digging the ditch 31 or the holes 32.
  • the drilling derrick 40 is carried by a crawler crane 42 for easy location thereof.
  • Each of the auger shafts 41 is provided at its tip with a nozzle 43 for injecting cement paste with bentonite added thereto or not.
  • the cement paste injected from the nozzle 42 will be mixed homogeneously with the remaining soil in the holes 32 by the action of the spirals on the auger shafts 41 as the drilling goes on so as to provide a soil-cement or soil-bentonite-cement mixture which defines said grout material for the grout curtain 30.
  • FIG. 13 illustrates a sequence of constructing the above sheet pile assembly 10 from the drilling of the holes 32 to driving of the sheet piles 11 thereinto, from which it is understood that the drilling of holes 32 and filling of the grout material into the holes 32 or ditch 31 are performed within one cycle from diving the auger shafts 41 into the ground to extracting the same from the ground. Accordingly, the holes 32 filled with the grout material is formed within one operational cycle of the drilling derrick 40. Said trench 31 is made by successively performing the above drilling operation in such a manner as to make a required configuration along the perimeter of the excavation to be dug, which simultaneously forms the loose or unsolidified grout curtain 30 of the required configuration in the ground.
  • said sheet piles 11 are successively inserted in the curtain 30 under their own weights or aided by a slight force applied to the top thereof.
  • the joint elements 15 and 16 can be slid one within the other so as to interconnect the adjacent sheet piles 11 within the loose grout curtain 30, as shown in Fig. 12B, while the grout material can readily permeate in the joint portions between the adjacent joint elements 15 and 16 such that it can securely link the adjacent ones of the sheet piles 11.
  • the sheet piles 11 are successively driven into the loose grout curtain 30 to extend therealong.
  • the sectional configuration of the sheet pile 11 allows the individual sheet pile 11 to be displaced angularly relative to the adjacent ones without the interference between the narrow flanges 14 of the adjacent sheet piles 11, whereby the sheet pile assembly can conform with not only a straight line but also a curved line or can make a corner portion, as shown in Fig. 4.
  • the sheet pile assembly 10 is fixedly installed in the curtain 30 to form therewith the cutoff wall in which the assembly 10 acts as a core structure.
  • Said perforations 18 in the web 12 of each sheet pile 11 allow the grout material to pass therethrough for assuring strong binding force developed between the portions of the grout curtain 30 on both sides of the web 12 of each sheet piles 11, which in turn assures a strong combining force between the sheet pile assembly 10 and the surrounding grout curtain 30.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

A steel sheet pile which is in use to be arranged in side edge to side edge relationship with adjacent piles of like construction to form the wall of an excavation, said sheet pile having a generally H-shaped cross section comprising a web with a wider flange on one side thereof and a narrow flange on the opposite side, said wide flange being provided at its side edges with joint elements for interconnection of the adjacently disposed sheet piles.

Description

    TECHNICAL FIELD
  • The present invention is directed to a steel sheet pile for forming the wall of an excavation, the sheet piling assembly formed of a plurality of the steel sheet piles and the method of construction the assembly.
  • BACKGROUND ART
  • As shown in Figs. 1 and 2, there have been widely utilized for the construction of such sheetpiling wall channel steel piles 1 with joint elements 2 at their side edges or H steel piles 3 with joint elements 4 at the side edges of each of opposed flanges 5 of equal width. These piles 1 and 3 are in use to be driven into the ground in side edge to side edge relationship with the joints elements interconnecting the adjacent piles. The H steel piles 3 are found to be advantageous over the channel piles 1 from an economical standpoint since they have inherent rigidity higher than the channel piles with respect to unit weight and can be designed in less weight or thickness for the same rigidity required in constructing the sheetpiling wall. However, such H steel piles 3 are designed to be arranged in a straight line along the wall of an excavation such as a trench and a well and therefore find themselves impossible in some situations to be placed along a curved portion and a corner portion of the wall, because the remaining flanges 5 that do not act as the joint will certainly jam with each other when the piles 3 are required to be placed with little intervening space therebetween, as shown in Fig. 3, to prohibit an angled positioning of the H steel pile in relation to the adjacent piles. That is, the prior H piles 3 can be angularly disposed with each other only with considerable spaces therebetween which could weaken the sheet piling wall assembly to an unusable extent. In addition, the use of the H steel pile 3 will sometimes incur a problem that the web 6 of each H steel pile 3 traverses the ground so as to divide the ground into separate portions, resulting in less binding forces between the individual portions of the ground on both sides of each web 6 and between the pile 3 and the ground.
  • DISCLOSURE OF THE INVENTION
  • The above drawbacks have been eliminated by the present invention which provides a steel sheet pile of unique and useful configuration for forming the wall of an excavation. The sheet piles are driven into the ground in side edge to side edge relationship to form the wall in the ground. Each of said sheet piles has a generally H-shaped cross section comprising a web with a wide flange on one side thereof and a narrow flange on the opposite side. Formed at the side edges of the wide flange are joint elements which interconnect the adjacent pairs of sheet piles and which allow a limited angular disposition of an individual sheet pile relative to the adjacent sheet pile. With this configuration of the sheet pile having the wide and narrow flanges in addition to the joint construction of allowing the angular disposition of the sheet pile, the sheet piles can be successfully placed along a curved wall or at a corner portion thereof without requiring considerable intervening spaces between the adjacent sheet piles.
  • Accordingly, it is a primary object of the present invention to provide steel sheet piles which can be arranged to form not only a straight wall but also curved and corner walls of the excavation, while retaining high rigidity resulting from the employment of the generally H-shaped configuration.
  • Formed in the web of each sheet pile are a series of longitudinally spaced perforations through which the soil of the ground or the like can pass for assuring strong binding of the soil or the like between the portions on both sides of the web and strong binding between the individual piles and the ground.
  • It is therefore another object of the present invention to provide a sheet pile which assures strong binding between the individual piles and the ground into which it is driven so as to be cooperative with the ground to form a consolidated wall of the excavation.
  • In a preferred embodiment, the sheet pile is formed at its wide flange with an integral rib of generally U-shaped configuration for increasing the mechanical strength of each sheet pile.
  • The above sheet piles are particularly advantageous when used in combination with a grout material such as soil-cement or soil-bentonite-cement mixture which is filled within the ground so as to be cooperative with the sheet piles driven thereinto to form a cutoff wall. A method of forming such cutoff wall comprises the steps of forming a loose or unsolidified grout curtain in the ground with that grout material, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly by connecting the joint elements of the adjacent sheet piles and to permit the grout material to pass through the perforations in the web of each sheet pile, and allowing the loose grout curtain to dry for solidification. With this method, the sheet piles can be sink in the ground under their own weight or aided by a slight push, enabling the sheet piles to be driven with a greatly reduced noise emission. After construction, the sheet piles serve to be the core of the solidified grout curtain so as to form therewith the consolidated cutoff wall.
  • It is therefore a further object of the present invention to provide a method of constructing a sheet pile assembly in the ground capable of driving the sheet piles under a greatly reduced noise circumstance to form the consolidated cutoff wall.
  • These and still other objects of the present invention will be more apparent in the following detailed description of the preferred embodiment when taken in conjunction with the attached drawings.
  • BRIEF DESCRIPTION OF THE DRAWINGS
    • Fig. 1 is a sectional view of a prior sheet piles of channel steel;
    • Fig. 2 is a sectional view of another sheet pile of H steel;
    • Fig. 3 is a schematic diagram showing the inconvenience encountered in arranging the above H steel pile at an angle with the adjacent one;
    • Fig. 4 is a transverse section of a sheet pile assembly when driven into a grout curtain formed in the ground in accordance with a preferred embodiment of the present invention;
    • Fig. 5 is a side elevation of a sheet pile employed in the above assembly;
    • Fig. 6 is a cross section along the line 6-6 of Fig. 5;
    • Fig. 7 is a cross section along the line 7-7 of Fig. 5;
    • Figs. 8A and 8B are respectively side elevations of modifications of the above sheet pile;
    • Fig. 9 is a sectional view of another modification of the above sheet pile;
    • Fig. 10 is a front elevation of a drilling derrick utilized for drilling holes into which the above sheet piles are driven;
    • Fig. 11 is a side elevation of the above digging device carried by a crawler crane; I
    • Figs. 12A and 12B are respectively schematic diagrams showing the plane configurations of the holes in the ground formed by the above digging device and the sheet piles placed in the holes; and
    • Fig. 13 is a schematic illustration showing the consequence of forming the sheet pile assembly in the ground.
    MODE FOR CARRYING OUT THE INVENTION
  • Referring now to Figs. 4 through 7, there is shown a sheet pile assembly 10 which is combined with a grout curtain 30 in the ground to form a cofferdam or a cutoff wall of an excavation such as a trench and a well. The sheet pile assembly 10 consists of a series of sheet piles 11 arranged in side edge to side edge relationship with each other to extend along a straight or curved line. Each of the sheet piles 11 is in the form of a generally H-shaped cross section along the entire length thereof comprising a web 12 with a wide flange 13 on one side thereof and a narrow flange 14 on the other side. Formed at the side edges of the wide flange 13 are joint elements 15 and 16 which are U-shaped return hooks, one up-turned and the other down-turned to have their openings facing in opposite directions. Such construction of the joint elements 15 and 16 is conventional and permits the adjacent sheet piles 11 to be interconnected in mutually slidable edge-engagement for facilitating the placement of the sheet piles 11 in addition to that it permits a limited angular disposition of the individual sheet pile 11 relative to the adjacent one. The members of the sheet pile 11 employed in the embodiment is dimensioned for example such that width A of web 12, width B of wide flange 13 and width C of narrow flange 14 are 400, 600 and 200 mm and that thickness T1 of web 12, thickness T2 of wide flange 13 and thickness T3 of narrow flange 14 are 4.5, 6 and 18 mm. Although the above dimensions are preferable, the sheet pile of the present invention should not limited to the above dimensional feature except that the narrow flange 14 has a width preferably a half or less of the wide flange 13. Formed in the web 12 are a series of longitudinally spaced perforations 18 which are trapezoid with one side thereof along the intersection between the web 12 and the wide flange 13. It is of course that the configuration and location of the perforations 18 should not limited to the above and may take the forms as illustrated in Figs. 8A and 8B.
  • Fig. 9 shows a modification of the above sheet pile which is similar to the above except that a sheet pile 21 is formed at its wide flange 23 with an integral rib 27 which is generally U-shaped in cross section and extends longitudinally along the intersection of a web 22 and the wide flange 23 for reinforcement of the sheet piles. Such reinforcing rib 27 may be formed at a portion other than that intersection but within the width of the wide flange 23..
  • Construction of the above sheet piles 11 are now discussed with reference to Figs. 10 through 13. The sheet pile assembly 10 of the present embodiment is placed in a grout curtain 30 formed in the ground and cooperative therewith to form a cutoff wall around an excavation. Said grout curtain 30 is made of a grout material such as soil-cement or soil-bentonite-cement mixture filled within a ditch 31 defined by a series of consecutive holes 32 dug in the ground. A drilling derrick 40 having three parallel auger shafts 41, as shown in Figs. 10 and 11, is employed for digging the ditch 31 or the holes 32. The drilling derrick 40 is carried by a crawler crane 42 for easy location thereof. Each of the auger shafts 41 is provided at its tip with a nozzle 43 for injecting cement paste with bentonite added thereto or not. The cement paste injected from the nozzle 42 will be mixed homogeneously with the remaining soil in the holes 32 by the action of the spirals on the auger shafts 41 as the drilling goes on so as to provide a soil-cement or soil-bentonite-cement mixture which defines said grout material for the grout curtain 30. Fig. 13 illustrates a sequence of constructing the above sheet pile assembly 10 from the drilling of the holes 32 to driving of the sheet piles 11 thereinto, from which it is understood that the drilling of holes 32 and filling of the grout material into the holes 32 or ditch 31 are performed within one cycle from diving the auger shafts 41 into the ground to extracting the same from the ground. Accordingly, the holes 32 filled with the grout material is formed within one operational cycle of the drilling derrick 40. Said trench 31 is made by successively performing the above drilling operation in such a manner as to make a required configuration along the perimeter of the excavation to be dug, which simultaneously forms the loose or unsolidified grout curtain 30 of the required configuration in the ground. After forming such loose grout curtain 40 in the ground, said sheet piles 11 are successively inserted in the curtain 30 under their own weights or aided by a slight force applied to the top thereof. In this insertion of the sheet piles 11, the joint elements 15 and 16 can be slid one within the other so as to interconnect the adjacent sheet piles 11 within the loose grout curtain 30, as shown in Fig. 12B, while the grout material can readily permeate in the joint portions between the adjacent joint elements 15 and 16 such that it can securely link the adjacent ones of the sheet piles 11. In this manner, the sheet piles 11 are successively driven into the loose grout curtain 30 to extend therealong. It it noted at this time that the sectional configuration of the sheet pile 11 allows the individual sheet pile 11 to be displaced angularly relative to the adjacent ones without the interference between the narrow flanges 14 of the adjacent sheet piles 11, whereby the sheet pile assembly can conform with not only a straight line but also a curved line or can make a corner portion, as shown in Fig. 4. After solidification of the grout curtain 30, the sheet pile assembly 10 is fixedly installed in the curtain 30 to form therewith the cutoff wall in which the assembly 10 acts as a core structure.
  • Said perforations 18 in the web 12 of each sheet pile 11 allow the grout material to pass therethrough for assuring strong binding force developed between the portions of the grout curtain 30 on both sides of the web 12 of each sheet piles 11, which in turn assures a strong combining force between the sheet pile assembly 10 and the surrounding grout curtain 30.
    Although only one aspect of the construction in which the sheet pile assembly is driven into the grout curtain in the above embodiment, the present invention should not be understood to be limited to the above aspect and the sheet pile assembly can be directly driven into the ground to support the walls of an excavation.
  • LIST OF REFERENCE NUMERALS
    • 1 channel steel pile 40 drilling derrick
    • 2 joint element 41 auger shaft
    • 3 H steel pile 42 crawler crane
    • 4 joint element 43 nozzle
    • 5 flange
    • 6 web
    • 10 sheet pile assembly
    • 11 sheet pile
    • 12 web
    • 13 wide flange
    • 14 narrow flange
    • 15 joint element
    • 16 joint element
    • 18 perforation
    • 21 sheet pile
    • 22 web
    • 23 wide flange
    • 24 narrow flange
    • 27 integral rib
    • 30 grout curtain
    • 31 ditch
    • 32 hole

Claims (6)

1. A steel sheet pile which is in use to be arranged in side edge to side edge relationship with adjacent piles of like construction to form the wall of an excavation, said sheet pile having a generally H-shaped cross section comprising a web with a wider flange on one side thereof and a narrow flange on the opposite side, said wide flange being provided at its side edges with joint elements for interconnection of the adjacently disposed sheet piles.
2. The sheet pile as set forth in claim 1, wherein said wide flange is provided with an integral reinforcing rib of generally U-shaped cross section.
3. The sheet pile as set forth in claim 1, wherein said web is formed with a series of longitudinally spaced perforations.
4. A sheet pile assembly including a series of sheet piles arranged in side edge to side edge relationship with each other for supporting the wall of an excavation; each of said sheet piles being provided at their side edges with joint elements for interconnecting the adjacent ones of the sheet piles, in which each of said sheet piles has a generally H-shaped cross section comprising a web with a wide flange on one side thereof and a narrow flange on the opposite side, said wide flange of each sheet pile being provided at its side edges with said joint elements, and the web of each sheet pile having therein a series of longitudinally spaced perforations.
5. A method of constructing a sheet pile assembly in the ground by the use of sheet piles each being shaped in the form of a generally H-shaped cross section having a web with a wide flange on on side thereof and a narrow flange on the opposite side, said wide flange of each sheet pile being provided at its side edges with joint elements for interconnection between a pair of adjacent sheet piles, said method comprising the steps of forming a loose grout curtain in the ground with a grout material such as soil-cement or soil-bentonite-cement mixtures, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly in the grout curtain by interconnecting the joint elements of the adjacent sheet piles and to permit the grout material to permeate in the joint portions between the adjacent joint elements, and allowing the loose grout curtain to dry for solidification.
6. A method of constructing a sheet pile assembly in the ground by the use of sheet piles each being shaped in the form of a generally H-shaped cross section having a web with a wide flange on on side thereof and a narrow flange on the opposite side, said wide flange of each sheet pile being provided at its side edges with joint elements for interconnection between a pair of adjacent sheet piles and the web of each sheet pile having therein a series of longitudinally spaced perforations, said method comprising the steps of forming a loose grout curtain in the ground with a grout material such as soil-cement or soil-bentonite-cement mixtures, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly in the grout curtain by interconnecting the joint elements of the adjacent sheet piles and to permit the grout material to permeate in the joint portions between the adjacent joint elements as well
EP84108125A 1983-09-22 1984-07-11 Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly Withdrawn EP0139100A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17551483A JPS6065826A (en) 1983-09-22 1983-09-22 Steel material used in landslide protection wall and construction method for landslide protection wall

Publications (1)

Publication Number Publication Date
EP0139100A1 true EP0139100A1 (en) 1985-05-02

Family

ID=15997378

Family Applications (1)

Application Number Title Priority Date Filing Date
EP84108125A Withdrawn EP0139100A1 (en) 1983-09-22 1984-07-11 Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly

Country Status (2)

Country Link
EP (1) EP0139100A1 (en)
JP (1) JPS6065826A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0562238A1 (en) * 1992-03-24 1993-09-29 Kabushiki Kaisha ASK Kenkyusho Underground water cutoff wall and method of constructing the same
JP2013155589A (en) * 2012-02-01 2013-08-15 Taisei Corp Continuous underground wall construction method and core member for continuous underground wall
CN103343538A (en) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer
CN104114770A (en) * 2012-02-29 2014-10-22 杰富意钢铁株式会社 Z-shaped steel sheet pile

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436719A (en) * 2016-10-09 2017-02-22 江西基业科技有限公司 Prefabricated pile composite retaining wall structure for foundation pit support and construction method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1841779A (en) * 1928-06-14 1932-01-19 Becker Enno Sheet piling for heavy loads
FR754438A (en) * 1933-04-15 1933-11-07 Ver Stahlwerke Ag Process for avoiding the reduction of moment of resistance in sheet piles whose assembly joints are located in the outer zone of the wall
US1975534A (en) * 1930-03-18 1934-10-02 Brusch Friedrich Wilhelm Flanged iron section
US1985795A (en) * 1931-03-09 1934-12-25 Vereinigte Stahlwerke Ag Sheet piling
DE646175C (en) * 1937-06-09 Ilseder Huette Sheet pile I-shaped cross-section
US2093208A (en) * 1931-03-16 1937-09-14 Dortmund Hoerder Huttenver Ag Method of making sheet metal piling
FR877386A (en) * 1941-02-06 1942-12-04 Double wall cofferdam, made of sheet piles with double tau profile
FR1262003A (en) * 1960-04-14 1961-05-26 Sainrapt & Brice Ets Improved sheet piles and sheet pile walls obtained
FR2083998A5 (en) * 1970-03-04 1971-12-17 Voest Ag
FR2231231A6 (en) * 1973-05-23 1974-12-20 Soletanche Wall built in trench in e.g. sand base - core of interlocking sheet piles surrounded by concrete mix
FR2291344A1 (en) * 1974-11-12 1976-06-11 Alpina Spa PREFABRICATED ELEMENT FOR THE CONSTRUCTION OF TRENCH WORKS AND RELATED PROCESS

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55155817A (en) * 1979-05-25 1980-12-04 Nippon Steel Corp H-beam steel sheet pile for underground structure for reducing propagation of ground vibration
JPS56111716A (en) * 1980-02-04 1981-09-03 Kawasaki Steel Corp H-shaped steel sheet pile

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE646175C (en) * 1937-06-09 Ilseder Huette Sheet pile I-shaped cross-section
US1841779A (en) * 1928-06-14 1932-01-19 Becker Enno Sheet piling for heavy loads
US1975534A (en) * 1930-03-18 1934-10-02 Brusch Friedrich Wilhelm Flanged iron section
US1985795A (en) * 1931-03-09 1934-12-25 Vereinigte Stahlwerke Ag Sheet piling
US2093208A (en) * 1931-03-16 1937-09-14 Dortmund Hoerder Huttenver Ag Method of making sheet metal piling
FR754438A (en) * 1933-04-15 1933-11-07 Ver Stahlwerke Ag Process for avoiding the reduction of moment of resistance in sheet piles whose assembly joints are located in the outer zone of the wall
FR877386A (en) * 1941-02-06 1942-12-04 Double wall cofferdam, made of sheet piles with double tau profile
FR1262003A (en) * 1960-04-14 1961-05-26 Sainrapt & Brice Ets Improved sheet piles and sheet pile walls obtained
FR2083998A5 (en) * 1970-03-04 1971-12-17 Voest Ag
FR2231231A6 (en) * 1973-05-23 1974-12-20 Soletanche Wall built in trench in e.g. sand base - core of interlocking sheet piles surrounded by concrete mix
FR2291344A1 (en) * 1974-11-12 1976-06-11 Alpina Spa PREFABRICATED ELEMENT FOR THE CONSTRUCTION OF TRENCH WORKS AND RELATED PROCESS

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0562238A1 (en) * 1992-03-24 1993-09-29 Kabushiki Kaisha ASK Kenkyusho Underground water cutoff wall and method of constructing the same
JP2013155589A (en) * 2012-02-01 2013-08-15 Taisei Corp Continuous underground wall construction method and core member for continuous underground wall
CN104114770A (en) * 2012-02-29 2014-10-22 杰富意钢铁株式会社 Z-shaped steel sheet pile
CN104114770B (en) * 2012-02-29 2016-03-16 杰富意钢铁株式会社 Z-shape steel sheet pile
CN103343538A (en) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer

Also Published As

Publication number Publication date
JPS6065826A (en) 1985-04-15
JPH0368172B2 (en) 1991-10-25

Similar Documents

Publication Publication Date Title
US4585678A (en) Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly
JP6632028B2 (en) Concrete assembly retaining wall
EP0139100A1 (en) Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
KR20190142492A (en) PHC pile to facilitate soil guard and construction method of soil guard structure using the same
JPS5841227Y2 (en) Element for mountain retainer
JP2002146774A (en) Soil cement column wall method
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JP2536701B2 (en) Earth retaining method for deep excavation
JP3000495B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPH06264462A (en) Jointing structure of steel wall and reinforced concrete floor slab
JP2521795Y2 (en) Retaining material
JP2988516B2 (en) Construction method of shield excavation wall
JPS5853321Y2 (en) Element for mountain retainer
JPH1088592A (en) Concrete retaining wall
JPH0343518A (en) Expanded continuous underground wall
JP2658692B2 (en) Earth retaining method for deep excavation
JP4079297B2 (en) Shield tunnel connection method
JPH0528288B2 (en)
JPS6262206B2 (en)
JPH0663235B2 (en) Soil retaining method
JPH0434207Y2 (en)
JPS6363897A (en) Tunnel or underground cavity lining structure
JP2605941B2 (en) Construction method for underground structures
JP2002070045A (en) Outer wall of underground structure and construction method

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Designated state(s): DE FR GB IT

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 19860107

RIN1 Information on inventor provided before grant (corrected)

Inventor name: KUNITOH, MITSUHIRO