EP0139100A1 - Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly - Google Patents
Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly Download PDFInfo
- Publication number
- EP0139100A1 EP0139100A1 EP84108125A EP84108125A EP0139100A1 EP 0139100 A1 EP0139100 A1 EP 0139100A1 EP 84108125 A EP84108125 A EP 84108125A EP 84108125 A EP84108125 A EP 84108125A EP 0139100 A1 EP0139100 A1 EP 0139100A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- sheet pile
- sheet
- piles
- flange
- web
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 19
- 239000010959 steel Substances 0.000 title claims abstract description 19
- 238000000034 method Methods 0.000 title claims description 9
- 238000009412 basement excavation Methods 0.000 claims abstract description 12
- 238000010276 construction Methods 0.000 claims abstract description 9
- 239000011440 grout Substances 0.000 claims description 38
- 239000000463 material Substances 0.000 claims description 13
- 239000004568 cement Substances 0.000 claims description 12
- 239000000203 mixture Substances 0.000 claims description 5
- 239000012466 permeate Substances 0.000 claims description 3
- 238000007711 solidification Methods 0.000 claims description 3
- 230000008023 solidification Effects 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 238000005553 drilling Methods 0.000 description 10
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 239000002689 soil Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 229910000278 bentonite Inorganic materials 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 230000009189 diving Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
Definitions
- the present invention is directed to a steel sheet pile for forming the wall of an excavation, the sheet piling assembly formed of a plurality of the steel sheet piles and the method of construction the assembly.
- Figs. 1 and 2 there have been widely utilized for the construction of such sheetpiling wall channel steel piles 1 with joint elements 2 at their side edges or H steel piles 3 with joint elements 4 at the side edges of each of opposed flanges 5 of equal width.
- These piles 1 and 3 are in use to be driven into the ground in side edge to side edge relationship with the joints elements interconnecting the adjacent piles.
- the H steel piles 3 are found to be advantageous over the channel piles 1 from an economical standpoint since they have inherent rigidity higher than the channel piles with respect to unit weight and can be designed in less weight or thickness for the same rigidity required in constructing the sheetpiling wall.
- H steel piles 3 are designed to be arranged in a straight line along the wall of an excavation such as a trench and a well and therefore find themselves impossible in some situations to be placed along a curved portion and a corner portion of the wall, because the remaining flanges 5 that do not act as the joint will certainly jam with each other when the piles 3 are required to be placed with little intervening space therebetween, as shown in Fig. 3, to prohibit an angled positioning of the H steel pile in relation to the adjacent piles. That is, the prior H piles 3 can be angularly disposed with each other only with considerable spaces therebetween which could weaken the sheet piling wall assembly to an unusable extent.
- H steel pile 3 will sometimes incur a problem that the web 6 of each H steel pile 3 traverses the ground so as to divide the ground into separate portions, resulting in less binding forces between the individual portions of the ground on both sides of each web 6 and between the pile 3 and the ground.
- the above drawbacks have been eliminated by the present invention which provides a steel sheet pile of unique and useful configuration for forming the wall of an excavation.
- the sheet piles are driven into the ground in side edge to side edge relationship to form the wall in the ground.
- Each of said sheet piles has a generally H-shaped cross section comprising a web with a wide flange on one side thereof and a narrow flange on the opposite side. Formed at the side edges of the wide flange are joint elements which interconnect the adjacent pairs of sheet piles and which allow a limited angular disposition of an individual sheet pile relative to the adjacent sheet pile.
- the sheet piles With this configuration of the sheet pile having the wide and narrow flanges in addition to the joint construction of allowing the angular disposition of the sheet pile, the sheet piles can be successfully placed along a curved wall or at a corner portion thereof without requiring considerable intervening spaces between the adjacent sheet piles.
- each sheet pile Formed in the web of each sheet pile are a series of longitudinally spaced perforations through which the soil of the ground or the like can pass for assuring strong binding of the soil or the like between the portions on both sides of the web and strong binding between the individual piles and the ground.
- the sheet pile is formed at its wide flange with an integral rib of generally U-shaped configuration for increasing the mechanical strength of each sheet pile.
- a method of forming such cutoff wall comprises the steps of forming a loose or unsolidified grout curtain in the ground with that grout material, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly by connecting the joint elements of the adjacent sheet piles and to permit the grout material to pass through the perforations in the web of each sheet pile, and allowing the loose grout curtain to dry for solidification.
- the sheet piles can be sink in the ground under their own weight or aided by a slight push, enabling the sheet piles to be driven with a greatly reduced noise emission.
- the sheet piles serve to be the core of the solidified grout curtain so as to form therewith the consolidated cutoff wall.
- a sheet pile assembly 10 which is combined with a grout curtain 30 in the ground to form a cofferdam or a cutoff wall of an excavation such as a trench and a well.
- the sheet pile assembly 10 consists of a series of sheet piles 11 arranged in side edge to side edge relationship with each other to extend along a straight or curved line.
- Each of the sheet piles 11 is in the form of a generally H-shaped cross section along the entire length thereof comprising a web 12 with a wide flange 13 on one side thereof and a narrow flange 14 on the other side.
- joint elements 15 and 16 are U -shaped return hooks, one up-turned and the other down-turned to have their openings facing in opposite directions.
- Such construction of the joint elements 15 and 16 is conventional and permits the adjacent sheet piles 11 to be interconnected in mutually slidable edge-engagement for facilitating the placement of the sheet piles 11 in addition to that it permits a limited angular disposition of the individual sheet pile 11 relative to the adjacent one.
- the members of the sheet pile 11 employed in the embodiment is dimensioned for example such that width A of web 12, width B of wide flange 13 and width C of narrow flange 14 are 400, 600 and 200 mm and that thickness T 1 of web 12, thickness T 2 of wide flange 13 and thickness T 3 of narrow flange 14 are 4.5, 6 and 18 mm.
- the sheet pile of the present invention should not limited to the above dimensional feature except that the narrow flange 14 has a width preferably a half or less of the wide flange 13.
- Formed in the web 12 are a series of longitudinally spaced perforations 18 which are trapezoid with one side thereof along the intersection between the web 12 and the wide flange 13. It is of course that the configuration and location of the perforations 18 should not limited to the above and may take the forms as illustrated in Figs. 8A and 8B.
- Fig. 9 shows a modification of the above sheet pile which is similar to the above except that a sheet pile 21 is formed at its wide flange 23 with an integral rib 27 which is generally U -shaped in cross section and extends longitudinally along the intersection of a web 22 and the wide flange 23 for reinforcement of the sheet piles.
- Such reinforcing rib 27 may be formed at a portion other than that intersection but within the width of the wide flange 23..
- the sheet pile assembly 10 of the present embodiment is placed in a grout curtain 30 formed in the ground and cooperative therewith to form a cutoff wall around an excavation.
- Said grout curtain 30 is made of a grout material such as soil-cement or soil-bentonite-cement mixture filled within a ditch 31 defined by a series of consecutive holes 32 dug in the ground.
- a drilling derrick 40 having three parallel auger shafts 41, as shown in Figs. 10 and 11, is employed for digging the ditch 31 or the holes 32.
- the drilling derrick 40 is carried by a crawler crane 42 for easy location thereof.
- Each of the auger shafts 41 is provided at its tip with a nozzle 43 for injecting cement paste with bentonite added thereto or not.
- the cement paste injected from the nozzle 42 will be mixed homogeneously with the remaining soil in the holes 32 by the action of the spirals on the auger shafts 41 as the drilling goes on so as to provide a soil-cement or soil-bentonite-cement mixture which defines said grout material for the grout curtain 30.
- FIG. 13 illustrates a sequence of constructing the above sheet pile assembly 10 from the drilling of the holes 32 to driving of the sheet piles 11 thereinto, from which it is understood that the drilling of holes 32 and filling of the grout material into the holes 32 or ditch 31 are performed within one cycle from diving the auger shafts 41 into the ground to extracting the same from the ground. Accordingly, the holes 32 filled with the grout material is formed within one operational cycle of the drilling derrick 40. Said trench 31 is made by successively performing the above drilling operation in such a manner as to make a required configuration along the perimeter of the excavation to be dug, which simultaneously forms the loose or unsolidified grout curtain 30 of the required configuration in the ground.
- said sheet piles 11 are successively inserted in the curtain 30 under their own weights or aided by a slight force applied to the top thereof.
- the joint elements 15 and 16 can be slid one within the other so as to interconnect the adjacent sheet piles 11 within the loose grout curtain 30, as shown in Fig. 12B, while the grout material can readily permeate in the joint portions between the adjacent joint elements 15 and 16 such that it can securely link the adjacent ones of the sheet piles 11.
- the sheet piles 11 are successively driven into the loose grout curtain 30 to extend therealong.
- the sectional configuration of the sheet pile 11 allows the individual sheet pile 11 to be displaced angularly relative to the adjacent ones without the interference between the narrow flanges 14 of the adjacent sheet piles 11, whereby the sheet pile assembly can conform with not only a straight line but also a curved line or can make a corner portion, as shown in Fig. 4.
- the sheet pile assembly 10 is fixedly installed in the curtain 30 to form therewith the cutoff wall in which the assembly 10 acts as a core structure.
- Said perforations 18 in the web 12 of each sheet pile 11 allow the grout material to pass therethrough for assuring strong binding force developed between the portions of the grout curtain 30 on both sides of the web 12 of each sheet piles 11, which in turn assures a strong combining force between the sheet pile assembly 10 and the surrounding grout curtain 30.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
A steel sheet pile which is in use to be arranged in side edge to side edge relationship with adjacent piles of like construction to form the wall of an excavation, said sheet pile having a generally H-shaped cross section comprising a web with a wider flange on one side thereof and a narrow flange on the opposite side, said wide flange being provided at its side edges with joint elements for interconnection of the adjacently disposed sheet piles.
Description
- The present invention is directed to a steel sheet pile for forming the wall of an excavation, the sheet piling assembly formed of a plurality of the steel sheet piles and the method of construction the assembly.
- As shown in Figs. 1 and 2, there have been widely utilized for the construction of such sheetpiling wall channel steel piles 1 with
joint elements 2 at their side edges orH steel piles 3 withjoint elements 4 at the side edges of each of opposedflanges 5 of equal width. Thesepiles 1 and 3 are in use to be driven into the ground in side edge to side edge relationship with the joints elements interconnecting the adjacent piles. TheH steel piles 3 are found to be advantageous over the channel piles 1 from an economical standpoint since they have inherent rigidity higher than the channel piles with respect to unit weight and can be designed in less weight or thickness for the same rigidity required in constructing the sheetpiling wall. However, suchH steel piles 3 are designed to be arranged in a straight line along the wall of an excavation such as a trench and a well and therefore find themselves impossible in some situations to be placed along a curved portion and a corner portion of the wall, because theremaining flanges 5 that do not act as the joint will certainly jam with each other when thepiles 3 are required to be placed with little intervening space therebetween, as shown in Fig. 3, to prohibit an angled positioning of the H steel pile in relation to the adjacent piles. That is, theprior H piles 3 can be angularly disposed with each other only with considerable spaces therebetween which could weaken the sheet piling wall assembly to an unusable extent. In addition, the use of theH steel pile 3 will sometimes incur a problem that the web 6 of eachH steel pile 3 traverses the ground so as to divide the ground into separate portions, resulting in less binding forces between the individual portions of the ground on both sides of each web 6 and between thepile 3 and the ground. - The above drawbacks have been eliminated by the present invention which provides a steel sheet pile of unique and useful configuration for forming the wall of an excavation. The sheet piles are driven into the ground in side edge to side edge relationship to form the wall in the ground. Each of said sheet piles has a generally H-shaped cross section comprising a web with a wide flange on one side thereof and a narrow flange on the opposite side. Formed at the side edges of the wide flange are joint elements which interconnect the adjacent pairs of sheet piles and which allow a limited angular disposition of an individual sheet pile relative to the adjacent sheet pile. With this configuration of the sheet pile having the wide and narrow flanges in addition to the joint construction of allowing the angular disposition of the sheet pile, the sheet piles can be successfully placed along a curved wall or at a corner portion thereof without requiring considerable intervening spaces between the adjacent sheet piles.
- Accordingly, it is a primary object of the present invention to provide steel sheet piles which can be arranged to form not only a straight wall but also curved and corner walls of the excavation, while retaining high rigidity resulting from the employment of the generally H-shaped configuration.
- Formed in the web of each sheet pile are a series of longitudinally spaced perforations through which the soil of the ground or the like can pass for assuring strong binding of the soil or the like between the portions on both sides of the web and strong binding between the individual piles and the ground.
- It is therefore another object of the present invention to provide a sheet pile which assures strong binding between the individual piles and the ground into which it is driven so as to be cooperative with the ground to form a consolidated wall of the excavation.
- In a preferred embodiment, the sheet pile is formed at its wide flange with an integral rib of generally U-shaped configuration for increasing the mechanical strength of each sheet pile.
- The above sheet piles are particularly advantageous when used in combination with a grout material such as soil-cement or soil-bentonite-cement mixture which is filled within the ground so as to be cooperative with the sheet piles driven thereinto to form a cutoff wall. A method of forming such cutoff wall comprises the steps of forming a loose or unsolidified grout curtain in the ground with that grout material, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly by connecting the joint elements of the adjacent sheet piles and to permit the grout material to pass through the perforations in the web of each sheet pile, and allowing the loose grout curtain to dry for solidification. With this method, the sheet piles can be sink in the ground under their own weight or aided by a slight push, enabling the sheet piles to be driven with a greatly reduced noise emission. After construction, the sheet piles serve to be the core of the solidified grout curtain so as to form therewith the consolidated cutoff wall.
- It is therefore a further object of the present invention to provide a method of constructing a sheet pile assembly in the ground capable of driving the sheet piles under a greatly reduced noise circumstance to form the consolidated cutoff wall.
- These and still other objects of the present invention will be more apparent in the following detailed description of the preferred embodiment when taken in conjunction with the attached drawings.
-
- Fig. 1 is a sectional view of a prior sheet piles of channel steel;
- Fig. 2 is a sectional view of another sheet pile of H steel;
- Fig. 3 is a schematic diagram showing the inconvenience encountered in arranging the above H steel pile at an angle with the adjacent one;
- Fig. 4 is a transverse section of a sheet pile assembly when driven into a grout curtain formed in the ground in accordance with a preferred embodiment of the present invention;
- Fig. 5 is a side elevation of a sheet pile employed in the above assembly;
- Fig. 6 is a cross section along the line 6-6 of Fig. 5;
- Fig. 7 is a cross section along the line 7-7 of Fig. 5;
- Figs. 8A and 8B are respectively side elevations of modifications of the above sheet pile;
- Fig. 9 is a sectional view of another modification of the above sheet pile;
- Fig. 10 is a front elevation of a drilling derrick utilized for drilling holes into which the above sheet piles are driven;
- Fig. 11 is a side elevation of the above digging device carried by a crawler crane; I
- Figs. 12A and 12B are respectively schematic diagrams showing the plane configurations of the holes in the ground formed by the above digging device and the sheet piles placed in the holes; and
- Fig. 13 is a schematic illustration showing the consequence of forming the sheet pile assembly in the ground.
- Referring now to Figs. 4 through 7, there is shown a
sheet pile assembly 10 which is combined with agrout curtain 30 in the ground to form a cofferdam or a cutoff wall of an excavation such as a trench and a well. Thesheet pile assembly 10 consists of a series ofsheet piles 11 arranged in side edge to side edge relationship with each other to extend along a straight or curved line. Each of thesheet piles 11 is in the form of a generally H-shaped cross section along the entire length thereof comprising aweb 12 with awide flange 13 on one side thereof and anarrow flange 14 on the other side. Formed at the side edges of thewide flange 13 are 15 and 16 which are U-shaped return hooks, one up-turned and the other down-turned to have their openings facing in opposite directions. Such construction of thejoint elements 15 and 16 is conventional and permits thejoint elements adjacent sheet piles 11 to be interconnected in mutually slidable edge-engagement for facilitating the placement of thesheet piles 11 in addition to that it permits a limited angular disposition of theindividual sheet pile 11 relative to the adjacent one. The members of thesheet pile 11 employed in the embodiment is dimensioned for example such that width A ofweb 12, width B ofwide flange 13 and width C ofnarrow flange 14 are 400, 600 and 200 mm and that thickness T1 ofweb 12, thickness T2 ofwide flange 13 and thickness T3 ofnarrow flange 14 are 4.5, 6 and 18 mm. Although the above dimensions are preferable, the sheet pile of the present invention should not limited to the above dimensional feature except that thenarrow flange 14 has a width preferably a half or less of thewide flange 13. Formed in theweb 12 are a series of longitudinally spacedperforations 18 which are trapezoid with one side thereof along the intersection between theweb 12 and thewide flange 13. It is of course that the configuration and location of theperforations 18 should not limited to the above and may take the forms as illustrated in Figs. 8A and 8B. - Fig. 9 shows a modification of the above sheet pile which is similar to the above except that a
sheet pile 21 is formed at itswide flange 23 with anintegral rib 27 which is generally U-shaped in cross section and extends longitudinally along the intersection of aweb 22 and thewide flange 23 for reinforcement of the sheet piles. Such reinforcingrib 27 may be formed at a portion other than that intersection but within the width of thewide flange 23.. - Construction of the
above sheet piles 11 are now discussed with reference to Figs. 10 through 13. Thesheet pile assembly 10 of the present embodiment is placed in agrout curtain 30 formed in the ground and cooperative therewith to form a cutoff wall around an excavation. Saidgrout curtain 30 is made of a grout material such as soil-cement or soil-bentonite-cement mixture filled within aditch 31 defined by a series ofconsecutive holes 32 dug in the ground. Adrilling derrick 40 having threeparallel auger shafts 41, as shown in Figs. 10 and 11, is employed for digging theditch 31 or theholes 32. The drilling derrick 40 is carried by a crawler crane 42 for easy location thereof. Each of theauger shafts 41 is provided at its tip with anozzle 43 for injecting cement paste with bentonite added thereto or not. The cement paste injected from the nozzle 42 will be mixed homogeneously with the remaining soil in theholes 32 by the action of the spirals on theauger shafts 41 as the drilling goes on so as to provide a soil-cement or soil-bentonite-cement mixture which defines said grout material for thegrout curtain 30. Fig. 13 illustrates a sequence of constructing the abovesheet pile assembly 10 from the drilling of theholes 32 to driving of thesheet piles 11 thereinto, from which it is understood that the drilling ofholes 32 and filling of the grout material into theholes 32 orditch 31 are performed within one cycle from diving theauger shafts 41 into the ground to extracting the same from the ground. Accordingly, theholes 32 filled with the grout material is formed within one operational cycle of thedrilling derrick 40. Saidtrench 31 is made by successively performing the above drilling operation in such a manner as to make a required configuration along the perimeter of the excavation to be dug, which simultaneously forms the loose orunsolidified grout curtain 30 of the required configuration in the ground. After forming suchloose grout curtain 40 in the ground, saidsheet piles 11 are successively inserted in thecurtain 30 under their own weights or aided by a slight force applied to the top thereof. In this insertion of the sheet piles 11, the 15 and 16 can be slid one within the other so as to interconnect the adjacent sheet piles 11 within thejoint elements loose grout curtain 30, as shown in Fig. 12B, while the grout material can readily permeate in the joint portions between the adjacent 15 and 16 such that it can securely link the adjacent ones of the sheet piles 11. In this manner, the sheet piles 11 are successively driven into thejoint elements loose grout curtain 30 to extend therealong. It it noted at this time that the sectional configuration of thesheet pile 11 allows theindividual sheet pile 11 to be displaced angularly relative to the adjacent ones without the interference between thenarrow flanges 14 of the adjacent sheet piles 11, whereby the sheet pile assembly can conform with not only a straight line but also a curved line or can make a corner portion, as shown in Fig. 4. After solidification of thegrout curtain 30, thesheet pile assembly 10 is fixedly installed in thecurtain 30 to form therewith the cutoff wall in which theassembly 10 acts as a core structure. - Said
perforations 18 in theweb 12 of eachsheet pile 11 allow the grout material to pass therethrough for assuring strong binding force developed between the portions of thegrout curtain 30 on both sides of theweb 12 of each sheet piles 11, which in turn assures a strong combining force between thesheet pile assembly 10 and the surroundinggrout curtain 30.
Although only one aspect of the construction in which the sheet pile assembly is driven into the grout curtain in the above embodiment, the present invention should not be understood to be limited to the above aspect and the sheet pile assembly can be directly driven into the ground to support the walls of an excavation. -
- 1
channel steel pile 40 drilling derrick - 2
joint element 41 auger shaft - 3 H steel pile 42 crawler crane
- 4
joint element 43 nozzle - 5 flange
- 6 web
- 10 sheet pile assembly
- 11 sheet pile
- 12 web
- 13 wide flange
- 14 narrow flange
- 15 joint element
- 16 joint element
- 18 perforation
- 21 sheet pile
- 22 web
- 23 wide flange
- 24 narrow flange
- 27 integral rib
- 30 grout curtain
- 31 ditch
- 32 hole
Claims (6)
1. A steel sheet pile which is in use to be arranged in side edge to side edge relationship with adjacent piles of like construction to form the wall of an excavation, said sheet pile having a generally H-shaped cross section comprising a web with a wider flange on one side thereof and a narrow flange on the opposite side, said wide flange being provided at its side edges with joint elements for interconnection of the adjacently disposed sheet piles.
2. The sheet pile as set forth in claim 1, wherein said wide flange is provided with an integral reinforcing rib of generally U-shaped cross section.
3. The sheet pile as set forth in claim 1, wherein said web is formed with a series of longitudinally spaced perforations.
4. A sheet pile assembly including a series of sheet piles arranged in side edge to side edge relationship with each other for supporting the wall of an excavation; each of said sheet piles being provided at their side edges with joint elements for interconnecting the adjacent ones of the sheet piles, in which each of said sheet piles has a generally H-shaped cross section comprising a web with a wide flange on one side thereof and a narrow flange on the opposite side, said wide flange of each sheet pile being provided at its side edges with said joint elements, and the web of each sheet pile having therein a series of longitudinally spaced perforations.
5. A method of constructing a sheet pile assembly in the ground by the use of sheet piles each being shaped in the form of a generally H-shaped cross section having a web with a wide flange on on side thereof and a narrow flange on the opposite side, said wide flange of each sheet pile being provided at its side edges with joint elements for interconnection between a pair of adjacent sheet piles, said method comprising the steps of forming a loose grout curtain in the ground with a grout material such as soil-cement or soil-bentonite-cement mixtures, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly in the grout curtain by interconnecting the joint elements of the adjacent sheet piles and to permit the grout material to permeate in the joint portions between the adjacent joint elements, and allowing the loose grout curtain to dry for solidification.
6. A method of constructing a sheet pile assembly in the ground by the use of sheet piles each being shaped in the form of a generally H-shaped cross section having a web with a wide flange on on side thereof and a narrow flange on the opposite side, said wide flange of each sheet pile being provided at its side edges with joint elements for interconnection between a pair of adjacent sheet piles and the web of each sheet pile having therein a series of longitudinally spaced perforations, said method comprising the steps of forming a loose grout curtain in the ground with a grout material such as soil-cement or soil-bentonite-cement mixtures, driving the sheet piles into the loose grout curtain in such a way as to form a continuous sheet pile assembly in the grout curtain by interconnecting the joint elements of the adjacent sheet piles and to permit the grout material to permeate in the joint portions between the adjacent joint elements as well
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17551483A JPS6065826A (en) | 1983-09-22 | 1983-09-22 | Steel material used in landslide protection wall and construction method for landslide protection wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| EP0139100A1 true EP0139100A1 (en) | 1985-05-02 |
Family
ID=15997378
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP84108125A Withdrawn EP0139100A1 (en) | 1983-09-22 | 1984-07-11 | Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly |
Country Status (2)
| Country | Link |
|---|---|
| EP (1) | EP0139100A1 (en) |
| JP (1) | JPS6065826A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0562238A1 (en) * | 1992-03-24 | 1993-09-29 | Kabushiki Kaisha ASK Kenkyusho | Underground water cutoff wall and method of constructing the same |
| JP2013155589A (en) * | 2012-02-01 | 2013-08-15 | Taisei Corp | Continuous underground wall construction method and core member for continuous underground wall |
| CN103343538A (en) * | 2013-07-17 | 2013-10-09 | 深圳市兴班建筑工程有限公司 | A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer |
| CN104114770A (en) * | 2012-02-29 | 2014-10-22 | 杰富意钢铁株式会社 | Z-shaped steel sheet pile |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106436719A (en) * | 2016-10-09 | 2017-02-22 | 江西基业科技有限公司 | Prefabricated pile composite retaining wall structure for foundation pit support and construction method |
Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US1841779A (en) * | 1928-06-14 | 1932-01-19 | Becker Enno | Sheet piling for heavy loads |
| FR754438A (en) * | 1933-04-15 | 1933-11-07 | Ver Stahlwerke Ag | Process for avoiding the reduction of moment of resistance in sheet piles whose assembly joints are located in the outer zone of the wall |
| US1975534A (en) * | 1930-03-18 | 1934-10-02 | Brusch Friedrich Wilhelm | Flanged iron section |
| US1985795A (en) * | 1931-03-09 | 1934-12-25 | Vereinigte Stahlwerke Ag | Sheet piling |
| DE646175C (en) * | 1937-06-09 | Ilseder Huette | Sheet pile I-shaped cross-section | |
| US2093208A (en) * | 1931-03-16 | 1937-09-14 | Dortmund Hoerder Huttenver Ag | Method of making sheet metal piling |
| FR877386A (en) * | 1941-02-06 | 1942-12-04 | Double wall cofferdam, made of sheet piles with double tau profile | |
| FR1262003A (en) * | 1960-04-14 | 1961-05-26 | Sainrapt & Brice Ets | Improved sheet piles and sheet pile walls obtained |
| FR2083998A5 (en) * | 1970-03-04 | 1971-12-17 | Voest Ag | |
| FR2231231A6 (en) * | 1973-05-23 | 1974-12-20 | Soletanche | Wall built in trench in e.g. sand base - core of interlocking sheet piles surrounded by concrete mix |
| FR2291344A1 (en) * | 1974-11-12 | 1976-06-11 | Alpina Spa | PREFABRICATED ELEMENT FOR THE CONSTRUCTION OF TRENCH WORKS AND RELATED PROCESS |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS55155817A (en) * | 1979-05-25 | 1980-12-04 | Nippon Steel Corp | H-beam steel sheet pile for underground structure for reducing propagation of ground vibration |
| JPS56111716A (en) * | 1980-02-04 | 1981-09-03 | Kawasaki Steel Corp | H-shaped steel sheet pile |
-
1983
- 1983-09-22 JP JP17551483A patent/JPS6065826A/en active Granted
-
1984
- 1984-07-11 EP EP84108125A patent/EP0139100A1/en not_active Withdrawn
Patent Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE646175C (en) * | 1937-06-09 | Ilseder Huette | Sheet pile I-shaped cross-section | |
| US1841779A (en) * | 1928-06-14 | 1932-01-19 | Becker Enno | Sheet piling for heavy loads |
| US1975534A (en) * | 1930-03-18 | 1934-10-02 | Brusch Friedrich Wilhelm | Flanged iron section |
| US1985795A (en) * | 1931-03-09 | 1934-12-25 | Vereinigte Stahlwerke Ag | Sheet piling |
| US2093208A (en) * | 1931-03-16 | 1937-09-14 | Dortmund Hoerder Huttenver Ag | Method of making sheet metal piling |
| FR754438A (en) * | 1933-04-15 | 1933-11-07 | Ver Stahlwerke Ag | Process for avoiding the reduction of moment of resistance in sheet piles whose assembly joints are located in the outer zone of the wall |
| FR877386A (en) * | 1941-02-06 | 1942-12-04 | Double wall cofferdam, made of sheet piles with double tau profile | |
| FR1262003A (en) * | 1960-04-14 | 1961-05-26 | Sainrapt & Brice Ets | Improved sheet piles and sheet pile walls obtained |
| FR2083998A5 (en) * | 1970-03-04 | 1971-12-17 | Voest Ag | |
| FR2231231A6 (en) * | 1973-05-23 | 1974-12-20 | Soletanche | Wall built in trench in e.g. sand base - core of interlocking sheet piles surrounded by concrete mix |
| FR2291344A1 (en) * | 1974-11-12 | 1976-06-11 | Alpina Spa | PREFABRICATED ELEMENT FOR THE CONSTRUCTION OF TRENCH WORKS AND RELATED PROCESS |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0562238A1 (en) * | 1992-03-24 | 1993-09-29 | Kabushiki Kaisha ASK Kenkyusho | Underground water cutoff wall and method of constructing the same |
| JP2013155589A (en) * | 2012-02-01 | 2013-08-15 | Taisei Corp | Continuous underground wall construction method and core member for continuous underground wall |
| CN104114770A (en) * | 2012-02-29 | 2014-10-22 | 杰富意钢铁株式会社 | Z-shaped steel sheet pile |
| CN104114770B (en) * | 2012-02-29 | 2016-03-16 | 杰富意钢铁株式会社 | Z-shape steel sheet pile |
| CN103343538A (en) * | 2013-07-17 | 2013-10-09 | 深圳市兴班建筑工程有限公司 | A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6065826A (en) | 1985-04-15 |
| JPH0368172B2 (en) | 1991-10-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4585678A (en) | Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly | |
| JP6632028B2 (en) | Concrete assembly retaining wall | |
| EP0139100A1 (en) | Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly | |
| JP3829319B2 (en) | Construction method of underground hollow structure and its underground hollow structure | |
| KR20190142492A (en) | PHC pile to facilitate soil guard and construction method of soil guard structure using the same | |
| JPS5841227Y2 (en) | Element for mountain retainer | |
| JP2002146774A (en) | Soil cement column wall method | |
| JP2558414B2 (en) | Construction method of the main retaining wall and the retaining wall | |
| JP2536701B2 (en) | Earth retaining method for deep excavation | |
| JP3000495B2 (en) | Large-scale, deep steel continuous basement wall and method of constructing the same | |
| JPH06264462A (en) | Jointing structure of steel wall and reinforced concrete floor slab | |
| JP2521795Y2 (en) | Retaining material | |
| JP2988516B2 (en) | Construction method of shield excavation wall | |
| JPS5853321Y2 (en) | Element for mountain retainer | |
| JPH1088592A (en) | Concrete retaining wall | |
| JPH0343518A (en) | Expanded continuous underground wall | |
| JP2658692B2 (en) | Earth retaining method for deep excavation | |
| JP4079297B2 (en) | Shield tunnel connection method | |
| JPH0528288B2 (en) | ||
| JPS6262206B2 (en) | ||
| JPH0663235B2 (en) | Soil retaining method | |
| JPH0434207Y2 (en) | ||
| JPS6363897A (en) | Tunnel or underground cavity lining structure | |
| JP2605941B2 (en) | Construction method for underground structures | |
| JP2002070045A (en) | Outer wall of underground structure and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| AK | Designated contracting states |
Designated state(s): DE FR GB IT |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
| 18D | Application deemed to be withdrawn |
Effective date: 19860107 |
|
| RIN1 | Information on inventor provided before grant (corrected) |
Inventor name: KUNITOH, MITSUHIRO |