DE3210791A1 - Ventilation and escape route integrated in the support - Google Patents
Ventilation and escape route integrated in the supportInfo
- Publication number
- DE3210791A1 DE3210791A1 DE19823210791 DE3210791A DE3210791A1 DE 3210791 A1 DE3210791 A1 DE 3210791A1 DE 19823210791 DE19823210791 DE 19823210791 DE 3210791 A DE3210791 A DE 3210791A DE 3210791 A1 DE3210791 A1 DE 3210791A1
- Authority
- DE
- Germany
- Prior art keywords
- expansion
- ventilation
- channel
- route
- shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/04—Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
- E21D23/0472—Supports specially adapted for people walking or transporting material
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F1/00—Ventilation of mines or tunnels; Distribution of ventilating currents
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
Abstract
Description
Im Ausbau integrierter Wetter- und FluchtwegWeather and escape route integrated in the expansion
Die Erfindung betrifft eine Vorrichtung zum flereingewinnen vor Kohle, insbesondere aus Restflächen eines Flözes oder Dämmen entlang einer Strecke mit mindestens einem einseitig von einer Strecke abgehenden Streb, beispielweise Kurzfrontstreb, unter Verwendung von Schild- und/oder Bockausbau und einer Sonderbewetterunc.The invention relates to a device for mining coal, in particular from residual areas of a seam or embankments along a route at least one longwall extending from a route on one side, for example a short-frontedwall, using shield and / or trestle extensions and a special weather function.
Die Gewinnungsbetriebe im Strebbau entwickelten sich in den vergangenen 20 Jahren zu Großbetrieben mit hohen Investitionskosten. Als Ergebnis dieser Entwicklung ist in nachteiliger Form die zunehmende Zahl von Pestflächen anzusehen, die durch den Strebbau nicht wirtschaftlich gewonnen werden konnten.The mining operations in longwall have developed in the past 20 years to large companies with high investment costs. As a result of this development The increasing number of plague areas that are caused by the longwall could not be economically won.
Durch die Konzentration auf Großbetriebspunkte sinkt die Lagerstättenausnutzung auf ca. 60 %. Uni diesen schlechten Lagerstättenausnutzungsgrad zu verbessern, sind Überlegungen dahingehnd entwickelt worden, die verbleiLenden Lagerstättenflacher ohne zusätzliche Streckenauffahrung über geeignete Kurzfrontbetriebe hereinzugewinnen.By concentrating on major operating points, the exploitation of the deposits decreases to about 60%. Uni to improve this poor deposit utilization rate are Considerations have been developed to make the leading deposits shallower gain in via suitable short-front operations without additional driveway driving.
Dabei ergeben sich Schwierigkeiten in der Förderung und Gewinnung ohne zusätzliche Pandhosten für Vorbereiten und Freischneiden der entsprechenden Einrichtungen sowie in der Sicherung der Wetterführung bei einseitigem Anschluß des Gewinnungsfeldes an eine vorhandene Strecke.Difficulties arise in the promotion and extraction without additional pandhosts for preparing and cutting the appropriate Facilities as well as in securing the weather management with unilateral connection of the extraction field to an existing route.
Bei der Konzeption einer entsprechenden Kurzfronttechnologie ergeben sich darüber hinaus bergbehördliche Auflagen für die Erstattung eines Fluchtweges sowie die Anordnung einer Sonderbewetterung ohne Einengung des Fahrweges und Benachteiligung durch das stänuige Schreiten des Ausbaus.When designing a corresponding short front technology In addition, there are mining authority requirements for the reimbursement of an escape route as well as the arrangement of special ventilation without narrowing the route and disadvantageous by the constant pace of expansion.
Die Erfindung hat sich nunmehr die Aufgabe gestellt, eine Vorrichtung zum Hereingewinnen stehengebliebener Lagerstätten, insbesondere Ober- und Unterdämmen zu schaffen, die unter Berücksichtigung der heute notwendigen Verhiebgeschwindigkeiten auch den Ansprüchen an Sicherheit und Leistungsfähigkeit entsprechend den bergbehärdlichen Richtlinien Genüge tut.The invention has now set itself the task of a device to win in remaining deposits, in particular upper and lower dams to create that, taking into account the moving speeds required today also the demands on safety and performance according to the mountain handicapped Guidelines are sufficient.
Diese Aufgabe wird erfindungsgemä.ß dadurch gelost, daß versatzseitiy über die Länge eines Strebes in den Ausbau inteyriert ein schachtartiger, allseits geschlossener Kanal vorgesehen ist, der als Bewetterungs- und Fluchtweg ausgebildet aus kraftschlüssig miteinander verbundenen Stahlbauelementen zusammengesetzt ist.This object is achieved according to the invention in that the offset side Over the length of a strut in the extension a shaft-like, inteyrated on all sides closed channel is provided, which is designed as a ventilation and escape route is composed of frictionally interconnected steel structural elements.
Im Rahmen der Erfindung erweist es sich als besonders vorteilhaft, daß die Stahlbauelemente eine geringfügig geyeneinander verschwenkbare Verbindung aufweisen und diese winkelbewegliche Verbindung der Stahlbauelemente untereinander wetterdicht ausgebildet ist.In the context of the invention, it proves to be particularly advantageous that the steel structural elements form a slightly mutually pivotable connection have and this angularly movable connection of the steel structural elements with one another is designed to be weatherproof.
Ebenso erweist es sich als besonders vorteilhaft, dab der schachtartig ausgebildete, versatzseitig vom Ausbau zwischen sich und den Ausbau einen Fahrweg bildent auf dem Liegenden geführte Kanal mit dem Ausbau über Rüchzylinder und Bruchschilde verbunden ist, und daß zwischen Bruchschild und Kappe eine Überlappung in der Große es Schreitmaßes vorgesehen ist.It also proves to be particularly advantageous that the shaft-like trained, offset side of the expansion between itself and the expansion a driveway formed on the lying canal with the extension over Rüchylinders and break shields is connected, and that between the fracture shield and the cap there is an overlap in the size it is provided for walking distance.
Nach einem weiteren Ausführungsbeispiel der Erfindung ist es vorstellbar, die zu einem schachtartigen Kanal zusammensetzbaren Stahlbauelemente unterhalb der rückkragenden Kappe des Ausbaus aufhängbar anzuordnen.According to a further embodiment of the invention, it is conceivable the assemblable to a shaft-like channel steel construction elements below the to arrange the protruding cap of the extension so that it can be suspended.
Bei jeder Ausführung des als Bewetterung- und Fluchtweg ausgebildeten schachtartigen Kanals aus einzelnen kraftschlüssig miteinander verbundenen Stahlbauelementen entsprechen die Innenmaße in Höhe und Breite ohne Einschränkung des Fahrweges wenigstens den Mindestanforderungen an den Fahrweg im Strebausbau. Die winkelbewegliche Verbindung ist wetterdicht ausgebildet, bezogen auf die für Sonderbewetterungsanlagen notwendigen Drücke. Vorteilhafterweise weisen die Stahlbauelemente, jedes einzelne oder auch über die Länge des Kurzfrontstrebs verteilt, Klappen auf, die jeweils von innen und außen zu verschliePen sind, wobei die Klappen in der Größe auszuführen sind, daß ein Schleifkorb mit einem Verletzten durch die Klappe in den Kanal eingeführt werden Kann.With every execution of the one designed as a ventilation and escape route Manhole-like channel made of individual non-positively interconnected steel construction elements the inside dimensions correspond at least in height and width without restricting the travel path the minimum requirements for the route in longwall construction. The angularly movable connection is designed to be weatherproof, based on what is required for special ventilation systems Press. Advantageously, the steel structural elements, either individually or as well Spread over the length of the short front brace, flaps open, each from the inside and are to be closed on the outside, the flaps being of the size that a grinding basket with an injured person is inserted through the flap into the canal can be.
Der als Wetter- und Fluchtweg konzipierte Kanal ist sowohl beim Schildausbau als auch beim Bockausbau einsetzbar. Darüber hinaus ist von besonderer Bedeutung, daß die Verbindung zwischen den Ausbau sowie dem schachtartigen Kanal so ausgeführt ist, daß die einzelnen Ausbaueinheiten ein Schreitmaß von 600 mm einhalten können. Dabei wird erst nach dem Vorrücken aller Ausbaueinheiten ein über die Länge des Strebs der als Wetter- und Fluchtweg ausgebildete Kanal in einer Einheit nachgezogen.The canal, which is designed as a weather and escape route, is both in the shielding phase and can also be used for trestle construction. In addition, it is of particular importance that the connection between the expansion and the shaft-like channel is carried out is that the individual expansion units can maintain a walking distance of 600 mm. Only after all expansion units have moved forward is an over the length of the Strebs retraced the canal, designed as a weather and escape route, in one unit.
Ein AL-sführungsbeispiel der Erfindung ist in den Zeichnungen dargestellt und wirü im folgenden naher erläutert. Es zeigen: Figur 1 eine Prinzipskizze für die Kurzfrontgewinnungstechnik, Figur 2 eine Seitenansicht eines Bockausbaus in schematisierter Form mit einem auf dem Liegenden nachgeführten Bewetterungs- und Fluchtweg in Form von allseits geschlossenen Stahlbauelementen in der Ausgangssituation, Figur 3 das in Figur 2 dargestellte Ausführungsbeispiel mit vorgerücktem Ausbau und Figur 4 eine Prinzipskizze der einzelnen Ausbauphasen ohne Gewinnungseinrichtung in einer Draufsicht.An AL example of the invention is shown in the drawings and is explained in more detail below. Show it: Figure 1 is a schematic diagram for the short front extraction technique, Figure 2 is a side view of a trestle extension in schematic form with a ventilation system tracked on the lying and escape route in the form of fully enclosed steel construction elements in the initial situation, Figure 3 shows the embodiment shown in Figure 2 with advanced expansion and FIG. 4 shows a schematic diagram of the individual expansion phases without an extraction device in a top view.
In der Figur 1 ist das Prinzip für eine Kurzfronttechnik ohne Berücksichtigung einer Gewinnungseinrichtung dargestellt. Von einer bestehenden Strecke 2 aus wird nach einer oder beiden Seiten der Strecke die restliche Kohle mittels eines Kurzfrontstrebes 3 abgebaut. In der Strecke 2 ist ein Fördermittel 5 und der Antrieb für eine nicht dargestellte Gewinnungsmaschine angedeutet.In FIG. 1, the principle for a short front technique is disregarded a recovery device shown. From an existing route 2 is after one or both sides of the route, the remaining coal by means of a short front brace 3 dismantled. In line 2 there is a conveyor 5 and the drive for one is not shown extraction machine indicated.
Die Richtung der Wetter ist durch den Pfeil A angeueutet.The direction of the weather is indicated by the arrow A.
Der Ausbau 4 kann sowohl ein Schild- als auch ein Bockausbau sein, dem sich das Bruchfeld oder Versatzfelci 7 anschließt. Der Bruch oder Versatz 7 ist geuenüber der Strecke 2 durch einen Damm õ aus speziellem Dammbaustoff getrennt. In der Strecke 2 ist weiterhin eine Sonderbewet:terung 6 angedeutet, die ii: eilen Kanal 9 über aelit, welcher in der Draufsicht unterhalb der Bruchschilde 14 verlauft. Der Verlauf der Sonderbewetterung ist durch die Pfeile im Streb 3 angedeutet. Der Unterdruck der Streckënetterführunc saugt die Wetter aus dem Streb 3 an.The extension 4 can be a shield or a trestle extension, which is followed by the fracture field or offset field 7. The break or misalignment 7 is separated from the route 2 by a dam made of special dam building material. In line 2, a special event 6 is also indicated, which are in a hurry Channel 9 via aelit, which runs below the fracture shields 14 in the plan view. The course of the special ventilation is indicated by the arrows in the longwall face 3. Of the The underpressure of the Streckënetterführunc sucks in the weather from the face 3.
In den Figuren 2 und 3 ist in einer Seitenansicht der schachtartige Kanal 9, bestehend aus Stahlbauelementen 10, in den Ausbau 4 in Form von Bockausbau integriert dargestellt.In Figures 2 and 3 is a side view of the shaft-like Channel 9, consisting of steel construction elements 10, in expansion 4 in the form of trestle expansion shown integrated.
In Figur 2 ist die Ausgangsphase dargestellt, in welcher der Ausbau 4 noch nicht gerückt ist. Der Ausbau 4 besteht im wesentlichen aus zwei zwischen einer Sohlschiene 12 und der Hangendkappe 11 angeordneten Stempeln 13. Der Ausbau 4 ist über den Hydraulikzylinder 21 mit einem nicht dargestellten Fördermittel bzw. einer nicht dargestellten Gewinnungsmaschine verbunden. Der allseits geschlossen ausgebildete schachtartige Kanal 9 ist in dem in den Figuren 2 und 3 dargestellten Ausführungsbeispiel auf dem Liegenden angeordnet und ist mit dem Ausbau 4 bzw. der Sohlschiene 12 über einen Rückzylinder 17 und mit der das Hangende 23 abstützenden Hangendkappe 11 über den Bruchschild 14 verbunden.In Figure 2, the initial phase is shown in which the expansion 4 has not yet moved. The expansion 4 consists essentially of two between a sole rail 12 and the hanging end cap 11 arranged punches 13. The expansion 4 is via the hydraulic cylinder 21 with a conveying means (not shown) or connected to a mining machine, not shown. Closed on all sides formed shaft-like channel 9 is shown in FIGS Embodiment arranged on the lying and is with the expansion 4 or the Base rail 12 via a rear cylinder 17 and with the hanging wall 23 supporting The hanging end cap 11 is connected via the fracture shield 14.
Der Bruchschild 14 ist in Anpassung an das erforderliche Schreitmaß a unterhalb der Hangendkappe 11 in einer Konsole 15, beispielsweise mittels Langlöchern 16 und einem Hydraulikzylinder 18 derart gefuhrt, daß die einzelnen Ausbaueinheiten des Ausbaus 4 mit einem Schreitmaß von 600 mm erst nach dem Vorrücken aller Ausbaueinheiten über die f;ydraulikzylinder 17 und 18 nachgezogen er«en konnten.The fracture shield 14 is adapted to the required step size a below the hanging cap 11 in a bracket 15, for example by means of elongated holes 16 and a hydraulic cylinder 18 guided in such a way that the individual expansion units of expansion 4 with a step dimension of 600 mm only after all expansion units have been advanced via the hydraulic cylinders 17 and 18.
In Anpassung an erforderliche Ausgleichsbewegungen sinu die Stahlbauelemente 10 des kanals 9 zwar kraftschlüssig aber mit einer möglichen Winkelbewegung bis zu 100 miteinander verbunden. Die Stahlbauelemente 10 sind zum Ausbau 4 hin gerichtet mit Klappen versehen. Darüber hinaus sinu in den Bruchschilden 14 insbesondere zur Überprüfung des @angenden 23 verschließbare Öffnungen 20 vorgesehen.The steel construction elements are adapted to the necessary compensatory movements 10 of the channel 9, although non-positive, but with a possible angular movement up to connected to 100. The steel construction elements 10 are directed towards the expansion 4 provided with flaps. In addition, sinu in the fracture shields 14 in particular to Review of the @angenden 23 closable openings 20 provided.
1 Flö7 2 Strecke 3 Streb 4 Ausbau 5 Fördermittel 6 Sonderbewetterung 7 Bruch- oder Versatzfeld 8 Damm 9 Kanal 10 Stahlbauelement 11 Hangendkappe 12 Sohlschiene 13 Stempel 14 Bruchschild/Kappe 15 Konsole 16 Langloch 17 Rückzylinder 18 Nachrückzylinder 19 Fahrweg 20 Öffnung 21 Zylinder 22 Liegendes 23 Hangendes a Schreitmaß1 Flö7 2 Line 3 Longwall 4 Expansion 5 Funding 6 Special ventilation 7 Broken or offset field 8 Embankment 9 Canal 10 Steel construction element 11 Hanging end cap 12 Base rail 13 Stamp 14 Break plate / cap 15 Bracket 16 Long hole 17 Back cylinder 18 Back cylinder 19 Track 20 Opening 21 Cylinder 22 Lying 23 hanging wall a walking distance
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE19823210791 DE3210791A1 (en) | 1982-03-24 | 1982-03-24 | Ventilation and escape route integrated in the support |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE19823210791 DE3210791A1 (en) | 1982-03-24 | 1982-03-24 | Ventilation and escape route integrated in the support |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE3210791A1 true DE3210791A1 (en) | 1983-10-06 |
Family
ID=6159158
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DE19823210791 Ceased DE3210791A1 (en) | 1982-03-24 | 1982-03-24 | Ventilation and escape route integrated in the support |
Country Status (1)
| Country | Link |
|---|---|
| DE (1) | DE3210791A1 (en) |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2509810B2 (en) * | 1975-03-06 | 1978-08-03 | Gewerkschaft Eisenhuette Westfalia, 4670 Luenen | Gradual expansion for use in mighty seams |
-
1982
- 1982-03-24 DE DE19823210791 patent/DE3210791A1/en not_active Ceased
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2509810B2 (en) * | 1975-03-06 | 1978-08-03 | Gewerkschaft Eisenhuette Westfalia, 4670 Luenen | Gradual expansion for use in mighty seams |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DE1219892B (en) | Control of a coal plow | |
| DE3107955C2 (en) | Facility for the expansion and extraction of seams | |
| DE2743625A1 (en) | MECHANIZED COAL PRODUCTION DEVICE | |
| DE2813143A1 (en) | METHOD FOR DRIVING AND REMOVING AN UNDERGROUND ROUTE AND DEVICE FOR EXERCISING THE METHOD | |
| EP0428781B1 (en) | Track maintenance machine for distributing and profiling the track bedding ballast | |
| DE3210791A1 (en) | Ventilation and escape route integrated in the support | |
| DE19511018C2 (en) | Extraction plant for extracting and removing mineral deposits deposited in the seam | |
| DE2145076C3 (en) | Process for driving excavation routes and tunneling machine for carrying out the process | |
| DE4329549A1 (en) | Machine system for winning minerals deposited as a stratum, especially coal | |
| DE736399C (en) | Arrangement of an extraction and loading device and a face conveyor under the protection of moving steel construction frames | |
| DE2309009A1 (en) | STEP EXPANSION | |
| DE1583039B1 (en) | Longwall equipment with mining machine for a short longwall | |
| DE678589C (en) | Procedure for dismantling camps | |
| DE2629788C3 (en) | Device for dust extraction in underground mining operations using the hollow profiles of the support frames as extraction lines | |
| DE1175633B (en) | Device for setting up the drive and reversing units of face lifting equipment and mining machines | |
| DE2847909A1 (en) | DEVICE FOR DRIVING A ROCKING AT MOUNTAIN MINING OPERATIONS | |
| DE2021839A1 (en) | Device for driving advancing structures | |
| DE611157C (en) | Method for opening up opencast mines using a waste extraction and conveyor system | |
| DE3335098A1 (en) | Mining method for seam-like deposits | |
| DE3008236A1 (en) | Steep coal seam working in mine - involves lemniscate stabilised shield blocks, integrated face interceptors and pneumatic packing | |
| DE102004061720B3 (en) | Method to secure a haulage crossing in mining according to which a support part coupled to a conveyor carries props holding rails which are laid down after support is dug out and set down again providing ongoing support during mining | |
| DE1182619B (en) | Device for lowering routes | |
| DE2538084C3 (en) | Process for the extraction of long fronts in the chamber-pillar construction | |
| DE3045231C2 (en) | Extraction machine for seam mining | |
| DE1246368B (en) | Continuous crushers, especially coal crushers, for use in longwall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 8110 | Request for examination paragraph 44 | ||
| 8131 | Rejection |