DE2845913A1 - WORKSTATION FOR A PRODUCTION LINE, IN PARTICULAR FOR AN ASSEMBLY MACHINE - Google Patents
WORKSTATION FOR A PRODUCTION LINE, IN PARTICULAR FOR AN ASSEMBLY MACHINEInfo
- Publication number
- DE2845913A1 DE2845913A1 DE19782845913 DE2845913A DE2845913A1 DE 2845913 A1 DE2845913 A1 DE 2845913A1 DE 19782845913 DE19782845913 DE 19782845913 DE 2845913 A DE2845913 A DE 2845913A DE 2845913 A1 DE2845913 A1 DE 2845913A1
- Authority
- DE
- Germany
- Prior art keywords
- workpiece carrier
- fixing
- work station
- workpiece
- prepositioning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000004519 manufacturing process Methods 0.000 title claims description 11
- 239000000969 carrier Substances 0.000 claims description 12
- 230000000295 complement effect Effects 0.000 claims 2
- 208000006011 Stroke Diseases 0.000 description 18
- 230000008901 benefit Effects 0.000 description 6
- 238000000034 method Methods 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 230000003993 interaction Effects 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 241000635279 Dorcatragus megalotis Species 0.000 description 1
- 238000009825 accumulation Methods 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 239000002981 blocking agent Substances 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 239000000872 buffer Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000006071 cream Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000003754 machining Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23Q—DETAILS, COMPONENTS, OR ACCESSORIES FOR MACHINE TOOLS, e.g. ARRANGEMENTS FOR COPYING OR CONTROLLING; MACHINE TOOLS IN GENERAL CHARACTERISED BY THE CONSTRUCTION OF PARTICULAR DETAILS OR COMPONENTS; COMBINATIONS OR ASSOCIATIONS OF METAL-WORKING MACHINES, NOT DIRECTED TO A PARTICULAR RESULT
- B23Q7/00—Arrangements for handling work specially combined with or arranged in, or specially adapted for use in connection with, machine tools, e.g. for conveying, loading, positioning, discharging, sorting
- B23Q7/005—Lifting devices
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P21/00—Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control
- B23P21/004—Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control the units passing two or more work-stations whilst being composed
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Automatic Assembly (AREA)
Description
-3- 2846913-3- 2846913
Die Erfindung betrifft eine Arbeitsstation für eine Fertigungsstraße, insbesondere für eine Ilontageiaaschine, gemäß dem Oberbegriff des Patentanspruchs 1.The invention relates to a work station for a production line, especially for an Ilontageiamaschine, according to the preamble of claim 1.
/irbeitsstationsn dieser Art sind für Werkstückträger (Paletten) bekannt. Durch das zum Fixieren des Wi.rkstückträgers in der Arbeitsstation durchgeführte Abheben desselben vom Friktionsförderer ergibt sich der Vorteil, daß während der Stillstandzeiten der Werkstückträger in de.r Arbeitsstation durch die Reibung mit dem Friktionsförde rt_r kein Verschleiß eintritt, obwohl der Friktionsförderer während des Betriebs dauernd in Tätigkeit ist. Als Friktionsfördercr kommen alle friktionsbewegten Transportmittel, wie Tragketten, Staurollenketten oder Friktionsrollenbänder in Frage. Nachteilig bei den bekannten /u'beitsstationen der erwähnten Art ist, daß ein zu hoher konstruktiver Aufwand betrieben werden muß, wenn die Arbeitsstation verschiedenartigen Anforderungen anpaßbar und betriebssicher sein soll.Workstations of this type are for workpiece carriers (Pallets) known. Through the fixation of the workpiece carrier lifting of the same from the friction conveyor carried out in the work station there is the advantage that during downtime the workpiece carrier in the workstation through the friction with the friction conveyor rt_r no wear occurs, although the friction conveyor is constantly in Activity is. All those moving with friction come as friction conveyors Means of transport, such as carrying chains, accumulation roller chains or friction roller belts in question. Disadvantage of the known / u'workstations of the kind mentioned is that too high a constructive Effort must be made when the workstation is diverse Requirements should be adaptable and operationally reliable.
Zur genauen Lagcausrichtung des Werkstückträger in der Arbeitsstation ist es bekannt, an Arbeitsstation und Werkstückträger Fixierstifte und zugeordnete Bohrungen vorzusehen, die beim Fixierhub des WErkstückträgers miteinander in Eingriff gebracht werden. Ein sicherer Eingriff der Fixierstifte und Bohrungen ist jedoch nicht ohne weiteres gewährleistet, da die Werkstückträger vom Friktionsförderer in nicht genau ausgerichteter Lage den Arbeitsstationen zugeführt werden, weil die Ausrichtlage der Werkstückträger auf dem Förderer verhältnismäßig ungenau definiert ist. Um einen sicheren Eingriff der Stifte und Bohrungen zu ermöglichen, muß man daher entweder die Haltemittel der Arbeitsstation, an denen die Werkstückträger anlaufen, sehr aufwendig gestalten, so daß die Werkstückträger beim Anlaufen in eine ausreichend definierte Lagegebracht v/erden, oder muß die Fixierstifte mit verhältnismäßig langen schrägen Anlaufflächen versehen, damit ein Hineinfinden in die Bohrungen auch bei einer gewissen Lageabweichung möglich ist. Es liegt auf der Hand, daß eine spezielle Ausgestaltung der Haltemittel die GesamtanlageFor precise alignment of the workpiece carrier in the work station, it is known on the work station and workpiece carrier Provide locating pins and associated bores, which when Fixing stroke of the workpiece carrier are brought into engagement with one another. A secure engagement of the locating pins and holes is not guaranteed without further ado, since the workpiece carrier from the friction conveyor is not in a precisely aligned position are fed to the workstations because the alignment position of the workpiece carriers on the conveyor is relatively imprecise is defined. In order to enable a secure engagement of the pins and holes, one must therefore either the holding means of Work station at which the workpiece carriers start to make very complex, so that the workpiece carriers when starting up in A sufficiently defined position must be brought to bear, or the locating pins must have relatively long inclined contact surfaces provided so that it is possible to find the holes even with a certain positional deviation. It is obvious, that a special design of the holding means the overall system
Π 3 0 0 1 7 / 0 5 r "Π 3 0 0 1 7/0 5 r "
verteuert und kompliziert. Die besondere Gestaltung der Stifte ist ebenfalls nachteilig/ da dabei längere Paßstifte, die einen aus Stabilitätsgründen entsprechend größeren Querschnitt besitzen müssen, erforderlich werden, was zusätzlich den Kachteil erbringt, daß der Fixierhub verhältnismäßig lang sein rauß.expensive and complicated. The special design of the pins is also disadvantageous / because longer dowel pins, one for reasons of stability must have a correspondingly larger cross-section, which is also the Kachteil yields that the fixing stroke is relatively long rough.
Der Erfindung liegt die Aufgabe zugrunde, für eine Fertigungsstraße der in Rede stehenden Art eine Arbeitsstation zu schaffen, die bei einem einfachen Grundaufbau verschiedenartigen Anforderungen anpaßbar ist und gleichzeitig hohe Betriebssicherheit gewährleistet.The invention is based on the object for a production line of the type in question to create a workstation which, with a simple basic structure, is different Requirements is adaptable and at the same time ensures high operational reliability.
Diese Aufgabe ist erfindungsgemäß durch die im Anspruch 1 genannten Merkmale gelöst. Dadurch, daß der Fixierhub erfindungsgemäß unterteilt ist und die erste Hubstufe für das Vorpositionieren der Werkstückträger dient, ergeben sich eine Reihe überraschender Vorteile. So können, da bei der ersten Stufe des Fixierhubs eine Vorpositionierung durchgeführt wird, die Haltemittel in den Arbeitsstationen zum Anhalten der Werkstückträger als einfache steuerbare Blockiermittel ausgebildet sein. Es sind auch keinerlei präzise gearbeitete Anlaufflächen an den Werkstückträgern für die Zusammenwirkung mit diesen Blockiermitteln erforderlich.According to the invention, this object is achieved by those mentioned in claim 1 Features solved. The fact that the fixing stroke is subdivided according to the invention and the first stroke stage for the Pre-positioning the workpiece carrier is used, there are a number of surprising advantages. So you can, there at the first Stage of the fixing stroke a prepositioning is carried out, the holding means in the work stations for stopping the workpiece carrier can be designed as a simple controllable blocking means. There are also no precisely machined contact surfaces on the workpiece carriers for interaction required with these blocking agents.
Wenn es sich um Arbeitsstationen handelt, an denen einfache Arbeitsgänge ausgeführt werden, beispielsweise Montagearbeiten, bei denen das Werkstück, und damit der Werkstückträger nicht mit sehr engen Toleranzen positioniert zu sein braucht, kann die Vorpositionierung als alleinige Lageausrichtung dienen, d.h., der Werkstückträger kann nach dem Vorpositionieren bei d=r zweiten Hubstufe in der beim Vorpositionieren eingestellten Lage zur Fixierung an der Arbeitsstation festgeklemmt warden, ohne daß Paßstifte zur Feinpositionierung in zugehörige Fixierbohrungen bei der zweiten Hubstufe eingefahren werden müßten.When it comes to workstations where simple operations are carried out, for example assembly work, where the workpiece, and thus the workpiece carrier, does not need to be positioned with very tight tolerances the prepositioning serve as the sole position alignment, i.e. the workpiece carrier can be used after prepositioning with d = r second stroke stage in the one set during prepositioning Position to be clamped to the workstation without dowel pins for fine positioning in the associated Fixing bores would have to be retracted in the second stroke stage.
030017/0508030017/0508
Wenn es sich um Arbeitsstationen handelt, die eine Feinpositionierung des Werkstückträgers erforderlich iaachen, wenn also kein einfaches Festklemmen des vorpositionierten Werkstückträgers in der Arbeitsstation ausreicht, sondern bei der zweiten Hubstufe des Fixierhubs Paßstifte und -bohrungen in Eingriff gebracht werden müssen, die an dem Vierkstückträger und der Arbeitsstation angeordnet sind, erbringt das zuvor durchgeführte Vorpositionieren den entscheidenden Vorteil, daß ein sicheres Einfahren der Paßnittel ohne weiteres gewährleistet ist, ohne daß die Paßstifte oder -bohrungen mit ausgedehnten Schrägflächen oder dergleichen versehen werden müßten. Auch erfordert dann die endgültige, genaue Positionierung nur eins sehr geringe Verstellung des Werkstückträgers, wodurch die Paßstifte kurz gehalten werden können und nur geringen Beanspruchungen unterliegen.When it comes to workstations that require fine positioning of the workpiece pallet is required, i.e. if the prepositioned workpiece pallet is not simply clamped in the workstation is sufficient, but in the second stroke of the fixing stroke dowel pins and holes must be brought into engagement, which on the four-piece carrier and the work station are arranged, the previously performed prepositioning provides the decisive advantage that a safe retraction of the passport is easily guaranteed without the dowel pins or bores having to be provided with extensive inclined surfaces or the like. The final, precise positioning then only requires a very small adjustment of the workpiece carrier, as a result of which the dowel pins can be kept short and are only subject to low stresses.
Ein weiterer Vorteil der Erfindung besteht darin, daß gemäß einem bevorzugten Ausführungsbeispiel eine Dreheinrichtung zum Verdrehen des in der ersten Hubstufe vom Friktionsförderer abgehobenen Werkstückträgers um vorgewählte Drehwinkel vorgesehen sein kann. Dadurch entfällt die Notwendigkeit, gesonderte Drehstationan vorzusehen, die den Arbeitsstationen vor- und nachgeschaltet sind, wie sie bei den bekannten Fertigungsstraßen vorhanden sein müssen, wenn ein Drehen der Werkstückträger erforderlich ist. Es liegt auf der Hand, daß bei Verwendung der erfindungsgemäßen Arbeitsstation dadurch eine einschneidende Platzersparnis bei gleichzeitiger starker Verringerung der Anlagekosten erzielt wird. Dazu kommt, daß durch die Erfindung im Gegensatz zu den bekannten Fertigungsstraßen beliebige Drehwinkel der Werkstückträger für den Arbeitsvorgang zur Verfügung gestellt werden können, während bei bekannten Fertigungsstraßen eine Verdrehung nur um 180° oder allenfalls 90° möglich ist. Dieser Nachteil der bekannten Straßen rührt daher, daß die in den Drehstationen gedrehten Werkstückträger nach dem Verdrehen mittels des Friktionsförderers in die Arbeits-Another advantage of the invention is that, according to a preferred embodiment, a rotating device for Rotation of the workpiece carrier lifted off the friction conveyor in the first lifting stage is provided by preselected rotation angles can be. This eliminates the need to provide separate turning stations that are connected upstream and downstream of the workstations, as is the case with the known ones Production lines must be available if the workpiece pallet needs to be rotated. It lies It is obvious that when using the workstation according to the invention, this results in a significant saving of space while at the same time significant reduction in investment costs is achieved. In addition, the invention in contrast to the known Production lines can be provided with any angle of rotation of the workpiece carrier for the work process, while in known production lines a rotation is only possible by 180 ° or at most 90 °. This disadvantage of the known Streets stems from the fact that the workpiece carriers turned in the turning stations after turning by means of the friction conveyor into the working
030017/0508030017/0508
station hineintransportiert v/erden müssen, ein Transport der Werkstückträger auf dem Friktionsförderer jedoch nur bei einer Drehung um 180°, allenfalls bei einer Drehung un 90° möglich ist. Diese Beschränkungen sind bei der Erfindung nicht gegeben, da das Drehen der Werkstückträger, unabhängig vom Transport derselben^ in den ArbeitsStationen selbst durchgeführt wird, wobei Drehungen um beliebige Winkel durchgeführt werden können. Der Konstrukteur der Arbeitsstationen ist daher, da ihm der Werkstückträger und damit das Werkstück, in beliebiger Drehlage zur Verfügung steht, völlig frei in der Anordnung der Montage- und/oder Bearbeitungseinheiten.station must be transported in, but only one transport of the workpiece carriers on the friction conveyor Rotation by 180 °, at most with a rotation of 90 °, is possible. These restrictions do not apply to the invention, since the rotation of the workpiece carrier, regardless of the transport of the same ^ is carried out in the work stations themselves, whereby Rotations by any angle can be performed. The designer of the workstations is therefore responsible for the workpiece carrier and so that the workpiece is available in any rotational position, completely free in the arrangement of the assembly and / or processing units.
Durch die Möglichkeit, das Werkstück in der Arbeitsstation in jede beliebige Drehstellung verdrehen zu können,ergibt sich darüber hinaus der Vorteil-, daß das Werkstück auf dem Werkstückträger, ohne daß man auf irgendwelche anderen Gegebenheiten Rücksicht zu nehmen brauchte, so angeordnet werden kann, daß es beim Transport die kleinstmögliche Stirnfläche, bezogen auf die Transportrichtung, darbietet. Dadurch ergibt sich die Möglichkeit, bei kleinstmöglicher Querschnittsfläche des Freiraums, d.h. bei kompaktester Bauweise der Fertigungsstraße, möglichst große Werkstücke durch die Fertigungsstraße hindurchzuführen.With the possibility of the workpiece in the work station in each to be able to rotate any rotational position, there is also the advantage that the workpiece on the workpiece carrier, without having to take any other conditions into account, it can be arranged in such a way that it has the smallest possible frontal area during transport, based on the direction of transport. This makes it possible to use the smallest possible cross-sectional area of the free space, i.e. with the most compact construction of the production line, the largest possible workpieces through the production line to lead through.
— 7 —- 7 -
030017/0508030017/0508
Die Erfindung wird nachfolgend anhand dor Zeichnung in einzel nen erläutert.The invention is explained below with reference to drawings in dor single NEN.
Ei zeigen:Show egg:
Fig. 1 eine teils aufgebrochen und geschnittenFig. 1 partially broken open and cut
sόν.*ic schematisch vereinfacht gezeichnet= Vorderansicht eines Ausführungsbeispiels einer Arbeitsstation und eines in diese eingefahrenden Werkstückträgers;sόν. * ic shown schematically simplified = Front view of one embodiment of a workstation and one in it retracting workpiece carrier;
Fig. 2 eine schematisch vereinfacht gezeichnete Draufsicht des Werkstückträgers;2 shows a schematically simplified plan view of the workpiece carrier;
Fig. 3 eine schematisch vereinfacht gezeichnete Draufsicht auf die Arbeitsstation gemäß Fig. 1 ohne Werkstückträger und3 shows a schematically simplified plan view of the work station according to FIG Fig. 1 without workpiece carrier and
Fig. 4 einen schematisiert, abgebrochen, teilsFig. 4 is a schematic, broken off, partly
aufgeschnitten und in größerem Maßstab gezeichneten Ausschnitt aus Fig. 1, in dem verschiedene Arbeitsstellungen des Werkstückträgers relativ zur Arbeitsstation angedeutet sind.cut open and drawn on a larger scale detail from Fig. 1, in which various Working positions of the workpiece carrier are indicated relative to the workstation.
Fig. 1 zeigt ein Ausführungsbeispiel einer als Ganzes mit 10 bezeichneten Arbeitsstation mit einem in dieser befindlichen Werkstückträger 11. Der Werkstückträger 11 hat, wie am besten aus Fig. 2 zu ersehen ist, im wesentlichen die Gestalt einer quadratischen Platte, auf deren Oberseite nicht dargestellte Spann- oder Fixiermittel zum Festspannen bzw. Aufnehmen eines ebenfalls nicht dargestellten Werkstücks angeordnet sind und die mit ihrer Unterseite auf einem Friktions-Rollenfördercr aufliegend längs einer gewünschten Transportbahn zu den entsprechenden Arbeitsstationen und durch diese hindurch bewegt wird. Beim gezeigten1 shows an exemplary embodiment of a 10 as a whole designated workstation with one located in this Workpiece carrier 11. As can best be seen from FIG. 2, the workpiece carrier 11 has essentially the shape of a square plate, on the top not shown clamping or fixing means for clamping or receiving a also not shown workpiece are arranged and the underside on a friction roller conveyor resting along a desired transport path to the corresponding work stations and moved through them will. When shown
030017/0506030017/0506
Beispiel weist der Rollenförderer reibschlüssig angetriebene Rollen 13 auf. Nie aus Fig. 1 zu ersehen ist, verläuft der Rollenförderer 12 oberhalb eines Gestells 15 der Arbeitsstation durch diese hindurch. Beidseits am Rollenförderer 12 angebrachte Leisten 14 verhindern, daß die Werkstückträger 11 seitlich vom Rollenförderer 12 herabgleiten.Example has the roller conveyor frictionally driven Rolls 13 on. Never seen from Fig. 1, the roller conveyor runs 12 above a frame 15 of the work station through this. Strips attached to both sides of the roller conveyor 12 14 prevent the workpiece carriers 11 from sliding down the side of the roller conveyor 12.
In Fig. 1 liegt der Werkstückträger 11 in seiner Transportstellung, die auch in Fig. 4 mit ausgezogener Linie eingezeichnet ist, unmittelbar auf den Rollen 13 des Rollenförderers auf. Der nicht dargestellte Friktionsantrieb der Rollen 13 ist im Betrieb dauernd in Tätigkeit, so daß auf die auf dem Förderer 12 aufliegenden Werkstückträger 11 dauernd eine Vorschubkraft in Transportrichtung einwirkt.Um die Werkstückträger in der Arbeitsstation zum Stillstand zu bringen, ist ein Anschlag 16 vorgesehen, der mit einer Tragplatte 17 verbunden ist, die mittels einer als Ganzes mit 18 bezeichneten Hubeinrichtung anhebbar ist, um den Anschlag 16 in die Bewegungsbahn der Transportbewegung der Werkstückträger 11 zu bewegen und diese zum Stillstand zu bringen, ohne daß der Friktions-Rollenförderer 12 außer Tätigkeit gesetzt wird. Beim dargestellten Ausführungsbeispiel weist die Hubeinrichtung drei Hubzylinder 19, 20 und 21 auf, die, wie nachstehend noch eingehender erläutert wird, unabhängig voneinander betätigbar sind, um die Tragplatte 17 in der Weise anzuheben, daß deren Vertikalbewegung stufenweise erfolgt. Beim Betätigen des Hubzylinders 19 wird die Tragplatte 17 und damit der Anschlag 16 so weit angehoben, daß ein in die Arbeitsstation einlaufender Werkstückträger 11 mit seiner Anschlagfläche 22 am Anschlag 16 anläuft. Die Tragplatte 17 ist für ihre Vertikalbewegung mit Säulen 23 verbunden, die in einer als Ganzes mit 24 bezeichneten Säulenführung verschiebbar sind, die am Gestell 15 befestigt ist.In Fig. 1 the workpiece carrier 11 is in its transport position, which is also shown in Fig. 4 with a solid line, directly on the rollers 13 of the roller conveyor on. The friction drive, not shown, of the rollers 13 is constantly in operation during operation, so that on the conveyor 12 on the workpiece carrier 11 continuously acts a feed force in the transport direction. To the workpiece carrier in the To bring the workstation to a standstill, a stop 16 is provided which is connected to a support plate 17 which can be raised by means of a lifting device designated as a whole by 18, in order to move the stop 16 into the path of the transport movement to move the workpiece carrier 11 and bring it to a standstill without the friction roller conveyor 12 is put out of action. In the illustrated embodiment, the lifting device has three lifting cylinders 19, 20 and 21, which, as will be explained in more detail below, can be actuated independently of one another in order to move the support plate 17 to raise in such a way that their vertical movement is gradual. When the lifting cylinder 19 is actuated, the support plate 17 and thus the stop 16 is raised so far that a workpiece carrier 11 entering the work station runs with its stop surface 22 on the stop 16. The support plate 17 is connected to columns 23 for its vertical movement, which are displaceable in a column guide, designated as a whole as 24, which is fastened to the frame 15.
030017/0508030017/0508
Dor Arbeitshub des Hubzylinders 19 wird über seine Kolbenstange 25 auf die Kolbenstange 26 des oberhalb angeordneten Hubzylinders 20 übertragen, wodurch dieser sowie der an ihm befestigte Hubzylinder 21 angehoben werden, welch letzterer durch seine Kolbenstange 27 die Tragplatte 17 anhebt.The working stroke of the lifting cylinder 19 is via its piston rod 25 transferred to the piston rod 26 of the lifting cylinder 20 arranged above, whereby this as well as the one on it attached lifting cylinder 21 are raised, the latter lifting the support plate 17 through its piston rod 27.
Um an dem Werkstück des in der Arbeitsstation 10 mittels des Anschlags 16 stillgesetzten Werkstückträgers 11 einen Arbeitsgang, beispielsweise einen Montagevorgang oder Bearbeitungsvorgang, durchführen zu können, muß der Werkstückträger 11 in der Arbeitsstation in einer fixierten Lage festgespannt werden. Dieses Festspannen erfolgt dadurch, daß der Werkstückträger vom Rollenförderer 12 abgehoben und so weit vertikal nach aufwärts bewegt wird, daß es durch Aneinanderdrücken von Anlageflächen 29, die in den Eckbereichen des Werkstückträgers ausgebildet sind,und ortsfest an der Arbeitsstation angeordneten Anlageflächen 30 zum Festklemmen des Werkstückträgers 11 kommt. Die Anlageflächen 30 der Arbeitsstation sind durch die Unterseite von Klemmleisten 31 gebildet, die an Böcken 32 befestigt sind, die ihrerseits auf dem Gestell 15 der Arbeitsstation befestigt sind. In order to work on the workpiece in the workstation 10 by means of the Stop 16 stopped workpiece carrier 11 one operation, For example, to be able to carry out an assembly process or machining process, the workpiece carrier 11 in the workstation can be clamped in a fixed position. This clamping takes place in that the workpiece carrier is lifted from the roller conveyor 12 and so far vertical is moved upwards by pressing together Contact surfaces 29, which are in the corner areas of the workpiece carrier are formed, and arranged stationary on the workstation Contact surfaces 30 for clamping the workpiece carrier 11 comes. The contact surfaces 30 of the workstation are through the The underside is formed by clamping strips 31 which are fastened to brackets 32 which in turn are fastened to the frame 15 of the work station.
Der Fixierhub zum Festspannen des Werkstückträgers 11 in der Arbeitsstation 10 wird durch einen Hubteller 33 erreicht, der über ein Zwischenstück 34 mit der Tragplatte 17 verbunden ist. Unterhalb des Zwischenstücks 34 ist die Kolbenstange 27 an der Tragplatte 17 befestigt. An der Oberseite des Hubtellers 33 sind eine sich radial über den Tellerrand nach außen erstreckende Platte 35, siehe insbesondere Fig. 3, zwei Positionierstifte 36 und 37 sowie zwei Auflagescheiben 38 und 39 angebracht. Am radial außen liegenden Ende ist die Platte 35 nach oben senkrecht zur Bildung des bereits erwähnten Anschlags 16 abgewinkelt. Die Positionierstifte 36 und 37 weisen in ihren unteren Bereich je einen Bund 40 bzw. 41 auf, deren Höhe, gemessen von der Oberseite des Hubtellers 33, der Höhe der Platte 35 und der Auflage-The fixing stroke for clamping the workpiece carrier 11 in the Work station 10 is reached by a lifting plate 33 which is connected to the support plate 17 via an intermediate piece 34. The piston rod 27 is fastened to the support plate 17 below the intermediate piece 34. On the top of the lifting plate 33 are a plate 35 extending radially outward beyond the rim of the cup, see in particular FIG. 3, two positioning pins 36 and 37 and two support washers 38 and 39 attached. At the radially outer end, the plate 35 is perpendicular to the top angled to form the abovementioned stop 16. The positioning pins 36 and 37 point in their lower area each have a collar 40 or 41, the height of which, measured from the top of the lifting plate 33, the height of the plate 35 and the support
030017/0508030017/0508
scheiben 38 und 39 entspricht. Die Oberseiten der Bunde 40, 41, der Platte 35 und der Auflagescheiben 38 und 39 bilden die Auflageflächen, die sich an die Unterseite des Werkstückträger 11 anlegen, um diesan beim Fixierhub für das Festspannen in der Arbeitsstation anzuheben. Dabei treten die Positionierstifte 36 und 37 in zugeordnete Fixierbohrungen 42 bzw. 43 (siehe Fig. 2) des Wsrkstückträgers 11 ein.washers 38 and 39 corresponds. The tops of the collars 40, 41, the plate 35 and the support washers 38 and 39 form the support surfaces which are attached to the underside of the workpiece carrier 11 in order to lift it up during the fixing stroke for clamping in the workstation. The positioning pins occur 36 and 37 into associated fixing bores 42 and 43 (see FIG. 2) of the workpiece carrier 11.
Dor Fixierhub des vom Anschlag 16 angehaltenen Werkstückträg-srs 11 erfolgtThe fixing stroke of the workpiece carrier stopped by the stop 16 11 takes place
in zwei Hubstufen, von denen die erste Hubstufe zum Vorpositionieren des Werkstucktragers 11 vor dem Festklemmen desselben in der Arbeitsstation dient. Für diese Hubstufe wird der Hubzylinder 20 betätigt, um den Hubteller 33 so weit anzuheben, daß die für den Vorgang des Vorpositionierens dienenden Positionierstifte 36 und 37 in die Fixierbohrungen 42 und 43 eintreten und der Werkstückträger 11 durch Anlegen der Auflageflächen des Hubtellers 33 sodann vom Rollenförderer 12 abgehoben und aus der in Fig. 4 mit ausgezogenen Linien eingezeichneten Transportstellung in eine mit gestrichelten Linien angedeutete Zwischenstellung nach oben bewegt wird, in der sich die Anlageflächen 29 noch in einem beträchtlichen Abstand von den ortsfesten Anlageflächen 30 befinden. Wird nach dem Vorpositionieren sodann durch zusätzliches Betätigen des Hubzylinders 21 die zweite Hubstufe durchgeführt, so wird der Werkstückträger 11 über diese Zwischenstellung hinaus so weit angehoben, daß die Anlageflächen 29 und 30 aneinandergepreßt v/erden und dadurch der Werkstückträger 11 in der Arbeitsstation 10 festgekleromt wird. Diese zweite Hubstufe des Fixierhubs des Werkstückträgers 11 ist in Fig. 4 ebenfalls mit gestrichelten Linien angedeutet.in two lifting stages, of which the first lifting stage is used for prepositioning of the workpiece carrier 11 before clamping the same in serves the workstation. The lift cylinder is used for this lift stage 20 actuated to raise the lifting plate 33 so far that the positioning pins used for the prepositioning process 36 and 37 enter the fixing bores 42 and 43 and the workpiece carrier 11 by applying the support surfaces of the Lifting plate 33 is then lifted off the roller conveyor 12 and out of the transport position shown in solid lines in FIG. 4 is moved up into an intermediate position indicated by dashed lines, in which the contact surfaces are 29 are still at a considerable distance from the stationary contact surfaces 30. Used after prepositioning the second lifting stage is then carried out by additionally actuating the lifting cylinder 21, the workpiece carrier 11 becomes Raised beyond this intermediate position so far that the contact surfaces 29 and 30 are pressed against one another and thus earthed the workpiece carrier 11 is festgekleromt in the work station 10 will. This second stroke stage of the fixing stroke of the workpiece carrier 11 is also indicated in FIG. 4 with dashed lines.
Der Durchmesser der zum Vorpositionieren dienenden Stifte 36 und 37 ist etwas geringer als derjenige der zugeordneten Fixierbohrungen 42 und 43. Das bedeutet, daß beim Vorpositionieren der Werkstückträger 11 noch nicht in eine besonders genau definierte Lage ausgerichtet wird, sondern zunächst nur eine Lageausrichtung innerhalb eines verhältnismäßig breiten ToleranzbereichsThe diameter of the pins 36 and 37 used for prepositioning is somewhat smaller than that of the associated fixing bores 42 and 43. This means that when prepositioning the workpiece carrier 11 not yet in a particularly precisely defined Position is aligned, but initially only a position alignment within a relatively wide tolerance range
030017/0 50 3030017/0 50 3
stattfindet. Durch den vergleichsweise geringen Durchmesser der Stifte 37 und 38 relativ zu den zugeordneten Bohrungen ergibt sich der Vorteil, daß ein sicheres Einfahren der Stifte in die Bohrungen gewährleistet ist, obgleich der Werkstückträger durch den Rollenförderer 12 in verhältnismäßig wenig kontrollierter Lageausrichtung zugeführt wird und nur ein einfacher und billiger Anschlag 16 zum Stillsetzen des Werkstückträgers verwendet wird. Wenn in der betreffenden Arbeitsstationtakes place. Due to the comparatively small diameter of the pins 37 and 38 relative to the associated bores there is the advantage that a safe retraction of the pins into the bores is guaranteed, although the workpiece carrier is fed by the roller conveyor 12 in a relatively uncontrolled positional alignment and only a simple one and cheap stop 16 is used to stop the workpiece carrier. If in the workstation in question
Arbeitsgänge ausgeführt werden, die keine überaus genaue Positionierung des Werkstücks und damit des Werkstückträgers erforderlich machen, kann dieser in der Lageausrichtung, in der er sich nach dem Vorpositionieren befindet, ohne weiteres in der zweiten Hubstufe an den ortsfesten Anlageflächen 30 festgeklemmt werden. Falls jedoch eine sehr genaue Lageausrichtung des Werkstückträgers 11 in der Arbeitsstation 10 erforderlich ist, wird bei der zweiten Hubstufe vor dem Festklemmen eine Feinpositionierung durchgeführt. Zu diesem Zweck erstrecken sich in zwei einander diametral gegenüberliegenden Eckbereichen des Werkstückträgers 11 innerhalb des Gebiets der Anlageflächen 29 angeordnete Feinpositionierstifte 45 und 46 nach oben. Diese Feinpositionierstifte sind für den Eingriff in Feinpositionierbohrungen 48 und 49 vorgesehen, die in Buchsen 50 ausgebildet sind, die in Aussparungen der Klemmleisten 31 einsetzbar sind.Operations are carried out that do not have an extremely precise positioning of the workpiece and thus of the workpiece carrier make necessary, this can easily be done in the positional orientation in which it is located after prepositioning are clamped to the stationary contact surfaces 30 in the second lifting stage. If, however, a very precise orientation of the workpiece carrier 11 is required in the work station 10, is in the second lifting stage before clamping fine positioning carried out. To this end, extend in two diametrically opposed Fine positioning pins 45 and 46 arranged in the corner areas of the workpiece carrier 11 within the area of the contact surfaces 29 up. These fine positioning pins are for engagement provided in fine positioning bores 48 and 49, which are formed in sockets 50, which are in recesses in the terminal strips 31 can be used.
Bei der zweiten Hubstufe des Werkstückträgers 11 erfolgt das Einfahren der Feinpositionierstifte 45, 46 in die Feinpositionierbohrungen 48 und 49 mit hoher Betriebssicherheit, da der Werkstückträger 11 durch das vorausgegangene Vorpositionieren bereits eine ziemlich genau definierte Lage einnimmt, so daß ein Hineinfinden der Stifte in die Bohrungen, ohne daß besondere Vorkehrungen erforderlich wären, erfolgen kann.In the second stroke stage of the workpiece carrier 11, the fine positioning pins 45, 46 are moved into the fine positioning bores 48 and 49 with high operational reliability, since the workpiece carrier 11 has been pre-positioned already occupies a fairly well-defined position, so that the pins can be found in the bores without any special Precautions would be required, can be made.
Wenn, wie bereits erwähnt, eine Feinpositionierung des Werkstückträgers 11 in einer betreffenden Arbeitsstation nicht erforderlich ist, so daß der Werkstückträger 11 in der nach dem Vorpositionieren eingenommenen Lage ohne weiteres an der Arbeitsstation festgeklemmt werden kann, können die Buchsen 50 in If, as already mentioned, fine positioning of the workpiece carrier 11 is not required in a relevant work station, so that the workpiece carrier 11 in the after prepositioning assumed position can easily be clamped at the workstation, the sockets 50 in
030017/0508030017/0508
den Klemmleisten 31 weggelassen werden, so daß sich die Fsinpositionierstifte 45, 46 ohne Feinpositionierung in die von den Buchsen 50 freigelassenen Aussparungen bei der zweiten Hubstufe hineinerstrecken, wenn der Werkstückträger 11 festgeklemmt wird. Das Weglassen der genau bearbeiteten Buchsen 50 erbringt eins wesentliche Verbilligung der Herstellungskosten der betreffenden Arbeitsstation. Falls bei allen Arbeitsstationsn einer Fertigungsstraße die Genauigkeit des Ausrichtens durch die Vorfixierung des Wcrkstückträgers für den jeweiligen Arbeitsgang ausreicht, können die Positionierstifte 48 und 49 auch v/eggelassen werden.the clamping strips 31 are omitted, so that the Fsinpositionierstifte 45, 46 extend without fine positioning into the recesses left free by the sockets 50 in the second lifting stage when the workpiece carrier 11 is clamped. The omission of the precisely machined sockets 50 results in a substantial reduction in the manufacturing costs of the work station in question. If the alignment accuracy of all workstations in a production line is sufficient for the respective work step by pre-fixing the workpiece carrier, the positioning pins 48 and 49 can also be omitted.
Da beim dargestellten Ausführungsbeispiel vier Klemmleisten 31 an den Arbeitsstationen vorhanden sind, können, falls es gewünscht wird, alle Klemmleisten 31 mit Buchsen 50 mit Feinpositionierbohrungen versehen sein, so daß außer den Feinpositionierbohrungen 48 und 49 gegebenenfalls zwei weitere Feinpositionierbohrungen 58, 59 vorhanden sind, wie es in Fig. 3 mit gestrichelter Linie angedeutet ist.Since there are four terminal strips 31 at the work stations in the illustrated embodiment, if it is desired that all terminal strips 31 be provided with sockets 50 with Feinpositionierbohrungen so that except for the Fine positioning bores 48 and 49, if necessary, two further fine positioning bores 58, 59 are present, as shown in FIG Fig. 3 is indicated with a dashed line.
Die Aufteilung des Fixierhubs in zwei Hubstufen eröffnet die besonders vorteilhafte Möglichkeit, den Werkstückträger 11, der in der Arbeitsstation zum Stillstand gebracht worden ist, in der Arbeitsstation selbst zu verdrehen. Vor und hinter den Arbeitsstationen angeordnete, gesonderte Drehstationen werden dadurch überflüssig gemacht. Die Werkstückträger 11 können, unabhängig davon, in welcher Drehstellung der Arbeitsgang in den betreffenden ArbeitsStationen ausgeführt werden soll, also immer in einer bestimmten gleichbleibenden Transportausrichtung auf dem Rollenförderer 12 zwischen den Arbsitsstationen 10 transportiert werden, so daß die Werkstückträger nicht an sämtlichen vier Seiten mit Puffern 52 versehen sein müssen, sondern lediglich an der bsi der Transportausrichtung vorderen Seite und der gegenüberliegenden, hinteren Seite. Entsprechendes gilt für die Anschlagfläche 22, die, obwohl in der Zeichnung zwei Anschlagflächen 22 dargestellt sind.The division of the fixing stroke into two stroke stages opens up the particularly advantageous possibility of using the workpiece carrier 11, which has been brought to a standstill in the workstation, to twist in the workstation itself. Separate turning stations are arranged in front of and behind the work stations thereby made superfluous. The workpiece carriers 11 can, regardless of the rotational position in which the operation be carried out in the relevant workstations should, so always in a certain constant transport orientation on the roller conveyor 12 between the work stations 10 are transported so that the workpiece carriers are not provided with buffers 52 on all four sides must, but only on the front side of the transport orientation and the opposite, rear side. The same applies to the stop surface 22 which, although two stop surfaces 22 are shown in the drawing.
03001 7/050803001 7/0508
nur an dar in Transportrichtung vorderen Seite am Werkstückträger 11 vorhanden zu sein braucht.only on the front side in the transport direction on the workpiece carrier 11 needs to be present.
Der Ilubteller 33 dient als Teil dar Dreheinrichtung für das Verdrehen des Werkstückträgers 11, die beira Ausführungsbcispiel für Verdrehwinkel bis etwa 100° ausgelegt ist. Kommen größere Winkel in Betracht, werden andersartige bekannte Drch£.inrichtunge.n, z.B. Sahnstangenantriebe, zum. Einsatz gebracht. Beim Ausführungsbaispiel ist das Zwischenstück 34, das mit dem Hubteller 33 fest verbunden ist, auf der Tragplatte 17 drehbar gelagert. Ein sich vom Zwischenstück 34 radial erstreckender Schwenkarm 53 ist an einer KolbenstangeThe Ilubteller 33 serves as part of the rotating device for the Rotation of the workpiece carrier 11, which beira exemplary embodiment is designed for angles of rotation up to about 100 °. If larger angles come into consideration, different types are known Drch £ .inrichtunge.n, e.g. cream stick drives, for. mission brought. In the exemplary embodiment, the intermediate piece 34, which is firmly connected to the lifting plate 33, rotatably mounted on the support plate 17. A from the intermediate piece 34 radially extending pivot arm 53 is on a piston rod
54 eines bei 55" schwenkbar an einem Ansatz 17' der Tragplatte 17 gelagerten Schwenkzylinder 55 angelenkt. Nach erfolgten Vorpositionieren, wenn der Werkstückträger 11 vom Rollenförderer 12 abgehoben und in eine Zwischenstellung angehoben ist, in der (siehe Fig. 4) noch keine Fixierung stattgefunden hat, wird eine durch Betätigen des Schwenkzylinders54 one at 55 "pivotable on a shoulder 17 'of the support plate 17 mounted pivot cylinder 55 articulated. After prepositioning, when the workpiece carrier 11 from the roller conveyor 12 is lifted and raised into an intermediate position in which (see FIG. 4) no fixation has yet taken place one is made by actuating the swivel cylinder
55 veranlaßte Drehbewegung des hubtellers 33 auf den Werkstückträger 11 übertragen, wobei die für das Vorpositionieren vorgesehenen Positionierstifte 36, 37 als Mitnehmer wirken.55 induced rotary movement of the lifting plate 33 on the workpiece carrier 11, with the positioning pins 36, 37 provided for prepositioning acting as drivers.
Wenn bei einer Arbsitsstation mit Dreheinrichtung ein von 90 oder 130 verschiedener Verdrehwinkel vorkommt, können in dit-ser Arbeitsstation anstelle von vier Klemmleisten 31, an uenen die Anlageflachen 29 des W-rkstückträgers 11 festgespannt werden, nur zwei anders Klc-i..nleist3n vorgesehen sain, da bei solchen Drehwinkeln in der Rtg&l zwei diametral gegenüberliegende Eckbereiche des Werkstückträgers 11 sich innerhalb des Bereichs der Transportband befinden, der frei von Vorrichtungsteilen bleiben muß. In einem solchen Falle ist es gegebenenfalls erforderlich, am Werkstückträger 11 nicht nur zwei einander diametral gegenüberliegende Feinpositionierstifte 45, 46 vorzusehen, sondern für das Zusammenwirken mit den in der betreffenden /^rbeitsstation entsprechend angeordneten Klemmleisten ein weiteres Paar von einander diametral gegenüberliegenden Feinpositionierstiften 56 undIf at a work station with a rotating device one of 90 or 130 different angles of rotation occur, instead of four terminal strips 31, the contact surfaces 29 of the workpiece carrier 11 are clamped firmly on the outside are provided, only two different Klc-i..nleist3n sain, since with such angles of rotation in the Rtg & l two diametrical opposite corner areas of the workpiece carrier 11 are located within the area of the conveyor belt, which must remain free of device parts. In such a case it may be necessary to not only have two diametrically opposed fine positioning pins on the workpiece carrier 11 45, 46, but for the interaction with those in the relevant workstation arranged terminal strips another pair of diametrically opposed fine positioning pins 56 and
030017/0508030017/0508
in den anderen beiden L'ckbereichen innerhalb der Anlageflächan
29 anzuordnen, und zwar, wie es in Fig. 2 mit gestrichelter Linie angedeutet ist, vorzugsweise in einer zur Drehachse
U^r Ür~hbe-./e jung des Werkstückträgers 11 symmetrischen Lageanordnung,
wie dies vorzugsweise auch bei den anderen Feinpositionierstiften
der Fall ist.to be arranged in the other two corner areas within the contact surface 29, as indicated in FIG. 2 with a dashed line, preferably in one to the axis of rotation
U ^ r Ür ~ hbe -. / E young of the workpiece carrier 11 symmetrical positional arrangement, as is preferably also the case with the other fine positioning pins.
bei der in der Zeichnung dargestellten /uisführungsforru sind
die Klemmleisten 31 rait den Feinpositionierbohrungen so angeordnet,
daß ein Verdrehen und Festklemmen des VZerkstiickträgers
11 nur bsi Drehbewegungen um 90 oder 180 möglich
ist.In the guiding form shown in the drawing, the clamping strips 31 are arranged along the fine positioning bores in such a way that the VZerkstiickträgers 11 can only be rotated and clamped by 90 or 180 rotational movements
is.
Claims (7)
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE19787831423 DE7831423U1 (en) | 1978-10-21 | 1978-10-21 | Work station for a production line, in particular for an assembly machine |
| DE19782845913 DE2845913A1 (en) | 1978-10-21 | 1978-10-21 | WORKSTATION FOR A PRODUCTION LINE, IN PARTICULAR FOR AN ASSEMBLY MACHINE |
| GB7936352A GB2035942A (en) | 1978-10-21 | 1979-10-19 | Positioning apparatus for a workpiece carrier |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE19782845913 DE2845913A1 (en) | 1978-10-21 | 1978-10-21 | WORKSTATION FOR A PRODUCTION LINE, IN PARTICULAR FOR AN ASSEMBLY MACHINE |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE2845913A1 true DE2845913A1 (en) | 1980-04-24 |
Family
ID=6052782
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DE19782845913 Withdrawn DE2845913A1 (en) | 1978-10-21 | 1978-10-21 | WORKSTATION FOR A PRODUCTION LINE, IN PARTICULAR FOR AN ASSEMBLY MACHINE |
| DE19787831423 Expired DE7831423U1 (en) | 1978-10-21 | 1978-10-21 | Work station for a production line, in particular for an assembly machine |
Family Applications After (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DE19787831423 Expired DE7831423U1 (en) | 1978-10-21 | 1978-10-21 | Work station for a production line, in particular for an assembly machine |
Country Status (2)
| Country | Link |
|---|---|
| DE (2) | DE2845913A1 (en) |
| GB (1) | GB2035942A (en) |
Cited By (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2950292A1 (en) * | 1979-01-08 | 1980-07-17 | La Salle Machine Tool | DEVICE FOR ALIGNING AND CLAMPING A WORKPIECE CARRIER |
| EP0048677A1 (en) * | 1980-08-28 | 1982-03-31 | Société Roland BAILLY Assemblages | Universal working stand of the table-type having exchangeable supporting plates |
| DE3628760A1 (en) * | 1985-09-03 | 1987-03-26 | Menziken Ag Maschf | Assembly and machining installation |
| EP0179955A3 (en) * | 1984-10-30 | 1987-06-10 | International Business Machines Corporation | Robotic assembly system |
| DE3621604A1 (en) * | 1986-06-27 | 1988-03-10 | Kessler Kg Maschf | CLAMPING DEVICE FOR PALLETS |
| US4736830A (en) * | 1985-09-09 | 1988-04-12 | Maschinenfabrik Ag Menziken | Production line system |
| DE3714716A1 (en) * | 1987-05-02 | 1988-11-10 | Herbert Hess | Clamping device |
| EP0308249A3 (en) * | 1987-09-17 | 1989-07-19 | Deere & Company | Lifting apparatus for use in assembling vehicles or other products |
| EP0255027A3 (en) * | 1986-07-30 | 1989-08-16 | Stribel GmbH | Assembling plant |
| DE3930371A1 (en) * | 1989-09-12 | 1991-03-21 | Schunk Automation Gmbh | ASSEMBLY STATION WITH A CONVEYOR FOR WORKPIECE CARRIERS |
| DE4019031A1 (en) * | 1990-06-14 | 1991-12-19 | Tetra Pak Gmbh | DEVICE FOR TURNING WORKPIECES, IN PARTICULAR TO TURN SLEEVES |
| CN103769836A (en) * | 2014-01-06 | 2014-05-07 | 汕头大学 | Rapid-replacement system for roller module |
| DE102014208018A1 (en) * | 2014-04-29 | 2015-10-29 | Robert Bosch Gmbh | Device for turning workpiece carriers on a conveyor line |
| CN105347006A (en) * | 2015-11-16 | 2016-02-24 | 彭方 | Automatic feeding device |
| CN106956161A (en) * | 2017-03-01 | 2017-07-18 | 姜�硕 | A kind of PCB board separators high-precision plate automatic lifting mechanism of screw rod hoisting type |
| CN107570726A (en) * | 2017-10-10 | 2018-01-12 | 浙江金汤机床有限公司 | The continuous full-automatic processing cnc lathe of engine valve and its method |
| CN108946123A (en) * | 2018-08-17 | 2018-12-07 | 芜湖安普机器人产业技术研究院有限公司 | A kind of more specification thin plate part jacking feeding devices |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5851530A (en) * | 1981-09-22 | 1983-03-26 | Toshiba Corp | Apparatus and method of arranging semiconductor pellet |
| JPH0818656B2 (en) * | 1986-10-15 | 1996-02-28 | ソニー株式会社 | Roller conveyor |
| US5933941A (en) * | 1997-09-02 | 1999-08-10 | Haeger, Inc. | Cantilevered X-Y positioning system for fastener insertion machine |
| DE19934866A1 (en) * | 1999-07-24 | 2001-01-25 | Bosch Gmbh Robert | Workpiece carriers, especially for manual conveyor tracks |
| KR100428338B1 (en) * | 2001-10-16 | 2004-04-28 | 현대자동차주식회사 | Jig device for bolster assembly of vehicle |
| CN111942863A (en) * | 2020-08-13 | 2020-11-17 | 张小友 | Transfer rotating frame for conveying moving frame for motor stator machining |
-
1978
- 1978-10-21 DE DE19782845913 patent/DE2845913A1/en not_active Withdrawn
- 1978-10-21 DE DE19787831423 patent/DE7831423U1/en not_active Expired
-
1979
- 1979-10-19 GB GB7936352A patent/GB2035942A/en not_active Withdrawn
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2950292A1 (en) * | 1979-01-08 | 1980-07-17 | La Salle Machine Tool | DEVICE FOR ALIGNING AND CLAMPING A WORKPIECE CARRIER |
| EP0048677A1 (en) * | 1980-08-28 | 1982-03-31 | Société Roland BAILLY Assemblages | Universal working stand of the table-type having exchangeable supporting plates |
| EP0179955A3 (en) * | 1984-10-30 | 1987-06-10 | International Business Machines Corporation | Robotic assembly system |
| DE3628760A1 (en) * | 1985-09-03 | 1987-03-26 | Menziken Ag Maschf | Assembly and machining installation |
| US4736830A (en) * | 1985-09-09 | 1988-04-12 | Maschinenfabrik Ag Menziken | Production line system |
| DE3621604A1 (en) * | 1986-06-27 | 1988-03-10 | Kessler Kg Maschf | CLAMPING DEVICE FOR PALLETS |
| US4898269A (en) * | 1986-06-27 | 1990-02-06 | Alfing Kessler Sondermaschinen Gmbh | Clamping device for pallets |
| EP0255027A3 (en) * | 1986-07-30 | 1989-08-16 | Stribel GmbH | Assembling plant |
| DE3714716A1 (en) * | 1987-05-02 | 1988-11-10 | Herbert Hess | Clamping device |
| EP0308249A3 (en) * | 1987-09-17 | 1989-07-19 | Deere & Company | Lifting apparatus for use in assembling vehicles or other products |
| DE3930371A1 (en) * | 1989-09-12 | 1991-03-21 | Schunk Automation Gmbh | ASSEMBLY STATION WITH A CONVEYOR FOR WORKPIECE CARRIERS |
| DE4019031A1 (en) * | 1990-06-14 | 1991-12-19 | Tetra Pak Gmbh | DEVICE FOR TURNING WORKPIECES, IN PARTICULAR TO TURN SLEEVES |
| US5172801A (en) * | 1990-06-14 | 1992-12-22 | Tetra Pak Holdings S.A. | Device for twisting workpieces, particularly for turning casings |
| CN103769836A (en) * | 2014-01-06 | 2014-05-07 | 汕头大学 | Rapid-replacement system for roller module |
| CN103769836B (en) * | 2014-01-06 | 2016-04-20 | 汕头大学 | Roller module fast replacement system |
| DE102014208018A1 (en) * | 2014-04-29 | 2015-10-29 | Robert Bosch Gmbh | Device for turning workpiece carriers on a conveyor line |
| CN105347006A (en) * | 2015-11-16 | 2016-02-24 | 彭方 | Automatic feeding device |
| CN105347006B (en) * | 2015-11-16 | 2018-03-16 | 彭方 | Automatic feeding |
| CN106956161A (en) * | 2017-03-01 | 2017-07-18 | 姜�硕 | A kind of PCB board separators high-precision plate automatic lifting mechanism of screw rod hoisting type |
| CN107570726A (en) * | 2017-10-10 | 2018-01-12 | 浙江金汤机床有限公司 | The continuous full-automatic processing cnc lathe of engine valve and its method |
| CN107570726B (en) * | 2017-10-10 | 2023-06-06 | 浙江金汤机床有限公司 | Special numerical control lathe and method for continuous automatic machining of engine valves |
| CN108946123A (en) * | 2018-08-17 | 2018-12-07 | 芜湖安普机器人产业技术研究院有限公司 | A kind of more specification thin plate part jacking feeding devices |
Also Published As
| Publication number | Publication date |
|---|---|
| DE7831423U1 (en) | 1979-04-12 |
| GB2035942A (en) | 1980-06-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DE2845913A1 (en) | WORKSTATION FOR A PRODUCTION LINE, IN PARTICULAR FOR AN ASSEMBLY MACHINE | |
| DE3304090C2 (en) | ||
| DE3618584C2 (en) | ||
| DE4100477A1 (en) | DEVICE FOR TREATING OBJECTS | |
| DD292407A5 (en) | MANUFACTURING INSTALLATION FOR WORKING AND ASSEMBLING COMPONENTS | |
| AT398922B (en) | HOUSING PART FOR A WORK OR MACHINING STATION OF A PRODUCTION PLANT | |
| DE69003391T2 (en) | Press line arrangement. | |
| DE69005628T2 (en) | DEVICE FOR FEEDING LONG OBJECTS LIKE TREE TRUNKS. | |
| DE3246129C2 (en) | Device for precisely stopping vehicles | |
| EP0276358A2 (en) | Apparatus for applying type to edges | |
| DE8902668U1 (en) | Positioning device for precise transfer of workpieces | |
| DE3345920C2 (en) | Device for automatic transport of workpieces | |
| AT525842A2 (en) | production line | |
| DE8813730U1 (en) | Assembly and/or production line section with transport plates carrying workpieces | |
| EP0063253A2 (en) | Device for automatically aligning and centralising of workpieces | |
| DE2444172A1 (en) | SYSTEM FOR THE SURFACE TREATMENT OF WORK PIECES, IN PARTICULAR FOR WASHING METAL PARTS | |
| DE3906616C2 (en) | ||
| DE4034592A1 (en) | Stacking storage system with fully automated loading and unloading - has entrainment element triggering release of locking element | |
| WO2001058746A1 (en) | Transport system used in body shell assembly of vehicle bodies | |
| WO2007143763A1 (en) | Transport installation for parts carriers | |
| DE2717536C3 (en) | Corner drive for piece goods | |
| DE3412575C2 (en) | Conveyor device | |
| DE1300227B (en) | Transfer device for the rotation-free transfer of workpieces, especially window frames, doors and the like. like | |
| DE2430737C3 (en) | Turntable | |
| DE69102057T2 (en) | ALIGNMENT BENCH FOR VEHICLE BODY. |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| OAP | Request for examination filed | ||
| OD | Request for examination | ||
| 8130 | Withdrawal |