DE10311841A1 - Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection - Google Patents

Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection Download PDF

Info

Publication number
DE10311841A1
DE10311841A1 DE10311841A DE10311841A DE10311841A1 DE 10311841 A1 DE10311841 A1 DE 10311841A1 DE 10311841 A DE10311841 A DE 10311841A DE 10311841 A DE10311841 A DE 10311841A DE 10311841 A1 DE10311841 A1 DE 10311841A1
Authority
DE
Germany
Prior art keywords
screw
screw connection
connection part
part according
opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE10311841A
Other languages
German (de)
Inventor
Erwin Keller
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE10311841A priority Critical patent/DE10311841A1/en
Publication of DE10311841A1 publication Critical patent/DE10311841A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B13/00Dowels or other devices fastened in walls or the like by inserting them in holes made therein for that purpose
    • F16B13/14Non-metallic plugs or sleeves; Use of liquid, loose solid or kneadable material therefor
    • F16B13/141Fixing plugs in holes by the use of settable material
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B35/00Screw-bolts; Stay-bolts; Screw-threaded studs; Screws; Set screws
    • F16B35/04Screw-bolts; Stay-bolts; Screw-threaded studs; Screws; Set screws with specially-shaped head or shaft in order to fix the bolt on or in an object
    • F16B35/041Specially-shaped shafts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B43/00Washers or equivalent devices; Other devices for supporting bolt-heads or nuts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B5/00Joining sheets or plates, e.g. panels, to one another or to strips or bars parallel to them
    • F16B5/02Joining sheets or plates, e.g. panels, to one another or to strips or bars parallel to them by means of fastening members using screw-thread

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bolts, Nuts, And Washers (AREA)

Abstract

The screw connection part has a bolt (10) passing through communicating passages in the parts (13,14) to be joined, a nut (18) for screwing onto the bolt shaft and any washers (16,17) used. A channel arrangement is provided for passing a setting material into the gap (23,24) between the shaft and a wall of at least one passage after making the screw connection. An independent claim is also included for the following: (a) a method of making a screw connection compressing at least two parts together.

Description

Die Erfindung betrifft ein Schraubverbindungsteil zur Herstellung einer mindestens zwei Bauteile zusammenpressenden Schraubverbindung, die eine miteinander kommunizierende Durchbrechungen der Bauteile durchsetzende Schraube, eine auf den Schraubenschaft aufschraubbare Mutter und eventuell eines der Bauteile und/oder mindestens eine unter der Mutter und/oder dem Schraubenkopf platzierbare Unterlegscheibe aufweist. Die Erfindung betrifft ferner ein Verfahren zur Herstellung einer mindestens zwei Bauteile zusammenpressenden Schraubverbindung, insbesondere beim Aufbau eines Gittermastes einer Windkraftanlage, mit den Schritten: Durchstecken einer Schraube in miteinander kommunzierende Durchbrechungen der aneinandergesetzten Bauteile, Aufschrauben einer Mutter auf den Schraubenschaft und Festziehen der Schraubverbindung.The invention relates to a screw connection part for the production of at least two components Bolted connection, which communicates with one another through openings of the screw passing through the components, one on the screw shaft screw-on nut and possibly one of the components and / or at least one that can be placed under the nut and / or the screw head Has washer. The invention further relates to a method for producing a screw connection that presses at least two components together, especially when building a lattice mast of a wind turbine, with the steps: inserting a screw into communicating Breakthroughs in the assembled components, screwing on one Nut on the screw shaft and tighten the screw connection.

Bei einer Relativbewegung der beiden durch die Schraubverbindung miteinander verbundenen Bauteile wird die Schraubverbindung belastet. Dies gilt insbesondere für Querbewegungen der Bauteile quer zum Schraubenschaft, die bei einer zu hohen Schub-Belastung im Extremfall zu einem Abscheren und somit zu einem Brechen der Schraube führen können. Derartige Belastungen treten insbesondere bei Gittermasten, beispielsweise bei Gittermasten für Windkraftanlagen, auf, die stets wechselnden Winddrücken ausgesetzt sind. Dementsprechend ist es notwendig, die Bauteile mit schubfesten Verbindungen miteinander zu verbinden.With a relative movement of the two components connected to one another by the screw connection the screw connection is loaded. This applies in particular to transverse movements of the components across the screw shank, which are subject to excessive thrust loads in extreme cases, shearing and thus breaking of the Can lead screw. such Loads occur particularly with lattice towers, for example for lattice towers for wind turbines, that are always exposed to changing wind pressures. Accordingly it is necessary to connect the components with shear resistant connections connect to.

Bedingt durch fertigungstechnische Ungenauigkeiten, insbesondere beim Aufbau von Gittermasten im Freien, müssen die Durchbrechungen der Bauteile, die Bohrlöcher, etwas größer sein als die Schraubenschaftdurchmesser der verwendeten Schrauben. Diese Toleranzen führen jedoch später bei der Herstellung einer schubfesten Verbindung zu Problemen.Due to manufacturing technology Inaccuracies, especially when building lattice masts outdoors, have to the openings of the components, the boreholes, should be somewhat larger than the screw shaft diameter of the screws used. This Lead tolerances however later at making a shear-proof connection to problems.

Eine Möglichkeit besteht darin, eine schubfeste Verbindung durch Nieten zu erzielen. Das eingebrachte Nietmaterial verfüllt den gesamten Hohlraum der Bohrlöcher, sodass kein "Spiel" mehr vorhanden ist, also Formschluss erzielt wird.One way is one to achieve a shear-resistant connection by riveting. The brought in Filled riveting material the entire cavity of the boreholes, so that there is no "game" left thus positive locking is achieved.

Ferner werden sogenannte hochfeste Verschraubungen (HV-Verschraubungen) eingesetzt, bei denen mittels einer extrem zugfesten Schraube die beiden Bauteile derart gegeneinander verpresst werden, dass zwischen den Bauteilen Reibschluss erzielt wird und somit die Schubbewegung verhindert oder zumindest stark eingeschränkt wird. Hochfeste Schraubverbindungen sind jedoch teuer.Furthermore, so-called high-strength Screwed connections (HV screwed connections) are used, for which means an extremely tensile screw the two components against each other are pressed in such a way that a frictional connection is achieved between the components and thus prevents the thrust movement or at least strongly limited becomes. However, high-strength screw connections are expensive.

Ferner kann man sogenannte Passschrauben verwenden, bei denen zunächst die Lage der beiden Bauteile relativ zueinander ge sichert werden muss. Dann werden die vorgebohrten Löcher gegebenenfalls auf das exakte Maß aufgebohrt und jedenfalls mittels einer Reibahle gerieben. Zudem müssen geschliffene Schraubenschäfte verwendet werden. Das Verfahren ist äußerst zeitaufwendig und teuer. Es eignet sich zum Aufbau von Gittermasten im Freien nicht. Daher wird in diesen Fällen auf hochfeste Schraubverbindungen zurückgegriffen, die jedoch bei schwingenden Belastungen die Gefahr in sich bergen, dass Material- und/oder Montagefehler zur Zerstörung der Schraubverbindung führen können.You can also use so-called fitting screws use which first the location of the two components must be secured relative to each other. Then the pre-drilled holes if necessary drilled to the exact measure and in any case grated using a reamer. In addition, ground screw shanks must be used become. The process is extremely time consuming and expensive. It is suitable for building lattice masts outdoors Not. Therefore, in these cases resorted to high-strength screw connections, which, however, at vibrating loads carry the risk that material and / or assembly errors to destroy the screw connection can.

Es ist daher die Aufgabe der vorliegenden Erfindung, das eingangs genannte Schraubverbindungsteil zur Herstellung einer schubfesten Schraubverbindung fortzubilden bzw. das Verfahren der eingangs genannten Art derart weiterzuentwickeln, dass eine schubfeste Schraubverbindung erzielt wird.It is therefore the object of the present invention the screw connection part mentioned at the beginning for producing a shear-resistant screw connection or the method of further developed in such a way that a shear-resistant Screw connection is achieved.

Zur Lösung ist bei dem Schraubverbindungsteil der eingangs genannten Art eine Kanalanordnung vorhanden, die dazu vorgesehen ist, um durch sie hindurch bei hergestellter Schraubverbindung eine aushärtbare Füllmasse in einen Zwischenraum zwischen dem Schraubenschaft und einer Wandung zumindest einer der Durchbrechungen einzupressen.The solution is for the screw connection part of the type mentioned a channel arrangement available that is provided to a through it when the screw connection curable filling compound at least in a space between the screw shaft and a wall to press one of the breakthroughs.

In entsprechender Weise ist bei dem Verfahren der eingangs genannten Art ein Einpressen einer aushärtbaren Füllmasse in einen Zwischenraum zwischen dem Schraubenschaft und einer Wandung zumindest einer der Durchbrechungen über eine Kanal anordnung vorgesehen, die in der Schraube und/oder der Mutter und/oder in mindestens einer unter der Mutter und/oder dem Schraubenkopf platzierbaren Unterlegscheibe vorgesehen ist.The same applies to the Method of the type mentioned at the beginning of pressing in a curable filling compound into a space between the screw shaft and a wall at least one of the openings is provided via a channel arrangement, those in the screw and / or the nut and / or in at least one Washer that can be placed under the nut and / or the screw head is provided.

Wenn die Füllmasse, vorzugsweise Gießharz, beispielsweise Epoxidharz, ausgehärtet ist, sitzt die Schraube formschlüssig in den Durchbrechungen der Bauteile, sodass eine Quer-/Schubbewegung der Bauteile relativ zueinander verhindert wird. Dementsprechend schubfest ist die erfindungsgemäße Schraubverbindung. Das Verfahren ist einfach anzuwenden. Besonders zugfeste Schrauben sind nicht unbedingt notwendig. Dadurch kann die Schraubverbindung verhältnismäßig preisgünstig hergestellt werden. Allerdings ist es auch möglich, dass für hochfeste Verbindungen ausgestaltete Schraubverbindungsteile erfindungsgemäß ausgestaltet sind, sodass äußerst schubfeste Schraubverbindungen möglich sind.If the filling compound, preferably cast resin, for example Epoxy resin, hardened is, the screw sits positively in the openings of the components, so that a transverse / pushing movement the components are prevented relative to each other. Accordingly the screw connection according to the invention is resistant to shear. The procedure is easy to use. Particularly tensile screws are not absolutely necessary. As a result, the screw connection can be produced relatively inexpensively become. However, it is also possible that for high strength Connections designed screw connection parts designed according to the invention are so extremely resistant to thrust Screw connections possible are.

Weitere Vorteile der Erfindung ergeben sich aus den abhängigen Ansprüchen sowie aus der Beschreibung.Further advantages of the invention result themselves from the dependent claims as well as from the description.

Vorteilhafterweise weist die Kanalanordnung mindestens eine bei hergestellter Schraubverbindung außenseitig zugängliche Eintrittsöffnung und mindestens eine in den Zwischenraum ausmündende Austrittsöffnung auf. Der mit der Füllmasse zu verfüllende Zwischenraum ist beispielsweise durch den Schraubenkopf und die Schraubenmutter, gegebenenfalls durch eine oder mehrere ein- oder beidseitig angeordnete Unterlegscheiben, verschlossen, sodass durch die Eintrittsöffnung die Füllmasse bequem einbringbar ist.The channel arrangement advantageously has at least one inlet opening that is accessible from the outside when the screw connection is produced and at least one outlet opening that opens into the intermediate space. The space to be filled with the filling compound is closed, for example, by the screw head and the screw nut, if appropriate by one or more washers arranged on one or both sides, so that the filling compound can be conveniently introduced through the inlet opening.

An der Eintrittsöffnung ist zweckmäßigerweise ein Anschlussmittel zum druckdichten Anschließen einer Einpressvorrichtung zum Einpressen der Füllmasse vorgesehen. Das Anschlussmittel ist beispielsweise eine Art Kopf oder Nippel, der von einem Anschlussstück der Einpressvorrichtung umschlossen wird.At the entrance opening is expedient a connection means for the pressure-tight connection of a press-in device for pressing in the filling compound intended. The connection means is, for example, a kind of head or nipple from a connector of the press-in device is enclosed.

Vorteilhaft ist an der mindestens einen Eintrittsöffnung ein Rückschlagventil angeordnet, das ein Zurückfließen der eingepressten Füllmasse aus dem Zwischenraum nach außen verhindert. Diese Ausführungsform wird insbesondere im Zusammenhang mit dem vorgenannten Anschlussmittel bevorzugt. Das Anschlussmittel und das Rückschlagventil bilden dabei vorzugsweise eine Baueinheit, ähnlich einem Schmiernippel.Is advantageous at least an entrance opening a check valve arranged that a backflow of the pressed-in filling compound from the gap to the outside prevented. This embodiment is particularly in connection with the aforementioned connection means prefers. The connection means and the check valve form preferably an assembly similar to one Grease fitting.

Vorzugsweise weist die Kanalanordnung eine oder mehrere Oberflächenvertiefungen und/oder eine oder mehrere Durchtrittskanäle auf. Die offene Seite einer derartigen Oberflächenvertiefung ist vorzugsweise bei hergestellter Schraubverbindung verschlossen, beispielsweise indem die Oberflächenvertiefung auf einem der miteinander zu verbindenden Bauteile zu liegen kommt.The channel arrangement preferably has one or several surface depressions and / or one or more passageways on. The open side of such a surface recess is preferred closed when the screw connection is established, for example by the surface depression comes to rest on one of the components to be connected.

Zweckmäßigerweise mündet bei hergestellter Schraubverbindung in jede der Durchbrechungen jeweils mindestens eine Austrittsöffnung der Kanalanordnung. Diese Maßnahme sorgt für eine optimale Verteilung der Füllmasse im Bereich der Durch brechungen. Prinzipiell wäre jedoch auch nur eine einzige Austrittsöffnung möglich, wenn die Füllmasse von einer Durchbrechung in die andere hineinfließen kann. Bei ausreichendem Einpressdruck ist auch dann eine optimale Verteilung der Füllmasse in den Durchbrechungen möglich.Conveniently flows into manufactured screw connection in each of the openings at least one outlet opening the channel arrangement. This measure ensures an optimal distribution of the filling mass in the area of breakthroughs. In principle, however, would only be one outlet opening possible, if the filling compound can flow from one opening to the other. With sufficient Press-in pressure is then also an optimal distribution of the filling compound possible in the openings.

Bei dem erfindungsgemäßen Schraubverbindungsteil sind mehrere Ausführungsformen möglich: Vorzugsweise ist es als eine Schraube mit einem Schraubenkopf und einem Schraubenschaft ausgestaltet.In the screw connection part according to the invention are several embodiments possible: It is preferably as a screw with a screw head and designed a screw shaft.

Dabei sind zweckmäßigerweise eine Eintrittsöffnung am Schraubenkopf und eine oder mehrere Austrittsöffnungen am radialen Außenumfang des Schraubenschafts angeordnet.An inlet opening is expediently on Screw head and one or more outlet openings on the radial outer circumference the screw shaft arranged.

Die Kanalanordnung der Schraube umfasst zweckmäßigerweise mindestens einen im Wesentlichen in Längsrichtung des Schraubenschafts verlaufenden Längskanal und mindestens einen mit diesem verbundenen, in die mindestens eine Austrittsöffnung mündenden und im Wesentlichen in radialer Richtung verlaufenden Radialkanal.The channel arrangement of the screw expediently comprises at least one essentially in the longitudinal direction of the screw shaft longitudinal channel and at least one associated with it, into which at least one Outlet opening and radial channel running essentially in the radial direction.

Vorzugsweise sind am Schraubenschaft axial zueinander beabstandete Austrittsöffnungen vorhanden. Dabei ist zweckmäßigerweise jeweils mindestens eine Austrittsöffnung einer Bauteil-Durchbrechung zugeordnet.Preferably on the screw shaft axially spaced outlet openings available. It is expediently at least one outlet opening of a component opening assigned.

Vorteilhaft sind die Austrittsöffnungen über den Umfang des Schraubenschafts verteilt. Diese Maßnahme bewirkt ebenso wie die vorher genannten Maßnahmen eine besonders gleichmäßige Verteilung der Füllmasse im Bereich der Durchbrechungen.The outlet openings above the are advantageous Circumference of the screw shaft distributed. This measure has the same effect as that previously mentioned measures a particularly even distribution the filling mass in the area of the breakthroughs.

Weiterhin ist das Schraubverbindungsteil vorteilhaft als Unterlegscheibe oder auch als Mutter ausgestaltet.The screw connection part is also advantageous designed as a washer or as a nut.

Es versteht sich, dass beliebige Kombinationen bekannter Schraubverbindungsteile zusammen mit den erfindungsgemäßen Schraubverbindungsteilen verwendet werden können. Beispielsweise können eine bekannte Schraube und eine bekannte Mutter zusammen mit einer erfindungsgemäßen Unterlegscheibe verwendet werden. Ferner kann eine erfindungsgemäße Schraube zusammen mit einer bekannten Mutter und einer erfindungsgemäßen Unterlegscheibe verwendet werden, wobei zweckmäßigerweise die erfindungsgemäße Unterlegscheibe zwischen der Mutter und dem der Mutter unmittelbar benachbarten Bauteil zu liegen kommt.It goes without saying that any Combinations of known screw connection parts together with the screw connection parts according to the invention can be used. For example a known screw and a known nut together with a washer according to the invention be used. Furthermore, a screw according to the invention can be used together with a known mother and a washer according to the invention used be, expediently the washer according to the invention between the mother and that immediately adjacent to the mother Component comes to rest.

Bei der erfindungsgemäßen Unterlegscheibe bzw. der erfindungsgemäßen Mutter ist die Eintrittsöffnung zweckmäßigerweise jeweils an der Stirnseite angeordnet und die mindestens eine Austrittsöffnung im Bereich einer Durchstecköffnung der Unterlegscheibe bzw. einer Einschrauböffnung der Mutter.In the washer or the mother of the invention is the entrance opening expediently each arranged on the end face and the at least one outlet opening in the Area of a push-through opening the washer or a screw hole of the nut.

Bei dieser Unterlegscheibe bzw. dieser Mutter sind die Eintrittsöffnung und die Austrittsöffnung zweckmäßigerweise durch mindestens einen radial verlaufenden Verbindungskanal miteinander verbunden.With this washer or this Mother are the entrance opening and the outlet opening expediently through at least one radially extending connecting channel connected.

Die Austrittsöffnung wird zweckmäßigerweise durch eine um die Durchstecköffnung bzw. die Einschrauböffnung zumindest teilweise in Umfangsrichtung verlaufende Oberflächenvertiefung gebildet. Die Oberflächenvertiefung wird bei hergestellter Schraubverbindung durch die Schraube und/oder durch eines der montierten Bauteile verschlossen. Die Oberflächenvertiefung ist zweckmäßigerweise an der der Eintrittsöffnung gegenüberliegenden Stirnseite angeordnet.The outlet opening is expedient through one around the push-through opening or the screw opening surface depression extending at least partially in the circumferential direction educated. The surface depression is with the screw connection made by the screw and / or by locked one of the assembled components. The surface depression is expediently on that of the entrance opening opposite End face arranged.

Eine weitere, besonders bevorzugte Variante sieht eine Ausgestaltung des Schraubverbindungsteils als eines der zu verbindenden Bauteile vor. Die Kanalanordnung zum Einpressen der aushärtbaren Füllmasse kann nämlich auch an einem solchen erfindungsgemäßen Bauteil vorgesehen sein.Another, particularly preferred A variant sees an embodiment of the screw connection part as one of the components to be connected. The channel arrangement for pressing in the curable filling compound can namely can also be provided on such a component according to the invention.

Zweckmäßigerweise weist das Bauteil ebenso wie die oben erläuterte erfindungsgemäße Unterlegscheibe eine plattenartige Gestalt auf. Vorteilhafterweise handelt es sich bei dem Bauteil bzw. der Unterlegsscheibe um eine Verbindungslasche.The component expediently points as well as the one explained above washer according to the invention a plate-like shape. It is advantageous for the component or the washer around a connecting strap.

Die nachfolgenden Ausgestaltungen beziehen auf derartige erfindungsgemäße Bauteile oder Unterlegscheiben, insbesondere auf Verbindungslaschen, wobei im Folgenden zur Vereinfachung zusammenfassend nur das Bauteil erwähnt wird Bei dem Bauteil ist zweckmäßigerweise die Eintrittsöffnung an der bei hergestellter Schraubverbindung außenseitig zugänglichen ersten Stirnseite und die Austrittsöffnung an der der Eintrittsöffnung gegenüberliegenden zweiten Stirnseite angeordnet.The following refinements relate to such components or washers according to the invention, in particular to connecting straps, with only the component being summarized below for the sake of simplicity arranged on the second end face opposite the inlet opening.

Die Austrittsöffnung wird vorteilhaft durch eine an der zweiten Stirnseite angeordnete Oberflächenvertiefungsstruktur gebildet. Die Oberflächenvertiefungsstruktur wird beispielsweise durch Prägen und/oder Stanzen und/oder Fräsen hergestellt.The outlet opening is advantageously by a surface recess structure arranged on the second end face is formed. The surface well structure is for example by embossing and / or Punching and / or milling manufactured.

Die Oberflächenvertiefungsstruktur weist vorteilhafterweise mindestens einen in einer Durchsteck- oder Einschrauböffnung ausmündenden Kanal auf. Der Kanal verläuft vorteilhaft zumindest teilweise in Umfangsrichtung der Durchsteck- oder Einschrauböffnung. Zweckmäßigerweise sind bei dem Bauteil mehrere Durchsteck- oder Einschrauböffnungen vorgesehen, zu denen die Füllmasse über die Oberflächenvertiefungsstruktur gelangen kann.The surface recess structure advantageously has at least one opening into a push-through or screw-in opening Channel on. The channel runs advantageous at least partially in the circumferential direction of the push-through or screw opening. Conveniently, there are several push-through or screw-in openings in the component provided to which the filler mass via the surface recess structure can reach.

Eine Dichtungsanordnung verhindert zweckmäßigerweise ein Ausströmen der Füllmasse aus der Kanalanordnung bzw. der Oberflächenvertiefungsstruktur. Die Dichtungsanordnung umfasst die Oberflächenvertiefungsstruktur vorteilhaft in Umfangsrichtung. Es ist auch möglich, dass die Dichtungsanordnung individuell einzelne Kanäle der Oberflächenvertiefungsstruktur abdichtet.A seal arrangement prevents expediently an outflow the filling mass from the channel arrangement or the surface recess structure. The Sealing arrangement advantageously includes the surface recess structure in the circumferential direction. It is also possible that the sealing arrangement individually individual channels the surface recess structure seals.

Die Dichtungsanordnung kann eines oder mehrere elastische Dichtelemente, z.B. aus Silikon oder Gummi, enthalten. Besonders bevorzugt ist eine Variante, bei der auf der zweiten Stirnseite der Unterlegscheibe bzw. des Bauteils wulstartig ausgebildete Erhebungen vorgesehen sind. Diese verlaufen beispielsweise beidseits von Kanälen der Oberflächenvertiefungsstruktur. Bei hergestellter Schraubverbindung liegen die Erhebungen an einem kooperierenden Bauteil, z.B. einem der zu verbindenden Bauteile, zur Abdichtung der Oberflächenvertiefungsstruktur an und sorgen so für die gewünschte Dichtigkeit. Die Erhebungen, die beispielsweise im Zusammenhang mit einem Prägen oder Fräsen von Kanälen der Oberflächenvertiefungsstruktur gebildet werden, werden zweckmäßigerweise beim Herstellen der Schraubverbindung durch das kooperierende Bauteil plastisch verformt.The sealing arrangement can be one or several elastic sealing elements, e.g. made of silicone or rubber, contain. A variant is particularly preferred in which second end face of the washer or the component bulges formed are provided. These run, for example, on both sides of the channels Surface depression structure. When the screw connection is made, the elevations lie on one cooperating component, e.g. one of the components to be connected, for sealing the surface recess structure and thus ensure the desired Tightness. The surveys related, for example with an embossing or milling of channels the surface recess structure are formed, are expedient plastically when establishing the screw connection by the cooperating component deformed.

Bei dem Verfahren ist es bevorzugt, dass die Füllmasse mit einem derartigen Druck eingepresst wird, dass sie sich ausgebend von dem Zwischenraum zwischen den aneinandergesetzten Bauteilen verteilt. Die Füllmasse wirkt dann sozusagen als ein die Bauteile miteinander verbindender Klebstoff und trägt zusätzlich zur Schubfestigkeit der Verbindung bei.In the method, it is preferred that the filling compound is pressed in with such a pressure that it expands distributed from the space between the components placed together. The filling compound then acts as it were as a connecting the components together Glue and carries additionally to the shear strength of the connection.

Zweckmäßigerweise wird die Verteilung der Füllmasse zwischen den Bauteilen noch dadurch verbessert, dass – noch vor dem Aneinandersetzen der Bauteile – an mindestens einem der Bauteile von dessen Durchbrechung ausgehend insbesondere radiale Oberflächenvertiefungen angebracht werden, die zwischen den aneinandergesetzten Bauteilen Verteilkanäle für die Füllmasse bilden. Zweckmäßig sind aber auch schneckenförmige Vertiefun gen. Die Vertiefungen können beispielsweise durch Anritzen von einem oder beiden Bauteilen angebracht werden.The distribution is expedient the filling mass between the components still improved in that - still before putting the components together - on at least one of the components starting from its opening, in particular radial surface depressions are attached, the distribution channels for the filling compound between the components placed next to each other form. Are expedient but also helical Wells. The wells can for example by scoring one or both components become.

Im Folgenden wird die Erfindung anhand zweier Ausführungsbeispiele unter Bezug auf die Figuren näher erläutert. Es zeigen:In the following the invention is based on two embodiments with reference to the figures explained. Show it:

1 eine seitliche Querschnittsansicht eines ersten Ausführungsbeispiels einer erfindungsgemäßen Schraubverbindung mit einer Unterlegscheibe, die eine erfindungsgemäße Kanalanordnung zum Einpressen einer aushärtbaren Füllmasse aufweist, 1 2 shows a lateral cross-sectional view of a first exemplary embodiment of a screw connection according to the invention with a washer which has a channel arrangement according to the invention for pressing in a curable filling compound,

2 eine vordere Querschnittsansicht des Ausführungsbeispiels gemäß 1 entlang einer Linie A-A, 2 a front cross-sectional view of the embodiment according to 1 along a line AA,

3 eine Ansicht der Unterlegscheibe gemäß 1 und 2 von unten, 3 a view of the washer according to 1 and 2 from underneath,

4 eine seitliche Querschnittsansicht eines zweiten Ausführungsbeispiels einer erfindungsgemäßen Schraubverbindung, bei der die Kanalanordnung in der Schraube vorgesehen ist, und 4 a side cross-sectional view of a second embodiment of a screw connection according to the invention, in which the channel arrangement is provided in the screw, and

5 eine vordere Querschnittsansicht des Ausführungsbeispiels gemäß 4 entlang einer Linie B-B in 4, 5 a front cross-sectional view of the embodiment according to 4 along a line BB in 4 .

6 eine Vorderansicht des dritten Ausführungsbeispiels, bei dem zwei Bauteile mittels erfindungs gemäßer Verbindungslaschen miteinander verschraubt sind, 6 3 shows a front view of the third exemplary embodiment, in which two components are screwed to one another by means of connecting straps according to the invention,

7 seitliche Querschnittsansicht entlang einer Linie C-C in 6, und 7 side cross-sectional view along a line CC in 6 , and

8 eine Querschnittsansicht eines Details einer Oberflächenvertiefungsstruktur in 6, etwa entlang einer Linie D-D. 8th FIG. 4 shows a cross-sectional view of a detail of a surface recess structure in FIG 6 , along a line DD.

Bei dem den 1 bis 3 gezeigten ersten Ausführungsbeispiel ist eine Schraube 10 durch miteinander kommunizierende Durchbrechungen 11, 12 von Bauteilen 13, 14 durchgesteckt. Die Schraube 10 ist beispielsweise eine bekannte Durchsteckschraube. Die Schraube 10 durchdringt eine Durchstecköffnung 37 einer Unterlegscheibe 16, auf der ihr Schraubenkopf 15 aufliegt. Die Unterlegscheibe 16 bildet ein erfindungsgemäßes Schraubverbindungsteil und ist zwischen dem Schraubenkopf 15 und dem Bauteil 13 angeordnet. Die Schraube 10 durchdringt ferner eine Unterlegscheibe 17, die außenseitig am Bauteil 14 anliegt. Ein mittlerer gewindeloser Abschnitt 19 der Schraube 10 ist im montierten Zustand im Bereich der Durchbrechungen 11, 12 angeordnet. Am freien, dem Schraubenkopf 15 entgegengesetzten Ende der Schraube 10 befindet sich ein Gewindeabschnitt 20, der die Unterlegscheibe 17 durchsetzt und in die Mutter 18 eingeschraubt ist.With the 1 to 3 The first exemplary embodiment shown is a screw 10 through communicating breakthroughs 11 . 12 of components 13 . 14 Box Type. The screw 10 is, for example, a known push-through screw. The screw 10 penetrates a push-through opening 37 a washer 16 on which her screw head 15 rests. The washer 16 forms a screw connection part according to the invention and is between the screw head 15 and the component 13 arranged. The screw 10 also penetrates a washer 17 , the outside of the component 14 is applied. A medium threadless section 19 the screw 10 is in the assembled state in the area of the openings 11 . 12 arranged. At the free, the screw head 15 opposite end of the screw 10 there is a threaded section 20 who the washer 17 interspersed and into the mother 18 is screwed in.

Bei den Bauteilen 13, 14 handelt es sich beispielsweise um Streben eines Gittermastes einer Windkraftanlage. Die Durchbrechungen 11, 12 sind im Idealfall zwar so angeordnet, dass sie zueinander fluchten. Dies ist allerdings bei der Montage in der Praxis kaum realisierbar, sodass die beiden Durchbrechungen 11, 12 zwar miteinander kommunizieren, jedoch nicht exakt zueinander fluchten. In der Figur ist der seitliche Versatz der Durchbrechungen 11, 12 aus Anschaulichkeitsgründen verhältnismäßig groß dargestellt.For the components 13 . 14 it is for example struts of a lattice mast of a wind turbine. The breakthroughs 11 . 12 are ideally arranged so that they are aligned with each other. However, this is hardly feasible in practice during assembly, so that the two openings 11 . 12 communicate with each other but not exactly aligned. In the figure is the lateral offset of the openings 11 . 12 shown relatively large for reasons of clarity.

Der Montagevorgang gestaltet sich folgendermaßen:The assembly process designed yourself as follows:

Die Schraube wird nacheinander durch die Unterlegscheibe 16, die Durchbrechungen 11, 12 und die Unterlegscheibe 17 durchgesteckt und anschließend in die Mutter 18 eingeschraubt. Nach dem Festziehen der Schraubverbindung dichten die Unterlegscheiben 16, 17 die Durchbrechungen 11, 12 nach außen ab. Wie aus der Zeichnung erkennbar, kann es dann noch zu einer Querbewegung der Bauteile 13, 14 relativ zueinander kommen, da die Durchbrechungen 11, 12 einen größeren Durchmesser aufweisen als der mittlere Abschnitt 19 des Schraubenschafts 21 der Schraube 10.The screw is successively through the washer 16 , the breakthroughs 11 . 12 and the washer 17 inserted and then into the mother 18 screwed. After tightening the screw connection, the washers seal 16 . 17 the breakthroughs 11 . 12 to the outside. As can be seen from the drawing, there can then be a transverse movement of the components 13 . 14 come relative to each other because of the breakthroughs 11 . 12 have a larger diameter than the central section 19 the screw shaft 21 the screw 10 ,

An dieser Stelle setzt die Erfindung ein:At this point sets the invention:

Bei der Unterlegscheibe 16 ist eine Kanalanordnung 22 vorhanden, durch die hindurch bei hergestellter Schraubverbindung eine in der Figur nicht dargestellte aushärtbare Füllmasse in Zwischenräume 23, 24 zwischen dem Schraubenschaft 21 und den Wandungen der Durchbrechungen 11 bzw. 12 einpressbar ist. Mit dieser Füllmasse werden die Zwischenräume 23, 24 verfüllt, wodurch ein Formschluss zwischen dem Schraubenschaft 21 und den Bauteilen 13, 14 hergestellt ist, sodass eine Quer-/Scherbewegung der Bauteile 13, 14 relativ zueinander vermieden wird.At the washer 16 is a channel arrangement 22 present, through which a curable filler material, not shown in the figure, is formed in the interstices when the screw connection is produced 23 . 24 between the screw shaft 21 and the walls of the openings 11 or 12 can be pressed. With this filling compound, the gaps are 23 . 24 filled, creating a positive connection between the screw shaft 21 and the components 13 . 14 is produced so that a transverse / shear movement of the components 13 . 14 is avoided relative to each other.

An einer Eintrittsöffnung 26 der Kanalanordnung 25 ist ein Anschlussmittel 27 in Form einer Art Schmiernippel angeordnet. Das Anschlussmittel 27 ist beispielsweise in die Unterlegscheibe 16 eingeschraubt. Es weist einen Kopf auf, an den eine in der Figur nicht dargestellte Einpressvorrichtung zum Einpressen der Füllmasse druckdicht anschließbar ist. Ebenfalls nicht dargestellt ist ein Rückschlagventil, das z.B. einen Bestandteil des Anschlussmittels 27 bildet. Das Rückschlagventil verhindert ein Zurückfließen einer eingepressten, aber noch nicht ausgeärteten Füllmasse aus den Zwischenräumen 23, 24 nach außen.At an entry opening 26 the channel arrangement 25 is a connection means 27 arranged in the form of a kind of grease nipple. The connection means 27 is, for example, in the washer 16 screwed. It has a head to which a press-in device (not shown in the figure) for pressing in the filling compound can be connected in a pressure-tight manner. Also not shown is a check valve, which is part of the connection means, for example 27 forms. The non-return valve prevents a pressed-in, but not yet fully cured, filling compound from flowing back from the gaps 23 . 24 outward.

Das Anschlussmittel 27 ist stirnseitig an der Unterlegscheibe 16 angeordnet und somit auch bei hergestellter Schraubverbindung außenseitig zugänglich. Über das Anschlussmittel 27 wird die Füllmasse in die Eintrittsöffnung 26 eingepresst. Sie fließt dann durch einen zur Durchstecköffnung 37 für den Schraubenschaft 21 parallelen Durchflusskanal 28 zu einem ra dial an der Unterlegscheibe 16 verlaufenden Verbindungskanal 29 zu einer Austrittsöffnung 30, die ebenso wie der Verbindungskanal 29 vorliegend als eine Oberflächenvertiefung ausgestaltet ist. Die Austrittsöffnung 30 verläuft um die Durchstecköffnung 37 der Unterlegscheibe 16 herum. Auf diese Weise kann die Füllmasse unabhängig von der jeweiligen Lage des Schraubenschafts 21 relativ zu der Durchbrechung 11 in den Zwischenraum 23 und von diesem weiter in den Zwischenraum 24 einströmen. Durch einen geeignet hohen Einpressdruck beim Einpressen der Füllmasse wird etwa in den Zwischenräume 23, 24 befindliche Luft aus diesen Zwischenräumen verdrängt.The connection means 27 is on the front of the washer 16 arranged and thus accessible from the outside even when a screw connection is made. About the connection means 27 the filling mass is in the inlet opening 26 pressed. It then flows through one to the push-through opening 37 for the screw shaft 21 parallel flow channel 28 to a ra dial on the washer 16 trending connecting channel 29 to an exit opening 30 that is just like the connecting channel 29 is designed here as a surface recess. The exit opening 30 runs around the push-through opening 37 the washer 16 around. In this way, the filling compound can be used regardless of the position of the screw shaft 21 relative to the breakthrough 11 in the space 23 and from there into the space 24 flow. Due to a suitably high injection pressure when the filling compound is injected, there is roughly in the spaces 23 . 24 air is displaced from these spaces.

Im Zusammenwirken mit der erfindungsgemäßen Unterlegscheibe 16 können eine bekannte Schraube und eine bekannte Mutter verwendet werden, gegebenenfalls auch solche, die für hochfeste vorgespannte Verbindungen üblich sind. Die Zugbelastbarkeit der Verbindung ist somit außerordentlich hoch.In cooperation with the washer according to the invention 16 a known screw and a known nut can be used, optionally also those which are customary for high-strength prestressed connections. The tensile strength of the connection is therefore extremely high.

Es versteht sich, dass anstelle der Unterlegscheibe 17 ebenfalls eine Unterlegscheibe in der Art der Unterlegscheibe 16 verwendet werden kann, sodass beidseitig bei der Schraubverbindung erfindungsgemäße Unterlegscheiben zum Einsatz kommen.It is understood that instead of the washer 17 also a washer type 16 can be used so that washers according to the invention are used on both sides in the screw connection.

Bei dem zweiten Ausführungsbeispiel gemäß den 4 und 5 ist anstelle der bekannten Schraube 10 eine erfindungsgemäße Schraube 31 verwendet, während anstelle der erfindungsgemäßen Unterlegscheibe 16 eine konventionelle Unterlegscheibe in der Art der Unterlegscheibe 17 verwendet wird. Diese Unterlegscheibe ist daher ebenfalls mit dem Bezugszeichen 17 versehen. Auch weitere Komponenten, die beim zweiten Ausführungsbeispiel gleich oder gleichartig sind wie beim ersten Ausführungsbeispiel, sind mit denselben Bezugszeichen versehen und werden im Folgenden nicht näher erläutert.In the second embodiment according to the 4 and 5 is instead of the well-known screw 10 a screw according to the invention 31 used while instead of the washer according to the invention 16 a conventional washer type 17 is used. This washer is therefore also with the reference symbol 17 Mistake. Other components that are the same or similar in the second exemplary embodiment as in the first exemplary embodiment are provided with the same reference numerals and are not explained in more detail below.

Die Schraube 31 weist eine Kanalanordnung 32 auf, die zum Einpressen einer ebenfalls nicht dargestellten Füllmasse in die Zwischenräume 23, 24 dient. Bei der Kanalanordnung 32 verläuft in Längsrichtung des Schraubenschaftes 21 ein Längskanal 33. In diesen ist die Füllmasse über ein stirnseitig am Schraubenkopf 15' angeordnetes Anschlussstück 34 einpressbar. Das Anschlussstück 34 ist, wie vom ersten Ausführungsbeispiel bekannt, eine Art Schmiernippel. Es ist beispielsweise in den Schraubenkopf 15 eingeschraubt, eingepresst oder in sonstiger Weise mit diesem verbunden. Vom Längskanal 33 zweigen in radialer Richtung Radialkanäle 35, 36 ab. Die Radialkanäle 35 und 36 sind axial zueinander beabstandet, wobei die Radialkanäle 35 in der Durchbrechung 11 und die Radialkanäle 36 in der Durchbrechung 12 ausmünden. Auf diese Weise können die Zwischenräume 23, 24 homogen mit der Füllmasse verfüllt werden.The screw 31 has a channel arrangement 32 on, for pressing a filling compound, also not shown, into the spaces 23 . 24 serves. With the channel arrangement 32 runs in the longitudinal direction of the screw shaft 21 a longitudinal channel 33 , In these the filling compound is on the face of the screw head 15 ' arranged connector 34 be pressed. The connector 34 is, as known from the first embodiment, a kind of grease nipple. For example, it is in the screw head 15 screwed, pressed or otherwise connected to this. From the longitudinal channel 33 radial channels branch in the radial direction 35 . 36 from. The radial channels 35 and 36 are axially spaced apart, the radial channels 35 in the breakthrough 11 and the radial channels 36 in the breakthrough 12 open out. In this way, the gaps 23 . 24 be filled homogeneously with the filling compound.

Ebenfalls zu einer gleichmäßigen Befüllung trägt bei, dass die Radialkanäle 35 und 36 jeweils sternförmig vom Längskanal 33 radial nach außen abzweigen.The radial channels also contribute to uniform filling 35 and 36 each star-shaped from the longitudinal channel 33 turn radially outwards.

Beim dritten, in den 6 bis 8 gezeigten Ausführungsbeispiel sind Bauteile 38, 38' mit Hilfe von Verbindungslaschen 39, 40 miteinander verbunden. Beispielsweise handelt es sich bei den Bauteilen 38, 38' um Streben eines Gittermasts einer Windkraftanlage. Die Bauteile 38, 38' sind übereinander angeordnet. Seitlich neben den Bauteilen 38, 38', an entgegengesetzten Seiten der Bauteile 38, 38', sind Verbindungslaschen 39, 40 angeordnet. Die Verbindungslaschen 39, 40 liegen flächig auf den Bauteilen 38, 38'. Die Verbindungslaschen 39, 40 sind mit den Bauteilen 38, 38' mittels Schrauben 44 und Muttern 45 verbunden. Die Schrauben 44 durchdringen die Bauteile 38, 38' an Durchbrechungen 41 und die Verbindungslaschen 39, 40 an Durchbrechungen 42, 43. Die Durchbrechungen 41, 42, 43 fluchten im wesentlichen miteinander. Die Schrauben 44 sind von der Verbindungslasche 40 her durch die Durchbrechungen 41 bis 43 hindurchgesteckt und mit den Muttern 45 verschraubt. Zwischen den Muttern 45 und der Verbindungslasche 39 und den Schraubenköpfen der Schrauben 44 und der Verbindungslasche 40 liegt jeweils eine Unterlegescheibe 46. Die Unterlegscheiben 46 verschließen die Durchbrechungen 41, 43 nach außen hin im wesentlichen.The third, in the 6 to 8th The exemplary embodiment shown are components 38 . 38 ' with the help of connecting straps 39 . 40 connected to each other the. For example, the components 38 . 38 ' around struts of a lattice mast of a wind turbine. The components 38 . 38 ' are arranged one above the other. Laterally next to the components 38 . 38 ' , on opposite sides of the components 38 . 38 ' , are connecting lugs 39 . 40 arranged. The connecting straps 39 . 40 lie flat on the components 38 . 38 ' , The connecting straps 39 . 40 are with the components 38 . 38 ' by means of screws 44 and nuts 45 connected. The screws 44 penetrate the components 38 . 38 ' of breakthroughs 41 and the connecting tabs 39 . 40 of breakthroughs 42 . 43 , The breakthroughs 41 . 42 . 43 essentially aligned with each other. The screws 44 are from the connecting tab 40 forth through the breakthroughs 41 to 43 put through and with the nuts 45 screwed. Between the nuts 45 and the connecting tab 39 and the screw heads of the screws 44 and the connecting tab 40 there is a washer in each case 46 , The washers 46 close the openings 41 . 43 outwardly essentially.

Die Durchbrechungen 41 bis 43 fluchten zwar im wesentlichen miteinander, jedoch nicht exakt. Dementsprechend ist zwischen den Durchbrechungen 41 bis 43 und den Schrauben 44 ein gewisses Spiel, das bei bekannten Schraubverbindungen zu derarti gen Querbelastungen für die Schrauben 44 führen würde, dass diese möglicherweise sogar abgeschert werden. Um dies zu verhindern, sind die zwischen den Schrauben 44 und den Durchbrechungen 41 bis 43 jeweils vorhandenen Zwischenräume 57 bis 59 wie bei den vorher erläuterten Ausführungsbeispielen mit einer Füllmasse 61 verfüllt. Zum Einbringen der Füllmasse 61 ist die Verbindungslasche 40 erfindungsgemäß ausgestaltet.The breakthroughs 41 to 43 are essentially in line with each other, but not exactly. Accordingly, is between the breakthroughs 41 to 43 and the screws 44 a certain game, the known screw connections to such cross conditions for the screws 44 would lead to them possibly even being sheared off. To prevent this, they are between the screws 44 and the breakthroughs 41 to 43 existing gaps 57 to 59 as in the previously explained embodiments with a filling compound 61 filled. For introducing the filling compound 61 is the connection tab 40 designed according to the invention.

Bei der Verbindungslasche 40 sind Kanalanordnungen 49, 50 zum Einpressen der Füllmasse 61 vorgesehen. Die Kanalanordnung 49 ist dem Bauteil 38', die Kanalanordnung 50 dem Bauteil 38 zugeordnet. An der von vorne zugänglichen Stirnseite der Verbindungslasche 40 sind Anschlussmittel 62 mit Eintrittsöffnungen 63 der Kanalanordnungen 49, 50 angeordnet. Die Anschlussmittel 62 sind vorliegend ähnlich wie die Anschlussmittel 27 als eine Art Schmiernippel ausgestaltet. Über die Eintrittsöffnungen 63 wird die Füllmasse 61 in die Kanalanordnungen 49, 50 eingepresst. Die Füllmasse 61 fließt dabei zunächst durch Durchtrittskanäle 65 von der Stirnseite 47 zu einer dieser gegenüberliegenden Stirnseite 48 der Verbindungslasche 40 zu Austrittsöffnungen 64. Die Austrittsöffnungen 64 sind bei der Verbindungslasche 40 als Oberflächenvertiefungsstrukturen 51, 52 ausgestaltet.At the connecting tab 40 are channel arrangements 49 . 50 for pressing in the filling compound 61 intended. The channel arrangement 49 is the component 38 ' , the channel arrangement 50 the component 38 assigned. On the front side of the connecting bracket, which is accessible from the front 40 are connection means 62 with entry openings 63 of the channel arrangements 49 . 50 arranged. The connection means 62 are similar to the connection means in the present case 27 designed as a kind of grease nipple. Via the entry openings 63 becomes the filling compound 61 into the channel arrangements 49 . 50 pressed. The filling compound 61 initially flows through passage channels 65 from the front 47 to a face opposite this 48 the connecting strap 40 to outlet openings 64 , The outlet openings 64 are at the connecting tab 40 as surface recess structures 51 . 52 designed.

Die Oberflächenvertiefungsstruktur 51 ist dem Bauteil 38', die Oberflächenvertiefungsstruktur 52 dem Bauteil 38 zugeordnet. Die Oberflächenvertiefungsstrukturen 51, 52 werden im montierten Zustand von den Bauteilen 38, 38' verschlossen. Die Oberflächenvertiefungsstrukturen 51, 52 bilden eine Art Kanalsystem, dessen Kanäle die Durchbrechungen 43 miteinander verbinden. Die Kanäle können beispielsweise sternförmig oder in sonstiger Weise von den jeweiligen Eintrittsöffnungen 63 her zu den Durchbrechungen 43 verlaufen. Bei den Strukturen 51, 52 führt jeweils ein Kanal zu einer Durchbrechung 43. Es ist auch möglich, dass mehrere Kanäle zu einer Durchbrechung führen und/oder dass die Durchbrechungen durch Quer-Kanäle miteinander verbunden sind, die nicht unmittelbar mit den Eintrittsöffnungen verbunden sind. Die Ausgestaltung der Oberflächenvertiefungsstrukturen 51, 52 ermöglicht zweckmäßigerweise eine gleichmäßige Verteilung der Füllmasse 61 in den Durchbrechungen 43 bzw. den mit diesen im wesentlichen fluchtenden Durchbrechungen 41 und 42.The surface well structure 51 is the component 38 ' who have favourited Surface Well Structure 52 the component 38 assigned. The surface recess structures 51 . 52 are assembled by the components 38 . 38 ' locked. The surface recess structures 51 . 52 form a kind of channel system, the channels of which are the openings 43 connect with each other. The channels can, for example, be star-shaped or in some other way from the respective inlet openings 63 forth to the breakthroughs 43 run. With the structures 51 . 52 one channel leads to an opening 43 , It is also possible for a plurality of channels to lead to an opening and / or for the openings to be connected to one another by transverse channels which are not directly connected to the inlet openings. The design of the surface recess structures 51 . 52 expediently enables a uniform distribution of the filling compound 61 in the breakthroughs 43 or the openings which are essentially aligned with these 41 and 42 ,

Damit sich die Füllmasse 61 möglichst optimal verteilt, ist ein hoher Einpreßdruck bevorzugt. Dieser Einpreßdruck kann allerdings zur Folge haben, dass die Füllmasse 61 aus den Kanälen der Strukturen 51, 52 z.B. seitlich heraus dringt und sich zwischen den Bauteilen 38, 38' und den Verbindungslaschen 39, 40 verteilt. Bis zu einem gewissen Maß kann dies, wie bereits im Zusammenhang mit dem zweiten Ausführungsbeispiel erläutert wurde, vorteilhaft sein, da die Füllmasse 61 gleichzeitig ein Verkleben der Bauteile 38 bis 40 bewirkt. Die Verklebungswirkung sorgt für eine zusätzliche Schubfes tigkeit der Verbindung. Allerdings ist es nicht erwünscht, dass sich die Füllmasse 61 noch weiter verteilt, das heißt beispielsweise seitlich an den Bauteilen 38 bis 40 heraustritt. Um dies zu verhindern, sind vorliegend Dichtungsanordnungen vorgesehen, die nachfolgend beschrieben werden.So that the filling compound 61 distributed as optimally as possible, a high injection pressure is preferred. However, this injection pressure can result in the filling compound 61 from the channels of the structures 51 . 52 For example, it comes out laterally and between the components 38 . 38 ' and the connecting tabs 39 . 40 distributed. To a certain extent, as already explained in connection with the second exemplary embodiment, this can be advantageous since the filling compound 61 at the same time gluing the components 38 to 40 causes. The adhesive effect ensures an additional shear strength of the connection. However, it is not desirable that the filling compound 61 distributed even further, for example on the side of the components 38 to 40 emerges. To prevent this, sealing arrangements are provided in the present case, which are described below.

Dichtungen 55, 56 umgeben die Oberflächenvertiefungsstrukturen 51, 52 ringförmig in der Art von Dichtringen. Sie liegen bei hergestellter Schraubverbindung zwischen der Verbindungslasche 40 sowie den zu verbindenden Bauteilen 38 bzw. 38'. Die Dichtungen 55, 56 sind aus einem elastischen Material, beispielsweise Silikon oder Gummi.seals 55 . 56 surround the surface recess structures 51 . 52 ring-shaped in the manner of sealing rings. When the screw connection is made, they lie between the connecting lugs 40 as well as the components to be connected 38 respectively. 38 '. The seals 55 . 56 are made of an elastic material, such as silicone or rubber.

Eine weitere Dichtungsanordnung zur Abdichtung der Kanäle der Oberflächenvertiefungsstrukturen 51, 52 wird im Folgenden anhand eines in 8 detailliert dargestellten Kanals 53 der Oberflächenvertiefungsstruktur 52 erläutert. Neben dem Kanal 53 sind seitlich Wulste 60 ausgebildet. Die Wulste 60 werden beispielsweise durch geeignetes Prägen des Kanals 53 gebildet.Another sealing arrangement for sealing the channels of the surface recess structures 51 . 52 is described below using an in 8th channel shown in detail 53 the surface recess structure 52 explained. Next to the channel 53 are beads on the side 60 educated. The beads 60 by embossing the channel appropriately 53 educated.

Beim Festziehen der Schrauben 44 wird die Verbindungslasche 40 fest gegen die Bauteile 38, 38' gepresst. Dadurch werden die vergleichsweise schmalen Wulste 60 plastisch verformt. Die Wulste 60 schmiegen sich an das kooperierende Bauteil 38, 38' an und liegen somit optimal dicht an der jeweiligen Ober seite der Bauteile 38, 38' an. Die Wulste 60 dichten den Kanal 53 seitlich ab.When tightening the screws 44 becomes the connection tab 40 firmly against the components 38 . 38 ' pressed. This makes the comparatively narrow beads 60 plastically deformed. The beads 60 nestle against the cooperating component 38 . 38 ' and are therefore optimally close to the respective upper side of the components 38 . 38 ' on. The beads 60 seal the channel 53 sideways.

Die Wulste 60 sind mit einer gestrichelten Linie im Zustand vor Herstellung der Schraubverbindung und in einer durchgezogenen Linie nach Herstellung der Schraubverbindung, d.h. nach der plastischen Verformung, dargestellt.The beads 60 are with a dashed line in the state before the screw connection was made and in a solid line after Her position of the screw connection, ie after the plastic deformation.

Es versteht sich, dass beliebige Kombinationen der vorgenannten Maßnahmen möglich sind.It goes without saying that any Combinations of the above measures are possible.

Beispielsweise kann auch beim zweiten Ausführungsbeispiel anstelle der Unterlegscheibe 17 eine erfindungsgemäße Unterlegscheibe in der Art der Unterlegscheibe 16 verwendet werden.For example, in the second embodiment, instead of the washer 17 a washer according to the invention in the manner of the washer 16 be used.

Zusätzlich zu den Radialkanälen 35, 36 könnten axial beabstandet weitere Radialkanäle vorgesehen sein.In addition to the radial channels 35 . 36 further radial channels could be provided axially spaced apart.

Claims (31)

Schraubverbindungsteil zur Herstellung einer mindestens zwei Bauteile (13, 14; 38, 38') zusammenpressenden Schraubverbindung, die eine miteinander kommunizierende Durchbrechungen (11, 12; 40-43) der Bauteile (13, 14; 38, 38') durchsetzende Schraube (10; 31; 44), eine auf den Schraubenschaft (21) aufschraubbare Mutter (18; 45) und eventuell eines der Bauteile (13, 14; 38', 38-40) und/oder mindestens eine unter der Mutter (18; 45) und/oder dem Schraubenkopf (15) platzierbare Unterlegscheibe (16, 17; 46) aufweist, gekennzeichnet durch eine Kanalanordnung (25; 32), die vorgesehen ist, um durch sie hindurch bei hergestellter Schraubverbindung eine aushärtbare Füllmasse in einen Zwischenraum (23, 24; 57-59) zwischen dem Schraubenschaft (21) und einer Wandung zumindest einer der Durchbrechungen (11, 12; 40-43) einzupressen.Screw connection part for producing at least two components ( 13 . 14 ; 38 . 38 ' ) compressing screw connection, which communicates with one another through openings ( 11 . 12 ; 40-43 ) the components ( 13 . 14 ; 38 . 38 ' ) penetrating screw ( 10 ; 31 ; 44 ), one on the screw shaft ( 21 ) screw-on nut ( 18 ; 45 ) and possibly one of the components ( 13 . 14 ; 38 ' . 38-40 ) and / or at least one under the mother ( 18 ; 45 ) and / or the screw head ( 15 ) placeable washer ( 16 . 17 ; 46 ), characterized by a channel arrangement ( 25 ; 32 ), which is provided so that a curable filling compound can be passed through it into a space (screw connection). 23 . 24 ; 57-59 ) between the screw shaft ( 21 ) and a wall of at least one of the openings ( 11 . 12 ; 40-43 ) press. Schraubverbindungsteil nach Anspruch 1, dadurch gekennzeichnet, dass die Kanalanordnung (25; 32) mindestens eine bei hergestellter Schraubverbindung außenseitig zugängliche Eintrittsöffnung (26; 63) und mindestens eine in den Zwischenraum (23, 24; 57-59) ausmündende Austrittsöffnung (30; 64) aufweist.Screw connection part according to claim 1, characterized in that the channel arrangement ( 25 ; 32 ) at least one inlet opening accessible from the outside when the screw connection is made ( 26 ; 63 ) and at least one in the space ( 23 . 24 ; 57-59 ) outlet opening ( 30 ; 64 ) having. Schraubverbindungsteil nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass an der mindestens einen Eintrittsöffnung (26; 63) ein Anschlussmittel (27; 34; 62) zum druckdichten Anschließen einer Einpressvorrichtung zum Einpressen der Füllmasse vorgesehen ist.Screw connection part according to claim 1 or 2, characterized in that at the at least one inlet opening ( 26 ; 63 ) a connection means ( 27 ; 34 ; 62 ) is provided for the pressure-tight connection of a press-in device for pressing in the filling compound. Schraubverbindungsteil nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass an der mindestens einen Eintrittsöffnung (26; 63) ein Rückschlagventil angeordnet ist, das ein Zurückfließen der eingepressten Füllmasse aus dem Zwischenraum (23, 24; 57-59) nach außen verhindert.Screw connection part according to one of claims 1 to 3, characterized in that at least one inlet opening ( 26 ; 63 ) a check valve is arranged which prevents the pressed-in filling material from flowing back out of the intermediate space ( 23 . 24 ; 57-59 ) prevented to the outside. Schraubverbindungsteil nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass die Kanalanordnung (25; 32) mindestens eine Oberflächenvertiefung (30; 64) und/oder mindestens einen Durchtrittskanal (28; 33, 35, 36) aufweist.Screw connection part according to one of the preceding claims, characterized in that the channel arrangement ( 25 ; 32 ) at least one surface depression ( 30 ; 64 ) and / or at least one passage channel ( 28 ; 33 . 35 . 36 ) having. Schraubverbindungsteil nach Anspruch 9, dadurch gekennzeichnet, dass bei hergestellter Schraubverbindung in jede der Durchbrechungen (11, 12; 40-43) jeweils mindestens eine Austrittsöffnung (30; 64) der Kanalanordnung (25; 32) ausmündet.Screw connection part according to claim 9, characterized in that when a screw connection is made in each of the openings ( 11 . 12 ; 40-43 ) at least one outlet opening ( 30 ; 64 ) the channel arrangement ( 25 ; 32 ) flows out. Schraubverbindungsteil nach einem der vorhergehenden Ansprüche, gekennzeichnet durch eine Ausgestaltung als Schraube (31) mit einem Schraubenkopf (15) und einem Schraubenschaft (21).Screw connection part according to one of the preceding claims, characterized by an embodiment as a screw ( 31 ) with a screw head ( 15 ) and a screw shaft ( 21 ). Schraubverbindungsteil nach Anspruch 7, dadurch gekennzeichnet, dass die mindestens eine Eintrittsöffnung (26; 63) am Schraubenkopf (15) und die mindestens eine Austrittsöffnung (30; 64) am radialen Außenumfang des Schraubenschafts (21) angeordnet sind.Screw connection part according to claim 7, characterized in that the at least one inlet opening ( 26 ; 63 ) on the screw head ( 15 ) and the at least one outlet opening ( 30 ; 64 ) on the radial outer circumference of the screw shaft ( 21 ) are arranged. Schraubverbindungsteil nach Anspruch 7 oder 8, dadurch gekennzeichnet, dass die Kanalanordnung (25; 32) mindestens einen im Wesentlichen in Längsrichtung des Schraubenschafts (21) verlaufenden Längskanal (33) und mindestens einen mit diesem verbundenen, in die mindestens eine Austrittsöffnung (30; 64) mündenden und im Wesentlichen in radialer Richtung verlaufenden Radial-Kanal (35, 36) aufweist.Screw connection part according to claim 7 or 8, characterized in that the channel arrangement ( 25 ; 32 ) at least one essentially in the longitudinal direction of the screw shaft ( 21 ) longitudinal channel ( 33 ) and at least one connected to it, into the at least one outlet opening ( 30 ; 64 ) opening and essentially radial channel ( 35 . 36 ) having. Schraubverbindungsteil nach einem der Ansprüche 7 bis 9, dadurch gekennzeichnet, dass axial zueinander beabstandet mindestens zwei Austrittsöffnungen (30; 64) an dem Schraubenschaft (21) vorgesehen sind.Screw connection part according to one of claims 7 to 9, characterized in that axially spaced apart at least two outlet openings ( 30 ; 64 ) on the screw shaft ( 21 ) are provided. Schraubverbindungsteil nach einem der Ansprüche 7 bis 10, dadurch gekennzeichnet, dass die Austrittsöffnungen (30; 64) über den Umfang des Schraubenschafts (21) verteilt sind.Screw connection part according to one of claims 7 to 10, characterized in that the outlet openings ( 30 ; 64 ) about the circumference of the screw shaft ( 21 ) are distributed. Schraubverbindungsteil nach einem der Ansprüche 1 bis 6, gekennzeichnet durch eine Ausgestaltung als Mutter (18).Screw connection part according to one of claims 1 to 6, characterized by an embodiment as a nut ( 18 ). Schraubverbindungsteil nach einem der Ansprüche 1 bis 6, gekennzeichnet durch eine Ausgestaltung als Unterlegscheibe (16).Screw connection part according to one of claims 1 to 6, characterized by a configuration as a washer ( 16 ). Unterlegscheibe nach Anspruch 13 oder Mutter (18) nach Anspruch 12, dadurch gekennzeichnet, dass die mindestens eine Eintrittsöffnung (26) an der Stirnseite der Unterlegscheibe (16) bzw. der Mutter (18) angeordnet ist, und dass die mindestens eine Austrittsöffnung (30) im Bereich einer Durchstecköffnung (37) der Unterlegscheibe (16) bzw. einer Einschrauböffnung der Mutter (18) angeordnet ist.Washer according to claim 13 or nut ( 18 ) according to claim 12, characterized in that the at least one inlet opening ( 26 ) on the front of the washer ( 16 ) or the mother ( 18 ) is arranged, and that the at least one outlet opening ( 30 ) in the area of a push-through opening ( 37 ) the washer ( 16 ) or a screw-in opening of the nut ( 18 ) is arranged. Unterlegscheibe bzw. Mutter (18) nach Anspruch 14, dadurch gekennzeichnet, dass die mindestens eine Eintrittsöffnung (26) und die mindestens eine Austrittsöffnung (30) durch mindestens einen radial verlaufenden Verbindungskanal (29) miteinander verbunden sind.Washer or nut ( 18 ) according to claim 14, characterized in that the at least one inlet opening ( 26 ) and the least an outlet opening ( 30 ) through at least one radially extending connecting channel ( 29 ) are connected. Unterlegscheibe bzw. Mutter (18; 45) nach Anspruch 14 oder 15, dadurch gekennzeichnet, dass die mindestens eine Austrittsöffnung (30) durch eine um die Durchstecköffnung bzw. die Einschrauböffnung zumindest teilweise in Umfangsrichtung verlaufende Oberflächenvertiefung gebildet wird.Washer or nut ( 18 ; 45 ) according to claim 14 or 15, characterized in that the at least one outlet opening ( 30 ) is formed by a surface recess extending at least partially in the circumferential direction around the push-through opening or the screw-in opening. Unterlegscheibe bzw. Mutter (18; 45) nach Anspruch 16, dadurch gekennzeichnet, dass die Oberflächenvertiefung an der der Eintrittsöffnung (26) gegenüberliegenden Stirnseite angeordnet ist.Washer or nut ( 18 ; 45 ) according to claim 16, characterized in that the surface recess at that of the inlet opening ( 26 ) opposite end face is arranged. Schraubverbindungsteil nach einem der Ansprüche 1 bis 6, gekennzeichnet durch eine Ausgestaltung als mindestens eines der zu verbindenden Bauteile (13, 14; 38', 38-40).Screw connection part according to one of claims 1 to 6, characterized by an embodiment as at least one of the components to be connected ( 13 . 14 ; 38 ' . 38-40 ). Schraubverbindungsteil nach einem der Ansprüche 13 bis 18, dadurch gekennzeichnet, dass die mindestens eine Eintrittsöffnung (26; 63) an einer bei hergestellter Schraubverbindung außenseitig zugänglichen ersten Stirnseite (47) des Schraubverbindungsteils (40) angeordnet ist, und die mindestens eine Austrittsöffnung (30; 64) an einer der Eintrittsöffnung (26; 63) entgegengesetzten zweiten Stirnseite (48) des Schraubverbindungsteils (40) angeordnet ist.Screw connection part according to one of claims 13 to 18, characterized in that the at least one inlet opening ( 26 ; 63 ) on a first end face accessible from the outside when the screw connection is made ( 47 ) of the screw connection part ( 40 ) is arranged, and the at least one outlet opening ( 30 ; 64 ) at one of the entry openings ( 26 ; 63 ) opposite second end face ( 48 ) of the screw connection part ( 40 ) is arranged. Schraubverbindungsteil nach einem der Ansprüche 13 bis 19, gekennzeichnet durch eine plattenartige Gestalt, insbesondere in der Art einer Verbindungslasche (40).Screw connection part according to one of claims 13 to 19, characterized by a plate-like shape, in particular in the manner of a connecting strap ( 40 ). Schraubverbindungsteil nach einem der Ansprüche 13 bis 20, dadurch gekennzeichnet, dass die mindestens eine Austrittsöffnung (30; 64) durch eine an der zweiten Stirnseite (48) angeordnete Oberflächenvertiefungsstruktur (51, 52) gebildet wird.Screw connection part according to one of claims 13 to 20, characterized in that the at least one outlet opening ( 30 ; 64 ) by one on the second face ( 48 ) arranged surface recess structure ( 51 . 52 ) is formed. Schraubverbindungsteil nach Anspruch 21, dadurch gekennzeichnet, dass die Oberflächenvertiefungsstruktur (51, 52) mindestens einen in einer Durchsteck- oder Einschrauböffnung ausmündenden Kanal aufweist.Screw connection part according to claim 21, characterized in that the surface recess structure ( 51 . 52 ) has at least one channel opening into a push-through or screw-in opening. Schraubverbindungsteil nach Anspruch 22, dadurch gekennzeichnet, dass der mindestens eine Kanal zumindest teilweise in Umfangsrichtung der Durchsteck- oder Einschrauböffnung verläuft.Screw connection part according to claim 22, characterized characterized in that the at least one channel at least partially runs in the circumferential direction of the push-through or screw-in opening. Schraubverbindungsteil nach einem der Ansprüche 19 bis 23, dadurch gekennzeichnet, dass eine die Oberflächenvertiefungsstruktur (51, 52) in Umfangsrichtung umfassende und/oder individuell einzelne Kanäle der Oberflächenvertiefungsstruktur (51, 52) abdichtende Dichtungsanordnung (55, 56) vorgesehen ist.Screw connection part according to one of claims 19 to 23, characterized in that the surface recess structure ( 51 . 52 ) circumferentially and / or individually individual channels of the surface recess structure ( 51 . 52 ) sealing seal arrangement ( 55 . 56 ) is provided. Schraubverbindungsteil nach Anspruch 24, dadurch gekennzeichnet, dass die Dichtungsanordnung mindestens ein elastisches Dichtelement (55, 56) enthält.Screw connection part according to claim 24, characterized in that the sealing arrangement at least one elastic sealing element ( 55 . 56 ) contains. Schraubverbindungsteil nach Anspruch 24 oder 25, dadurch gekennzeichnet, dass die Dichtungsanordnung (55, 56) mindestens eine auf der zweiten Stirnseite des Schraubverbindungsteils wulstartig ausgebildete Erhebung (60) enthält, die bei hergestellter Schraubverbindung an einem kooperierenden Bauteil (38, 38') zur Abdichtung der Oberflächenvertiefungsstruktur (51, 52) anliegt.Screw connection part according to claim 24 or 25, characterized in that the sealing arrangement ( 55 . 56 ) at least one elevation formed in the form of a bead on the second end face of the screw connection part ( 60 ) which, when a screw connection is made, on a cooperating component ( 38 . 38 ' ) for sealing the surface recess structure ( 51 . 52 ) is present. Schraubverbindungsteil nach Anspruch 26, dadurch gekennzeichnet, dass die mindestens eine Erhebung (60) beim Herstellen der Schraubverbindung durch das kooperierende Bauteil insbesondere plastisch verformbar ist.Screw connection part according to claim 26, characterized in that the at least one elevation ( 60 ) is particularly plastically deformable when the screw connection is made by the cooperating component. Verfahren zur Herstellung einer mindestens zwei Bauteile (13, 14; 38', 38-40) zusammenpressenden Schraubverbindung, insbesondere beim Aufbau eines Gittermastes einer Windkraftanlage, mit den Schritten: – Durchstecken einer Schraube (10; 31; 44) in miteinander kommunizierende Durchbrechungen (11, 12; 40-43) der aneinandergesetzten Bauteile (13, 14; 38', 38-40), – Aufschrauben einer Mutter (18; 45) auf den Schraubenschaft (21), – Festziehen der Schraubverbindung, und – Einpressen einer aushärtbaren Füllmasse in einen Zwischenraum (23, 24; 57-59) zwischen dem Schraubenschaft (21) und einer Wandung zumindest einer der Durchbrechungen (11, 12; 40-43) über eine Kanalanordnung (25; 32), die in der Schraube (31) und/oder in der Mutter (18; 45) und/oder in einem der Bauteile (13, 14; 38', 38-40) und/oder in mindestens einer unter der Mutter (18; 45) und/oder dem Schraubenkopf (15) platzierbaren Unterlegscheibe (16) vorgesehen ist.Method for producing at least two components ( 13 . 14 ; 38 ' . 38-40 ) compressing screw connection, in particular when building a lattice mast of a wind power plant, with the steps: - pushing through a screw ( 10 ; 31 ; 44 ) in communicating breakthroughs ( 11 . 12 ; 40-43 ) of the assembled components ( 13 . 14 ; 38 ' . 38-40 ), - screwing on a nut ( 18 ; 45 ) on the screw shaft ( 21 ), - tightening the screw connection, and - pressing a hardenable filling compound into a space ( 23 . 24 ; 57-59 ) between the screw shaft ( 21 ) and a wall of at least one of the openings ( 11 . 12 ; 40-43 ) via a channel arrangement ( 25 ; 32 ) in the screw ( 31 ) and / or in the mother ( 18 ; 45 ) and / or in one of the components ( 13 . 14 ; 38 ' . 38-40 ) and / or in at least one under the mother ( 18 ; 45 ) and / or the screw head ( 15 ) placeable washer ( 16 ) is provided. Verfahren nach Anspruch 28, dadurch gekennzeichnet, dass als aushärtbare Füllmasse Gießharz verwendet wird.A method according to claim 28, characterized in that as curable filling compound Cast resin is used. Verfahren nach Anspruch 28 oder 29, dadurch gekennzeichnet, dass die Füllmasse mit einem derartigen Druck ein gepresst wird, dass sie sich ausgehend von dem Zwischenraum zwischen den aneinandergesetzten Bauteilen verteilt.A method according to claim 28 or 29, characterized in that that the filling compound with such a pressure that it starts going out of the space between the components placed together distributed. Verfahren nach Anspruch 30, dadurch gekennzeichnet, dass an mindestens einem der Bauteile von dessen Durchbrechung ausgehend insbesondere radiale Oberflächenvertiefungen angebracht werden, die zwischen den aneinandergesetzten Bauteilen Verteilkanäle für die Füllmasse bilden.A method according to claim 30, characterized in that starting from the opening thereof, in particular radial surface depressions are made on at least one of the components, between the structures placed one against the other divide distribution channels for the filling compound.
DE10311841A 2003-01-29 2003-03-18 Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection Withdrawn DE10311841A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE10311841A DE10311841A1 (en) 2003-01-29 2003-03-18 Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DE10303528 2003-01-29
DE10303528.1 2003-01-29
DE10311841A DE10311841A1 (en) 2003-01-29 2003-03-18 Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection

Publications (1)

Publication Number Publication Date
DE10311841A1 true DE10311841A1 (en) 2004-08-12

Family

ID=32695025

Family Applications (1)

Application Number Title Priority Date Filing Date
DE10311841A Withdrawn DE10311841A1 (en) 2003-01-29 2003-03-18 Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection

Country Status (1)

Country Link
DE (1) DE10311841A1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014067924A1 (en) * 2012-11-02 2014-05-08 Hilti Aktiengesellschaft Method for connecting prefabricated concrete elements
EP2792411A1 (en) * 2013-04-16 2014-10-22 Sandvik Intellectual Property AB Gyratory crusher bearing
US20160341237A1 (en) * 2015-05-20 2016-11-24 Hamilton Sundstrand Space Systems International, Inc. Washer for retaining assembly pin
DE102015111005A1 (en) * 2015-07-08 2017-01-12 Airbus Operations Gmbh Method for connecting two components by means of a bolt-shaped element
DE102016012297A1 (en) * 2016-10-17 2018-04-19 JORDAHL GmbH Reinforced concrete structure
US9956702B2 (en) 2013-07-05 2018-05-01 Sandvik Intellectual Property Ab Method and device for manufacturing a cutting insert green body
CN108518316A (en) * 2018-04-03 2018-09-11 优利康达(天津)科技有限公司 A kind of hubcap with press mounting structure
CN115083855A (en) * 2022-04-28 2022-09-20 西屋开关设备(江苏)有限公司 Universal breaker moving contact with fixing structure and mounting method thereof
DE102022203669A1 (en) 2022-04-12 2023-10-12 Volkswagen Aktiengesellschaft Fastening device, screw connection, motor vehicle and method for connecting components

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014067924A1 (en) * 2012-11-02 2014-05-08 Hilti Aktiengesellschaft Method for connecting prefabricated concrete elements
EP2792411A1 (en) * 2013-04-16 2014-10-22 Sandvik Intellectual Property AB Gyratory crusher bearing
WO2014170120A1 (en) * 2013-04-16 2014-10-23 Sandvik Intellectual Property Ab Gyratory crusher bearing
CN105263632A (en) * 2013-04-16 2016-01-20 山特维克知识产权股份有限公司 Gyratory crusher bearing
US9433945B2 (en) 2013-04-16 2016-09-06 Sandvik Intellectual Property Ab Gyratory crusher bearing
US9956702B2 (en) 2013-07-05 2018-05-01 Sandvik Intellectual Property Ab Method and device for manufacturing a cutting insert green body
US20160341237A1 (en) * 2015-05-20 2016-11-24 Hamilton Sundstrand Space Systems International, Inc. Washer for retaining assembly pin
US10288110B2 (en) * 2015-05-20 2019-05-14 Hamilton Sundstrand Space Systems International, Inc. Washer for retaining assembly pin
DE102015111005A1 (en) * 2015-07-08 2017-01-12 Airbus Operations Gmbh Method for connecting two components by means of a bolt-shaped element
DE102016012297A1 (en) * 2016-10-17 2018-04-19 JORDAHL GmbH Reinforced concrete structure
CN108518316A (en) * 2018-04-03 2018-09-11 优利康达(天津)科技有限公司 A kind of hubcap with press mounting structure
DE102022203669A1 (en) 2022-04-12 2023-10-12 Volkswagen Aktiengesellschaft Fastening device, screw connection, motor vehicle and method for connecting components
DE102022203669B4 (en) * 2022-04-12 2025-06-26 Volkswagen Aktiengesellschaft Fastening device, screw connection, motor vehicle and method for connecting components
CN115083855A (en) * 2022-04-28 2022-09-20 西屋开关设备(江苏)有限公司 Universal breaker moving contact with fixing structure and mounting method thereof
CN115083855B (en) * 2022-04-28 2025-10-31 西屋开关设备(江苏)有限公司 Universal circuit breaker moving contact with fixed structure and installation method thereof

Similar Documents

Publication Publication Date Title
DE4033763C2 (en) Device for securing a nut received in an opening in a panel
EP2283231B2 (en) Method for establishing a blade connection of a rotor blade, a blade connection and a securing element for a blade connection
DE3733243C2 (en)
EP0753675B1 (en) Fastening device
DE1289374B (en) Pipe connection piece for high pressure lines
EP2278180B1 (en) Method and device for axially securing a bearing ring
DE1907519A1 (en) Nut with several twist ties
DE102011054861A1 (en) Fastening element with tolerance compensation function
WO2008046439A1 (en) Sleeve
DE602004000688T2 (en) Sheet metal part containing means for attachment to a support member and a seal
DE10311841A1 (en) Screw connection part, especially for wind power plant mast, has channel arrangement for passing setting material into gap between bolt shaft, wall of at least one passage after making connection
DE3545849C2 (en)
DE102004020586A1 (en) Blind rivet with adhesive for joining and adhesive filling process
EP1457688B1 (en) Spreading dowel
EP0965721A1 (en) Mounting for insulated glazing unit
DE102012102550A1 (en) Expansion dowel with an expansion screw
EP3307518A1 (en) Thermoplastic frictional connector
WO2012013352A1 (en) Preform for an interior trim part of a vehicle and interior trim part
EP1948945B1 (en) Mounting screw for fastening fitting parts, in particular hinge parts to hollow-chamber profiles
DE69316931T2 (en) HYDRAULICALLY SUPPORTED FASTENERS
EP3301310A1 (en) Mounting kit, component assembly and method for formation of a component assembly
EP3988803B1 (en) Functional unit with connecting element and fixing element
EP3974602A1 (en) Coupling device for coupling tower segments of a tower of a wind turbine and assembly method therfore
DE20316200U1 (en) Connecting arrangement has metal fastening element with threaded shank with thread of saw-tooth profile with fine pitch and conical outer contour, and plastic component with conical smooth-walled bore
EP3008350A1 (en) Screw connection of at least two adjacent components

Legal Events

Date Code Title Description
8139 Disposal/non-payment of the annual fee