CN206635657U - A kind of symmetrical formula Bridge Erector of setting a roof beam in place - Google Patents
A kind of symmetrical formula Bridge Erector of setting a roof beam in place Download PDFInfo
- Publication number
- CN206635657U CN206635657U CN201720212230.3U CN201720212230U CN206635657U CN 206635657 U CN206635657 U CN 206635657U CN 201720212230 U CN201720212230 U CN 201720212230U CN 206635657 U CN206635657 U CN 206635657U
- Authority
- CN
- China
- Prior art keywords
- cylinder component
- entablature
- girder
- sill
- place
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of symmetrical set a roof beam in place formula Bridge Erector, beam erecting method and passing method, treat frame concrete beam by being sling under line by two simultaneously by first and second jack machinism, two panels treats frame concrete beam synchronous ascending, save the process that conventional beam car coordinates Bridge Erector feeding beam, it can realize and beam is transported under line directly to position of setting a roof beam in place, two panels concrete beam is set up simultaneously, efficiency of setting a roof beam in place doubles;And complete machine need not laterally draw anchor or counterweight, job site personnel workload is reduced, is increased economic efficiency and integral construction efficiency.
Description
Technical field
Bridge construction equipment Bridge Erector technical field is the utility model is related to, more particularly to a kind of symmetrical formula bridge formation of setting a roof beam in place
Machine.
Background technology
Bridge Erector, it is the equipment for prefabricated beam piece to be placed into prefabricated bridge pier up.Bridge Erector has belonged to
Heavy-duty machine category, because its major function is to lift beam piece, put down after being then transported to position.But Bridge Erector with general sense
Crane be very different.The condition of Bridge Erector requirement is harsh, and traveling on beam piece be present, or cries vertical shift.Build bridge
It is several that machine is divided into erection highway bridge, conventional railway bridge, railway of passengers' private line bridge etc..
Bridge Erector generally comprises:Horn, trolley, No.1 post, No. two posts and No. three posts.
Horn is the support main beam of Bridge Erector, is double box-beam structures, according to the force status of horn and finite element analysis meter
Calculate, every box beam casting is into box variable cross-section form.
Bridge Erector is furnished with two trolleys, there is each independent lifting mechanism, running mechanism and transverse-moving mechanism.Every is risen
Weight dolly is equipped with two sets of independent lifting mechanisms, and two sets of lifting mechanisms of rear dolly make left and right suspension centre stress equal by force equalization mechanism
Weighing apparatus, so as to which four-point lifting during Bridge Erector hanging beam operation is converted into three suspension centres, make box beam equilibrium stand under load, quiet takeoff and landing.
No.1 post is the front leg strut of Bridge Erector, is supported on the pier first half support pinner of front.Mainly by support change gear machine
Structure, folding column, telescopic mast etc. form.Set a roof beam in place operation when with horn it is longitudinally fixed into articulated structure, turn into flexible leg, with machine
Arm, No. two post composition gantry frame structures, meet operation support requirement of setting a roof beam in place.Can be relative between No.1 post and horn during vertical shift operation
Motion, realizes Bridge Erector stride vertical shift.No.1 post is provided with fold mechanism, can meet normally to set a roof beam in place and last hole box beam erection
When No.1 post on abutment support needs.No.1 post and horn have three fixed positions to meet three kinds of different spans box beams
Set up.
No. two posts are located in the middle part of horn, are consolidated with horn, are rigid legs.The sill of No. two posts is provided with two supporting legs,
Pad and the dismounting of support sleeper are realized by hydraulic jack, meets to change stable support when walking and set a roof beam in place operation during vertical shift and requires.
Two supporting legs have transverse-moving mechanism, horn yaw are driven by traversing No. two posts of oil cylinder pushing, so as to laterally adjust bridge formation seat in the plane
Put, accommodation curve is set a roof beam in place needs.Because beam car packs the needs of Bridge Erector operating mode, sill is designed to detachable.
No. three posts be Bridge Erector vertical shift driving pillar, for meet beam car feeding beam by and Bridge Erector vertical shift driving require,
It is designed to portal-framed structure.It is made up of lifting column, fold mechanism, running mechanism, hydraulic suspension balancer, steering mechanism etc..
Bridge Erector has set up highway and railroad bridge very generally, the Bridge Erector used both at home and abroad at present, is setting up letter
During strutbeam, hanging beam dolly is first laterally moved to two girder truss centre positions, and front and rear hanging beam dolly coordinates hanging beam, vertical shift to two abutments it
Between, then traversing Bridge Erector and hanging beam dolly fall beam to accurate location.
With rapid development of economy, there occurs great variety, highway, railway traffic system to have considerable for the vehicles
Sustainable development.During road traffic is built, bridge, the progress of bridge construction construction of grand bridge are completed to whole piece traffic route
Work has significant impact.To improve bridge construction efficiency, generally using Prefabricated Concrete beam, transported, set up using setting up girder, compared with
Cast-in-situ Beam greatly improved construction quality and speed in the past, had saved cost.At present in bridge construction, especially highway bridge
Construction, a bridge block are made up of porous (across) bridge, are made up of per bridge multi-disc Prefabricated Concrete beam.The process for setting up such concrete beam before this
For:Beam car packs monolithic concrete beam to end of the bridge from precast beam field, then coordinates Bridge Erector trolley from bridge formation drive end unit feeding beam
(i.e. feeding beam on bridge floor), feeding beam in place after trolley is traversing falls beam afterwards in place, a process of setting a roof beam in place sets up a piece of concrete beam.Set up
During the side girders of circuit one (per the outermost concrete beam of bridge), to ensure safety, Bridge Erector other side need to carry out drawing anchor or adding matching somebody with somebody
Weight, to increase complete machine lateral stability, therefore, cause to construct comparatively laborious, efficiency is low.
Utility model content
Many aspects of the present utility model provide a kind of symmetrical formula Bridge Erector of setting a roof beam in place, and can simplify construction procedure, raising is applied
Work efficiency rate, while reduce equipment cost.
One side of the present utility model provides a kind of symmetrical formula Bridge Erector of setting a roof beam in place, and the symmetrical formula Bridge Erector of setting a roof beam in place includes the
One jack machinism, the second jack machinism, front leg strut, middle supporting leg, rear support leg, girder, the first transverse-moving trolley and the second transverse-moving trolley;
Wherein, treat that frame concrete beam will be used for frame between preceding bridge pier and rear abutment for two, the rear abutment opposite side has been pacified
It is equipped with frame concrete beam;The front leg strut branch is stood on the preceding bridge pier, the middle supporting leg branch stand on it is described on frame concrete beam, it is described
First transverse-moving trolley and second transverse-moving trolley are located on the girder and can moved in the girder;
At the front leg strut, first transverse-moving trolley includes first, second chassis, first, second chassis point
Not Wei Yu the girder both sides, and drawn by corresponding two first jack machinisms, first, second chassis is used respectively
In two same one end for treating frame concrete beam of handling;
At the middle supporting leg, second transverse-moving trolley includes the three, the 4th chassis, the three, the 4th chassis point
Not Wei Yu the girder both sides, and drawn by corresponding two second jack machinisms, the three, the 4th chassis is used respectively
In two same other ends for treating frame concrete beam of handling.
Alternatively, the front leg strut includes entablature, anti-change gear drive device, vertical shift cylinder component, telescopic, jacking oil
Cylinder component, sill, traversing cylinder component, lower template beam and bearing diagonal and intermediate plate;Wherein, the front leg strut passes through the underlay
Beam is supported on the pier top face of the preceding bridge pier, by girder described in skid plates support, by the anti-change gear drive device along institute
State the lower flange automatic moving of girder;The front leg strut voluntarily adjusts height to adapt to line slope;The front leg strut sets horizontal
Move cylinder component and meet complete machine curve via holes.
Alternatively, the lower template beam is supported on the pier top face of the preceding bridge pier, and the sill is located at the lower template beam
On, the traversing cylinder component is located on the sill, passes through the telescopic between the entablature and the sill
Connection, includes the bearing diagonal between the entablature and the sill, and described in the lower end of the bearing diagonal is supported on
On sill, the upper end of the bearing diagonal supports an intermediate plate, and the jacking cylinder component is located on the intermediate plate, and institute
State the jacking cylinder component other end and connect the entablature, by the flexible adjustment intermediate plate of the jacking cylinder component and
The distance between described entablature, the anti-change gear drive device and the vertical shift cylinder component are located on the entablature, institute
State on anti-change gear drive device and the vertical shift cylinder component again by girder described in the skid plates support;The entablature leads to
Lower flange automatic moving of the anti-change gear drive device along the girder is crossed, and the vertical shift oil is additionally provided with the entablature
Cylinder component, it is the telescopic on the outside of the front leg strut.
Alternatively, the middle supporting leg includes entablature, anti-change gear drive device, vertical shift cylinder component, telescopic, jacking oil
Cylinder component, sill, slew gear and lower support beam;Wherein, the middle supporting leg is supported on described on the beam face of frame concrete beam, is led to
Girder described in skid plates support is crossed, by the anti-change gear drive device along girder lower flange automatic moving;The middle supporting leg
Height is voluntarily adjusted to adapt to line slope;The middle supporting leg sets the slew gear to coordinate the front leg strut to meet complete machine
Curve via holes.
Alternatively, the lower support beam is supported on described on the beam face of frame concrete beam, wherein, the concrete of the frame beam is located at institute
State on the pier face of rear abutment, the slew gear is located in the lower support beam, and the sill is located at the slew gear
On, connected between the entablature and the sill by the telescopic, the jacking cylinder component is located at the lower horizontal stroke
Liang Shang, the jacking cylinder component other end connects the entablature, by described in the flexible adjustment of the jacking cylinder component
The distance between entablature and the sill, the anti-change gear drive device and the vertical shift cylinder component are located at the upper horizontal stroke
Liang Shang, pass through girder described in the skid plates support again on the anti-change gear drive device and the vertical shift cylinder component.
Alternatively, the rear support leg includes tie-beam, entablature, telescopic, jacking cylinder component and lower support beam;
The lower support beam be supported on it is described on the beam face of frame concrete beam, wherein the concrete of the frame beam is located on bridge pier, institute
State entablature to connect by the telescopic with the lower support beam, the jacking cylinder is additionally provided with the lower support beam
Component, the other end of the jacking cylinder component connect the entablature, by described in the flexible adjustment of the jacking cylinder component
The distance between entablature and the lower support beam, the tie-beam is located on the entablature, and the tie-beam other end
Connect the girder.
Relative to prior art, the symmetrical formula Bridge Erector of setting a roof beam in place of many aspects offer of the present utility model, conventional fortune is saved
Beam car coordinates the process of Bridge Erector feeding beam, it is possible to achieve and beam is transported under line directly to position of setting a roof beam in place, while sets up two panels concrete beam, effect of setting a roof beam in place
Rate doubles;And complete machine need not laterally draw anchor or counterweight, job site personnel workload is reduced, is increased economic efficiency and overall
Efficiency of construction.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art
Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are these
Some embodiments of utility model, for those of ordinary skill in the art, without having to pay creative labor,
Other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the symmetrical formula Bridge Erector structural representation of setting a roof beam in place of one kind of the embodiment of the utility model one;
Fig. 2 is Fig. 1 of the utility model embodiment Section A-A view;
Fig. 3 is Fig. 1 of the utility model embodiment section B-B view;
Fig. 4 is Fig. 1 of the utility model embodiment C-C section views;
Fig. 5 is a kind of side view of the front leg strut of symmetrical formula Bridge Erector of setting a roof beam in place of another embodiment of the utility model;
Fig. 6 is a kind of side view of the middle supporting leg of symmetrical formula Bridge Erector of setting a roof beam in place of another embodiment of the utility model;
Fig. 7 is a kind of side view of the rear support leg of symmetrical formula Bridge Erector of setting a roof beam in place of another embodiment of the utility model;
Fig. 8 is a kind of girder section view of symmetrical formula Bridge Erector of setting a roof beam in place of another embodiment of the utility model;
During Fig. 9-1 to 9-5 is respectively the symmetrical formula girder erection by bridging machine of setting a roof beam in place of one kind of another embodiment of the utility model
State diagram;
Figure 10-1 to 10-5 is respectively that the symmetrical formula Bridge Erector via of setting a roof beam in place of one kind of another embodiment of the utility model walked
The state diagram of journey;
Figure 11 is that the symmetrical formula Bridge Erector of setting a roof beam in place of one kind of another embodiment of the utility model sets up downhill bridge state diagram;
Figure 12 is that the symmetrical formula Bridge Erector of setting a roof beam in place of one kind of another embodiment of the utility model sets up slope-climbing road state diagram.
Embodiment
It is new below in conjunction with this practicality to make the purpose, technical scheme and advantage of the utility model embodiment clearer
Accompanying drawing in type embodiment, the technical scheme in the embodiment of the utility model is clearly and completely described, it is clear that is retouched
The embodiment stated is the utility model part of the embodiment, rather than whole embodiments.Based on the implementation in the utility model
Example, the every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made, is belonged to
The scope of the utility model protection.
As shown in figure 1, be the symmetrical formula Bridge Erector structural representation of setting a roof beam in place of one kind of the embodiment of the utility model one, it is described right
Title set a roof beam in place formula Bridge Erector include the first jack machinism 1A, the second jack machinism 1B, front leg strut 2, middle supporting leg 3, rear support leg 4, girder
5th, the first transverse-moving trolley 6A and the second transverse-moving trolley 6B.Wherein, two after frame concrete beam 8,8 ' will be used for frame in preceding bridge pier 7A and after
Between bridge pier 7B, the rear abutment 7B opposite sides have been mounted with frame concrete beam 9.The front leg strut 2 stands on the preceding bridge pier
On 7A, the middle supporting leg 3 stands on described on frame concrete beam 9, the first transverse-moving trolley 6A and the second transverse-moving trolley 6B
It can move on the girder 5 and in the girder 5.
As shown in figures 2 and 5, wherein, Fig. 2 is Fig. 1 of the utility model embodiment Section A-A view, and Fig. 5 is this practicality
A kind of side view of the front leg strut of symmetrical formula Bridge Erector of setting a roof beam in place of new another embodiment, the front leg strut 2 include entablature 2-
1st, anti-change gear drive device 2-2, vertical shift cylinder component 2-3, telescopic 2-4, jacking cylinder component 2-5, sill 2-6, traversing
Cylinder component 2-7, lower template beam 2-8 and bearing diagonal 2-9.Wherein, the front leg strut 2 is supported on described by the lower template beam 2-8
On preceding bridge pier 7A pier top face, the girder 5 is supported by slide plate 10, by the anti-change gear drive device 2-2 along the master
The lower flange automatic moving of beam 5.The front leg strut 2 can voluntarily adjust height to adapt to line slope.The front leg strut 2 sets horizontal stroke
Move cylinder component 2-7 and meet complete machine curve via holes.
Wherein, the lower template beam 2-8 is supported on the pier top face of the preceding bridge pier 7A, and the sill 2-6 is positioned at described
On lower template beam 2-8, the traversing cylinder component 2-7 is located on the sill 2-6, the entablature 2-1 and the sill
By the telescopic 2-4 connections between 2-6, the bearing diagonal is included between the entablature 2-1 and the sill 2-6
2-9, and the lower end of the bearing diagonal 2-9 is supported on the sill 2-6, the upper end of the bearing diagonal 2-9 is supported in one
Between plate 2-10, the jacking cylinder component 2-5 is located on the intermediate plate 2-10, and the jacking cylinder component 2-5 other ends
The entablature 2-1 is connected, passes through the flexible adjustment intermediate plate 2-10 of the jacking cylinder component 2-5 and the entablature
The distance between 2-1, the anti-change gear drive device 2-2 and the vertical shift cylinder component 2-3 are located on the entablature 2-1,
The girder 5 is supported by the slide plate 10 again on the anti-change gear drive device 2-2 and the vertical shift cylinder component 2-3.
The entablature 2-1 is by lower flange automatic movings of the anti-change gear drive device 2-2 along the girder 5, and the upper horizontal stroke
The vertical shift cylinder component 2-3 is additionally provided with beam 2-1, is the telescopic 2-4 in the outside of front leg strut 2.
Wherein, at the front leg strut 2, the first transverse-moving trolley 6A includes first, second chassis 6A-1,6A-2, institute
State first, second chassis 6A-1,6A-2 and be located at the both sides of girder 5 respectively, and by corresponding two first jack machinisms
1A is drawn, and described first, second chassis 6A-1,6A-2 are respectively used to same one end that frame concrete beam 8,8 ' is treated in handling two.
As shown in figs. 3 and 6, Fig. 3 is Fig. 1 of the utility model embodiment section B-B view, and Fig. 6 is the utility model
A kind of side view of the middle supporting leg of symmetrical formula Bridge Erector of setting a roof beam in place of another embodiment, the middle supporting leg 3 include entablature 3-1, anti-
Change gear drive device 3-2, vertical shift cylinder component 3-3, telescopic 3-4, jacking cylinder component 3-5, sill 3-6, slew gear
3-7 and lower support beam 3-8.Wherein, the middle supporting leg 3 is supported on described on the beam face of frame concrete beam 9, is passed through slide plate 11 and is supported institute
Girder 5 is stated, by the anti-change gear drive device 3-2 along the lower flange automatic moving of girder 5.The middle supporting leg 3 can be voluntarily
Height is adjusted to adapt to line slope.The middle supporting leg 3 sets the slew gear 3-7 to coordinate the front leg strut 2 whole to meet
Machine curve via holes.
Wherein, the lower support beam 3-8 is supported on described on the beam face of frame concrete beam 9, wherein, 9, the concrete of the frame beam
In on the pier face of the rear abutment 7B, the slew gear 3-7 is located on the lower support beam 3-8, the sill 3-6 positions
In on the slew gear 3-7, pass through the telescopic 3-4 connections, institute between the entablature 3-1 and the sill 3-6
State jacking cylinder component 3-5 to be located on the sill 3-6, the jacking cylinder component 3-5 other ends connect the entablature
3-1, by the distance between flexible adjustment described entablature 3-1 and the sill 3-6 of the jacking cylinder component 3-5,
The anti-change gear drive device 3-2 and vertical shift cylinder component 3-3 is located on the entablature 3-1, is driven in the anti-change gear
The girder 5 is supported by the slide plate 11 again on the dynamic device 3-2 and vertical shift cylinder component 3-3.
Wherein, at the middle supporting leg 3, the second transverse-moving trolley 6B includes the three, the 4th chassis 6B-1,6B-2, institute
State the three, the 4th chassis 6B-1,6B-2 and be located at the both sides of girder 5 respectively, and by corresponding two second jack machinisms
1B is drawn, and described three, the 4th chassis 6B-1,6B-2 be respectively used to the same other end that frame concrete beam 8,8 ' is treated in handling two, i.e., and the
Frame concrete beam 8, the second chassis 6A-2 and the 4th another of chassis 6B-2 handlings are treated in one chassis 6A-1 and three chassis 6B-1 handlings one
Treat frame concrete beam 8 '.
As illustrated in figures 4 and 7, Fig. 4 is Fig. 1 of the utility model embodiment C-C section views, and Fig. 7 is the utility model
A kind of side view of the rear support leg of symmetrical formula Bridge Erector of setting a roof beam in place of another embodiment, the rear support leg 4 include tie-beam 4-1, on
Crossbeam 4-2, telescopic 4-3, jacking cylinder component 4-4 and lower support beam 4-5.Wherein, the rear support leg 4 is supported on the frame
On the beam face of concrete beam 9, the rear support leg 4 is fixedly mounted on the afterbody of girder 5, can voluntarily adjust height to adapt to circuit slope
Degree.
The lower support beam 4-5 be supported on it is described on the beam face of frame concrete beam 9, wherein the concrete of the frame beam 9 is located at bridge pier
On, the entablature 4-2 is connected with the lower support beam 4-5 by the telescopic 4-3, on the lower support beam 4-5 also
The jacking cylinder component 4-4 is provided with, the other end of the jacking cylinder component 4-4 connects the entablature 4-2, passes through institute
State that jacking cylinder component 4-4 is flexible can to adjust the distance between the entablature 4-2 and the lower support beam 4-5, the company
Meet beam 4-1 to be located on the entablature 4-2, and the tie-beam 4-1 other ends connect the girder 5.
As shown in figure 8, a kind of girder section view of symmetrical formula Bridge Erector of setting a roof beam in place for another embodiment of the utility model,
The girder 5 includes main frame 5-1, cantilever beam 5-2, vertical shift slide rail 5-3.The girder 5 is single-beam form, and middle part sets left and right
Symmetrical cantilever beam 5-2, i.e., described cantilever beam 5-2 are arranged symmetrically in main frame 5-1 both sides, and the vertical shift slide rail 5-3 is positioned at described
Main frame 5-1 lower ends, meet transverse-moving trolley transverse shifting hanging beam function,
What the utility model embodiment was provided symmetrical sets a roof beam in place the technical scheme of formula Bridge Erector and operation principle is institute as follows
State, as shown in figure 1, the symmetrical formula Bridge Erector of setting a roof beam in place finishes in end of the bridge spelling, before front leg strut 2 is supported on bridge pier, middle supporting leg 3
Liang Mianshang is supported on, rear support leg 4 is hanging.By adjusting the jacking cylinder component 2-5 of front leg strut 2 and the jacking cylinder of middle supporting leg 3
Component 3-5, make girder 5 horizontal.By operating the first jack machinism 1A, the second jack machinism 1B, the first transverse-moving trolley 6A and the
Two transverse-moving trolley 6B, frame two panels concrete beam synchronous hoisting is treated, it is synchronous traversing, in synchronous decentralization to bridge pier.Above-mentioned synchronism is by electric
System security, it has been technology known to those skilled in the art, has will not be described here.
It is this reality as shown in figure 11 when the symmetrical formula Bridge Erector of setting a roof beam in place of the utility model embodiment sets up downhill bridge
Downhill bridge state diagram is set up with the symmetrical formula Bridge Erector of setting a roof beam in place of one kind of new another embodiment, middle supporting leg 3 is highly constant, front leg strut
2 height are adjusted by jacking cylinder component 2-5 to be increased, and keeps girder 5 horizontal.
It is this reality as shown in figure 12 when the symmetrical formula Bridge Erector of setting a roof beam in place of the utility model embodiment sets up slope-climbing road
Slope-climbing road state diagram is set up with the symmetrical formula Bridge Erector of setting a roof beam in place of one kind of new another embodiment, middle supporting leg 3 is highly constant, front leg strut
2 height are adjusted by jacking cylinder component 2-5 to be reduced, and keeps girder 5 horizontal.
Therefore, the symmetrical formula Bridge Erector of setting a roof beam in place of the utility model embodiment, it is possible to achieve beam car is in bridge pier both sides
Ground on transport beam, i.e., transport beam under line, and two panels concrete beam is packed simultaneously using two beam cars, directly pack to waiting to set a roof beam in place under
Side.The transverse-moving trolley of Bridge Erector is laterally moved to both sides, and the suspender contraposition of jack machinism lower section is treated frame concrete beam, lifted by crane simultaneously after affixed, whole
Machine left-right balance, without drawing anchor and counterweight.Transverse-moving trolley is simultaneously traversing to inboard at the same speed after lifting in place, in place rear two panels concrete beam
Dropping place is on bridge pier simultaneously.So far, first group of two panels concrete erection is completed, and then repeatedly above-mentioned operation sets up next group of concrete beam.
The symmetrical formula Bridge Erector of setting a roof beam in place of the utility model embodiment be in existing highway bridge construction, per bridge by two panels or
Multi-disc Prefabricated Concrete beam forms, and needs concrete beam is repeatedly set up piecewise situation and utility model design.The jack machinism possesses together
When symmetrical hang carry two panels concrete beam function, by the symmetrical traversing fortune beam of transverse-moving trolley, in place after fall beam simultaneously, therefore effect of constructing
Rate doubles, and by the dead-weight balanced complete machine lateral stability of concrete beam, is laterally applied without counterweight or the pre-buried anchoring of pier top, reduction
Work Field Force's workload, increase economic efficiency and integral construction efficiency.Circuit bridge can be realized by adjusting each supporting leg state
The gradient is set up and curve is set up.Voluntarily vertical shift via can also be driven by front leg strut and middle supporting leg.
Another embodiment of the present utility model also provides a kind of beam erecting method of symmetrical formula Bridge Erector of setting a roof beam in place, as Fig. 9-1 to
Shown in 9-5, Fig. 9-1 to 9-5 is respectively a kind of symmetrical formula girder erection by bridging machine process of setting a roof beam in place of another embodiment of the utility model
State diagram, wherein, Fig. 9-2 to 9-5 does not show each supporting leg, the symmetrical formula girder erection by bridging machine side that sets a roof beam in place of the utility model embodiment
For method so that single hole bridge is made up of four concrete beams (i.e. two panels treats frame concrete beam 8,8 ' and two panels frame concrete beam 9) as an example, main process is as follows
It is described.
Step 91, as shown in Fig. 9-1, Fig. 9-2, treat that the two panels of frame is treated that frame concrete beam 8,8 ' is placed in advance by beam car and treated
Frame bridge pier both sides, mounting hanger, jack machinism will treat frame concrete beam 8,8 ' by being sling under line, and two panels treats frame concrete beam 8,8 ' synchronization onwards
Rise.
Step 92, as shown in Fig. 9-3, jack machinism lifting after frame concrete beam 8,8 ' in place after, both sides on the cantilever beam of girder
Transverse-moving trolley it is synchronous symmetrically traversing to wire center direction.
Step 93, as shown in Fig. 9-4, two panels treats that frame concrete beam 8,8 ' synchronously is laterally moved to beam position, and jack machinism is synchronous by two
Piece treats the decentralization of frame concrete beam 8,8 ' to bridge pier, and be in the milk firm concrete beam support, releases suspender.
Step 94, as shown in Fig. 9-5, transverse-moving trolley is laterally moved to hanging beam position, above-mentioned step 91 of setting a roof beam in place is repeated to 93, by residue
Two panels treats that frame concrete beam 8,8 ' is set up and completes, carry out between four concrete beams it is affixed be connected, so far this bridge sets up and finished.
Another embodiment of the present utility model also provides a kind of passing method of symmetrical formula Bridge Erector of setting a roof beam in place, Figure 10-1~figure
10-5 is a kind of state diagram of symmetrical formula Bridge Erector via process of setting a roof beam in place of another embodiment of the utility model, and the utility model is real
The passing method of the symmetrical formula Bridge Erector of setting a roof beam in place of example is applied, main process is as described below.
Step 101, as shown in Figure 10-1, the jacking cylinder component 4-4 of rear support leg 4 is packed up, rear support leg 4 is departed from bridge floor.
The vertical shift cylinder component 2-3 of front leg strut 2 and the vertical shift cylinder component 3-3 of middle supporting leg 3 are driven, makes the stepped advancement of girder 5.
Step 102, as shown in Figure 10-2, after girder 5 moves forward in place, the jacking cylinder component 4-4 of rear support leg 4 is stretched out, is made
Rear support leg 4 is supported on Liang Mianshang.
Step 103, as shown in Figure 10-3, the jacking cylinder component 3-5 of middle supporting leg 3 is packed up, middle supporting leg 3 is departed from bridge floor,
It is suspended on the bottom wing listrium of girder 5.The anti-change gear drive device 3-2 of supporting leg 3, makes middle supporting leg 3 move forward in unlatching.
Step 104, as shown in Figure 10-4, middle supporting leg 3 moves forward in place, and the jacking cylinder component 3-5 of supporting leg 3, makes in stretching
Middle supporting leg 3 is supported on Liang Mianshang.The jacking cylinder component 2-5 of front leg strut 2 is packed up, front leg strut 2 is departed from bridge floor, is suspended on girder
On 5 bottom wing listriums.The anti-change gear drive device 2-2 of front leg strut 2 is opened, front leg strut 2 is moved forward.
Step 105, as shown in Figure 10-5, front leg strut 2 moves forward in place, stretches out the jacking cylinder component 2-5 of front leg strut 2, makes
Front leg strut 2 is supported on bridge pier.Rear support leg 4 is packed up, drives the vertical shift cylinder component 2-3 of front leg strut 2 and the vertical shift oil of middle supporting leg 3
Cylinder component 3-3, make the stepped advancement of girder 5 in place.So far formula Bridge Erector of symmetrically setting a roof beam in place moves forward a span from via is completed, and is reached
To the state of setting a roof beam in place.
By foregoing description, the symmetrical formula Bridge Erector of setting a roof beam in place of the utility model embodiment, conventional beam car is eliminated
Coordinate the process of Bridge Erector feeding beam, beam is transported under line directly to position of setting a roof beam in place;Two panels concrete beam is set up simultaneously, efficiency of setting a roof beam in place doubles;
Complete machine need not laterally draw anchor or counterweight, reduce job site personnel workload, increase economic efficiency and integral construction efficiency.
It is last it should be noted that:Above example is only to illustrate the technical solution of the utility model, rather than it is limited
System;Although the utility model is described in detail with reference to the foregoing embodiments, one of ordinary skill in the art should manage
Solution:It can still be modified to the technical scheme described in foregoing embodiments, or which part technical characteristic is entered
Row equivalent substitution;And these modifications or replacement, the essence of appropriate technical solution is departed from various embodiments of the utility model
The spirit and scope of technical scheme.
Claims (6)
1. a kind of symmetrical formula Bridge Erector of setting a roof beam in place, it is characterised in that the symmetrical formula Bridge Erector of setting a roof beam in place includes the first jack machinism
(1A), the second jack machinism (1B), front leg strut (2), middle supporting leg (3), rear support leg (4), girder (5), the first transverse-moving trolley (6A)
With the second transverse-moving trolley (6B);
Wherein, treat that frame concrete beam (8,8 ') will be used for frame between preceding bridge pier (7A) and rear abutment (7B) for two, the rear abutment
(7B) opposite side has been mounted with frame concrete beam (9);Front leg strut (2) branch is stood on the preceding bridge pier (7A), the middle branch
Leg (3) branch is stood on described on frame concrete beam (9), and first transverse-moving trolley (6A) and second transverse-moving trolley (6B) are located at institute
State on girder (5) and can be moved in the girder (5);
At the front leg strut (2) place, first transverse-moving trolley (6A) includes first, second chassis (6A-1,6A-2), and described
First, the second chassis (6A-1,6A-2) is located at the girder (5) both sides respectively, and by corresponding two first jack machinisms
(1A) is drawn, and first, second chassis (6A-1,6A-2) is respectively used to same one end that frame concrete beam (8,8 ') are treated in handling two;
At middle supporting leg (3) place, second transverse-moving trolley (6B) includes the three, the 4th chassis (6B-1,6B-2), and described
3rd, the 4th chassis (6B-1,6B-2) is located at the girder (5) both sides respectively, and by corresponding two second jack machinisms
(1B) is drawn, and the three, the 4th chassis (6B-1,6B-2) is respectively used to handling two and treats the same another of frame concrete beam (8,8 ')
End.
2. Bridge Erector as claimed in claim 1, it is characterised in that the front leg strut (2) includes entablature (2-1), anti-change gear
Drive device (2-2), vertical shift cylinder component (2-3), telescopic (2-4), jacking cylinder component (2-5), sill (2-6), horizontal stroke
Move cylinder component (2-7), lower template beam (2-8) and bearing diagonal (2-9) and intermediate plate (2-10);Wherein, the front leg strut (2) passes through
The lower template beam (2-8) is supported on the pier top face of the preceding bridge pier (7A), is supported the girder (5) by slide plate (10), is led to
Cross lower flange automatic moving of the anti-change gear drive device (2-2) along the girder (5);The front leg strut (2) voluntarily adjusts
Height is to adapt to line slope;The front leg strut (2) sets traversing cylinder component (2-7) to meet complete machine curve via holes.
3. Bridge Erector as claimed in claim 2, it is characterised in that the lower template beam (2-8) is supported on the preceding bridge pier (7A)
Pier top face on, the sill (2-6) is located on the lower template beam (2-8), and the traversing cylinder component (2-7) is positioned at described
On sill (2-6), connected between the entablature (2-1) and the sill (2-6) by the telescopic (2-4),
Include the bearing diagonal (2-9) between the entablature (2-1) and the sill (2-6), and under the bearing diagonal (2-9)
End is supported on the sill (2-6), and the upper end of the bearing diagonal (2-9) supports an intermediate plate (2-10), the jacking
Cylinder component (2-5) is located on the intermediate plate (2-10), and the jacking cylinder component (2-5) other end connects the upper horizontal stroke
Beam (2-1), pass through the flexible adjustment intermediate plate (2-10) and the entablature (2-1) of the jacking cylinder component (2-5)
The distance between, the anti-change gear drive device (2-2) and the vertical shift cylinder component (2-3) are located at the entablature (2-1)
On, institute is supported by the slide plate (10) again on the anti-change gear drive device (2-2) and the vertical shift cylinder component (2-3)
State girder (5);The entablature (2-1) by lower flange of the anti-change gear drive device (2-2) along the girder (5) voluntarily
It is mobile, and the vertical shift cylinder component (2-3) is additionally provided with the entablature (2-1), it is described on the outside of the front leg strut (2)
Telescopic (2-4).
4. Bridge Erector as claimed in claim 1, it is characterised in that the middle supporting leg (3) includes entablature (3-1), anti-change gear
Drive device (3-2), vertical shift cylinder component (3-3), telescopic (3-4), jacking cylinder component (3-5), sill (3-6), return
Rotation mechanism (3-7) and lower support beam (3-8);Wherein, the middle supporting leg (3) is supported on described on the beam face of frame concrete beam (9), leads to
Cross slide plate (11) and support the girder (5), by the anti-change gear drive device (3-2) along the girder (5) lower flange voluntarily
It is mobile;The middle supporting leg (3) voluntarily adjusts height to adapt to line slope;The middle supporting leg (3) sets the slew gear (3-
7) front leg strut (2) is coordinated to meet complete machine curve via holes.
5. Bridge Erector as claimed in claim 4, it is characterised in that the lower support beam (3-8) is supported on the frame concrete beam
(9) on beam face, wherein, the concrete of the frame beam (9) is located on the pier face of the rear abutment (7B), the slew gear (3-7)
Positioned on the lower support beam (3-8), the sill (3-6) is located on the slew gear (3-7), the entablature
Connected between (3-1) and the sill (3-6) by the telescopic (3-4), the jacking cylinder component (3-5) is located at institute
State on sill (3-6), jacking cylinder component (3-5) other end connects the entablature (3-1), passes through the jacking oil
The distance between described entablature of flexible adjustment (3-1) and the sill (3-6) of cylinder component (3-5), the anti-change gear drive
Dynamic device (3-2) and the vertical shift cylinder component (3-3) are located on the entablature (3-1), in the anti-change gear drive device
The girder (5) is supported by the slide plate (11) again on (3-2) and the vertical shift cylinder component (3-3).
6. Bridge Erector as claimed in claim 1, it is characterised in that the rear support leg (4) includes tie-beam (4-1), entablature
(4-2), telescopic (4-3), jacking cylinder component (4-4) and lower support beam (4-5);
The lower support beam (4-5) be supported on it is described on the beam face of frame concrete beam (9), wherein the concrete of the frame beam (9) is located at bridge
On pier, the entablature (4-2) and the lower support beam (4-5) are connected by the telescopic (4-3), in the lower support beam
The jacking cylinder component (4-4) is additionally provided with (4-5), the other end of the jacking cylinder component (4-4) is connected on described
Crossbeam (4-2), pass through the jacking cylinder component (4-4) the flexible adjustment entablature (4-2) and the lower support beam (4-5)
The distance between, the tie-beam (4-1) is located on the entablature (4-2), and the tie-beam (4-1) other end connection institute
State girder (5).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720212230.3U CN206635657U (en) | 2017-03-06 | 2017-03-06 | A kind of symmetrical formula Bridge Erector of setting a roof beam in place |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720212230.3U CN206635657U (en) | 2017-03-06 | 2017-03-06 | A kind of symmetrical formula Bridge Erector of setting a roof beam in place |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206635657U true CN206635657U (en) | 2017-11-14 |
Family
ID=60251889
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720212230.3U Active CN206635657U (en) | 2017-03-06 | 2017-03-06 | A kind of symmetrical formula Bridge Erector of setting a roof beam in place |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206635657U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108439206A (en) * | 2018-04-09 | 2018-08-24 | 中交武汉港湾工程设计研究院有限公司 | A kind of rachis face steel box-girder monoblock type erection crane |
| CN108532462A (en) * | 2017-03-06 | 2018-09-14 | 秦皇岛天业通联重工科技有限公司 | A kind of symmetrically set a roof beam in place and its is set a roof beam in place, passing method at formula Bridge Erector |
| CN110593131A (en) * | 2019-10-16 | 2019-12-20 | 合肥正浩机械科技有限公司 | A cross-traversal avoidance beam drop device and beam drop method of a bridge erecting machine |
-
2017
- 2017-03-06 CN CN201720212230.3U patent/CN206635657U/en active Active
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108532462A (en) * | 2017-03-06 | 2018-09-14 | 秦皇岛天业通联重工科技有限公司 | A kind of symmetrically set a roof beam in place and its is set a roof beam in place, passing method at formula Bridge Erector |
| CN108439206A (en) * | 2018-04-09 | 2018-08-24 | 中交武汉港湾工程设计研究院有限公司 | A kind of rachis face steel box-girder monoblock type erection crane |
| CN108439206B (en) * | 2018-04-09 | 2024-04-09 | 中交武汉港湾工程设计研究院有限公司 | Integral bridge floor crane of central cable plane steel box girder |
| CN110593131A (en) * | 2019-10-16 | 2019-12-20 | 合肥正浩机械科技有限公司 | A cross-traversal avoidance beam drop device and beam drop method of a bridge erecting machine |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102071650B (en) | Universal bridging machine inside and outside Railway Tunnel | |
| CN105780660B (en) | A kind of section assembling box girder construction technique | |
| CN101851898B (en) | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof | |
| CN109653105B (en) | Main truss system of box girder bridge cantilever construction hanging basket and use method thereof | |
| CN109695204B (en) | Bridge girder erection machine and bridge girder erection method | |
| CN104003320B (en) | Hydraulic pressure changes the outfit frame and rapid-assembling method thereof | |
| CN104594198B (en) | For the method for setting up juxtaposition case beam in tunnel | |
| CN110158486B (en) | Bridge girder erection machine for erecting spliced wide beams and construction method | |
| CN206635657U (en) | A kind of symmetrical formula Bridge Erector of setting a roof beam in place | |
| CN1609342A (en) | Down-guiding girder type bridge erecting machine and its beam erecting method | |
| CN108677742A (en) | The moving cantilever type Bridge Erector of full precast pier, cushion cap and beam body prefabricated construction | |
| CN114808747A (en) | Multifunctional bridge girder erection machine and bridge girder erection construction method | |
| CN210561749U (en) | A multi-frame juxtaposed double cantilever bridge erecting machine | |
| CN102134832A (en) | Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane | |
| CN105648925B (en) | Section assembling box beam erection Bridge Erector | |
| CN201943004U (en) | Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal | |
| CN106758872A (en) | Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution | |
| CN115465791A (en) | A bridge deck separation belt cover installation trolley and installation method | |
| CN107747280A (en) | The Bridge Erector of full span erection steel-pipe concrete truss | |
| CN108532462A (en) | A kind of symmetrically set a roof beam in place and its is set a roof beam in place, passing method at formula Bridge Erector | |
| CN105839548B (en) | Section assembling box beam erection construction technology based on down-type bridge-erecting machine | |
| CN205954500U (en) | Balanced free cantilever erection frame bridge crane of single girder low level | |
| CN100395411C (en) | Walking box girder bridge erecting machine | |
| CN106400700A (en) | Double-line cantilever type bridge formation machine | |
| CN205636494U (en) | HZQY900 type fortune frame all -in -one |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |