[go: up one dir, main page]

CN205346400U - Room formula bag package shipment equipment of in bundling - Google Patents

Room formula bag package shipment equipment of in bundling Download PDF

Info

Publication number
CN205346400U
CN205346400U CN201620094434.7U CN201620094434U CN205346400U CN 205346400 U CN205346400 U CN 205346400U CN 201620094434 U CN201620094434 U CN 201620094434U CN 205346400 U CN205346400 U CN 205346400U
Authority
CN
China
Prior art keywords
column
assembly
beam assembly
vertical beam
purlin car
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620094434.7U
Other languages
Chinese (zh)
Inventor
盛文理
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENLING SHENGKAI LOGISTIC EQUIPMENT TECHNOLOGY Co Ltd
Original Assignee
WENLING SHENGKAI LOGISTIC EQUIPMENT TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENLING SHENGKAI LOGISTIC EQUIPMENT TECHNOLOGY Co Ltd filed Critical WENLING SHENGKAI LOGISTIC EQUIPMENT TECHNOLOGY Co Ltd
Priority to CN201620094434.7U priority Critical patent/CN205346400U/en
Application granted granted Critical
Publication of CN205346400U publication Critical patent/CN205346400U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Packaging Of Machine Parts And Wound Products (AREA)

Abstract

The utility model belongs to the technical field of shipment equipment, refer in particular to a room formula bag package shipment equipment of in bundling, be provided with a left side respectively on controlling on -edge column base assembly, the roof beam assembly is found on the right side, a left side, the unsettled setting of front end of roof beam assembly is stood on the right side, on a left side, be provided with the shed roof between the last plane of the upright roof beam assembly in the right side, on a left side, before the upright roof beam assembly in the right side, before back both ends are passed through respectively, after connect the crossbeam and connect, in the front, after connect the left side between the crossbeam, the right side is found the roof beam assembly and is gone forward, back interval is provided with takes driving rail's two to go up purlin car spandrel girder, be provided with a left side between two driving rail, right side bale purlin car hangs equipment, be provided with the lower purlin car spandrel girder of taking driving rail respectively on the left and right medial surface that founds the roof beam assembly, set up the complete set bag package that has more than a set between two driving rail and in bundle the big purlin car that the combination lifted by crane and hang equipment, the utility model discloses have shed roof and wall body, have certain effect that protects from the wind and rain, improved workman's operational environment with all -weather loading operation's condition greatly.

Description

A kind of room formula bag pack is in bundled shipment equipment
Technical field:
This utility model belongs to shipment equipment technical field, refers in particular to that a kind of Ji Daibaoji dress is tied up, combined shipment, shipment equipment in bundled by the room formula bag pack being integrated that protects from the wind and rain.
Background technology:
At present, bag cargo is typically all the pattern transported by Bales Off.This transhipment pattern also exists following defect: outbound, transfer in Material Transportation process and enter in the middle of the links such as storehouse, be substantially all the original manpower of employing coordinates certain machinery to carry by hand in units of Bales Off, so, not only to consume a lot of man power and materials, and working strength is high, inefficiency, meanwhile, also easily causes the breakage of Bales Off material packing and the loss of goods and materials.Furthermore, this transporting mode is work post the most arduous in logistic industry, especially the handling of shipping of goods, the breakage of packaging is very big, if dress is powdery goods and materials in packaging, carrying can produce substantial amounts of airborne dust, not only to environment, meanwhile, also the healthy of workman in serious threat.Particularly during high temperature; because considering the operating of loop wheel machine; workman is typically under burning sun to carry out operation; measure also without cooling dedusting; the working environment very severe of workman; heatstroke phenomenon is often there is because of high temperature, also can because of dust generation skin allergy, the work of this severe working environment and over loading has severely impacted the physical and mental health of workman.
Along with the progress of technical merit, bag cargo Bales Off transhipment will become history.Collection dress bale packing transhipment pattern preliminarily forms, and certainly will move towards to popularize in an all-round way.The transhipment of bag pack containerization is the logistic pattern of a kind of innovation, and adopting conventional logistics equipment is the operation that cannot complete overall process.
Summary of the invention:
The purpose of this utility model is to provide a kind of simple, convenient, loads and unloads effective room formula bag pack and in bundles shipment equipment.
This utility model is achieved in that
A kind of room formula bag pack is in bundled shipment equipment, include a left side, the column foot assembly that right septum is arranged, every edge-on suspension column assembly is provided with two or more, left side column foot assembly is provided with left vertical beam assembly, right side uprights foot assembly is provided with right vertical beam assembly, left vertical beam assembly, the unsettled setting in front end of right vertical beam assembly, at left vertical beam assembly, it is provided with ceiling between the upper plane of right vertical beam assembly, at left vertical beam assembly, before right vertical beam assembly, rear two ends are respectively through front connecting cross beam, rear connecting cross beam connects, at front connecting cross beam, left vertical beam assembly between rear connecting cross beam, right vertical beam assembly is gone forward, after be arranged at intervals with on two purlin car spandrel girder, on two, the upper plane of purlin car spandrel girder is provided with Crane Rail, it is provided with left bale packing purlin car between two Crane Rails and hangs equipment and right bale packing purlin car hangs equipment;The medial surface of left and right vertical beam assembly is respectively arranged with lower purlin car spandrel girder, twice purlin car spandrel girders are provided with Crane Rail, being provided with the in bundle big purlin car of combination lifting of a set of above complete bag pack between two Crane Rails and hang equipment, left bale packing purlin car hangs equipment, right bale packing purlin car hangs equipment, big purlin car hangs the action of equipment by electric controller control.
In technique scheme, described twice purlin car spandrel girder mounting seats and corresponding Crane Rail extend to the back-end, and the elongated end of twice purlin car spandrel girder mounting seats is connected with column foot assembly, and is supported by column foot assembly.
In technique scheme, described left vertical beam assembly, right vertical beam assembly includes the front column that time interval is arranged, central post and rear column, the height of central post is higher than front column, rear column, between front column and central post, the unsettled post of more than one it is arranged at intervals with between central post and rear column, in each column and each unsettled post, connected by linking beam between bottom, the top of each column and each unsettled post is connected by herringbone beam, at front column, rear column and each unsettled post are provided with and hold cable regulating device, hold and be connected by bearing rope between cable regulating device and the top of central post.
In technique scheme, upper and lower between two described central posts it is arranged at intervals with more than one connecting cross beam, lower connecting cross beam is positioned at the middle part of central post, and higher than front connecting cross beam, rear connecting cross beam, described left vertical beam assembly, right vertical beam assembly the back of herringbone beam be provided with horizontal trusses, ceiling is covered in the upper plane on horizontal trusses.
In technique scheme, the ladder that personnel that described central post is provided with overhaul up and down.
In technique scheme, described every edge-on suspension column assembly is respectively arranged with two, rear end being positioned at left and right vertical beam assembly, another be positioned at the middle part of left and right vertical beam assembly.
In technique scheme, described column foot assembly is made up of the bearing column foot being vertically arranged and the column foot that bears that is obliquely installed, bearing column foot and the upper end bearing column foot are connected with installing plate, installing plate is connected with the left and right central post of vertical beam assembly and the baseplane of rear column, at bearing column foot and bear the web beam being provided with more than between column foot, at bearing column foot and bear the bottom of column foot and be provided with the end installing plate for being connected with ground.
In technique scheme, it is provided with diagonal angle between two bearing column feet of described every edge-on suspension column assembly and connects the reinforcement structure of the X-shaped formed.
In technique scheme, described in bear column foot be provided with ladder.
In technique scheme, described left and right vertical beam assembly, between forward and backward connecting cross beam and ground, it is provided with body of wall, is connected with each other between adjacent body of wall, and be connected formation house with ceiling.
The advantage that this utility model highlights compared to existing technology is:
1, this utility model has ceiling and body of wall, has certain effect protected from the wind and rain, and substantially increases the working environment of workman and the condition of round-the-clock ship-loading operation;
2, left vertical beam assembly of the present utility model, right vertical beam assembly unsettled of front end choose to the water surface of wharf apron, carrying vessel is made to freight by access arrangement job area, conveniently bag pack is delivered to inside cabin, simultaneously, operator can operate on freighter deck, improves the safety coefficient of the speed of loading, quality and operation;
3, twice purlin car spandrel girder mounting seats of the present utility model extend to the back-end, and the big purlin car being disposed thereon hangs equipment and can move to extending part, it is possible to carry out car loading operation, use scope wide;
4, column of the present utility model is higher than ceiling, adopts the left and right vertical beam assembly oblique pull bearing Suo Xiangqian rear, and employing is held cable regulating device and tightened, it is achieved suspension frame heavy burden effect;
5, on this utility model, purlin car spandrel girder mounting seat, lower purlin car spandrel girder mounting seat are that upper and lower two-layer is arranged, it is achieved upper and lower, vertical, horizontal cross-operation coordinates automatic bag stacking machine to realize automatic stacked package, lifts by crane, ties up, combines, loads one continuous line seamless link operation onto ship;
6, this utility model can operate when shipment on freighter deck, and sight line is very good, therefore improves shipment quality and safety work;
7, this utility model is greatly improved the transport efficiency of bag pack, expands the transport scope of bag pack;
8, this utility model achieves and running speed and quality is greatly improved, and the operating of bag pack cargo handling completely zero is damaged, has broken away from bag cargo up hill and dale and has produced, in handling transfer operation process, the atmospheric pollution that airborne dust causes;Decrease more than 80 the percent of transfer handling labour;The dirty physical work of weight is all cancelled;Logistics cost is greatly reduced;Effectively improve the quality of life of practitioner;Eliminate the potential safety hazard that bag cargo handling operation field labor is intensive.
Accompanying drawing illustrates:
Fig. 1 is schematic perspective view of the present utility model;
Fig. 2 is the schematic perspective view that this utility model does not install ceiling, body of wall;
Fig. 3 is the schematic perspective view not installing ceiling, body of wall, column foot assembly of the present utility model;
Fig. 4 is side of the present utility model solid simplified schematic diagram;
Fig. 5 is the simplified schematic diagram of column foot assembly of the present utility model.
Detailed description of the invention:
With specific embodiment, this utility model is further described below, referring to Fig. 15:
A kind of room formula bag pack is in bundled shipment equipment, include a left side, the column foot assembly 1 that right septum is arranged, every edge-on suspension column assembly 1 is provided with two or more, left side column foot assembly 1 is provided with left vertical beam assembly 2, right side uprights foot assembly 1 is provided with right vertical beam assembly 3, left vertical beam assembly 2, the unsettled setting in front end of right vertical beam assembly 3, at left vertical beam assembly 2, it is provided with ceiling 4 between the upper plane of right vertical beam assembly 3, what the present embodiment adopted is iron sheet watt ceiling, at left vertical beam assembly 2, before right vertical beam assembly 3, rear two ends are respectively through front connecting cross beam 5, rear connecting cross beam 6 connects, at front connecting cross beam 5, left vertical beam assembly 2 between rear connecting cross beam 6, right vertical beam assembly 3 is gone forward, after be arranged at intervals with on two groups purlin car spandrel girder mounting seat, often group upper purlin car spandrel girder mounting seat is provided with purlin car spandrel girder 7, on two, the upper plane of purlin car spandrel girder 7 is provided with Crane Rail, it is provided with left bale packing purlin car between two Crane Rails and hangs equipment 8 and right bale packing purlin car hangs equipment 9, left bale packing purlin car hangs equipment 8 and right bale packing purlin car hangs the two ends of equipment 9 and is separately positioned on two on purlin car spandrel girder 7 and can move back and forth by the Crane Rail on purlin car spandrel girder 7 along two;On a left side, right vertical beam assembly 2, the medial surface of 3 is respectively arranged with lower purlin car spandrel girder mounting seat, the baseplane of lower purlin car spandrel girder 10 is fixing with the upper plane of lower purlin car spandrel girder mounting seat 17 to be connected, the upper plane of lower purlin car spandrel girder 10 is provided with Crane Rail, it is provided with the in bundle big purlin car of combination lifting of a set of above complete bag pack between two Crane Rails and hangs equipment 11, as arranged a set of or two sets, the present embodiment is provided with two sets, big purlin car hangs the two ends of equipment 11 and can move back and forth by the Crane Rail along twice purlin car spandrel girders 10, left bale packing purlin car hangs equipment 8, right bale packing purlin car hangs equipment 9, big purlin car hangs the action of equipment 11 by electric controller control.
In technique scheme, described twice purlin car spandrel girder mounting seats 10 extend to the back-end, and development length is arranged according to actual needs.The elongated end of twice purlin car spandrel girder mounting seats 10 is connected with column foot assembly 1, and is supported by column foot assembly 1.At this point it is possible to occasion uses in entrucking, warehouse entry storehouse etc..
In technique scheme, described left vertical beam assembly 2, right vertical beam assembly 3 includes the front column 12 that time interval is arranged, central post 13 and rear column 14, the height of central post 13 is higher than front column 12, rear column 14, between front column 12 and central post 13, the unsettled post 15 of more than one it is arranged at intervals with between central post 13 and rear column 14, at each column 12, 13, 14 and each unsettled post 15 in, connected by linking beam between bottom, each column 12, 13, 14 and the top of each unsettled post 15 connected by herringbone beam 16, at front column 12, the outer side elevation of rear column 14 and each unsettled post 15 is provided with and holds cable regulating device 18, inner side facade is provided with lower purlin car spandrel girder mounting seat 17, hold and be connected by bearing rope 19 between cable regulating device 18 and the top of central post 13, the suspension ring connected it are provided with at the top of central post 13.The rate of tension bearing rope 19 is regulated by holding cable regulating device 18.
The two ends facade of front connecting cross beam 5 and the fixing connection of the medial surface of two front columns 12, the two ends facade of rear connecting cross beam 6 and the fixing connection of the medial surface of two rear columns 14.
Upper purlin car spandrel girder mounting seat is fixed on left vertical beam assembly 2, right vertical beam assembly on corresponding unsettled post 15.The two ends facade of twice purlin car spandrel girders 10 is fixing with inside the facade of corresponding unsettled post 15 to be connected.
In technique scheme, upper and lower between two described central posts 13 it is arranged at intervals with more than one connecting cross beam, the present embodiment is provided with two, upper connecting cross beam connects 20 tops connecing two central posts 13, lower connecting cross beam 21 is positioned at the middle part of central post 13, and higher than front connecting cross beam 5, rear connecting cross beam 6, described left vertical beam assembly 2, right vertical beam assembly 3 the back of herringbone beam 16 be provided with horizontal trusses, ceiling 4 is covered in the upper plane on horizontal trusses.Upper connecting cross beam connects 20, the two ends of lower connecting cross beam 21 are fixing with inside the inner side on 13 central posts 13 respectively is connected.
In technique scheme, the ladder 22 that personnel that described central post 13 is provided with overhaul up and down, it is simple to staff's is upper and lower.
Herringbone beam 16 enable installation after ceiling discharge rainwater, it is prevented that be collapsed ceiling.
In technique scheme, described every edge-on suspension column assembly 1 is respectively arranged with two, rear end being positioned at left and right vertical beam assembly 2,3, another be positioned at the middle part of left and right vertical beam assembly 2,3.
In technique scheme, described column foot assembly 1 is made up of the bearing column foot 23 being vertically arranged and the column foot 24 that bears that is obliquely installed, bearing column foot 23 and the upper end bearing column foot 24 are connected with installing plate 25, installing plate 25 is connected with central post 13 and rear column 14 baseplane of left and right vertical beam assembly 2,3, at bearing column foot 23 and bear the web beam 26 being provided with more than between column foot 24, at bearing column foot 23 and bear the bottom of column foot 24 and be provided with the end installing plate 27 for being connected with ground.
In technique scheme, it is provided with diagonal angle between two bearing column feet 23 of described every edge-on suspension column assembly 1 and connects the reinforcement structure 28 of the X-shaped formed.
In technique scheme, described in bear column foot 24 be provided with ladder 29, facilitate staff to overhaul up and down.
In technique scheme, described left and right vertical beam assembly 2,3, be provided with body of wall 30 between forward and backward connecting cross beam 5,6 and ground, be connected with each other between adjacent body of wall 30.Body of wall 30 and ceiling 4 form a room.Body of wall 30 is generally adopted iron sheet wall or cement wall or brick wall.
Operation principle of the present utility model:
This utility model in use, controls by electric controller that left bale packing purlin car hangs equipment 8, right bale packing purlin car hangs the equipment 9 position on upper purlin car spandrel girder installing rack 6, it is achieved tie up;
Controlled big purlin car by electric controller and hang the equipment 11 position on lower purlin car spandrel girder installing rack 10, it is achieved shipment;
By operation upper and lower, vertical, horizontal crossover location, coordinate full-automatic bag stacking machine to realize automatic stacked package, lift by crane, tie up, combine, load one continuous line seamless connection operation onto ship.
Above-described embodiment is only one of preferred embodiment of the present utility model, not limits practical range of the present utility model with this, therefore: all equivalence changes done according to shape of the present utility model, structure, principle, all should be covered by within protection domain of the present utility model.

Claims (10)

1. a room formula bag pack is in bundled shipment equipment, it is characterized in that: include a left side, the column foot assembly that right septum is arranged, every edge-on suspension column assembly is provided with two or more, left side column foot assembly is provided with left vertical beam assembly, right side uprights foot assembly is provided with right vertical beam assembly, left vertical beam assembly, the unsettled setting in front end of right vertical beam assembly, at left vertical beam assembly, it is provided with ceiling between the upper plane of right vertical beam assembly, at left vertical beam assembly, before right vertical beam assembly, rear two ends are respectively through front connecting cross beam, rear connecting cross beam connects, at front connecting cross beam, left vertical beam assembly between rear connecting cross beam, right vertical beam assembly is gone forward, after be arranged at intervals with on two purlin car spandrel girder, on two, the upper plane of purlin car spandrel girder is provided with Crane Rail, it is provided with left bale packing purlin car between two Crane Rails and hangs equipment and right bale packing purlin car hangs equipment;The medial surface of left and right vertical beam assembly is respectively arranged with lower purlin car spandrel girder, twice purlin car spandrel girders are provided with Crane Rail, being provided with the in bundle big purlin car of combination lifting of a set of above complete bag pack between two Crane Rails and hang equipment, left bale packing purlin car hangs equipment, right bale packing purlin car hangs equipment, big purlin car hangs the action of equipment by electric controller control.
2. a kind of room according to claim 1 formula bag pack is in bundled shipment equipment, it is characterized in that: described twice purlin car spandrel girder mounting seats and corresponding Crane Rail extend to the back-end, the elongated end of twice purlin car spandrel girder mounting seats is connected with column foot assembly, and is supported by column foot assembly.
3. a kind of room according to claim 1 formula bag pack is in bundled shipment equipment, it is characterized in that: described left vertical beam assembly, right vertical beam assembly includes the front column that time interval is arranged, central post and rear column, the height of central post is higher than front column, rear column, between front column and central post, the unsettled post of more than one it is arranged at intervals with between central post and rear column, in each column and each unsettled post, connected by linking beam between bottom, the top of each column and each unsettled post is connected by herringbone beam, at front column, rear column and each unsettled post are provided with and hold cable regulating device, hold and be connected by bearing rope between cable regulating device and the top of central post.
4. a kind of room according to claim 3 formula bag pack is in bundled shipment equipment, it is characterized in that: upper and lower between two described central posts be arranged at intervals with more than one connecting cross beam, lower connecting cross beam is positioned at the middle part of central post, and higher than front connecting cross beam, rear connecting cross beam, described left vertical beam assembly, right vertical beam assembly the back of herringbone beam be provided with horizontal trusses, ceiling is covered in the upper plane on horizontal trusses.
5. a kind of room according to claim 3 formula bag pack is in bundled shipment equipment, it is characterised in that: the ladder that the personnel that are provided with on described central post overhaul up and down.
6. a kind of room according to claim 1 formula bag pack is in bundled shipment equipment, it is characterised in that: described every edge-on suspension column assembly is respectively arranged with two, rear end being positioned at left and right vertical beam assembly, another be positioned at the middle part of left and right vertical beam assembly.
7. a kind of room formula bag pack according to claim 1 or 6 is in bundled shipment equipment, it is characterized in that: described column foot assembly is made up of the bearing column foot being vertically arranged and the column foot that bears that is obliquely installed, bearing column foot and the upper end bearing column foot are connected with installing plate, installing plate is connected with the left and right central post of vertical beam assembly and the baseplane of rear column, at bearing column foot and bear the web beam being provided with more than between column foot, at bearing column foot and bear the bottom of column foot and be provided with the end installing plate for being connected with ground.
8. a kind of room according to claim 7 formula bag pack is in bundled shipment equipment, it is characterised in that: it is provided with diagonal angle between two bearing column feet of described every edge-on suspension column assembly and connects the reinforcement structure of the X-shaped formed.
9. a kind of room according to claim 7 formula bag pack is in bundled shipment equipment, it is characterised in that: described in bear column foot be provided with ladder.
10. a kind of room according to claim 1 formula bag pack is in bundled shipment equipment, it is characterised in that: described left and right vertical beam assembly, between forward and backward connecting cross beam and ground, it is provided with body of wall, is connected with each other between adjacent body of wall, and is connected with ceiling and forms house.
CN201620094434.7U 2016-01-29 2016-01-29 Room formula bag package shipment equipment of in bundling Expired - Fee Related CN205346400U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620094434.7U CN205346400U (en) 2016-01-29 2016-01-29 Room formula bag package shipment equipment of in bundling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620094434.7U CN205346400U (en) 2016-01-29 2016-01-29 Room formula bag package shipment equipment of in bundling

Publications (1)

Publication Number Publication Date
CN205346400U true CN205346400U (en) 2016-06-29

Family

ID=56182618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620094434.7U Expired - Fee Related CN205346400U (en) 2016-01-29 2016-01-29 Room formula bag package shipment equipment of in bundling

Country Status (1)

Country Link
CN (1) CN205346400U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105460645A (en) * 2016-01-29 2016-04-06 温岭市盛开物流设备科技有限公司 House type bag bundling and shipping device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105460645A (en) * 2016-01-29 2016-04-06 温岭市盛开物流设备科技有限公司 House type bag bundling and shipping device
CN105460645B (en) * 2016-01-29 2018-05-22 温岭市盛开物流设备科技有限公司 A kind of room formula bag package bundle fills shipment equipment

Similar Documents

Publication Publication Date Title
CN101892736A (en) High altitude moving hanging basket construction method
CN205972386U (en) Shipment device that large -scale drum product was used
CN104060543A (en) Installation device of prefabricated bridge deck
CN205346400U (en) Room formula bag package shipment equipment of in bundling
RU2571042C2 (en) System for transportation of bulky objects
CN205346398U (en) Multistage folding belt of driving formula shipment machine
CN202483180U (en) Movable building material loading and unloading platform
US20030077154A1 (en) Empty container storage for the intermediate storage of empty iso containers
CN203529772U (en) Container loading and unloading system with double-layer cross-sea trestle
CN106639287B (en) Stone Vertical transportation resources in exterior wall scaffold
CN205973615U (en) Dual fixed elevating platform
CN105460645B (en) A kind of room formula bag package bundle fills shipment equipment
CN201649654U (en) Discharging platform for high-rise building construction
CN104481148B (en) A kind of ultralong thin walled color steel roofing construction method
CN219840354U (en) Aerial work platform for installing suspended ceiling in ultra-high steel structure
CN102730425A (en) Container storehouse wharf and using method of container storehouse wharf
CN209585651U (en) Floor material outward transportation system based on outer scaffold is exempted from to demolish
CN202575428U (en) Ceramic tile stack and ceramic tile stacking equipment
CN206407419U (en) A kind of container and movable panel
CN213011602U (en) Gantry tool for equipment installation and transportation
CN203960753U (en) A kind of erecting device of prefabricated bridge
CN108502578A (en) A kind of timber stacking knot installation and Wood Transportation system
CN207089909U (en) A common pallet for steel coil transportation
CN209009113U (en) A kind of irony turnover pallet
CN209321747U (en) A mobile maintenance plank road for automated three-dimensional warehouse

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160629

CF01 Termination of patent right due to non-payment of annual fee