[go: up one dir, main page]

CN1981099B - Crack control in cementitious materials - Google Patents

Crack control in cementitious materials Download PDF

Info

Publication number
CN1981099B
CN1981099B CN2005800204559A CN200580020455A CN1981099B CN 1981099 B CN1981099 B CN 1981099B CN 2005800204559 A CN2005800204559 A CN 2005800204559A CN 200580020455 A CN200580020455 A CN 200580020455A CN 1981099 B CN1981099 B CN 1981099B
Authority
CN
China
Prior art keywords
crack
cracks
substance
controlling
bonding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2005800204559A
Other languages
Chinese (zh)
Other versions
CN1981099A (en
Inventor
克里斯托弗·约翰·福瑟吉尔·库克
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of CN1981099A publication Critical patent/CN1981099A/en
Application granted granted Critical
Publication of CN1981099B publication Critical patent/CN1981099B/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/08Packing of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/10Packing of plastic or elastic materials, e.g. wood, resin
    • E01C11/106Joints with only prefabricated packing; Packings therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Building Environments (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Finishing Walls (AREA)

Abstract

Embodiments of the invention relate to an apparatus (1) for controlling cracks in a cementitious material, such as a concrete body, having an elongate base portion (2), elongate side wall portions (3) and (4) extending from the base portion and inclined to one another, and apertures in the side wall portions. When a means for controlling cracking is used, it may be positioned bottom down so that a cementitious substance susceptible to cracking can be poured around and at least partially through it so that cracks formed in the cementitious substance occur at or near the means for controlling cracking.

Description

Crackle control in the binding material
Technical field
The present invention relates to control the device of crackle in the binding material, for example in concrete.
Background technology
Under the situation of concrete construction, when it solidified, concrete main body crackle was general.At this crackle normally inevitably simultaneously, when processing a large amount of concrete, from the viewpoint of building, hope can be controlled the position of crackle.Therefore, the purpose of at least one embodiment of the present invention is to have at least the crackle that benefits in the control concrete, or offers the useful selection of the public at least.
Be appreciated that and if ought use term here about direction, when for example " making progress " etc., will be understood that it is with reference to the object correlation when service orientation usually, except as otherwise noted.
Be appreciated that also term " comprises " and derivative, for example " include " etc., should be interpreted as the meaning of " contain or comprise "---promptly not to be used for restriction.
Summary of the invention
According to an aspect of the present invention, the device of control bonding material main body internal fissure is provided, the device of this control crackle comprises elongated bottom, the elongate side wall part of extending and tilting mutually from the bottom, with the hole in the sidewall sections, the device of this control crackle constitutes like this, when it uses, it can be provided with downwards the bottom, be poured in around it so that be prone to the adhesive mass-energy of crackle, and pass it at least in part, so that subsequently near the inner crackle that forms of bonding material occurs in the device place of control crackle or its.
Preferably, this bonding material comprises concrete.
Preferably, this sidewall sections is with the common triangle that forms when cross section is watched of the part of therebetween bottom.
Preferably, an extension is arranged, its summit from this triangle extends upward.
Preferably, the device of control bonding material main body internal fissure combines with joint, makes up with the device with a plurality of described control crackles.
According to a further aspect of the invention, the device of control bonding material main body internal fissure is provided, this device has elongated bottom, the upwardly extending elongated wall part from the bottom, so that the bottom becomes inverted T-shape substantially with wall part, with the one or more holes in the wall part, the device of control crackle constitutes like this, when it uses, it can be provided with downwards the bottom, be poured in around it so that be prone to the adhesive mass-energy of crackle, and pass it at least in part, so that subsequently near the inner crackle that forms of bonding material occurs in the device place of control crackle or its.
Preferably, this bonding material comprises concrete.
Preferably, these one or more holes constitute this wall or wall part about 50% or more, decide as the case may be.
According to a further aspect in the invention, the device of control bonding material main body internal fissure is provided, this device comprises the part of two elongated basic one-tenth V-types, the elongated wall part, this elongated wall part internally extends and extends to the summit of another V-type part from the summit of a V-type part, with the one or more holes in this wall part, the device of control crackle so constitutes, when it uses, it can be arranged to make the adhesive mass-energy that is prone to crackle to be poured in around it, and pass this one or more holes at least in part, so that subsequently near the inner crackle that forms of bonding material occurs in the device place of control crackle or its.
Preferably, the summit of these two V-type parts is towards essentially identical direction.
Alternatively, the summit of this V-type part is towards opposite substantially direction.
Alternatively, a V-type part is basically greater than another V-type part.
Preferably, these one or more holes at least this wall part of basic comprising superficial area 50%.
According to a further aspect in the invention, the device of control bonding material main body internal fissure is provided, this device comprises elongated bottom and the extended elongated wall part from this bottom, so that bottom and wall part basically form the right angle, with the one or more holes in the wall part, this hole at least the basic comprising wall part 50%, the device of control crackle constitutes like this, when it uses, it can be placed to the adhesive mass-energy that easy crackle occurs is poured in around it, and pass one or more holes at least in part, so that subsequently near the inner crackle that forms of bonding material occurs in the device place of control crackle or its.
According to a further aspect in the invention, provide a kind of method, control the crackle in the bonding material that is prone to crackle, may further comprise the steps:
I) obtain the device of any described control crackle of aspect as described above, place it in crackle forms in the bonding material of expection position or near the position it then;
A large amount of bonding materials ii) is set so that it extends around wall or wall part and passes wall or wall part to small part, decide as the case may be and
Crackle is formed in bonding material near the control device place of crackle or its.
Preferably, this bonding material comprises concrete.
According to a further aspect in the invention, provide a kind of method, control the crackle in the bonding material that is prone to crackle, may further comprise the steps:
I) obtain the crackle controller, wherein the crackle controller comprises bottom, extended one or more walls from the bottom, one or more holes in one or more walls, and crackle controller layout is on the throne, in this position, in the position that the crackle in bonding material of expection forms
A large amount of bonding materials ii) are set so that its extend around described one or more walls and pass at least in part one or more walls and
Crackle is formed in bonding material near crackle controller place or its.
Preferably, one or more holes constitute at least one or more walls superficial area 50%.
Description of drawings
Optimal ways more of the present invention will utilize example now and reference will be made to the accompanying drawings, wherein:
Fig. 1 is the cross-sectional view of concrete cracks controller,
Fig. 2 is the lateral view of the crackle controller of Fig. 1,
Fig. 3 is the plan view of the crackle controller among Fig. 1 and Fig. 2,
Fig. 4 is the stereogram of another kind of concrete cracks controller,
Fig. 5 is the end view of the crackle controller of Fig. 4,
Fig. 6 is the cross-sectional view of straight line connector,
Fig. 7 and 8 is respectively the lateral view and the plan view of four-way connector,
Fig. 9 and 10 is respectively the lateral view and the plan view of three-way connector,
Figure 11 and 12 be respectively the lateral view of two-way angle connector and plan view and
Figure 13 and 14 is respectively the lateral view and the plan view of threeway t connector,
Figure 15 to 18 is the stereogram and the end view of another kind of concrete cracks controller.
Specific embodiment
Referring to Fig. 1,2 and 3, concrete cracks controller 1 is an elongate articles, and it has bottom 2, and this bottom has from the bottom obliquely crossing two elongate side wall 3 and 4.Therefore, controller 1 is a hollow, and cross section is generally triangle.Shown in Fig. 2 and 3, sidewall 3 and 4 has the elongated hole 5 at a plurality of intervals.As can be seen, extend a little in each side of wall 3 and 4 bottom 2, and the summit of wall has vertical extension 6.
When controller 1 in use, it can be placed downwards bottom 2, then with a large amount of concrete spoutings around it.The basic at least overlay controller 1 of concrete, and by hole 5, pass therethrough.If desired, also the reinforcing bar (not shown) can be passed hole 5.When concrete setting, it is easily at controller 1 place or occur crackle in its vicinity.Because the concrete main body of controller both sides has basically than controller and/or passes the fact of the bigger quality of concrete part of controller, helps this controlled crackle.
Figure 4 and 5 have shown another kind of concrete cracks controller 7, and it has bottom 8 and upwardly extending wall 9.The bottom becomes inverted T-shape substantially with wall.As shown, controller 7 has the elongated hole 10 at a plurality of intervals.Described selectable crackle controller 7 is used to control concrete cracks in the mode very identical with above-mentioned controller, is about to bottom 8 and places down, then concrete perfusion and run through controller around.Also reinforcing bar can be passed hole 10.The crackle that forms in the concrete easily occurs near controller 7 places or its, because it forms one or more weakening region in concrete.
Preferably, if desired, controller 1 and 7 respectively is provided with aperture in its bottom 2 or 8, so that it can be fixed in basal plane.Preferably, if necessary, these bottoms 2 and 8 are flat substantially, so that controller 1 and 7 can easier maintenance level.
Under the situation of the controller of mentioning at first 1, by wall 3 and 4 and the triangle that forms of the bottom of bottom 2 measure of intensity and stability is provided, for example stop the transverse movement of undesirable wall.
Controller 1 and 7 can be made by any suitable material, for example by steel, and plastics, or common resinous material is made.
When controller 1 and 7 in use, in some cases, wish it is connected to other such controller 1 and 7.In order to reach this purpose, it can use with suitable straight line, angle or T-shape joint as required.Figure 6 shows that straight line connector 11, it can be used for connecting two controllers of mentioning at first 1.More particularly, two crackle controllers 1 can be installed on the connector 11 as sleeve pipe, and each controller is installed in the opposite end of connector 11.Connector 11 can be established flange 12 at its each end, so that length restriction can be installed within the crackle controller 1 for it.
Fig. 7 and 8, Fig. 9 and 10, Figure 11 and 12, and Figure 13 and 14 shown the connector that other are different, it can use with reference Fig. 1,2 and 3 described crackle controllers 1.Under each situation, crackle controller 1 is installed on the connector as sleeve pipe.Preferably, each in these connectors all has one or more holes, so that concrete or similar item can enter the inside and/or pass them.
Alternatively, above-mentioned crackle controller 1 and 7 and various connector form by the steel or the plastics of 2.0-3.5mm (or preferably by 2.5-3.0mm) specification.The specification that can select material therefor is to be fit to the size at required shrinkage joint.
Preferably, the hole 5 and 10 in the crackle controller account for greatly sidewall 50% or more, and more preferably account for its 52%.
Be appreciated that at least some embodiment of the present invention can make it form controllable shrinkage joint in concrete main body or similar item.The shrinkage joint can be under concrete surface corresponding to the position of crackle controller.
Figure 15,16,17 and 18 have shown according to the present invention the crackle controller 13,14,15 and 16 of optional embodiment.Each figure has shown each crackle controller 13,14,15 or 16 with end view and stereogram.Each crackle controller 13-16 is applicable to various application, for example is used for the turning of concrete panel, with the crackle of controlling the there or the crackle that is controlled at the place, floor.Concrete can utilize gunite or any other suitable manner to be applied to controller 13-16.
As Figure 15, shown in 16 and 18, controller 13,14 and 16 respectively has two V-type end parts and intermediate connecting wall part.Wall part is provided with the hole, so that concrete or some other binding materials can pass therethrough.Under the situation of controller 13 and 14, the summit of two V-type end parts is pointed to same direction and is connected in its wall part on its summit, as the case may be, and in the inside or outside connection the on summit.In the situation of controller 16, the summit of two V-types part point to mutually away from direction, and interconnect by its wall part in the inside on this summit.Controller 15 as shown in figure 17 is right angle forms, and the one side at angle is as the bottom, and another side is as the wall part that wherein has the hole.Preferably, for all controller 13-16, in all cases, its hole at least the basic comprising wall part superficial area 50%.
When utilizing example to describe preferred forms more of the present invention, should be appreciated that and under the situation that does not break away from the accessory claim scope, can make amendment or improve.

Claims (18)

1.一种控制粘结物质主体内裂纹的装置,所述控制裂纹的装置包括细长底部、从底部延伸出并相互倾斜的细长侧壁部分和所述侧壁部分中的一个或多个孔,所述控制裂纹的装置这样构成,当其使用时,其可底部向下设置,以使易出现裂纹的粘结物质能灌注在其周围,并且自由地穿过它,即穿过一个或多个孔,以使随后在粘结物质内部形成的裂纹发生在所述控制裂纹的装置处或其附近。1. A means for controlling cracks in a body of bonding substance, said means for controlling cracks comprising an elongated base, an elongated side wall portion extending from the base and inclined towards one another, and one or more of said side wall portions The hole, said means for controlling cracks, is constructed so that when it is in use, it can be placed with the bottom down, so that the bonding substance prone to cracks can be poured around it and freely pass through it, that is, through one or A plurality of holes, so that subsequent formation of cracks within the bonding substance occurs at or near said crack control means. 2.根据权利要求1的控制粘结物质主体内裂纹的装置,其中,所述粘结物质包括混凝土。2. The device for controlling cracks in a body of cementitious substance according to claim 1, wherein said cementitious substance comprises concrete. 3.根据权利要求1或2的控制粘结物质主体内裂纹的装置,其中,所述侧壁部分与其间的底部的一部分共同形成从横截面观看时的三角形状。3. The device for controlling cracks in a body of bonding substance according to claim 1 or 2, wherein said side wall portions together with a portion of the base therebetween form a triangular shape when viewed in cross section. 4.根据权利要求3的控制粘结物质主体内裂纹的装置,其中,设有一延伸部,其从所述三角形状的顶点向上延伸。4. The device for controlling cracks in a body of bonding substance according to claim 3, wherein there is an extension extending upwardly from the apex of said triangular shape. 5.根据权利要求1的控制粘结物质主体内裂纹的装置,其与接头结合,以组合多个所述控制裂纹的装置。5. The device for controlling cracks in a body of bonding substance according to claim 1, which is combined with a joint to combine a plurality of said devices for controlling cracks. 6.一种控制粘结物质主体内裂纹的装置,所述装置包括:细长底部;从底部向上延伸的细长壁部分,以使所述底部和所述壁部分基本成倒置的“T”型;和所述壁部分中的一个或多个孔,所述控制裂纹的装置这样构成,当其使用时,其可底部向下设置,以使易出现裂纹的粘结物质能灌注在其周围,并且自由地穿过它,即穿过一个或多个孔,以使随后在粘结物质内部形成的裂纹发生在所述控制裂纹的装置处或其附近。6. A device for controlling cracks in a body of bonding substance, said device comprising: an elongated base; an elongated wall portion extending upwardly from the base such that said base and said wall portion form a substantially inverted "T" type; and one or more holes in said wall portion, said crack control means being constructed so that, when in use, it can be set bottom down so that a bonding substance prone to cracks can be poured around it , and freely pass through it, ie through one or more holes, so that the subsequent formation of cracks inside the bonding substance occurs at or near said crack-controlling means. 7.根据权利要求6的控制粘结物质主体内裂纹的装置,其中,所述粘结物质包括混凝土。7. The device for controlling cracks in a body of cementitious substance according to claim 6, wherein said cementitious substance comprises concrete. 8.根据权利要求1的控制粘结物质主体内裂纹的装置,其中,听述一个或多个孔构成所述壁或壁部分的50%或更多,根据具体情况而定。8. The device for controlling cracks in a body of cementitious substance according to claim 1, wherein said one or more pores constitute 50% or more of said wall or wall portion, as the case may be. 9.一种控制粘结物质主体内裂纹的装置,所述装置包括两个细长的基本成,V型的部分、细长壁部分和所述壁部分中的一个或多个孔,所述细长壁部分从一个V型部分的顶点内部延伸出并延伸到另一个V型部分的顶点,所述控制裂纹的装置这样构成,当其使用时i其可以设置成使易出现裂纹的粘结物质能灌注在其周围,并至少部分地穿过所述一个或多个孔,以使随后在粘结物质内部形成的裂纹发生在所述控制裂纹的装置处或其附近。9. A device for controlling cracks in a body of bonding substance, said device comprising two elongated, substantially V-shaped sections, an elongated wall section and one or more holes in said wall section, said The elongated wall portion extends from the inside of the apex of one V-shaped portion and extends to the apex of the other V-shaped portion, said crack control means being constructed so that when it is in use it can be arranged so that crack-prone bonds A substance can be impregnated therearound and at least partially through said one or more apertures so that subsequent formation of cracks within the bonded substance occurs at or near said crack control means. 10.根据权利要求9的控制裂纹的装置,其中,两个V型部分的顶点指向基本相同的方向。10. The crack control device of claim 9, wherein the vertices of the two V-shaped portions point in substantially the same direction. 11.根据权利要求9的控制裂纹的装置,其中,V型部分的顶点指向基本相反的方向。11. The crack control device of claim 9, wherein the vertices of the V-shaped portions point in substantially opposite directions. 12.根据权利要求9、10或11的控制裂纹的装置,其中,一个V型部分基本上大于另一个V型部分。12. A crack control device according to claim 9, 10 or 11, wherein one V-shaped portion is substantially larger than the other V-shaped portion. 13.根据权利要求9的控制裂纹的装置,其中,所述一个或多个孔至少构成所述壁部分表面积的50%。13. The crack control device of claim 9, wherein said one or more holes constitute at least 50% of the surface area of said wall portion. 14.一种控制粘结物质主体内裂纹的装置,所述装置包括细长底部和从所述底部延伸出的细长壁部分,以使所述底部和壁部分形成直角,所述装置还包括所述壁部分中的一个或多个孔,所述孔至少构成所述壁部分的50%,控制裂纹的装置这样构成,当其使用时,其可以设置成使易出现裂纹的粘结物质能灌注在其周围,并至少部分地穿过一个或多个孔,以使随后在粘结物质内部形成的裂纹发生在所述控制裂纹的装置处或其附近。14. A device for controlling cracks in a body of bonding substance, said device comprising an elongated base and an elongated wall portion extending from said base such that said base and wall portion form a right angle, said device further comprising One or more holes in said wall portion, said holes constituting at least 50% of said wall portion, the means for controlling cracking is constructed so that, when used, it can be arranged so that a bonding substance prone to cracking can Pouring around it and at least partially through the hole or holes so that subsequent crack formation within the bonding mass occurs at or near said crack control means. 15.一种控制易出现裂纹的粘结物质中的裂纹的方法,包括以下步骤:15. A method of controlling cracks in a crack-prone bonding substance comprising the steps of: i)获得如前面任一项权利要求中所述的控制裂纹的装置,然后将其设置在预期的粘结物质中裂纹形成的位置或邻近所述位置;i) obtaining a crack control device as claimed in any one of the preceding claims, which is then placed at or adjacent to the location of expected crack formation in the bonding substance; ii)设置大量的粘结物质,以使其在所述壁或壁部分周围延伸并穿过所述壁或壁部分,根据具体情况而定,和ii) providing a mass of bonding substance so as to extend around and through said wall or wall portion, as the case may be, and iii)使裂纹在粘结物质内形成在控制裂纹的装置处或其附近。iii) causing cracks to form within the bonding substance at or near the crack-controlling means. 16.根据权利要求15的方法,其中,所述粘结物质包括混凝土。16. The method of claim 15, wherein the cementitious substance comprises concrete. 17.一种控制易出现裂纹的粘结物质中的裂纹的方法,包括以下步骤:17. A method of controlling cracks in a crack-prone bonding substance comprising the steps of: i)获得裂纹控制器,其中所述裂纹控制器包括底部、从底部延伸的一个或多个壁和所述一个或多个壁中的一个或多个孔,并将所述裂纹控制器设置在预期的粘结物质中裂纹形成的位置,i) Obtaining a crack controller, wherein the crack controller comprises a base, one or more walls extending from the base, and one or more holes in the one or more walls, and placing the crack controller in The expected location of crack formation in the bonded substance, ii)设置大量粘结物质,以使其在所述一个或多个壁周围延伸并自由地穿过所述一个或多个壁,和ii) providing a plurality of bonding substances such that they extend around said one or more walls and pass freely through said one or more walls, and iii)使裂纹在粘结物质内形成在裂纹控制器处或其附近。iii) causing a crack to form within the bonding substance at or near the crack controller. 18.根据权利要求17的方法,其中,所述一个或多个孔至少构成所述一个或多个壁的表面面积的50%。18. The method of claim 17, wherein the one or more pores constitute at least 50% of the surface area of the one or more walls.
CN2005800204559A 2004-06-25 2005-06-10 Crack control in cementitious materials Expired - Fee Related CN1981099B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
NZ533777 2004-06-25
NZ533777A NZ533777A (en) 2004-06-25 2004-06-25 Controlling cracks in cementitious materials
PCT/NZ2005/000125 WO2006001713A1 (en) 2004-06-25 2005-06-10 Controlling cracks in cementitious materials

Publications (2)

Publication Number Publication Date
CN1981099A CN1981099A (en) 2007-06-13
CN1981099B true CN1981099B (en) 2010-09-29

Family

ID=32986088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2005800204559A Expired - Fee Related CN1981099B (en) 2004-06-25 2005-06-10 Crack control in cementitious materials

Country Status (10)

Country Link
US (1) US20080022622A1 (en)
EP (1) EP1759070A1 (en)
JP (1) JP2008503672A (en)
KR (1) KR20070028562A (en)
CN (1) CN1981099B (en)
AU (1) AU2005257680B2 (en)
CA (1) CA2573502A1 (en)
GB (1) GB2429721B (en)
NZ (1) NZ533777A (en)
WO (1) WO2006001713A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1786989A4 (en) * 2004-08-13 2014-03-26 Timothy Charles O'brien Concrete expansion joint forming device
CN102071615B (en) * 2010-12-21 2012-12-26 东南大学 Method for controlling crack spacing of continuously reinforced cement concrete pavement
EE05873B1 (en) * 2019-04-05 2024-09-16 Primostar Tootmine Oü Cracking agent for concrete structures

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1071986A (en) * 1991-08-13 1993-05-12 三菱重工业株式会社 A kind of concrete-filled steel bearing wall and manufacture method thereof
CN1156490A (en) * 1994-06-28 1997-08-06 拉斯科特种结构有限公司 Seam guide for prescribed cracks
US5743065A (en) * 1995-10-13 1998-04-28 Dolese Brothers Co. Method for reducing stress cracks at re-entrant corners of a concrete slab

Family Cites Families (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1233508A (en) * 1913-05-07 1917-07-17 August C Rogalske Concrete construction.
US2167904A (en) * 1936-05-18 1939-08-01 Older Clifford Concrete expansion and contraction joint
US2321813A (en) * 1942-07-01 1943-06-15 John H Henzel Refractory panel construction
US2748591A (en) * 1952-07-22 1956-06-05 Arthur H Brown Wall panels
US2961803A (en) * 1957-03-21 1960-11-29 Kenneth E Shapiro Contraction joint and seal for concrete structures
FR1328489A (en) * 1962-04-19 1963-05-31 Clip and ceiling able to withstand expansion due to heating
US3596421A (en) * 1969-01-21 1971-08-03 Elkhart Bridge & Iron Co Structural beam for supporting concrete flooring
US4132043A (en) * 1977-02-22 1979-01-02 H. B. Fuller Company Structural units
US5033248A (en) * 1990-01-05 1991-07-23 Phillips Charles N Reinforced concrete building and method of construction
SE468097B (en) * 1991-03-13 1992-11-02 Combiform Ab AID ELEMENT FOR USE IN CONCRETE FLOORING
FI92089C (en) * 1993-01-13 1994-09-26 Deltatek Oy Prefabricated steel-concrete composite beam
JP3398188B2 (en) * 1993-08-09 2003-04-21 株式会社フジタ Crack-inducing joint device for reinforced concrete wall-like structures.
JP2513580B2 (en) * 1993-11-05 1996-07-03 株式会社ピー・エス Construction method of crack inducing part in continuous concrete pavement
JPH07224535A (en) * 1994-02-14 1995-08-22 Mitsui Constr Co Ltd Concrete crack prevention method
US5918428A (en) * 1997-02-19 1999-07-06 Engineered Devices Corporation Crack inducer plate for concrete
KR200152480Y1 (en) * 1997-02-28 1999-07-15 조세훈 Deck Panel of Reinforced Concrete Slab
US5857302A (en) * 1997-04-02 1999-01-12 Lill; Deryl L. Concrete crack control system
JPH1161978A (en) * 1997-08-13 1999-03-05 Hayakawa Rubber Co Ltd Concrete structure and manufacture thereof
JP2000248743A (en) * 1999-03-03 2000-09-12 Shimizu Corp Mass concrete casting method
JP3775185B2 (en) * 1999-09-02 2006-05-17 株式会社大林組 Crack control structure in concrete members.
ATE386844T1 (en) * 2000-08-04 2008-03-15 Building Innovations Pty Ltd METHOD AND SYSTEM FOR PRODUCING LARGE CONTINUOUS CONCRETE PANELS
US20040025858A1 (en) * 2002-07-30 2004-02-12 Barenberg Ernest J. Crack/joint inducers for portland cement concrete pavement and slabs
CA2404535A1 (en) * 2002-09-20 2004-03-20 Canam Manac Group Inc. Composite floor system
ES1053970Y (en) * 2003-02-12 2003-09-16 Oliveras Valenti Centellas EXPANSION BOARD FOR CONCRETE WORKS.
EP1763612B1 (en) * 2004-07-05 2013-11-13 Concrete Slab Technology Pty Ltd Method and apparatus for forming cracks in concrete

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1071986A (en) * 1991-08-13 1993-05-12 三菱重工业株式会社 A kind of concrete-filled steel bearing wall and manufacture method thereof
CN1156490A (en) * 1994-06-28 1997-08-06 拉斯科特种结构有限公司 Seam guide for prescribed cracks
US5743065A (en) * 1995-10-13 1998-04-28 Dolese Brothers Co. Method for reducing stress cracks at re-entrant corners of a concrete slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP平7-127008 1995.05.16

Also Published As

Publication number Publication date
JP2008503672A (en) 2008-02-07
AU2005257680A1 (en) 2006-01-05
GB2429721A (en) 2007-03-07
EP1759070A1 (en) 2007-03-07
US20080022622A1 (en) 2008-01-31
GB0700389D0 (en) 2007-02-14
GB2429721B (en) 2009-07-22
CN1981099A (en) 2007-06-13
CA2573502A1 (en) 2006-01-05
AU2005257680B2 (en) 2008-12-11
NZ533777A (en) 2004-09-24
WO2006001713A1 (en) 2006-01-05
KR20070028562A (en) 2007-03-12

Similar Documents

Publication Publication Date Title
CN107100290A (en) A kind of prefabricated shear wall and overlapping plate node
CN103541305B (en) A kind of construction method of the hollow slab bridge structure with integration pave-load layer
CN105756088A (en) Combined prefabricated assembled multi-cabin comprehensive pipe rack
CN1981099B (en) Crack control in cementitious materials
KR101460559B1 (en) Structure and Method for Connecting between Precast Column and In-situ Concrete Slab
KR20170060769A (en) Multi-layer construction structure of the structure using double-wall PC and construction method thereof
CN107130634A (en) A kind of noncontact attachment structure of the prefabricated piping lane of split-type
CN205421646U (en) Floor structures
CN206554283U (en) Prefabricated board connecting structure
CN206693474U (en) A kind of insulation Sloping roof structure of double-deck prefabricated board Cast-in-situ Beam
KR20080104534A (en) Formwork support beam
CN205296521U (en) Superimposed sheet of piece concatenation is made by C shape steel sheet
CN209482822U (en) Concrete prefabricated fence
JP3996110B2 (en) Manufacturing method of precast concrete board.
CN204001445U (en) A kind of reinforcement bar support support member
CN205857523U (en) A kind of composite flat beam
CN203530845U (en) Hollow slab bridge structure with integration pavement layer
KR20100089644A (en) A connection member for system support
JP4298435B2 (en) Embedding material, embedding material unit, and piping arrangement method
CN2592749Y (en) Light wallboard withou mounting crack
EP1795666A1 (en) Beam element, building system and method
TWI245093B (en) A shaping device and construction method of an opening presetting in concrete floor
JPH03140720A (en) Heat accumulation board with floor and wallpanelframes and its manufacture as well as board frame
KR101229397B1 (en) Fill opening slab that use connection reinforcing rod and mold structure
CN100560904C (en) A reinforced concrete lightweight board

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100929

Termination date: 20150610

EXPY Termination of patent right or utility model