CN112681359A - Method for pile pulling construction in collapsible loess area - Google Patents

Method for pile pulling construction in collapsible loess area Download PDF

Info

Publication number
CN112681359A
CN112681359A CN202011486901.8A CN202011486901A CN112681359A CN 112681359 A CN112681359 A CN 112681359A CN 202011486901 A CN202011486901 A CN 202011486901A CN 112681359 A CN112681359 A CN 112681359A
Authority
CN
China
Prior art keywords
pile
soil
soaking
sampling
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011486901.8A
Other languages
Chinese (zh)
Inventor
张峰
王立博
高鹏
何坤
辛小宇
李潇
常迪
许超
何楠
朱斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SCEGC No 6 Construction Engineering Group Co Ltd
Original Assignee
SCEGC No 6 Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SCEGC No 6 Construction Engineering Group Co Ltd filed Critical SCEGC No 6 Construction Engineering Group Co Ltd
Priority to CN202011486901.8A priority Critical patent/CN112681359A/en
Publication of CN112681359A publication Critical patent/CN112681359A/en
Pending legal-status Critical Current

Links

Landscapes

  • Sampling And Sample Adjustment (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a method for pile pulling construction in a collapsible loess area, which comprises the following steps: s1, sampling: utilizing a soil sampler to define a designated area, and cutting and sampling soil on the collapsible yellow land to be treated; s2, testing the soil sample: placing the cut soil sample in a designated container, adding water for soaking, and knowing the soaking water amount and the settlement condition of the soil; s3, field sampling test: sampling, adding water and soaking in the pretreated area, knowing the soaking amount of the central area and the settlement condition of the soil, and judging the error rate of the test; s4, punching and adding water: then, punching holes around an area needing pile pulling, arranging the punching holes according to actual needs, and adding water for soaking; s5, selecting: and (4) according to the water immersion amount of the soil test and the field sampling test and the settlement condition of the soil. The method for pile pulling construction in the collapsible loess area not only can ensure the accuracy of pile pulling selection, but also can reduce the burden of pile pulling.

Description

Method for pile pulling construction in collapsible loess area
Technical Field
The invention belongs to the technical field of pile pulling construction, and particularly relates to a method for pile pulling construction in a collapsible loess area.
Background
The collapsible loess refers to soil which undergoes significant additional deformation due to structural damage of soil after being soaked under the action of self-weight stress of an overlying soil layer or under the combined action of the self-weight stress and additional stress, and belongs to special soil. Some miscellaneous fill also has a collapsible nature. Loess widely distributed in northeast, northwest, China and east China has a plurality of collapsibility. (the loess as used herein refers to loess and loess-like soil, collapsible loess is classified into self-weight collapsible loess and non-self-weight collapsible loess, and some old loess does not have collapsibility).
In collapsible loess areas, pile pulling is difficult because special processing equipment is used for pretreatment during pile driving.
Therefore, in view of the current situation, it is urgently needed to design and produce a method for pile pulling construction in collapsible loess areas so as to meet the requirements of practical use.
Disclosure of Invention
The invention aims to provide a method for pile pulling construction in a collapsible loess area, which aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a method for pile pulling construction in collapsible loess areas comprises the following steps:
s1, sampling: utilizing a soil sampler to define a designated area, and cutting and sampling soil on the collapsible yellow land to be treated;
s2, testing the soil sample: placing the cut soil sample in a designated container, adding water for soaking, and knowing the soaking water amount and the settlement condition of the soil;
s3, field sampling test: sampling, adding water and soaking in the pretreated area, knowing the soaking amount of the central area and the settlement condition of the soil, and judging the error rate of the test;
s4, punching and adding water: then, punching holes around an area needing pile pulling, arranging the punching holes according to actual needs, and adding water for soaking;
s5, selecting: selecting a proper pile extractor according to the water immersion amount of the soil test and the field sampling test and the settlement condition of the soil;
s6, pile pulling: clearing the above-ground obstacles, marking underground structures and pipelines within the range of a treatment site, keeping the site smooth, and pulling out ground piles;
s7, after material feeding: and after the ground pile is pulled out, transporting the ground pile out of the field by using equipment.
Preferably, the soil sampler adopts large soil sampling equipment to ensure the accuracy of the subsequent soaking dosage.
Preferably, in the pile pulling process, a plurality of groups of high-pressure water spraying devices are installed on the periphery of the pile pulling machine, and the pulled ground pile is sprayed with water by the aid of the plurality of groups of high-pressure water spraying devices to remove the adhered soil on the periphery of the ground pile.
Preferably, the lower half part of the ground pile is further provided with a filtering and recycling device for recycling the sprayed water.
Preferably, in the pile pulling process, the ground pile is excited by the aid of the vibrator to vibrate soil on the periphery of the ground pile.
Preferably, the vibrator adopts an eccentric moment adjustable hydraulic vibration pile hammer.
Preferably, the pile extractor adopts a pressure holding type pile clamping device.
Preferably, the earth pits present after the post-loading process are filled and leveled.
The invention has the technical effects and advantages that: according to the method for pile pulling construction in the collapsible loess area, after sampling, soaking and understanding treatment are carried out on soil, the pile pulling burden is reduced, the model and the power of a pile pulling machine to be used can be known, and the accuracy of selection is guaranteed; the high-pressure water spraying and soil vibrating can greatly remove the soil on the periphery of the ground pile, and reduce the workload of the pile extractor; the method for pile pulling construction in the collapsible loess area not only can ensure the accuracy of pile pulling selection, but also can reduce the burden of pile pulling.
Detailed Description
The technical solutions in the present disclosure will be clearly and completely described below with reference to the present disclosure, and it is obvious that the described contents are only a part of the present disclosure, and not all of the present disclosure. All other matters which can be obtained by a person skilled in the art without making creative efforts based on the contents of the present invention belong to the protection scope of the present invention.
The invention provides a method for pile pulling construction in a collapsible loess area, which comprises the following steps:
s1, sampling: utilizing a soil sampler to define a designated area, and cutting and sampling soil on the collapsible yellow land to be treated;
s2, testing the soil sample: placing the cut soil sample in a designated container, adding water for soaking, and knowing the soaking water amount and the settlement condition of the soil;
s3, field sampling test: sampling, adding water and soaking in the pretreated area, knowing the soaking amount of the central area and the settlement condition of the soil, and judging the error rate of the test;
s4, punching and adding water: then, punching holes around an area needing pile pulling, arranging the punching holes according to actual needs, and adding water for soaking;
s5, selecting: selecting a proper pile extractor according to the water immersion amount of the soil test and the field sampling test and the settlement condition of the soil;
s6, pile pulling: clearing the above-ground obstacles, marking underground structures and pipelines within the range of a treatment site, keeping the site smooth, and pulling out ground piles;
s7, after material feeding: and after the ground pile is pulled out, transporting the ground pile out of the field by using equipment.
Specifically, the soil sampler adopts large soil sampling equipment to ensure the accuracy of the subsequent soaking dosage.
Specifically, in the pile pulling process, a plurality of groups of high-pressure water spraying devices are installed on the periphery of the pile pulling machine, and the pulled ground piles are sprayed with water by the aid of the plurality of groups of high-pressure water spraying devices to remove the adhered soil on the periphery of the ground piles.
Specifically, the lower half part of the ground pile is also provided with a filtering and recycling device for recycling the sprayed water liquid.
Specifically, in the pile pulling process, the ground pile is excited by the aid of the vibrator to vibrate soil on the periphery of the ground pile.
Specifically, the vibrator adopts an eccentric moment adjustable hydraulic vibration pile hammer.
Specifically, the pile extractor adopts an embracing type pile clamping device.
Specifically, the existing soil pit is filled and leveled after the process of material preparation.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing description, it will be apparent to one skilled in the art that various changes, modifications, equivalents, and improvements may be made without departing from the spirit and scope of the invention.

Claims (8)

1. A method for pile pulling construction in a collapsible loess area is characterized by comprising the following steps:
s1, sampling: utilizing a soil sampler to define a designated area, and cutting and sampling soil on the collapsible yellow land to be treated;
s2, testing the soil sample: placing the cut soil sample in a designated container, adding water for soaking, and knowing the soaking water amount and the settlement condition of the soil;
s3, field sampling test: sampling, adding water and soaking in the pretreated area, knowing the soaking amount of the central area and the settlement condition of the soil, and judging the error rate of the test;
s4, punching and adding water: then, punching holes around an area needing pile pulling, arranging the punching holes according to actual needs, and adding water for soaking;
s5, selecting: selecting a proper pile extractor according to the water immersion amount of the soil test and the field sampling test and the settlement condition of the soil;
s6, pile pulling: clearing the above-ground obstacles, marking underground structures and pipelines within the range of a treatment site, keeping the site smooth, and pulling out ground piles;
s7, after material feeding: and after the ground pile is pulled out, transporting the ground pile out of the field by using equipment.
2. The method for pile extraction in collapsible loess areas according to claim 1, wherein: the soil sampler adopts large soil sampling equipment to ensure the accuracy of the subsequent soaking dosage.
3. The method for pile extraction in collapsible loess areas according to claim 1, wherein: in the pile pulling process, a plurality of groups of high-pressure water spraying devices are installed on the periphery of the pile pulling machine, and the pulled ground piles are sprayed with water by the aid of the plurality of groups of high-pressure water spraying devices to remove the adhered soil on the periphery of the ground piles.
4. The method for pile extraction in collapsible loess areas according to claim 3, wherein: the lower half part of the ground pile is also provided with a filtering and recycling device for recycling the sprayed water liquid.
5. The method for pile extraction in collapsible loess areas according to claim 1, wherein: in the pile pulling process, the vibrator is used for exciting the ground pile so as to vibrate the soil on the periphery of the ground pile.
6. The method for pile extraction in collapsible loess areas according to claim 5, wherein: the vibrator adopts an eccentric moment adjustable hydraulic vibration pile hammer.
7. The method for pile extraction in collapsible loess areas according to claim 1, wherein: the pile extractor adopts a holding and pressing type pile clamping device.
8. The method for pile extraction in collapsible loess areas according to claim 1, wherein: and filling and leveling the soil pit after the material-loading process.
CN202011486901.8A 2020-12-16 2020-12-16 Method for pile pulling construction in collapsible loess area Pending CN112681359A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011486901.8A CN112681359A (en) 2020-12-16 2020-12-16 Method for pile pulling construction in collapsible loess area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011486901.8A CN112681359A (en) 2020-12-16 2020-12-16 Method for pile pulling construction in collapsible loess area

Publications (1)

Publication Number Publication Date
CN112681359A true CN112681359A (en) 2021-04-20

Family

ID=75448306

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011486901.8A Pending CN112681359A (en) 2020-12-16 2020-12-16 Method for pile pulling construction in collapsible loess area

Country Status (1)

Country Link
CN (1) CN112681359A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030102165A1 (en) * 2001-12-03 2003-06-05 Frantz Anthony F. System and apparatus for excavating contaminated pilings
CN103233454A (en) * 2013-04-07 2013-08-07 西安理工大学 Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN103485344A (en) * 2013-09-17 2014-01-01 常熟理工学院 Method for extracting construction engineering pile foundation
CN104005406A (en) * 2014-01-29 2014-08-27 陈东曙 Tubular pile construction method and pile tube structure of tubular pile
CN104652436A (en) * 2014-12-24 2015-05-27 福建工程学院 Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method
CN204456112U (en) * 2015-02-04 2015-07-08 绥棱县宏运养鱼场 One scraps well well casing plucking device
KR101789492B1 (en) * 2017-01-23 2017-10-27 (주)대한하이텍건설 A System for Reinforcing Soft Ground and Restoring Depressed structures including Urethane and Construction Methods Using Thereof
CN110468843A (en) * 2019-07-15 2019-11-19 中国一冶集团有限公司 A kind of dynamic pile pulling power calculation method of tubular pole
CN111472356A (en) * 2020-04-14 2020-07-31 周力 Larsen steel sheet pile sleeve obstacle clearing and pile pulling construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030102165A1 (en) * 2001-12-03 2003-06-05 Frantz Anthony F. System and apparatus for excavating contaminated pilings
CN103233454A (en) * 2013-04-07 2013-08-07 西安理工大学 Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN103485344A (en) * 2013-09-17 2014-01-01 常熟理工学院 Method for extracting construction engineering pile foundation
CN104005406A (en) * 2014-01-29 2014-08-27 陈东曙 Tubular pile construction method and pile tube structure of tubular pile
CN104652436A (en) * 2014-12-24 2015-05-27 福建工程学院 Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method
CN204456112U (en) * 2015-02-04 2015-07-08 绥棱县宏运养鱼场 One scraps well well casing plucking device
KR101789492B1 (en) * 2017-01-23 2017-10-27 (주)대한하이텍건설 A System for Reinforcing Soft Ground and Restoring Depressed structures including Urethane and Construction Methods Using Thereof
CN110468843A (en) * 2019-07-15 2019-11-19 中国一冶集团有限公司 A kind of dynamic pile pulling power calculation method of tubular pole
CN111472356A (en) * 2020-04-14 2020-07-31 周力 Larsen steel sheet pile sleeve obstacle clearing and pile pulling construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
中国水利工程协会主编: "《岩土工程类 地基与基础》", 31 December 2008, 郑州:黄河水利出版社 *
于海峰主编: "《全国注册岩土工程师专业考试培训教材》", 31 July 2006, 武汉:华中科技大学出版社 *

Similar Documents

Publication Publication Date Title
CN103541359B (en) Method for repairing and treating quality defect of cast-in-place pile
CN110965473B (en) Construction method of bridge bearing platform
CN104790372B (en) Vibration-compressed air-vacuum combination foundation reinforcement system and method
CN106014429B (en) A kind of method of shield tunnel rectification of distortion correction
CN106759440A (en) Foundation of iron tower screw bolt reinforcing method
CN202492854U (en) Foundation platform structures of deepwater bare rock and karstic piles
CN106907157B (en) A kind of shield machine normal pressure opens the cabin operation construction method
CN103924572A (en) Embedding device and method for soil pressure gauges in deep silt soil layer
CN104947648A (en) Deep replacement dynamic compaction gravel pile foundation reinforcement method
CN208201855U (en) A kind of steel-pipe pile high-pressure water knife device for drawing hole construction
CN113174991A (en) Method for reinforcing collapse and grouting of stratum around marine deep-water inclined pile
CN100523389C (en) Ballastless track steel reinforced concrete pile-net construction method
CN112681359A (en) Method for pile pulling construction in collapsible loess area
CN113174992B (en) Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile
CN115644013A (en) Ancient tree full-crown transplanting system and transplanting method thereof
CN110409416A (en) A kind of processing method of collapsible soil or molten sunken property soil base
CN105002891B (en) A kind of cast-in-situ bored pile exempts from inter-pile soil excavation construction method
CN102505685A (en) Tubular pile defect processing method
CN211200425U (en) High side slope composite supporting construction that fills of gravel soil
CN109024531A (en) A kind of collapsible loess foundation construction treating methods
CN102797262B (en) The construction treating methods of cast-in-situ triangular compound foundation pile
CN102758434A (en) Pile-sinking device for centrally driving prestressed centrifugal pipe pile (square pile) and novel pile-sinking method thereof
CN105798052A (en) Moist curing method for accelerating subsidence and stability of coal gangue filling reclamation
CN206887984U (en) A kind of photovoltaic generation support steel bar concrete reinforcement steel pipe pile foundation
CN105220699B (en) Cofferdam construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210420