CN111884121A - Pre-buried wiring method for standardized pipeline of assembled laminated slab - Google Patents

Pre-buried wiring method for standardized pipeline of assembled laminated slab Download PDF

Info

Publication number
CN111884121A
CN111884121A CN202010755138.8A CN202010755138A CN111884121A CN 111884121 A CN111884121 A CN 111884121A CN 202010755138 A CN202010755138 A CN 202010755138A CN 111884121 A CN111884121 A CN 111884121A
Authority
CN
China
Prior art keywords
pipeline
pipelines
laminated board
embedded
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010755138.8A
Other languages
Chinese (zh)
Inventor
鲁川
张晓峰
刘春荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202010755138.8A priority Critical patent/CN111884121A/en
Publication of CN111884121A publication Critical patent/CN111884121A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/48Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/36Installations of cables or lines in walls, floors or ceilings
    • H02G3/38Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts
    • H02G3/381Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts in ceilings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Installation Of Indoor Wiring (AREA)

Abstract

本发明公开了一种装配式叠合板标准化管线预埋布线方法,涉及装配式建筑工程在生产及安装过程中的技术领域。本发明提供的装配式叠合板标准化管线预埋布线方法,避免在施工现场进行剔凿、切割时破坏预制构件,预留预埋点位综合图方便查漏补缺的同时也便于检查各个系统间的设备点位冲突情况,及时发现问题并解决问题;出具管线优化布置图后,施工现场相同户型的管线敷设方式相同,便于后期管线修复;对于重叠交叉区域进行单独设计,减小结构层厚度,不会由于管线过于集中而造成叠合板后期开裂,同时降低工程造价;混凝土浇筑完成后在布线区内做好标识,防止后期由于施工过程破坏管线。

Figure 202010755138

The invention discloses a pre-embedded wiring method for a standardized pipeline of a prefabricated laminated board, and relates to the technical field in the production and installation process of a prefabricated building project. The pre-embedded wiring method for standardized pipelines of prefabricated laminated boards provided by the present invention avoids damage to prefabricated components during chiseling and cutting at the construction site, and a comprehensive map of pre-embedded points is reserved to facilitate checking for leaks and filling gaps, as well as for checking the wiring between systems. In the case of equipment point conflicts, problems can be found and solved in time; after the pipeline optimization layout drawing is issued, the pipelines of the same house type on the construction site are laid in the same way, which is convenient for later pipeline repairs; the overlapping and intersecting areas are individually designed to reduce the thickness of the structural layer and avoid Due to the excessive concentration of pipelines, the laminated board will be cracked in the later stage, and the project cost will be reduced at the same time; after the concrete pouring is completed, make a mark in the wiring area to prevent the pipeline from being damaged in the later stage due to the construction process.

Figure 202010755138

Description

装配式叠合板标准化管线预埋布线方法Standardized pipeline pre-embedded wiring method of prefabricated laminated board

技术领域technical field

本发明涉及装配式建筑工程在生产及安装过程中的技术领域,尤其涉及一种装配式叠合板标准化管线预埋布线方法。The invention relates to the technical field in the production and installation process of prefabricated construction projects, in particular to a pre-embedded wiring method of prefabricated laminated board standardized pipelines.

背景技术Background technique

对于目前的装配式叠合板施工,一般做法为,将顶板一分为二,线管敷设在顶板的现浇层内,需要在现场湿作业完成。预制叠合板为60mm厚,现浇层厚度的确定除考虑结构安全外,还要考虑走线的要求,若管线敷设出现交叉的情况,现浇层的厚度至少需要70~80mm。对于这种施工方式:For the current prefabricated laminate construction, the general practice is that the roof is divided into two parts, and the line pipes are laid in the cast-in-place layer of the roof, which needs to be completed by wet work on site. The prefabricated laminated board is 60mm thick. In addition to the structural safety, the thickness of the cast-in-place layer should also be considered. If the pipeline is laid cross, the thickness of the cast-in-place layer should be at least 70-80mm. For this construction method:

(1)由于顶板管线较多,线管之间难免交叉,甚至出现重叠三层或以上的现象,不仅不利于成品保护,而且会影响楼板完成面的标高;(1) Due to the large number of pipelines on the roof, it is inevitable that the pipelines will cross each other, and even three or more layers overlap, which is not only unfavorable for the protection of the finished product, but also affects the elevation of the finished surface of the floor;

(2)现场施工中对于相同的户型,因为由不同的人员施工,管线的敷设方式会有不同,这就造成顶板内管线的敷设路径根据施工人员的不同,会有很大的随机性,如果施工过程中出现堵管的现象,后期管线修复难度会很大;(2) For the same type of house during on-site construction, the laying methods of pipelines will be different because of the construction by different personnel, which causes the laying path of pipelines in the roof to be very random according to the different construction personnel. During the construction process, the phenomenon of pipe blockage occurs, and it will be very difficult to repair the pipeline in the later stage;

(3)顶板管线敷设完毕后,由于不同工种施工人员交叉作业,会出现有大量的人员踩踏管线的现象,再加上混凝土浇筑,从而出现堵管的现象更是普遍。(3) After the roof pipeline is laid, there will be a large number of people stepping on the pipeline due to the cross-operation of construction personnel of different types. Coupled with the concrete pouring, the phenomenon of blocking the pipeline is more common.

(4)一般户内强电箱的入户线缆,为JDG32mm的镀锌导管,桁架筋下方与预制叠合板之间空隙较小,此类线管无法穿过叠合板敷设的区域。(4) The household cable of the general indoor strong electric box is JDG32mm galvanized conduit, and the gap between the bottom of the truss rib and the prefabricated laminated board is small, and this type of wire pipe cannot pass through the area where the laminated board is laid.

发明内容SUMMARY OF THE INVENTION

为了解决上述技术问题,本发明提供了一种装配式叠合板标准化管线预埋布线方法,避免在施工现场进行剔凿、切割时破坏预制构件,方便后期检修。In order to solve the above technical problems, the present invention provides a pre-embedded wiring method for standardized pipelines of prefabricated laminated plates, which avoids damage to prefabricated components during chiseling and cutting at the construction site, and facilitates later maintenance.

为实现此技术目的,本发明采用如下方案:一种装配式叠合板标准化管线预埋布线方法,包括如下步骤:In order to achieve this technical purpose, the present invention adopts the following scheme: a pre-embedded wiring method for standardized pipelines of prefabricated laminated plates, comprising the following steps:

S1、进行叠合板预留预埋点位综合:将不同电气系统所需的预留孔洞、预埋件综合在一张施工图纸上,并出具叠合板预留预埋点位综合图;S1. Carry out the synthesis of the pre-embedded points reserved for the laminated board: Integrate the reserved holes and pre-embedded parts required by different electrical systems on a construction drawing, and issue a comprehensive drawing of the pre-embedded points reserved for the laminated board;

S2、根据叠合板预留预埋点位综合图,进行管线优化布置:将户内强弱电管线分别从户内强弱电箱开始引出,根据管线作用和位置的不同进行路径规划,并出具管线优化布置图;S2. According to the comprehensive map of the pre-embedded points reserved for the laminated board, optimize the pipeline layout: lead the indoor strong and weak current pipelines from the indoor strong and weak current boxes, plan the path according to the role and location of the pipeline, and issue Pipeline optimization layout;

S3、在管线优化布置图中对管线集中或交叉较多的区域进行单独的管钱布线区设计:间隔布置管线,当管线交叉较多现浇层不能满足钢筋保护层要求时,管线布线区预制叠合板厚度降低1~1.5cm,管线上部增设网片钢筋;S3. In the pipeline optimization layout drawing, design a separate management and money wiring area for the areas where the pipelines are concentrated or intersected more: arrange the pipelines at intervals. When the pipelines intersect more than the cast-in-place layer cannot meet the requirements of the steel protection layer, the pipeline wiring area is prefabricated. The thickness of the laminated board is reduced by 1-1.5cm, and mesh reinforcement is added to the upper part of the pipeline;

S4、混凝土浇筑完成后,在管线布线区域做好标识。S4. After the concrete pouring is completed, make a mark in the pipeline wiring area.

与现有技术相比,本发明的有益效果在于:本发明提供的装配式叠合板标准化管线预埋布线方法,避免在施工现场进行剔凿、切割时破坏预制构件,预留预埋点位综合图方便查漏补缺的同时也便于检查各个系统间的设备点位冲突情况,及时发现问题并解决问题;出具管线优化布置图后,施工现场相同户型的管线敷设方式相同,便于后期管线修复;对于重叠交叉区域进行单独设计,减小结构层厚度,不会由于管线过于集中而造成叠合板后期开裂,同时降低工程造价;混凝土浇筑完成后在布线区内做好标识,防止后期由于施工过程破坏管线。Compared with the prior art, the beneficial effects of the present invention are: the pre-embedded wiring method of the prefabricated laminated board standardized pipeline provided by the present invention avoids damage to the prefabricated components during chiseling and cutting at the construction site, and reserves pre-embedded points for integration. The diagram is convenient for checking leaks and filling vacancies, but also for checking the conflict of equipment points between various systems, so as to find and solve problems in time; after the pipeline optimization layout drawing is issued, the pipelines of the same house type on the construction site are laid in the same way, which is convenient for later pipeline repairs; The overlapping and intersecting areas are individually designed to reduce the thickness of the structural layer, which will not cause the later cracking of the laminated board due to the excessive concentration of pipelines, and reduce the project cost at the same time; after the concrete pouring is completed, make a mark in the wiring area to prevent the pipeline from being damaged later due to the construction process. .

本发明的优选方案为:The preferred solution of the present invention is:

S3中根据管线的数量和管线交叉重叠情况,将管线间隔地排列,间隔不小于2cm。In S3, according to the number of pipelines and the overlapping situation of pipelines, the pipelines are arranged at intervals, and the interval is not less than 2cm.

S3中网片钢筋敷设宽度大于等于管线布线区宽度,并向两边各延伸150mm。The width of the mesh reinforcement in S3 is greater than or equal to the width of the pipeline wiring area, and extends 150mm to both sides.

S3中重叠交叉区域避开桁架筋、横向钢筋和纵向钢筋置于叠合板下层。In S3, the overlapping and intersecting area avoids truss bars, transverse bars and longitudinal bars and is placed in the lower layer of the laminated slab.

附图说明Description of drawings

图1为本发明实施例提供的室内强电管线布置平面图;1 is a plan view of an indoor strong-current pipeline arrangement provided by an embodiment of the present invention;

图2为本发明实施例提供的室内弱电管线布置平面图;2 is a plan view of an indoor weak current pipeline arrangement provided by an embodiment of the present invention;

图3为本发明实施例提供的室内预留预埋点位综合图;3 is a comprehensive diagram of indoor reserved pre-embedded points provided by an embodiment of the present invention;

图4为本发明实施例提供的室内管线优化布置图;Fig. 4 is an indoor pipeline optimization layout diagram provided by an embodiment of the present invention;

图5为本发明实施例提供的管线布线区的结构示意图;5 is a schematic structural diagram of a pipeline wiring area provided by an embodiment of the present invention;

图中标记为:1-桁架筋,2-横向钢筋,3-纵向钢筋,4-叠合板,5-钢筋网片,6-现浇层,7-线管。Marked as: 1-truss bar, 2-transverse steel bar, 3-longitudinal steel bar, 4-laminated plate, 5-reinforced mesh sheet, 6-cast-in-place layer, 7-line pipe.

具体实施方式Detailed ways

为充分了解本发明之目的、特征及功效,借由下述具体的实施方式,对本发明做详细说明,但本发明并不仅仅限于此。In order to fully understand the purpose, features and effects of the present invention, the present invention will be described in detail by the following specific embodiments, but the present invention is not limited thereto.

本发明提供的一种装配式叠合板标准化管线预埋布线方法,步骤如下:The present invention provides a pre-embedded wiring method for an assembled laminated board standardized pipeline, the steps are as follows:

第一步,进行叠合板预留预埋点位综合,由于电气专业系统众多,每个系统都有单独的一套图纸。为确保预制件中的设备点位齐全,避免在施工现场进行剔凿、切割时破坏预制构件,将各系统所需的预留孔洞、预埋件综合在一张图纸上,并出具叠合板预留预埋点位综合图。方便查漏补缺的同时也便于检查各个系统间的设备点位是否存在冲突、管线路径是否重合,能够及时发现问题并将其解决。The first step is to carry out the synthesis of the pre-buried points reserved for the laminated board. Due to the large number of electrical professional systems, each system has a separate set of drawings. In order to ensure that the equipment points in the prefabricated parts are complete and avoid damaging the prefabricated components during chiseling and cutting at the construction site, the reserved holes and embedded parts required by each system are integrated on one drawing, and the prefabricated prefabricated panels are issued. A comprehensive map of pre-embedded points is reserved. It is convenient to check for leaks and fill gaps, and it is also convenient to check whether there is a conflict between the equipment points of each system and whether the pipeline paths overlap, so that problems can be found and solved in time.

第二步,根据叠合板预留预埋点位综合图,进行管线优化布置。户内的强弱电管线均从户内强弱电箱开始引出,按管线作用和位置的不同进行路径规划。一般照明管线一路、厨房管线一路、卫生间管线一路、普通插座管线一路、空调管线一路和弱电管线一路等,针对每一路管线分别进行路径规划,尽量减少管线交叉,并出具管线优化布置图,以保证施工现场相同户型的管线敷设方式均相同,也便于后期管线修复。管线的规划路径应躲避装修层内敷设的给水及采暖管道,以防止安装管卡时,破坏已敷设的管线。The second step is to optimize the pipeline layout according to the comprehensive map of the pre-embedded points reserved for the laminated board. The indoor strong and weak electric pipelines are all led out from the indoor strong and weak electric boxes, and the path planning is carried out according to the different functions and positions of the pipelines. One general lighting pipeline, one kitchen pipeline, one toilet pipeline, one ordinary socket pipeline, one air-conditioning pipeline, and one weak current pipeline, etc., carry out route planning for each pipeline separately, minimize pipeline crossover, and issue an optimized pipeline layout to ensure The pipelines of the same house type on the construction site are laid in the same way, which is also convenient for later pipeline repairs. The planned path of the pipeline should avoid the water supply and heating pipelines laid in the decoration layer, so as to prevent the pipelines that have been laid from being damaged when the pipe clamps are installed.

第三步,在管线优化布置图中,针对不可避免的管线集中或者交叉较多的区域,规划出专门的管线布线区,并对此区域进行单独的优化设计,合理的设计可减小结构层厚度,从而降低工程造价。The third step, in the pipeline optimization layout drawing, plan a special pipeline routing area for the inevitable pipeline concentration or cross-over area, and carry out a separate optimization design for this area. Reasonable design can reduce the structural layer. thickness, thereby reducing the project cost.

对于此管线布线区:For this line routing area:

(1)根据管线的多少和管线交叉重叠情况而规划此管线布线区域的尺寸:管路的排列不能紧靠在一起,间隔不小于2cm,以保证管线敷设时,不会由于管线过于集中而造成叠合板后期开裂。(1) Plan the size of the pipeline wiring area according to the number of pipelines and the overlapping situation of pipelines: the arrangement of pipelines cannot be close together, and the interval is not less than 2cm, so as to ensure that when the pipelines are laid, they will not be caused by excessive concentration of pipelines. Laminated board cracks later.

(2)叠合板预制时,此管线布线区预制厚度降低1~1.5cm,形成一个凹槽结构,槽内放置管线,方便后期布设管线,此种方式可使电源入户管在不断桁架筋的情况下进行敷设,并在此管线布线区域预制叠合板内,增设Φ4@40mm网片强筋,防止叠合板吊装时开裂。(2) During the prefabrication of the laminated board, the prefabricated thickness of the pipeline wiring area is reduced by 1-1.5cm to form a groove structure, and pipelines are placed in the groove to facilitate the later pipeline layout. Lay it under certain circumstances, and add Φ4@40mm mesh reinforcement in the prefabricated laminated board in this pipeline wiring area to prevent the laminated board from cracking during hoisting.

(3)现场施工时,根据管线优化布置图进行管线敷设,布线区内管线需做到规范、整齐、美观,管线敷设完毕,管线布线区避开桁架筋、横向钢筋和纵向钢筋置于叠合板下层。上部增设网片钢筋,可为Φ4@40mm,宽度不应小于布线区宽度,并向两边各延伸150mm。网片刚接和其他钢筋尽量贴合,避免出现上层混凝土的厚度不满足保护层要求的情况。(3) During on-site construction, the pipeline should be laid according to the optimized pipeline layout. The pipelines in the wiring area should be standardized, neat and beautiful. After the pipelines are laid, the pipeline wiring area should avoid truss bars, transverse bars and longitudinal bars and place them on the laminated board. lower level. The mesh reinforcement is added to the upper part, which can be Φ4@40mm, the width should not be less than the width of the wiring area, and extend 150mm to both sides. The mesh is just connected to other steel bars as closely as possible to avoid the situation that the thickness of the upper concrete does not meet the requirements of the protective layer.

第四步,混凝土浇筑完成后,在布线区内做好标识,以防止后期由于施工需要使用膨胀螺栓打孔等破坏管线。The fourth step, after the concrete pouring is completed, make a mark in the wiring area to prevent the pipeline from being damaged due to the need to use expansion bolts to drill holes in the later stage.

以一个具体户型为例,图1中某户型强电管线布置平面图,图2为该户型弱电管线布置平面图,消防设备位于公共区域,公共区域一般为现浇筑区区域。将图1图2综合至一张预留预埋点位综合图(图3)。图3中线路路径混乱,交叉重叠区域较多,为减少管线交叉,将全部管线进行路径规划,如图4所示,减少管线交叉重叠区域,并将管线不可避免的重叠区域规划出专门的管线布线区。图4中虚线区域为标示的管线布线区,请参阅图5,管线布线区内各管线间隔排列,间隔不小于2cm,叠合板上的管线布线区预制厚度降低1~1.5cm形成一个凹槽结构,在凹槽结构的下方增设网片钢筋,并将钢筋网片向管线布线区的两边各延伸150cm。之后浇筑混凝土,混凝土浇筑完成后,在管线布线区内做好标识,以防止后期由于施工需要使用膨胀螺栓打孔等破坏管线。Taking a specific house type as an example, the layout plan of a certain type of strong current pipeline in Figure 1, Figure 2 is the layout plan of the weak current pipeline of this type, the fire equipment is located in the public area, and the public area is generally the cast-in-place area. Figure 1 and Figure 2 are integrated into a comprehensive map of reserved pre-embedded points (Figure 3). In Figure 3, the line paths are chaotic, and there are many overlapping areas. In order to reduce the intersection of pipelines, all pipelines are routed. As shown in Figure 4, the overlapping areas of pipelines are reduced, and special pipelines are planned for the unavoidable overlapping areas of pipelines. wiring area. The dotted area in Figure 4 is the marked pipeline wiring area. Please refer to Figure 5. The pipelines in the pipeline wiring area are arranged at intervals, and the interval is not less than 2cm. The prefabricated thickness of the pipeline wiring area on the laminated board is reduced by 1-1.5cm to form a groove structure. , add mesh reinforcement below the groove structure, and extend the reinforcement mesh to each side of the pipeline wiring area by 150cm. After pouring concrete, after the concrete pouring is completed, make a mark in the pipeline wiring area to prevent the pipeline from being damaged due to the need to use expansion bolts to drill holes in the later stage.

最后,需要注意的是:以上列举的仅是本发明的优选实施例,当然本领域的技术人员可以对本发明进行改动和变型,倘若这些修改和变型属于本发明权利要求及其等同技术的范围之内,均应认为是本发明的保护范围。Finally, it should be noted that: the above enumeration is only the preferred embodiment of the present invention, of course those skilled in the art can make changes and modifications to the present invention, if these modifications and modifications belong to the scope of the claims of the present invention and its equivalent technology within the scope of protection of the present invention.

Claims (4)

1.一种装配式叠合板标准化管线预埋布线方法,其特征在于,包括如下步骤:1. a pre-embedded wiring method for prefabricated laminated board standardized pipeline, is characterized in that, comprises the steps: S1、进行叠合板预留预埋点位综合:将不同电气系统所需的预留孔洞、预埋件综合在一张施工图纸上,并出具叠合板预留预埋点位综合图;S1. Carry out the synthesis of the pre-embedded points reserved for the laminated board: Integrate the reserved holes and pre-embedded parts required by different electrical systems on a construction drawing, and issue a comprehensive drawing of the pre-embedded points reserved for the laminated board; S2、根据叠合板预留预埋点位综合图,进行管线优化布置:将户内强弱电管线分别从户内强弱电箱开始引出,根据管线作用和位置的不同进行路径规划,并出具管线优化布置图;S2. According to the comprehensive map of the pre-embedded points reserved for the laminated board, optimize the pipeline layout: lead the indoor strong and weak current pipelines from the indoor strong and weak current boxes, plan the path according to the role and location of the pipeline, and issue Pipeline optimization layout; S3、在管线优化布置图中对管线集中或交叉较多的区域进行单独的管钱布线区设计:间隔布置管线,叠合板上设置管线布线区;当管线交叉较多现浇层不能满足钢筋保护层要求时,管线布线区预制叠合板厚度降低1~1.5cm,管线上部增设网片钢筋;S3. In the pipeline optimization layout drawing, design a separate management and money wiring area for the areas where the pipelines are concentrated or intersected more: the pipelines are arranged at intervals, and the pipeline wiring area is set on the laminated board; when the pipelines intersect more, the cast-in-place layer cannot meet the steel protection When the layer is required, the thickness of the prefabricated laminated board in the pipeline wiring area is reduced by 1-1.5cm, and the mesh reinforcement is added on the upper part of the pipeline; S4、混凝土浇筑完成后,在管线布线区域做好标识。S4. After the concrete pouring is completed, make a mark in the pipeline wiring area. 2.根据权利要求1所述的装配式叠合板标准化管线预埋布线方法,其特征在于,S3中根据管线的数量和管线交叉重叠情况,将管线间隔地排列,间隔不小于2cm。2. The pre-embedded wiring method for prefabricated laminated board standardized pipelines according to claim 1, characterized in that, in S3, according to the number of pipelines and the overlapping situation of pipelines, the pipelines are arranged at intervals, and the interval is not less than 2cm. 3.根据权利要求1所述的装配式叠合板标准化管线预埋布线方法,其特征在于,S3中网片钢筋敷设宽度大于等于管线布线区宽度,并向两边各延伸150mm。3. The pre-embedded wiring method for prefabricated laminated board standardized pipelines according to claim 1, characterized in that the width of the mesh reinforcement in S3 is greater than or equal to the width of the pipeline wiring area, and extends 150mm to both sides. 4.根据权利要求1所述的装配式叠合板标准化管线预埋布线方法,其特征在于,S3中重叠交叉区域避开桁架筋、横向钢筋和纵向钢筋置于叠合板下层。4 . The pre-embedded wiring method of the prefabricated laminated board standardized pipeline according to claim 1 , wherein the overlapping and intersecting area in S3 is placed on the lower layer of the laminated board, avoiding truss bars, transverse reinforcement bars and longitudinal reinforcement bars. 5 .
CN202010755138.8A 2020-07-31 2020-07-31 Pre-buried wiring method for standardized pipeline of assembled laminated slab Withdrawn CN111884121A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010755138.8A CN111884121A (en) 2020-07-31 2020-07-31 Pre-buried wiring method for standardized pipeline of assembled laminated slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010755138.8A CN111884121A (en) 2020-07-31 2020-07-31 Pre-buried wiring method for standardized pipeline of assembled laminated slab

Publications (1)

Publication Number Publication Date
CN111884121A true CN111884121A (en) 2020-11-03

Family

ID=73205800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010755138.8A Withdrawn CN111884121A (en) 2020-07-31 2020-07-31 Pre-buried wiring method for standardized pipeline of assembled laminated slab

Country Status (1)

Country Link
CN (1) CN111884121A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293857A (en) * 2021-07-06 2021-08-24 文佳 Basement for reducing floor height by laying channels through overall pipelines
CN113808258A (en) * 2021-09-18 2021-12-17 广东博意建筑设计院有限公司 Fine laying cooperative design method and system for electric conduit system in laminated slab

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06128992A (en) * 1992-10-20 1994-05-10 Mirai Ind Co Ltd Recess forming tool for bent pipe
WO2000005538A1 (en) * 1997-01-14 2000-02-03 Selvaag Homes As Method for the laying of a heat emitting floor
CN107201782A (en) * 2017-07-18 2017-09-26 西安全鼎建筑科技有限公司 A kind of wall of assembled architecture, floor connecting node and method
CN108661223A (en) * 2018-05-07 2018-10-16 浙江省建工集团有限责任公司 A kind of prefabricated superimposed sheet of assembled architecture reserves the construction technology of wire casing
CN109577535A (en) * 2018-12-10 2019-04-05 中建二局第二建筑工程有限公司 Assembled architecture PC superimposed sheet and the electromechanical installation built-in process of dry wall combination
CN110042963A (en) * 2019-04-25 2019-07-23 江苏浩森建筑设计有限公司 A method of reducing assembled floor superimposed sheet thickness
CN111119332A (en) * 2019-12-31 2020-05-08 广东省第一建筑工程有限公司 Prefabrication and installation and connection construction method of new type electric wire pipe of prefabricated building

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06128992A (en) * 1992-10-20 1994-05-10 Mirai Ind Co Ltd Recess forming tool for bent pipe
WO2000005538A1 (en) * 1997-01-14 2000-02-03 Selvaag Homes As Method for the laying of a heat emitting floor
CN107201782A (en) * 2017-07-18 2017-09-26 西安全鼎建筑科技有限公司 A kind of wall of assembled architecture, floor connecting node and method
CN108661223A (en) * 2018-05-07 2018-10-16 浙江省建工集团有限责任公司 A kind of prefabricated superimposed sheet of assembled architecture reserves the construction technology of wire casing
CN109577535A (en) * 2018-12-10 2019-04-05 中建二局第二建筑工程有限公司 Assembled architecture PC superimposed sheet and the electromechanical installation built-in process of dry wall combination
CN110042963A (en) * 2019-04-25 2019-07-23 江苏浩森建筑设计有限公司 A method of reducing assembled floor superimposed sheet thickness
CN111119332A (en) * 2019-12-31 2020-05-08 广东省第一建筑工程有限公司 Prefabrication and installation and connection construction method of new type electric wire pipe of prefabricated building

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293857A (en) * 2021-07-06 2021-08-24 文佳 Basement for reducing floor height by laying channels through overall pipelines
CN113808258A (en) * 2021-09-18 2021-12-17 广东博意建筑设计院有限公司 Fine laying cooperative design method and system for electric conduit system in laminated slab

Similar Documents

Publication Publication Date Title
CN109614723B (en) Comprehensive construction method based on BIM technology
CN109577535A (en) Assembled architecture PC superimposed sheet and the electromechanical installation built-in process of dry wall combination
CN103161258B (en) The pre-buried distribution method of prefabricated concrete structure architectural electricity
CN107893496A (en) A kind of assembly concrete integrated floor and its manufacture method
CN111884121A (en) Pre-buried wiring method for standardized pipeline of assembled laminated slab
CN111119332A (en) Prefabrication and installation and connection construction method of new type electric wire pipe of prefabricated building
CN101736839A (en) Construction method for prestressed concrete floor slab reserved with water-heating pipeline well opening
US20250376845A1 (en) Modular building panels with building services
CN110107972B (en) Cabin type refrigerating machine room and construction method thereof
CN206189685U (en) Integrated floor of modularization and house
CN207453225U (en) A kind of superstructure unit and assembly concrete integrated floor
CN208803681U (en) Piping shaft and building structure
CN217758934U (en) Single-layer basement with equipment pipe gallery
CN216446280U (en) Be applicable to assembled PEC roof beam and superimposed sheet electric wire pipeline structure
CN118445898A (en) Comprehensive construction method for pipeline in prefabricated laminated slab
CN215483828U (en) Wall in assembled integration
CN109469099A (en) Prefabricated underground pipe gallery
CN204645358U (en) Template and floor
CN104153610A (en) Modularization box type integral integrated electric control device for fuel gas power plant and installing method of modularization box type integral integrated electric control device
CN107882067A (en) A kind of design and construction structure of contignation underground garage pipe gallery
CN222667261U (en) Assembled floor of integrated spool
CN113982169A (en) Be applicable to assembled PEC roof beam and superimposed sheet electric wire pipeline structure
CN113374269A (en) Autoclaved lightweight concrete wallboard standard layer construction optimization method based on 3D lofting
CN207651821U (en) First and second unit equipment prefabricated cabins of 35kV with additional maintenance cabin
CN111884152A (en) Electrical pre-buried wiring method for prefabricated concrete structure building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20201103