[go: up one dir, main page]

CN110836120A - Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults - Google Patents

Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults Download PDF

Info

Publication number
CN110836120A
CN110836120A CN201911082860.3A CN201911082860A CN110836120A CN 110836120 A CN110836120 A CN 110836120A CN 201911082860 A CN201911082860 A CN 201911082860A CN 110836120 A CN110836120 A CN 110836120A
Authority
CN
China
Prior art keywords
lining structure
layer
monitoring
tunnel lining
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911082860.3A
Other languages
Chinese (zh)
Other versions
CN110836120B (en
Inventor
薛翊国
宋茜
邱道宏
孔凡猛
柏成浩
公惠民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201911082860.3A priority Critical patent/CN110836120B/en
Publication of CN110836120A publication Critical patent/CN110836120A/en
Application granted granted Critical
Publication of CN110836120B publication Critical patent/CN110836120B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/32Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring the deformation in a solid

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种适用于穿越活断层的自监测调节的隧道衬砌结构及其施工方法,隧道衬砌结构,包括:注浆加固层,为在断层破碎带的围岩开挖面施工时实现开挖稳定;消能减震层,覆盖注浆加固层的底部;预制隧道衬砌结构,设置于消能减震层的上方,由多段通过铰接而成;钢拱架,设置于预制隧道衬砌结构的上方,钢拱架的两端分别安装在消能减震层的两端钢板顶部;钢拱架与注浆加固层之间预留一定距离;注浆加固区的内壁上设置监测加固仪,监测加固仪包括监测装置和喷头,监测装置安装在注浆加固区的内壁上,喷头安装在监测装置上,喷头与注浆泵连接,注浆泵与浆液源连接。

Figure 201911082860

The invention discloses a tunnel lining structure suitable for self-monitoring and adjustment of crossing active faults and a construction method thereof. The tunnel lining structure comprises: a grouting reinforcement layer, which is used to realize the opening of the surrounding rock excavation surface of the fault fracture zone during construction. The excavation is stable; the energy dissipation and shock absorption layer covers the bottom of the grouting reinforcement layer; the prefabricated tunnel lining structure is arranged above the energy dissipation and shock absorption layer, and is formed by hinged multiple sections; the steel arch frame is arranged at the bottom of the prefabricated tunnel lining structure Above, the two ends of the steel arch are installed on the tops of the steel plates at both ends of the energy dissipation and shock absorption layer; a certain distance is reserved between the steel arch and the grouting reinforcement layer; The reinforcement instrument includes a monitoring device and a nozzle, the monitoring device is installed on the inner wall of the grouting reinforcement area, the nozzle is installed on the monitoring device, the nozzle is connected to the grouting pump, and the grouting pump is connected to the slurry source.

Figure 201911082860

Description

适用于穿越活断层的自监测调节的隧道衬砌结构及施工方法Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults

技术领域technical field

本发明涉及隧道工程技术领域,尤其涉及一种适用于穿越活断层的自监测调节的隧道衬砌结构及施工方法。The invention relates to the technical field of tunnel engineering, in particular to a tunnel lining structure and a construction method suitable for self-monitoring and adjustment of crossing active faults.

背景技术Background technique

公开该背景技术部分的信息仅仅旨在增加对本发明的总体背景的理解,而不必然被视为承认或以任何形式暗示该信息构成已经成为本领域一般技术人员所公知的现有技术。The information disclosed in this Background section is only for enhancement of understanding of the general background of the invention and should not necessarily be taken as an acknowledgement or any form of suggestion that this information forms the prior art already known to a person of ordinary skill in the art.

随着我国经济的不断增长,为满足国民经济持续快速协调发展的迫切需要,我国的交通建设实现跨越式发展,加快扩大路网规模、完善路网结构以形成完整、便利、快捷的交通运输体系为目标。当今多种交通工程形式不断发展,隧道依靠其能够大大缩短线路长度,减小能耗的优点往往成为工程建设的最佳选择。With the continuous growth of my country's economy, in order to meet the urgent needs of the sustained and rapid coordinated development of the national economy, my country's transportation construction has achieved leapfrog development, accelerated the expansion of the road network scale, and improved the road network structure to form a complete, convenient and fast transportation system. as the target. Nowadays, with the continuous development of various forms of traffic engineering, tunnels can greatly shorten the length of lines and reduce energy consumption by virtue of their advantages, which often become the best choice for engineering construction.

随着西部大开发的深入进行,川藏铁路正在规划建设,川藏铁路所经区域地势跌宕起伏,地处欧亚板块与印度板块碰撞隆升形成的青藏高原中东部,沿线山高谷深、地层岩性混杂多变,新构造活动剧烈,深大活动断裂广泛分布。断层在围岩强度高的地区会积累应变能达到一定强度后突然滑动引发地震,在围岩强度低的断层持续不断缓慢移动直接导致衬砌偏压,是工程安全的直接威胁。但铁路隧道建设不可避免的需要穿越断裂带区域。若不对隧道结构进行改进优化,穿越断层的的隧道会产生衬砌断裂剥落,产生较大的挠曲变形,甚至隧道塌陷透顶,严重时导致坍塌破坏。With the in-depth development of the western region, the Sichuan-Tibet Railway is being planned and constructed. The terrain of the area covered by the Sichuan-Tibet Railway is ups and downs. The lithology is mixed and changeable, the neotectonic activity is intense, and the deep and large active faults are widely distributed. Faults in areas with high surrounding rock strength will accumulate strain energy to a certain strength and then suddenly slide to cause earthquakes. Continuous and slow movement of faults with low surrounding rock strength directly leads to lining bias, which is a direct threat to engineering safety. However, the construction of railway tunnels inevitably requires crossing the fault zone. If the tunnel structure is not improved and optimized, the lining of the tunnel passing through the fault will be fractured and peeled off, resulting in large deflection and deformation, and even the tunnel will collapse to the top, leading to collapse and damage in severe cases.

如何保证隧道安全穿越活断层区域,并在发生错动时减小对隧道结构的损害成为目前亟待解决的难题。How to ensure the safe passage of the tunnel through the active fault area and reduce the damage to the tunnel structure when misalignment occurs has become an urgent problem to be solved.

发明内容SUMMARY OF THE INVENTION

为了解决现有技术中存在的技术问题,本发明的目的是提供一种适用于穿越活断层的自监测调节的隧道衬砌结构及其施工方法。该隧道衬砌结构可以根据监测设备监测的断层运动数据对隧道衬砌结构进行加固,提高隧道结构整体的抗错运动,使隧道内部可以错动,但不错断,维持隧道的整体结构安全。In order to solve the technical problems existing in the prior art, the purpose of the present invention is to provide a tunnel lining structure suitable for self-monitoring and adjustment across active faults and a construction method thereof. The tunnel lining structure can reinforce the tunnel lining structure according to the fault movement data monitored by the monitoring equipment, and improve the overall anti-error movement of the tunnel structure, so that the interior of the tunnel can be staggered, but not broken, and the overall structural safety of the tunnel is maintained.

为了解决以上技术问题,本发明的技术方案为:In order to solve the above technical problems, the technical scheme of the present invention is:

一种适用于穿越活断层的自监测调节的隧道衬砌结构,包括:A self-monitoring and adjusting tunnel lining structure suitable for crossing active faults, comprising:

注浆加固层,为在断层破碎带的围岩开挖面施工时实现开挖稳定;The grouting reinforcement layer is to achieve excavation stability during the construction of the surrounding rock excavation face in the fault fracture zone;

消能减震层,覆盖注浆加固层的底部;The energy dissipation and shock absorption layer covers the bottom of the grouting reinforcement layer;

预制隧道衬砌结构,设置于消能减震层的上方,由多段通过铰接而成;The prefabricated tunnel lining structure is arranged above the energy dissipation and shock absorption layer, and is formed by hinged multiple sections;

钢拱架,设置于预制隧道衬砌结构的上方,钢拱架的两端分别安装在消能减震层的两端顶部的钢板上;The steel arch frame is arranged above the prefabricated tunnel lining structure, and the two ends of the steel arch frame are respectively installed on the steel plates on the tops of the two ends of the energy dissipation and shock absorption layer;

钢拱架与注浆加固层之间预留一定距离;注浆加固区的内壁上设置监测加固仪,监测加固仪包括监测装置和喷头,监测装置安装在注浆加固区的内壁上,喷头安装在监测装置上,喷头与注浆泵连接,注浆泵与浆液源连接。A certain distance is reserved between the steel arch and the grouting reinforcement layer; a monitoring and reinforcement instrument is installed on the inner wall of the grouting reinforcement area. The monitoring and reinforcement instrument includes a monitoring device and a nozzle. The monitoring device is installed on the inner wall of the grouting reinforcement area, and the nozzle is installed On the monitoring device, the nozzle is connected with the grouting pump, and the grouting pump is connected with the slurry source.

在一些实施例中,所述注浆加固层还包括若干锚杆,锚杆为无缝钢管。钢管直径、注浆孔直径和间距根据围岩等级而定。In some embodiments, the grouting reinforcement layer further includes several bolts, and the bolts are seamless steel pipes. The steel pipe diameter, grouting hole diameter and spacing are determined according to the surrounding rock grade.

在一些实施例中,所述消能减震层的材料为橡胶材料,厚度为10-30cm,具体参考围岩等级取值。In some embodiments, the material of the energy dissipation and shock absorption layer is a rubber material, and the thickness is 10-30 cm, and the specific value is determined with reference to the grade of the surrounding rock.

进一步的,所述消能减震层包括第一段、第二段和第三段,第二段覆盖设置于注浆加固层的上方,第一段和第三段分别设置于第二段的两侧,钢拱架的两端分别安装在第一段和第三段的顶端。Further, the energy dissipation and shock absorption layer includes a first section, a second section and a third section, the second section is covered and arranged above the grouting reinforcement layer, and the first section and the third section are respectively arranged on the second section. On both sides, the two ends of the steel arch are installed at the top of the first and third sections, respectively.

更进一步的,第一段和第三段的顶端均设置有钢板。钢板对钢拱架具有更好的支撑作用力,保证钢拱架安装的稳定性。Further, the top ends of the first section and the third section are provided with steel plates. The steel plate has a better supporting force on the steel arch, ensuring the stability of the installation of the steel arch.

在一些实施例中,所述钢拱架为格栅拱架。钢架纵向间距、钢架之间的纵向钢拉杆长度根据隧道围岩等级而定。In some embodiments, the steel arches are grid arches. The longitudinal spacing of the steel frames and the length of the longitudinal steel tie rods between the steel frames are determined according to the grade of the surrounding rock of the tunnel.

在一些实施例中,钢拱架与注浆加固层之间的距离为0.5-1m。In some embodiments, the distance between the steel arch and the grouting reinforcement layer is 0.5-1 m.

在一些实施例中,每段预制隧道衬砌结构的长度为5-10m。In some embodiments, the length of each prefabricated tunnel lining structure is 5-10 m.

进一步的,所述预制隧道衬砌结构从外向内包括依次叠加设置的第一钢筋混凝土层、衬砌防水层、减震层和第二钢筋混凝土层。Further, the prefabricated tunnel lining structure includes, from the outside to the inside, a first reinforced concrete layer, a lining waterproof layer, a shock absorption layer and a second reinforced concrete layer that are stacked in sequence.

更进一步的,第一钢筋混凝土层、衬砌防水层、减震层和第二钢筋混凝土层的厚度比为1:1:1:2。Further, the thickness ratio of the first reinforced concrete layer, the lining waterproof layer, the shock absorption layer and the second reinforced concrete layer is 1:1:1:2.

更进一步的,所述衬砌防水层为防水卷材和土工布的复合材料或无纺布。Further, the lining waterproof layer is a composite material or non-woven fabric of a waterproof membrane and a geotextile.

更进一步的,所述减震层采用橡胶材料制成。Further, the shock absorption layer is made of rubber material.

在一些实施例中,钢拱架与注浆加固层之间的距离为0.5-1m。In some embodiments, the distance between the steel arch and the grouting reinforcement layer is 0.5-1 m.

进一步的,所述注浆加固区的内壁上,喷头的安装方式为环向8-10组,纵向相邻喷头间距为1-3m,经过断层错动段时适当加密。Further, on the inner wall of the grouting reinforcement area, the nozzles are installed in 8-10 groups in the circumferential direction, and the distance between the adjacent nozzles in the longitudinal direction is 1-3m, which is properly encrypted when passing through the fault dislocation section.

所述适用于穿越活断层的自监测调节的隧道衬砌结构的施工方法,包括如下步骤:The construction method of the self-monitoring and adjusting tunnel lining structure suitable for crossing active faults includes the following steps:

隧道开挖经过断层破碎带时,施作超前小导管注浆的超前支护形式,并施工注浆加固层,对断层破碎带进行加固,维持岩体稳定;When the tunnel excavation passes through the fault fracture zone, the advanced support form of advanced small conduit grouting is applied, and the grouting reinforcement layer is constructed to reinforce the fault fracture zone and maintain the stability of the rock mass;

在注浆加固层内壁上布设监测加固仪;A monitoring and reinforcement instrument is arranged on the inner wall of the grouting reinforcement layer;

在断层破碎带隧道区间,施工消能减震层,在消能减振层上施工预制隧道衬砌结构;In the tunnel section of the fault fracture zone, construct the energy dissipation and shock absorption layer, and construct the prefabricated tunnel lining structure on the energy dissipation and vibration absorption layer;

最后架设钢拱架。Finally erect the steel arch.

在一些实施例中,消能减震层包括三段,首先施工第二段,施工完预制隧道衬砌结构后,再施工第一段和第二段。In some embodiments, the energy dissipation and shock absorption layer includes three sections, the second section is constructed first, and the first section and the second section are constructed after the prefabricated tunnel lining structure is constructed.

本发明的有益效果为:The beneficial effects of the present invention are:

本发明通过在在预留净空变形层内部设有监测加固仪器,实现对断层的运动情况进行监测的目的。当仪器中的应变片所监测到的位移较大时,贴于应变片前的喷头及时根据应变片数据对钢拱架进行加固;隧道衬砌结构采用预制结构,段与段之间相互铰接,允许两段之间发生相对位移,使隧道内部错动但不错断;衬砌结构下部施作消能减震层,吸收断层错动能量的同时减小对衬砌结构的损伤。钢拱架架设在消能减震层顶部的两端钢板上,提高隧道上部的承载能力。提高隧道结构的整体抗错动,维持隧道的整体结构安全。本方法能更好的保证隧道整体结构的安全,利于隧道结构灾后的快速抢通、修复加固。The invention realizes the purpose of monitoring the movement of the fault by providing a monitoring and reinforcement instrument inside the reserved clearance deformation layer. When the displacement monitored by the strain gauge in the instrument is relatively large, the nozzle attached to the front of the strain gauge reinforces the steel arch in time according to the data of the strain gauge; the tunnel lining structure adopts a prefabricated structure, and the sections are hinged to each other, allowing The relative displacement occurs between the two sections, so that the inside of the tunnel is dislocated but not broken; the lower part of the lining structure is applied as an energy dissipation and shock absorption layer, which absorbs the energy of fault dislocation and reduces the damage to the lining structure. Steel arches are erected on the steel plates at both ends of the top of the energy dissipation and shock absorption layer to improve the bearing capacity of the upper part of the tunnel. Improve the overall anti-shock movement of the tunnel structure and maintain the overall structural safety of the tunnel. The method can better ensure the safety of the overall structure of the tunnel, and is beneficial to the rapid recovery, repair and reinforcement of the tunnel structure after a disaster.

附图说明Description of drawings

构成本发明的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。The accompanying drawings forming a part of the present invention are used to provide further understanding of the present invention, and the exemplary embodiments of the present invention and their descriptions are used to explain the present invention, and do not constitute an improper limitation of the present invention.

图1为本发明实施例的隧道横断面图;Fig. 1 is the tunnel cross-sectional view of the embodiment of the present invention;

图2是本发明实施例的隧道纵断面结构示意图;Fig. 2 is the tunnel longitudinal section structural schematic diagram of the embodiment of the present invention;

图3是本发明实施例A部分局部放大示意图;Fig. 3 is the partial enlarged schematic diagram of part A of the embodiment of the present invention;

图4是本发明实施例预支隧道衬砌结构示意图;4 is a schematic diagram of the lining structure of a pre-supported tunnel according to an embodiment of the present invention;

图中,1.围岩,2.断层破碎带,3.注浆加固层,4.监测加固仪器,5.钢拱架,6.消能减震层,7.预制隧道衬砌结构,8.铰接设备,9.钢板,10.预留变形层,11.衬砌防水层,12.钢筋混凝土结构,13.锚杆,14.减震层。In the figure, 1. Surrounding rock, 2. Fault fracture zone, 3. Grouting reinforcement layer, 4. Monitoring reinforcement instrument, 5. Steel arch frame, 6. Energy dissipation and shock absorption layer, 7. Prefabricated tunnel lining structure, 8. Hinged equipment, 9. Steel plate, 10. Reserved deformation layer, 11. Lining waterproof layer, 12. Reinforced concrete structure, 13. Anchor rod, 14. Damping layer.

具体实施方式Detailed ways

应该指出,以下详细说明都是示例性的,旨在对本发明提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本发明所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is exemplary and intended to provide further explanation of the invention. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本发明的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used herein is for the purpose of describing specific embodiments only, and is not intended to limit the exemplary embodiments according to the present invention. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural as well, furthermore, it is to be understood that when the terms "comprising" and/or "including" are used in this specification, it indicates that There are features, steps, operations, devices, components and/or combinations thereof.

下面结合实施例对本发明进一步说明:Below in conjunction with embodiment, the present invention is further described:

如图1所示,本发明公开的一种适用于穿越活断层的自监测调节的隧道衬砌结构,在断层破碎带2处的围岩1开挖面设有注浆加固层3,注浆加固层3包括隧道初支,采用锚网喷的形式,锚杆采用无缝钢管,钢管直径、注浆孔直径、间距根据围岩等级而定;浆液采用水泥-水玻璃双液注浆的形式;隧道采用预制隧道衬砌结构7,衬砌结构7下部施作消能减震层6,消能减震层6采用橡胶材料,厚度依据实际工程情况而定,用于吸收错动能量;钢拱架5架设在消能减震层6顶部的两端钢板9上,所述钢拱架选用格栅拱架,钢架纵向间距、钢架之间的纵向钢拉杆长度根据隧道围岩等级而定;As shown in FIG. 1 , a tunnel lining structure suitable for self-monitoring and adjustment through active faults disclosed in the present invention is provided with a grouting reinforcement layer 3 on the excavation surface of the surrounding rock 1 at the fault fracture zone 2, and the grouting reinforcement is Layer 3 includes the initial branch of the tunnel, which is in the form of anchor mesh spraying, and the anchor rod is made of seamless steel pipe. The diameter of the steel pipe, the diameter of the grouting hole, and the spacing are determined according to the grade of the surrounding rock; the grout is in the form of cement-water glass double-liquid grouting; The tunnel adopts a prefabricated tunnel lining structure 7, and the lower part of the lining structure 7 is provided with an energy dissipation and shock absorption layer 6. The energy dissipation and shock absorption layer 6 is made of rubber material, and its thickness is determined according to the actual engineering conditions to absorb the dislocation energy; the steel arch frame 5 It is erected on the steel plates 9 at both ends of the top of the energy dissipation and shock absorption layer 6, and the steel arch is selected as a grid arch, and the longitudinal spacing of the steel frames and the length of the longitudinal steel tie rods between the steel frames are determined according to the grade of the surrounding rock of the tunnel;

如图2所示,隧道开挖经过断层破碎带2时,隧道衬砌结构采用预制结构7,段与段之间通过铰接设备8相互铰接,允许两段之间发生相对位移,在断层错动时使隧道内部错动但不错断。As shown in Figure 2, when the tunnel excavation passes through the fault fracture zone 2, the tunnel lining structure adopts a prefabricated structure 7, and the sections are hinged to each other through the hinge device 8, allowing the relative displacement between the two sections. Make the inside of the tunnel staggered but not broken.

如图3所示,在断层破碎带2的注浆加固区3与钢拱架5外部之间预留预留变形层10;预留变形层可以允许在断层错动时位移先发生在隧道外部,并在变形比较大时,可以通过监测加固装置填充预留层对钢拱架进行加固。在注浆加固区3内壁上设有监测加固仪4,监测加固仪4包括监测装置和喷头,监测装置安装在注浆加固区的内壁上,喷头安装在监测装置上,喷头与注浆泵连接,注浆泵与浆液源连接。监测加固装置通过应变片感应隧道变形,变形位移较大时隧道监测加固装置会喷射混凝土浆液用于加固隧道。As shown in Fig. 3, a reserved deformation layer 10 is reserved between the grouting reinforcement area 3 of the fault fracture zone 2 and the outside of the steel arch 5; the reserved deformation layer can allow the displacement to occur outside the tunnel first when the fault is displaced , and when the deformation is relatively large, the steel arch can be reinforced by filling the reserved layer with the monitoring reinforcement device. A monitoring and reinforcement device 4 is arranged on the inner wall of the grouting reinforcement area 3. The monitoring and reinforcement device 4 includes a monitoring device and a nozzle. The monitoring device is installed on the inner wall of the grouting reinforcement area. The nozzle is installed on the monitoring device, and the nozzle is connected to the grouting pump. , the grouting pump is connected to the slurry source. The monitoring and reinforcement device senses the tunnel deformation through strain gauges. When the deformation displacement is large, the tunnel monitoring and reinforcement device will spray concrete slurry to reinforce the tunnel.

如图4所示,预制隧道衬砌结构7为:衬砌防水层11、消能减震层6以及钢筋混凝土结构12。衬砌防水层11采用防水卷材+土工布或无纺布形式进行防水;消能减震层6采用橡胶材料,厚度为10-20cm。As shown in FIG. 4 , the prefabricated tunnel lining structure 7 includes a lining waterproof layer 11 , an energy dissipation and shock absorption layer 6 and a reinforced concrete structure 12 . The lining waterproof layer 11 is waterproof in the form of waterproof membrane + geotextile or non-woven fabric; the energy dissipation and shock absorption layer 6 is made of rubber material with a thickness of 10-20cm.

适用于穿越活断层的自监测调节的隧道衬砌结构的施工方法,包括以下步骤:The construction method of tunnel lining structure suitable for self-monitoring and adjustment across active faults includes the following steps:

A、隧道开挖经过断层破碎带时,施作超前小导管注浆的超前支护形式,并施作注浆加固层,对断层破碎带进行加固,维持岩体稳定;A. When the tunnel excavation passes through the fault fracture zone, the advanced support form of advanced small conduit grouting is applied, and the grouting reinforcement layer is applied to reinforce the fault fracture zone and maintain the stability of the rock mass;

B、断层破碎带处的隧道区间,先施作消能减震层底部,当该段隧道衬砌设置完成后再施作两侧的消能减震层;B. In the tunnel section at the fractured zone of the fault, the bottom of the energy-dissipating and shock-absorbing layer shall be applied first, and then the energy-dissipating and shock-absorbing layers on both sides shall be applied after the lining of this section of the tunnel is completed;

C、施作消能层顶端的两侧钢板,并在钢板上架设钢拱架,钢板与钢拱架之间采用焊接的形式连接;C. Use steel plates on both sides of the top of the energy dissipation layer, and erect steel arches on the steel plates, and the steel plates and the steel arches are connected by welding;

D、布设监测加固仪,用于监测断层运动情况及时加固衬砌结构。D. A monitoring and reinforcement instrument is installed to monitor the movement of the fault and reinforce the lining structure in time.

以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1.一种适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:包括:1. a tunnel lining structure suitable for self-monitoring adjustment across active faults, is characterized in that: comprising: 注浆加固层,为在断层破碎带的围岩开挖面施工得到的筒状结构;The grouting reinforcement layer is a cylindrical structure constructed on the excavation face of the surrounding rock in the fault fracture zone; 消能减震层,覆盖注浆加固层的底部;The energy dissipation and shock absorption layer covers the bottom of the grouting reinforcement layer; 预制隧道衬砌结构,设置于消能减震层的上方,由多段通过铰接而成;The prefabricated tunnel lining structure is arranged above the energy dissipation and shock absorption layer, and is formed by hinged multiple sections; 钢拱架,设置于预制隧道衬砌结构的上方,钢拱架的两端分别安装在消能减震层的两端顶部;The steel arch frame is arranged above the prefabricated tunnel lining structure, and the two ends of the steel arch frame are respectively installed on the tops of the two ends of the energy dissipation and shock absorption layer; 钢拱架与注浆加固层之间预留一定距离;注浆加固区的内壁上设置监测加固仪,监测加固仪包括监测装置和喷头,监测装置安装在注浆加固区的内壁上,喷头安装在监测装置上,喷头与注浆泵连接,注浆泵与浆液源连接。A certain distance is reserved between the steel arch and the grouting reinforcement layer; a monitoring and reinforcement instrument is installed on the inner wall of the grouting reinforcement area. The monitoring and reinforcement instrument includes a monitoring device and a nozzle. The monitoring device is installed on the inner wall of the grouting reinforcement area, and the nozzle is installed On the monitoring device, the nozzle is connected with the grouting pump, and the grouting pump is connected with the slurry source. 2.根据权利要求1所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:所述注浆加固层还包括若干锚杆,锚杆为无缝钢管。2 . The tunnel lining structure suitable for self-monitoring and adjustment across active faults according to claim 1 , wherein the grouting reinforcement layer further comprises a plurality of bolts, and the bolts are seamless steel pipes. 3 . 3.根据权利要求1所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:所述消能减震层的材料为橡胶材料,厚度为10-30cm;3. The tunnel lining structure suitable for self-monitoring and adjustment of crossing active faults according to claim 1, characterized in that: the material of the energy dissipation and shock absorption layer is rubber material, and the thickness is 10-30cm; 进一步的,所述消能减震层包括第一段、第二段和第三段,第二段覆盖设置于注浆加固层的上方,第一段和第三段分别设置于第二段的两侧,钢拱架的两端分别安装在第一段和第三段的顶端;Further, the energy dissipation and shock absorption layer includes a first section, a second section and a third section, the second section is covered and arranged above the grouting reinforcement layer, and the first section and the third section are respectively arranged on the second section. On both sides, the two ends of the steel arch are installed at the top of the first and third sections respectively; 更进一步的,第一段和第三段的顶端均设置有钢板。Further, the top ends of the first section and the third section are provided with steel plates. 4.根据权利要求1所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:所述钢拱架为格栅拱架。钢架纵向间距、钢架之间的纵向钢拉杆长度根据隧道围岩等级而定。4 . The tunnel lining structure suitable for self-monitoring and adjustment across active faults according to claim 1 , wherein the steel arch is a grid arch. 5 . The longitudinal spacing of the steel frames and the length of the longitudinal steel tie rods between the steel frames are determined according to the grade of the surrounding rock of the tunnel. 5.根据权利要求1所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:钢拱架与注浆加固层之间的距离为0.5-1m。5 . The tunnel lining structure suitable for self-monitoring and adjustment across active faults according to claim 1 , wherein the distance between the steel arch and the grouting reinforcement layer is 0.5-1 m. 6 . 6.根据权利要求1所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:每段预制隧道衬砌结构的长度为5-10m;6. The tunnel lining structure suitable for self-monitoring adjustment of crossing active faults according to claim 1, characterized in that: the length of each prefabricated tunnel lining structure is 5-10m; 进一步的,所述预制隧道衬砌结构从外向内包括依次叠加设置的第一钢筋混凝土层、衬砌防水层、减震层和第二钢筋混凝土层。Further, the prefabricated tunnel lining structure includes, from the outside to the inside, a first reinforced concrete layer, a lining waterproof layer, a shock absorption layer and a second reinforced concrete layer that are stacked in sequence. 7.根据权利要求6所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:第一钢筋混凝土层、衬砌防水层、减震层和第二钢筋混凝土层的厚度比为1:1:1:2;7. The tunnel lining structure suitable for self-monitoring adjustment of crossing active faults according to claim 6, wherein the thickness ratio of the first reinforced concrete layer, the lining waterproof layer, the shock absorption layer and the second reinforced concrete layer is 1:1:1:2; 进一步的,所述衬砌防水层为防水卷材和土工布的复合材料或无纺布;Further, the lining waterproof layer is a composite material or non-woven fabric of a waterproof membrane and a geotextile; 更进一步的,所述减震层采用橡胶材料制成。Further, the shock absorption layer is made of rubber material. 8.根据权利要求1所述的适用于穿越活断层的自监测调节的隧道衬砌结构,其特征在于:钢拱架与注浆加固层之间的距离为0.5-1m。8 . The tunnel lining structure suitable for self-monitoring and adjustment of crossing active faults according to claim 1 , wherein the distance between the steel arch and the grouting reinforcement layer is 0.5-1 m. 9 . 进一步的,所述注浆加固区的内壁上,喷头的安装方式为环向8-10组,纵向相邻喷头间距为1-3m。Further, on the inner wall of the grouting reinforcement area, the nozzles are installed in 8-10 groups in the circumferential direction, and the distance between adjacent nozzles in the longitudinal direction is 1-3m. 9.权利要求1-8任一所述适用于穿越活断层的自监测调节的隧道衬砌结构的施工方法,其特征在于:包括如下步骤:9. The construction method of the self-monitoring and regulated tunnel lining structure of any one of claims 1-8, characterized in that: comprising the steps of: 隧道开挖经过断层破碎带时,施作超前小导管注浆的超前支护形式,并施工注浆加固层,对断层破碎带进行加固,维持岩体稳定;When the tunnel excavation passes through the fault fracture zone, the advanced support form of advanced small conduit grouting is applied, and the grouting reinforcement layer is constructed to reinforce the fault fracture zone and maintain the stability of the rock mass; 在注浆加固层内壁上布设监测加固仪;A monitoring and reinforcement instrument is arranged on the inner wall of the grouting reinforcement layer; 在断层破碎带隧道区间,施工消能减震层,在消能减振层上施工预制隧道衬砌结构;In the tunnel section of the fault fracture zone, construct the energy dissipation and shock absorption layer, and construct the prefabricated tunnel lining structure on the energy dissipation and vibration absorption layer; 最后架设钢拱架。Finally erect the steel arch. 10.根据权利要求9所述的施工方法,其特征在于:消能减震层包括三段,首先施工第二段,施工完预制隧道衬砌结构后,再施工第一段和第二段。10 . The construction method according to claim 9 , wherein the energy dissipation and shock absorption layer comprises three sections, the second section is constructed first, and the first section and the second section are constructed after the prefabricated tunnel lining structure is constructed. 11 .
CN201911082860.3A 2019-11-07 2019-11-07 Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults Active CN110836120B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911082860.3A CN110836120B (en) 2019-11-07 2019-11-07 Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911082860.3A CN110836120B (en) 2019-11-07 2019-11-07 Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults

Publications (2)

Publication Number Publication Date
CN110836120A true CN110836120A (en) 2020-02-25
CN110836120B CN110836120B (en) 2020-11-06

Family

ID=69576365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911082860.3A Active CN110836120B (en) 2019-11-07 2019-11-07 Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults

Country Status (1)

Country Link
CN (1) CN110836120B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111412937A (en) * 2020-04-18 2020-07-14 深圳特发东部服务有限公司 Tunnel safety monitoring structure based on fiber grating
CN112343630A (en) * 2020-10-20 2021-02-09 中交第二公路勘察设计研究院有限公司 Anti-dislocation supporting structure for tunnel crossing active fracture zone and construction method thereof
CN113756835A (en) * 2021-08-05 2021-12-07 中国科学院武汉岩土力学研究所 Tunnel anti-fault-breaking structural system
CN114320463A (en) * 2021-11-26 2022-04-12 北京中煤矿山工程有限公司 Method for measuring friction force of contact surface of underground engineering lining and surrounding rock
CN115263353A (en) * 2022-08-10 2022-11-01 大连理工大学 Large-deformation self-adaptive supporting structure for soft rock tunnel
CN116641737A (en) * 2023-07-07 2023-08-25 中国电建集团西北勘测设计研究院有限公司 An underground high-pressure cavern structure and its construction method based on joint force

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0681594A (en) * 1992-09-02 1994-03-22 Shimizu Corp Concrete side wall construction system
CN101550831A (en) * 2009-04-09 2009-10-07 西南交通大学 Shock resisting and reducing structure spanning movable fault tunnel
CN105569690A (en) * 2016-01-11 2016-05-11 西南交通大学 Secondary lining for preventing stick slip diastrophism of active fault spanning tunnel and construction method of secondary lining
CN106285715A (en) * 2016-10-26 2017-01-04 中铁十局集团城市轨道工程有限公司 The construction method of a just bored tunnel is worn in balancing earth-pressure shielding machine closely side
CN106522977A (en) * 2016-10-26 2017-03-22 西南交通大学 Multistage tunnel shock absorption structure penetrating through active fault
CN107218061A (en) * 2017-07-04 2017-09-29 山东大学 The tunnel monitoring supporting combined system and method for a kind of Coupled Rigid-flexible
CN107237641A (en) * 2017-08-07 2017-10-10 水利部交通运输部国家能源局南京水利科学研究院 The intelligent sprayed construction method and device of single shell lining based on monitoring feedback technique
CN208456615U (en) * 2018-07-10 2019-02-01 新疆乌京铁建轨道交通有限公司 A tunnel lining structure crossing strike-slip faults
CN109595003A (en) * 2019-01-24 2019-04-09 三峡大学 A kind of big section of tunnel is backbreak liner supporting and autonomous pressure relief device and construction method
CN109989768A (en) * 2019-04-26 2019-07-09 山东大学 A lining structure suitable for tunnel crossing active fault and its construction method
CN110159314A (en) * 2019-05-07 2019-08-23 山东大学 A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0681594A (en) * 1992-09-02 1994-03-22 Shimizu Corp Concrete side wall construction system
CN101550831A (en) * 2009-04-09 2009-10-07 西南交通大学 Shock resisting and reducing structure spanning movable fault tunnel
CN105569690A (en) * 2016-01-11 2016-05-11 西南交通大学 Secondary lining for preventing stick slip diastrophism of active fault spanning tunnel and construction method of secondary lining
CN106285715A (en) * 2016-10-26 2017-01-04 中铁十局集团城市轨道工程有限公司 The construction method of a just bored tunnel is worn in balancing earth-pressure shielding machine closely side
CN106522977A (en) * 2016-10-26 2017-03-22 西南交通大学 Multistage tunnel shock absorption structure penetrating through active fault
CN107218061A (en) * 2017-07-04 2017-09-29 山东大学 The tunnel monitoring supporting combined system and method for a kind of Coupled Rigid-flexible
CN107237641A (en) * 2017-08-07 2017-10-10 水利部交通运输部国家能源局南京水利科学研究院 The intelligent sprayed construction method and device of single shell lining based on monitoring feedback technique
CN208456615U (en) * 2018-07-10 2019-02-01 新疆乌京铁建轨道交通有限公司 A tunnel lining structure crossing strike-slip faults
CN109595003A (en) * 2019-01-24 2019-04-09 三峡大学 A kind of big section of tunnel is backbreak liner supporting and autonomous pressure relief device and construction method
CN109989768A (en) * 2019-04-26 2019-07-09 山东大学 A lining structure suitable for tunnel crossing active fault and its construction method
CN110159314A (en) * 2019-05-07 2019-08-23 山东大学 A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111412937A (en) * 2020-04-18 2020-07-14 深圳特发东部服务有限公司 Tunnel safety monitoring structure based on fiber grating
CN112343630A (en) * 2020-10-20 2021-02-09 中交第二公路勘察设计研究院有限公司 Anti-dislocation supporting structure for tunnel crossing active fracture zone and construction method thereof
CN113756835A (en) * 2021-08-05 2021-12-07 中国科学院武汉岩土力学研究所 Tunnel anti-fault-breaking structural system
CN114320463A (en) * 2021-11-26 2022-04-12 北京中煤矿山工程有限公司 Method for measuring friction force of contact surface of underground engineering lining and surrounding rock
CN115263353A (en) * 2022-08-10 2022-11-01 大连理工大学 Large-deformation self-adaptive supporting structure for soft rock tunnel
CN116641737A (en) * 2023-07-07 2023-08-25 中国电建集团西北勘测设计研究院有限公司 An underground high-pressure cavern structure and its construction method based on joint force

Also Published As

Publication number Publication date
CN110836120B (en) 2020-11-06

Similar Documents

Publication Publication Date Title
CN110836120B (en) Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults
CN110159314B (en) Tunnel flexible ring type supporting system suitable for penetrating through movable fracture zone
CN109989768B (en) Lining structure suitable for tunnel crossing active fault and construction method thereof
CN106522977A (en) Multistage tunnel shock absorption structure penetrating through active fault
CN104047614B (en) A method of replacement and support for strongly expansive muddy soft rock roadway
CN103410528B (en) Tunnel lining structure and construction method
CN106481343B (en) A kind of Soft Rock Tunnel Excavation and preliminary bracing method
US11821316B1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method
CN204311364U (en) Hangar tunnel
CN107558387A (en) Protect the novel combination type flexible hangar tunnel structure of high-altitude falling rocks and colluvial rubble
CN114635720A (en) Large-section deep-buried soft rock tunnel combined supporting system and construction method
CN108019222A (en) A kind of tunnel lining structure filled using haydite and construction method
CN103032080A (en) Support method of weak and broken surrounding rock tunnel
CN114542122A (en) Energy-absorbing yielding tunnel primary support structure system and construction method thereof
CN110374627A (en) A kind of support system and its construction method of existing railway
CN210977516U (en) A scour protection energy release composite support structure for rock burst mine tunnel
CN211038688U (en) Supporting structure for salt rock tunnel
CN114109437B (en) Rolling hinge point anchor beam supporting method suitable for soft rock large-deformation tunnel
CN204738819U (en) Non-disturbed cave cavity support structure for tunnel
CN103924981B (en) Single-arch large span shallow-depth-excavation tunnel reinforcement system and construction method thereof
CN212003199U (en) A soft rock large deformation tunnel lining support structure
CN113833491A (en) Tunnel lining support and tunnel penetrating through active fault fracture zone
Bai et al. Construction of shallow buried large-span metro stations using the small pipe roof-beam method
CN118933935A (en) Flexible initial support structure and construction method for tunnels in high-energy geological environments
CN116220749B (en) A prevent accuse structure for rock burst tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant